81
Social Monitoring Report Progress Report June 2019 VAN: Energy Access Project LARP Implementation Progress Report Prepared by the Department of Energy and Vanuatu Project Management Unit for the Vanuatu Government and the Asian Development Bank.

49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Social Monitoring Report

Progress Report June 2019

VAN: Energy Access Project LARP Implementation Progress Report

Prepared by the Department of Energy and Vanuatu Project Management Unit for the Vanuatu Government and the Asian Development Bank.

Page 2: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any

designation of or reference to a particular territory or geographic area in this document, ADB

does not intend to make any judgments as to the legal or other status of any territory or area.

Page 3: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Land Acquisition Resettlement Plan

VAN: Energy Access Project

Brenwe Hydro Power Subproject – Land Acquisition Resettlement Plan

16 May 2019

Revision 1 ADB Comments

received on 29 May

2019

Reviewed and revised

by VPMU completed on

4/6/19

Approved for release to

ADB by VPMU PA on

4/6/19

Revision 2 ADB Comments

received on 6 June 2019

Reviewed and revised

by VPMU completed on

6/6/19

Approved for release to

ADB by VPMU PA on

6/6/19

Prepared by the Department of Energy, Republic of Vanuatu for the Asian Development Bank updated by Stantec New Zealand, September 2018. Last update on May 2019 by VPMU.

Page 4: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | i

ABBREVIATIONS

ADB – Asian Development Bank AH – Affected Household AP – Affected Person/People BHPP – Brenwe Hydropower (sub) project BSC – Brenwe Steering Committee CBO – Community based organisation CCPP – Communication, Consultation and Participation Plan CLMO – Customary Lands Management Office CLMA – Customary Lands Management Act COTA – Custom Owners Trust Account DD – Due diligence DOE – Department of Energy DMS – Detailed Measurement Survey EA – Executing agency EAP – Energy Access Project GAP – Gender Action Plan GDP – Gross Domestic Product GOV – Government of Vanuatu GRM – Grievance Redress Mechanism GWh – Gigawatt per hour HH – Household HIES – Household Income and Expenditure Survey HPP – Hydropower Project IA – Implementing Agency IR – Involuntary Resettlement LAA – Land Acquisition Act LARP – Land Acquisition Resettlement Plan MWh – Megawatt per hour M&E – Monitoring and Evaluation MLNR – Ministry of Lands and Natural Resources MoCC – Ministry of Climate Change MPG – Malampa Provincial Government NGO – Non-government organisations NSO – National Statistics Office (Vanuatu) PMU – Project Management Unit PPTA – Project Preparatory Technical Assistance LARP _ Resettlement Plan SPS – Safeguard Policy Statement TOR – Terms of Reference TA – Technical Assistance USD – United States Dollar VG – Valuer General VPMU – Vanuatu Project Management Unit VT or VUV – Vanuatu Vatu ZOI – Zone of Influence

This land acquisition/resettlement plan is a document of the borrower. The views expressed herein do not

necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in

nature.

In preparing any country programme or strategy, financing any project, or by making any designation of or

reference to a particular territory or geographic area in this document, the Asian Development Bank does not

intend to make any judgment as to the legal or other status of any territory or area.

Page 5: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | ii

CONTENTS

I. EXECUTIVE SUMMARY 3

II. PROJECT DESCRIPTION 6

A. Background and Rationale 6 B. Project Outputs 7 C. Scope of Work of Brenwe HP Subproject 7

III. SCOPE OF LAND ACQUISITION AND RESETTLEMENT PLAN 9

A. Scope of Land Acquisition 9 B. Land Acquisition Impacts and Affected Household/Persons (APs) 9

IV. SOCIOECONOMIC INFORMATION AND PROFILE OF AFFECTED PERSONS AND SUBPROJECT COMMUNITIES 12

A. Subproject Communities 12 B. Profile of Subproject Communities - Malekula Island and local villages 12 C. Socioeconomic Profile of Households/Persons Affected by BHPP Land Acquisition 14

V. INFORMATION DISCLOSURE, CONSULTATIONS, AND PARTICIPATION 19

A. Stakeholders 19 B. Community Consultations Held 20 C. Consultation on LARP Preparation 21 D. Disclosure of Draft LARP 22 E. Consultations and Information Disclosure during Project Implementation 23

VI. GRIEVANCE REDRESS MECHANISM 23

VII. LEGAL AND POLICY FRAMEWORK 25

A. Vanuatu Laws on Land Acquisition and Resettlement 25 B. ADB’s Policy on Involuntary Resettlement 31 C. Policy Differences and Reconciliation 31 D. Principles and Policies for the Project 34

VIII. ENTITLEMENTS, ASSISTANCE AND BENEFITS 35

A. Categorises of APs 35 B. Eligibility for Compensation 35 C. Entitlements 35

IX. INCOME RESTORATION AND REHABILITATION 37

X. LAND ACQUISITION RESETTLEMENT BUDGET AND FINANCING SOURCE 37

XI. INSTITUTIONAL FRAMEWORK 37

A. Institutional Arrangements 37 B. Implementation Arrangements for the LARP 38 C. Resettlement Database 38

XII. IMPLEMENTATION SCHEDULE 38

XIII. MONITORING AND REPORTING 39

XIV. APPENDICES 41

Appendix 1: Copy of Memorandum of Agreement on Project Access 41 Appendix 2: Consultations 45 Appendix 3 - Communications, Consultation and Participation Plan for Brenwe Hydropower

Project 60

Page 6: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 3

I. EXECUTIVE SUMMARY

ADB’s Energy Access Project (the project) will assist the Republic of Vanuatu’s (the Government) efforts to reduce the country’s heavy reliance on imported fossil fuels for power generation by providing a secure, sustainable and environmentally sound source of electricity for private and commercial consumers. The impact of the project is expected to improve the livelihoods of households in Malekula and Espiritu Santo. The outcome of the project will support Government policy in increasing the supply of clean renewable electricity to households in Malekula and Espiritu Santo.

The project will have the following outputs: (i) distribution grid extension in Santo and Malekula islands, (ii) Brenwe Hydropower Project (BHPP) in Malekula, (iii) capacity building, and (iv) efficient project management services. The feasibility study was undertaken in 2014 under Project Preparatory Technical Assistance (PPTA) funded by the Asian Development Bank (ADB) and further studies that took place in early 2016.

This Resettlement Plan (referred to throughout as the LARP) has been prepared for the BHPP subproject in Malekula, Malampa Province. The subproject requires 30ha of land area to construct the hydropower facilities. The transmission line and grid extension will follow the existing provincial road corridor and the site access road and is not expected to require permanent land acquisition. The land access for these components will be guided by existing government laws such as Electricity Act and the necessary consent and agreement from all the landowners will be obtained.

Table E1. Land Requirement and Affected Persons for Brenwe HPP1

Parameter Comment

Ownership/type of land Customary land

Type of land use Natural bush covered ravine. Not used for any residential,

commercial, or agricultural purpose.

Land acquisition requirement ha 30 ha

Number of groups having claims to the land2 2

Number of affected households At least 72

Number of Female-Headed Households None

Affected households losing 10% or more land None

Other Affected Assets Trees within transmission line corridors

Source: PPTA; updated by VPMU

4 The BHPP subproject site is customary-owned bush land located within a steep ravine that is not used for any residential or agricultural purpose. It will therefore not have impacts of physical displacement and is not expected to negatively affect any major income source for any person. The BHPP will require 30 ha of land. The land claimants and local community members view the BHPP as an opportunity to access regular power supply as well as providing cash compensation for land owners, thus generating benefits to them from otherwise economically unproductive land. Depending on the final alignment of the right and left bank site access ways, some land users may lose income from cash crop production due to the removal of productive trees, and will need to be compensated for the loss of these assets. Although transmission line establishment and grid extension are not expected to require land acquisition, it will require removal and trimming of trees within the (combined) transmission corridor and road reserve. The households affected by the loss of such assets cannot be determined until the detailed design for the transmission is available. In

1 Data on land are preliminary estimates based on PPTA. These are subject to confirmation during the implementation.

The updated LARP will provide final data on those to be affected by tree cutting along the transmission lines and the provision of access to the BHPP site.

2 Landowners have been declared by court for the East bank. There are three claimants for the West Bank.

Page 7: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 4

the early 1990’s a foreign company had almost completed the development of a hydropower project within the same area and only failed because of the lack of financing and disputes with local communities regarding the transmission corridor which would traverse rich agricultural lands adversely affecting local people. The construction of the said project was then abandoned and never became operational; land was not acquired.

6 Based on this lesson, GOV will acquire and compensate for the land for the Brenwe HPP site and the transmission lines will be located within the corridor of the existing provincial road to avoid and minimize impacts. The grid extensions will also follow the existing road corridors. Infrastructure will only be installed on customary land where there is negotiated agreement on the use of that land. With these various undertakings, the GOV has received strong support for the BHPP by the local communities and their leaders. During interviews, research and multiple rounds of consultations with Affected Persons (APs) and communities, those concerned have expressed the need for the electrification project and a willingness to allow the government to acquire the land.

7 The project will follow ADB’s Safeguard Policy Statement (SPS, 2009) and Vanuatu’s applicable laws on land acquisition and compensation. The table below summarises the entitlement for APs.

Table E2. Entitlement Matrix

Type of Impact Entitled Persons Entitlements

Loss of land Land owners Compensation at replacement cost based on current

market price (based on most recent transactions of

comparable value) will be paid for the land to be

acquired.

Loss of use of

the land

Land users, including

lessees

Refund of all rental/lease payments paid in advance from

the date of notice of acquisition (if any), and

Payment of rent for 1 year for an equivalent area of land

elsewhere equal to the land area forgone, and

compensation for lost crops as below.

Impaired access

to adjacent

productive land

Users of land

immediately adjacent to

but not on acquired or

leased land

Payment of cost of re-establishing or repairing access

tracks or driveways to previous or better standard.

Loss of trees,

crops, and food

sources

All APs owning the

planted trees and/or

crops on the acquired or

affected land

APs will be entitled to harvest any natural trees, planted

trees, and crops belonging to them on the acquired or

leased land before site clearance.

If the tree and crop owners are not able to harvest, they

will be paid full compensation at replacement cost based

on market prices.

Fruit trees, nut trees, and housing material trees will be

compensated for at replacement cost or

market/comparable price. The compensation will include

loss of existing crop and of future crop for 1 year.

Planted timber trees, if any, will be compensated for at

market price for a mature tree of the same species.

Loss of trees,

vegetation,

crops, and

structures in

power

transmission and

distribution

corridors

Persons, regardless of

status, owning the

asset/s impinging on the

transmission

corridor/easement

APs will be entitled to harvest or remove assets

belonging to them prior to corridor/easement clearing.

APs will be compensated for crops and fruit trees at

market value of the asset lost OR will be given paid

employment by the power agency/ contractor in trimming

and removing those trees (but not both). A signed

agreement will be executed with the APs in the event

Page 8: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 5

Type of Impact Entitled Persons Entitlements

they choose this option and are willing to forgo

compensation and donate the asset lost.

Owners of structures (e.g. roadside market stall) will be

provided with materials and labour to re-establish the

structure nearby to an equivalent or better standard.

Impacts on

assets and

livelihoods of

vulnerable

groups

Vulnerable groups

including include

women, youth and poor

households

Training and project-generated employment given on

priority basis to the affected households; and assistance

to vulnerable households for income restoration.

Determined on a case by case need

Unforeseen or

unintended

impacts on

livelihoods and

assets

Concerned affected

people

These will be determined on a case by case basis as per

the principles of this LARP and ADB's SPS.

8 The LARP has been prepared using information from the environmental and social impact

assessments, household survey, and several rounds of consultations undertaken during the SMEC PPTA in 2014 and subsequently. While the LARP is a ‘living document” subject to updating as the project planning progresses, it has been endorsed by the Executing Agency (EA), disclosed to APs, and posted on ADB website before the project appraisal. The LARP will be updated after the detailed design for the BHPP and site access roads becomes available, and then after the detailed design for the transmission line and grid extension has been prepared.

9 The following is the implementation schedule for land acquisition and resettlement planning activities:

Table E3. Implementation Schedule

N° Activities Progress / date

completed

1

Confirmation of land requirement and

consultation/information disclosure with

landowners/APs

Completed

2 Land survey and valuation Completed

3 Confirmation of landowners by the Customary Lands

Management Office (CLMO)

Court determinations

completed for Tervaut land

(28 November 2018)

Wiaru land has been

confirmed

4

Submission to Department of Lands (DOL) of land

survey report and to prepare for formal negotiation

with landowners/APs and budget allocation for land

acquisition

Completed

Valuation reported to APs

5

Negotiation with landowners/APs: consultation with

affected landowners to negotiate for land

acquisition/purchase.

MOA signed with each land

claimant to proceed with

project until ownership is

determined

6

Agreement on land acquisition/purchase and approval

by the government on allocation and release of fund

for land compensation payment

Valuation done and given to

land claimants.

1 claimant lodged objection to

valuation. Objection letter has

been responded to by DOL.

Fund allocation has been

approved by government and

Page 9: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 6

N° Activities Progress / date

completed

moved to COTA in February

2019

7

Vanuatu Project Management Unit (VPMU) in

coordination with Department of Energy (DOE) and

DOL updates the LARP including agreements on

compensation rates with landowners and discloses

updated LARP to APs.

September 2017, September

2018, February 2019, May

2019 and is ongoing

8 VPMU submits the updated LARP to ADB for approval

and posting on ADB website

LARP is currently being

updated and submitted May

2019

9 Execution of land acquisition and payment of

compensation

Compensation had been

lodged in Customary Owners

Trust Account (COTA)

pending land ownership

determination. Claimants

advised. East bank land

owners have been declared

by court on 28 Nov 2018

West bank land owners have

been declared.

10 VPMU submits to ADB a land acquisition and

compensation completion report

Yet to be completed and work

in progress.

11 VPMU submits safeguard monitoring report May 2019

II. PROJECT DESCRIPTION

A. Background and Rationale

10. Vanuatu is a South Pacific island nation composed of more than 80 islands with a total land area of about 12,190 km2 spread over an ocean area of 612,300 km² in the South Pacific stretching from Hiu Island in the north to Mathew and Hunter Islands in the south. Most (around 60%) of these islands are permanently inhabited, and around half are mountainous and densely forested with narrow strips of farming land on the coasts. Five volcanoes are still active and volcanic eruptions are not uncommon. In 2016, the country had a total population of approximately 272,459 in 55,527 households with almost 80 per cent of them living on the twelve largest islands. The two main cities are Port Vila (50,944 people) and Luganville (15,865 people).

11. Vanuatu’s economy is primarily agriculture-based. More than three-quarters of inhabitants live in rural areas and rely on traditional subsistence farming methods. Vanuatu’s economy has been unable to grow quickly enough to meet the needs of its expanding population. A significant consequence is a high rate of youth unemployment. The main exports are copra (35 per cent), coconut oil, cocoa, coffee, kava root, cattle and timber. The country’s tax haven status and unspoilt natural beauty has led to a growing reliance on the finance and tourism industries. Overseas aid from Australia, New Zealand, France and Britain is also important.

12. Vanuatu has no known developable fossil fuel reserves. The country is relatively rich in renewable energy resources which include geothermal, hydro, solar, bio-energy and wind. Electricity generation and transport are still mainly based on imported fossil fuel though have significant potential for further conversion to renewable energy in the future. On average, around 65% of petroleum imports are used for transport, 30% for electricity generation and 4% for household use. About 7% of rural dwellers have access to any sort of electrical services other than portable lights and radios powered by dry cell batteries.

13. The government wants to reduce imports of fossil fuels as the cost of petroleum product imports typically exceeds 50% of the total value of Vanuatu’s exports. The ADB has provided PPTA to the Government of Vanuatu for the Energy Access Project to increase energy access to

Page 10: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 7

households and businesses on Malekula and Espiritu Santo through expansion of existing distribution grids and the development of low-cost renewable energy generation from hydropower. This is being complemented by other GOV initiatives to increase electrification of rural communities through the provision of stand-alone hybrid solar power plants.

14. The impact of the project is expected to improve the livelihoods of households in Malekula and Espiritu Santo and facilitate an increased supply of clean renewable electricity to households.

B. Project Outputs

15. The project will have following outputs: (i) power distribution grid extension in Santo and Malekula islands, (ii) Brenwe Hydropower Plant (BHPP) in Malekula, (iii) capacity building, and (iv) efficient project management services.

C. Scope of Work of Brenwe HP Subproject

16. The Brenwe HP subproject is located along the Brenwe River system on the island of Malekula in Malampa Province. The Malampa province comprise of the main islands of Malekula, Ambrym and Paama. Malekula is the second largest island of the Vanuatu archipelago and its township which is also the provincial capital is Lakatoro. The airport is located some 5 km away in Norsup.

17. The hydropower site is approximately 23 km from Lakatoro the provincial administrative centre and Norsup. The subproject will harness the flow of the Brenwe River to generate hydro-electric power. The layout is similar to the partially constructed Brenwe hydropower project which was abandoned in the mid-1990s.

18. The intake of the run-of-river scheme is located at RL160 m above sea level about 5 km NNW of Unmet village and comprises a low weir with a single gated sluice on the left (east) side. Water is diverted into a side intake and sand trap on the left bank before being conveyed along a south trending headrace canal for approximately 1 km. The headrace canal passes alongside a gorge where it is cut into a steep to sub vertical slope. Along the gorge the river drops nearly 100 m over less than 1 km. The canal discharges into a forebay (16 m x 4 m). A 150 m steel penstock conveys water from the head pond west to the powerhouse (15 m x 8 m) located on the left bank of the Brenwe River at elevation RL 80 m above sea level which will provide an output of up to 400 kilowatt (kW) with a design flow of 0.8 m3/s.

19. Access to the site from Lakatoro is via the existing northwest Malekula Provincial Road which crosses the Brenwe River just upstream of the intake site. Access roads to the intake, powerhouse and forebay sites will be established within the 30ha land area being acquired, The detailed engineering surveys established that site access requires the use of additional land, and this has been achieved through a “Memorandum for Land Access” with the land owners who are the same owners as for the acquired land.

20. An approximately 23 km long 20 kV transmission line3 will be constructed from the powerhouse to Lakatoro where it will connect to UNELCO’s existing grid. The line route will be within the corridor of the powerhouse access road and the northwest Malekula Provincial public road to Lakatoro (existing 10m wide corridor). It is not a registered road per se but is maintained by Public Works Department as seen during the Bidders Site visit in May 2019.

21. Construction of the Brenwe River hydropower scheme will involve construction activities consisting of largely manual labour under the supervision of trained personnel. The site is accessible by access roads and transportation of construction material is not an issue. Civil works will require both skilled and unskilled workers. Construction of the subproject will provide the opportunity for the use of local people for future maintenance. The use of prefabricated equipment, reinforced concrete and masonry, minimises the quantities of building materials. It is

3 20 kV is a distribution voltage and is mounted on poles and aligned along existing road corridors. It does not require a

clearance corridor typical of high voltage transmission lines. However, for the purposes of this project the 20 kV line performs a transmission function and is therefore referred to throughout this report as a transmission line.

Page 11: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 8

estimated that temporary employment of 50 to 80 workers (60% skilled) will be required for the Project over the construction period of about 24 months.

22. The access roads to the intake, forebay and powerhouse sites will be used if possible but will require clearing of vegetation and regrading and new access roads will be constructed. This will be followed by demolition and removal of the abandoned weir, forebay and powerhouse structures. As much as possible waste materials (concrete, masonry, etc.) will be reused as construction materials.

23. At the head works site a temporary coffer dam and channel diversion will be constructed to enable construction of the intake works. This will be followed by largely manual excavation of soil rock and boulders to form the head works. As much as possible excavated material will be used as backfill with surplus material disposed of as required. The intake structure will be manually constructed with reinforced concrete.

24. Vegetation clearance and excavation of the headrace canal/pipeline, head pond and penstock route will be followed by construction of the stone masonry or concrete canal and forebay structures and concrete support piers and anchor blocks for the penstock.

25. Powerhouse and tailrace construction will commence with site clearance followed by excavation of discharge pit and concrete slab foundation for the powerhouse. River bank protection works adjacent to the tailrace will involve placement and filling of gabion baskets.

26. The 23 km long 20 kV transmission line will be built using insulated Aerial Bundled Cables (ABC) to minimize vegetation clearance. However, it will require i) minimum vegetation trimming in along a few sections of the road corridor; ii) transporting 12 m steel or concrete poles to the road side; iii) erection of poles; iv) stringing of cables; and v) installation of transformers. These sequential activities are primarily manual activities involving a small team with minimal use of mechanical equipment. No excavation is required other than manual or machine digging for the pole footing. Concrete foundations will be provided in some locations for the pole footings. Local residents will be employed to assist in this transmission line work, including vegetation clearance.

27. The grid supplied by power from Brenwe HPP will be extended to an estimated additional 1,050 households in Malekula, including the settlements of Unmet, Brenwe, Leviamp, and Lambubu. The VEAP will also extend the grid on Espiritu Santo north of Luganville. The VEAP will finance 79 km distribution lines, step-down transformers and poles.

28. The Executing Agency (EA) will be the Ministry of Finance and Economic Management (MFEM) and the implementing agency (IA) will be the Department of Energy (DOE) assisted by the Vanuatu Project Management Unit (VPMU).

29. This LARP is based on the findings of the assessment of the selected site in Malekula in Malampa Province carried out under the PPTA. The LARP has been prepared following ADB’s Safeguards Policy Statement (SPS) and applicable laws of the Republic of Vanuatu. It follows the following outline as prescribed by SPS: (i) Executive Summary; (ii) Project Description; (iii) Scope of Land Acquisition/Resettlement; (iv) Socioeconomic Information and Profile; (v) Information Disclosure, Consultation, and Participation; (vi) Grievance Redress Mechanisms (GRM); (vii) Legal/Policy Framework; (viii) Entitlements, Assistance and Benefits; (ix) Income Restoration; (x) Budget and Financing; (xi) Institutional Arrangements; (xii) Implementation Schedule; and (xii) Monitoring and Reporting.

Page 12: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 9

III. SCOPE OF LAND ACQUISITION AND RESETTLEMENT PLAN

A. Scope of Land Acquisition

30. The Brenwe HPP includes the development of hydropower facilities and infrastructure (water intake, headrace, forebay, canal, power station) with an output of up to 400 kW. It will include an access road from the power plant to the existing Provincial road and construction of a 20 kV power transmission lines to connect the power station to the existing Norsup/Lakatoro gridline. In summary:

16. 30 hectares for hydropower facilities. 17. Forebay road from boundary of acquired land to existing road (100m). 18. Power Station road from boundary of 30 Ha acquired land to existing road (about

2.5km) 19. Road reserve for 22km transmission line.

31. It requires 30 ha of land area to develop the hydropower facilities. The transmission line will

follow the existing provincial road corridor and it is not expected to involve any land acquisition. The extent of tree cutting and trimming within the transmission/road corridor can only be determined during the detailed design. The power concessionaire is expected to install the transmission infrastructure. The project will undertake full land acquisition and compensation for the hydropower facilities following the required ADB and GOV processes and procedures. Two custom lands, each with multiple landowners, were identified as the land required to accommodate the hydropower facilities, i.e., Wiaru land (west side of the river, 12 ha) and Tervaut land (east side of the river, 18ha). The access road crosses Tervaut and Timbun custom lands. There is a developed cocoa and coconut plantation, along with small areas of food garden, on the land that may be traversed by the forebay access. The owners of these crops have been identified and the compensation mechanism has been captured in the Road Access MoA signed by the Land holders and verified by a Third Party Verifier (TPV). If in the event the Land holders are willing to forgo compensation then a signed agreement will be effected by VPMU and the APs and verified by third party. Affected custom lands, if any, and APs along transmission line corridors have not yet been determined.

32. Consultation was held with APs and communities in 2014, 2016, 2017, and 2018 on the land requirement of the BHPP. The custom landowners and their representatives were informed of the scope of the Government’s land requirement. A Schedule One4 notice (a public notice that the land may be required for a public purpose) was posted on 18 May 2017. Schedule 2 was served on 17 July 2017. After investigation of the land, a Schedule Three notice (to custom owners and interested persons that the government intends to acquire the land) was issued on 21 August 2017. A Schedule Four notice (advising that a custom owner or person interested in the land could lodge a claim for compensation) was issued on 10 February 2018.

33. Three groups have claimed customary ownership of the Wiaru land. Three groups have also claimed ownership of the Tervaut land. The process of determining the rightful customary landowners have been processed through the village, area and island tribunals to the Supreme Court for resolution. Following these processes, the Tervaut Land Appeal Case was heard before the Supreme Court in November 2017 and the judgment was made in November 2018 in favour of the Tamat Family. The Wiaru land ownership has been previously determined by the court. The final LARP will include the list of legal customary owners and affected persons once the detailed design is available.

B. Land Acquisition Impacts and Affected Household/Persons (APs)

34. The subproject requires 30 ha of land for the hydropower facilities. The land is located within rugged and steep terrain with the major portion bounded by very steep ridges (almost vertical)

4 As required by the Land Acquisition Regulations under the Land Acquisition Act

Page 13: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 10

dropping down to the river bed. No economic use of the area is undertaken within the area of land being acquired.

35. The affected land is not used for any productive purpose and therefore not a source of subsistence or income for any of the land claimants and their families. No other known persons will lose income or from use of the acquired land. No loss of homes, incomes, employment or important food source, will result from the acquisition of the land. Instead, landowners and other residents of the district will benefit from the BHPP by being able to access a reliable electricity supply, including potential income generating opportunities during construction and in the long term. From site inspections and interviews with landowners, traditional leaders and Island Council members, it is assessed that no persons will lose 10 per cent or more of their land or income due to the subproject. Interviews with APs also confirmed availability of lands on other parts of the island that APs have access to for food and income. The exact extent of need for clearing of trees and vegetation on the transmission routes will be determined after the detailed design study.

Table 1 below provides a summary of features of the HPP including estimated land requirement and numbers of APs in the subproject site:

Table 1: Brenwe Hydropower Subproject Features and Land Requirements5

Feature

Proposed Interventions Construction of hydropower facilities, road, & transmission line

Location of proposed site for subproject Brenwe River

Weir (10 m x 20 m) 200 m2

Intake/ Settling Basin (15 m x 30 m) 450 m2

Head Race Canal Corridor (8 m x 900 m) 7,200 m2

Forebay (15 m x 30 m) 450 m2

Penstock Corridor (8 m x 100 m) 800 m2

Switch Yard (20 m x 30 m) 600 m2

Powerhouse (20 m x 30 m x 6m) 600 m2

Accommodation (20 m x 30 m) 600 m2

Storage and Site setup (40 m x 50 m) 2,000 m2

Ownership/type of land Customary land

Type of land use Natural bush covered ravine. No residential, commercial, or agricultural use

Land acquisition requirement 30 ha

Number of groups making claims to the land 6

Number of affected households At least 72

Number of Female-Headed Households None

Affected households losing 10% or more land None

Other Affected Assets Trees within transmission line corridors

36. The list of land claimants/ representatives/ landowners is shown in Table 2 below:

Table 2: List of Brenwe HPP Land Claimants/land owners

Land for hydropower facilities

on East Side of Brenwe River

(Tervaut lands)

Land for hydropower facilities –

West Side of Brenwe River (Wiaru

lands)

Transmission line6 (tree

cutting)

Tamat Family(Land owner)

• 4 HH, plus extended family

with unknown number of

members

• Nicholas Nakar /Achille Nakar (

Land Owner) 3 HH, 11 members

Numerous HHs along roadside

are likely to be affected (can be

determined only after detailed

design)

Source: PPTA and updated 2019

5 Data on land are preliminary estimates. These are subject to confirmation and might change during the

implementation.

6 The extent of impact will depend on whether the road is formally gazetted under the Road Act 2013 or a mutual

agreement between parties is made.

Page 14: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 11

38. The PPTA consultants have tried to minimise land requirements during PPTA design. The acquisition area of 30 ha is the minimum area necessary for access, construction and long-term security. Engineering designs for the access roads and transmission corridor and infrastructure will minimise livelihoods and resettlement impacts. The measures include:

1) Appropriate siting of hydro facilities.

2) Utilise existing public roads to access the project sites to minimise land acquisition requirement.

3) Utilise existing road corridor right of way and local roads for the location of the transmission lines and for the distribution network.

4) Use of insulated cables for transmission lines to minimise vegetation clearance.

39. While no persons will be physically displaced or expected to lose 10% or more of their land or income, a number of households will be affected by the land acquisition for hydropower facilities. The subproject is therefore classified as Category B in terms of land acquisition/involuntary resettlement impacts.

40. The identified land owner-claimants and the land users could be affected by the creation of BHPP site access roads that extend outside the boundary of the acquired land. Depending on the detailed design, cocoa and coconut plantation trees will need to be removed to make a 10 m wide access road from the Provincial road on the east side of the river. Up to 1000 sq.m of land might need to be cleared for this access. Compensation will be paid to the crop owners for the lost trees and crops. An access road agreement with the land owners including a Third Party Verifier (TPV) has been executed in February/March 2019. Other households will be partially affected due to tree-cutting along transmission line and grid extension (actual number to be determined later).Similar compensation practices will be employed by the Project in this instance with the Department of Agriculture carrying out an assessment prior to tree cutting being effected along the final T&D design routes. At present a 4-6 m road carriageway exists, exclusive of road shoulders. Current practice for transmission lines in Malekula is 3 m from the edge of the road with 15 m right of way (ROW), which was acceptable to the local communities. The affected persons will be entitled to compensation for affected structures including crops, trees and gardens. Current practise by UNELCO (the electricity supply concessionaire) is that landowners and residents are paid for casual labour rather than receiving cash compensation for loss of crops and trees within the 3 m shoulder, In the event this option is chosen by the APs to forgo compensation then an agreement will be executed by VPMU and the APs and verified by a Third Party. The Road Administrator and Director General of Ministry of Infrastructure Public Works Utilities (MIPWU) and the Malampa Provincial Public Works Department (PWD) will determine the exact ROW to be used for BHPP.

Page 15: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 12

Figure 1: Brenwe Hydropower project – proposed facilities and acquisition area (30ha)

IV. SOCIOECONOMIC INFORMATION AND PROFILE OF AFFECTED PERSONS AND SUBPROJECT COMMUNITIES

A. Subproject Communities

41. The PPTA included meetings with key persons and stakeholders, including the Malampa Provincial Government members, the Secretary General, community leaders, interviews of APs and site visits, along with assembly of socioeconomic data for the subproject communities and APs. Household surveys of communities around the Brenwe River, Unmet, Brenwe village and Uri village7 were conducted.

B. Profile of Subproject Communities - Malekula Island and local villages

42. In 2016, the total population of the Malekula Island was 31,556 in 6,743 households. The male ratio was slightly higher than female at 51:49 while average household size was 4.3, which was much lower than the national average of 4.9. The province, including its capital Lakatoro is considered primarily rural. The population is almost exclusively Ni Vanuatu Melanesian.

43. Lakatoro is the main provincial and government administrative centre of Malampa Province and receives visits by people from the other areas of Malekula for short periods, mainly for the purpose of access to banking facilities, hospital, shops, airport, and markets to sell their produce. According to the 2016 mini census, the annual urban growth rate was 1.6 %, compared with the national average of 2.3%.

44. Approximately 90% of households own their houses and 80% are customary owners of the land on which their houses are located. The remainder are renting their houses and the land on which the house is located, or they are occupying the land by informal agreement.

7 The survey covered 75 households in addition to APs and this was undertaken to collect baseline socio-economic data as part of the

poverty and social assessment (PSA).

Page 16: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 13

45. As of 2016, only about 7.5% of households on Malekula were using electricity from the distribution grid. The majority of households (71%) were using kerosene lamps as their main source of lighting. The remainder were using solar power, torches, candles, wood, gas or Coleman lamps as their primary source of light. A few households also reported using small petrol generators. UNELCO supplies electricity within the Lakatoro - Norsup grid where about 526 customers (year 2012) are connected, i.e. only 21% of the potential customers within the service area of the UNELCO power plant. In the December quarter of 2014, the total electricity consumption was 171,000kWh (UNELCO) – supplied by diesel and solar generation.

46. In terms of drinking water source, about 35% of households in 2009 had a shared pipe system, 16% shared a village tank, 13% took water from a river/spring or lake, 10% had a household tank, 10% reported had their own private pipe system, and 9% had a protected well. The remainder sourced their drinking water either from village stand pipe, an unprotected well or used bottled water or another unspecified source.

47. In 2009 Malampa province had 8 health centres,19 dispensaries, and 44 first aid posts

48. The educational facilities of the province are composed mainly of primary and secondary and vocational schools as shown in Table 3 below.

Table 3: Schools and school rolls in the Brenwe Subproject area as of 2014

School Name School ID Enrolment

M F Totals

Leviamp 042936 142 108 250

Brenwe 042912 65 44 109

Unmet primary 042978 104 107 211

Unmet Secondary 0429379 57 56 113

Ste Therese de Mae (Unmet) 042944 60 50 110

Lambubu 2013 042931 61 62 123

Source: PPTA.

49. In 2009, of the population in Malekula 15 years and over 27% had completed primary education; 22% had some primary education; 10% had trio certificate 7% senior secondary almost 3% and 2% had some college degree and completed bachelor’s degree respectively. Approximately 15% had received no schooling at all. The literacy rate of the province was about 94.3%, with women having higher literacy rate than males (96% cf. 93%).

50. In terms of sanitary facilities, the majority (68%) of Malekula households use pit latrines (either individual or shared); only 16% use water sealed toilets and less than 1% of households use the flush-type toilet. Less than one percent reported having no toilet at all.

51. The 2009 Census found that the main source of income of Malekula households was sale of agricultural, fishery or handicraft products (53%). About 15% derived their cash income from salaries and wages, 12% from operating their own business, and 11% from unspecified sources. About 9% reported having no cash income at all.

52. The 2010 Household Income and Expenditure Survey (HEIS) found that the average monthly income of Malampa households was VUV 62,200, with an average per capita income of VUV 13,800. Approximately 56% of household incomes are from cash sources; on the other hand, 34% of total household expenditures is in cash. The proportion of households below basic needs poverty line (BNPL) in 2010 was 8.3%, slightly lower than the 9.0% reported in 2006.

53. Close to Brenwe HPP site, the most important settlement is Unmet village. It is approximately 5 km from the Brenwe HPP and 23 km from Lakatoro. It is bigger than Lakatoro in terms of population size. The village has both French and English speaking residents and it has both a primary and secondary schools. French and English are taught in the secondary schools and it has strong ‘kastom’ influence.

54. Unmet also has its own church, dispensary, and small market. Most of the households in the community depend on agriculture as their means of livelihood and subsistence. Coconut, cocoa

Page 17: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 14

and seasonal vegetables are the principal crops, and produce is usually marketed in Lakatoro. However, for coconut and copra a ship from Luganville occasionally comes to purchase the produce directly from the growers. There are extensive plantations of cocoa and coconut in the Brenwe River vicinity.

C. Socioeconomic Profile of Households/Persons Affected by BHPP Land Acquisition

55. The Supreme Court has made a decision on the rightful customary owner of the Tervaut land (18 ha) which is part of the 30 ha of land being acquired for the BHPP. As for the ownership of the Wiaru land (12 ha), the Courts had determined a few years earlier the rightful customary landowner it may now be possible to clearly provide a profile of those who will be actually affected by the Brenwe land acquisition and any other lands for which access may be sought. For the Wiaru land, it is reasonable to conclude that certain households will be definitely affected as landowners, while non-owning land users may be affected if access roads outside the acquired lands are necessary. Earlier drafts of this LARP provided a combined profile of the three claimant groups for the Tervaut lands. No socio-economic profile is available for the claimants to the Wiaru land being acquired for the BHPP and will be carried out by VPMU and the DSC before the next update of the LARP.

56. Based on earlier interviews with the land claimants, the 3 groups of claimants for the acquired Tervaut custom land (18ha) had included at least seven households (comprising 36 persons) from the villages of the Brenwe HPP area and the greater Lakatoro town area. However following the Court judgement in 2018, this will now involve only the Tamat Family and extended family members. For the acquired Wiaru lands (12 ha), the interviews conducted in 2018 indicated three groups of land claimants, made up of seven households with at least 37 members, most residing in the Brenwe-Unmet-Wiaru area. Following the clarification from the Director General Lands, this will now involve only the Nakar Family and extended family members and reported in the next updated version of the LARP.

1. Demographic Profile of Brenwe HPP APs

a. Tervaut land claimants

57. Of the total (36) members of the potentially affected Tervaut land households, 39% are composed of female while 61% are males. Households have an average size of 5.1 members. All are Ni Vanuatu Melanesian in ethnicity (Table 4).

Table 4: Population of Potentially Affected Tervaut Households

Indicators N° %

Number of affected households 7 100

Number of total persons in HH 36 100

Of which, # of female members 14 39

Of which, # of male members 22 61

Average # of persons in HH 5.1 -

HH by Ethnicity – Ni Vanuatu 7 100

58. In terms of the residency profile, the declared customary land owner for the East bank lives at

Tautu 23 km away from the project area, On average the residence of the households is about 1 km away from an existing road, 1-3 km away from school and about 1-3 km away from the public health centre and about 17 km from the major market in Lakatoro. In terms of physical characteristics of their houses, the majority of houses at Tautu are concrete buildings with iron roofing while those at Brenwe would be from light traditional materials. All households have their own toilets and all the houses are built on community land as well as customary owned land. Tautu village is part of the Unelco grid at Lakatoro whereas Energy source (for lighting) in

Page 18: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 15

Brenwe is either from individual Solar Panels or from traditional sources. Table 5 shows the source.

Table 5: Status of Residency of Affected Households of Brenwe Subproject

Status of Residence No %

Length of Stay in place

Over 10 years 7 100

Physical characteristic of house

Average distance from nearest facility (KM)

Road < 1 km

Market 17 km

School 1-3 km

Health centre 1-4 km

No of HH by house type

Traditional light material 7 100

No of HH by tenure status - house

Owner w/title 7 100

No of HH by tenure status –land where house is

Owner w/title 3 43

No of HH by power/energy sources

Power Grid 2 29

Solar 1 14.3

Others 2 29

Not stated 2 29

No of HH by having Toilet

Owned 7 100

Water Source

Piped Two-thirds 66

59. Among the affected land users of Tervaut land living at Brenwe, there is a high proportion of

household heads without any formal schooling (43%). Only one head has attained secondary level education while 3 had primary level education (Table 6).

Table 6: Educational Attainment of Heads of Affected Households of Brenwe Subproject

Education Level Attained Brenwe

No. %

Illiterate / No Schooling 2 29%

No Schooling but can read and write 1 14%

Primary education 3 43%

Secondary education 1 14%

Grand Total 7 100%

60 The PPTA socioeconomic survey showed that majority of the heads of the potentially affected

households were engaged in agriculture, off farm labouring, civil service, private sector employment, and/or business. See Table 7 below.

Table 7: Occupation of Head of Affected Households, Brenwe

Occupation Total (multiple

responses

N° %

Subsistence farmer 6 86

Business 3 43

Private Sector employ 2 29

Civil Service 1 14

Page 19: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 16

Source: PPTA

61. The average annual income of these potentially affected households was VUV315,005 (USD 2850). On monthly basis, income of households is VUV26,250 (USD 242); per capita monthly income is estimated to be VUV5,147 (USD48).

62. The major contributors to total annual household income for these potentially affected households are agriculture (root crops; vegetable; fruit and animal husbandry), harvest of forest products, salaries and wages, and trading.

63 The average annual total expenditure of the potentially affected households is about VUV424,065, which is greater than the reported income.

b. The Wiaru land claimants

A socio-economic survey of the Wiaru land claimants is yet to be conducted and the LARP to be updated accordingly but there are 30 HH in the village and would have a similar demographic profile and average annual income as the Tervaut Landowners given that this areas are in relatively close proximity to each other. This will now be done by VPMU and the DSC and concentrated to the Nakar Family and updated in the next version of the LARP

D. Assessment of Impacts of the BHPP

1. Extent of Loss and Impacts from Land Acquisition

64. A total of 30 ha of customarily owned land is being acquired for the BHPP, all of it being unoccupied, uncultivated, and non-economically productive. Hence there is no expected risk of landlessness, loss of home or other structures, and/or loss of major income source due to the land acquisition for the BHPP. No land is expected to be acquired for the establishment of the power transmission lines, though some livelihoods assets may be lost by those whose land lies immediately adjacent to or impinges upon the road right-of-way within which the transmission and power distribution infrastructure will be located.

65. The customary landowners of the Brenwe HPP area will lose a total of 30 ha of bush or idle lands. It will not negatively impact the livelihoods of the landowners since the site is heavily clad bush land on very high slopes. Interviews with Village leaders and potential APs as well as visual observation revealed that the affected land is not used for residential or agricultural activities. People from villages in the wider Brenwe river district do not have their food gardens on the site, though extensive plantations and some food gardens are located adjacent to the road, and on more suitable land away from the Brenwe river gorges. There is no plan in the immediate future to use the area for any development by the village communities.

66. The impacts of the transmission line and grid extension can only be determined during the detailed design stage. Assessment will be part of the updated LARP following the detailed design for these components and the Contractor in conjunction with the DSC and VPMU will update the LARP.

67. The loss for the potential APs is not expected to be more than 10% of total land and income reported by APs. The initial estimation was done through interviews and/or discussions with land claimants and key community leaders which indicated the approximate boundaries of the claimants’ customary estates. The potentially affected people and their representatives reported that they currently have access to adequate lands in other parts of the island for food production or income generation.

c. Views of Potential Affected Persons on Impact of Loss of Land

68. All interviewed land claimants view the loss of their land as insignificant since the site is physically unsuitable for cultivation and there are other available and more accessible plots for

Page 20: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 17

agriculture. The majority of landowner-claimants and residents view the development of the upper Brenwe River site for hydro electricity generation as an opportunity to stabilise and collectively gain direct access to the power supply, thus maximising the value of otherwise unproductive or unused land. All the land claimants expect cash compensation for affected land, and in early 2018 had received the Valuer General’s Statutory Valuation for the land over which they have made a claim. In this, the Tervaut land, including trees, was valued at 18 million Vatu, and the “Lamu and Tepenel land” (referred to here as Wiaru land) as 22 million Vatu. In interviews in September 2018, most of the land claimants were satisfied with the valuation, though several parties were unclear of how the land value was determined. As of September 2018, Kemuel Harry, one of the current declared customary landowner of Tervuat lodged a formal objection to the valuation stating that he be given the opportunity to also provide his own independent valuation of the then disputed Tervuat land. He enquired about the valuation of the Tervaut land which was greater in area but lesser in value compared to the Wiaru land. Department of Lands have responded to his letter and also sent copies of the letter to other parties who were claimants at that time. This was discussed during the Community Consultation and Awareness program of February 2019 end led by the DG Lands with the Harry family and this has been resolved.

69. All consulted land claimants and village and provincial councils support the project and are not in favour to deter project implementation by refusing access to land for further investigation and development. This was again affirmed during consultations in September 2018 and February 2019.

d. Agreement on Land Access

70. During interviews in 2014 and February 2019, and subsequently, all the land claimants / potential APs expressed strong support to allow the government to acquire the proposed site for the project. The development benefits, as well as cash compensation for land, are key considerations for the land claimants’ and community leaders’ support for the BHPP and their willingness to allow the GOV to acquire the land for this public purpose. A copy of an initial memorandum of agreement (MOA) on willingness to support and allow the project access to site is in Appendix 1.

A site visit and consultation was conducted in December 2018 with the land users/ land owners for both the East Bank access road from existing provincial road to the forebay and west bank access road from the main road to the powerhouse. There are six (6) land users with gardens, cattle farm and coconut plantations on the West bank access road and declared land owner, Nakar Family. There are two (2) land users with garden and plantations and declared land owner, Tamat Family, on the East bank. An inventory of affected plantations will be undertaken by the Department of Agriculture after the final road design is determined and before the actual construction work is commenced as per the MoA for the Access Roads. The Affected Persons will be entitled to compensation for the affected crops and trees. Any alternative arrangements to forgo compensation will be acceptable as long as this will not result to any major economic impacts to the affected persons and voluntarily decided by the affected persons. Alternative option such as agreements over vegetation clearance for paid employment from landowners and land users affected by the installation of the transmission infrastructure within the road corridors will be subject to MoA and third party verification. A Memorandum of Agreement, valid for five years, to provide consent to build the access roads through the land has been signed by all of the land users whose names and details have been appended to the MoA. During construction of the Project and within the five years term, the GoV has the option to acquire permanently the access road land or extend the MoA term as confirmed by the DG Lands. The MoA signing process has been completed and compensation for the damaged crops will be made to the users once an assessment is carried out by the Department of Agriculture.

e. Poverty Status of Potentially Affected Households in BHPP Area

71. As per findings of the social economic survey (SES) undertaken in 2014, poverty incidence among the affected households in BHPP area including the access road is as follows.

Page 21: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 18

72. The estimated average monthly income of the surveyed claimant households is VUV 26,250. The monthly per capita income is derived by dividing average monthly income by average size of household (5.1); this is equivalent to VUV 5,147. The average per capita income per week is VUV 1,286. The BNPL in Vanuatu in 2010 was VUV 1,761 per capita income per week or VUV 1,900 per capita per week adjusted for inflation in 2013. 8 Of the seven potentially affected Tervaut households, four have a weekly per capita income below the BNPL; one household did not report his income while two have income above the BPNL. Data on the Wiaru households will be provided in the update LARP.

f. Impacts on Women and the Poor

73. Women and those economically marginalized will be major beneficiaries of the Project. Improved access to reliable power, as a goal of the VEAP, will facilitate provision and availability of health and educational services as well as improved safety of women and girls during night time. Improved safety enables greater participation in the life of the community, especially decision-making forums. Women also report that having reliable and affordable lighting and power will enable their children to study in the evenings, to undertake home industry and crafts etc for income generation, and to have home entertainment (e.g. recorded music and TV) for the family. Where affordable, refrigeration will reduce food wastage, especially of animal and fish protein, and reduce the incidence of gastrointestinal illness due to food contamination. In general, community members anticipate a significant improvement in their standard of living.

74. There are no prominent gender issues among APs identified in this subproject as the Council of Women has not yet been consulted. There are no recorded female-headed households among those claiming ownership of the acquired land.

75. The Department of Women’s Affairs, under the Ministry of Justice, had been consulted in January 2019 however, and has emphasised on the importance of building and maintaining good relationships and communications with the chiefs so they are aware of the need and importance of including women in the discussions regarding the project. Sensitivity should be given to the timings of meetings with women in communities and whether or not it would be more appropriate to meet with them separately. Meetings can discuss employment opportunities and opportunities for economic activities that may become available due to the presence of the project, such as catering for workers and gardening and sale of fresh produce to the workers camp, which would be of economic benefit.

76. Key priorities identified by women APs include (i) stable affordable power and (ii) access to employment during construction.

g. Indigenous Peoples or Cultural Heritage

76. The local people in the project sites do not meet the ADB criteria (distinctiveness and vulnerability) of Indigenous Peoples. The potentially affected people in the project sites are part of mainstream Ni-Vanuatu Melanesian society and are not considered to have a distinct culture from the mainstream society and are not discriminated upon by any other groups due to their language, skin colour and education level. Thus, they will not require special protection or attention from the project. Although they have dialect distinct from other outer islands, as with other Ni Vanuatu, they communicate with one another using either Bislama, French or English. However, communities in the project area are known to be strong in ‘kastom’ beliefs and cultural practices with various local languages. There has been one tabu place revealed to the project staff which was located on an initially proposed access road. This proposed road will no longer be used in order to protect the cultural heritage area.

77. There are no expected adverse impacts from the land acquisition for the BHPP on the cultural heritage and practises of the potentially affected people.

8 Inflation in Vanuatu from 2010 to 2013 was as follows: 2010 – 3.0; 2011 – 1.0 and 2012 – 1.4 (ADB)

Page 22: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 19

1. Conclusion

78. Based on the result of the household survey, household access to grid electricity in the BHPP area is non-existent. Many households have low-power 12-volt solar panels sufficient only for several hours of light. Some in the grid extension area (e.g., at Lambubu) are connected to a localised, generator-driven network. Others in the UNELCO concession area around Lakatoro already have access to the electricity network. The majority of households want to be connected to grid electricity and are willing to pay for the service as long as it is affordable. More broadly, the provision of hydroelectricity to the northern part of Malekula will stimulate general improvement in the social economic situation of the whole community including improvement in the availability of basic well-being and social development services such as health and education. Availability of public lighting at night help allay personal safety concerns among women and girls an enable them to have greater participation in the life of the community.

V. INFORMATION DISCLOSURE, CONSULTATIONS, AND PARTICIPATION

A. Stakeholders

79. There are several categories of project stakeholders for the VEAP and the BHPP in particular: landowners, traditional leaders, private sector, non-government organisations (NGOs) and community groups, including women and youth. Several Government agencies and their ministers are also stakeholders, including the Department of Lands and Natural Resources, the Ministry of Agriculture Forestry and Fisheries, the Ministry of Infrastructure and Public Utilities, and the VPMU.

80. The Government agencies are committed to providing support in achieving government’s target of increasing renewable energy sources for the country; thus, they are willing to provide necessary support to acquire required land for the BHPP. The Government is committed to develop an alternative energy source to lessen dependence on imported oil and be able to sustain viability of its investment.

81. Key stakeholders’ specific interests are:

1) Provincial government/council – Supportive of the proposed hydropower subproject. They would like to see the subproject to start as soon as possible. Consultations have been going on for some time.

2) Affected landowners/claimants – Interested to benefit from access to power and cash compensation for affected land. They would like to see the subproject to start as soon as possible.

3) Women’s groups - benefits from access to electricity, and employment/income opportunities.

4) Communities around the sites – Supportive of the government’s project to develop alternative sources of reliable and affordable power supply to stabilise power tariffs and also benefit from improved government services such as health, agriculture and education. Communication will also be improved with availability of power, in particular use of technological devices, such as mobile phones, that are powered by electricity.

5) Youth groups – Access to information, skills and employment opportunities.

6) Business groups – Access to cheaper and reliable source of power supply.

Figure 2: Traditional governance structure in Malekula9

9 Note: there may also be ‘custom area council of chiefs’ depending on how local leaders have decided to structure

themselves.

Page 23: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 20

B. Community Consultations Held

82. As part of social surveys and assessments during the PPTA, stakeholders and community consultations were carried out during field visits over March - April 2014 with follow-up in February 2016 and continuing with project design work in 2017, 2018 and 2019. Stakeholder consultations were carried out through meetings with key officers at offices of different government and non-government agencies in Lakatoro and at village council offices. Key respondent interviews focus group discussions and questionnaire surveys were conducted on-site in the villages and local residents’ homes.

83. More than 10 stakeholder consultation meetings were conducted in Malekula during the PPTA and involved at least 200 officials/participants from various agencies, i.e., Lands Department, Environment Authorities, Statistics Office, utility offices, landowners/claimants/APs, women’s groups etc. The list of officials/stakeholders consulted at that time is presented in Appendix 2. The consultations included both discussions with stakeholders and discussions with community/island/provincial level authorities including APs, traditional and elected leaders and women’s groups from the subproject sites.

84. During PPTA Safeguards Team site visit, the village councils in Unmet and Brenwe areas and the island (Malekula) and Malampa provincial councils confirmed general awareness of the proposed hydro subproject and general site locations. Details of consultations carried out during PPTA field visits are presented in Table 9 following.

Table 9: Stakeholder/ Community Consultations during Visits of Subproject Sites

Date / Venue N° of participants/

organisations

Activities/Issues discussed / remarks10

19 March 2014 –

Malampa Provincial

Office

12 officials of province. Discussion of objectives and concerns of Project; requirement

for support in terms of data /site access.

19 March 2014 at

open ground in

Unmet village

More than 100 participants

– women health/school

teacher, chief, farmers,

villagers.

Re Brenwe HPP, Environmental and Social Safeguards,

scope of land acquisition and willingness to participate in the

project. Concerns on benefits for the community.

April-May 2014 at

provincial and

community levels

Various informants:

landowners/claimants,

lease holders, officials,

women groups, etc.

Socio-economic concerns; demand/need for projects,

satisfaction with power services, etc.

29 April 2014 –

Malampa Provincial

Office

4 officials of province

including Secretary

General Samuel +3,

Chairman Council of

Chiefs, Brenwe land

owners.

Brief on scope of project; clarifications with land owner and

council of chiefs, emphasis on clear resolution of land issues

and requirement to have formal MOA agreeing in principle to

access to sites and negotiations to procure land for the

Brenwe HPP.

10 Queries raised by people were answered to their satisfaction and it was assured that their concerns would be

addressed in the process of project design.

National Council of Chiefs (Malvatumauri)

Malekula Island Council of Chiefs (Malmetanvanu)

Six Area Councils of Chiefs

Village Council of Chiefs (nakamals, land tribuals)

Paramount Chief

Page 24: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 21

Date / Venue N° of participants/

organisations

Activities/Issues discussed / remarks10

First week of May

2014- communities

within Brenwe HPP

4 focus group discussions

composed of 10-15 people

per group.

Environment and social issues; concerns on land acquisition

and compensation, community development issues such as

livelihood and income opportunities, gender and participation

concerns, access to power and willingness to participate in

the project.

First week of May

2014 - communities

within Brenwe HPP

60-80 Sample households

including APs.

Socio-economic profile of households, issues and concerns re

environment and land acquisition and willingness to

participate.

February 2016 30 persons including

officials and landowners.

Follow up meeting on proposed project and land issues

around hydro site.

September 2018 6 groups of landowners,

officials.

Stantec team, with DOE, VPMU, and provincial council

support. Checking on progress on land acquisition process,

compliance with ADB social safeguards policy, AP project

understanding and consent, responses to land valuation,

responses to alternative site access proposals, and capacity

for project implementation – to update LARP.

December 2018 4 out of the 8 land

users/claimants at Brenwei

VPMU, DOE, DOL and Malampa provincial support.

Consultation on MOA for land for access roads to the

boundary of the 30ha land for project site.

February 2019

February & March

2019

Tervaut Landowner

All 6 BHP Land Claimants,

Land Users and all relevant

communities

VPMU – Follow up on letter of objection to valuation report

and response from DOL. Clarification on internal conflicts

among landowner.

VPMU, DOE, DOL and Malampa provincial support.

Consultation and execution with TPV on MOA for land for

access roads to the boundary of the 30ha land for project site,

general community awareness and consultations on the

subproject and extent of Transmission and Distribution

network from Leviamp, Brenwe, Unmet to Lambubu and

Kona Point.

85. Overall, the BHPP land claimants and village and island leaders have expressed support for the

project. Potential APs are willing to allow the Government to acquire their land to construct hydropower infrastructure. They entered into a memorandum of agreement (MOA) with the GOV accordingly. See Appendix 1.

86. On issues raised, some stakeholders were concerned about the location of the transmission line and site access routes. The failed hydro development project in the 1990s by a foreign company had attempted to short-cut the connection of transmission lines from the power plant to the Norsup-Lakatoro road by cutting across valuable agricultural lands and in the process cut down valuable trees and damaged crops. The ensuing outrage resulted in stoppage of the project and consequent withdrawal of the foreign developer from the partially completed project. During consultations during PPTA, assurance was sought that the current design for the BHPP would route the transmission lines alongside the existing Provincial road and avoid valuable areas. Given such assurance, the local communities have expressed strong support for the project.

Regarding the access roads to the project site area, one of the APs, Joshua Mathew, raised concern that an access road through his coconut plantation and cattle farm, would increase likelihood of thefts, therefore requested that the access roads be monitored and access be restricted during the implementation of the project. The Tamat family, who are the declared land owners of the Tervaut land, also requested they be included in discussions regarding access roads through Tervaut land which was done in February 2019. Although they reside in Tautu village, and do not directly use the land affected, they are the land owners.

C. Consultation on LARP Preparation

87. This LARP has been prepared in close ongoing consultation with representatives of the potentially affected parties. The various project teams have visited the affected site, most

Page 25: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 22

recently with the visit of the Stantec design team members in August and September 2018 and the VPMU, DOL and DOE on 25 to 28 February 2019. The following consultations were conducted:

• Meetings undertaken on May 2014 with provincial and villages officials as well as concerned landowners/claimants on the need for agreement (MOA) on allowing access to site and willingness to sell affected land for the project.

• Meeting with representatives of the affected landowners/claimants, villages leader, provincial council (April- May 2014) - Issues discussed are presented in Annex 3.

• Meeting with representative of Department of Lands in April 2014 in order to discuss the processes by which the Government acquires the land according to the laws of Vanuatu.

• Consultation with the Valuer General’s office regarding compensation entitlements and valuations.

• Update the MOA in February 2016 with landowners and claimants in Lakatoro, including meeting with representatives from CLMO, DOL and Provincial Government.

• During 2017 and 2018, various visits by the Acquiring Officer and other officials to provide information and deliver and discuss notices required under the regulations of the Land Acquisition Act

• Update of the LARP as part of the Stantec design work which included site visits and discussions with BHPP land claimants and GOV stake-holding officers.

• In February 2019, representatives from DOE, VPMU, Lands Department made Community consultations and awareness with the execution with TPV on MOA for land for access roads into the boundary of the 30ha land for project site, general community awareness and consultations on the subproject and extent of Transmission and Distribution network from Leviamp, Brenwe, Unmet to Lambubu and Kona Point. An Information Booklet of the Project was prepared in the three languages and handed out during this major consultation

88. During the detailed design and further updating of the LARP, additional information gathering and consultation with the affected landowners and land users and their families will be carried out to ensure full stakeholder participation in project preparation as per the Communication, Consultation and Participation Plan (CCPP), and as required by the ADB safeguards policy. In addition, the landowners and communities along the transmission line and grid extension sites will be consulted. They will be entitled to compensation for affected structures including crops, trees and gardens. Any arrangements that they will prefer to enter to forgo compensation will be acceptable as long as this will not result to any major economic impacts to the affected persons and voluntarily decided by the affected persons. Alternative option such as agreements over vegetation clearance for paid employment from landowners and land users affected by the installation of the transmission infrastructure within the road corridors will be subject to MoA and third party verification. This task will be carried out by the design and contracting consultant in coordination with the VPMU and the DSC, other key project approval and land acquisition agencies, and the power distribution concessionaire.

D. Disclosure of Draft LARP

89. The LARP was prepared based on PPTA findings and consultations with concerned stakeholders particularly the potentially affected/land claimant households. Consultations on the draft LARP were carried out with the potentially affected persons, provincial government, and other local stakeholders during the preparation of the Memorandum of Agreement (MOA).

90. Once detailed design of the BHPP and the transmission route is available, the LARP will be updated and disclosed to affected parties in English and Bislama, with the notices including a summary of land acquisition information translated to other two official local languages - Bislama and French as required by Vanuatu law. A copy of the LARP will be made available at the DOE and DOL offices in Port Vila and provincial government offices in Malekula. The LARP will be posted on the ADB project website as required by the Bank’s safeguards policy.

Page 26: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 23

91. As part of the legal requirements and compliance with the ADB safeguards policy the DOE, and DOL will ensure all the required Schedule notices for a compulsory land acquisition for public purposes under the Land Acquisition Act (LAA) are issued in a timely and informative manner and will keep full records of any disclosures, requirements, and consultations with affected persons regarding the land acquisition and LARP preparation. At each key stage in the acquisition process the responsible agencies will conduct awareness sessions in affected communities in order to ensure the community residents, especially those who are illiterate, are kept informed and they are able to contribute to the LARP.

E. Consultations and Information Disclosure during Project Implementation

92. A Communications, Consultation and Participation Plan (CCPP) is included in Appendix 3. Consultations will continue during the detailed design and updating of the LARP before start of the civil works construction as well as at the implementation stage. VPMU/DOE with DOL and provincial representatives will continue consultations with leaders in the Island Councils, village leaders including traditional chiefs, affected landholders/APs and all other interested members of the community. Separate meetings will also be organised with women to continue to understand and discuss their preferences and concerns. These consultations will be facilitated by a BHPP Community Liaison Officer.

93. Prior to any construction on the BHPP commencing, the DOE in coordination with the DOL and Malampa Provincial Government will advise on the compensation monies and procedures for settlement with the land owners for the 18 ha of Tervaut land, and land owners for the 12 ha of Wiaru land being acquired for the project. They will also seek access agreements for any new roads that might be required for the construction and the transmission corridor, and identify and compensate current land users (if any) for any losses to crops, trees, and loss of access etc. Specific terms of compensation rates as well as grievance redress procedures will be explained to the actual or potential APs. In addition, DOE/DOL and Councils will inform the landowners when and how compensation will be paid, including payment of the compensation due into a customary landowners’ trust account pending final determination of the actual landowners.

94. During project implementation, public consultation and awareness will be continued through regular meetings organised by the contractors in conjunction with the VPMU and relevant agencies. The purpose of these meetings is to ensure that the community is aware of the construction implementation plans, detailed design, and updated LARP implementation. They will also identify with the APs any LARP implementation problems and will undertake timely remedial actions.

VI. GRIEVANCE REDRESS MECHANISM

95. There are customary village level mechanisms, as well as legal systems to address local issues and grievances. Councils of chiefs and community leaders play key roles in resolving disputes at local level. There are also courts such as a Customary Land Tribunal at the provincial level to formally hear and adjudicate on matters related to customary land. The VEAP will use or adapt existing conflict resolution mechanisms as part of a project grievance redress mechanism (GRM). The key functions of the GRM will be to (i) receive, record and prioritize local grievances; (ii) settle the grievances in consultation with complainant(s) and other stakeholders; (iii) inform the aggrieved parties about the solutions; and (iv) forward the cases to appropriate levels.

Community Level Mechanism

96. The project will coordinate with the Council of Chiefs to resolve matters related to internal village affairs regarding customary land and the distribution of compensation payment among family members. To support and supplement the roles of the Council of Chiefs, a community-level committee made up of community leaders, representatives of landowning APs, and representatives of the relevant provincial councils will be set up. The Committee will elect a Chairperson, expected to be a senior village chief, to coordinate its affairs. Any VEAP community complaints will be submitted to the Committee through the Chair, who will inform the VPMU verbally or in writing of complaints/grievance referred to it. The Committee will meet in

Page 27: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 24

the case where a complaint is lodged11. VPMU staff may facilitate but will not take any side in the Committee’s deliberation. Meetings will be fully documented and VPMU staff may assist in this process. The Committee will decide on a particular case within one month of the complaint being lodged. In the event that the Chair himself is a party to a case being reviewed, the meetings on this particular case will be chaired by a senior committee member.

97. In addition to resolving disputes, the VPMU will also work with the community-level committee and community liaison officer to develop community consensus and to ensure local support to the subproject.

Project-Level Mechanism 98. In order to receive and facilitate the resolution of APs’ any concerns, complaints, or grievances

about the project’s social and environmental safeguards performance, a GRM will be established at the subproject level. The GRM will address the complainant’s concerns promptly and transparently, and this will be gender responsive and readily accessible to all APs at no cost. It will not however impede or seek to override or impede APs access to customary redress or legal remedies.

99. The VPMU’s subproject manager supported by its staff and consultants will be the grievance focal point to receive, review and address project-related concerns and to facilitate resolution of disputes in coordination with the Government authorities. Complaints or grievances reported to the project contractor will be recorded and passed to the VPMU within one working day. When subproject implementation starts, a sign will be erected and maintained at all sites providing the public with updated project information and summarizing the GRM process including contact details of the relevant person at the VPMU. This will be complemented by a printed brochure – containing all the necessary process and contact information – to be distributed to all households of the project area.

100. All project-related complaints will be recorded and investigated by the VPMU in coordination with relevant authorities. The VPMU will inform the DOE and Provincial Government within five working days after a complaint is received. A complaints register will be maintained which will show the details and nature of the complaint, the channel through which the complaint was received, the date, the complainant’s name and contact details, and a description of the actions taken to resolve the complaint. All corrective actions carried out on site will be documented. The VPMU will include this information in its progress reports to the ADB.

101. Table 10 below sets out the process and durations for resolving any project related grievances.

Table 10: Grievance Redress Process

Stage Process Duration

1 Affected Person (AP) /village elected or traditional chief

takes grievance to VPMU

Any time

2 VPMU reviews and finds solution to the problem in

consultation with village or traditional chief and relevant

agencies

Within two weeks

3 VPMU reports back an outcome to village/traditional

chief/AP

1 week

If unresolved or not satisfied with the outcome at VPMU level

4 AP/village or traditional chief takes grievance to DOE Within 1 month of receipt of

decision in step 3

5 DOE reviews and find a solution 1 month

6 DOE reports back the solution/decision to AP/village or

traditional chief

1 week

11 A complaint may be lodged with the VPMU if the complaint is to be lodged prior to a committee being set-up, which in

this case, the VPMU will be obligated to set up the community level committee to hear the Grievance. The VPMU will set up the Community level committee immediately within 5 days of the complaint submission.

Page 28: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 25

If unresolved or at any stage if AP is not satisfied

AP/village or traditional chief can take the matter to appropriate court As per judicial system

Judicial System: Customary Land Tribunal and Courts

102. If not satisfied with the Project level decision or at any time, the complainant may choose to appeal to the legal or judicial system as per the Vanuatu law. Under the law and current procedures in Vanuatu, the complaints procedure can last up to 30 days. The decision of the tribunal or court is generally final, though may be appealed. Appeals may be made to the court at a higher level in the case that the customary tribunal or local court procedures were faulty in the specific case. The judicial system or the judiciary is the last level where the aggrieved party may raise his complaint.

103. The jurisdictions of courts are as follows:

• Customary land tribunals (Nakamal and Area Land Tribunal) have jurisdictions on the customary land ownership and related matters.

• The Island Court has jurisdiction over causes or matters in which all the parties are residents or within the territorial jurisdiction of the court. It cannot hear and decide civil cases relating to lands, except for appeals over tribunals’ decisions.

• The Magistrate’s Court has jurisdiction to try and decide civil proceedings where the amount or value of property involved is not more than VUV 1 million. It can also hear and decide criminal complaints.

• The Supreme Court has unlimited jurisdiction to hear and decide civil and criminal cases but will not hear customary landownership cases except for appeals over lower courts’ decisions.

• The Court of Appeals - Decisions of the Supreme Court may be appealed to the Court of Appeals except on cases that originate from the Island court.

104. The project’s land-related disputes, if not resolved at community-level, will be resolved by the Customary Land Tribunal. The government has set up a customary land management office including in Malekula, and the VPMU will coordinate with this office for the determination of the land ownership of the BHPP site before the LARP is up dated.

VII. LEGAL AND POLICY FRAMEWORK

106. The policy framework for the Project is based on the ADB’s safeguard requirements on involuntary resettlement as embedded in the Safeguards Policy Statement (SPS) and the laws of Vanuatu. Where differences exist between the local laws and ADB requirements, the resettlement policy will be resolved in favour of the ADB requirements.

A. Vanuatu Laws on Land Acquisition and Resettlement

107. Land acquisition, resettlement and associated land issues are recognised in legal terms in Vanuatu by the Constitution and more than 10 laws (or Acts). This section presents a brief overview of the salient national legal instruments pertaining to land acquisition and resettlement.

1. Constitution of Vanuatu

108. The Constitution of the Republic of Vanuatu came into being on 30 July 1980. The Constitution, “as the supreme Law of Vanuatu”, contains two relevant sections to land acquisition and resettlement.

109. Chapter 5, Articles 29 to 32, of the Constitution refers to the “National Council of Chiefs”. Of relevance is the Article 30 which recognises the National Council of Chiefs membership having the competence to discuss, and may be consulted on, any issue related to customs, culture and its preservation in any matter, as required by the National Government.

Page 29: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 26

110. Although a very short Chapter, considering the traditional ties between Vanuatu nationals and the land, Chapter 12 of the Constitution of the Republic of Vanuatu is devoted to land. Most discussions related to land have centred on Articles 30 (in Chapter 5) and Articles 73, 74, 75 and 76 of Chapter 12. Nine articles from 73 to 81 are relevant to land acquisition and resettlement depending upon the situation. This states that all land is owned by its traditional, customary owners; parliament prescribes the criteria for compensation payment for land; the Government may own and acquire land for State interest and may redistribute land away from traditional owners, in such cases as informal settlements and relocating of residents from other islands; and disputes in land ownership will be resolved through appropriate process.

2. Legal Acts Pertaining to Land Acquisition and Resettlement

111. There are several Acts related to land acquisition and resettlement as follows:

1) The Land Acquisition Act N° 5 of 1992 (Amendment Act N° 34 of 2000) is the key law directly related to land acquisition. This Act gives the Minister for Lands and Natural Resources (MLNR) powers to acquire land on the Government’ behalf for a public purpose. It provides for the compensation for damages made during the process of land valuation, compensation entitlements for land and for rents and business losses (s9), basic rights for grievance and appeals, and notice periods. This Act does recognise market value compensation for land. Section 12 provides a judicial appeal mechanism to the Supreme Court for cases where affected landowners are not satisfied with the compensation.

2) The Land Acquisition (forms) Regulations No 32 of 1994 provides for various forms (specified as Schedules) required under the Land Acquisition Act. There are six such Schedules prescribing the forms for notices issued during the land acquisition process.

3) Land Reform Act 35 (1980 and updated 1981, 1983, 1985, 1992, 2000 & 2013): This Act specifies that all land titles will be customary or transferred to the traditional owners, whose percentage can be traced back locally to 200 years. It outlines specifically about indigenous owners and the non-indigenous land users.

4) Customary Land Management Act No 33 of 2013: This Act details management of customary land including the dispute resolution through Nakamal and Customary Area Land Tribunals (CALT) and process for affected persons to appeal the Nakamal and CALT decisions. Division 2 outlines procedures for determination of custom owners and Part 4 details the process for determination of land disputes by a nakamal.

5) Valuation of Land Act N° 22 (2002) relates to the organisation of the “Valuer General” Office and their role. The Act does not stipulate approach to valuation of the land, structures, etc, which is more directly related to the “Land Acquisition Act”.

6) Land Surveyors Act N° 11 (1984): This is basically a code of conduct, or a term of reference for registered land surveyors, whom must be registered through the Land Surveyors Board.

7) Land Leases Act (1983) and Amendment (2014): The Act details the rights and obligations of person or entities entering into an arrangement or agreement with another person and/or entity for the use of land under a lease or rent agreement. Land can be leased for up to 75 years, administered by the Government on behalf of the customary landowners and registered in the Land Leases Register. Leases for development on customary land require the free, prior and informed consent of the custom owner group.

8) Public Road Act 2013: This Act defined the road reserve as (i) 15 metres either side of the centreline for an arterial road; or (ii) 10 m either side of the centreline for a feeder or an urban road where boundaries are not clearly defined or recorded by DOL (Part 1, s1). Section 6(3) states that the Director General of the Ministry of Infrastructure and Public Utilities (MIPU) may classify a public road according to its function, that is: (a) a public road whose main function is to link nationally important industries to ports and markets or which facilitate regionally based trips are more likely to be classified as arterial

roads; (b) a public road in a Local Government area whose main function is to facilitate local trips

Page 30: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 27

within communities, or to link to local services or markets or link to an arterial road, are more likely to be classified as feeder roads; (c) a public road in a Municipal Council area whose main function is to facilitate local trips within the Municipal Council, or link to local services and markets or link to an arterial road, are more likely to be classified as urban roads.12

9) Once roads are declared and/or gazetted they are assigned a classification level and the Government to be responsible for the upkeep and maintenance. Part 5 also outlines procedures for regulating access, utilities and encroachments on public road reserve that is directly applicable to BHPP.

3. Current Practices in Land Acquisition and Resettlement for Public Purposes in Vanuatu

a. Identification of areas for acquisition

112. In the past GOV policy on land needed for public purposes has been to lease the land or strike an access agreement with land owners, and only use its powers to compulsorily acquire land if the land will be needed indefinitely or greater than 75 years, e.g. for airports, government centres, commercial centres, and major infrastructure13. The majority of Government’s land acquisition in Vanuatu has therefore been for smaller projects such as village health facilities and educational institutions. More recently, apart from Tanna airport, in Port Vila the Government has acquired land along the river at Freswota for river protection and reduce urban encroachment issues. The Sarakata HPP land acquisition and compensation is the most significant experience in the power sector14.

113. In the year prior to an infrastructure development project, each Ministry and other Government agencies develop their work plans for the following fiscal year. This is inclusive of the other feasibility study requirements such as budgeting, environmental, engineering etc. At this time proposals for projects where land acquisition is involved should be submitted. This is subject to the approval of the Council of Ministers. There is no minimum standard that requires the projects to minimise land acquisition and impact on the community.

114. The government is in the process of establishing customary land management offices and land tribunals in each province of the country to assist in settling customary land disputes. Customary lands identification is still an ongoing process since 1980 given that there are limited records to prove that a claimant’s ties to a certain plot(s) of land go back over 200 years as specified in the legislation.

b. The formal process for land acquisition

115. On an annual basis, the Government allocates in its National budget 200 million Vatu for Government Land Acquisition projects. According to MLNR, if the budget is not spent the remaining amount accrues on top of the normal, annual VUV 200 million budget. In the event that the budget is used up, but finances still required, the Government and Ministry executing a project is responsible to find further finances to cover the necessary Land Acquisition budget requirement.

116. Once an area of land is selected by the Government for the public purpose, a notice signed by the Minister of MLNR is provided to the customary owners and “persons interested” and a public notice is erected in full public view. The notice is made for a minimum of 30 days. After investigations, the Minister notifies the owners and the public that the land is suitable for the said purpose and states his/her intention to acquire the land. Anyone wishing to object must do so within 30 days (Schedule 3 notice).

12 Manning & Hughes (2008) note that in relation to the acquisition of land for public purposes “Roads were declared state property at

independence, but since independence little of the land on which other public assets are located has been acquired or had formal lease agreements completed”.

13 Manning, M., & Hughes, P. (2008). Acquiring land for public purposes in Papua New Guinea and Vanuatu. Volume two.,Australian Department of Foreign Affairs And Trade, Canberra.

14 A separate Due Diligence/Social Compliance Audit Report for Sarakata HPP provides a comprehensive documentation of the

process and outcome

Page 31: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 28

117. After this period, the land is assessed and valued to determine the amount of compensation payable. The basis for land valuation is stipulated by the LAA, and involves consideration of the following:

1) Lease type – residential/agricultural/commercial/special industrial.

2) Marketability – number of properties marketed nearby in recent times and price range of those transactions

3) Physical characteristics – terrain, vegetation, soil type, improvements made and land area.

4) Intangibles – interest, customary and other resource rights attached.

118. According to the MLNR, valuations include both land and structures affected and may include the value of income produced from land. However, this does not include “non-land producing” incomes such as income from a shop etc. Valuation of agricultural crops and trees is done by relevant officers of the Ministry of Agriculture. Valuation of the land itself is done by the office of the Valuer General. Any damage to the land, caused by valuation investigations is liable for compensation to the existing owners (Schedule 2). Once the valuation has been made, signed by the Minister, and provided to the landowners (Schedule 5), the owners have 30 days to file objections to the amount. At the same time, the MLNR must disclose information on the valuation and proposed land acquisition over a 30 day period by radio at least 3 times on separate occasions, in one national newspaper each week, on the main notice boards and on the land itself. On the decision by the Minister, an objector may appeal the Minister’s decision through the Supreme Court of Vanuatu. However, if the issues are related to tradition and custom, then the National Council of Chiefs may be consulted if necessary.

c. Carrying out the acquisition of land/structures

119. After a 30 day notice period, and as long as all conflict claims and complaints are resolved, the actual compensation processes can then commence. The Ministry of Lands is responsible for this process, monitored by the Ministry of Finance and Economic Management (MFEM). However, this stage may include complaints about the process of valuation to compensation itself; and process of the assessment of disputes. This is generally supposed to be settled through the Customary Lands Tribunal or if unresolved through the Supreme Court system.

d. Negotiation in land acquisition

120. The Land Acquisition Act 1992 (amendment) and Act No.34 of 2000 stipulates the processes and procedures on negotiation for land acquisition. It involves the following:

• The Government to serve a 30 day notice of its intention to acquire land.

• The Notice would be posted in public conspicuous places near the land to be acquired in three languages (Bislama, English and French) as well as published in newspaper both local and national.

• The notice will include specification that if there are objections to the proposed acquisition such would have to be conveyed to the land officer not less than 30 days from the date on which such notice is given.

• Furthermore, the notice will state that claims for compensation for the acquisition of that land or easement may be made to the acquiring officer.

• In case there are conflicts in terms of land ownership and claim, the issue shall be referred to the local land tribunal for review and resolution. A notice is given to the landowners/claimants to make known their claim to the local land tribunal. At the end of the specified period the land tribunal will proceed to make its decision on who the rightful customary landowners are.

• The Government through the acquiring officer will request the customary landowners to propose compensation taking into consideration market value of land during the time of publication of notice, damage made to the land resulting from the activities undertaken in regard to the land acquisition objective, loss of income as result of the loss of land as well

Page 32: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 29

as displacement or relocation as a result of land acquisition. The acquiring officer through his principals shall likewise prepare his own estimate.

• The Government would compare the requested compensation package of the customary landowners with that of the Government (Valuer General). The estimate to be provided by the Valuer General is the final valuation of the Government; if the custom owners still reject the said valuation their recourse is to appeal to the Supreme Court.

• If a determination on compensation is made and no appeal is made, the decision of the Acquiring Officer is final.

Page 33: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 30

e. Use of Custom Owners Trust Account

121. The Custom Owners Trust Account (COTA) is a trust account being managed by the Director General of the MFEM intended for the purpose of keeping land acquisition compensation payments while customary ownership of the land is in dispute. Funds may be withdrawn from the COTA and paid to the owner of the land that has been determined to be the custom owner under the CLMA 2013. The use of COTA under the project has been agreed with the landowners through a Memorandum of Agreement.

4. The Land Acquisition Process and Notices Used for the Brenwe HPP

122. Under the LAA regulations, Schedule 1 is the first instrument to be served on the landowners and any interested parties to allow government officials to enter any land for the purposes of conducting their preliminary surveys, test, investigation, soil test, engineering survey etc to ascertain the suitability of the land for the particular public purpose project. Schedule 1 was issued on 18 May 2017.

123. Schedule 2 is usually a notice notifying the landowners or interested parties of any damages caused during the 'investigation' phase (notified by the Schedule 1 form) and the award/valuation for these damages. This was issued on 17 July 2017.

124. Schedule 3 notice was issued on 21 August 2017 for the BHPP land acquisition. This announced the Government‘s intention to acquire the specific land in question. When this notice is issued, landowners or interested parties have the opportunity to either 'object' or agree for the government to acquire. In the BHPP case, it is not clear if any of the parties filed any objection or even wrote any letter agreeing to the acquisition. However, the MOU signed by the identified land claimants with the Government appears to have had the same effect as a Schedule 3 notice.

125. Schedule 4 is the declaration that the Minister will acquire the land. At this point the landowners or interested parties are allowed the first opportunity to seek an independent or private valuer to assess the land to be acquired, and to state their claims. The specific values to be assessed are listed under Section 9 of the LAA as outlined above. This notice was issued on 10 February 2018 to the BHPP land claimants. However, from Stantec’s discussions with the claimants, it appears they did not receive advice nor understood that they were required to submit their own valuation of their land. In one case, a land claimant interpreted the notice as an opportunity to state his 'land ownership claim' and responded accordingly. None of the landowners engaged any independent valuer during the period stated under Schedule 4.

126. Schedule 5 is where a valuation or determination of compensation value is issued by the Acquiring Officer. In the BHPP case, the Government’s Statutory Valuation report was issued to the landowner-claimants in July 2018, stating a total valuation of VUV 40 million. Stantec consultations carried out as part of the update of this LARP, revealed that the Government valuation report was not explained in detail to the landowners leading to some confusion on the differences between the Tervaut area and the Wiaru (Lamu and Tepenpel) areas and their valuations. Only one of the land claimants expressed his intention to object to the valuation/compensation offer. The legal representative of Mr Kemuel Harry wrote to the Acquiring Officer raising some 'concerns' regarding the Government’s planned acquisition and the compensation to be paid. Consultations held with Harry’s representative in mid February 2019 indicated that Mr Harry was still waiting for a response from the DoL. However, one Joseph Temakon of DOE confirmed delivery of the Acquiring Officer’s response to Tele Harry the representative of the Harry Family at his office. The response was in the Bislama language. If any counter claims or objections are received in the future, it will be dealt with according to the Project Grievance procedure or an acceptable GoV process.

127. Schedule 6 is the final notice in the process of acquisition. This is where notice is issued of a final determination of the valuation, or value being agreed to by all parties. As of late September 2018, Government had initiated the process of a payment of VUV 40 million into the Custom Owners Trust Account (COTA) despite the confusion and written objection to the valuation by one of the then land claimants. The rightful land owner for the Tervaut land has been determined

Page 34: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 31

by Court in late November 2018. There are some internal issues that still need to be resolved within the Tervaut land owners however this should not impact on the project. Once the registration process for the rightful owner is complete, the landowners will be able to access the compensation funds. The compensation money will continue to be held in COTA until a final decision is made by the courts regarding the rightful owner/s of the Wiaru lands. Government will provide for further negotiation on the amount of compensation once the declared landowner/s has been able to carry out their own valuations if they wish. While not strictly in accordance to the formalised process, this will avoid hefty expenditure on valuations by those land claimants whose ownership claim is eventually rejected by the courts.

B. ADB’s Policy on Involuntary Resettlement

128. The ADB Safeguards Policy Statement (SPS) requires ADB-assisted projects to (i) avoid resettlement impacts wherever possible; ii) minimise impacts by exploring project design alternatives; iii) enhance, or at least restore the livelihoods of all APs in real terms relative to pre-project levels; and iv) improve the standards of living of the affected poor and other vulnerable people. It covers both economic/livelihoods impacts and risks, and physical displacement.

129. The key principles of the ADB safeguards policy on resettlement are as follows:

1) Screen the projects resettlement impacts and risks early.

2) Carry out meaningful consultations with participation of APs, inform all APs of their entitlements and resettlement options paying particular attention to the needs of vulnerable groups.

3) Establish a grievance mechanism.

4) Improve, or at least restore the livelihoods of all APs through (i) Land-based resettlement or cash compensation at replacement value as relevant; (ii) Prompt replacement of assets; iii) Prompt compensation at full replacement cost; and iv) Additional revenues and services through benefit sharing schemes where possible.

5) Provide APs with needed assistance including: i) If there is relocation, secured tenure to relocation and better housing; ii) Transitional support and development assistance; and iii) Civic infrastructure and community services as required.

6) Improve the standards of living of the affected poor and vulnerable groups to at least national minimum standards.

7) Develop procedure in a transparent, consistent and equitable manner if land acquisition is through negotiated settlement.

8) Ensure that APs without titles are eligible for resettlement assistance and compensation for loss of non-land assets.

9) Prepare a Resettlement Plan (RP) elaborating on APs entitlements, income and livelihood restoration strategy.

10) Disclose a RP in an accessible place and a form and languages understandable to the APs and other stakeholders.

11) Conceive and execute resettlement as part of a development project or program.

12) Provide compensation and other entitlements before physical or economic displacement.

13) Monitor and assess resettlement outcomes and their impacts on the standards of living of APs.

C. Policy Differences and Reconciliation

130. A comparison between ADB policies and the laws and practices of land acquisition and resettlement used by the Government of Vanuatu is summarised in Table 10. Any differences between the laws and practices of the Government of Vanuatu and ADB SPS will be resolved in favour of the latter by adopting the gap filling measures.

Page 35: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 32

Table 10 - Comparison of Land Acquisition and Resettlement in Vanuatu and ADBs SPS 2009

SN ADB SPS 2009 Safeguards Comparisons to Vanuatu Law Gap filling measures

1 Avoid resettlement impacts wherever possible.

There is no minimum standard that requires the projects to avoid resettlement impacts.

The Project will ensure that resettlement and land acquisition impacts are avoided, wherever possible.

2 Minimise impacts by exploring project design alternatives.

There is no minimum standard that requires the projects to minimise land acquisition and impact on the community.

The Project will ensure resettlement and land acquisition and impacts are minimised wherever possible by exploring design options, including minimising the amount of land to be compulsorily acquired.

3 Enhance, or at least restore the livelihoods of all APs in real terms relative to pre-project levels.

Compensation is determined based on issues including land type, crops etc and other improvements. However, this does not include “non-land producing” income. It also does not necessarily require the conditions of the APs be the same or better than pre-project situation. However, APs may seek legal remedies to achieve compensation they believe is fair.

The project is not expected to impact any non-land related businesses. If any, they and their employees (if any) will be compensated.

The LARP adopts the objective that APs living standard is restored or improved through fair compensation and development opportunities.

4 Improve the standards of living of the affected people and other vulnerable. It covers both economic and physical displacement.

Laws and practices in Vanuatu do not recognise the standards of living of the poor and vulnerable, in determining compensation for land acquisition and resettlement per-se.

The LARP will include assistance for vulnerable APs to improve living standards. The project aims to supply electricity to APs and rural communities in order to improve their standard of living and wellbeing.

5 Screen the projects resettlement impacts and risks early

Laws and practices in Vanuatu relating to Government Capital Works Projects require that the Project budget considers and includes associated resettlement and land acquisition costs. Other than the social aspects of an EIA that might be required for an Environmental Permit for project construction, there are no assessments of resettlement impacts required prior to budget approval, and capital works commencing.

The VEAP project has screened the risks and potential resettlement impacts and prepared a land acquisition and resettlement plan.

6 Carry out meaningful consultations with participation of APs and inform all APs of their entitlements and resettlement options. Pay particular attention to the needs of vulnerable groups.

The law and current practices require the land acquisition and relocation notices to be disclosed several times over radio, in the printed media over a 1-month period, and on site However, there is no recognition of vulnerable groups nor compulsory consultation with or participation of APs at any part of the process, except in the case of people given opportunity to make claims of ownership or lodge objections.

The LARP includes measures for consultation and participation during project design and during the preparation and update of the LARP. This includes particular attention to vulnerable groups. A Community Liaison Officer will be appointed to facilitate communications between the project and the community.

7 Establish a grievance mechanism.

Vanuatu already has traditional grievance redress system for general village matters. MLNR has set up at Provincial level a Customary Land Tribunal. Mechanisms exist for land claimants and APs to object to aspects of the land acquisition and compensation, and to seek redress through the courts.

The project will use the existing systems as well as establishing a grievance redress system. This will allow AP participation, relatively rapid action and results, and coordinate with existing grievance procedures. The grievance mechanism will be promulgated throughout the affected communities through public meetings/workshops and in newsletters.

Page 36: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 33

SN ADB SPS 2009 Safeguards Comparisons to Vanuatu Law Gap filling measures

8 Improve, or at least restore the livelihoods of all APs through (i) Land-based resettlement or cash compensation at replacement value as relevant; (ii) Prompt replacement of assets; iii) Prompt compensation at full replacement cost; and iv) Additional revenues and services through benefit sharing schemes where possible.

In Vanuatu valuation of land is stipulated by Law and is conducted based on several factors regarding that specific plot of affected land such as lease and ownership type; location of property; amenities; market price of nearby properties; physical land characteristics; and intangible values.

The Law specifically points out times for disclosure prior to valuation, time for objection to valuation and acquisition of lands and assets. However, the law does not provide any clauses for compensation, income restoration and entitlements to be provided to the AP in “prompt” manner.

Land is valued by Valuer General in MLNR. The VG will determine compensation requirements relating to land, land-based income losses by any affected party. Minimally, all compensation will be at replacement cost based on existing market rates.

Compensation will be provided promptly. Where not immediately payable, the compensation moneys will be held in a Custom Owners Trust Account administered by the Ministry of Finance.

9 Provide APs with needed assistance including i) If there is relocation, secured tenure to relocation and better housing; ii) Transitional support and development assistance; and iii) Civic infrastructure and community services as required.

In Vanuatu, land acquisition, resettlement and compensation for land-based losses are included under the law. However, impacts on business and their employees are less clear and there is no recognisable transitional support mechanism under the law.

No relocation will be required for the BHPP. ADB SPS 2009 will be enforced in supplementing the Law of Vanuatu by covering transition assistance, compensation for business and employees (if impacted).

10 Develop procedure in a transparent, consistent and equitable manner if land acquisition is through negotiated settlement.

Vanuatu laws provide procedures on negotiation for land acquisition, lease or purchase.

Vanuatu laws and practices as well as SPS provision on negotiations will be followed by the project.

11 Ensure that APs without titles are eligible for resettlement assistance and compensation for loss of non-land assets.

Laws have no clauses that recognise encroachers in any way to be entitled or NOT entitled to compensation or rehabilitation. Lessees and legitimate non-owning users of custom land are recognised.

ADB SPS 2009 will be enforced to recognise encroachers (if any) who are affected at the time of the census/detailed household survey conducted for the project planning.

12 Prepare an RP elaborating on APs entitlements, income and livelihood restoration strategy.

Under Vanuatu Law, land acquisition and resettlement and compensation is carried out focusing on households affected and the values of the land and structures affected. However, an RP per-se is not necessarily required.

An LARP is prepared and will be updated during the detailed design.

13 Disclose a RP in an accessible place and a form and languages understandable to the APs/DPs and other stakeholders

Although the Law does not require an actual RP to be prepared, its clauses do necessitate notices and official valuations by the MLNR. The law and current practices also require that land acquisition and relocation notices for a specific site be disclosed three times over radio and in the printed media over a 1 month period, as well as displayed on-site. However, only the radio would be useful for the illiterate to become informed of any pending land acquisition and resettlement activity on a specific site.

This practice will be followed in addition to the disclosure of the LARP at local level as well as posting on the ADB website. The DOL and VPMU will conduct explanatory workshops with APs and their communities.

Page 37: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 34

SN ADB SPS 2009 Safeguards Comparisons to Vanuatu Law Gap filling measures

14 Conceive and execute resettlement as part of a development project or programme.

The MLNR has a VAV 200 million budget for land acquisition and resettlement for Capital Works Projects allocated on an annual basis. The year prior to a public good infrastructure development project, Government agencies develop their work plans for the following fiscal year. At this time proposals for projects where land acquisition is involved are submitted. This is subject to the approval of the Council of Ministers.

DOE will ensure that the LARP costs are included in its annual budget and are approved by the government on time. Compensation for vegetation clearance along the road/transmission corridor will be provided by the contractor/power distribution concessionaire in the form of paid employment and any necessary training to the APs.

15 Provide compensation and other entitlements before physical or economic displacement.

Compensation is to be provided after a period of disclosure and a period for objection has finished. However, legislation does not clearly state that compensation will be provided prior to commencement of construction.

ADB SPS 2009 will be enforced to ensure land acquisition, resettlement and / or compensation measures are completed prior to construction commencing. The LARP includes this measure.

16 Monitor and assess resettlement outcomes and their impacts on the standards of living of APs.

There is no specific clause in the law of practice in Vanuatu that requires monitoring and assessment of APs during or after land acquisition and resettlement commences.

ADB SPS 2009 will be enforced to ensure that monitoring is set up for this sub-project. Specialist consultants have been appointed to monitor implementation of the LARP.

D. Principles and Policies for the Project

131. Given the assessment of the Vanuatu laws and practices and the ADB policy differences referred to above, some additional measures have been made on top of the provisions set out under the Vanuatu laws in order to ensure consistency with the ADB’s SPS requirements on land acquisition/resettlement. In preparing and implementing resettlement activities under the project, the following project principles and policies will apply:

1) Involuntary resettlement and loss of land, structures and other assets and incomes shall be avoided and minimised through careful project design.

2) APs will be provided with compensation for their lost assets, incomes and businesses, and provided with rehabilitation measures sufficient to assist them to improve or at least maintain their pre-project living standards, income levels and productive capacity.

3) Lack of legal rights to the assets lost will not preclude affected persons receiving entitlement in form of compensation for non-land assets and/or rehabilitation measures.

4) Affected land and assets shall be replaced or compensated at replacement cost based on their current market values.

5) Preparation of resettlement plans and their implementation shall be carried out with participation and consultation of affected people, the Vanuatu government and its responsible agencies, and the VPMU.

6) Schedule of budget for resettlement planning and implementation will be incorporated into DOE’s budgetary cycle as required. This will require close consultation with VPMU, MFEM, MLNR, DOE and approvals by the Council of Ministers of Vanuatu.

7) Payment of compensation or replacement of affected assets and any resettlement to new locations (if necessary) will be completed prior to civil works implementation. Payment for lands with outstanding land disputes or court cases will be deposited into the COTA according to the government mandated processes and distributed once the dispute is legally resolved.

8) Rehabilitation measures will be put in place before start of civil works, but not necessarily completed, as these may be ongoing activities.

Page 38: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 35

9) Compensation and rehabilitation assistance for socially disadvantaged persons, such as households headed by women, the disabled and elderly, will be carried out with respect for their cultural values and specific needs.

10) APs whose land or assets are temporarily taken or made inaccessible by the works under the project shall be fully compensated for their net loss of income, damaged assets, crops and trees at replacement cost. The contractor shall also ensure that all temporarily acquired or blocked land and structures are returned in their pre-project state or better.

11) If any APs lose only part of their land or other physical assets they will not be left with a proportion that will not be viable to sustain its productive use. Such a minimum size will be identified and agreed with APs, and sufficient replacement land or assets provided for.

12) APs will be systematically informed and consulted about the Project, the rights and options available to them and proposed mitigating measures. This will be aided by the VPMU and a Community Liaison Officer.

13) Adequate budget support will be committed and made available to finalise and implement the LARP. Budgets also include activities such as formal detailed physical surveys and administrative functions associated with compensation and resettlement.

14) Any community facilities and infrastructure damaged shall be restored or repaired as the case may be, in consultation with, but at no cost to, the community.

15) While the Government has the option to pursue compulsory acquisition, negotiated land purchase or lease agreement shall be attempted first in acquiring land for the Project. This will be applied to any additional road required to access the BHPP sites.

VIII. ENTITLEMENTS, ASSISTANCE AND BENEFITS

A. Categorises of APs

132. APs may include: (i) Customary landowners of affected custom lands; (ii) Tenants or users of customary land; (iii) Resource owners of trees/crops and (iv) Persons with customary access rights.

B. Eligibility for Compensation

132. The initial identification of APs and affected land and the ensuing negotiation for land acquisition started during the PPTA. The Department of Energy (DoE) in coordination with Department of Lands, provincial government, and specialist consultants has been consulting with potential APs and carrying out detailed land surveys, inventories of losses, and investigations to collect detailed information about APs, their communities, and their livelihoods. The date of the land valuation survey will be the “cut-off date” for eligibility for compensation. Payment for the land with existing land disputes will be deposited to the COTA as agreed with the land claimants. Following are the procedures summarising eligibility for compensation and other assistance to APs:

1) Landowners and/or users that have documented claims to the affected land, trees, etc. as of the cut-off date will be eligible for compensation and/or rehabilitation assistance as per the project policy.

2) Any person or group that occupies or uses the land identified for the subproject construction after the cut-off date will not be eligible for any compensation and/or assistance.

3) APs with legal rights or claims will receive compensation for land. If any, non-titled APs will receive compensation at market rates for assets attached to land and will receive other assistance as required to maintain or improve their livelihoods.

C. Entitlements

Table 11 summarises the entitlement matrix.

Page 39: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 36

Table 11: Entitlement Matrix

Type of Impact Entitled Persons Entitlements

Loss of land. Land owners. Compensation at replacement cost based on current

market price (based on most recent transactions of

comparable value) will be paid for the land to be

acquired. Values to be calculated according to the

provisions of the LAA.

Loss of use of the

land.

Land users, including

lessees.

Refund of all rental/lease payments paid in advance

from the date of notice of acquisition (if any).

Payment of rent for 1 year for an equivalent area of

land elsewhere equal to the land area forgone; and

compensation for lost crops as below

Impaired access to

adjacent

productive land.

Land users of land

immediately adjacent to

but not on acquired or

leased land.

Payment of cost of re-establishing or repairing access

tracks or driveways to previous or better standard.

Loss of trees,

crops, and food

sources.

All APs owning planted

trees and/or crops on the

acquired or affected land.

Land owners will be entitled to be compensated for

any natural trees on their land and allowed to harvest

them prior to construction commencing.

Owners of planted food trees and crops belonging to

them on the acquired or leased land will be allowed to

harvest their crops, and plant materials before site

clearance.

If the tree and crop owners are not able to harvest,

they will be paid full compensation based on market

prices.

Fruit, nut, and housing material trees will be

compensated at replacement cost or market-

comparable price. The compensation will include the

value of loss of the existing crop and a future crop for

1 year.

Planted timber trees, if any, will be compensated for

at market price for a mature tree of the same species.

Loss of trees,

vegetation, crops,

and structures in

power transmission

and distribution

corridors.

Persons, regardless of

status, owning the

asset/s impinging on the

transmission

corridor/easement.

APs will be entitled to harvest or remove assets

belonging to them prior to corridor/easement clearing.

APs will be compensated for crops and fruit trees at

market value of the asset lost. Other options than

compensation will be acceptable as long as affected

persons will not experience major economic impacts

and APs voluntarily forgo the compensation to be

documented through a MoA and verified by third party

according to ADB requirements.

Owners of structures (e.g. roadside market stall) will

be provided with materials and labour to re-establish

the structure nearby to an equivalent or better

standard.

Impacts on the

assets and

livelihoods of

vulnerable groups.

Vulnerable groups

including include women,

infirmed, and poor

households.

Training and project-generated employment given on

priority basis to the affected households; and

assistance to vulnerable households for income

restoration. Determined on a case by case need.

Page 40: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 37

Type of Impact Entitled Persons Entitlements

Unforeseen or

unintended

impacts on

livelihoods and

assets.

Concerned affected

people.

These will be determined on a case by case basis as

per the principles of this LARP and ADB's SPS.

IX. INCOME RESTORATION AND REHABILITATION

133. While the Project, and in particular the BHPP, is not expected to impact on any land owner or user, major income source, or any residential or business structures, the following assistance will be provided by the IA to APs and vulnerable households in the subproject area: (i) Skills training suitable for project construction; and (ii) Priority employment in project works such as vegetation clearance and maintenance works. There are no female-headed households out of the initial identified APs. However, if continued consultations identify any such affected households, they will be provided priority employment in these activities. The project design will reflect this and the updated LARP will describe its details including special assistance to vulnerable groups.

X. LAND ACQUISITION RESETTLEMENT BUDGET AND FINANCING SOURCE

134. Necessary costs for the project’s land compensation will be financed by the GOV as counterpart funds. The cost of consultants and experts to prepare and monitoring the LARP will be funded under GoV . These will include ,, consultation costs, LARP updates, training and legal costs, and LARP monitoring and an estimate of 1 Million Vatu is in the project budget by the GoV. The costs for such activities for the BHPP subproject will be updated after the detailed design. The GOV will release sufficient budget for implementation of land related activities in an appropriate and timely manner.

135. Compensation for losses to land owners and users, and for other affected assets will be paid at replacement costs based on current comparable market prices as discussed in previous section. The VPMU will inform affected landowners/APs about the policies and procedures regarding payment of compensation. It will also inform the landowners when and how compensation will be paid prior to project implementation.

136. A preliminary cost estimate was made by PPTA Consultant during the feasibility stage based on available data and most recent transactions provided by the Department of Lands on a similar project. The minimum total budget is estimated at USD 400,000 to cover land acquisition and compensation, and minimally to USD100,000 for other necessary items (e.g. surveys, consultations, skills training, etc.). However, specific compensation amounts will be determined during the final LARP update and once the detailed inventory of losses is completed and compensation rates and detailed terms of acquisition are agreed between the government and landowners.

XI. INSTITUTIONAL FRAMEWORK

A. Institutional Arrangements

137. The MFEM will be the executing agency (EA) for overall guidance and DOE will be the Implementing Agency responsible for project implementation. The VPMU will assist the DOE in project implementation, including safeguards compliance. The VPMU will be supported by the international and national Design and Supervision Consultants, Stantec New Zealand. The VPMU together with the Stantec team will provide DOE technical support and coordination during implementation if the Project is eventually financed by ADB. With Stantec and additional consultant support if necessary, the VPMU will also ensure compliance with assurances, including safeguards and preparing and submitting the resettlement plan update, reports, resettlement plan monitoring reports.

Page 41: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 38

138. The MFEM will work also together with the VPMU and the MLNR on the budget approval and disbursement for the LARP implementation.

B. Implementation Arrangements for the LARP

139. Stantec will assist the VPMU to:

1) Update the final LARP, based on the inventory of losses and detailed design of the hydropower infrastructures including transmission line and grid extension.

2) Implement, monitor and prepare monitoring reports to be submitted to ADB confirming compliance with the LARP.

3) Collate all Contractor Final Design details prior to the assessment of inventory of losses by the Department of Agriculture

140. When the updated LARP is finalised through identification of site specific impacts and detailed compensation costs, a document will be signed with APs signifying their satisfaction on the compensation. The VPMU will prepare a pro-forma document to be used for recording the settlement of obligations in land acquisition and compensation.

141. Disbursement of cash from the COTA and other sources to APs will follow the approval of budgets for compensation. The VPMU, assisted by resettlement specialists, will inform the APs of the schedule of fund release. They will also advise the APs to produce relevant legal documents pertaining to their identification for claiming the compensation. It is the main responsibility of VPMU to ensure that all the compensations and entitlements have been paid to and settled with APs prior to the commencement of clearing o f the construction sites. The DOE will arrange with the MFEM, as per the law of Vanuatu, for the compensation to be dispersed directly to APs on presentation of identification. APs will sign a document indicating the receipt of their compensation and entitlements. As noted previously, the compensation monies for any disputed landownership will remain in COTA until the dispute is resolved by the court. A Compensation Completion Report will be submitted by VPMU after the compensation process is completed in its entirety.

C. Resettlement Database

143. All information concerning land acquisition including socio-economic information, inventory of losses, compensation and entitlements, payments will be recorded by the VPMU. These records will form the basis of information for implementation, monitoring and reporting, and will facilitate efficient management and monitoring of compensation distribution.

XII. IMPLEMENTATION SCHEDULE

The following Table 12 is the implementation schedule for updating the LARP and implementation of land acquisition and compensation.

Table 12: Implementation Schedule

N° Activities Progress / date

completed

1

Confirmation of land requirement and

consultation/information disclosure with

landowners/APs

Completed

2 Land survey and valuation Completed

3 Confirmation of landowners by the Customary Lands

Management Office (CLMO)

Completed

Appeal with Supreme Court

for Tervaut land complete.

Wiaru land completed earlier .

4

Submission to Department of Lands (DOL) of land

survey report and to prepare for formal negotiation

with landowners/APs and budget allocation for land

acquisition

Completed

Valuation reported to APs

Page 42: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 39

N° Activities Progress / date

completed

5

Negotiation with landowners/APs: consultation with

affected landowners to negotiate for land

acquisition/purchase.

MOA with each land claimant

to proceed with project until

ownership is determined

(December 2017) MOA for

access roads signed with

landowners on February

2019.

6

Agreement on land acquisition/purchase and approval

by the government on allocation and release of fund

for land compensation payment

Valuation done and given to

land claimants.

1 claimant lodged objection to

valuation.

7

Vanuatu Project Management Unit (VPMU) in

coordination with Department of Energy (DOE) and

DOL updates the LARP including agreements on

compensation rates with landowners and discloses

updated LARP to APs.

September 2017, September

2018, February and May 2019

and is ongoing

8

VPMU submits the updated LARP to ADB for approval

and posting on ADB website

The following activities will be included in the next

update and VPMU will be responsible for its delivery:

a) impacts of the transmission line and grid extension

following detailed design

b) Update on the socio-economic information for the

Wiaru land

c) update on the land acquisition budget and financing

source

d) Inventory of losses for the access road

Last updated May 2019 and

revised on 4 June after ADB

input. Next update after

detailed designs are

completed by contractors

9 Execution of land acquisition and payment of

compensation

Compensation has been

lodged in Customary Owners

Trust Account (COTA)

pending land ownership

determination.

Claimants advised.

10 VPMU submits to ADB a land acquisition and

compensation completion report

Process not yet complete and

in progress

11 VPMU submits safeguard monitoring report

Semi-annual safeguards

report July-December 2018

submitted May 2019

XIII. MONITORING AND REPORTING

144. Based on the LARP, the EA and IA will monitor all activities associated with land acquisition and payment of compensation to APs. The scope of monitoring includes: (i) Compliance with the agreed policies and procedures for land acquisition and compensation; (ii) Timeliness of approval, allocation and disbursements of funds and payment of compensation to APs, including supplemental compensation for additional and/or unforeseen losses; and, (iii) Remedial actions, as required. The monitoring will also cover whether APs are able to and restore, and preferably improve, their pre-project living standards, incomes, and productive capacity.

145. The DOE will maintain proper documentation of the consultation process and keep relevant records of land acquisition and transaction. The VPMU will assist in documentation of the consultation, negotiation and transaction process.

Page 43: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 40

146. The DOE will prepare and submit semi-annual progress reports to ADB as part of project performance monitoring. DoE will also submit a subproject land acquisition and compensation completion report to ADB following compensation payment before start of the civil works.

Page 44: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 41

XIV. APPENDICES

Appendix 1: Copy of Memorandum of Agreement on Project Access

Page 45: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 42

Page 46: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 43

Page 47: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 44

Page 48: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 45

Appendix 2: Consultations

Documentation of Consultations Conducted in Brenwe HPP Malampa Province, March – May 2014 - Provincial and Community Consultation

1. Provincial and community consultations in respect of both environmental and social issues were undertaken in Lakatoro township and Unmet village on 19th March 2014. The project consultation personnel included the Consultant’s international environment specialist (IES) and international and national social/resettlement specialists. Local logistical support was provided by the Malampa Provincial Assistant Planner. Key activities during the consultation visit included:

• Introductory meeting with Malampa Provincial Government.

• Consultation meeting with project affected land owners, interested stakeholders and community members at Unmet.

2. The purpose of the provincial and community consultation was to disseminate basic project information and obtain the views and concerns of communities with respect to environmental issues related to the project with a view to addressing these issues in the project design and implementation. The consultations also provided the opportunity to gather relevant site specific information from the stakeholder’s perspective on the physical biological and social environments of the project area.

3. Malampa Provincial Government (MPG). An initial meeting was held with the MPG to introduce the Safeguards team, explain the purpose of the visit and consultation process within the context of the overall TA objectives including ADB’s safeguards requirements, obtain information relating to the community’s readiness for the project including any issues of concern they might have, and to request the MPGs assistance in supporting the consultation process. Twelve members of the Provincial council attended the meeting.

4. A power point presentation delivered by the IES provided the opportunity to inform the MPG of what the proposed Brenwe hydropower project entailed. The presentation included sketches of the key project components, a summary of potential environmental and social impacts and benefits arising from the project, and a preliminary assessment of the significance of such impacts and likely mitigation measures required to ensure impacts are minimised and acceptable.

5. The MPG were familiar with the key components of the hydropower project through their previous experience with the partially constructed and abandoned Brenwe hydropower project during the 1990s. The provincial council expressed overall support for the project. In respect of environmental issues one member queried the potential impact on downstream water quality in the Brenwe River and loss of water between the intake and powerhouse due to the project. These issues were clarified during discussions with the council. In particular they were advised that significant impacts on water quality downstream of the project were unlikely and any impacts associated with reduction of water between the intake and powerhouse will be investigated as part of the IEE with necessary mitigation measures proposed to ensure impacts are minimised and acceptable.

6. Other issues raised included questions on the proposed alignment of the transmission line; whether or not the transmission line will be routed to Lakatoro; whether or not the project would result in lower cost of electricity; and whether or not the partially completed and abandoned hydropower sites and facilities would be used.

Page 49: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 46

7. Details regarding land acquisition issues discussed with the MPG are addressed in the LARP.

8. Community consultation/information dissemination. An outdoor meeting was held in Unmet Village and involved the participation of approximately one hundred community members including community leaders, affected landowners, school teachers and interested people. A significant proportion of the participants were women and youth.

9. The meeting commenced with introduction of the consultant team by the international social/resettlement specialist and outline of the teams proposed activities during the visit and the overall purpose of the stakeholder consultation process. This was followed by a brief description of the project by the IES and identification of the potential environmental and social impacts and benefits associated with the project.

10. Following the presentation, participants were asked to express any and every concern they might have regarding the project. Most of the queries and discussion centred around the proposed alignment of the transmission line including the need to consult closely with the community regarding the alignment as well as ensuring appropriate compensation to land owners. The community was also keen to ensure that their community would benefit from the electricity generated. The community’s experience of the previous Brenwe hydropower project abandoned during construction in the 1990s due to conflicts over land and the transmission line alignment was foremost in their minds.

11. When specifically asked if anyone had any concerns over environmental issues associated with the project the response was “no”. The community reported that there were no tambu sites in the vicinity of the project area, no-one actually lived within or close to the project footprint and no one relied on the water resources in the stretch of river that would have reduced flows between the weir and the powerhouse.

12. The communities clearly understood the concept of hydropower and were very familiar with what the project involved due to the previous project and they expressed a strong desire for the project to go ahead. Various comments were made regarding the community’s need for electricity to enhance the existing and flourishing economic activity and population growth in the area including school facilities for the growing population. It was mentioned by a retired school teacher that this area of Malekula produces the most kava and cocoa of any region in Vanuatu and that cargo ships periodically anchor offshore of Unmet to load up these commodities.

13. Conduct of FGD/HHSES/KII – In addition to the above consultations, the Team undertook focus group discussions, socio-economic survey of sample households and key informant interviews (KII). Four FGD attended by 10-15 participants per FGD, 80 households within the influence zone of BHPP as well as a number of KII were conducted. Results of these information gathering and consultations have been integrated in the social and environmental reports as well. Consulted groups and persons are included in the list of persons consulted with at the Malampa Provincial Council on 19 March 2014 is provided below.

14. Consultation with Affected Households –and concerned local officials on Land Acquisition Issues and Concerns. In the conduct of various consultation activities land acquisition issues were discussed with local and provincial officials as well as the affected person/households.

15. Concerns raised were as follows:

Page 50: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 47

• Customary landowners/claimant – Primary concerns raised was the compensation and other benefits that APs are entitled to; willing to give up land as the area required is uncultivable and not useful for agriculture but compensation issues/concerns must be addressed and agreed first.

• Other landowners/communities – Concerns on whether the transmission line will pass through the same areas originally traversed by the aborted Chinese project which will result in substantial loss of fertile agricultural land and massive losses of fruit bearing trees like coconut, cocoa and kava; worries that the previous experience with the Chinese project will have detrimental impact on getting the current project approved. Strong support for the project expressed and willingness to give up (for cutting and trimming) some fruit trees along the road where the transmission line is proposed to pass.

• Local Officials – brought up the issues of benefit that the Project will get from the Project considering that the transmission line is planned to connect to the existing Norsup-Lakatoro grid; whether the communities near the Brenwe project will be covered and provided electricity as well.

• Provincial Officials – expressed full support to the project and will work with the national agency in facilitating land acquisition.

List of Attendees at Consultation Meeting with Malampa Provincial Government

Lakatoro, 19 March 2014

Name Responsibility Summary of Comments made

Lapi Kalmet Assistant Planner • MPG familiar with the key components of the hydropower project through their previous experience of Brenwe hydropower project during the 1990s.

• expressed support for the project.

• one member queried the potential impact on downstream water quality in the Brenwe River and loss of water between the intake and powerhouse due to the project. These issues were clarified. MPG were advised that significant impacts on water quality downstream of the project were unlikely and any impacts associated with reduction of water between the intake and powerhouse will be investigated as part of the IEE with necessary mitigation measures proposed to ensure impacts are minimised and acceptable.

• Other issues raised included questions on the proposed alignment of the transmission line; whether or not the transmission line will be routed to Lakatoro; whether or not the project would result in lower cost of electricity; and whether or not the partially completed and abandoned hydropower sites and facilities would be used.

Edna Paolo Tourism Officer

Melteras Salavina Cultural Centre

John Bongnaim Customary Lands

Tribunal

Kevin Enrol Malampa Province

Toufau Kalsakau Forestry Officer

George Tusai Agriculture Officer

Samson M Correctional Services

Noel Nathan Health Department

Renjo Samuel Education Officer

Palen Ata Provincial Planner

Joanna Lingi Women’s Affairs

• List of Attendees of signing of MOA between Province and Landowners/Claimants – See MOA

Page 51: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 48

2016 Consultations Date: 16 February 2016 Time: 10am Venue: Malampa Provincial Government Office, Lakatoro

Attendees:

Lapi Kalmet Assistant Planner, MPG

Antony Garae Off Grid Officer, DOE

Alfred Joel On Grid Officer, DOE

Claire Forbes ADB Consultant

Hannington Alatoa VPMU

Collyne Tete Clerk, Island Court

John Bongnaim Custom Land Officer, CLMO

Edward Korty Chairman, Malmatemvanu

Notes: The team thanked the officials for attending the meeting and explained the project status – i.e. that it is still is the pipeline and ADB is a potential funder for the Project, and that it is high on the Government’s priority list and very important for the people of Malekula. The team explained the value of their role in land and managing custom lands which is important for project’s success. The Island Court representative explained custom lands of Timbun, Tervaut and Wiaru are relevant and Tervaut has a pending Supreme Court case (set for March 2016). The CLMO representative advised that his office was unaware of the Project and requested formal notification from DOE. DOE agreed to send a letter. The Chairman of Malmetemvanu explained the Council’s jurisdiction preceded over the Village Council of Chiefs, Area Council of Chiefs and Island Council of Chiefs. He is the Chair of Island Council of Chiefs and explained that the Area Council of Chiefs are nominated by their own people according to traditional customs and decisions are made by consensus. Date: 16 February 2016 Time: 11am Venue: Public Works Dept, Lakatoro

Attendees: Lapi Kalmet Assistant Planner, MPG Antony Garae Off Grid Officer, DOE Alfred Joel On Grid Officer, DOE Claire Forbes ADB Consultant Hannington Alatoa VPMU Mr Fred Siba Division Manager, PWD

Notes: The team met with the PWD Division Manager in Lakatoro to discuss current road projects and definition of road reserves. It was unclear whether the roads where the transmission line will run have been gazetted since the Road Act is still new (2014) and there has been recent change of government. Mr Siba comments that the road carriageway is typically 4-6 m wide in Malekula and for the transmission line to Vao

Page 52: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 49

the community agreed to 3 m from the edge of the road to be cleared. He also agreed that establishing a Brenwe Steering Committee would be a good idea. Date: 17 February 2016 Time: 9am - noon Venue: Malampa Provincial Government Office, Lakatoro

Attendees: Lapi Kalmet Assistant Planner, MPG Antony Garae Off Grid Officer, DOE Alfred Joel On Grid Officer, DOE Claire Forbes ADB Consultant Hannington Alatoa VPMU Multiple persons Chiefs and land claimants

Notes: The meeting was opened with a prayer by Remo Reuben. The team explained their roles and the purpose of the visit to update the MOA on Land Access that was signed in 2014. The DOE representative thanks everyone for their attendance and explained the project is still in the pipeline and there are numerous steps to complete before construction could start on such a project. He explained the stages in project development, stating that feasibility had been completed in 2014/15. The team also highlighted the importance of understanding custom lands surrounding the old hydro site and the need for transparency between all parties. Meeting attendees asked how long the process will take to complete, and the team responded explaining there is commitment to start the project but it will depend on cooperation with landowners and communities. Josaia Nato stated he was in full support of the project. One person asked whether the project could change its name since the site is not actually located at Brenwe (Brenwe village is downstream). Comments were raised about communication and consultation and how people would be informed. The team raised the idea of a steering committee, explained how this first needs approval from Director General (DG), and that DOE will look at how to improve communications and information sharing in Malekula. The custom lands of the project area were discussed amongst landowners, land claimants and their Chiefs. It was identified that the project site was located on Tervaut and Wiaru custom lands and the access road passed through Timbun land. The team presented the updated MOA and read it aloud in English, then in Bislama and confirmed all meeting attendees understood the purpose of the MOA for Land Access. The MPG representative explained the need for signatures and proper representation to allow studies to continue to inform final design. The meeting attendees signed the MOA and the team explained a final copy would be distributed to them via MPG. The team visited the Brenwe site that afternoon and collected additional signatures from those that did not attend the meeting (including Paramount Chief Virabaut in Unmet for Timbun land, Kalman Hapsai, Chief of Brenwe village and Chairman of Area Council of Chiefs; and Achille Nakar, Chief of Wiaru).

Page 53: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 50

Consultations conducted in 2018 Date: 3rd – 10th September 2018 Venue: Brenwe and Tautu village, Malekula Proposed extension grid route from Turtle Bay to Port Olry, Santo

Gerard Fitzgerald Stantec social specialist

Phillipe de Greslan Stantec national consultant

Levi Tarosa Stantec national land specialist

Lapi Kalmet provincial government officer, local logistics

Joseph Temakon DoE, Grid officer

Christy Haruel VPMU – newly appointed

Walter Jonah Local guide for site visit and land claimant

Notes

1. All but one of the land claimants were successfully located and consulted with.

These included:

a. Daniel and Josiah Nato Kemuel Harry and Chief Michael Otak, and

Walter Jonah– being the three claimant groups for the 18 ha of land on

the left (east) side of the Brenwe River ;

b. Chief Nurapath at Wiaru, and Achille Nakar (son and representative of

Nicolas, the aging Chief at Unmet) – being 2 of the 3 land claimants to the

12ha on the right side of the river.

c. John Mathew, the third claimant on the right side of the river was absent

in Port Vila, and was to be located and interviewed following the team’s

return to Port Vila.

2. No additional land claimants have been identified by the Department of Lands for

the compulsory acquisition area of 30 ha versus 4.4 ha and this was confirmed by

the existing claimants.

3. All the claimant groups, or at least their representatives, were given copies of the

government’s land and assets valuation in December 2017. One official objection

to the valuation was reportedly received from Kemuel Harry. He felt that the

valuation for the 18ha on left side was too low compared with the valuation for the

12ha on the right side of the river.

4. Most of the remaining claimants reported they were satisfied with the valuation,

though they did not fully understand the process. No formal hearing over the

valuation has been conducted. There is potential for a dispute to develop over the

valuation.

5. None of the claimants were willing to withdraw their land claim cases to the

Supreme Court in favour of using processes provided for in the Custom Land

Management Act. However, at the same time all the claimants indicated that they

would accept the Supreme Court’s ruling on the ownership and would not

subsequently enter into any form of dispute. This relates to the memorandum of

agreement signed by the land claimants.

6. There appears to be a current conflict between Mr Harry’s group of claimants and

Mr Nato’s group. Chief Michael had referred to the use of namele leaves (the

‘Chief’s palm’) which is used to invoke a prohibition/tabu – implying a threat to

close down the land acquisition and the project.

Page 54: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 51

Update: Following the decision by the Supreme Court in November 2018 in

favour of Tamat Family, Kemuel Harry, attempted to settle this conflict using

customary dispute resolution by chiefs from Brenwe and Tautu. This was

reportedly unsuccessful as Mr. Nato repeatedly refused to attend several

meetings called to resolve the conflict. Subsequently, Mr Harry’s group as part of

the declared custom land owners of Tervuat land have made it known that any

interference in the Project by Mr Nato’s group or anyone in the future will be

regarded as Trespassing.

Update: When Mr. Josaia Nato was quizzed on his non-appearance he

responded that Mr. Harry Kemuel was a spokesman and he, as the rightful

representative had no obligation to respond to a spokesperson according to

Melanesian tradition. This was succinctly summarised by DG Lands Mr. Arthur

Faerua to Ninebeth Cardang of ADB in an email update of March 2019 that the

Courts had awarded the Tamat Family as Customary Landowners and the

dispute is a family affair to be resolved by the families.

7. On the issue of Stantec’s proposed site access roads: the land required for these

is owned by the current land claimants. All the claimant representatives said they

would be willing to enter into a lease to provide easements for the access roads

on land outside the acquisition area. Update is that all the Land Claimants by six

have signed the MoA inclusive of the TPV granting consent for the development

of Access Roads from the public road to the project site

8. The easement on the left side of the river passes through a coconut and cocoa

plantation (and possibly yam gardens) which belongs to land users. Once

defined, the easements will need to be surveyed and a valuation prepared for the

compensation for agricultural assets on that land to the land users as well as

decision made on a rental. The leasing process could begin immediately as soon

as the alignment of the access road is determined. The process has been clearly

spelt out in the MoA.

9. Over the past few years, a considerable number of people from various agencies

and companies have visited and consulted the communities and landowners

within the area in regards to a hydro project. So it is expected that with the project

tender process going out soon, the number of potential visitors will continue to

increase. Therefore it is essential that a Community Liaison Officer be appointed

to coordinate and manage all visits and communications to the area. The process

of appointing the CLO is currently being undertaken.

10. There is need for an improved awareness of the project and the land acquisition

process to the local communities and the land claimants. Printed materials

describing the project and its rationale, including the planning process need to be

prepared and distributed to the communities and land claimants as soon as

possible.

11. Stantec’s local consultant (Levi Tarosa) followed up on some research on the

acquisition process by the Department of lands and will compare this with the

requirements of existing laws for the update of the RP.

12. The Secretary-General of Malampa province and the head of the VPMU both

advised that the land acquisition and planning process needs to be explained to

the Council of Chiefs for Malekula and later to chiefs of communities concerned.

It is recommended that this process be initiated immediately, facilitated by the

VPMU and Stantec’s local specialist, and involving senior people in the

Page 55: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 52

Department of Lands. Due to other commitments, Mr Levi Tarosa is now no

longer working under this project.

13. The Stantec team, with Christy Haruel made a preliminary inspection of the route

for the proposed HV power grid extension from Turtle Bay to Port Olry on Santo.

Establishment of the line appears achievable with a very low impact on peoples’

livelihoods assets. Eight roadside stalls were counted, all of which could be easily

avoided by the poles and lines, or relocated a few meters. Individual trees will

need to be removed or cut back.

14. VUI the company responsible for providing electricity in Santo has in place a

community engagement program. This has seen the involvement of communities

in cutting down trees or tree branches during powerline works, and payment

made to the communities concerned. Members of communities are also recruited

as casual labourers to assist line crews erect poles etc. This method was also

observed to be used by Unelco on Malekula.

Date: 15th December 2018 Time: AM Venue: Brenwei Participants:

Joseph Temakon Department of Energy

Arthur Faeura Department of Lands

Christy Haruel VPMU

Walter Jonah Unmet Village (guide)

Lapi Kalmet (support) Malampa Provincial Headquarters

Notes 1. Lapi Kalmet met the team briefly at the airport and provided an update on the

court determination, made on 28th November 2018, on the Tervaut land appeal case, in favour of the Tamat Family.

2. The purpose of the trip was to identify Affected Parties (APs) along the proposed

access roads to be used by the project and to discuss and sign MOA for the access roads with these APs. Opportunity was also taken to disseminate awareness information to the communities.

3. Six(6) land users were identified for the access road connecting the provincial road to the boundary of the 30 ha land acquired for the project. This is also the old Chinese road(OCR) located on the west bank. Two (2) land users were identified for the access road on the east bank , to the forebay. The landowner for the east bank or Tervaut, who was recently determined by court, resides in Tautu Village. He was not consulted at that time. Affected Land Users:

West Bank Access Road East bank Access Road

John Mathew Tito Niptik

Abram Willion Ringmal (5698803)

Doume Alick

Gilda

Joshua Mathew (5495243)

Page 56: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 53

Alick

4. The main types of vegetation observed along these proposed access roads are secondary forest, coconut and cocoa plantations, gardens with crops such as yams, island cabbage, peanuts, beans, bananas, corn, kumala and taro. A cattle farm is also located along the route. A full assessment and valuation of crops will be conducted by Ministry of Agriculture, for compensation.

5. Since the MOA for the access roads was still in draft and had not yet received approval from ADB at the time of the visit, the draft MOA was used for discussion with the land users. Although a few of them signed the draft MOA, it was decided later that these signed draft MOAs will be compared with the approved MOA and where needed, the signing would be re-organised and completed in the presence of a Third Party Validator (TPV).

6. Tume Alick signed the draft MOA. He has 2 sons and 5 grandchildren. His wife is a teacher. Tume enquired whether it was possible to provide access road in exchange for free electricity. The team responded that this may not be possible and cannot be guaranteed.

7. Discussion held with Joshua Mathew on his plantation:14.36pm 15/12/2018 . The OCR previously used in the 1990s traversed through Mathew’s farm. Mathew started his cattle farm in 2012. Mathew supports the project and agrees to shifting his fenceline to make room for the access road. Mathew has a security concern however in that if an access road were to be built through his farm, it would expose this investment to the public and the likelihood of thieves entering and stealing cattle. It was suggested that during project construction, access could be controlled at the gate turning into the access road. Mathew signed the draft MOA.

8. Willion Ringmal resides at Unmet village. His garden along the access roads consists of various root crops and several Natangura trees Possible compensation of removed trees and crops with same or better quality and more seedlings of the same kind. Ringmal asked if compensation could be in monetary terms rather than seedlings. Ringmal signed the draft MOA after the content was explained to him.

9. About 100 flyers containing information about the Project, were distributed to the communities at Brenwei,

10. A third party validator (TPV) is required. It was suggested that a pastor or priest from the community church be used as the TPV to be present during all signing of MOA. Date: 6 February 2019 Time: 2pm Venue: Rambay & Associates Office, Port Vila

Attendees Position

Tele Harry Representative of Tervaut Customary Land Owners

Tony Ata Social Safeguards consultant

Christy Haruel VPMU Social Safeguards Specialist

Page 57: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 54

Notes: Tele Harry said he appreciated the opportunity to finally sit and talk to someone in regards to the VEAP after the land appeal case concerning the Tervaut Land was declared in favour of his elder brother Kemuel Harry as spokesperson for the Customary Land owners. He said immediately after the declaration by the Supreme Court, chiefs of Brenwe called a meeting of reconciliation between Harry’s Group and Josiah Nato’s group who are close relatives. Mr Nato’s group did not show up and after a couple more unsuccessful attempts, the chiefs decided not to pursue this further. This action by Nato family was seen by the chiefs and Harry family as pure non-submission, refusal to cooperate and ignoring of the ordained process for resolving conflicts set by the chiefs. On whether this response from Nato’s group can be seen as a threat to the progress of the project, Harry confirmed that Harry’s family who are the declared Customary Land owners have reached a decision that as from that time onwards, any attempt by anyone including Josiah Nato and his family to disrupt proceedings of the Hydropower Project on the Tervaut Land will be regarded as trespassing. Tele also said that Harry’s group had previously refused to sign any document while waiting for a decision from the Supreme Court. However, that has now changed and after the declaration by the Court, the family feels confident to speak out. He said it is right timing for the Project to proceed and any minor issues within the family will be solved between them at family or village level while any agreement between them and the Government will be honoured. Harry emphasized that he had previously mentioned to Levi Tarosa, former Stantec consultant, that government cannot acquire land unfairly due to landowners not given opportunity to conduct their own valuation of the acquired land. Harry raised concern that the process has to be respected because it is transparent and will result in all parties concerned having the same understanding and will avoid unnecessary delays to the project. He said he has written to Lands Department about this but has not received a response. He also requested a copy of the map showing the acquired land for his information so that he can also keep members of the family up dated of proceedings. Date: 16 February 2019 Time: 10am Venue: Rambay Consulting Services, Port Vila

Attendees Position

Tele Harry Representative of Tervaut Customary Land Owners

Tony Ata Social Safeguards Consultant

Christy Haruel VPMU Social Safeguards Specialist

Notes: Tony enquired about a statement made in an earlier consultation regarding compensation for previous Hydro-power project in the Tervaut land and whether there were any issues regarding demand for compensation to be made prior to giving access for the VEAP. Tele said the family had been discussing about this especially for the Tervaut Land however he confirmed he is speaking on behalf of the family and that Harry family has agreed not to raise this issue in this project as it may prolong proceedings and pose risks to the project stopping.

Page 58: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 55

Tony informed Tele about the compensation for damages to crops that will assessed by Department of Agriculture and then processed through Department of Finance and paid to owners of the crops but not to the landowners. Tele said he is aware of this and will inform those concerned. He said the Harry family is concerned if the guide Walter Jonah is still being used as he was also part of the claimants of Tervaut land and this could cause confusion and misunderstanding so they request someone from the Project area that can be trusted as a guide as well as having good background knowledge of the area. He also reiterated that he is still pursuing independent valuation of the Tervaut Land as per processes in place however this should not stop the project progressing forward as this will be an issue between landowners and the government. Tony asked him if required whether he can provide something in writing to confirm this and he said he is ready to do so. On the question whether he had any comments on the MOA signed, he said Harry family will honour any relevant agreements signed with Government as long as it is for the interest of all parties concerned. Tele also said Harry family will work closely with whoever is declared the Customary Land Owner of Wiaru Land which is still yet to be determined by the Court.

COMMUNITY CONSULTATIONS AND AWARENESS INCLUDING CONSENT FOR

ACCESS ROAD REPORT on 25 to 28 February 2019 1. Consultation Team

Name Position Organisation Dates

Arthur Faerua Safeguards Specialist (DG MLNR)

Ministry of Land 28 February

Johnson Waibaiat

Director - VPMU VPMU 28 February

Fatiaki Gibson

VEAP – Project Advisor

VPMU 26 to 28 February

Joseph Temakon

Principal Scientific Officer – On Grid

Department of Energy (DOE)

26 to 28 February

Steven Tahi DSC National Social Safeguards Specialist

Noreve Consultancy as part of the DSC Stantec NZ

26 to 28 February

Benjamin Nehemiah

Planning Officer Malampa Provincial Office

26 to 28 February

Lapt Kalmet Project Officer Malampa Provincial Office

26 to 28 February

Page 59: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 56

2. Areas Covered in the Consultation Meeting

Date

Location

Approximate Numbers

People/Areas that attended the Meeting

26-02-2019

Unmet Secondary School

Registered – 80 with 20 people outside

Unmet, Brenwe, Uri, Wiaru, Lasunwei, Tuluwe, Caroline Boieu, Tuagi, Mahe

27-02-2019

Leviamp 1 – Woman’s Hall

Registered - 32 Leviamp 1 & 2, Vint, Nabour

27-02-2019

Lambubu Cocoa Plantation

Spoke informally to 3 from Management as workers were dispersed due to the bad weather

Management office team with local foreman

27-02-2019

Kona Point SDA Church

Registered - 32 Kona Point Settlement and nearby areas

28-02-2019

Tautu Primary School

Registered - 7 Nato Family

28-02-2019

Harry Family Homestead

Registered - 11 Harry Family

28-02-2019

Tautu Village Community Hall

Registered -16 Tautu community

3. Summary of Activities

1. Prior to the visit for the Community Consultations and Awareness program, Notices as per appended in Annex 1, were prepared by the Malampa Provincial Office and was posted in various strategic locations around all the communities for the members to be alerted to the program ahead and not go to their farms or gardens or fishing for example.

2. The Communities were made aware of the Brenwe Hydro Project and the Transmission and Distribution Network that will connect the hydro power station to the diesel power station at Lakatoro by Joseph Temakon of the Department of Energy (DOE). They were explained the extent of the distribution power network and the coverage areas including the need to clear the vegetation alongside the roads

3. They were all given information booklets as per appended in Annex 2 which was translated to Bislama and French from English and that will be a good point of reference for every household. Additional copies were given out so that the men could take it home for their spouses and children as women cannot attend meetings in a closed area with men as per cultural norms. There was generally a good turn out to the consultations as the communities were looking forward to being updated on the progress of this development.

Page 60: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 57

4. In the Unmet meeting the students of Year 10 were involved in the meeting and had access to the information booklets.

5. Meeting attendees were encouraged and given the opportunities to raise concerns or questions for clarity and these were responded to and were recorded fully at all the venues and samples of this is are appended in Annex 3. Most of the dialogue was in Bislama but the community members understood English so there was two sets of recordings by Lapi Kalmet and Fatiaki Gibson

6. The general awareness meeting was conducted first and then the specific meeting for the Access Road Consent and signing of MoA and TPV form (ADB Approved Format) followed, as done in Unmet School meeting on 26 February 2019. These are appended in Annex 4.

7. In the Tautu example, of 28 February, consultation was done first and then the discussions entered the access roads and its need within the two families, concluding with the landowners signing off on the MoA and the third party verifier signed off. These are appended in Annex 5

8. In all, the various communities were looking forward to this project and the direct and indirect benefits that will ensue from its development. They collectively voiced their support for the development and could not wait any longer to see its construction commence.

9. They were all updated on the steps going forward and probable timeline when tender bids will close and the tender evaluation, concluding in an award for the Works.

10. They were assured that once a contractor was engaged, they will be informed and the probable time for mobilisation to start so that all the plantations in the access road corridors can be cleared after assessment by the Department of Agriculture

Page 61: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 58

Annex 1.

Page 62: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 59

Annex 2. ..\LAND ACQUISITION PROCESS\Fatiaki Desk Top Docs\Community Liaison Handouts - Bislama Version Rev 1 21-2-19.pdf Annex 3. Consultations Record Unmet 26 Feb 2019.pdf Annex 4. ..\LAND ACQUISITION PROCESS\Road Access MoA & TPV\Consultation Record for Wiaru and Tervaut LO Users for Access Roads .pdf Annex 5. ..\LAND ACQUISITION PROCESS\Road Access MoA & TPV\Signed MoA with Harry Family.pdf

Day 4

Thursday 28th Feb

Public awareness on VEAP and Consultation with land owners and users for the access roads on West Bank and East Bank

Tautu Village 2.00pm DOE/VPMU/DG Lands

Thank yu tumas long Cooperation blong yumi everiwan mo Malampa Provincial Government Council I stap luk forward blong lukim yumi eveiwan long taem blong Awareness/Consultation. Sign MPGC

Page 63: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 60

Appendix 3 - Communications, Consultation and Participation Plan for Brenwe Hydropower Project

Introduction

This Communication, Consultation and Participation Plan (CCPP) has been developed for the

Brenwe Hydro Power Project (BHPP). The Department of Energy (DOE) within the Ministry of

Climate Change (MoCC) is being supported by the Vanuatu Project Management Unit (VPMU)

to implement this subproject under the Vanuatu Energy Access Project (VEAP). This plan has

been developed in accordance with ADB’s Public Communication Policy. This plan is a working

document being implemented from Q1 2016.

Purpose

The purpose of this plan is to guide effective project-related consultation and engagement

activities with stakeholders at all levels throughout the project cycle. It will also help to involve

affected people in project design and implementation, and increase involvement of civil

society, including a beneficiary-driven approach to facilitate long-term development goals.

Objectives

The objectives of the plan are to:

• Maximise the benefits brought about by the project.

• Disseminate important project information and progress to communities and

stakeholders in a timely manner to minimise misinformation, unnecessary disputes

and disturbances.

• Facilitate participation of communities and stakeholders in relevant project activities

and developments, and be responsive to stakeholder feedback, concerns and input.

• Establish a two-way communication channel that enables participation and feedback

at all levels.

• Build awareness of project activities (and timeframes) and community acceptance of

the project.

• Provide clear, adequate and timely notification to affected parties, communities and

property owners during construction phase.

• Establish a grievance redress mechanism for managing and responding to complaints

• Ensure transparency and accountability.

Approach and Key Principles

DOE is committed to a meaningful consultation process that:

(i) Begins early in project preparation stage and is carried out on an ongoing basis

throughout the project cycle.

(ii) Provides timely disclosure of sufficient information that is understandable and readily

accessible to all stakeholders (in local languages etc).

(iii) Is undertaken without intimidation or coercion and gives adequate time for decision-

making.

(iv) Is gender inclusive and tailored to the needs of disadvantaged and vulnerable groups;

(v) Incorporates the views of stakeholders into decision-making.

(vi) Is documented to keep track of who has been consulted and the key issues raised.

(vii) Is responsive and reports back in a timely way to those consulted, with clarification of

next steps.

Page 64: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 61

These principles lay the foundation for a ‘code of conduct’ when carrying out consultation

activities. Consultation activities will aim to secure 40% participation by women so as to

ensure their full comprehension of, and participation in, the project implementation stages.

The consultation process involves four key stages:

(i) Awareness-raising with broader community.

(ii) Identification of affected persons, households, villages and properties.

(iii) Targeted consultation sessions with affected villages and persons.

(iv) Formal notification of works commencement.

Project Area

BHPP is located in North-West Malekula, approximately five kilometres north of the village of

Unmet, one of the largest settlements outside the urban areas in Vanuatu. Project

infrastructure will be established on the Brenwe River upstream of the village areas, and a

transmission line will run along the access road, to the main road toward the provincial

business centre of Lakatoro.

Figure 1 : Project Location in Malekula (area outlined in red indicates Brenwe Hydro location.

Area outline in yellow indicates project area of influence.

Page 65: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 62

Table 1. Key Stakeholders

Level Primary Key Persons Methods

Na

tio

na

l Ministry of Infrastructure and

Public Utilities (MIPU)

Public Works Department Meeting with DOE as

needed

UNELCO Managing Director Regular communication

with DOE

Dept of Water Director General Meeting with DOE as

needed

VPMU (within Prime Minister’s

Office)

Project Manager, Safeguards

Specialists

Regular communication

with DOE

Dept of Lands (DOL) Director General, Valuer

General, Surveyor General

Meeting with DOE as

needed

Customary Land Management

Office (CLMO)

Deputy Director Meeting with DOE as

needed

Design and Supervision

Consultant (DSC)

Project Manager/Team

Leader

Regular meetings with

DoE (and MPG if

required), consultation

with affected persons and

communities

Pro

vin

cia

l

Malampa Provincial Government

(MPG)

Secretary General, Provincial

Planner

Regular communication

with DOE,

Chairperson of Brenwe

Steering Committee

Public Works Department (PWD) Division Manager Attends Brenwe Steering

Committee meetings

Malampa Province Technical

Advisory Committee (MPTAC)

Chairman, Secretary Representative

participates in Brenwe

Steering Committee

meetings

Customary Land Management

Office (CLMO)

Custom Land Officer Attends Brenwe Steering

Committee meetings

Island Council of Chiefs

(Malmetanvanu)

Chairman Attends Brenwe Steering

Committee meetings

Council of Women President Attends Brenwe Steering

Committee meetings

Agriculture Provincial Officer Attends Brenwe Steering

Committee meetings

Industry and Trade Provincial Officer Attends Brenwe Steering

Committee meetings

Training and Vocational

Education (TVE)

TVE Centre (construction

jobs)

Noticeboards

UNELCO Manager/Engineer

(Lakatoro)

Regular communication

with DOE and MPG

Health, Education, Tourism, Non-

Government Organisations

Provincial Representatives When needed

Su

b-

dis

tric

t/A

rea

Contractor for construction Site Manager Reports to DOE, meetings

with communities and

affected persons as

required

Page 66: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 63

Level Primary Key Persons Methods

North-West Area Council Chairman Via Brenwe Steering

Committee

Meeting with MPG

North-West Council of Chiefs Chairman Via Brenwe Steering

Committee

Central Council of Chiefs Chairman Via Brenwe Steering

Committee

Central Area Council Chairman Via Brenwe Steering

Committee

Meeting with MPG

Loca

l

Directly affected persons

(customary landowners of Wiaru,

Tervaut lands)

Landowners Community meetings

Project Brochures

Noticeboards

Formal letters

Residents along access road and

transmission line (including

Tervaut lands)

Landowners and residents Community meetings

Project Brochures

Noticeboards

Formal letters

Beneficiary communities and

Villages in the greater Unmet

area (Uri, Unmet, Brenwe,

Leviamp, Lambubu Unvar, Wiaru)

Paramount Chiefs in North-

West Malekula

Community meetings

Project Brochures

Noticeboards

Village Councils Chairman Via Brenwe Steering

Committee

Women’s Association(s) Representatives from North-

West and Central Area

Council of Women

Community meetings

Via Council of Women

Phase One: Feasibility and Planning (2013-2015)

During the feasibility stage of the project, ADB staff and consultants carried out consultation

sessions with stakeholders through targeted and public meetings, site visits, key informant

interviews, focus groups and household surveys.

Phase Two: Design Phase (Community Preparation) [2016-2018]

During the design phase, a project steering committee will be established supported by the

DOE, Malampa Provincial Government (MPG) and VPMU. Consultation sessions will become

more frequent in the lead-up to construction phase.

Key Activities

(i) Establishment of institutional mechanism responsible for community

development/participation activities.

(ii) Orientation workshop, focus group discussions and information dissemination activities

including the communication and disclosure to affected people and other stakeholders

of impacts and proposed mitigation measures.

(iii) Setting up mechanism (e.g. Brenwe Steering Committee) for networking, liaison and

coordination with partners and associated agencies.

(iv) Establishment of grievance redress procedures at local, provincial to national levels.

(v) Conduct of consultations and disclosure activities.

Phase Three: Implementation Phase (Construction/Community Mobilisation) [2019-2021]

Page 67: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 64

The structures that were set up for communication during the design phase will be utilized to

provide adequate notification of works and upcoming activities.

The designated VPMU staff and safeguard specialists of the Design and Supervision Consultant

will take the lead in coordinating and organizing the conduct of these activities with support

and advise from MPG. This will also involve coordinating the participatory assessment/survey,

data collection etc., related to land acquisition and watershed management and ensuring the

conduct of information dissemination and full project disclosure regarding project impacts

and mitigating measures. Additionally, consultation activities will result in increased

awareness on the importance of electricity taking gender aspects into consideration.

Discussion will also highlight the community’s responsibilities particularly women in the

project and activities that will mainstream awareness of gender concerns and issues.

Key Activities

(i) Mobilisation of community groups/members especially women’s groups.

(ii) Conduct of consultations.

(iii) Orientation of various groups on gender issues and sensitivity to provide push to efforts

in improving women’s chances to socioeconomic benefit and improved quality of life.

(iv) Conduct of orientation/training and creation of demand for skills improvement to

improve chances of success in engaging in income generating activities.

Phase Four: Commissioning and Handover Period (2021-22)

This Phase involves the preparation for the transfer of responsibilities in order to

institutionalise the mechanism for consultation and participation. VPMU and potentially the

power utilities will be the main agencies eventually responsible for carrying out participatory

programs and activities related to the Project. The specialists and key persons trained during

the Detailed Design Phase and initial stage of subproject implementation including the

Operation and Maintenance (O&M) personnel for the system will now be able to carry out

the project activities on their own.

Key Activities

(i) Coordination and linkages.

(ii) Institutionalisation.

(iii) Conduct of regular project related activities.

(iv) Decide on the future role of Brenwe Steering Committee (if any).

Methods and Activities

The methods of consultation are outlined in Table 2 below. They include:

• Public Forums and Information Sessions (design and construction phase).

• Community Awareness-Raising.

• Targeted Negotiation with Landowners and Tenants.

• Targeted Consultation with Landowners, property owners and communities along the

transmission line.

• Formal disclosure activities of project documentation.

• Steering Committee meetings.

Responsibilities

Table 2 outlines the roles and responsibilities for key government agencies and important

stakeholders in project communications and consultation.

Page 68: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 65

Table 2 Roles and Responsibilities

Agency Responsible Person Responsibility

Department of Energy Director Overall oversight of the project and reporting

progresses and issues to Government through

the Director General and the Hon. Minister of

Climate Change.

Department of Energy On-grid Officer &

Communication Officer

Directly responsible for day-to-day liaison and

collaboration between all the parties involved

in the project, regular meetings with VPMU,

conducting awareness, preparing consultation

materials (e.g. newsletter), facilitating duty

exemptions and coordinating the meetings of

the Brenwe Steering Committee.

VPMU Safeguard Officer Compliance with funding agreements and ADB

safeguard procedures and updating the Office

of the Prime Minister; updating safeguard

documentation; developing consultation

materials; focal point for land issues,

facilitating and coordinating with Dept of

Lands on land acquisition/leasing in

compliance with ADB Safeguards.

Malampa Provincial

Government (MPG)

Secretary General and

Planner

Key Government focal point for

communications and information

dissemination to the landowners, property

owners, communities, chiefs and women

groups within the project areas. Responsible

for hosting the Brenwe Steering Committee

meetings and facilitating meetings with parties

directly and indirectly affected by the project.

Department of Lands

(DoL)

Director General, Valuer

General, Surveyor General

Will be responsible to call meetings with

regard to the project land, the right of ways

and land easements. They will also survey and

evaluate the land to be occupied by the

project and to take lead in facilitating

compensations.

Public Works

Department

Division Manager based in

Lakatoro

Will take the lead in upgrading the main roads

towards the project site.

State Law Office Attorney General To review all agreements and give legal

opinions prior to execution and also to assist

Lands Department in land issues.

Agriculture

Department

Officer based in Lakatoro To assess value of cash crops, fruit trees,

coconut trees, cocoa trees and trees for

timbers.

Environment

Department

Director (Port Vila) To assist the project development by

facilitating relevant environmental

assessments.

Brenwe Steering

Committee

Chairman (Secretary General

of MPG)

Will be the backbone of the project to ensure

that the project is implemented according to

the design and timeframe, solve issues

Page 69: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 66

Agency Responsible Person Responsibility

affecting the project, document all issues

arising out of the project, provide regular

reporting to VPMU and is the body responsible

for putting out public information about the

project.

Customary Land

Management Office

Officer based in Lakatoro To progress the identification of the true

landowners of the project occupied areas and

finalize their customary rights. Also assist

Lands Department to issue land titles on the

project lands.

North-west Area

Council of Chiefs

Chairman To be the liaising body with the Brenwe

Steering Committee, to facilitate awareness

activities and support the implementation of

the project.

UNELCO Managing Director Will be collaborating with the DoE and the

Consultant/Contract for inter-connecting the

project into the UNELCO.

Tervaut Affected

Landowners; Wiaru

Affected Landowners

Nominated representative

and identified landowner(s)

Directly liaising with the Customary Land

Management Office and the Lands

Department to identify the true landowners of

the project occupied lands.

Other Affected

Landowners

Nominated representative

and identified landowner(s)

As above, as required.

Landowners, Property

Owners and

Communities along

transmission line

route

Chiefs, head of households,

Nominated spokesperson

To participate in the awareness activities and

facilitate clearing of access routes.

Consultant/Contractor Project Manager/Team

Leader

Be the main project implementing agency and

collaborating with the Brenwe Steering

Committee in the development of the project.

Provide fortnightly progress reporting to the

Brenwe Steering Committee, the VPMU and

the DOE.

Grievance Redress and Complaints Management (As per LARP above)

The grievance mechanism presented here outlines a process for documenting and addressing

project-related grievances (complaints) that may be raised by affected persons or community

members regarding specific project activities, environmental and social performance, the

engagement process, and/or unanticipated social and environmental impacts resulting from

project activities. It describes the scope and procedural steps and specifies roles and

responsibilities of the parties involved. The procedures are subject to revision based on

experience and feedback from stakeholders.

The DOE will communicate the procedures in an understandable manner to affected

stakeholder groups through consultation activities (e.g. toksave). Confidentiality will be

respected and DoE will take all reasonable steps to protect parties from retaliation.

Page 70: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 67

Communities and affected persons should be advised of the procedures in the early stages of

engagement, and be made aware of:

• How they can access the grievance mechanism (i.e. key people and complaint forms);

• Who to speak to and lodge a formal complaint;

• The timeframes for each stage of the process;

• The process being confidential, responsive and transparent; and

• Alternative avenues where conflicts of interest exist.

The procedures will utilise formal, informal and traditional grievance procedures suitable to

the local context and the issue at hand. All complaints will be directed to chairperson of the

BSC who will notify VPMU. Depending on the nature of the complaint, the complaint will be

directed to either community level to be dealt with at the nakamal, or it can be directed to

the BSC or DOE to discuss and advise on way forward. Generally, complaints and disputes will

be resolved at the community level as much as possible through the nakamal process.

Grievances may be firstly referred to customary conflict mediation arrangements according

to custom where appropriate, so long as they are not directly affiliated with traditional leaders

who are party. If the issue cannot be resolved at this level, it will be raised to the next level

and so on.

Grievance Register

The DoE, through the BSC, shall set up and maintain a Register of Grievances which shall

include:

• Time and date of complaint;

• Type of communication (face to face, telephone, written, etc);

• Person(s) to whom the complaint is directed;

• Name, address and contact details of complainant;

• Details of complaint;

• Action planned and taken to settle the matter;

• Confirmation that resolution has been reached to the satisfaction of all parties.

The Grievance Register shall be available at all times for inspection by the VPMU and ADB

throughout the project.

Reporting

Each consultation session will be recorded with a list of attendees. A template is provided in

Appendix 4. Updates on community consultation will be provided in progress reports of the

consultants and VPMU.

Page 71: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 68

Table 3 Consultation Activities Summary

Activity Target

Stakehol

ders

Method Objectives Budget

Source

Completi

on Date

Project

Orientation

Governme

nt officials,

officers,

and

VPMU

staff (Port

Vila)

• Meeting with powerpoint

• Introduce the Project

• Demonstrate the link between watershed protection and improved water resource supply for hydro and reliability of power supply

• Discuss roles and accountabilities of various government units

• Discuss issues related to use of land acquisition, temporary resettlement, and environmental clearances and permits

• Mitigate potential problems

• Discuss gender issues and concerns and how to optimize women participation

• Gather recommendations

DoE

and

Project

Consul

tants,

Port

Vila

VPMU Complete

d

Project

Orientation

Provinci

al Govt,

UNELC

O,

Brenwe

Steerin

g

Commit

tee

(Maleku

la)

• Meeting • Project description and scope

• Key responsibilities

• Timeframe

• Current demand load and forecasts

DoE,

VPMU

Complete

d

Public

Information

Session

Commu

nities

in/near

the

project

area;

service

users

Public

forum

(nakam

al and

Lakator

o

market

)

Energy

Forum

• Introduce the Project, highlighting its importance and benefits to the community

• Demonstrate the link between watershed protection and project continuity

• Gather concerns and views related to electricity

• Gather recommendations

DoE,

VPMU,

Brenw

e

Steerin

g

Commi

ttee

VPMU Complete

d

Targeted

consultation

Affecte

d

Person

s:

Landow

ners,

local

officials

(nakam

al,

Lakator

o)

• Nakamal

• Meeting

• Discuss potential Project impacts (temporary and permanent)

• Solicit the views of affected persons on avoidance/mitigation strategies

• Agree on mitigating measures

• Agree on impacts that may require compensation or assistance

VPMU,

Brenw

e

Steeri

ng

Com

mittee

VPMU Complete

d

Formal

notification

and

negotiation

Landow

ners

and

land

• Letter

• Poster notification (DoL)

• Discuss project footprint and potential impacts to custom lands

• Correctly identify landowners

• Agree on compensation measures

DoE,

DoL,

CLMO

VPMU

MoCC Complete

d

Page 72: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 69

on land

(hydro site)

claiman

t,

CLMO,

DoL

rep.

Dept

Agricult

ure

• Meetings

• Site visit

Formal

notification

(transmissio

n line)

Landow

ners,

land

claiman

ts,

resourc

e

owners,

Dept

Agricult

ure

• Letter

• Meetings

• Site visit

• Discuss project footprint and potential impacts to trees, crops

• Correctly identify resource owners

• Agree on compensation measures

DoE,

VPMU

, Dept

Agricu

lture

MoCC Complete

d

Document

disclosure

(LARP/IEE/

EMP)

Commu

nities

in/near

the

project

area

Affecte

d

persons

and

househ

olds

• Report Summary in Bislama

• Report available in Lakatoro MPG Office

• Brief meeting (as needed basis)

• Disclose details of the LARP and EMP particularly with regards to various mitigating measures

VPMU,

MPG

VPMU,

Civil work

contracto

r

Another

round

when

Civil

Contracto

r is

appointed

Gender

activities

Council

of

Women

represe

ntatives

,

Brenwe

Steerin

g

Commit

tee

• Gender training

• Awareness of gender concerns/issues

• Gender action plan implementation

• Skills development for women groups

VPMU,

MPG

VPMU TBA

Consultatio

n on

opportunitie

s for

business/in

dustry

Business

sector;

Brenwe

Steering

Committe

e; TVET

• Focus Group Discussion

• Energy Forum

• Introduce the Project

• Demonstrate the link between improved electricity supply and income generating activities, women’s empowerment, and improved access to social services

• Mitigate potential resistance to the project

• Gather recommendations

VPMU

in

cooper

ation

with

busine

ss

group

organi

zation

VPMU Another

round to

TBA

Brenwe

Steering

Committee

Meetings

Brenwe

Steering

Committe

• Monthly meetings

• Project progress updates

• Carry out actions from meetings

• Liaise and disseminate information to project stakeholders

MPG DoE Another

round

before

Page 73: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 70

Appendix 1. Brenwe Community Liaison Committee

Appendix 2. Work Plan

Appendix 3. Information Sheet and Flowchart

Appendix 4. Meeting Minutes Template

e

members

constructi

on starts

Vanuatu

Project

Manageme

nt Unit

VPMU,

DoE

• Meetings Bi-monthly meetings

• Review compliance with social safeguards, environment, and gender frameworks and plans

• Discuss progress in implementation, including problems encountered and means to mitigate/address them

• Regularly report on the progress of implementation

VPMU,

DoE,

ADB

VPMU,

DoE

Work in

Progress

with new

resources

in VPMU

Page 74: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 71

Appendix 1

Brenwe Steering Committee

Terms of Reference

Introduction

The National Energy Roadmap (2013-2020) forecasts up to 65% of electricity generated in

Vanuatu from renewable sources by 2020, and result in achieving supply-side efficiency

targets, increase reliability of supply, and improve affordability of electricity, particularly in

rural areas. The Brenwe Hydropower Project (BHPP) in Malekula was identified as a key

renewable energy project that will generate 400kW using a run-of-river design connecting to

the main grid in Lakatoro.

Community participation is an important milestone for the ownership and sustainability of

infrastructure development. Combined with political and departmental leadership,

infrastructure assets cannot be built without involving the community members in each step

of the planning and implementation process. The affected community must be consulted

informed and involved. This CLC TOR helps promote ownership and participation among

communities affected by the Project by including community representatives in regular,

formal interactions with PWD and the Contractor. Its existence and operation is a

compulsory requirement and the selected Contractor must adhere to it.

The Brenwe Steering Committee (BSC) is being established by the Department of Energy (DoE)

in partnership with the Malampa Provincial Government (MPG). Since the Brenwe

Hydropower Project (BHPP) is a significant project for Malekula and DoE has no formal

presence at the provincial level, all parties have agreed that setting up a Steering Committee

would be an important step and allow for regular communications regarding the project’s

progress. The BSC also forms a fundamental part of the Brenwe Communication, Consultation

and Participation Strategy.

Objective

The Brenwe Steering Committee is established to ensure a two-way communication process

between key stakeholders and fair participation in decision making by all stakeholders at all

levels, throughout the life of the project.

Functions

The Brenwe SteeringLiaison Committee will support the active participation and proactive

consultation of stakeholders for the Brenwe Hydropower Project in North-West Malekula. The

BSC will function in coordination with the Department of Energy in Port Vila, regarding the

planning, management and implementation of project activities. The Committee will:

i) Hold monthly meetings to provide project updates to key stakeholders at the Area

Council and village levels

ii) Build awareness and manage stakeholder expectations about social and economic

changes brought about by the project

iii) Provide notification to custom landowners of the project schedule and when access

shall be required (particularly in the construction phase)

Page 75: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 72

iv) Host forums and meetings with stakeholders on Malekula as the need arises, and in

coordination with Department of Energy (Port Vila)

v) Regularly communicate with Department of Energy (Port Vila) and provide feedback

to the DoE as required

vi) Facilitate and encourage dialogue between key stakeholders and identify

opportunities for participation in the project

vii) Address and maintain a register of any concerns or grievances arising in the project

area or among stakeholders in consultation with Department of Energy (Port Vila) as

required

viii) Promote the inclusion of women and other community members, as able, in the

Project’s available employment opportunities as well as provide enabling

environment for the participation of women in the project implementation and

management at community level

ix) Facilitate and promote awareness initiatives such as on Gender and HIV/AIDS issues,

labour and employment opportunities

Membership

Members of the BSC will comprise two-tiers – core members and associate members made of

stakeholders in Lakatoro and Unmet.

Core members (compulsory attendance) Associate members (on as needs basis)

Malampa Provincial Government Agriculture

Public Works Department Business, Industry and Trade

Department of Lands Agriculture

Customary Land Management Office TVET Centre (construction jobs)

Council of Women Health

NW Area Councillor /Area Secretary UNELCO

Central Area Councillor/Area Secretary Environment

Village Council of Chiefs Primary and Secondary School

Department of Energy

Consultant/Contractor

Membership Eligibility

Requirements:

• All core members shall serve on the Committee for a period of three years

• Members shall be recommended and approved by the Department of Energy and/or the

Provincial Government based on suitability for the role and fair representation.

• Core members shall reside in the Province and be present to attend all meetings.

• The member shall be an active participant in the community.

Structure and Responsibility

Chairperson (SG of MPG): The Chairperson shall:

Page 76: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 73

(a) Call meetings in consultation with the Contrator, chair the meetings and facilitate

discussion based on meeting agenda and action items; follow up with members on

action items.

(b) Delegate responsibility to another member if the Chairperson will be absent for

longer than normal periods. This delegation should be authorized by a meeting of

the CLC

(c) Report to the Contractor and Engineer on matters of urgency affecting the

community or the Contractor’s work

(d) Ensure that all committee members are functioning at all times for activities

delegated to them

Secretary: The Secretary shall:

(a) Facilitate meeting dates, times and venues in consultation with Chairperson,

(b) Confirm availability of committee members to attend scheduled meetings and

prepare meeting agenda;

(c) Ensure all proceeds of the meetings are recorded, typed and distributed to all key

stakeholders (DoE, Malampa Provincial Technical Advisory Committee etc).

Committee Members: All members of the BSC shall:

(a) attend scheduled meetings at the request of Chairmen and Secretary;

(b) reach mutual agreement on specific issues

(c) Carry out actions as requested by the Chairman and documented in meeting minutes.

(d) Inform their respective groups and communities on any information or changes as

approved by the committee meetings

(e) Take leading role in community activities

Charter

The BCLC is the main representative body for the Project in Malampa Province. The Charter is

as follows:

(i) Meetings shall be held monthly on the third week of the month; An extraordinary

meeting may be called by the Chairperson if required

(ii) The Committee shall be in regular contact with the DoE and Technical Advisory

Committee (TAC) regarding project updates and information that needs to be

disseminated to key stakeholders in Malekula;

(iii) The Committee will record minutes of all meetings and send copies to DoE and the

TAC (including list of actions to be reported on each meeting);

(iv) The Committee will make a note of any complaints or grievances related to the Project

and inform DoE (and respond where appropriate);

(v) The Committee shall disseminate project information and respond to queries and

concerns in a timely manner;

(vi) The Committee will facilitate and host (where necessary) public information sessions

on the Project with community members;

(vii) The Committee will action any meetings with key stakeholders in the Province as

required by DoE;

Page 77: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 74

(viii) Ensure stakeholders have proper understanding of project information, milestones

and key dates (in local languages as required);

(ix) Encourage the participation of women in all meetings and public information sessions;

(x) The Committee will advise DoE (and relevant parties) of stakeholder views and seek

opportunities to maximize benefits of the Project.

(xi) In the absence of the Chairperson, the vice-chairperson shall preside over a

meeting

Page 78: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 75

Appendix 2

Work Plan

1) Work Plan for Consultation Activities

Resp. Activity Timeframe

YEAR ONE: J F M A M J J A S O N D

DoE Meeting with VPMU X

VPMU Nominate consultation

lead

X

VPMU Secure budget for

consultation activities

X

VPMU,

DoE

Brief internal team on key

dates and activities

(Project Orientation)

X X

VPMU,

DoE

Develop engagement

materials

X

DoE Project Orientation for

MPG and UNELCO

(Malekula)

X

MPG Brenwe Steering

Committee Meetings

x x x x x

DoE,

MPG

Public Information Session X X

VPMU,

DoE

Public awareness

campaign and media

broadcasts

X X

DoE Targeted consultation X X

DoE Formal notification and

negotiation on land (hydro

site)

X

DoE Formal notification

(transmission line)

X

VPMU Document disclosure (

LARP/IEE/EMP)

X

VPMU Gender activities X

MPG Consultation on

opportunities for

business/industry

X

Page 79: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Version March 2016

Appendix 3

Information Sheet and Flowchart

Information Sheet

The National Energy Roadmap (2013-2020) was developed by the Government of Vanuatu

(GoV). It identified that there is potential for 65% of electricity generated in Vanuatu to come

from renewable sources by 2020. This will reduce reliance on unsustainable and expensive

fossil fuels such as diesel, particularly in rural areas.

The Asian Development Bank (ADB) is supporting the Government of Vanuatu (GoV) through

the Department of Energy (DOE) to develop reliable and sustainable supply of electricity in

Malekula to assist economic growth and increase the capacity to support greater access to

electricity for local residents, businesses and industry.

The project will increase capacity to meet growing electricity demand for the next twenty-five

or so years. The electricity generated from this plant is essential for improving the affordability

of electricity on Malekula15. Once the project is established it is expected to displace most of

the diesel generation in the concession area.

The proposed Brenwe Hydropower Project (BHPP) is located in northwest Malekula Island,

Malampa Province approximately 20 km WNW of Lakatoro, the provincial administrative

centre. The Project will harness the natural flow of the Brenwe River to generate hydro-

electric power. The layout follows the footprint of the partially constructed Brenwe

hydropower project which was abandoned in the mid-90s.

The intake of the run-of-river scheme is located at 160 m above sea level about 5 km north-

west of Unmet village and comprises a low weir. Access to the site from Lakatoro is via the

northwest Malekula Road which crosses the Brenwe River about 400 m upstream of the intake

site. The existing access road from the public road to the intake, powerhouse and forebay

sites will be used for this project and rehabilitated. An approximately 23 km long 20 kV

transmission line will be constructed from the powerhouse to Lakatoro where it will connect

to the existing grid.

How does Run-of-River work?

Small hydro is referred to as ‘run-of-river’. This technology is capable of yielding lower costs

per kWh than other sources, such as polluting diesel generators. The design utilizes the energy

in flowing water to generate electricity. Running water is diverted from a river and guided

down a narrow penstock (channel) to a generating house. The force of the flowing water spins

a turbine which drives a generator. No water is stored in this process and the water is fed back

into the main river downstream. In drought and periods of low rainfall the system is unlikely

to work since there is not enough flow of water. In periods of high rainfall the system will

produce more electricity.

15 The levelized cost of electricity generated from the hydro plant is estimated to be 29.5VUV/kWh, which is

below the levelized cost of diesel-generated electricity of VUV33.3

Page 80: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 77

Page 81: 49450-008: Energy Access Project - Asian Development Bank · Government and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed

Page | 78

Appendix 4. Meeting Minutes Template

Date Time Venue

Purpose of Meeting

Attendees

Apologies (absentees)

Chairperson

Agenda/Discussion Topics

• .

• .

• .

Issues Raised

Issue Raised by

Outcomes

Action/Resolution By Who