14
1 5. Conclusions and Recommendations 5.1 Conclusions At present most of the local design engineers do not consider the impact of temporary construction cost on total construction cost of the bridge. This study was carriedout to find the impact of coffer-damming and de-watering cost on the total construction cost of bridge foundation and hence the total construction cost of the bridge. Also this study establishes valuable relationships among various bridge construction activities. Analysis of the data collected from the Road Construction and Development Co. (Pvt.) Ltd., pertaining to recent bridge projects have been carried out. In the first category, construction cost for 11 completed bridges have been analysed to establish valuable relationship among various bridge construction activities. In the second category, construction (direct and total) costs of foundations of 16 bridges have been analysed to establish relationship between direct construction costs and total construction costs of foundations. The first category of sample contains all three types of foundations, including three bridges of spread foundations, five bridges of pile foundations, a bridge of caisson foundations, a bridge having combination of spread and pile foundations and the other bridge having combination of all three types of foundations. It is therefore inappropriate to analyse the average relationship among different bridges having same foundation types, as the sample that represents it would become small. Also results should be read cautiously, because of the following reasons; a) The small samples of bridges were analysed. b) All bridges are standard types, simply supported girder bridges, spans ranges from 16.2 m to 7.0 m. c) Bridges have been constructed at different point of times. d) Depth of foundations have not been considered.

5. Conclusions and Recommendations 1

  • Upload
    others

  • View
    10

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 5. Conclusions and Recommendations 1

1 5. Conclusions and Recommendations

5.1 Conclusions

At present most of the local design engineers do not consider the impact of temporary construction cost on total construction cost of the bridge. This study was carriedout to find the impact of coffer-damming and de-watering cost on the total construction cost of bridge foundation and hence the total construction cost of the bridge. Also this study establishes valuable relationships among various bridge construction activities.

Analysis of the data collected from the Road Construction and Development Co. (Pvt.) Ltd., pertaining to recent bridge projects have been carried out. In the first category, construction cost for 11 completed bridges have been analysed to establish valuable relationship among various bridge construction activities. In the second category, construction (direct and total) costs of foundations of 16 bridges have been analysed to establish relationship between direct construction costs and total construction costs of foundations.

The first category of sample contains all three types of foundations, including three bridges of spread foundations, five bridges of pile foundations, a bridge of caisson foundations, a bridge having combination of spread and pile foundations and the other bridge having combination of all three types of foundations. It is therefore inappropriate to analyse the average relationship among different bridges having same foundation types, as the sample that represents it would become small. Also results should be read cautiously, because of the following reasons;

a) The small samples of bridges were analysed. b) All bridges are standard types, simply supported girder bridges, spans ranges from

16.2 m to 7.0 m. c) Bridges have been constructed at different point of times. d) Depth of foundations have not been considered.

Page 2: 5. Conclusions and Recommendations 1

5.1.1 Conclusions based on the study of cost break down of completed bridges

(i) The average direct foundation cost is around 39% of the total construction cost of

a bridge.

(ii) On average, the total foundation cost (Direct cost and coffer-damming and de-

watering cost) is around 50.5% of the total construction cost of a bridge.

(iii)Average total temporary construction cost is about 13.5%, and most of the cost components (around 11.5%) are influenced by coffer-damming and de-watering costs.

(iv) Average total foundation and sub-structure cost is around 64.5% and the average super structure cost is around 18.5% of total construction cost of a bridge. Vazirani and Ratwani (1992), Khanna (1981) have mathematically proved that in economical bridge design, super structure cost is equal or nearly equal to the total foundation and sub-structure cost. Comparing results deduced, with the above theory, this study shows that most of our bridge designs are not economical or optimal.

5.1.2 Conclusions based on the study of cost break down of foundations

(i) The total construction cost of foundation with spread footing is approximately over 200% of the direct foundation cost. Which indicates that the cost of coffer damming and de-watering etc are more than the direct cost of the foundation for spread footing.

(ii) The total foundation cost for piled foundation is 119% of the direct foundation cost. Which means that the coffer-damming and de-watering etc, account for only 19% of the direct cost of foundation. The total foundation cost for caisson is 120% of the direct foundation cost and it means only 20% needs for coffer-damming and de-watering etc. (Please refer the note given in section 4.3 for further clarifications.)

(iii) The cheapest form of foundation appears to be pile foundations. However, for foundations with depths less than 5 m it is not practicable to use piles, using pile driving method. Therefore for foundations up to about 4 m, spread footing appears to be the most suitable type. Above that depth pile is the best in-terms

44

Page 3: 5. Conclusions and Recommendations 1

of total foundation costs, which will result in the lowest total cost of bridge as well. Here the span of the bridge is assumed to be independent of the foundation type.

Caissons are likely to be the most expensive type of foundation for any depth.

However, there may be situations in which the most suitable type of foundation

can be the caisson, where the selection will not be based on the cost of

foundation. For example, if a bridge is to be constructed in build up area or place

where the depth of water is considerably high, the caisson type of foundation

should be chosen without considering the cost.

45

Page 4: 5. Conclusions and Recommendations 1

5.2 Recommendations

Based on the results of this study the following recommendations are made.

1. In designing foundations for Road Bridges, the option of Pile Foundation should

always be considered as it is found to be the most economical type of

foundation.

2. Action should be taken to review the design techniques of superstructure and sub structure.

3. A study should be carried out to find out the possibility of using new technology

to construct shallow pile foundations particularly when the depth of foundation

is less than 5.0 m.

4. A study can be carried out to construct single span bridge with longer span on

simple beam type abutment, found on pile (driven or bored) foundation or

spread footing with no huge abutment sections.

5. A study should be carried out to find out the optimum type of super structure, for example the span, as the Sri Lankan bridges seem to have a lower cost value for the super structure compared to the total construction cost.

46

Page 5: 5. Conclusions and Recommendations 1

6. References

Jha ,J. and Sinha , S.K. (1993). Construction Foundation Engineering (5th Edition),

Khanna Publishers , Delhi.

Khanna, P.N. (1981). Indian Practical Civil Engineer's Hand Book (8th Edition),

Engineers Publishers, Delhi.

RDA (1996).Road Development Authority, "Roads Materials Design and construction

Standard's Study, Bridges", Ministry of Highways, Sri Lanka.

RDA (1989).Road Development Authority, "Standard Specifications for Construction

and Maintenance of Road and Bridges", Ministry of Highways, Sri Lanka.

Vazirani.V.N. and Chandola, S.P. (1986). Railway Bridges and Tunnels (4th Edition),

Khanna Publishers, Delhi.

Vazirani, V.N. and Ratwani, MM. (1992). Concrete Structures (15th Edition),

Khanna Publishers, Delhi.

47

Page 6: 5. Conclusions and Recommendations 1

Appendix A

Design of Foundation and Abutment Sections

Concept of Design

a) Bed rock or hard strata are found in less than 3 m from ordinary water level (OWL)- up­to that depth no alternative except spread foundation.

b) Bedrock or hard strata are found in more than 3-m depth from OWL- caissons can be chosen.

c) Bedrock or hard strata are found more than 5 m from OWL and over burden is more than 4 m • piles can be chosen.

Standards used

a) British standard BS 5400

b) British standard CP 110

c) Reinforced concrete design code • IESL

Type of Loading

H a type loading

I

Page 7: 5. Conclusions and Recommendations 1

Design of bridge abutments and foundations

Data used Clear & pan of the bridge

Type of bean s Width of the abutment Design load from deck per meter length of abutment Tractive force on abutment in meter length of abutment Live load surcharge Designed bearing pressure Density of concrete Density of Earth Angle of internal friction Ranking coefficient Permissible tensile stress in concrete Type of pile Type of abutment

Type of concrete Foundation slab, pile cap and caisson cap 37.5mm) For caisson Reinforcement used

: 15.2 : 16.15m standard psc : 9.6 m

: 210 KN

: 17.15 KN : 10 KN/sq.m : 700 KN/sq.m : 24 KN/Cu.m : 18 KN/Cu.m : 30° : 1/3

: 0.25 N/mm* : 355 x 355 mm A 2 precast RCC piles : Mass concrete 1:2:4(37.5 mm) with

20% (150x225) plums

: G. 25, (30% 19mm and70%

: G. 25(19 mm) : G.425 cold worked deformed high

yield steel.

Design procedure - Abutment

At each section the positions of resultants due to all vertical loads and horizontal forces were found and the compression and tensile stresses were calculated. The width of the section was designed, so that the maximum tensile stress should be less than the allowable tensile stress.

II

Page 8: 5. Conclusions and Recommendations 1

SELECTED SECTIONS OF SPREAD FOUNDATION AND ABUTMENT SECTIONS FOR AVERAGE DEPTHS

Depth of foundation 3 m from OWL

1,200

Depth of foundation 4 m from OWL

1,200

1,200

1,200

600

600

400

400

400

1,150

2,150 2,150

350

J II 6 I

2,750

1,200

1,200

1,200

Depth of foundation 5 m from OWL

1,200

1,200

2,150

All dimensions are in mm.

350 Reinforcement : Main bars 16 mm dia. T.S. at225C.C. Distribution bars : 12 mm dia. T.S. at 250 C.C.

Ordinars Water Level

3,550

III

Page 9: 5. Conclusions and Recommendations 1

Depth of foundation 6 m from OWL

1,200

1,200

1,200

1,200

1,200

550

600

40oJ

400

400

400

600

1,200

2,150

350

-ii ft 4,150

All dimensions are in mm.

Reinforcement : Main bars 16 mm dia. T.S. at 225 C.C. Distribution bars 12 mm dia. T.S. at 250 C.C.

OWL Ordinars Water Level

IV

Page 10: 5. Conclusions and Recommendations 1

SELECTED SECTIONS OF PILE FOUNDATION AND ABUTMENT SECTION

1,200

,400, 1,100 , 1,100 , i j i i

400 1,760 » 1,760

PILE LAYOUT

Reinforcement : 16 mm dia. T.S. at 225 C.C. in both for top and bottom nets of Pile Cap

directions

SELECTED S E C T I O N S O F C A I S S O N F O U N D A T I O N S A N D A B U T M E N T S E C T I O N

1,200 2,250 . 200 . 2.250

•4 M M »i

3,550

9600

CAISSON LAYOUT

Reinforcement : 16 mm dia. T.S. at 225 C.C. in both directions for top and bottom of caisson cap

All dimensions are in mm.

V

Page 11: 5. Conclusions and Recommendations 1

Appendix B

Nine bridge design engineers attached to RDA and RCDC were interviewed based on a structured questionnaire as shown here. According to the details provided by the design engineers all bridges are standard type, concrete deck supported on spread or pile foundations. The results abstracted from the questionnaire are analysed in the page VIII. Design engineers comment on specific question No.q and r are given in page IX.

The comment on question q and r imply that nonof the design engineer has done detail analysis of cost on temporary construction.

VI

Page 12: 5. Conclusions and Recommendations 1

OUESTIONAIRE FOR BRIDGE DESIGN ENGINEERS

(1) name of the bridge designed :-Year

(2) Detail of the bridge : - Concrete Steel

Span No. of Spans

(3) Type of Super Structure : - Solid Slab Simply supported

Continuous Girders ... Cantilevered

Arch

(4) Type of Foundation : - Spread Pile

Caisson Cylinder

Raft

(5) Did you consider the following factors in designing the bridge

Yes / N o Comment

a. Volume and nature of the traffic

b. Live load on the Bridge

c. Length and Width of the Bridge

d. Aesthetic appearance

e. Geographical and physical features of the area

f. Environmental factors particular to the site

g. Social problems ion location

h. Nature of the river

I. Straight, and horizontal approaches

j . Firm and well defined banks

k. Straight streamline and smooth flow

I. Minimum depth of water and width

m. Right angle crossing

n. Soil profile at the site

o. Suitable type of foundation

p. Depth required for proper founding

q. Cost of coffer damming and de-watering

r. Cost of other temporarily construction

s. Availability of resources

t. Method of construction

u. Economical and technical feasibility

v. Facilities available for construction and maintenance

w. Time for construction

x. Economy between feasible alternatives i

* If space is not available attach a separate sheet.

VII

Page 13: 5. Conclusions and Recommendations 1

summary of the results of the questionnaire No. Factors considered in design process Answer - { Yes - Y No • N > Total ol

Y N a) Volume and nature of the traffic Y N

i 1 i N N N N N N 2 7

b) Live load on the Bridge Y Y Y | N

i . Y Y N N Y 6 3

c) Length and Width of the Bridge Y Y Y I v i Y Y Y Y Y 9 0

d) Aesthetic appearance N N N N N N N N N 0 9

e) Geographical and physical features of the area Y N N Y Y N Y N 5 4

0 Environmental factors particular to the site Y N N j V N N N N N 2 7

g) Social problems ion location N N N y N N N N N 1 8

h) Nature of the river Y Y Y Y Y N Y Y N 7 2

i) Straight and horizontal approaches Y Y Y N Y N N Y Y 6 3

j ) Firm and well defined banks N N N N Y N N N N 1 8

k) Straight streamline and smooth flow N Y Y N Y N N Y N 4 5

1) Minimum depth of water and width Y Y Y 1 Y N Y Y 7 1 m) Right angle crossing Y Y Y N Y Y N Y N 6 3

n) Soil profile at the site Y Y Y Y Y Y Y N Y 8 1

o) Suitable type of foundation Y Y Y V Y Y Y Y Y 9 0

P) Depth required for proper founding Y Y Y V Y Y Y Y Y 9 0

q) Cost of coffer damming and de-watering N Y N Y Y N N Y Y 5 4

r) Cost of other temporarily construction N Y Y N Y N Y N Y 5 4

s) Availability of resources Y Y N Y Y Y Y Y N 7 2

t ) Method of construction Y Y N N N N N Y N 3 6

u) Economical and technical feasibility N Y Y Y N N Y Y N 5 4

v) Facilities available for construction and maintenance Y N N N Y Y Y N N 4 5 w) Time for construction N N N N Y Y Y Y N 4 5

x) Economy between feasible alternatives N Y N N N N Y N Y 3 6 Type of bridge C C C C C C C C C

Type of foundation BP SP SP SP SP DP SP SP SP

Span of the bridge in m 1 6 2 3 1 6 2 3 15.23 16.23 1 6 2 3 7 0 0 16 23 1 2 2 0 16 23

Number of spans 1 3 2 2 1 1 2 1 1

C - Concrete

SP - Spread

BP • Bored Pile

DP • Driven Pile

VIII

Page 14: 5. Conclusions and Recommendations 1

Comment on specific questions

Did you consider the Comments Answer

i

Cos

t of

cof

fer

dam

min

g an

d

de-w

ater

ing

Alternations are not considered N

i

Cos

t of

cof

fer

dam

min

g an

d

de-w

ater

ing

Considered but not analysed Y

i

Cos

t of

cof

fer

dam

min

g an

d

de-w

ater

ing Not considered (rock exposed) N

i

Cos

t of

cof

fer

dam

min

g an

d

de-w

ater

ing

Considered (shallow depth) Y i

Cos

t of

cof

fer

dam

min

g an

d

de-w

ater

ing

Considered but not analysed Y

i

Cos

t of

cof

fer

dam

min

g an

d

de-w

ater

ing

Not considered (no alternative foundation type) N

i

Cos

t of

cof

fer

dam

min

g an

d

de-w

ater

ing

Not considered N

i

Cos

t of

cof

fer

dam

min

g an

d

de-w

ater

ing

Not seriously considered (rock exposed) Y

i

Cos

t of

cof

fer

dam

min

g an

d

de-w

ater

ing

To decide the excavation cost but not analysed Y

Cos

t of

othe

r

tem

pora

ry

cons

truc

tion

s

No comments N

Cos

t of

othe

r

tem

pora

ry

cons

truc

tion

s

Considered but did not analysed Y

Cos

t of

othe

r

tem

pora

ry

cons

truc

tion

s Considered to provide by road but did not analysed

Y

Cos

t of

othe

r

tem

pora

ry

cons

truc

tion

s

Standard and simple bridge N

Cos

t of

othe

r

tem

pora

ry

cons

truc

tion

s

Allow existing traffic but did not analysed Y

Cos

t of

othe

r

tem

pora

ry

cons

truc

tion

s

Not required, new location N

Cos

t of

othe

r

tem

pora

ry

cons

truc

tion

s

To deviate traffic Y Cos

t of

othe

r

tem

pora

ry

cons

truc

tion

s

Not congested N

Cos

t of

othe

r

tem

pora

ry

cons

truc

tion

s

Not analysed Y

I X