68
Environmental Monitoring Report Project Number: 45030-002 February 2018 PRC: Yunnan Sustainable Road Maintenance (Sector) Project Prepared by the Yunnan Highway Administration Bureau for the People’s Republic of China and the Asian Development Bank This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. Asian Development Bank

45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

Environmental Monitoring Report

Project Number: 45030-002 February 2018

PRC: Yunnan Sustainable Road Maintenance

(Sector) Project

Prepared by the Yunnan Highway Administration Bureau for the People’s Republic of China and

the Asian Development Bank

This environmental monitoring report is a document of the borrower. The views expressed herein

do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may

be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Asian Development Bank

Page 2: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

PRC-3074: Yunnan Sustainable Road Maintenance

(Sector) Project

The Environmental Monitoring Report

in the Second Half of 2017

For Phase III-Road Maintenance Subproject

Prepared in February 2018

Prepared by the Yunnan Highway Administration Bureau for the Asian Development Bank

Page 3: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

i

Table of Contents

TABLE OF CONTENTS I

EXECUTIVE SUMMARY V

I. BACKGROUND AND PROJECT PROGRESS 1

II. REPORT PREPARATION 5

A. Purposes and Objectives 5

B. Policy, Legal, and Administrative Framework 5

C. Report Period 6

D. Scope of Environment Monitoring 6

III IMPLEMENTATION OF EMP 7

A. Detailed design drawings and bidding documents 7

B. Institutional Arrangements 7

C. Construction Supervisors 7

D. Implementation status of the mitigation measures 8

E. Analysis of Environmental Monitoring Results 11

F. Institutional Capacity Building and Training 18

IV. PUBLIC CONSULTATION, INFORMATION DISCLOSURE AND GRIEVANCE

REDRESS MECHANISM 19

A. Public Consultation, Information Disclosure 19

B. Grievance Redress Mechanism (GRM) 25

V. CONCLUSIONS AND SUGGESTIONS 27

Appendices

APPENDIX 1: SUMMARY OF POTENTIAL ENVIRONMENTAL IMPACTS AND THE

MITIGATION MEASURES IMPLEMENTED 28

APPENDIX 2 ESSU’S QUARTERLY COMPLIANCE CHECKLIST FOR PHASE II, III AND

IV SUBPROJECT ROADS (REPORTING PERIOD: Q3 AND Q4 2017, ABSTRACT)

40

APPENDIX 3: SITE PHOTOS 51

Page 4: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

List of Figures, Tables and Pictures

Figure 1 Organizational Chart for Supervision of Environmental Protection, Water and Soil

Conservation 8

Figure 2 Procudures of Project GRM 26

Table-1 Road Sections for Maintenance during the Phase III of the Project and Project

Progress 3

Table- 2 Environmental Quality Standards for Surface Water(GB3838-2002) 11

Table- 3 Water Quality Monitoring Results of Phase III Subproject 12

Table- 4 Ambient Air Quality Standard (GB3095-2012) 12

Table- 5 Air Quality Monitoring Results of Phase Phase III Subproject 13

Table- 6 Environmental quality standard for noise (GB3096-2008) 15

Table- 7 Emission standard of environment noise for boundary of construction site

(GB12523-2011) 15

Table- 8 Major Noise Source 15

Table- 9 Noise Monitoring Results of the Environmental Sensitive Receptors Along Phase III

Subproject 16

Table- 10 List of Persons Consulted With 19

Page 5: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

CURRENCY EQUIVALENTS

(As of 31 December 2017)

Currency unit – Yuan (CNY) CNY1.00 = $ 0.1542

$1.00 = CNY 6.4832

ABBREVIATIONS

ADB – Asian Development Bank ADB SPS – Asian Development Bank Safeguard Policy Statement 2009 CEWP – Construction Environmental Work Plan CIEE – Consolidated Initial Environmental Examination(i.e. many

subprojects addressed in one IEE) dBA – A measure of audible (the ear) noise EARF – Environmental Assessment and Review Framework EIA – Environmental Impact Assessment EMP – Environmental Management Plan ESSU – Environment, Social and Safety Unit (established within

YHAB) GRM – Grievance Redress Mechanism IEE – Initial Environmental Examination masl – metres above sea level PMO – Project Management Office PRC – People’s Republic of China RP – Resettlement Plan RoW – Right of Way SDAP – Social Development Action Plan subIDFor

m – Sub-identification form, provided in the project’s Operations

Manual summarizing all features for a subproject vpd – Vehicles per day YEPD – Yunnan Environmental Protection Department YHAB – Yunnan Highway Administration Bureau YPDOT – Yunnan Provincial Department of Transportation YSRI – Yunnan Science and Technology Research Institute of

Highways

WEIGHTS AND MEASURES

CO – Carbon monoxide kph – Kilometers per hour mu – Land measurement unit = 666.6m2 NO2 – Nitrate or Nitrogen Dioxide SO2 – Sulphur dioxide

NOTE

In this report, "$" refers to US dollars.

Page 6: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

Monitoring Indicators

Water Quality

SS – Suspended substance CODcr – Chemical oxygen demand pH – pH value DO – Dissolved oxygen

Air Quality

PM10 – Inhalable particulate matter (particle size less than 10 microns, harmful to the lungs)

NO2 – Nitrogen dioxide SO2 – Sulfur dioxide

Acoustic Quality

LAeq – equivalent continuous sound level A

This environmental monitoring report is a document of the borrower. The views expressed

herein do not necessarily represent those of Asian Development Bank Board of Directors,

Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms

of use” section of this website.

In preparing any country program or strategy, financing any project, or by making any

designation of or reference to a particular territory or geographic area in this document, the

Asian Development Bank does not intend to make any judgments as to the legal or other status

of any territory or area.

Page 7: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

Executive Summary

1. The Yunnan Sustainable Road Maintenance (Sector) Project (the Project) is located

in Yunnan Province in the People’s Republic of China. The Yunnan Department of Transport (YPDOT) is the executing agency and the Yunnan Highway Administration Bureau (YHAB) the implementing agency. The latter manages non-tolled national highways, provincial roads and important county roads in the province. Condition of the network has been deteriorating resulting in a reduced level of service and safety, increased transport costs and environmental degradation.

2. The Project includes four outputs: maintenance of 866.8 km of national, provincial and county roads (Output 1); pilot of performance-based maintenance contracts (Output 2); development of a road asset management system (Output 3); and institutional development to enhance the performance and sustainability of YHAB road maintenance (Output 4). Maintenance activities will be implemented over five years in four Phases. The Project with loan amount of $80 million was approved by ADB on 9 December 2013. The Loan and Project Agreements were signed on 30 May 2014. The loan became effective on 7 August 2014.

3. Currently, only phase III subproject is in implementation. ⚫ Phase I contracts were signed in middle of 2014 and the subproject has been

completed except 2 performance based contracts in maintenance stages; ⚫ Phase II subproject contracts were signed in Dec 2015 and officially started civil

works in Jan 2016; and the subproject was completed and put into operation in first half of 2017;

⚫ Phase III subproject contracts were signed and officially started civil works in Jan~Apr 2017; and the subproject is still in implementation; and

⚫ The Phase IV subproject is under preparation.

4. Phase I , II and III Safeguards compliance. YHAB and the environmental

monitoring reports (EMRs, included in the project quarterly progress reports through

2014~2017) confirmed that none of the Phase I,II and III – road sections involved

resettlement, environmental or indigenous people impacts and therefore Phase I remains category B while Phases II, III, IV remain category C consistent with the project design. This EMR is mainly to report EMP implementation status of Phase III subproject which was the only subproject under implementation during this reporting period.

5. Phase III subproject is classified as environment Category C since it is likely to have

minimal or no adverse environmental impacts. According to the project IEE and EARF (Environmental Assessment and Review Framework), the ESSU is responsible for environmental monitoring. A summary monitoring checklist was prepared (Appendix 2) and used to verify the implementation of each mitigative and monitoring measure defined in the EMP. In addition, during this monitoring period, field onsite sampling and laboratory testing was undertaken by Yunnan Science and Technology Research Institute of Highways (YSRI), the subordinate of the YHAB, albeit not a third party or nationally accredited environmental testing agency (neither mandatory for Category C project monitoring nor required in the EMP). YSRI designated environmental specialists and professional sampling and testing equipment & instruments for this assignment to provide quantitative construction site environmental status information to some extent.

Page 8: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

6. The monitoring results indicate that the IAs of phase III subproject, the constructors and construction supervision companies performed their respective duties in accordance with the EMP. During implementation, environmental mitigation measures were carried out to reduce the impacts of construction on the surrounding environment and people’s health to the minimum as possible. They had minimized the pollution and improved local public transport.

Page 9: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

vii

Map 1- Project Roads (phase II) -G213, S313 and Two Sections of G320

G213 E’shan~Xinping,72km

S313 Yimeng to Yimeng,57km

G320Dali(Yangbi~Yongping),91km

G320Baoshan (Yaoqiao~Baoshan) 83km

Page 10: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

8

Map 2 Project Roads (phase III)

Note: subproject road alignments (292km, 11 sections in total).

Source: YSRI.

Myanmar

Vietnam

Laos

G214

S303

G213

G320

G324

S202

S202

S207

G323

Guangxi

Yunnan

Yunnan

Page 11: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

Note: subproject road alignments (125.23km, 6 road sections in five prefectures).

Source: Based on Phase IV Subprojects Screening Result – First Stage Submission, June 2017,YHAB

and YSRI.

Map 3 Project Roads (phase IV)

S235 (K0 + 000 ~ K18 + 000) In Baoshan

S325(K88+035~~K118+035) In Lincang

G324 (K2502 + 830 - K2513 + 658) in Kunming

G248(K582+127—K600+127) in Qujing

S240(K73 + 000 ~ K83 + 400) in Qujing

S242(K0+000 ~K38+000) in Wenshan

Page 12: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

1

I. Background and Project Progress

1. The Yunnan Sustainable Road Maintenance Project (the Project) is located in Yunnan Province in the People’s Republic of China. The Yunnan Department of Transport (YPDOT) is the executing agency and the Yunnan Highway Administration Bureau (YHAB) the implementing agency. The latter manages non-tolled national highways, provincial roads and important county roads in the province. Condition of the network has been deteriorating resulting in a reduced level of service and safety, increased transport costs and environmental degradation.

2. The outcome of the Project will be more sustainable management of the local road network in Yunnan. The project aims to: (i) improve the condition of the YHAB road network; (ii) increase the proportion of the YHAB road network receiving maintenance; (iii) strengthen YHAB’s capacity and operational performance; and, (iv)fill the gap between estimated maintenance needs and available resources.

3. The Project includes four outputs: maintenance of 850 km of national, provincial and county roads (Output 1); pilot of performance-based maintenance contracts (Output 2); development of a road asset management system (Output 3); and institutional development to enhance the performance and sustainability of YHAB road maintenance (Output 4). Maintenance activities will be implemented over five years in four Phases. The Project with loan amount of $80 million was approved by ADB on 9 December 2013. The Loan and Project Agreements were signed on 30 May 2014. The loan became effective on 7 August 2014.

4. The Phase I subproject is classified as environment Category B since there will be limited, generally site-specific impacts that are largely reversible and that can be readily addressed through mitigation measures. An Initial Environmental Examination (IEE) and Environmental Management Plan (EMP) had been prepared for Phase I maintenance works, in accordance with ADB Safeguard Policy Statement 2009. Phase I covers 10 road sections, associated with nine subprojects in six prefectures, of a total length of 276 km. Phase I contracts were signed in middle of 2014 and the subproject has been completed except 2 performance based contracts in maintenance stages.

5. Phase II , III and IV subprojects are classified as environment Category C since it

is likely to have minimal or no adverse environmental impacts. The works are confined to maintenance activities within existing RoWs. Much of the work is minor, such as replacement of guard rails, painting of road markings, and repair of potholes. Most roads have sections of pavement replaced and their horizontal alignments raised to reduce flooding. All construction earthwork materials used, including aggregate, quarry rock, concrete, and asphalt are purchased from existing licensed operations located as close as possible to the work areas. No new facilities or access roads are necessary.

6. During Phase II, maintenance is proposed for 4 road sections in 3 prefectures in Yunnan province. The proposed work will be confined to maintenance activities within existing RoWs. Much of the work will be minor, such as replacement of guard rails, painting of road markings, and repair of potholes. Most roads will

Page 13: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

2

have sections of pavement replaced and their horizontal alignments raised to reduce flooding. All construction earthwork materials used, including aggregate, quarry rock, concrete, and asphalt will be purchased from existing licensed operations located as close as possible to the work areas. No new facilities or access roads will be necessary. Phase II subprojects contracts were signed in Dec 2015 and officially started civil works in Jan 2016; and the subproject was completed and put into operation in first half of 2017.

7. During Phase III, maintenance is proposed for 11 road sections in 5 prefectures in Yunnan province. The proposed works will be confined to maintenance activities within existing RoWs. Much of the work will be minor, such as replacement of guard rails, painting of road markings, and repair of potholes. Most roads will have sections of pavement (asphalt concrete) replaced and their horizontal alignments raised to reduce flooding. All construction earthworks materials used, including aggregate, quarry rock, concrete, and asphalt will be purchased from existing licensed operations located as close as possible to the work areas. No new facilities or access roads will be necessary. The implementation of all Phase III subproject contracts were signed and officially started civil works in Jan~Apr 2017 and will be completed by the 2nd quarter of 2018, with maintenance periods of 15 months.

8. Table 1 provides details of road sections where maintenance is proposed during Phase II and Phase III subprojects associated with types of maintenance proposed and sub-project progress.

9. The Phase IV subproject is under preparation.

Page 14: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

3

Table 1 Road Sections for Maintenance during the Phase II and III of the Project and Project Progress (as of December 2017)

Road No. Sect. No. YHAB Local Area Office

Prefecture Road Class

Width (m) Rehab Length (Km)

Type of Maintenance: Major(Mj), Medium(Md), Minor

(Mi) (%)

Project Progress

Starting date Completed (CNY, 10’000)

Completed(%)

Phase II

S313 1 S313-Yuxi General Section

Yuxi 3 6.5/7.5 57.3 Mj Feb 2016 11,804 100.00

G213 2 G213-Yuxi General Section

Yuxi 3/4 7.5/8 61.56 Mj Feb 2016 12,901 100.00

G320

3 G320-Dali General Section

Dali 2/3 6.5/7.5/8.5 91 Mj 30 Nov 2015 13,687 100.00

4 G320-Baoshan General Section

Baoshan 1/2/3 7.5/8.5/12 83 Md 1 Dec 2015 12,631 100.00

Phase III

S313 1 Section: S202(270.575-282.875)

Qujing 2 11.2 [email protected] 1.1km@12m

12.3 Major

2017.4 2102.76 35.01

G213 2 Section: S202(294.075-312.775)

Qujing 2 [email protected] 2.56km@12m

18.7 Major

G320

3 Section: S202(150-160)

Qujing 3

7.5 m

10 Major

2017.4 1609.95 28.44 4 Section: S207(28-42)

Qujing 3

7 m

14 Major

S313 5 Section: S207(59-70)

Qujing 3

6.5 m

11 Major

Page 15: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

4

Road No. Sect. No. YHAB Local Area Office

Prefecture Road Class

Width (m) Rehab Length (Km)

Type of Maintenance: Major(Mj), Medium(Md), Minor

(Mi) (%)

Project Progress

Starting date Completed (CNY, 10’000)

Completed(%)

G213 6 Section: G324(2451.5-2484.0)

Kunming 2

12 m

20 intermediate

2,017.4 3956.91 64.69

G320

7 Section: G320(2745.3-2755.3)

Kunming 3

7.5 m

10 Major

8 Section: G214(2542-2563)

Lincang 2

12 m

21 Major 30.923 0.7

S313 9 Section: S303(47.588-60.588)

Lijiang 3

7 m

13 Major 2017.4 1126.93 47.23

G213 10 Section: G213(1950.2-2053.115)

Kunming 2/3

[email protected] [email protected] 102.915 Major 2017.1.1 20956 100

G320 11 Section: G323(1609.9-1668.932)

Wenshan 3

[email protected] [email protected] 59.032 Major 2017.1.1 3590 34.27

Source: YHAB and the IAs database

Page 16: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

5

II. Report Preparation

A. Purposes and Objectives

10. This report aims to investigate, monitor and evaluate the ecology and environment quality alongside the phase III maintenance subproject.

11. Through qualitative and quantitative analysis of the environmental impact of the project during the construction period, the impact scope and extent will be reported to provide a basis for rational construction.

12. According to the impact scope and extent during the construction phase, corresponding

environmental protection measures will be proposed to minimize negative impact caused by the project and well coordinate both development and environmental protection.

13. Emphasize public participation as a complementary to the environmental monitoring,

improve construction management, optimize unity of environmental, social and economic benefits, and provide realistic basis for the project management and environmental management.

B. Policy, Legal, and Administrative Framework

14. For the proposed road maintenance and rehabilitation works associated with this project, the following legislation does:

a) The Environmental Protection Law of PRC (1989), fundamental law; b) Management Directory of EIA Classification for Construction Project (MEP, 2008); c) Regulations on Review and Approval of EIAs for Construction Project (MEP,

2009); d) Regulation on Hierarchical Review and Approval of EIAs for Construction Project

in Yunnan Province (2010), covering management of the whole EIA process; e) Environmental Protection Management Ordinance for Construction Project (1998); f) Environmental Protection Management Regulation for Transport Construction

Project (MOT, 2003); g) Environmental Protection Ordinance of Yunnan Province (2004); h) Notice on Enforcement of Environmental Supervision in Transport Construction

Project (MOT, 2004), covering environmental management for the life cycle of the transport construction project;

i) Water Pollution Prevention Law of PRC (2008) and relevant regulations, mandatory requirements for water pollution prevention and mitigation;

j) Air Pollution Prevention Law of PRC (2000) and relevant regulations, mandatory requirements for air pollution prevention and mitigation;

k) Environmental Noise Pollution Control Law of PRC (1996) and relevant regulations, mandatory requirements for noise pollution prevention and mitigation;

l) Solid Waste Pollution Control Law of PRC (2005) and relevant regulations, mandatory requirements for solid wastes pollution control and recycling;

m) Water and Soil Conservation Law of PRC (2010) and relevant regulations, mandatory requirements for soil erosion control;

n) Land Management Law of PRC (2004); o) Highway Safety Ordinance of PRC (2011); p) Quota for Land Use of Highway Construction Project (Ministry of Construction

combined with Ministry of Land and Resources,1999), regulatory requirements for land acquisition of the highways;

q) Nature Reserve Ordinance of PRC (1994), Ordinance for Scenic Resorts and Historic Sites of PRC (2006);

Page 17: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

6

r) Ordinance for Management of Nature Reserves in Yunnan Province (1998), mandatory requirements for conservation of the protected areas;

s) Ordinance for Redress of Public Complaints (the State Council, 2005), Interim Procedures for Public Consultation in EIA (SEPA, 2006), and Environmental Complaints Management Regulation (SEPA, 2006), requirements for EIA public consultation and environmental grievance redress;

t) Notice on Strengthening EIA Management to Control Environmental Risks (SEPA, 2003);

u) Interim Management Regulation for Contingency Plan of Environmental Incidents (MEP, 2010), management requirements for environmental risks control, preparation and implementation of environmental contingency plan;

v) Environmental standards and guidelines, including environmental quality standards for surface water, air, and ambient noise; emission standards for polluting sources of wastewater, air pollutants, and noise; as well as EIA guidelines such as Technical Guideline on EIA published by MEP; and

w) PRC guideline HJ/T169-2004, National Inventory of Hazardous Goods & MEP Dec.1, 2008.

15. Yunnan has a large number of international, national, provincial and local protected

areas. For each Phase, determination of the location of any designated sites in relation to the roads to be maintained will be necessary. The phase III maintenance subproject does not involve any protected areas.

C. Report Period

16. This report, the EMR in 2nd half 2017, focuses on atmosphere, water and acoustic environmental impacts during the construction and various indicators before and during construction are compared.

D. Scope of Environment Monitoring

17. Phase III subprojects is classified as environment Category C since it is likely to have minimal or no adverse environmental impacts. According to the project IEE and EARF (Environmental Assessment and Review Framework), the ESSU is responsible for environmental monitoring. A summary monitoring checklist was prepared (Appendix 2) and used to verify the implementation of each mitigative and monitoring measure defined in the EMP. In addition, during this monitoring period, field onsite sampling and laboratory testing was undertaken by environmental specialists of Yunnan Science and Technology Research Institute of Highways (YSRI), the subordinate of the YHAB, albeit not a third party or nationally accredited environmental testing agency (neither mandatory for Category C project monitoring nor required in the EMP). YSRI designated environmental specialists with professional sampling and testing equipment &instruments for this assignment to provide quantitative construction site environmental status information to some extent. Field onsite sampling and laboratory testing includes: (1) atmosphere environment: within 200m on the two sides of the roads’ centre; (2) noise: within 50m on the two sides of the road center, those nearest to the roads, such as residential areas, buildings, schools, parks, hospitals and other sensitive points; (3) surface water: water quality of the rivers section, nearest to the roads; and (4) ecological environment: the affected land, vegetation, animals and plants along the roads.

Page 18: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

7

III Implementation of EMP

A. Detailed design drawings and bidding documents

18. The construction drawings and design documents contains environmental management. The construction precautions list soil and water conservation, ecological protection, water, dust and noise control, human health and safety and environmental protection during the construction should be paid attention to (see construction drawing designs). EMP is also included in the bidding documents. (see the bidding documents)

B. Institutional Arrangements

19. Yunnan Highway Administration Bureau (YHAB), the implementing agency (IA), is responsible for organizing, coordinating and supervising the implementation of these two components. The IAs of phase III subproject had been set up in Dali, Wenshan, Baoshan and Yuxi General Sections, under which, the safeguards departments were responsible for supervision and inspection of safety, occupation health, environmental protection on constructors, ensuring smooth road traffic, as well monitoring major hazards and investigating safety accident. The IAs of phase III subproject formulated the implementation plans of environment protection and water and soil conservation, construction safety and traffic management according to approved EMP and SEPP.

C. Construction Supervisors

20. With good testing equipment and strong technical capacities of construction supervision, the CSCs have undertaken all types (I, II, III) of highway project supervision.

21. The organizational chart for supervision of environmental protection, water and soil

conservation are shown as follows. The EHS personnel composes: a. Chief Construction Supervisor is also the chief of Environmental Protection, Water

and Soil Conservation Department. b. The director of the Chief Construction Supervisor Office is also the EHS engineer in

the Environmental Protection, Water and Soil Conservation Department. c. A full-time EHS engineer is set up in each residential office. And d. The subgrade, pavement, traffic engineering and test supervision engineers in the

residential offices are concurrently environmental protection, water and soil conservation engineers, responsible for supervision and compliance of EMP and SEPP within their work scopes.

Page 19: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

8

Figure 1 Organizational Chart for Supervision of Environmental Protection, Water

and Soil Conservation

22. Scope of supervision of environmental protection, water and soil conservation covers the areas directly influenced by the two components, including construction sites of main highway works and temporary works, construction camp, construction access road, borrow pit, disposal site, sand quarry, mixing plant, and other existing local roads bearing a large number of haulage.

23. The construction supervisors developed phase III road maintenance supervision plans,

including contract-specific environmental supervision plans, safety supervision plans, and incorporated detailed guidelines for implementation of construction supervision, environmental protection and soil and water conservation into daily supervision work. Part-time environmental protection engineers were designated to be responsible for inspection on possible environmental impacts and soil and water loss, safety issues, on-site and inspection during the process of main construction process, in order to ensure mitigation measures to be well implemented.

D. Implementation status of the mitigation measures

24. Implementation status of the mitigation measures during this reporting period are summarized in the Appendix 1. The implementation status of the mitigation measures are summarized in the last columns of the tables for comparison with the designed mitigation measures stated in the EMP. In summary, the mitigation measures have to date been implemented effectively.

25. Contractors prepared monthly contract-specific construction environmental work reports to record progress with implementation of the EMP. The ESSU undertook quarterly compliance audits of the YHAB and their contractors in evaluating performance against project environmental indicators in the EMP, and submitted quarterly environmental compliance monitoring reports to the YHAB. The Appendix 2 summarizes the ESSU’s quarterly environmental compliance status by checklist for Phase II, III and IV Subproject

Chief Construction Supervisor Office

Chief Construction Supervisor

EHS engineers, and other professional engineers

Onsite supervisors Logistic personnel

Page 20: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

9

Roads (Reporting period: Q3 and Q4 2017, abstract). This semi-annual environmental monitoring report abstracting quarterly environmental compliance audits will be submitted to ADB for uploading on ADB's website after ADB's review and clearance.

26. In accordance with clauses and technical specifications in the construction contracts and

the EMP, corresponding mitigation measures are adopted during construction management. Specific measures are shown as follows (The site photos pls. see the Appendix 3):

i.Water: The construction area does not involve any drinking water source, irrigation water source or other important water body. A little construction waste water was generated, so the impact to the surface water is very minor.

a. The entire construction process does not generate wastewater because the maintenance components were applied with in-situ cold recycling, gradation gravel pavement with warm asphalt, b. On construction sites, no new barrack was built. The phase III subproject IAs, the supervisors and the contractors rented house of local villagers as workplace, with toilet and septic tank. Domestic wastewater and catering wastewater was not directly discharged. c. Equipment maintenance and refueling were undertaken in the fixed places, rather than on the construction sites, which did not permeate into the water body. d. The equipments and vehicles were cleaned up in the vicinity of nearby car washing shops, so the maintenance section did not generate vehicle washing wastewater. e. Drainage ditches were built on both sides of the roads. The construction workers cleaned up the construction waste in a timely manner to ensure smooth drainage.

ii.Air: The impact of the air quality is mainly from smoke, dust and exhaust of

construction machinery and vehicle, etc. Main mitigation measures are shown as below:

a. The constructor was equipped with 7 sprinklers, 4 times a day, and increased to 6 times at construction section near the villages. b. Hauling trucks in bulk materials were covered by canvas as much as possible to reduce the dust during transport. c. A gradation mixing station is located about 1 km away from the construction site, and an asphalt mixing station and a cement mixing station were built together. The asphalt mixing station was equipped with bag dust removing equipments to reduce asphalt smoke emissions. And the cement mixing station was sprayed with a small amount of water in the hopper to reduce dust emissions. No any resident or farmland is located nearby, therefore, the generated dust had little impact to the public.

iii.Noise: Noise pollution at construction stage is mainly caused by the construction

machinery and vehicle hauling activities. The constructor worked from 8:00-18:00 time during daytime, and at night without construction. If at construction section near the villages, construction stopped during 12:00-14:00 to avoid disturbance with the villagers.

iv.Solid waste: During construction period, the earth materials, asphalt, gravel were

piled in the slope less than 5% in the fixed places.

v.Soil erosion. Soil erosion of the component was mainly caused by solid waste, construction waste, leaking oil in case of rain runoff. Main mitigation measures are

Page 21: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

10

shown as below: a. Only a small amount of pavement material was used to repair the pavement, so did not need to dispose of solid waste. After in-situ cold recycling, the used asphalt is reused to repair the maintenance section. b. Before daily construction, firstly checking the construction vehicles and machinery status. If any problem, the vehicle was sent to the nearest vehicle repair shop for maintenance. Vehicle was refueled in the refueling station in the vicinity. c. On the construction sites, there was no vehicle maintenance and refueling. d. Renting nearby village houses as a living area and office area, so the garbage generated by the construction workers was collected by the community sanitation department. e. The constructors leased the existing asphalt mixing station, which was set in the abandoned quarries, without any water body or resident nearby. The asphalt spill was also collected and processed in the container. The groundwater was not affected by surface runoff.

vi.Flora and Fauna: Within the scope of construction area, no ancient tree has been

found. The construction sites was limited on the original road, without expansion or no excavation and blasting operations, therefore, it did not affect the roadside farmland and trees.

vii.Health and Safety. Health and safety education is the important content during

construction period. Most construction workers are local villagers. If any illness, they went to local community hospitals for medical treatment. In order to ensure the construction safety and quality, before construction, the constructors conducted safety and skills training for all the staff. Main mitigation measures are shown as below:

a. Worker personal protection. Before construction, all construction workers are trained on use of personal protection equipments. b. At the construction sections, the bulletin boards, safety cones, marking and other warning signs were erected to indicate the project name, project brief introduction, constructors, designers, supervisors, and their telephone numbers. c. Traffic cones were used in the construction area with a designed construction staff in charge of traffic management. d. All workers were provided with protective masks, gloves, safety vest, helmet and protective shoes, etc. On-site construction workers were wearing eye-catching safety vest. e. Renting local village houses as office spaces, equipped with drinking water, life necessities, and clean public toilets. f. Daily supervision and inspection of the construction workers whether safety protection measures were completed, the construction equipments were under normal operation according to standard procedures. Daily or weekly logs of supervision were kept. g. Irregular maintenance on the vehicles and construction machinery. h. Regularly inspecting the cable lines in the construction area to eliminate the safety hazard. And i. Related disease prevention knowledges were frequently posted, such as H7N9 bird flu.

viii.Landscape: The phase III subproject is not within the scope of the scenic area, so

the natural landscape was not significantly impacted. The construction equipment

Page 22: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

11

and material was only temporarily stored, will be recovered after completion. Main mitigation measures are shown as below:

a. The village houses were rented as office space and for living. Construction sheds were built along the sides of the road, so the landscape was not affected. b. Rented houses were equipped with garbage pool. The community sanitation management department regularly collected then transported to the landfill for disposal. c. Trucks with bulk materials were covered with canvas in order to keep the vehicle clean and tidy as possible. d. No new path was built to avoid the destruction of land or vegetation. e. Mixing station and material yard were leased with local existing equipment and facilities, and will be recovered after completion. And

ix.Cultural Heritage: No any cultural heritage was found within the scope of at a radius

of 25 km around the construction sites.

E. Analysis of Environmental Monitoring Results

27. During this monitoring period, field onsite sampling and laboratory testing was undertaken by Yunnan Science and Technology Research Institute of Highways (YSRI), the subordinate of the YHAB, albeit not a third party or nationally accredited environmental testing agency (neither mandatory for Category C project monitoring nor required in the EMP). YSRI designated environmental specialists with professional sampling and testing equipment &instruments for this assignment to provide quantitative construction site environmental status information to some extent.

28. Water quality monitoring: Phase III subproject road maintenance involve only one river (Chi’na River), while the other maintenance sections do not involve any river, reservoir or any other surface water body. Chi’na River should meet the Class III standards of Environmental Quality Standards for Surface Water (GB 3838-2002, see Table 2). YSRI conducted on-site sampling and monitoring on Chi’na River. The monitoring results are indicated as follows (see Table 3).

Table- 1 Environmental Quality Standards for Surface Water(GB3838-2002)

Unit:mg/L, except PH dimensionless

No. Item Class III

1 CODCr ≤20

2 pH 6-9

3 DO ≥5.0

4 NH3-N ≤1.0

Page 23: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

12

Table- 2 Water Quality Monitoring Results of Phase III Subproject

Unit:mg/L

Sub-components

Monitoring Point

Monitoring Date CODcr pH DO NH3-N SS

Phase III

Section: S202(270.575-282.875)

Chi’na River

Pre-construction Period (24 Aug 2016)

19 8 8 0.2 18

Construction Period (18 Sept. 2017)

15 8 8 0.2 65

Construction Period (21 Nov. 2017)

17 8 8 0.2 76

Class IV, Environmental Quality Standards for Surface Water

(GB3838-2002)

30 6-9 3 1.5

Compliance Status Complied with

29. Evaluation of water quality monitoring results. The monitoring results of the above river show its water quality can meet the classes III of Surface Water Environmental Quality Standards (GB3838-2002). At the same time, it also shows that the water quality during construction of the phase III subproject is no worse than that pre-construction.

30. Air quality monitoring. The main pollutants in the construction period are dust and

asphalt. Along the road, the Class II standard in the Ambient Air Quality Standard "(GB3095 - 2012) should be complied with, as shown in Table 4. YSRI undertook on-site air quality monitoring. The results are as follows (see Table 5).

Table- 3 Ambient Air Quality Standard (GB3095-2012)

Unit:mg/ m3

Item Sampling Period Class II, Standard Limit

PM10 Daily Average 0.15

NO2 Daily Average 0.12

SO2 Daily Average 0.15

Page 24: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

13

Table- 4 Air Quality Monitoring Results of Phase III Subproject

Unit: mg/m3

Sub-components Monitoring

Point Indictor PM10 NO2 SO2

Phase III

Section:S202(270.575-

282.875) Tianba town

Construction Period (18 Sept. 2017)

0.1 0.02 0.06

Construction Period (21 Nov. 2017)

0.12 0.02 0.04

Class II 0.15 0.12 0.15

Compliance Status Complied with

Section: S202(150-160) Dadegang village

Pre-construction Period (25 August 2016)

0.11 0.01 0.01

Construction Period (19 Sept. 2017)

0.10 0.01 0.08

Construction Period (22 Nov. 2017)

0.12 0.02 0.06

Class II 0.15 0.12 0.15

Compliance Status Complied with

Section: S207(28-42) Wulong town

Pre-construction Period (26 August 2016)

0.10 0.01 0.01

Construction Period (10 Sept. 2017)

0.09 0.01 0.02

Construction Period (23 Nov. 2017)

0.10 0.03 0.01

Class II 0.15 0.12 0.15

Compliance Status Complied with

Section:G324(2451.5-2484.0) Jiangtou Village

Pre-construction Period (27 July 2016)

0.04 0.01 0.01

Construction Period (21 Sept. 2017)

0.11 0.01 0.01

Construction Period (2 Nov. 2017)

0.11 0.02 0.01

Class II 0.15 0.12 0.15

Page 25: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

14

Sub-components Monitoring

Point Indictor PM10 NO2 SO2

Compliance Status Complied with

Section:G320(2745.3-2755.3) Xiaoshao village

Pre-construction Period (30 August 2016)

0.10 0.02 0.01

Construction Period (22 Sept. 2017)

0.07 0.02 0.01

Construction Period (29 Dec. 2017)

0.10 0.01 0.01

Class II 0.15 0.12 0.15

Compliance Status Complied with

Section: G214(2542+000 ~

2563+000) Shaojie village

Construction Period (26 Sept. 2017)

0.09 0.02 0.01

Construction Period (6 Dec. 2017)

0.09 0.01 0.02

Class II 0.15 0.12 0.15

Compliance Status Complied with

Section: S303(47+588 ~

60+588)

Gaozhai village of

Renhe town

Construction Period (29 Sept. 2017)

0.09 0.01 0.02

Construction Period (13 Dec. 2017)

0.10 0.01 0.02

Class II 0.15 0.12 0.15

Compliance Status Complied with

Section:G323(1609.9-

1668.932) Guichao village

Construction Period (6 Sept. 2017)

0.11 0.02 0.01

Construction Period (21 Dec. 2017)

0.13 0.01 0.01

Class II 0.15 0.12 0.15

Compliance Status Complied with

31. Evaluation of air quality monitoring results. The atmospheric impact scope is mainly focused within the 50m near both sides of the RoWs. The construction (road maintenance) period lasted short with very limited impact. From the above data, the air monitoring indicators, PM10, NO2 and SO2, before construction and construction period,

Page 26: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

15

had little change and both were better than Class II standard in the Ambient Air Quality Standard "(GB3095 - 2012). It shows that the construction activity has no serious influence on the surrounding air quality after taking effective mitigation measures, such as timely sprinkling water to suppress dust.

32. Noise monitoring: The construction noise has a certain effect on the sound

environment quality, which is mainly caused by the construction machinery and vehicles.

33. For phase III Subproject, the Class 4a standard in the Standards for Acoustic Environmental Quality (GB3096-2008) (see Table 6) should be complied with. During construction phase, Emission Standard of Environment Noise for Boundary of

Construction Site(GB12523-2011(see Table 7) is applicable. The main noise source

during the construction period sees Table 8, and the noise monitoring results are shown in Table 9.

Table- 5 Environmental quality standard for noise (GB3096-2008)

Unit:dB (A)

Acoustic environment functional area

Noise Limit LAeq(dB)

Daytime Nighttime

Class 4a 70 55

1

Table- 6 Emission standard of environment noise for boundary of construction site

(GB12523-2011)

Daytime (LAeq(dB)) Nighttime(LAeq(dB))

70 55

Table- 7 Major Noise Source

Period Major Noise Source

Noise Limit LAeq(dB)

Daytime Nighttime

Construction

Period

All kinds of vehicles 70 55

All kinds of vehicles, concrete mixer, etc. 70 55

Bulldozer, excavator, paver 75 55

Page 27: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

16

Table- 8 Noise Monitoring Results of the Environmental Sensitive Receptors Along

Phase III Subproject

Unit: dB (A)

Period/ Sub-components Time Environmental

Sensitive Receptors

Distance to

road center line(m)

LAeq(dB) Compliance

Status Monitoring Value

Standard limit

Phase III

Section:S202(270.575-

282.875)

9:00-17:00, 18 Sept. 2017, Daytime

Yangchang village 15 54 70

Complied with

Xuanwei 4th middle school 30 51 60

Complied with

Shuchang village 20 48 70

Complied with

Tianba town 18 50 70

Complied with

9:00-17:00, 21 Nov. 2017, Daytime

Yangchang village 15 53 70

Complied with

Xuanwei 4th middle school 30 50 60

Complied with

Shuchang village 20 50 70

Complied with

Tianba town 18 51 70

Complied with

Section: S202(150-160) 9:00-17:00, 19 Sept. 2017, Daytime

Dadegang village 5 58 70

Complied with

Xiaodegang village

5 57 70 Complied

with

9:00-17:00, 22 Nov. 2017, Daytime

Dadegang village 5 56 70

Complied with

Xiaodegang village

5 55 70 Complied

with

Section: S207(28-42) 9:00-17:00, 10 Sept. 2017, Daytime

Wulong town 15 56 70 Complied

with

Nanyan village 15 48 70 Complied

with

Lugu village 15 48 70 Complied

with

9:00-17:00, 23 Nov. 2017, Daytime

Wulong town 15 52 70 Complied

with

Nanyan village 15 47 70 Complied

with

Lugu village 15 45 70 Complied

with

Section:G324(2451.5-

2484.0)

9:00-17:00, 21 Sept. 2017, Daytime

Shuijinpo village

20 47 70 Complied

with

Anjiatian village 15 49 70

Complied with

Jiangtou village 15 50 70

Complied with

Baohong village 20 44 70

Complied with

Page 28: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

17

Period/ Sub-components Time Environmental

Sensitive Receptors

Distance to

road center line(m)

LAeq(dB) Compliance

Status Monitoring Value

Standard limit

9:00-17:00, 2 Nov. 2017, Daytime

Shuijinpo village

20 50 70 Complied

with

Anjiatian village 15 51 70

Complied with

Jiangtou village 15 49 70

Complied with

Baohong village 20 46 70

Complied with

Section:G320(2745.3-

2755.3)

9:00-17:00, 22 Sept. 2017, Daytime

Songming prison 20 46 70

Complied with

Xiaoshao village 30 43 70

Complied with

9:00-17:00, 29 Dec. 2017, Daytime

Songming prison 20 44 70

Complied with

Xiaoshao village 30 42 70

Complied with

Section: G214 (2542+000~

2563+000)

9:00-17:00, 26 Sept. 2017, Daytime

Xiyi village 20 51 70 Complied

with

Gazhi village 15 45 70 Complied

with

Shaojie village 10 46 60 Complied

with

9:00-17:00, 6 Dec. 2017, Daytime

Xiyi village 20 46 70 Complied

with

Gazhi village 15 45 70 Complied

with

Shaojie village 10 46 60 Complied

with

Section: S303 (47+588 ~

60+588)

9:00-17:00, 29 Sept. 2017, Daytime

Gaozhai village 20 49 70 Complied

with

Hongde village 25 46 70 Complied

with

Akexi village 10 50 60 Complied

with

9:00-17:00, 13 Dec. 2017, Daytime

Gaozhai village 20 45 70 Complied

with

Hongde village 25 43 70 Complied

with

Akexi village 10 52 60 Complied

with

Section:G323(1609.9-

1668.932)

9:00-17:00, 6 Sept. 2017, Daytime

Pingban village 10 46 70 Complied

with

Longmen Village

10 45 70 Complied

with

Guichao school 40 42 60 Complied

with

9:00-17:00, 21 Dec. 2017, Daytime

Pingban

village 10 49 70

Complied with

Longmen

Village 10 47 70

Complied with

Guichao

school 40 44 60

Complied with

Page 29: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

18

34. Evaluation of noise monitoring results. 24 representative monitoring points were set along the phase III subproject. The main noise source during construction period is social traffic noise and construction machinery noise. Because construction is prohibited at night, construction machinery noise has little effect on the surrounding residents. All the monitoring result meets national standards.

F. Institutional Capacity Building and Training

35. To strengthen the implementation of the project, an ADB loan PMO was established in the Maintenance Department under YHAB. During the project implementation, the PMO is in charge of overall supervision on technical, quality, environmental, social and safety aspects, and responsible for implementing the environmental protection requirements in the approved EMP, and supervising the contractor's daily environmental mitigation and monitoring and preparing quarterly progress reports.

36. The PMO was led by the deputy director (a senior engineer) of Maintenance Department

under YHAB, and designated a full-time senior engineer and other environmental, social, and safety experts. The Department is responsible for coordination and supervision among the IA, the constructors the CSCs, and supervision and inspection of environmental mitigation measures in the EMP.

37. The PMO, the phase III subproject IAs, CSCs, and the constructors assigned EHS staffs.

38. Before construction, the PMO, the constructors, CSCs, and the relevant departments undertook the relevant training on environmental management plan and road safety.

39. In order for implement the mitigation measures and environmental monitoring, before

entering construction sites and during construction period, ADB's environmental experts/loan implementation environmental consultant/YHAB/phase III subproject IAs provided training related to environmental protection to the CSCs and constructors. The training was mainly focused on implement the mitigation measures and environmental monitoring. Training activities were held in the onsite project management office meeting room. Training activities include the following aspects:

a. Understanding and application of internationally accepted environmental management practices.

b. Compliance monitoring method, required equipment and methods. c. Compliance monitoring information analysis. d. Environmental safeguards enforcement methods and measures. e. Training contents include case studies and field trips.

Page 30: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

19

IV. Public Consultation, Information Disclosure and Grievance Redress

Mechanism

A. Public Consultation, Information Disclosure

40. During Jul. to Dec. 2017, YSRI carried out two rounds of public opinion survey to the public along the phase III subproject. The below questions asked are as follows: (i) Do you think there is any impact of the noise and dust generated during construction on your production and life? (ii) During the construction period, is there any influence on your trip due to traffic control? (iii) Any impact on your farmland and crops during the construction period? (iv)How do you think the constructors to take measures to mitigate environmental pollution? (v) Should overloading vehicles be controlled?

41. A total of 146 villagers/residents alongside the along the phase III subproject were

consulted, including 43 women or 36 ethnic minorities, as shown in the below Table 10. The main feedback is as follows:

a) The residents expressed support for the maintenance program and hoped that good road conditions could give their jobs, more conveniences, and more opportunities to improve the quality of life.

b) The residents hoped to repair the road as soon as possible, and the poor road conditions lasted for many years and have brought a lot of adverse effects to their work and life, such as rainy days and dust.

c) It is desirable to have the opportunity to participate in construction activities or to provide other services to increase economic income.

d) The respondents thought that pollution was minor during the construction period, and the duration was short and acceptable.

e) Hoped to help solve some practical problems (such as drainage, safety, etc.). All the above comments and recommendations (especially for the above (e)) have been passed to YHAB/IAs/contractors.

Table- 9 List of Persons Consulted With

No. Name Gender Minorities Profession Name of Village

Phase III

Section: S202(270.575-282.875) ,18 Sept. 2017

1 Konɡ Yɑhuɑ Female Han Villager

Wenhe village, Haidai Town

2 Zhɑnɡ Qionɡhuɑ Female Yi Driver

Shiba village, Haidai Town

3 Dinɡ Henɡhui Male Han Villager

Jijie village, Banqiao Town

4 He Dɑoqiɑnɡ Male Han Repairman

Yueliangtian village, Haidai Town

5 Konɡ Chunyɑn Female Han Villager

Shuchang village, Haidai

Page 31: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

20

No. Name Gender Minorities Profession Name of Village

Town

6 Mo Yunpin Male Han Driver

Jichang village, Yangchang Town

7 Li Jixiɑn Female Han Driver

Dasongshu village, Yangchang Town

8 Sun Yinɡhe Male Han Businessman Luosuo village

9 Zhɑo Yonɡtuɑn Male Han Lorry driver Mide village

10 Huɑnɡ Meifen Female Han Gas Station Staff Tiɑnba town

Section: S202(270.575-282.875) ,30 Dec. 2017

1 Zhɑnɡ Decɑi Male Han Shop owner Haidai Town

2 Luo Guifen Female Han Villager Tiɑnba town

3 Konɡ Weimou Male Han Villager Shuchang village, Haidai Town

4 Wɑnɡ Xiɑofenɡ Female Han Villager Luosuo village

5 Xu Xinɡe Female Han Shop owner Mide village

6 Zhou Chenɡfɑ Male Han Driver Xiaoqu Village

7 Zhu Shun Male Han Villager

Xiaoqu Village

8 Qiɑn Li Female Han Villager

Mide village

9 Chen Yun Male Han Doctor Jichang village, Yangchang Town

10 Wɑnɡ Xinɡ Male Han Villager Qingshui village

Section: S202(150-160) , 19 Sept. 2017

1 Cui Zhipinɡ Male Han Villager Dagɑnɡde village

2 Mɑ Bɑoqiɑnɡ Male Hui Shop owner Dagɑnɡde village

3 Mɑ Li Female Hui Shop owner Dagɑnɡde village

4 Shi Zulonɡ Male Han Shop owner Dagɑnɡde village

5 Li Zhufen Female Han Villager Xiɑogɑnɡde village

6 Yɑnɡ Linɡfen Female Yi Villager Xiɑogɑnɡde village

7 Cɑo Xiɑohuɑn Female Han Villager Xiɑogɑnɡde village

8 Zhɑnɡ Qiɑnɡ Male Han Villager Xiɑogɑnɡde village

Page 32: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

21

No. Name Gender Minorities Profession Name of Village

9 Zhenɡ Shɑoyonɡ Male Han Businessman Meijiabei village

10 Niɑn Degui Male Han Worker Meijiabei village

Section: S207(28-42), 10 Sept. 2017

1 Wɑnɡ Qiɑofu Male Zhuang Villager Shuaizhai Village, Goujie town

2 Xionɡ Jinyonɡ Male Zhuang Villager Guiche Village, Goujie town

3 Donɡ Xiɑohonɡ Male Zhuang Villager Nanyan Village

4 He Lihui Male Zhuang Villager Nanyan Village

5 Liu Yɑnshenɡ Male Han Villager Bayda Village

6 Yuɑn Shuliɑnɡ Male Han Businessman Sanheyin Village

7 Liu Xiɑoliɑnɡ Male Zhuang Villager Hongbeng Village

8 Chen Shɑnlin Male Han Driver Luopinɡ county

Section: S207(28-42), 14 Dec. 2017

1 Liɑnɡ Jiɑshenɡ Male Han Villager Banjiang Street, Wulong Township

2 Xionɡ Jinyonɡ Male Zhuɑnɡ Villager Guiche Village, Goujie town

3 Donɡ Xiɑohonɡ Male Zhuɑnɡ Villager Guiche Village, Goujie town

4 Zhɑnɡ Decɑi Male Han Villager Naxia Village, Gaoliang town , Shizong county

5 He Lihui Male Zhuɑnɡ Villager Nanyan Village

6 Fu Shichɑo Male Han Villager Sheli village

7 Yuɑn Shuliɑnɡ Male Han Shopper Sanheyin Village

8 Mr. Wang Male Han Villager Guiche Village, Goujie town

9 Wɑnɡ Qinɡsonɡ Male Han Driver Shizong county

Section: G324(2451.5-2484.0) , 21 Sept. 2017

1 Gɑo Yɑninɡ Male Han Hotel owner Goujie town

2 Chen Honɡgɑnɡ Male Han Villager Relongtan village , Muxing Community

3 Sun Xutɑo Male Han Worker Yiliang Gas Station

4 You Yupinɡ Male Han Worker Xinchen Gas Station

5 Huɑnɡ Yuɑnlin Male Han Businessman Dahoubu village

Page 33: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

22

No. Name Gender Minorities Profession Name of Village

6 Li Hɑiquɑn Male Han Villager Qixing village

7 Xu Ronɡgui Male Han Villager Tangjiawan village

8 Xionɡ Jiɑnlin Male Han Villager Qixing village

9 Bi Mɑoxiɑnɡ Male Han Businessman Qingshan village

10 Mɑ Conɡan Male Han Villager Qixing village

11 Li Cuizhen Female Yi Villager Xiaohoubu village

Section: G324(2451.5-2484.0) , 30 Dec. 2017

1 Li Fenɡmei Female Han Villager Qingshan Village

2 Xu Qinɡdenɡ Male Han Businessman Qingshan Village

3 Bi Mɑoxiɑnɡ Male Han Villager Qingshan Village

4 Tiɑn Peiyun Male Han Businessman Qingshan Village

5 Mɑ Zhonɡlu Male Han Villager Qixing village

6 Xu Ronɡgui Male Han Villager Tangjiawan village

7 Donɡ Gɑohui Male Han Businessman Qixing village

8 Ruɑn Xuebin Male Han Villager Relongtan village

9 Honɡ Yonɡ Male Han Villager Xiaodoukou village

10 He Zhonɡyun Male Han Villager Xiaodoukou village

Section: G320(2745.3-2755.3) , 22 Sept. 2017

1 Tɑn Zhonɡchun Female Han Villager Xinnong village

2 Li ancestor Female Han Villager Xinnong village

3 Huɑnɡ Yunxiɑnɡ Female Han Villager Bajia villages

4 Yɑnɡ Jiyinɡ Female Han Villager Xinnong village

5 Bi Guihuɑ Female Han Villager Xinnong village

6 Jin Huifen Female Han Villager Suomeiao Village

7 Zhu Honɡshun Male Han Villager Suomeiao Village

8 Shen Zhonɡhonɡ Male Han Villager Xinnong village

9 Zhou Bɑofen Female Han Villager Xiaoshao village

Page 34: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

23

No. Name Gender Minorities Profession Name of Village

10 Yɑnɡ Yonɡhe Male Han Villager Xiaoshao village

Section: G320(2745.3-2755.3) , 30 Dec. 2017

1 Hu Yushenɡ Male Han Villager Xiaoshao village

2 Zhu Ronɡ Male Han Villager Xiaoshao village

3 Zhɑo Wenjiɑo Female Han Villager Xiaoshao village

4 Zhou Zilonɡ Male Han Villager Xiaoshao village

5 Tɑn Luxiɑn Female Han Villager Xinnong village

6 Mɑo Yunyonɡ Male Han Villager Xinnong village

7 Jiɑnɡ Yun Male Han Villager Xinnong village

8 Shen Ronɡxinɡ Male Han Villager Xinnong village

9 Shen Zhonɡyou Male Han Villager Xinnong village

10 Zhɑnɡ Yuhui Female Han Villager Xinnong village

Section: G214(2542-2563), 26 Sept. 2017

1 Chɑ Zhuɑnɡ Male Yi Villager Shaojiezhong village

2 Chɑ Chunchenɡ Male Yi Villager Shaojie village

3 Yɑnɡ Chenɡlin Male Han Villager Shaojiezhong village

4 Shi Guogui Male Yi Villager Shaojieshang village

5 Yɑnɡ Shidiɑn Male Han Villager Shaojieshang village

6 Chɑ Xuewɑnɡ Male Yi Villager Dujia village

7 Wɑnɡ Shɑoyinɡ Male Han Villager Sanjia Village

8 Xu Xuediɑn Male Han Villager Xiyi Village

9 Shi Yuɑnyɑo Male Han Villager Yongbao village

10 Pu Xinɡhui Female Yi Villager Yanzitou Village

Section: G214(2542-2563), 27 Dec. 2017

1 Luo Kɑihe Male Yi Villager Banahe Village

2 Luo Yuronɡ Male Yi Villager Banahe Village

3 Luo Yuren Male Yi Villager Banahe Village

Page 35: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

24

No. Name Gender Minorities Profession Name of Village

4 Chɑ Jun Male Yi Villager Dujia village

5 Li Wenbin Male Yi Villager Dujia village

6 Li Wenchɑnɡ Male Yi Villager Dujia village

7 Shi Guoxiu Female Yi Villager Shaojiezhong village

8 Zi Honɡxiu Female Yi Villager Shaojieshang village

9 Zi Guohuɑ Female Yi Villager Haizi village

10 Xiɑ Fenɡ Male Han Villager Minɡzishɑn village

Section: S303(47.588-60.588), 29 Sept. 2017

1 Chen Chunwu Male Han Villager Shangping Village, , Renhe Town

2 Wɑnɡ Fuxiɑnɡ Male Han Villager Shangping Village, , Renhe Town

3 Wɑnɡ Fuliɑn Female Han Villager Longtan village, Renhe Town

4 Luo Shunyinɡ Female Han Villager Xiaobingxi Village

5 Zhɑo Youyɑn Female Han Villager Xiaobingxi Village

6 Yɑnɡ Jinmei Female Han Villager Dabingxi Village

7 Guo Fenɡxiɑn Female Han Villager Dabingxi Village

8 Wɑnɡ Yunkun Female Han Villager Xiaping Village, , Renhe Town

9 Wɑnɡ Yunfen Female Han Villager Xiaping Village, , Renhe Town

10 Wɑnɡ Yinyuɑn Male Han Villager Longtan village, Renhe Town

Section: S303(47.588-60.588),29 Dec. 2017

1 Liu Guofu Male Han Villager Shangping Village

2 Liu Guozhonɡ Male Han Villager Xiaobingxi Village

3 Ni Ronɡcɑn Male Han Villager Shangping Village

4 Guɑn Kouxiɑnɡ Male Han Villager Shangping Village

5 Shɑ Guyun Male Susu Villager Xiaobingxi Village

6 Zhou Xinɡhɑi Male Han Villager Xiaobingxi Village

7 Yɑnɡ Wenhui Female in the first place

Villager Xiaobingxi Village

8 Wɑnɡ Fuxiɑnɡ Male Han Villager Shangping Village

Page 36: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

25

No. Name Gender Minorities Profession Name of Village

9 Chen Chunwu Male Han Villager Shangping Village

10 Zhɑo Youyɑn Femal

e Han Villager Xiaobingxi Village

Section: G323(1609.9-1668.932), 6 Sept. 2017

1 Zhɑnɡ Zhenbo Male Han Villager Guichao town

2 Liu Honɡ Female Han Villager Guichao town

3 Xu Xiɑopɑn Female Han Villager Guichao town

4 Liɑnɡ Chɑnɡchenɡ Male Yao Villager Guichao town

5 Zhɑnɡ Guoqinɡ Male Han Villager Guichao town

6 Yɑnɡ Jiɑshun Male Yao Villager Guichao town

7 Mɑ Lili Female Han Worker Funinɡ county

Section: G323(1609.9-1668.932), 29 Dec. 2017

1 Quɑn Shimei Female Miao Villager Longmen village

2 Xionɡ Lizhi Female Miao Villager Longmen village

3 Xie Qinwei Male Yi Villager Longmen village

4 He Yunkun Male Han Villager Longmen village

5 Huɑnɡ Shɑojin Male Yao Villager Feiluo village

6 Wei Guɑnɡchenɡ Male Yao Villager Feiluo village

7 Xie Penɡ Male Han Villager Feiluo village

8 Luo Yuɑnpenɡ Male Han Villager Lonɡpang village

9 Zhɑnɡ Jiɑn Male Han Villager Lonɡpang village

10 Liɑnɡ Yonɡzhɑo Male Han Villager Lonɡpang village

B. Grievance Redress Mechanism (GRM)

42. YHAB established environmental GRM, and publicized the relevant information, such as phones numbers, etc.

43. During construction, the constructors and the relevant village committees have not

received any complaint on environmental protection or safety issue.

44. The procedures of GRM are shown as below.

Page 37: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

26

Figure 2 Procudures of Project GRM

45. The basic grievance redress steps are described below and shown in Figure 4. The ESSU will be responsible for facilitating, tracking and reporting grievance resolution at each step:

Step 1: The affected person should first try to resolve the issue of concern directly with the contractor and the local village committee. A solution must be presented within five days. If successful, no further follow-up is required.

Step 2: If there is no resolution the person can file the grievance with the county office of YHAB, the Maintenance Section or the Prefecture level Office the General Section. A resolution must be reached within two weeks

Step 3: If no resolution is found the complainant can take the next step and contact

the county or prefecture government offices where resolution will be required within two weeks.

Resolve issue with

contractor or village

committee

STEP 1

STEP 2

Resolve issue with

YHAB Maintenance or

General Section

Resolve issue with

Prefecture Government

STEP 3

5 days

2 weeks

2 weeks

ESSU to

facilitate

and track

resolution

and report

to ADB

Page 38: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

27

V. Conclusions and Suggestions

46. During construction, the phase III subproject IAs, the constructors and CSCs had taken the corresponding environmental impact mitigation measures in the EMP. The construction noise, dust and wastewater, and other impacts on the surrounding environment were reduced to a minimum.

47. Through field inspection, the constructors strengthened environmental protection, water

conservation, safety and other aspects according to relevant national environmental protection laws and regulations, ADB's SPS (2009) and the EMP. No land acquisition, demolition, road widening, occupation of farmland and other resettlement issue were identified. The environmental impacts of the component during the construction period were limited, and the construction period was short. With the completion of the component, the pollution will be eliminated in time, and the environment will revert to the state better than the original. From the point of view of the whole process of construction, the constructors strictly abided by the provisions, actively took mitigation measures to reduce pollution. So it obtained the strong support of the local community and the village. Through carrying out public consultation, the local residents were satisfied with the Project. During this period, no any pollution complaint did occur.

48. Suggestions: (i) Local villagers were hired, and their mobility was frequent. To address their

potential safety issue, it is recommended that safety and environmental protection awareness education should be carried out to improve safety and environmental awareness of the villagers and construction workers then to reduce environmental pollution and ecological damage. And (ii) More frequently watering at the sections nearby the villages and towns is recommended to reduce dust from construction.

Page 39: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

28

Appendix 1: Summary of Potential Environmental Impacts and the Mitigation Measures Implemented

(As of December 2017)

Environmental Issue Mitigation Measures

Compliance Status Proposed Corrective Action

1. PRECONSTRUCTION PERIOD

1.1 Lack of environmental technical capacity within YHAB and its General and Maintenance Sections in environmental assessment and design, management, supervision and reporting.

1.1 YHAB will establish a unit, the ESSU, to manage environmental, social and safety aspects of maintenance projects. The ESSU will be staffed by 3 full-time suitably qualified people. ADB will support international and national environmental consultancy services to develop and deliver a 5-day environmental assessment and management training workshop for YHAB staff and a 2-day workshop for first year Contractors.

Complied with. ESSU was established prior to loan effectiveness. YHAB training was completed during detailed design and prior to bidding. Contractor training was undertaken on appointment.

Not applicable

1.2 Translation of IEE, EMP, contract clauses and other templates for use by General and Maintenance Sections,

1.2 ESSU will provide the design team with translated copies of IEE, EMP and templates and check relevant clauses have been included.

YHAB/ESSU will provide the successful contractor with translated copies of IEE/EMP and assist contractor to prepare the Construction Environmental Work Plan (CEWP).

General Section will provide the Maintenance Section site engineer with the IEE, EMP and other templates for use in their inspection process. Given the uncertainty of inspection qualifications , the workshops as defined above will be held at the six General Section offices

Complied with or to be complied with. Translated during detailed design stage and provided instructions prior to contractor field mobilization. As part of the above item 1.1, workshops were held in Dali, Wenshan, Yuxi, Baoshan, Qujing, Kunming, Lincang, and Lijiang prefecture General Sections.

Not applicable

1.3 Consideration of IEE/EMP in preparation of the detailed design and bid documents.

1.3 ESSU will check that design and bid documents are responsive to key environmental, social and safety considerations.

Complied with.

Not applicable

1.4 Optimise design and planning of works to minimise impacts

1.4 During detailed design YHAB will incorporate mitigation measures defined in the IEE as follows:: 1. minimize the removal of mature trees from roadsides; 2. optimise traffic management to minimise access

restrictions

Complied with.

Not applicable

Page 40: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

29

Environmental Issue Mitigation Measures

Compliance Status Proposed Corrective Action

3. provide step-by-step guidance on environmentally acceptable bridge and culvert replacement methods

1.5 Announcement of subproject with road signs

1.5 Four weeks before work begins announce the project on roadside sign(s), at a location(s) easily accessible by the public. Signs should be presented in a language that can be understood by affected people, in Yunnan, there may be a need to provide signs in multiple languages.

At the same time, provide information on the construction activity via the Maintenance Section

Complied with. At both ends (boundaries) of the project. 3-4 weeks before the start of work

Not applicable

2. CONSTRUCTION PERIOD

2.1 Preparation of Environmental Documentation

2.1.1 Technical environmental capacity of Contractor to prepare the CEWP and to implement all mitigation and monitoring measures

2.1.1 Contractor team will include a specialist with environmental assessment experience to prepare the CEWP and obtain all relevant permits. The contractor will not be permitted to mobilize the workers without an approved CEWP and the appropriate permits in place.

Complied with. Prior to the start of the construction work.

Not applicable

2.2 Soils, Earthworks & Erosion

2.2.1 Management of earthworks transport and Storage procedures, including cleaning; leading to dust and air pollution

2.2.1 Large volumes of crushed quarry rock, aggregate and sand may be transported to and/or stored in the work site. These operations and storage areas will be constantly exposed to the elements and will create primarily dust during the frequent windy conditions, and some silty runoff.

Dust will be managed by daily use of watering trucks, subject to availability of water.

All topsoil needs to be collected, stored and reused to rehabilitate/revegetate the areas disturbed. This is applicable only to projects with IEEs

Complied with. Construction roads were enclosed with colored fence. Hauling vehicles were not overloaded, and covered with waterproof canvas. The constructors sprayed water with sprinklers at 2 times a day. In the vicinity of the villages and the schools, the frequencies of watering were increased.

Not applicable

2.2.2 Erosion control and slope stabilization, risk of land slip and chronic erosion at cuts and water crossings.

2.2.2 Contractor will be required to know the subsoil materials that are being cut into and excavated and have ready appropriate plans to stop land slippage and erosion,. At water crossings where structures are to be upgraded, careful replacement and use of gabions with culverts and bioengineering methods for rapid

Complied with. Based on an analysis of soil conditions by contractor and consultation with the General Sections’ hydrology and geotechnical

Not applicable

Page 41: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

30

Environmental Issue Mitigation Measures

Compliance Status Proposed Corrective Action

revegetation and slope stabilization will be used. Bioengineering approaches to be explored as described in Annex D.

experts, construction activities were limited on the original road, without building a new road.

2.2.3 Slope slippage and landslide zones left unaddressed

2.2.3 In any road sections where maintenance takes place and where there is a history of landslides and slope slippage, the contractor will be required to report any such conditions (if not already known) to the Maintenance Section and propose a costed remedial action, then undertake this work to stabilize the road and reduce risk of failure; including bioengineering solutions, metal netting and other proven methods.

Not applicable. Not applicable

2.2.4 Risk of erosion, landslide and destruction of landscape from side borrow operations

2.2.4 Any need for borrow material outside of the RoW will be subject to local environmental approvals and procedures and should also be carried out in consultation with ADB. Bioengineering approaches should be considered.

Not applicable. No borrow pit is required.

Not applicable

2.2.5 Side casting of waste by Contractor degrading down-slope area and blocking/ contaminating water body

2.2.5 Side casting of waste earthen materials is not permitted where slope is more than 5% and a side cast waste materials cannot be easily stabilized and prevented from eroding during a rain event, or extend outside the road RoW.

Complied with. No waste dumping.

Not applicable

2.2.6 Handling of contaminated construction waste materials

2.2.6 When encountering contaminated materials or it is a construction waste, contractors will follow PRC national and provincial requirements, consulting with EPBs if needed

Complied with.

Not applicable

2.2.7 Inappropriate disposal of spoil from construction work leading to contamination

2.2.7 Contractors will be required to: a) attempt to recycle all clean spoils material where possible and b) consider composting or b) dispose of all other material at sites approved by the local EPB.

Complied with. No soil dumping.

Not applicable

2.3 Poor Contractor Operating Procedures

2.3.1 Failure to adhere to construction related good housekeeping practices, including solid and sanitary waste management

2.3.1 Contractors will adhere to standard good housekeeping practices as defined in the contract Terms & Conditions and Contract Specifications. Special considerations will be given to 1. management of construction waste and water 2. equipment lubricants and fuel, including management

and collection of waste oils and fuel particularly

Complied with. Solid waste was collected in certain places and transported regularly. Renting nearby farmers’ houses.

Not applicable

Page 42: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

31

Environmental Issue Mitigation Measures

Compliance Status Proposed Corrective Action

related to refuelling depots, maintenance areas and diesel generator sets

3. Sewage will require latrines or chemical toilets with complete clean up after the construction is complete.

4. Garbage will be collected and properly disposed of after recycling and sorting,

This work will be completed in accordance with PRC, regulations and standards which the contractor will be expected to know. Also, the contractor shall orient all construction workers in basic sanitation and health care issues, and on the specific hazards of their work and will need to certify to that effect at the start of the construction period. 5. Once the site is no longer needed the contractor must

fully decommission it, with special emphasis on waste removal and clean up of any spills or hazardous materials plus any necessary revegetation.

Septic tank was equipped with. Fecal sewage and catering wastewater were discharged separately. Not affecting surface water.

2.3.2 Management of bitumen storage, asphalt, sealcoat and concrete production facilities to avoid leakage, dust and air pollution for community in vicinity

2.3.2 YHAB has indicated that no new facilities will be needed, but

for smaller jobs bitumen will be stored at the worksites. Under these conditions, the contractor will be required to provide secure locations for storage, handing and safe disposal of any worksite bitumen supplies. PRC’s hazardous materials handling regulations ( as defined in IEE, Section II) will be adhered to.

Complied with.

Not applicable

2.3.3 Management of petroleum products such as fuel, lubricants and bitumen to avoid spill and contamination.

2.3.3 Contractor will be required to have the following spill prevention measures in place at all work sites: 1. all fuelling to be done on a concrete surface provided

with spill catch surfaces that can be cleaned and all spilled fuel recovered and recycled based on discussions with fuel supplier.

2. All repair and maintenance work must either be done on a concrete surface with oil spill catch basin or oil catch pans must be provided at all service areas and training provided to all ‘mechanics’.

3. All fuel use areas where spills and leakage is possible, e.g. the generator, must have drip basins installed to prevent any leakage. These recovered materials must be recycled.

Complied with.

Not applicable

Page 43: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

32

Environmental Issue Mitigation Measures

Compliance Status Proposed Corrective Action

4. A fuelling areas must be equipped with proper non-drip fuel nozzles

5. All fuel tanks must have means for containment of accidental spills.

6. All bitumen handling must not permit any material from leaking to the ground, including transfer areas and any areas where bitumen is transported in drums.

7. Bitumen drums must be stored in a dry covered secure place where no leakage to water or ground is possible. Drums must be recycled at least once a year.

8. Any spills must be cleaned up and contaminated soils and water treated according to PRC regulations and standards within 24 hours of the occurrence.

2.3.4 Overloading of construction vehicles leading to damage to existing roads

2.3.4 The tonnage of material hauled must not exceed the road capacity. If the material mobilization causes damage of the road, then contractor must repair it immediately.

Complied with. No overloading in all materials hauling roads.

Not applicable

2.3.5 No or inadequate consideration for recycling and reuse of construction ‘wastes’ by the contractor

2.3.5 The contractor will need to demonstrate that an attempt has been made to reuse, recycle, convert by composting construction wastes such as asphalt, wooden materials, plant materials and other benign organic matter

Complied with.

Not applicable

2.3.6 Work Duration 2.3.6 Contractors will be encouraged to complete the work as quickly as possible, consulting with local communities on best timing and agreeing to such a timetable

Complied with.

Not applicable

2.4 Surface Water, Drainage and Water Pollution

2.4.1 Modification of surface drainage during culvert and bridge replacement and/or raising of horizontal road alignment

2.4.1 When modifying or interfering with surface drainage of any sort the contract will have to undertake the following: 1. All culverts must be sized at or larger than the one

being replaced and with care about slope and erosion protection at inflow and outflow. All construction materials at the entrance of culverts must be removed so as not to provide any obstruction. Culvert removal and replacement will be done when there are low flows or no water in the channel and during the dry months of the year. Confirm culverts are clear of

Complied with. No bridge or culvert involved. Drainage ditch built. Well maintenance to keep smooth.

Not applicable

Page 44: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

33

Environmental Issue Mitigation Measures

Compliance Status Proposed Corrective Action

debris on completion. 2. Bridges will be repaired and widened and as such

there will be machinery at least at the water edge. Maximum care is needed to avoid degradation of the river, stream shore and to undertake excessive excavation at the shore and in the water (at least not when there is water in the stream). Demolition must be done in a way that prevents large chunks of material from falling into the river. Stabilization of disturbed crossing banks must take place as part of the construction work and include filter fabric, gabions and preferably bioengineering techniques.

3. Where horizontal alignments are raised to reduce flooding, extra care is needed to ensure that all drainage channels convey water properly. The contractor must undertake a surface drainage inventory of the future raised road sections, identifying where there will be new culverts or where existing culverts need to be replaced or relocated. This inventory needs to be submitted to the supervising engineer.

4. When modifying the existing drainage system through culvert replacement, the contractor must minimize flood risk by carefully confirming that all works to be undertaken will not flood roadside properties due to improper design or construction practices. The contractor will be required to fully rehabilitate property damaged due to flooding.

2.4.2 Management of contaminated construction wastewater

2.4.2 Where drainage from a construction site involves more than 20 linear meters of roadway, a drainage channel into a grassed area of some detention area allowing an suspended sediment and minor contaminants to settle, must be prepared by the contractor(s).

Complied with.

Not applicable

2.4.3 Fuel storage for generators powering the asphalt plant, aggregate preparation plant, and for vehicles and avoidance of leakage of hazardous materials into surface and

2.4.3 All fuel storage sites must be checked daily for leaks and held in an impervious site where spilled/leaking material can be collected.

Complied with. Had taken measures to prevent oil spills. Without refueling facilities, equipment

Not applicable

Page 45: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

34

Environmental Issue Mitigation Measures

Compliance Status Proposed Corrective Action

groundwater. onsite and vehicle cleaning is not in the construction site, but in the vehicle washing area outside construction site.

2.4.4 Air pollution 2.4.4 TPM, SO2 and NO2 will be monitored once a month. Two samples will be taken (one during the morning traffic peak, and one when construction has stopped for the day) at each of six stations along the road.

Complied with. PM10, SO2 and NO2 were monitored.

Not applicable

2.5 Air and Noise Pollution

2.5.1 Construction-period air pollution

2.5.1 Emissions will be kept to a minimum by: 1. ensuring that the contractor’s fleet of vehicles are

properly maintained according to manufacturers specifications; and

2. use acceptable fuel and haul loads within specified limits.

3. Vehicle idling time limits to no more than 2 minutes and

4. equipment maintenance specifications will be imposed through construction inspection and regular reporting,

5. Dust control at the construction site will be particularly stringently controlled by watering, setting strict speed limits of no more than 30kph in or near settled areas, and sweeping of paved haul roads.

6. Equipment such as the diesel generator will be included in the emission control program and will be and regularly tuned to prevent excessive TPM pollution.

Complied with.

Not applicable

2.5.2 Dust and noise from road milling machine

2.5.2 Due to respirable silica dust from cutter heads, contractor needs to have water spray nozzles on milling machine a) directed at the point of cutting and the drum, one nozzle every 30-40 cm and b) nozzles along the conveyor on both sides every ½ meter. Avg. water flow should be around 24L/min. Alternative is to provide dust masks to all operators and workers supporting the milling operation

Complied with.

Not applicable

2.5.3 Managing dust, noise and drainage associated with earthworks and haul roads.

2..5.3 Mitigation will involve 1. enforcing a speed limit of 30 kph within 500m of any

village and the use of chemical dust suppressants at

Complied with.

Not applicable

Page 46: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

35

Environmental Issue Mitigation Measures

Compliance Status Proposed Corrective Action

least on road for 500m on either side of a village, Same approach is to be taken if the other site is used.

2. restricting operating hours through roadside villages and settlements to between hours of 0800 and 1800.

2.5.4 Excessive Noise 2.5.4 At the same locations and times that surface water quality is tested, noise measurements will be completed, but with site variations focused on sensitive receptors such as schools, residential areas and health care facilities. Measurement frequency will be the same as for air quality

Complied with.

Not applicable

2.6 Flora and Fauna

2.6.1 Protection of roadside trees and shelter belt planting along roadsides

2.6.1 For each section of the road, contractors are required to develop a sketch map of the location number and species of trees along the roadside that are located within the area likely to be cleared. In areas where there are large trees creating a treed/shaded corridor, designers will be contacted and alternative designs, such as narrowing the carriageway and transforming this area into a roadside rest area should be discussed and an option found that requires the minimum tree loss. Any tree removed will be replaced by replanting several (>2) young trees of the same species.

Complied with.

Not applicable

2.6.2 Selection of landscape species and management of arisings

2.6.2 Specify native species of local provenance that are appropriate for the local setting for any new areas of landscaping.

Ensure that any invasive species cleared during landscape works are managed in accordance with PRC regulations and standards.

Consider opportunities for establishing composting facilities at General and Maintenance Sections, to enable recycling of green waste.

Complied with.

Not applicable

2.7 Cultural Sites and Local Communities

2.7.1 Loss of physical cultural resources

2.7.1 Since all the work is within existing RoWs and in previously disturbed soil, the risk of loss of historical or cultural relics is highly unlikely. However when widening roads in villages and towns, contractors will have to meet with local mayor to consult about any possible past relics or foundations of old buildings along the road. Contractor

Not applicable so far.

Not applicable

Page 47: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

36

Environmental Issue Mitigation Measures

Compliance Status Proposed Corrective Action

will also need to consult the database on archaeological sites in Yunnan, retained with the Provincial Cultural Relics Department as well as the County Cultural Relics Bureau. Any finds during works must be reported to the Maintenance Section Head and all construction work stopped until authorities have inspected the site.

2.7.2: Loss of access for roadside residents

2.7.2 Contractor shall provide safe and convenient passage for vehicles and pedestrians to and from side roads and properties connecting the project road/area, whether public or private. Work that affects the use of side roads and existing access shall not be undertaken without provision of adequate alternate routes; to the prior satisfaction of the Engineer and affected persons.

Complied with.

Before construction, a notice had been issued. During the period of limited access, traffic control persons were responsible for directing traffic. On construction sites, public signs were established to provide phone numbers and other information of the IA, supervisors, and constructors.

Not applicable

2.7.3 Traffic/access diversions and road dust management

2.7.3 Temporary bypasses will be constructed with the approval of the Engineer and in consultation with affected persons.

The temporary traffic detours shall be kept free of dust by frequent sweeping or application of water.

Complied with.

Not applicable

2.7.4 Spread of Vector-Born Diseases

2.7.4 Contractors will be required to conduct rigorous inspections of the work sites to be sure that there are no stagnant waters. This will include removal of items such as old tires, drums and other receptacles where water can collect. These are all breeding grounds for malaria, encephalitis and dengue fever mosquitoes.

Complied with.

Not applicable

2.7.5 Community safety 2.7.5 In order to protect the safety of communities on the construction zone contractors will need to provide appropriate traffic management, lighting, management of excavations and making communities aware of any particular hazards.

Complied with.

Not applicable

2.7.6 Hiring locally 2.7.6 Contractors will be encouraged to hire at least unskilled labour locally

Complied with.

Not applicable

2.7.7 Work outside the RoW 2.7.7 Construction activities may, in rare instances, be necessary outside the RoW. Where this becomes necessary, the use of land outside the RoW must be

Not applicable

Not applicable

Page 48: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

37

Environmental Issue Mitigation Measures

Compliance Status Proposed Corrective Action

planned and agreed with owners of the affected land and properties prior to the start of the construction

2.8 Occupational Health And Safety

2.8.1 Protecting the workforce and maintaining a safe working environment

2.8.1 Contractor to implement adequate traffic management measures, including safety cones, marking and use of traffic control personnel to maintain a safe environment for workforce and community.

Contractor must provide safety vests, hard hats and protective footwear for all workers handling heavy materials, and working with caustic and hazardous materials such as concrete, asphalt, paints, cleaning agents, herbicides and pesticides.

Contractor must provide protective masks to milling machine operators, and anyone working in the area of the milling machine dust- with masks of a micron size, capable of capturing dust down to 2 microns.

Contractor must provide high-visibility clothing for workers at sites that have active traffic. Any works at night should be adequately lit and high visibility clothing worn.

The contractor should provide basic training on use of protective clothing and equipment

Complied with. Providing workers with health knowledge. Setting traffic signs on construction site. Community hospitals providing health counseling and disease prevention knowledge to the villagers. Providing safety equipment for construction workers. Traffic control personnel responsible for directing traffic.

Not applicable

2.8.2 Medical facilities and assistance

2.8.2 Contractor must have first aid services available to all staff and workers at all times;

Contractor must have at least one emergency treatment specialist on call at all times and available for emergency treatment as required.

Complied with. Not applicable

2.8.3 Storage, handing and use of toxic and/or hazardous materials

2.8.3 Handling of all caustic, petroleum based materials, and other

hazardous materials, such as pesticides/herbicides and cleaning agents, must be done, wearing protective footwear and clothing and application on steep slopes avoided

Storage of such materials must be protected from the weather, clearly marked and safe from potential tampering and theft. Transport of such materials will be made according to PRC regulations and standards including pre-notification of shipment to local EPB

Complied with. Not applicable

2.8.4 Provision of sanitary toilet facilities

2.8.4Contractor must provide sanitary toilet for all full-time workers on the construction site and make sure it is

Complied with. Not applicable

Page 49: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

38

Environmental Issue Mitigation Measures

Compliance Status Proposed Corrective Action

serviced daily.

2.8.5 Control of movement of large equipment and handling of construction items

2.8.5 Ensure large vehicles have safety equipment such as reverse alarms and assistants are available to provide traffic control and direction when large equipment is moved on the construction site. Demarcate work areas and use traffic cones as needed.

Complied with. Not applicable

2.8.6 Child Labour 2.8.6 No Children (less than 16 year of age ) can work on any contract

Complied with. Not applicable

2.8.7 Records of Safety and Health

2.8.7 The Contractor shall maintain such records and make such reports concerning safety, health, and welfare of persons and damage to property available for inspection as the Engineer may from time to time prescribe

Complied with. Not applicable

2.8.8 Reporting of Accidents 2.8.8 The Contractor shall report to the Engineer details of any accident as soon as possible after its occurrence. In the case of any fatality or serious accident, the Contractor shall, in addition, notify the Engineer immediately by the quickest available means

Not applicable. Not applicable

2.8.9 Provision of Potable Water 2.8.9 The contractor shall provide potable water to all staff working on the worksite and at all times

Complied with. Not applicable

2..8.10 Working into the night and disturbing communities ( see also 2.2.5)

2.8.10 Generally contractors will be restricted to work only during the daylight hours. However consultation and agreement with local communities will allow for modifications. Contractor consultation with subproject corridor communities will be important

Complied with. No construction at night.

Not applicable

3. OPERATING PERIOD

3.1 Increased risk of pedestrian accidents due to improved roads, faster speeds and greater traffic volume

3.1 The project includes a road and community safety programme, which will include various mitigation measures to control traffic speed, reduce hazards and to increase awareness of local communities.

Post-maintenance consultation with local communities is proposed to check that provisions are adequate.

Not yet due. Not applicable

3.2 Diverted traffic damaging roads and endangering communities

3.2 A number of the subprojects parallel toll road and it has been observed that under these conditions, improvements to non tolled roads results in truck traffic shifting to avoid tolls. To prevent that YHAB will install height barriers at both entrances to the affected roads

Not yet due. Not applicable

3.3 Social and community-based enhancements in support of

3.3 YHAB will support financial incentives for transport entities to re-establish public transport services along

Not yet due. Not applicable

Page 50: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

39

Environmental Issue Mitigation Measures

Compliance Status Proposed Corrective Action

positive impacts subproject roads and will monitor roads to assess changes in the provision of public transportation.

Page 51: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

40

Appendix 2 ESSU’s Quarterly Compliance Checklist for Phase II, III and IV Subproject Roads (Reporting period: Q3 and Q4 2017, abstract)

Environmental Issue Applicable

Subproject during this reporting

period

Location Time Frame By whom Implementation status

Implementation

Supervision

By when Measures undertaken during this reporting period

Compliance status and corrective action needed

1. PRECONSTRUCTION PERIOD

1.1

Lack of environmental technical capacity within YHAB and its General and Maintenance Sections in environmental assessment and design, management, supervision and reporting.

Category C Phase IV subproject

Headquarters of the General Sections involved

ESSU will be established prior to loan effectiveness. YHAB training will be completed during detailed design and prior to bidding. Contractor training will be on appointment.

YHAB YHAB Nov 2017 1.1 Confirm that YHAB and Contractor training is carried out during the relevant timescales.

Complied with.

No need corrective action

1.2

Translation of IEE, EMP, contract clauses and other templates for use by General and Maintenance Sections,

Category C Phase IV subproject

As part of 1.1 Workshop will be held in General Sections

Translate during detailed design stage and provide instructions prior to contractor field mobilization. To be determined

ESSU YHAB Nov 2017 1.2

Confirm that Chinese version of IEEs and EMPs are with the General and Maintenance Sections of YHAB

Confirm that bid documents contain environmental clauses tailored to the project conditions as well as a general set

Complied with.

No need corrective action.

1.3

Consideration of IEE/EMP in preparation of the detailed design and bid documents.

Category C Phase IV subproject

NA Before the bid documents for Section 3 and 6 contracts are completed

ESSU YHAB Nov 2017 1.3

Confirm that design and bid documentation reflect IEE and EMP recommendations.

Complied with.

No need corrective action plan

1.4

Optimise design and planning of works to minimise impacts

Category C Phase IV subproject

1. At any locations where mature trees will be cut down

2. At all sites along an existing road

3. N A

Design and implementation planning for subprojects

ESSU, YSRI

YHAB Apr 2017 1.4 Monitor to verify that best practices and environmentally acceptable design elements including engineering methods are used in the engineering design documentation.

Complied with.

No need corrective action plan

Page 52: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

41

Environmental Issue Applicable Subproject during this reporting

period

Location Time Frame By whom Implementation status

Implementation

Supervision

By when Measures undertaken during this reporting period

Compliance status and corrective action needed

1.5

Announcement of subproject with road signs

Category C Phase IV subproject

At both ends (boundaries) of the project

3-4 weeks before the start of work

Maintenance Section

General Section

Mar 2017 1.5

Confirm that the sign has been established and inform local residents to select other alternative routes in time

Complied with.

No need corrective action plan

2. CONSTRUCTION PERIOD

2.1 Preparation of Environmental Documentation

2.1.1

Technical environmental capacity of Contractor to prepare the CEWP and to implement all mitigation and monitoring measures

Category C

Phase III subproject

NA Prior to the start of the construction work.

Contractor ESSU/ YHAB

Apr 2017 2.1.1

Meet with contractor’s environmental expertise and discuss all issues and confirm level of involvement in the job throughout the construction period.

Complied with.

No need corrective action plan

2.2 Soils, Earthworks & Erosion

2.2.1

Management of earthworks transport and Storage procedures, including cleaning; leading to dust and air pollution

Category C

Phase III subproject

Anywhere where there is material moved, earthworks cutting and filling

Throughout the construction period

Contractor ESSU/ YHAB

Through Jul to Dec 2017 2.2.1

During construction inspections, confirm earthworks and dust are being managed, including use of tarpaulins by trucks hauling fine materials, watering and use of chemical suppressants along the haul road sections at villages and that a speed limit of 30 km/per hour is enforced.

Applicable to Category C, only when larger earthworks involved

Complied with.

No need corrective action plan

2.2.2

Erosion control and slope stabilization, risk of land slip and chronic erosion at cuts and water crossings.

Category C

Phase III subproject

Based on an analysis of soil conditions by contractor and consultation with the General Sections hydrology and geotechnical

Throughout the construction period

Contractor ESSU/ YHAB

Through Jul to Dec 2017 2.2.2

Undertake regular inspection to confirm that slope stabilization and standard erosion protection method are being used by the contractor for all work where there is clearing of topsoil, cutting and filling

Complied with.

No need corrective action plan

Page 53: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

42

Environmental Issue Applicable Subproject during this reporting

period

Location Time Frame By whom Implementation status

Implementation

Supervision

By when Measures undertaken during this reporting period

Compliance status and corrective action needed

expertise

2.2.3

Slope slippage and landslide zones left unaddressed

Category C

Phase III subproject

Roadsides Prior to the start of maintenance work in that road section

Contractor ESSU/ YHAB

Through Jul to Dec 2017 2.2.3

Identify landslide, unstable slope areas and inspect on rehabilitation and stabilization

Complied with.

No need corrective action plan

2.2.4

Risk of erosion, landslide and destruction of landscape from side borrow operations

Category C

Phase III subproject

Along any stretches where road will be raised and fill is needed, particularly in areas with long visual distances

Throughout the construction period

Contractor ESSU/ YHAB

Through Jul to Dec 2017 2.2.4

Undertake inspections to determine the type of borrow operations the contractor is applying and ensure that roadside borrowing is not taking place and is always out of the visual field from the road.

Complied with.

No need corrective action plan

2.2.5

Side casting of waste by Contractor degrading down-slope area and blocking/ contaminating water body

Category C

Phase III subproject

On all Project Roads

Throughout construction

Contractor ESSU/ YHAB

Through Jul to Dec 2017 2.2.5

Contractor report on waste materials management and location of any side casting reviewed and inspection completed. If excessive side casting clean up required. An inspection report, including photos must be filed.

Complied with.

No need corrective action plan

2.2.6

Handling of contaminated construction waste materials

Category C

Phase III subproject

Where existing road materials are to be excavated

Throughout construction

Contractor ESSU/ YHAB

Through Jul to Dec 2017 2.2.6

Examine contractor’s reports on the management of contaminated construction materials; follow up by a discussion with local citizens in areas where such issues are likely.

Complied with.

No need corrective action plan

2.2.7

Inappropriate disposal of spoil from construction work leading to contamination

Category C

Phase III subproject

On all Project Roads

Throughout construction

Contractor ESSU/ YHAB

Through Jul to Dec 2017 2.2.7

Contractor prepares a statement indicating disposal method and location for cleared materials.

Complied with.

No need corrective action plan

2.3 Poor Contractor Operating Procedures

2.3.1 Category C All work sites,

construction

During the construction period

Contractor ESSU/ YHAB

Through Jul to Dec 2017 2.3.1.

Complied with.

No need corrective

Page 54: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

43

Environmental Issue Applicable Subproject during this reporting

period

Location Time Frame By whom Implementation status

Implementation

Supervision

By when Measures undertaken during this reporting period

Compliance status and corrective action needed

Failure to adhere to construction related good housekeeping practices, including solid and sanitary waste management

Phase III subproject

maintenance yards and any other areas operated by the contractor and involved in the project

Using a monitoring checklist, confirm that the items as listed in the EMP; Mitigation Measures Table Item 2.1.3 [1-4] are fully implemented.

action plan

2.3.2

Management of bitumen storage, asphalt, sealcoat and concrete production facilities to avoid leakage, dust and air pollution for community in vicinity

Category C

Phase III subproject

At any bitumen storage and heating areas

Throughout the construction period

Contractor ESSU/ YHAB

Through Jul to Dec 2017 2.3.2

Confirm that sighting specification for both asphalt and concrete plants are according to PRC’s Regulation and Specifications, but also that are at least as far away from settlement areas as defined in the mitigation table.

Bitumen storage and handling is done without spillage

Complied with.

No need corrective action plan

2.3.3

Management of petroleum products such as fuel, lubricants and bitumen to avoid spill and contamination.

Category C

Phase III subproject

At any work camps, maintenance yards and any other areas that the contractor uses or subcontractor use during the construction period

Throughout the construction period

Contractor ESSU/ YHAB

Through Jul to Dec 2017 2.3.3

Using the monitoring checklist, the 8 specific spill and contamination prevention measures listed in item 2.3.3 of the Mitigation Table will be assessed and reported on. Any non-compliance will be rectified immediately.

Complied with.

No need corrective action plan

2.3.4

Overloading of construction vehicles leading to damage to existing roads

Category C

Phase III subproject

All materials haul roads

At all times Contractor Maintenance Section

Through Jul to Dec 2017 2.3.4

Contractor to provide waybills—or record book entries of materials hauled as required by Maintenance Section and/or ESSU inspector(s)

Complied with.

No need corrective action plan

2.3.5

No or inadequate consideration for recycling and reuse of construction ‘wastes’ by the contractor

Category C

Phase III subproject

At construction sites were spoils exist

Throughout construction

Contractor Maintenance Section

Through Jul to Dec 2017 2.3.5

The contractor will need to demonstrate that an attempt has been made to reuse, recycle, convert by composting construction wastes

Complied with.

No need corrective action plan

Page 55: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

44

Environmental Issue Applicable Subproject during this reporting

period

Location Time Frame By whom Implementation status

Implementation

Supervision

By when Measures undertaken during this reporting period

Compliance status and corrective action needed

such as asphalt, wooden materials, plant materials and other benign organic matter

2.3.6

Work Duration

Category C

Phase III subproject

All construction sites

Throughout construction

Contractor Maintenance Section

Through Jul to Dec 2017 2.3.6

General or Maintenance section to discuss work duration with selected contractor and urge rapid completion—then track progress based on inspection reports

Complied with.

No need corrective action plan

2.4 Surface Water, Drainage and Water Pollution

2.4.1

Modification of surface drainage during culvert and bridge replacement and/or raising of horizontal road alignment

Category C

Phase III subproject

1. At all existing culvert sites and where new culverts are specified in the design drawings

2. At all bridges which will need widening and repair

3. Along any road sections where vertical alignments are to be raised via the addition of fill material and where the draining system is to be modified.

Throughout the construction period

Contractor ESSU/ YHAB

Through Jul to Dec 2017 2.4.1

The Construction inspector(s) will inspect and verify that adequate drainage works and protection have been provided: specifically that the four mitigation measures defined in 2.4.1 of the Mitigation Table are fully implemented in a timely manner.

Clearing of all culverts, confirming that they have not been blocked with construction materials will be completed

Complied with.

No need corrective action plan

2.4.2

Management of contaminated construction wastewater

Category C

Phase III

All construction sites where silt runoff is

Throughout the construction period

Contractor ESSU/ YHAB

Through Jul to Dec 2017 2.4.2

Inspect large construction sites to verify drainage water management scheme

Complied with.

No need corrective

Page 56: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

45

Environmental Issue Applicable Subproject during this reporting

period

Location Time Frame By whom Implementation status

Implementation

Supervision

By when Measures undertaken during this reporting period

Compliance status and corrective action needed

subproject possible action plan

2.4.3

Fuel storage for generators powering the asphalt plant, aggregate preparation plant, and for vehicles and avoidance of leakage of hazardous materials into surface and groundwater.

Category C

Phase III subproject

All Storage and handling sites

Daily check Contractor ESSU/

YHAB Through Jul to Dec 2017 2.4.3

Request inspection reports from contractor and undertaken spot audits of the asphalt plants and fuel storage sites for any work lasting more than 2 months and requiring on a mobile asphalt plant.

Complied with.

No need corrective action plan

2.5 Air and Noise Pollution

2.5.1

Construction-period air pollution

Category C

Phase III subproject

Anywhere at construction sites where vehicles of the contractor or under the contractors control, such as subcontracted trucks and hauling materials

Throughout the construction period

Contractor ESSU/ YHAB

Through Jul to Dec 2017 2.5.1

Using a monitoring checklist confirm that the six mitigation actions defined in 2.5.1 of the Mitigation Table are being implemented.

Complied with.

No need corrective action plan

2.5.2

Dust and noise from road milling machine

Category C

Phase III subproject

At any site where asphalt milling to take place

Prior to start of any milling work

Contractor ESSU/ YHAB

Through Jul to Dec 2017 2.5.2

Inspect milling machine operations and check for dust suppression and operator masks-

Complied with.

No need corrective action plan

2.5.3

Managing dust, noise and drainage associated with earthworks and haul roads.

Category C

Phase III subproject

1-2. All access roads and haul routes for materials movement, particularly through

Throughout the construction period

Contractor ESSU/ YHAB

Through Jul to Dec 2017 2..5.3

Obtain written confirmation from contractor that the mitigation measures defined are being implemented

Confirm operating period restriction , but consider any agreements made with

Complied with.

No need corrective action plan

Page 57: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

46

Environmental Issue Applicable Subproject during this reporting

period

Location Time Frame By whom Implementation status

Implementation

Supervision

By when Measures undertaken during this reporting period

Compliance status and corrective action needed

settlement areas, villages and towns

communities

2.5.4

Excessive Noise

Category C

Phase III subproject

Two samples will be taken (one during the morning traffic peak, and one when construction has stopped for the day) along each road.

Monthly cycle for 4 subproject roads

Contractor or retained specialist consultant

ESSU/YHAB

Through Jul to Dec 2017 2.5.4

Review noise data provided by contractor and confirm validity

Complied with.

No need corrective action plan

2.5.5

Air pollution

Category C

Phase III subproject

Two samples will be taken (one during the morning traffic peak, and one when construction has stopped for the day) along each road.

Monthly cycle for 4 subproject roads

Contractor or retained specialist consultant

ESSU/YHAB

Through Jul to Dec 2017 2.5.5

Review sampling results and confirm acceptable standards being maintained.

Complied with.

No need corrective action plan

2.6 Flora and Fauna

2.6.1

Protection of roadside trees and shelter belt planting along roadsides

Category C

Phase III subproject

Along any section of the road were trees are encroaching into the area to be cleared for widening

Prior to any clearing taking place

Contractor ESSU/ YHAB

Through Jul to Dec 2017 2.6.1

Inspection of cutting plan and confirmation of consultation with local Forestry Dept., then review and record re-planting/revegetation efforts.

Complied with.

No need corrective action plan

2.6.2

Selection of landscape species and management of arisings

Category C

Phase III

At any site where landscape management

Design During clearance works

Contractor ESSU/YHAB

Through Jul to Dec 2017 2.6.2

Review landscape specifications proposed for subprojects. Review at which General

Complied with.

No need corrective

Page 58: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

47

Environmental Issue Applicable Subproject during this reporting

period

Location Time Frame By whom Implementation status

Implementation

Supervision

By when Measures undertaken during this reporting period

Compliance status and corrective action needed

subproject takes place. Maintenance Sections composting facilities can be established.

action plan

2.7 Cultural Sites and Local Communities

2.7.1

Loss of physical cultural resources

Category C

Phase III subproject

Locally important cultural heritage sites and features, particularly in ethnic minority areas and within 200m of any town or village along a project road.

During the construction period and ahead of excavation at any such site Prior to earth moving in these areas

Contractor ESSU/ YHAB

Through Jul to Dec 2017 2.7.1

Confirm that all roadside cultural and historical sites have been identified and all proper procedures according to PRC regulations have been adhered to.

Complied with.

No need corrective action plan

2.7.2:

Loss of access for roadside residents

Category C

Phase III subproject

Along any project roads—where residences, businesses, etc. lead directly onto road where maintenance is taking place

Prior to the start of any work on each road

Contractor ESSU/ YHAB

Through Jul to Dec 2017 2.7.2

Confirm that contractor(s) has re-established existing road access for roadside residents impacted.

Complied with.

No need corrective action plan

2.7.3 Traffic/access diversions and road dust management

Category C

Phase III subproject

As defined by the YHAB representative on the job

Implemented at start of any work where traffic diversion or access reduction is expected

Contractor ESSU/ YHAB

Through Jul to Dec 2017 2.7.3

Inspect traffic management at diversion sites and time delays and record diversion staff functions

Complied with.

No need corrective action plan

2.7.4

Spread of Vector-Born Diseases

Category C

Phase III subproject

All construction sites, particularly these were excavation has taken place.

Within 5 days of any rain event capable of leaving ponded water. Throughout the construction period.

Contractor ESSU/ YHAB

Through Jul to Dec 2017 2.7.4

Inspect all construction sites where earth removal can lead to ponding of stagnant water, particularly during the rainy season and where construction materials are stored in the open. Request immediate clean up and visual inspection for mosquito larvae.

Complied with.

No need corrective action plan

Page 59: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

48

Environmental Issue Applicable Subproject during this reporting

period

Location Time Frame By whom Implementation status

Implementation

Supervision

By when Measures undertaken during this reporting period

Compliance status and corrective action needed

2.7.5 Community safety

Category C

Phase III subproject

All construction sites involving a larger work area and period of more than or equal to 7 days

Prior to start of a construction activity

Contractor ESSU/ YHAB

Through Jul to Dec 2017

2.7.5

In order to protect the safety of communities on the construction zone contractors will need to provide appropriate traffic management, lighting, management of excavations, making communities aware of any particular hazards.

Complied with.

No need corrective action plan

2.7.6 Hiring locally

Category C

Phase III subproject

For all work contracts

Immediately after contractor mobilization

Contractor YHAB Through Jul to Dec 2017

2.7.6 Obtain written statistics on number of local hires

Complied with.

No need corrective action plan

2.7.7 Work outside the RoW

Category C

Phase III subproject

Communities and/or owners affected

At least 2 weeks prior to start of work

Contractor ESSU Through Jul to Dec 2017

2.7.7 Confirm that consultation and proper steps were taken prior to working outside RoW

Complied with.

No need corrective action plan

2.8 Occupational Health And Safety

2.8.1 Protecting the workforce and maintaining a safe working environment

Category C

Phase III subproject

All work sites All the time Contractor ESSU/ YHAB

Through Jul to Dec 2017 2.8.1

Complete a weekly occupational health and safety inspection reporting on all safety matters defined in Items 2.8.1-2.8.9—using a simple checklist provided—as this form.

Complied with.

No need corrective action plan

2.8.2 Medical facilities and assistance

Category C

Phase III subproject

All construction sites

All the time Contractor ESSU/ YHAB

Through Jul to Dec 2017 2.8.2

See above,

For Category C projects, very small work force and short duration, inputs, return to home each day..

Complied with.

No need corrective action plan

2.8.3 Storage, handing and use of toxic and/or hazardous materials

Category C

Phase III subproject

For all construction operations

At any time during the construction period

Contractor ESSU/ YHAB

Through Jul to Dec 2017 2.8.3

inspection of the storage areas and application sites of toxic materials to be undertaken

Complied with.

No need corrective action plan

2.8.4 Provision of sanitary toilet facilities

Category C

All work sites operated by contractor and

At all times during the construction period

Contractor ESSU/ YHAB

Through Jul to Dec 2017 2.8.4

Complied with.

No need corrective

Page 60: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

49

Environmental Issue Applicable Subproject during this reporting

period

Location Time Frame By whom Implementation status

Implementation

Supervision

By when Measures undertaken during this reporting period

Compliance status and corrective action needed

Phase III subproject

without existing facilities

See above: action plan

2.8.5 Control of movement of large equipment and handling of construction items

Category C

Phase III subproject

The entire construction operation

At all times throughout the construction period

Contractor ESSU/ YHAB

Through Jul to Dec 2017

2.8.5 See above

Complied with.

No need corrective action plan

2.8.6 Child Labour

Category C

Phase III subproject

Everywhere the contractor is involved

At all times Contractor ESSU/ YHAB

Through Jul to Dec 2017

2.8.6 Confirm that child labour is not practiced by examining the labour hire records

Complied with.

No need corrective action plan

2.8.7 Records of Safety and Health

Category C

Phase III subproject

Everywhere the contractor is involved

At all times Contractor ESSU/ YHAB

Through Jul to Dec 2017

2.8.7 See above

Complied with.

No need corrective action plan

2.8.8 Reporting of Accidents

Category C

Phase III subproject

For all work sites

Weekly Contractor ESSU/ YHAB

Through Jul to Dec 2017

See above Complied with.

No need corrective action plan

2.8.9; Provision of Potable Water

Category C

Phase III subproject

All construction sites

All the time Contractor ESSU/ YHAB

Through Jul to Dec 2017 2.8.9

Confirm that this is provided at all times and is accessible to all workers

Complied with.

No need corrective action plan

2..8.10 Working into the night and disturbing communities ( see also 2.2.5)

Category C

Phase III subproject

All construction sites within 500 m of a community or sensitive facility such as hospital or school

All the time Contractor ESSU/YHAB

Through Jul to Dec 2017

2.8.10

Verify that contractor is abiding by working hour restrictions as agreed in contract and with local communities

Complied with.

No need corrective action plan

3. OPERATING PERIOD

3.1 Increased risk of pedestrian accidents due to improved roads, faster speeds and greater traffic volume

Category C

Phase II subproject

In village and towns where the roads will be improved

Planned during the detailed design stage and installed during the construction period then completed at the start of operations

General Section; Maintenance Section

ESSU/ YHAB

Through Jul to Dec 2017 3.1

Inspect urban areas where road has been improved, survey re average speed and define what speed management measures have been

Complied with.

No need corrective action plan

Page 61: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

50

Environmental Issue Applicable Subproject during this reporting

period

Location Time Frame By whom Implementation status

Implementation

Supervision

By when Measures undertaken during this reporting period

Compliance status and corrective action needed

installed.

3.2 Diverted traffic damaging roads and endangering communities

Category C

Phase II subproject

Where the road parallels expressways

Immediately before the improved roadway becomes operational

General Section and ESSU

YHAB Through Jul to Dec 2017

3.2

Confirm construction of the height barriers and report to YHAB

Complied with.

No need corrective action plan

3.3 Social and community-based enhancements in support of positive impacts

Category C

Phase II subproject

Communities where special support provided by YHAB for re-establishing public transport services

Within 6 months of improved road being operational and continuing for 1 year

General Section and ESSU

YHAB Through Jul to Dec 2017 3.3

Conduct the survey as defined in 3.1 and report results in annual operating period report

Complied with.

No need corrective action plan

Page 62: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

51

Appendix 3: Site Photos

Phase III- Section: S202 (270.575-282.875)

Picture A3- 1 Pavement construction Picture A3-2 Ditch construction

Picture A3- 3 Half cross section construction Picture A3-4 Water-spraying

Page 63: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

52

Phase III- Section: S207(28-42)

Picture A3- 5 Construction announcement Picture A3- 6 Maintenance personnel directing traffic

Picture A3- 7 Water-spraying Picture A3-8 Safety signboard

Page 64: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

53

Phase III- Section: G324(2451.5-2484.0)

Picture A3- 9 Completed pavement Picture A3- 10 Completed pavement

Picture A3- 11 Pavement construction site Picture A3- 12 partially completed pavement

Page 65: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

54

Phase III- Section: G320(2745.3-2755.3)

Picture A3- 13 Ditch Picture A3- 14 Safety warning mark

Picture A3- 15 Enclosed ditch t Picture A3- 16 Completed pavement

Page 66: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

55

Phase III- Section: G214(2542+000~2563+000)

Picture A3- 17 Half cross section construction Picture A3- 18 Stockpiled quarry

Picture A3- 19 Onsite Safety Training Picture A3- 20 Consulting hired villagers

Page 67: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

56

Phase III- Section: S303 (47+588~60+588)

Picture A3- 21 Safety warning mark Picture A3- 22 Site Construction

Picture A3- 23 Retaining wall constructed Picture A3- 24 Diverting traffic

Picture A3- 25 Partially completed road Picture A3- 26 Consult roadside villagers

Page 68: 45030-002: Yunnan Sustainable Road Maintenance (Sector) Project · 2018-09-03 · works in Jan 2016; and the subproject ... K38+000) in Wenshan . 1 I. Background and Project Progress

57

Phase III- Section: G323(1609.9-1668.932)

Picture A3- 27 Pavement construction Picture A3- 28 Pavement construction(2)

Picture A3- 29 Pavement construction(3)