Upload
dheeraj-menon
View
148
Download
16
Embed Size (px)
Citation preview
QP CONTRACTORS’ FORUM:
MANAGING HSE IN QP CONTRACTS
1
Corporate HSE Department
PRESENTATION OUTLINE• PART 1: BACKGROUND
– Background
– The Gaps
• PART 2: THE NEW PROCESS– Process Flow
– What has changed
• PART 3: QP HSE REGULATIONS FOR CONTRACTORS– Introduction
– Overview of QP HSE Regulations for Contractors
• PART 4: WHAT IT ALL MEANS– Roles & responsibilities
– What is needed2
BACKGROUND• QP HSE Policy
Manage HSE as an integral part of business activities
Strive towards incident free, secure, safe, and healthy workplace
Line Managers are fully responsible…All activities must be in line with HSE policy
Ensure that…QP Contractors apply QP’s HSE Standards
…HSE performance to be managed with same gravity as any other aspect of industrial performance
3
BACKGROUND Continued• 2008:
• 2009:
Fatalities
Lost Time Injuries
Recordable Cases
First Aid Cases
Near Miss
QPContractors
0 7
44 8214 74
3 30
56 55
Fatalities
Lost Time Injuries
Recordable Cases
First Aid Cases
Near Miss
QPContractors
0 5
28 5716 74
7 27
18 19
4
BACKGROUND Continued
0
20
40
60
80
100
120
140
160
180
200
FAC Near Miss / Near Hit
Damage Env/Leak Fire MVI / RTA
44
5649
69
13
54
82
55
100
1217
131126
111
149
81
30
185
Nu
mb
er
Reportable Cases 2008
QP
Con
Total
5
1 CCW Project Fire incident: Estimated Cost = Over QR 14, 000,000 !!!
BACKGROUND Continued
• Five Year Performance
0 0 0 0 0
21 1
3
7
0
2
4
6
8
2004 2005 2006 2007 2008
Number
Years
Fatalities (2004 – 2008)
QP
Con
8
21
92 5
30
92
56
2230
0
10
20
30
40
50
60
70
80
90
100
2004 2005 2006 2007 2008
Nu
mb
er
Year
Lost Time Injuries (2004 - 2008)
QP
Con
6
BACKGROUND Continued
• There is a Gap between HSE Policy and implementation
• Multi-disciplinary Team set up to:» Define the gap» Address the gap
• Team membership:» 13 Depts./Dir. /Regions represented» Multi-disciplinary (OH, Safety, Env., Operations, Engrg, CN, etc.)
• Team carried out Gap analysis via:– Process comparison (QP vs. Best practice)– Review of existing documentation (QP Contr. Safety Reg., Contracts Dept docs.)– Review of HSE Mgt. in existing Contract (Mesaieed)– Survey carried out to establish baseline info.
• Team Established a systematic approach through:» New QP Procedure for managing HSE in contracts» New Guidelines for managing HSE in contracts» New QP HSE Regulations for contractors
7
MANAGING HSE IN CONTRACTS
2008 2009 2011 2012 2013 2014
IMPLEMENTATION PLAN
Initiation : Consultation, Gap
Analysis, scoping
Training of users (CH, QSR)
Train CHPES Users
Management Workshop
Review, update & possible
inclusion of JVs & Subsidrs.
Develop Documents, obtain
Approvals & launch
Develop Web-based CHPES tool
2010
Verification of usage
Usage of Documents
(Pilot)
Interim Review
Fully functional system8
GAPS IN THE EXISTING PROCESS
Decision made to contract out work
HSE in pre-tender documents based on
subjective content
Bidders assessed on Technical and
Commercial criteria
Contract Awarded
Kick-off Meeting sometimes held
Contract execution and some HSE monitoring
Contract ends
No systematic approach (No Plan, do, check, feedback)
No training on HSE Mgt. in Contracts
HSE not award determining factor
No Pre-execution audit/inspection
No HSE certificate b/4 work starts
No HSE performance Database
Poor definition of Roles & Responsibilities
Standard HSE clauses/templates in-adequate
Cont. Safety Regulations not always given
Etc.
GAPS
• QP EXISTING PRACTICE
9
THE NEW PROCESS• OVERVIEW
PLANNING AND
INVITATION TO
TENDER
TENDER PERIOD
EVALUATION AND
CONTRACT AWARD
MOBILISATION
EXECUTION
DE-MOBILISATION
CLOSE-OUT HSE close out Report
Prepare Contract HSE Mgt.
Plan
Pre-qualify
Potential bidders
Maintain same level
of vigilance as in execution
Finalize Contract
HSE plan
Hold Kick-off
Meeting
CONTRACT AWARD
Evaluate tender
Contractor prepares
Contract HSE Plan
Conduct HSE Assessment
& determine HSE Strategy
Finalize Tender document
Establish contract scope
Feedback for update of
Contractor HSE
Performance database
Appoint Contract Holder
Specify HSE requirements
Monitor Contract HSE
Plan implementation
& Performance
10
WHAT HAS CHANGED• Roles & responsibilities more clearly defined
• HSE Management in contracts training introduced
• Contract Holder to prepare a Contract HSE Mgt. Plan
• HSE assessment of the contract at the beginning
• Contractor’s HSE performance database to record performance and improve contractor selection
• New HSE Regulations doc. must be issued to contractors at award stage
• Tenderers to conduct own HSE risk assessment & hence submit HSE Plan
11
• HSE to be an award criteria (Traffic lighted: Green vs Red basis)
• HSE Certificate must be issued before work commencement
• New Statement of HSE requirements template (for both High & Low risk contracts)
• Contractor HSE Officer’s interview/test
• Appointment of QP Site Reps. to monitor site HSE
• Contractors to submit monthly HSE perf. Reports
• HSE close-out & Site restoration certificate to be issued
WHAT HAS CHANGED
12
13
APPENDIX 3: CONTRACTOR MONTHLY HSE PERFORMANCE REPORT FORM
CONTRACT NUMBER: CONTRACT TITLE:
SPONSOR DEPT.: CONTRACTOR:
HSE STATISTICS FOR THE MONTH OF:
Number of EMPLOYEES WORKING ON CONTRACT*:
Number of MAN-HOURS worked (including any overtime) in the month:
Number of FATALITIES in the month: (FAT)
Number of PERMANENT DISABILITIES in the month: (PPD & PTD)
Number of LOST WORKDAY CASES in the month: (LWC)
Number of RESTRICTED WORK CASES in the month: (RWC)
Number of MEDICAL TREATMENT CASES in the month: (MTC)
Number of FIRST AID CASES in the month: (FAC)
Number of NEAR MISSES in the month: (NMs)
Number of UNSAFE ACTS / CONDITIONS reported in month (UA/UC)
TOTAL RECORDABLE OCCUPATIONAL ILLNESSES in month: (TROI)
Number of CALENDAR MAN-DAYS LOST due to SICKNESS ABSENCE
TOTAL RECORDABLE INCIDENTS in the Month: (TRI)
Number of: NON-ACCIDENTAL DEATHS in the month: (NAD)
Number of: ROAD TRAFFIC ACCIDENTS in the month: (RTA)
Quantity of WASTE GENERATED in the Month (Kg):
Number of personnel HSE TRAINED in the month (include HSE induction)
Number of TOOLBOX TALKS held in the month
Number of HSE MEETINGS held in the month
Number of HSE INSPECTIONS/AUDITS held in the month
Number of EMERGENCY DRILLS held in the month
MONTHLY LOGISTICS STATISTICS NO. OF VEHICLES/CRAFTS TOTAL KILOMETRES DRIVEN
Heavy Vehicles (>3500 kg )
Light Vehicles (Cars, etc)
Marine Vessels (MV’s)
Names of INJURED PEOPLE ABSENT FROM WORK OR ON RESTRICTED WORK** during the month:
NAME DATE
WAS CERTIFIED UNFIT ON
WAS CERTIFIED UNFIT ON
INTRODUCTION: THREE DOCUMENTS
• PROCEDURE:Gives step by step process to follow
• GUIDELINES: Explanations, tools & templates to make implementation easy (plug & play)
• REGULATIONS: Revised version of existing Safety Regulations documentHealth and Environmental requirements added Summary of HSE management process included for awareness of contractors To be given to each contractor at contract award
QP HSE REGULATIONS FOR CONTRACTORS
GUIIDELINES FOR MANAGING HSE IN CONTRACTS
PROCEDURE FOR MANAGING
HSE IN CONTRACTS
14
NEW QP HSE REGULATIONS FOR CONTRACTORS
• DESCRIPTION:
– Revised version of existing Safety Regulations doc.
– Consists of 4 main sections:» General HSE Mgt. reqs.
» Safety reqs.
» OH/IH reqs.
» Environmental Reqs.
• GENERAL STRUCTURE:
– Briefly states key requirements on HSE issues
– Refers to appropriate doc. for details e.g Lifting Eqpt. Regulations doc. (DOC. NO: QP-REG-Q-001)
– Future: Detailed docs. to be developed where non-existent
• INTENTION:
– To be given to QP Contractors
15
16
− Addition of HSE mgt. requirements
− Update and addition of Safety requirements(44% modified, 48% New, 8% untouched)
− New OH/IH Requirements added
− New Env. Requirements added
− Overall: 80% New, 20 % Existing
• WHAT HAS CHANGED:
OVERVIEW OF THE QP HSE REGULATIONS FOR CONTRACTORS
QP HSE REGULATIONS FOR CONTRACTORS
17
• Approval & Message from HE The Minister (Mgt. commitment & empowerment)
• Introduction by SQ: • Situates in context of QP Ctr. HSE mgt. system
• Summarizes Contractor’s role vs QP
• General HSE Mgt. Requirements:• Specifies reqs. key to HSE mgt. in line with new procedure
• Includes:
» Requirement for Risk assessment by contractor
» Requirement for Contract HSE Plan
» Requirement for contractor to have HSE-MS
» Requirements on mgt. of Sub-contractor HSE
» Appointment of Ctr. key personnel
» HSE competence of contractor personnel
» Pre-execution audits
» Issuance of Work Commencement Certificate
CONTENTS
SAFETY REQUIREMENTS
18
REF HEADING ACTION REMARK
5.1 GENERAL OCC. SAFETY REQS.-PERSONNEL CONDUCT-NO SMOKING POLICY -SAFE TOOLS AND EQUIPMENT-HOUSE-KEEPING
Modified No smoking policy & personnel conduct added
5.2 PERMIT TO WORK Modified Ref. made to related certs.Ref. to location-specific procedures
5.3 PERSONAL PROTECTIVE EQUIPMENT-STANDARDS FOR PPE-HEAD PROTECTION-EYE AND FACE PROTECTION-FOOT PROTECTION-FALL PROTECTION-USE OF LADDERS-HAND PROTECTION-RESPIRATORY PROTECTION-HEARING PROTECTION-PERSONAL FLOATATION DEVICES
Modified - Consolidated: one section- Classes (Head, Foot, Fall etc.) explained in detail-Freq. of issue added-Stds (BS & ANSI) updated -Sections added e.g. use of ladders , PFD’s
SAFETY REQUIREMENTS
19
REF HEADING ACTION REMARK
5.4 LIFTING EQUIPMENT- LIFTING EQPT. CERTIFICATION-COMPETENCE & CERT. OF L.E. PERSONNEL-SAFE WORKING LOADS-GENERAL REQS. FOR L.E.-LIFTING EQUIPMENT SPECIFIC RISKS
Modified -Removed technical details & referenced the rel. std.: QP L.E. Tech. Reg. (QP-REG-Q-001)-Only key generic reqs. Left
5.5 USE OF HAND TOOLS- Portable Tools
Modified -Reference made to the std.: QP Guidelines for Hand /Power tools Safety (IP-SF-017)
5.6 SCAFFOLDING & MEANS OF ACCESS AND ESCAPE-REQS. FOR BOARDS AND PLANKS-WORKING PLATFORM- MOBILE TOWER-INDEPENDENT TOWERS-FALLING OBJECTS-THE USE OF LIGHT METAL ALLOYS IN HAZARDOUS AREAS
Modified -Ref. made to location-specific procedures (IP-OPS-026, 030 & 034)
SAFETY REQUIREMENTS
20
REF HEADING ACTION REMARK
5.7 GUARDS AND GUARDING SYSTEMS Modified - Guards/ handrails for walkways & Rig-floor V-doors added
5.8 HAZARDOUS GASES- HYDOGEN SULPHIDE
- CARBON DIOXIDE AND NITROGEN
- LIQUID NITROGEN
New/Modified - H2S & CO2 added to existing Liquid N2 which was modified
5.9 GAS CYLINDERS- CYLINDER IDENTIFICATION- STORAGE OF CYLINDERS- STACKING OF CYLINDERS- HANDLING AND MOVEMENT OF CYLINDERS- CYLINDER FITTINGS- GAS WELDING EQUIPMENT- TEST CERTIFICATES
Modified -Reference to IP-SF-015
5.10 RADIOACTIVE SUBSTANCES-STORAGE- TRANSPORT- HANDLING & PERSONAL PROTECTION - INCIDENTS & EMERG. PROCEDURES
Modified -Ref. to Qatari Laws e.g. Decree Law no 31 of 2002, & SCENR Regulations 2, 3, and 4 of 2007 on Radiation.- NORM section added
SAFETY REQUIREMENTS
21
REF HEADING ACTION REMARK
5.11 ROAD SAFETY- SEAT BELTS- DRIVER TRAINING & QUALIFICATN- COMMUNICATION DEVICES- JOURNEY MANAGEMENT - DUI (ALCOHOL, DRUGS,MEDICINES)- DRIVER FITNESS AND ALERTNESS- VEHICLE SPECIFICATIONS- ROAD TRAFFIC MGT. SYSTEM- ROAD WORKS & ROAD DIVERSIONS- SPECIAL PURPOSE VEHICLES/EQPT.- MANAGING VULNERABLE ROAD USERS- TRANSPORTATION OF HAZARDOUS GOODS
New/Modified - Existing scanty veh. & driving rules modified substantially-Journey Mgt., Road traffic mgt. system, etc. added
- Recent addition, Hazchem has been added
5.12 CONCRETE AND MASONRY- FORMWORK AND SHORING- VERTICAL SLIP FORMS- RE-INFORCEMENT STEEL- REMOVAL OF FORMWORK- PRE-CAST CONCRETE- LIFT-SLAB OPERATIONS - PRECAUTIONS DURING MASONRY AND CONSTRUCTION
New - Added to address hazards associated with concrete & masonry work
SAFETY REQUIREMENTS
22
REF HEADING ACTION REMARK
5.13 EXCAVATION AND MICRO-TUNNELLING - GENERAL REQUIREMENTS- MICRO-TUNNELLING
New/Modified -Micro-tunnelling introduced- Reference to location-specific Exc. Procedures (IP-OPS-023, 032, & 036)
5.14 HSE IN DRILLING AND WELL SERVICING OPERATIONS- GENERAL- EQUIPMENT SPECIFICATIONS-SAFETY & FIRE EQPT. FOR OFFSHORE DRILLING UNIT- ONSHORE DRILLING UNITS
New/Modified - Wireline ops. added- Ref. to drilling Ops Manual, EMS, etc.- Additions include: Coiled tubing ops., Hammer unions, Rigfloor tools for tubulars, use of pick-up/laydown machine, etc.
5.15 STEEL ERECTION New - Added to address hazards associated with Steel erection
5.16 PROCESS SAFETY New - Added to address hazards associated with production processes
SAFETY REQUIREMENTS
23
REF HEADING ACTION REMARK
5.22 HOT WORK-SAFE WELDING AREA- HOT WORK PERMIT- INSPECTION AND TESTING- HOT WORK PRECAUTIONS - VENTILATION DURING HOT WORK
New - Added to address hazards associated with it
5.23 OFFICE SAFETY New - Added to address hazards associated with it
5.24 SAFETY OF VISITORS Modified - Added induction for visitors
5.25 SAND BLASTING & PAINTING New - Added due to demand
5.26 PROJECT SAFETY New - Added due to demand
5.27 WORKING ON RADIO TOWERS & MASTS New - Added due to demand
5.28 WORKING ALONE New - Added due to demand
5.25 SPECIFICATION FOR CONTRACTOR COMPOUNDS, ACCOMMODATN AND PORTACABINS
Retained - Combined and retained
SAFETY REQUIREMENTS
24
REF HEADING ACTION REMARK
5.17 MATERIALS HANDLING & STORAGE- LIFTING OF LOADS BY PERSONNEL- USE OF FORKLIFT - MATERIAL STORAGE
New - Added to address hazards associated with it
5.18 CONFINED SPACE ENTRY- MINIMUM REQS. FOR ENTRY
New - Added to address hazards associated with it
5.19 MARINE SAFETY AND DIVING- MARINE SAFETY- DIVING SAFETY
Modified -Marine and Diving combined- Ref. to relevant stds. (Inshore Diving Regs. OPS-REG-001)- Updates e.g. IMCA vs AODC
5.20 USE OF EXPLOSIVES- GENERAL- RULES FOR STORAGE - DISPOSAL OF EXPLOSIVES
Modified - Topic now on its own
5.21 ELECTRICAL SAFETY- PERSONNEL- BASIC RULES- INSPECTION & TESTING - PERSONAL ELECTRICAL APPARATUS
New - Added to address hazards associated with it- Ref. relevant QP procedures e.g. IP-OPS-021, 024,037&8
25
REF HEADING ACTION REMARK
6.1 GENERAL REQUIREMENTS-INTRODUCTION- LEGAL, REG. & PERF. REQUIREMENTS- HEALTH / HYGIENE ISSUES IN POLICY
New Addresses the H in HSE
6.2 INDUSTRIAL HYGIENE REQS.- HEALTH RISK ASSESSMENT- HAZARDOUS CHEMICALS - ERGONOMICS - WELFARE & PUBLIC HEALTH
New Ditto
6.3 HEALTH REQUIREMENTS- HEALTH IMPACT ASSESSMENTS
- HEALTHCARE PROVISION- FITNESS TO WORK EXAMINATIONS- MEDICAL EMERGENCY PLANNING- PREVENTIVE MEASURES & VACCINATNS.- WORK ACCIDENTS REPORT- REPORTING & RECORDS- ALCOHOL, DRUGS & CONTROLLED SUBSTANCES
New Ditto
OCC.HEALTH/ IND. HYGIENE REQUIREMENTS
ENVIRONMENTAL REQUIREMENTS
26
REF HEADING ACTION REMARK
7.1 SITE SELECTION, ABANDONMENT & RESTORATION - CONTRACTORS’ FOR SITE SELECTION- CONTRACTORS’ SITE PREPARATION- INSTRUCTIONS FOR SITE ABANDONMENT & RESTORATION- SPECS. FOR REMEDIATION- SPECS. FOR LANDSCAPE RESTORATION- ENV. PERF. MONITORING
New Addresses the E in HSE
7.2 WASTE MANAGEMENT- SPECS. FOR WASTE MGT. - GUIDELINES FOR W.MGT – OFFSHORE & HALUL (Doc No. QP-ENV-001)- HAZARDOUS WASTE- PYROPHORIC / HAZARDOUS WASTE- ASBESTOS WASTE MGT. PLAN- CHEMICAL USE- WASTE WATER MANAGEMENT
New Ditto
7.3 ENVIRONMENTAL INCIDENTS- DEFINITION
- REPORTABLE ENV. INCIDENTS- WHO CAN REPORT?- IDENTIFICATION & REPORTING OF ENV. INCIDENTS
New Ditto
ROLES & RESPONSIBILITIES• HSE is Line Responsibility
• HSE professionals are just advisers
• Hierachy of Contract HSE Responsibilities:
• CONTRACTOR SITE SUPERVISION• SITE WORKERS
CONTRACTOR SITE MANAGEMENT
CONTRACT HOLDER
CONTRACT SPONSOR
QP DIRECTORS
• CORPORATE HSE• REGIONAL/OPERATIONAL HSE• QP SITE HSE REP
• CONTRACTOR HSE MANAGRS• CONTRACTOR HSE OFICERS
27
28
ROLES & RESPONSIBILITIES Continued
• QP DIRECTORS:» Review /approve HSE pre-qualification of potential
tenderers
» Review/approve bid evaluation criteria including that of HSE
» Review/approve award of contract to most suitable bid in terms of HSE, technical and commercial considerations
• TENDER COMMITTEES:» Reviewing and granting approval for HSE pre-qualification
to be done
» Review/approval of bid evaluation criteria including that of HSE
» Review/Recommend to Directors award of contract to most suitable bid in terms of HSE, technical and commercial considerations.
28
ROLES & RESPONSIBILITIES Continued
• SPONSOR DEPT:» Dept. responsible for specifying, controlling and supervising
works or services to be performed under a contract, liaising with the user department, and that is accountable to QP higher management for the performance of a contractor.
• CONTRACT SPONSOR:» The person within sponsor dept. who has budget and
management authority to execute the contract (e.g. Dept Manager, Project Manager, Asst. Manager or Divisional Head).
» Roles:• Appoint the Contract Holder.
• Provision of sufficient funds.
• Monitoring the Contract Holder.
• Manage integrity of the process.
29
• CONTRACT HOLDER:– Person appointed within the Sponsor Dept. to make and manage all
aspects of the contract (e.g. Lead Engineer, Divisional Head, Sectional Head, etc.). Sometimes called a Job Officer
– Roles:» Prepares Contract scope and Contract HSE Management Plan» Conducts HSE assessment and select appropriate HSE strategy» Pre-qualifies potential tenderers» Ensure preparation of contract HSE specification» Prepares HSE monitoring programme» Evaluates Contractor’s HSE plan with assistance from HSE» Conduct pre-execution HSE audit.» Jointly with HSE personnel, authorize the contractor to commence
work» Monitor performance of the contractor against his HSE plan» Authorize deviations from the Contract HSE plan» Authorize additional HSE requirements.» Recommends or applies sanctions.» Ensure contractor’s compliance with HSE performance reporting
requirements.» Resolution of interface problems» Ensure proper close-out of the contract
ROLES & RESPONSIBILITIES Continued
30
• QP SITE HSE REPRESENTATIVE:– Person appointed to assist the Contract Holder with site HSE monitoring
during execution of contract. Can be either from Regional/Operational HSE or from the sponsor dept.’s HSE unit.
– Roles:
» Support monitoring of contractor’s HSE related activities.
» Verify hazards and effects management controls
» Attend HSE meetings
» Perform assurance checks
» Identify deficiencies in implementation of contractor’s HSE plan
» Instigate sanctions in consultation with Contract Holder
» Assist in the issue of HSE Certificate authorizing work to start
» Inspections/audits to monitor implementation of the HSE plan
» Issue an HSE close-out certificate.
» Upload the contractor’s HSE performance into the database
» Hold Contractor HSE Forums
» Provide additional advisory support, where needed, to small local contractors
ROLES & RESPONSIBILITIES Continued
31
ROLES & RESPONSIBILITIES Continued
• REGIONAL / OPERATIONAL HSE:» Provide advice and support to the Contract Holder.
» Evaluate the preliminary Contract HSE Plan.
» Participate in the technical evaluation of the bid.
» Approve the contractor’s appointed HSE personnel.
» Attend kick-off meetings.
• CORPORATE HSE:» Develop / Facilitate implementation of QP Contractor HSE
Management policies/Procedures
» Provide training for relevant personnel.
» Promote and facilitate good contractor HSE management.
» Verification inspections/Audits & reviews of Contract HSE management
» Review and update the QP Guidelines & Regulations for HSE in contracts
» Liaise with Contracts department 32
• CONTRACTOR’S PROJECT MANAGER:» Ensures workforce HSE competencies
» Ensures sub-contractors work to the same HSE standards
» Provides adequate resources and time to manage the contract
» Notifies the Contract Holder of Contractor-nominated key personnel
» Ensures that any necessary work is adequately resourced.
» Understands the contents of QP’s Contractor HSE Regulations
• CONTRACTOR’S SITE REPRESENTATIVE:» Fulfills HSE requirements and supervises the work daily on behalf of
Contractor
» Implements the Contractor’s HSE plan and Quality plan
» Seeks formal approval from Contract Holder for any proposed deviations from Contract HSE or other plans
» Implements any additional HSE requirements as agreed with the Contract Holder
» Attends HSE & other regular meetings with the Contract Holder or his rep.
» Organizes and participates in audits/inspections & implements the findings
ROLES & RESPONSIBILITIES Continued
33
• CONTRACTOR’S HSE ADVISERS» Advises contractor staff and management
» Monitors and reports HSE performance
» Communicates information to workers
» Conducts emergency response drills
» Conducts HSE meetings
» Ensures close-out of HSE inspection/audit recommendations
» Familiar with QP HSE Policies, procedures & Regulations
» Etc.
ROLES & RESPONSIBILITIES Continued
34
WHAT IS NEEDED FROM CONTRACTORS
• Commitment to apply the new Regulations in all your contracts
• Co-operation with QP personnel applying the new process & regulations
• Information to your Key staff
• Appoint only competent personnel to work on QP projects
• Prompt your staff to comply with requirements of the new HSE Regulations
• Ensure your Sub-Contractors comply with the new QP HSE Regulations for Contractors
• Carry out own HSE risk assessment and submit fit for purpose HSE plan
• Expect past performance to factor into award of contracts
35
36
THANK YOU
37
Back-up Slides
• INCIDENT RATES (QP)
38
BACKGROUND Continued
0.44
1.1
0.41
0.080.12
0.7
1.52
0.64
0.37
0.56
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
2004 2005 2006 2007 2008
Fre
qu
en
cy (
No
. /M
illio
n M
anh
ou
rs)
Year
Lost Time Injury Frequency & Total Recordable Case Frequency (2004 -2008)
LTIF
TRCF
MANAGEMENT SYSTEM Principle for CONTINUAL IMPROVEMENT
PLAN
Do
CHECK
FEED
BA
CK
(A
ct)
39
PLANNING FOR HSE MANAGEMENT IN THE CONTRACT
KEY CONTROLS• Only trained Contract Holders (CH) to be appointed
• Contract Holder to draw up a Contract Management Plan
• HSE Assessment: Identify likely major HSE hazards to determine risk level, strategy, and HSE requirements
• If Tender Committee approves, conduct pre-qualification (High risk contracts)
• HSE needs analysis must be done before variation order is raised
• Invitation To Tender must contain generic Statement of HSE requirements to inform potential bidders (Template is available)
40
CONTRACTOR SELECTION
KEY CONTROLS• Bidder to carry out own initial risk assessment
and submit Preliminary Contract HSE Plan
• Bid Evaluation: Assess Contract HSE Plans based on approved bid evaluation criteria
• HSE to be weighted heavily in the technical bid evaluation (Traffic lighted: Green vs Red basis)
• Contract to be awarded only to most suitable bid in terms of HSE, technical, and commercial criteria
41
FLOW CHART FOR CONTRACTOR SELECTION
42
PREPARE HSE
BID
EVALUATION
CRITERIA
SUBMIT & OBTAIN
TENDER COMMITTEE
APPROVAL
BID EVALUATION.
Evaluate preliminary
HSE plan;
Participate in technical
bid evaluation.
RECOMMEND CONTRACT AWARD
(based on best HSE, technical and
commercial bid).
CONTRACT
AWARD.
Carry out Hse Risk assessment
of contract.
Prepare preliminary Contract
HSE Plan.
CONTRACTOR ACTIVITIES
QP ACTIVITIES
MOBILZATION AND WORK COMMENCEMENT
KEY CONTROLS• QP appoints other key personnel (QP Site HSE Representative, Site Engineers, etc)
• QP holds Kick-Off meeting with Contractor: HSE must be prominent
• Contractor submits list of Sub-Contractors
• Contractor proposes his Key personnel (HSE personnel, Site mgt. & Supervision)
• QP approves key HSE personnel (interview and/or competency test)
• QP HSE to review and approve Contractor’s HSE Plan
• Contract Holder prepares HSE Monitoring Program
• Contractor confirms readiness to start work
• QP conducts pre-execution HSE audit
• QP issues HSE Work Commence Certificate for work to start if satisfied43
FLOWCHART FOR MOBILISATION & CONTRACT EXECUTION Contract Award
Contract Award
Contract AwardAppoint QP Site Rep.
Contractor Mobilizeslocally?
Approve Contractor Key personnel
Contractor (& Sub-contractors) mobilizes to works vicinity
Pre-execution HSE Audit
Issue HSE Certificate for work to start
Hold Kick-off meeting locally
Contractor nominates Contractor Key personnel
Kick-off at contractor’s base
Contractor confirms readiness
Has contractor met all specified requirements?
Yes
Yes
No
No
QP:• Monitor Contract HSE Plan /performance• Work Supervision
QP:• Review & approve Contract HSE Plan• Prepare HSE monitoring program
MOBILIZATION – LOCAL TO WORKS VICINITY
Contractor:• Finalize Contract HSE Plan• Carry out HSE training and induction •• Fulfill all mobilization requirements, etc.
Contractor:• Implement Contract HSE Plan• Supervision, Audits/inspections/ reporting
EXECUTION
Support from HSE
Contract Holder step
LEGEND
Joint responsibility
44
HSE MONITORING DURING CONTRACT EXECUTION
KEY CONTROLS• Contractor:
» Implements the Contract HSE Plan» Carries out HSE training» Holds HSE meetings / toolbox talks» Carries out inspections/audits» Reports and investigates incidents» Periodically reports HSE performance» Sub-Contractors must apply same HSE standards
• QP Contract Holder & QP Site Rep:– Verifies HSE systems– Monitors contractor’s HSE performance against the plan;– Carries out HSE audits/inspections & significant incident investigations– Holds regular performance review meetings with Contractor, etc.– Ensures proper management of change
• QP Contract Sponsor:– Holds Work & HSE performance review meetings with Contract Holder (regularly)– Ensures proper management of change
• Change Control:– HSE and work-scope changes/deviations must be proposed, reviewed and authorized– Approved changes / deviations must be communicated to all parties
45
HSE IN DE-MOB & CONTRACT CLOSE-OUT
KEY CONTROLS
• Same vigilance to be maintained during de-mob as in execution
• Contractor:» Demobilizes & restores site
» Submits end-of-contract HSE Performance Report
• QP Contract Holder /HSE Adviser:– Issues HSE Close-out Certificate;
– Prepare Final HSE performance report issued;
– Update Contractor HSE performance database
• Contract Sponsor:– Checks that above actions are carried out
46
FLOWCHART FOR HSE IN DE-MOB & CLOSE-OUT
DEMOBILISATION
QP
– Monitor demobilisation activities
- Ensure the same level of HSE is applied as
during contract execution.
CONTRACTOR
- Waste management and disposal
- Site restoration
- Demobilise as per Contract HSE Plan
- Submit close-out HSE report
ISSUE HSE CLOSE-
OUT CERTIFICATE
TO CONTRACTOR
Compile final
HSE
performance
report
Upload contract
HSE
performance
into database.
47
48
REF HEADING ACTION REMARK
5.13 EXCAVATION AND MICRO-TUNNELLING - GENERAL REQUIREMENTS- MICRO-TUNNELLING
New/Modified -Micro-tunnelling introduced- Reference to location-specific Exc. Procedures (IP-OPS-023, 032, & 036)
5.14 HSE IN DRILLING AND WELL SERVICING OPERATIONS- GENERAL- EQUIPMENT SPECIFICATIONS-SAFETY & FIRE EQPT. FOR OFFSHORE DRILLING UNIT- ONSHORE DRILLING UNITS
New/Modified - Wireline ops. added- Ref. to drilling Ops Manual, EMS, etc.- Additions include: Coiled tubing ops., Hammer unions, Rigfloor tools for tubulars, use of pick-up/laydown machine, etc.
5.15 STEEL ERECTION New - Added to address hazards associated with Steel erection
5.16 PROCESS SAFETY New - Added to address hazards associated with process safety
5.17 MATERIALS HANDLING & STORAGE- LIFTING OF LOADS BY PERSONNEL- USE OF FORKLIFT - MATERIAL STORAGE
New - Added to address hazards associated with it
5.18 CONFINED SPACE ENTRY- MINIMUM REQS. FOR ENTRY
New - Added to address hazards associated with it
5.19 MARINE SAFETY AND DIVING- MARINE SAFETY- DIVING SAFETY
Modified -Marine and Diving combined- Ref. to relevant stds. (Inshore Diving Regs. OPS-REG-001)- Updates e.g. IMCA vs AODC
5.20 USE OF EXPLOSIVES- GENERAL- RULES FOR STORAGE - DISPOSAL OF EXPLOSIVES
Modified - Topic now on its own
5.21 ELECTRICAL SAFETY- PERSONNEL- BASIC RULES- INSPECTION & TESTING - PERSONAL ELECTRICAL APPARATUS
New - Added to address hazards associated with it- Ref. relevant QP procedures e.g. IP-OPS-021, 024,037&8
5.22 HOT WORK-SAFE WELDING AREA- HOT WORK PERMIT- INSPECTION AND TESTING- HOT WORK PRECAUTIONS - VENTILATION DURING HOT WORK
New - Added to address hazards associated with it
5.23 OFFICE SAFETY New - Added to address hazards associated with it
5.24 SAFETY OF VISITORS Modified - Added induction for visitors
5.25 SAND BLASTING & PAINTING New - Added due to demand
5.26 PROJECT SAFETY New - Added due to demand
5.27 WORKING ON RADIO TOWERS & MASTS New - Added due to demand
5.25 SPECIFICATION FOR CONTRACTOR COMPOUNDS, ACCOMMODATN AND PORTACABINS Retained - Combined and retained
OCCUPATIONAL HEALTH / INDUSTRIAL HYGIENE REQUIREMENTS
6.1 GENERAL REQUIREMENTS-INTRODUCTION- LEGAL, REG. & PERF. REQUIREMENTS- HEALTH / HYGIENE ISSUES IN POLICY
New Addresses the H in HSE
6.2 INDUSTRIAL HYGIENE REQS.- HEALTH RISK ASSESSMENT- HAZARDOUS CHEMICALS - ERGONOMICS - WELFARE & PUBLIC HEALTH
New Ditto
6.3 HEALTH REQUIREMENTS- HEALTH IMPACT ASSESSMENTS - HEALTHCARE PROVISION- FITNESS TO WORK EXAMINATIONS- MEDICAL EMERGENCY PLANNING- PREVENTIVE MEASURES & VACCINATNS.- WORK ACCIDENTS REPORT- REPORTING & RECORDS- ALCOHOL, DRUGS & CONTROLLED SUBSTANCES
New Ditto
ENVIRONMENTAL REQUIREMENTS
7.1 SITE SELECTION, ABANDONMENT & RESTORATION - CONTRACTORS’ FOR SITE SELECTION- CONTRACTORS’ SITE PREPARATION- INSTRUCTIONS FOR SITE ABANDONMENT & RESTORATION- SPECS. FOR REMEDIATION- SPECS. FOR LANDSCAPE RESTORATION- ENV. PERF. MONITORING
New Addresses the E in HSE
7.2 WASTE MANAGEMENT- SPECS. FOR WASTE MGT. - GUIDELINES FOR W.MGT – OFFSHORE & HALUL (Doc No. QP-ENV-001)- HAZARDOUS WASTE- PYROPHORIC / HAZARDOUS WASTE- ASBESTOS WASTE MGT. PLAN- CHEMICAL USE- WASTE WATER MANAGEMENT
New Ditto
7.3 ENVIRONMENTAL INCIDENTS- DEFINITION- REPORTABLE ENV. INCIDENTS- WHO CAN REPORT?- IDENTIFICATION & REPORTING OF ENV. INCIDENTS
New Ditto
OVERVIEW OF QP HSE REGULATIONS FOR CONTRACTORS - Continued
49
REF HEADING ACTION REMARK
GENERAL REQUIREMENTS
i Message from H.E. The Minister New To demonstrate commitment at the highest authority level
ii QP HSE Policy New To inform Contractors about the Corporation’s HSE Policy
ii Introduction by Corporate HSE Manager New To demonstrate Management commitment and highlight Management expectations
4.0 – 4.23 GENERAL REQUIREMENTS ON HSE MANAGEMENT New To specify what QP requires from contractors in terms of HSE management in line with the new procedure
SAFETY REQUIREMENTS
5.1 GENERAL OCC. SAFETY REQS.-PERSONNEL CONDUCT-NO SMOKING POLICY -SAFE TOOLS AND EQUIPMENT-HOUSE-KEEPING
Modified No smoking policy & personnel conduct added
5.2 PERMIT TO WORK Modified Ref. made to related certs.Ref. to location-specific procedures
5.3 PERSONAL PROTECTIVE EQUIPMENT-STANDARDS FOR PPE-HEAD PROTECTION-EYE AND FACE PROTECTION-FOOT PROTECTION-FALL PROTECTION-USE OF LADDERS-HAND PROTECTION-RESPIRATORY PROTECTION-HEARING PROTECTION-PERSONAL FLOATATION DEVICES
Modified - Consolidated: one section- Classes (Head, Foot, Fall etc.) explained in detail-Freq. of issue added-Stds (BS & ANSI) updated -Sections added e.g. use of ladders , PFD’s
5.4 LIFTING EQUIPMENT- LIFTING EQPT. CERTIFICATION-COMPETENCE & CERT. OF L.E. PERSONNEL-SAFE WORKING LOADS-GENERAL REQS. FOR L.E.-LIFTING EQUIPMENT SPECIFIC RISKS
Modified -Removed technical details & referenced the rel. std.: QP L.E. Tech. Reg. (QP-REG-Q-001)-Only key generic reqs. Left
5.5 USE OF HAND TOOLS- Portable Tools
Modified -Reference made to the std.: QP Guidelines for Hand /Power tools Safety (IP-SF-017)
5.6 SCAFFOLDING & MEANS OF ACCESS AND ESCAPE-REQS. FOR BOARDS AND PLANKS-WORKING PLATFORM- MOBILE TOWER-INDEPENDENT TOWERS-FALLING OBJECTS-THE USE OF LIGHT METAL ALLOYS IN HAZARDOUS AREAS
Modified -Ref. made to location-specific procedures (IP-OPS-026, 030 & 034)
5.7 GUARDS AND GUARDING SYSTEMS Modified - Guards/ handrails for walkways & Rig-floor V-doors added
5.8 HAZARDOUS GASES- HYDOGEN SULPHIDE- CARBON DIOXIDE AND NITROGEN- LIQUID NITROGEN
New/Modified - H2S & CO2 added to existing Liquid N2 which was modified
5.9 GAS CYLINDERS- CYLINDER IDENTIFICATION- STORAGE OF CYLINDERS- STACKING OF CYLINDERS- HANDLING AND MOVEMENT OF CYLINDERS- CYLINDER FITTINGS- GAS WELDING EQUIPMENT- TEST CERTIFICATES
Modified -Reference to IP-SF-015
5.10 RADIOACTIVE SUBSTANCES-STORAGE- TRANSPORT- HANDLING & PERSONAL PROTECTION - INCIDENTS & EMERG. PROCEDURES
Modified -Ref. to Qatari Laws e.g. Decree Law no 31 of 2002, & SCENR Regulations 2, 3, and 4 of 2007 on Radiation.- NORM section added
5.11 ROAD SAFETY- SEAT BELTS- DRIVER TRAINING & QUALIFICATN- COMMUNICATION DEVICES- JOURNEY MANAGEMENT - DUI (ALCOHOL, DRUGS,MEDICINES)- DRIVER FITNESS AND ALERTNESS- VEHICLE SPECIFICATIONS- ROAD TRAFFIC MGT. SYSTEM- ROAD WORKS & ROAD DIVERSIONS- SPECIAL PURPOSE VEHICLES/EQPT.- MANAGING VULNERABLE ROAD USERS- TRANSPORT OF HAZARDOUS GOODS
New/Modified - Existing scanty veh. & driving rules modified substantially-Journey Mgt., Road traffic mgt. system, etc. added
- Recent addition, Hazchem has been added
5.12 CONCRETE AND MASONRY- FORMWORK AND SHORING- VERTICAL SLIP FORMS- RE-INFORCEMENT STEEL- REMOVAL OF FORMWORK- PRE-CAST CONCRETE- LIFT-SLAB OPERATIONS - PRECAUTIONS DURING MASONRY AND CONSTRUCTION
New - Added to address hazards associated with concrete & masonry work
KEY
New
Modified
Unchanged
OVERVIEW OF QP HSE REGULATIONS FOR CONTRACTORS - Continued