Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Environmental Monitoring Report
Project Number: 45030-002 February 2018
PRC: Yunnan Sustainable Road Maintenance
(Sector) Project
Prepared by the Yunnan Highway Administration Bureau for the People’s Republic of China and
the Asian Development Bank
This environmental monitoring report is a document of the borrower. The views expressed herein
do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may
be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Asian Development Bank
PRC-3074: Yunnan Sustainable Road Maintenance
(Sector) Project
The Environmental Monitoring Report
in the Second Half of 2017
For Phase III-Road Maintenance Subproject
Prepared in February 2018
Prepared by the Yunnan Highway Administration Bureau for the Asian Development Bank
i
Table of Contents
TABLE OF CONTENTS I
EXECUTIVE SUMMARY V
I. BACKGROUND AND PROJECT PROGRESS 1
II. REPORT PREPARATION 5
A. Purposes and Objectives 5
B. Policy, Legal, and Administrative Framework 5
C. Report Period 6
D. Scope of Environment Monitoring 6
III IMPLEMENTATION OF EMP 7
A. Detailed design drawings and bidding documents 7
B. Institutional Arrangements 7
C. Construction Supervisors 7
D. Implementation status of the mitigation measures 8
E. Analysis of Environmental Monitoring Results 11
F. Institutional Capacity Building and Training 18
IV. PUBLIC CONSULTATION, INFORMATION DISCLOSURE AND GRIEVANCE
REDRESS MECHANISM 19
A. Public Consultation, Information Disclosure 19
B. Grievance Redress Mechanism (GRM) 25
V. CONCLUSIONS AND SUGGESTIONS 27
Appendices
APPENDIX 1: SUMMARY OF POTENTIAL ENVIRONMENTAL IMPACTS AND THE
MITIGATION MEASURES IMPLEMENTED 28
APPENDIX 2 ESSU’S QUARTERLY COMPLIANCE CHECKLIST FOR PHASE II, III AND
IV SUBPROJECT ROADS (REPORTING PERIOD: Q3 AND Q4 2017, ABSTRACT)
40
APPENDIX 3: SITE PHOTOS 51
List of Figures, Tables and Pictures
Figure 1 Organizational Chart for Supervision of Environmental Protection, Water and Soil
Conservation 8
Figure 2 Procudures of Project GRM 26
Table-1 Road Sections for Maintenance during the Phase III of the Project and Project
Progress 3
Table- 2 Environmental Quality Standards for Surface Water(GB3838-2002) 11
Table- 3 Water Quality Monitoring Results of Phase III Subproject 12
Table- 4 Ambient Air Quality Standard (GB3095-2012) 12
Table- 5 Air Quality Monitoring Results of Phase Phase III Subproject 13
Table- 6 Environmental quality standard for noise (GB3096-2008) 15
Table- 7 Emission standard of environment noise for boundary of construction site
(GB12523-2011) 15
Table- 8 Major Noise Source 15
Table- 9 Noise Monitoring Results of the Environmental Sensitive Receptors Along Phase III
Subproject 16
Table- 10 List of Persons Consulted With 19
CURRENCY EQUIVALENTS
(As of 31 December 2017)
Currency unit – Yuan (CNY) CNY1.00 = $ 0.1542
$1.00 = CNY 6.4832
ABBREVIATIONS
ADB – Asian Development Bank ADB SPS – Asian Development Bank Safeguard Policy Statement 2009 CEWP – Construction Environmental Work Plan CIEE – Consolidated Initial Environmental Examination(i.e. many
subprojects addressed in one IEE) dBA – A measure of audible (the ear) noise EARF – Environmental Assessment and Review Framework EIA – Environmental Impact Assessment EMP – Environmental Management Plan ESSU – Environment, Social and Safety Unit (established within
YHAB) GRM – Grievance Redress Mechanism IEE – Initial Environmental Examination masl – metres above sea level PMO – Project Management Office PRC – People’s Republic of China RP – Resettlement Plan RoW – Right of Way SDAP – Social Development Action Plan subIDFor
m – Sub-identification form, provided in the project’s Operations
Manual summarizing all features for a subproject vpd – Vehicles per day YEPD – Yunnan Environmental Protection Department YHAB – Yunnan Highway Administration Bureau YPDOT – Yunnan Provincial Department of Transportation YSRI – Yunnan Science and Technology Research Institute of
Highways
WEIGHTS AND MEASURES
CO – Carbon monoxide kph – Kilometers per hour mu – Land measurement unit = 666.6m2 NO2 – Nitrate or Nitrogen Dioxide SO2 – Sulphur dioxide
NOTE
In this report, "$" refers to US dollars.
Monitoring Indicators
Water Quality
SS – Suspended substance CODcr – Chemical oxygen demand pH – pH value DO – Dissolved oxygen
Air Quality
PM10 – Inhalable particulate matter (particle size less than 10 microns, harmful to the lungs)
NO2 – Nitrogen dioxide SO2 – Sulfur dioxide
Acoustic Quality
LAeq – equivalent continuous sound level A
This environmental monitoring report is a document of the borrower. The views expressed
herein do not necessarily represent those of Asian Development Bank Board of Directors,
Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms
of use” section of this website.
In preparing any country program or strategy, financing any project, or by making any
designation of or reference to a particular territory or geographic area in this document, the
Asian Development Bank does not intend to make any judgments as to the legal or other status
of any territory or area.
Executive Summary
1. The Yunnan Sustainable Road Maintenance (Sector) Project (the Project) is located
in Yunnan Province in the People’s Republic of China. The Yunnan Department of Transport (YPDOT) is the executing agency and the Yunnan Highway Administration Bureau (YHAB) the implementing agency. The latter manages non-tolled national highways, provincial roads and important county roads in the province. Condition of the network has been deteriorating resulting in a reduced level of service and safety, increased transport costs and environmental degradation.
2. The Project includes four outputs: maintenance of 866.8 km of national, provincial and county roads (Output 1); pilot of performance-based maintenance contracts (Output 2); development of a road asset management system (Output 3); and institutional development to enhance the performance and sustainability of YHAB road maintenance (Output 4). Maintenance activities will be implemented over five years in four Phases. The Project with loan amount of $80 million was approved by ADB on 9 December 2013. The Loan and Project Agreements were signed on 30 May 2014. The loan became effective on 7 August 2014.
3. Currently, only phase III subproject is in implementation. ⚫ Phase I contracts were signed in middle of 2014 and the subproject has been
completed except 2 performance based contracts in maintenance stages; ⚫ Phase II subproject contracts were signed in Dec 2015 and officially started civil
works in Jan 2016; and the subproject was completed and put into operation in first half of 2017;
⚫ Phase III subproject contracts were signed and officially started civil works in Jan~Apr 2017; and the subproject is still in implementation; and
⚫ The Phase IV subproject is under preparation.
4. Phase I , II and III Safeguards compliance. YHAB and the environmental
monitoring reports (EMRs, included in the project quarterly progress reports through
2014~2017) confirmed that none of the Phase I,II and III – road sections involved
resettlement, environmental or indigenous people impacts and therefore Phase I remains category B while Phases II, III, IV remain category C consistent with the project design. This EMR is mainly to report EMP implementation status of Phase III subproject which was the only subproject under implementation during this reporting period.
5. Phase III subproject is classified as environment Category C since it is likely to have
minimal or no adverse environmental impacts. According to the project IEE and EARF (Environmental Assessment and Review Framework), the ESSU is responsible for environmental monitoring. A summary monitoring checklist was prepared (Appendix 2) and used to verify the implementation of each mitigative and monitoring measure defined in the EMP. In addition, during this monitoring period, field onsite sampling and laboratory testing was undertaken by Yunnan Science and Technology Research Institute of Highways (YSRI), the subordinate of the YHAB, albeit not a third party or nationally accredited environmental testing agency (neither mandatory for Category C project monitoring nor required in the EMP). YSRI designated environmental specialists and professional sampling and testing equipment & instruments for this assignment to provide quantitative construction site environmental status information to some extent.
6. The monitoring results indicate that the IAs of phase III subproject, the constructors and construction supervision companies performed their respective duties in accordance with the EMP. During implementation, environmental mitigation measures were carried out to reduce the impacts of construction on the surrounding environment and people’s health to the minimum as possible. They had minimized the pollution and improved local public transport.
vii
Map 1- Project Roads (phase II) -G213, S313 and Two Sections of G320
G213 E’shan~Xinping,72km
S313 Yimeng to Yimeng,57km
G320Dali(Yangbi~Yongping),91km
G320Baoshan (Yaoqiao~Baoshan) 83km
8
Map 2 Project Roads (phase III)
Note: subproject road alignments (292km, 11 sections in total).
Source: YSRI.
Myanmar
Vietnam
Laos
G214
S303
G213
G320
G324
S202
S202
S207
G323
Guangxi
Yunnan
Yunnan
Note: subproject road alignments (125.23km, 6 road sections in five prefectures).
Source: Based on Phase IV Subprojects Screening Result – First Stage Submission, June 2017,YHAB
and YSRI.
Map 3 Project Roads (phase IV)
S235 (K0 + 000 ~ K18 + 000) In Baoshan
S325(K88+035~~K118+035) In Lincang
G324 (K2502 + 830 - K2513 + 658) in Kunming
G248(K582+127—K600+127) in Qujing
S240(K73 + 000 ~ K83 + 400) in Qujing
S242(K0+000 ~K38+000) in Wenshan
1
I. Background and Project Progress
1. The Yunnan Sustainable Road Maintenance Project (the Project) is located in Yunnan Province in the People’s Republic of China. The Yunnan Department of Transport (YPDOT) is the executing agency and the Yunnan Highway Administration Bureau (YHAB) the implementing agency. The latter manages non-tolled national highways, provincial roads and important county roads in the province. Condition of the network has been deteriorating resulting in a reduced level of service and safety, increased transport costs and environmental degradation.
2. The outcome of the Project will be more sustainable management of the local road network in Yunnan. The project aims to: (i) improve the condition of the YHAB road network; (ii) increase the proportion of the YHAB road network receiving maintenance; (iii) strengthen YHAB’s capacity and operational performance; and, (iv)fill the gap between estimated maintenance needs and available resources.
3. The Project includes four outputs: maintenance of 850 km of national, provincial and county roads (Output 1); pilot of performance-based maintenance contracts (Output 2); development of a road asset management system (Output 3); and institutional development to enhance the performance and sustainability of YHAB road maintenance (Output 4). Maintenance activities will be implemented over five years in four Phases. The Project with loan amount of $80 million was approved by ADB on 9 December 2013. The Loan and Project Agreements were signed on 30 May 2014. The loan became effective on 7 August 2014.
4. The Phase I subproject is classified as environment Category B since there will be limited, generally site-specific impacts that are largely reversible and that can be readily addressed through mitigation measures. An Initial Environmental Examination (IEE) and Environmental Management Plan (EMP) had been prepared for Phase I maintenance works, in accordance with ADB Safeguard Policy Statement 2009. Phase I covers 10 road sections, associated with nine subprojects in six prefectures, of a total length of 276 km. Phase I contracts were signed in middle of 2014 and the subproject has been completed except 2 performance based contracts in maintenance stages.
5. Phase II , III and IV subprojects are classified as environment Category C since it
is likely to have minimal or no adverse environmental impacts. The works are confined to maintenance activities within existing RoWs. Much of the work is minor, such as replacement of guard rails, painting of road markings, and repair of potholes. Most roads have sections of pavement replaced and their horizontal alignments raised to reduce flooding. All construction earthwork materials used, including aggregate, quarry rock, concrete, and asphalt are purchased from existing licensed operations located as close as possible to the work areas. No new facilities or access roads are necessary.
6. During Phase II, maintenance is proposed for 4 road sections in 3 prefectures in Yunnan province. The proposed work will be confined to maintenance activities within existing RoWs. Much of the work will be minor, such as replacement of guard rails, painting of road markings, and repair of potholes. Most roads will
2
have sections of pavement replaced and their horizontal alignments raised to reduce flooding. All construction earthwork materials used, including aggregate, quarry rock, concrete, and asphalt will be purchased from existing licensed operations located as close as possible to the work areas. No new facilities or access roads will be necessary. Phase II subprojects contracts were signed in Dec 2015 and officially started civil works in Jan 2016; and the subproject was completed and put into operation in first half of 2017.
7. During Phase III, maintenance is proposed for 11 road sections in 5 prefectures in Yunnan province. The proposed works will be confined to maintenance activities within existing RoWs. Much of the work will be minor, such as replacement of guard rails, painting of road markings, and repair of potholes. Most roads will have sections of pavement (asphalt concrete) replaced and their horizontal alignments raised to reduce flooding. All construction earthworks materials used, including aggregate, quarry rock, concrete, and asphalt will be purchased from existing licensed operations located as close as possible to the work areas. No new facilities or access roads will be necessary. The implementation of all Phase III subproject contracts were signed and officially started civil works in Jan~Apr 2017 and will be completed by the 2nd quarter of 2018, with maintenance periods of 15 months.
8. Table 1 provides details of road sections where maintenance is proposed during Phase II and Phase III subprojects associated with types of maintenance proposed and sub-project progress.
9. The Phase IV subproject is under preparation.
3
Table 1 Road Sections for Maintenance during the Phase II and III of the Project and Project Progress (as of December 2017)
Road No. Sect. No. YHAB Local Area Office
Prefecture Road Class
Width (m) Rehab Length (Km)
Type of Maintenance: Major(Mj), Medium(Md), Minor
(Mi) (%)
Project Progress
Starting date Completed (CNY, 10’000)
Completed(%)
Phase II
S313 1 S313-Yuxi General Section
Yuxi 3 6.5/7.5 57.3 Mj Feb 2016 11,804 100.00
G213 2 G213-Yuxi General Section
Yuxi 3/4 7.5/8 61.56 Mj Feb 2016 12,901 100.00
G320
3 G320-Dali General Section
Dali 2/3 6.5/7.5/8.5 91 Mj 30 Nov 2015 13,687 100.00
4 G320-Baoshan General Section
Baoshan 1/2/3 7.5/8.5/12 83 Md 1 Dec 2015 12,631 100.00
Phase III
S313 1 Section: S202(270.575-282.875)
Qujing 2 11.2 [email protected] 1.1km@12m
12.3 Major
2017.4 2102.76 35.01
G213 2 Section: S202(294.075-312.775)
Qujing 2 [email protected] 2.56km@12m
18.7 Major
G320
3 Section: S202(150-160)
Qujing 3
7.5 m
10 Major
2017.4 1609.95 28.44 4 Section: S207(28-42)
Qujing 3
7 m
14 Major
S313 5 Section: S207(59-70)
Qujing 3
6.5 m
11 Major
4
Road No. Sect. No. YHAB Local Area Office
Prefecture Road Class
Width (m) Rehab Length (Km)
Type of Maintenance: Major(Mj), Medium(Md), Minor
(Mi) (%)
Project Progress
Starting date Completed (CNY, 10’000)
Completed(%)
G213 6 Section: G324(2451.5-2484.0)
Kunming 2
12 m
20 intermediate
2,017.4 3956.91 64.69
G320
7 Section: G320(2745.3-2755.3)
Kunming 3
7.5 m
10 Major
8 Section: G214(2542-2563)
Lincang 2
12 m
21 Major 30.923 0.7
S313 9 Section: S303(47.588-60.588)
Lijiang 3
7 m
13 Major 2017.4 1126.93 47.23
G213 10 Section: G213(1950.2-2053.115)
Kunming 2/3
[email protected] [email protected] 102.915 Major 2017.1.1 20956 100
G320 11 Section: G323(1609.9-1668.932)
Wenshan 3
[email protected] [email protected] 59.032 Major 2017.1.1 3590 34.27
Source: YHAB and the IAs database
5
II. Report Preparation
A. Purposes and Objectives
10. This report aims to investigate, monitor and evaluate the ecology and environment quality alongside the phase III maintenance subproject.
11. Through qualitative and quantitative analysis of the environmental impact of the project during the construction period, the impact scope and extent will be reported to provide a basis for rational construction.
12. According to the impact scope and extent during the construction phase, corresponding
environmental protection measures will be proposed to minimize negative impact caused by the project and well coordinate both development and environmental protection.
13. Emphasize public participation as a complementary to the environmental monitoring,
improve construction management, optimize unity of environmental, social and economic benefits, and provide realistic basis for the project management and environmental management.
B. Policy, Legal, and Administrative Framework
14. For the proposed road maintenance and rehabilitation works associated with this project, the following legislation does:
a) The Environmental Protection Law of PRC (1989), fundamental law; b) Management Directory of EIA Classification for Construction Project (MEP, 2008); c) Regulations on Review and Approval of EIAs for Construction Project (MEP,
2009); d) Regulation on Hierarchical Review and Approval of EIAs for Construction Project
in Yunnan Province (2010), covering management of the whole EIA process; e) Environmental Protection Management Ordinance for Construction Project (1998); f) Environmental Protection Management Regulation for Transport Construction
Project (MOT, 2003); g) Environmental Protection Ordinance of Yunnan Province (2004); h) Notice on Enforcement of Environmental Supervision in Transport Construction
Project (MOT, 2004), covering environmental management for the life cycle of the transport construction project;
i) Water Pollution Prevention Law of PRC (2008) and relevant regulations, mandatory requirements for water pollution prevention and mitigation;
j) Air Pollution Prevention Law of PRC (2000) and relevant regulations, mandatory requirements for air pollution prevention and mitigation;
k) Environmental Noise Pollution Control Law of PRC (1996) and relevant regulations, mandatory requirements for noise pollution prevention and mitigation;
l) Solid Waste Pollution Control Law of PRC (2005) and relevant regulations, mandatory requirements for solid wastes pollution control and recycling;
m) Water and Soil Conservation Law of PRC (2010) and relevant regulations, mandatory requirements for soil erosion control;
n) Land Management Law of PRC (2004); o) Highway Safety Ordinance of PRC (2011); p) Quota for Land Use of Highway Construction Project (Ministry of Construction
combined with Ministry of Land and Resources,1999), regulatory requirements for land acquisition of the highways;
q) Nature Reserve Ordinance of PRC (1994), Ordinance for Scenic Resorts and Historic Sites of PRC (2006);
6
r) Ordinance for Management of Nature Reserves in Yunnan Province (1998), mandatory requirements for conservation of the protected areas;
s) Ordinance for Redress of Public Complaints (the State Council, 2005), Interim Procedures for Public Consultation in EIA (SEPA, 2006), and Environmental Complaints Management Regulation (SEPA, 2006), requirements for EIA public consultation and environmental grievance redress;
t) Notice on Strengthening EIA Management to Control Environmental Risks (SEPA, 2003);
u) Interim Management Regulation for Contingency Plan of Environmental Incidents (MEP, 2010), management requirements for environmental risks control, preparation and implementation of environmental contingency plan;
v) Environmental standards and guidelines, including environmental quality standards for surface water, air, and ambient noise; emission standards for polluting sources of wastewater, air pollutants, and noise; as well as EIA guidelines such as Technical Guideline on EIA published by MEP; and
w) PRC guideline HJ/T169-2004, National Inventory of Hazardous Goods & MEP Dec.1, 2008.
15. Yunnan has a large number of international, national, provincial and local protected
areas. For each Phase, determination of the location of any designated sites in relation to the roads to be maintained will be necessary. The phase III maintenance subproject does not involve any protected areas.
C. Report Period
16. This report, the EMR in 2nd half 2017, focuses on atmosphere, water and acoustic environmental impacts during the construction and various indicators before and during construction are compared.
D. Scope of Environment Monitoring
17. Phase III subprojects is classified as environment Category C since it is likely to have minimal or no adverse environmental impacts. According to the project IEE and EARF (Environmental Assessment and Review Framework), the ESSU is responsible for environmental monitoring. A summary monitoring checklist was prepared (Appendix 2) and used to verify the implementation of each mitigative and monitoring measure defined in the EMP. In addition, during this monitoring period, field onsite sampling and laboratory testing was undertaken by environmental specialists of Yunnan Science and Technology Research Institute of Highways (YSRI), the subordinate of the YHAB, albeit not a third party or nationally accredited environmental testing agency (neither mandatory for Category C project monitoring nor required in the EMP). YSRI designated environmental specialists with professional sampling and testing equipment &instruments for this assignment to provide quantitative construction site environmental status information to some extent. Field onsite sampling and laboratory testing includes: (1) atmosphere environment: within 200m on the two sides of the roads’ centre; (2) noise: within 50m on the two sides of the road center, those nearest to the roads, such as residential areas, buildings, schools, parks, hospitals and other sensitive points; (3) surface water: water quality of the rivers section, nearest to the roads; and (4) ecological environment: the affected land, vegetation, animals and plants along the roads.
7
III Implementation of EMP
A. Detailed design drawings and bidding documents
18. The construction drawings and design documents contains environmental management. The construction precautions list soil and water conservation, ecological protection, water, dust and noise control, human health and safety and environmental protection during the construction should be paid attention to (see construction drawing designs). EMP is also included in the bidding documents. (see the bidding documents)
B. Institutional Arrangements
19. Yunnan Highway Administration Bureau (YHAB), the implementing agency (IA), is responsible for organizing, coordinating and supervising the implementation of these two components. The IAs of phase III subproject had been set up in Dali, Wenshan, Baoshan and Yuxi General Sections, under which, the safeguards departments were responsible for supervision and inspection of safety, occupation health, environmental protection on constructors, ensuring smooth road traffic, as well monitoring major hazards and investigating safety accident. The IAs of phase III subproject formulated the implementation plans of environment protection and water and soil conservation, construction safety and traffic management according to approved EMP and SEPP.
C. Construction Supervisors
20. With good testing equipment and strong technical capacities of construction supervision, the CSCs have undertaken all types (I, II, III) of highway project supervision.
21. The organizational chart for supervision of environmental protection, water and soil
conservation are shown as follows. The EHS personnel composes: a. Chief Construction Supervisor is also the chief of Environmental Protection, Water
and Soil Conservation Department. b. The director of the Chief Construction Supervisor Office is also the EHS engineer in
the Environmental Protection, Water and Soil Conservation Department. c. A full-time EHS engineer is set up in each residential office. And d. The subgrade, pavement, traffic engineering and test supervision engineers in the
residential offices are concurrently environmental protection, water and soil conservation engineers, responsible for supervision and compliance of EMP and SEPP within their work scopes.
8
Figure 1 Organizational Chart for Supervision of Environmental Protection, Water
and Soil Conservation
22. Scope of supervision of environmental protection, water and soil conservation covers the areas directly influenced by the two components, including construction sites of main highway works and temporary works, construction camp, construction access road, borrow pit, disposal site, sand quarry, mixing plant, and other existing local roads bearing a large number of haulage.
23. The construction supervisors developed phase III road maintenance supervision plans,
including contract-specific environmental supervision plans, safety supervision plans, and incorporated detailed guidelines for implementation of construction supervision, environmental protection and soil and water conservation into daily supervision work. Part-time environmental protection engineers were designated to be responsible for inspection on possible environmental impacts and soil and water loss, safety issues, on-site and inspection during the process of main construction process, in order to ensure mitigation measures to be well implemented.
D. Implementation status of the mitigation measures
24. Implementation status of the mitigation measures during this reporting period are summarized in the Appendix 1. The implementation status of the mitigation measures are summarized in the last columns of the tables for comparison with the designed mitigation measures stated in the EMP. In summary, the mitigation measures have to date been implemented effectively.
25. Contractors prepared monthly contract-specific construction environmental work reports to record progress with implementation of the EMP. The ESSU undertook quarterly compliance audits of the YHAB and their contractors in evaluating performance against project environmental indicators in the EMP, and submitted quarterly environmental compliance monitoring reports to the YHAB. The Appendix 2 summarizes the ESSU’s quarterly environmental compliance status by checklist for Phase II, III and IV Subproject
Chief Construction Supervisor Office
Chief Construction Supervisor
EHS engineers, and other professional engineers
Onsite supervisors Logistic personnel
9
Roads (Reporting period: Q3 and Q4 2017, abstract). This semi-annual environmental monitoring report abstracting quarterly environmental compliance audits will be submitted to ADB for uploading on ADB's website after ADB's review and clearance.
26. In accordance with clauses and technical specifications in the construction contracts and
the EMP, corresponding mitigation measures are adopted during construction management. Specific measures are shown as follows (The site photos pls. see the Appendix 3):
i.Water: The construction area does not involve any drinking water source, irrigation water source or other important water body. A little construction waste water was generated, so the impact to the surface water is very minor.
a. The entire construction process does not generate wastewater because the maintenance components were applied with in-situ cold recycling, gradation gravel pavement with warm asphalt, b. On construction sites, no new barrack was built. The phase III subproject IAs, the supervisors and the contractors rented house of local villagers as workplace, with toilet and septic tank. Domestic wastewater and catering wastewater was not directly discharged. c. Equipment maintenance and refueling were undertaken in the fixed places, rather than on the construction sites, which did not permeate into the water body. d. The equipments and vehicles were cleaned up in the vicinity of nearby car washing shops, so the maintenance section did not generate vehicle washing wastewater. e. Drainage ditches were built on both sides of the roads. The construction workers cleaned up the construction waste in a timely manner to ensure smooth drainage.
ii.Air: The impact of the air quality is mainly from smoke, dust and exhaust of
construction machinery and vehicle, etc. Main mitigation measures are shown as below:
a. The constructor was equipped with 7 sprinklers, 4 times a day, and increased to 6 times at construction section near the villages. b. Hauling trucks in bulk materials were covered by canvas as much as possible to reduce the dust during transport. c. A gradation mixing station is located about 1 km away from the construction site, and an asphalt mixing station and a cement mixing station were built together. The asphalt mixing station was equipped with bag dust removing equipments to reduce asphalt smoke emissions. And the cement mixing station was sprayed with a small amount of water in the hopper to reduce dust emissions. No any resident or farmland is located nearby, therefore, the generated dust had little impact to the public.
iii.Noise: Noise pollution at construction stage is mainly caused by the construction
machinery and vehicle hauling activities. The constructor worked from 8:00-18:00 time during daytime, and at night without construction. If at construction section near the villages, construction stopped during 12:00-14:00 to avoid disturbance with the villagers.
iv.Solid waste: During construction period, the earth materials, asphalt, gravel were
piled in the slope less than 5% in the fixed places.
v.Soil erosion. Soil erosion of the component was mainly caused by solid waste, construction waste, leaking oil in case of rain runoff. Main mitigation measures are
10
shown as below: a. Only a small amount of pavement material was used to repair the pavement, so did not need to dispose of solid waste. After in-situ cold recycling, the used asphalt is reused to repair the maintenance section. b. Before daily construction, firstly checking the construction vehicles and machinery status. If any problem, the vehicle was sent to the nearest vehicle repair shop for maintenance. Vehicle was refueled in the refueling station in the vicinity. c. On the construction sites, there was no vehicle maintenance and refueling. d. Renting nearby village houses as a living area and office area, so the garbage generated by the construction workers was collected by the community sanitation department. e. The constructors leased the existing asphalt mixing station, which was set in the abandoned quarries, without any water body or resident nearby. The asphalt spill was also collected and processed in the container. The groundwater was not affected by surface runoff.
vi.Flora and Fauna: Within the scope of construction area, no ancient tree has been
found. The construction sites was limited on the original road, without expansion or no excavation and blasting operations, therefore, it did not affect the roadside farmland and trees.
vii.Health and Safety. Health and safety education is the important content during
construction period. Most construction workers are local villagers. If any illness, they went to local community hospitals for medical treatment. In order to ensure the construction safety and quality, before construction, the constructors conducted safety and skills training for all the staff. Main mitigation measures are shown as below:
a. Worker personal protection. Before construction, all construction workers are trained on use of personal protection equipments. b. At the construction sections, the bulletin boards, safety cones, marking and other warning signs were erected to indicate the project name, project brief introduction, constructors, designers, supervisors, and their telephone numbers. c. Traffic cones were used in the construction area with a designed construction staff in charge of traffic management. d. All workers were provided with protective masks, gloves, safety vest, helmet and protective shoes, etc. On-site construction workers were wearing eye-catching safety vest. e. Renting local village houses as office spaces, equipped with drinking water, life necessities, and clean public toilets. f. Daily supervision and inspection of the construction workers whether safety protection measures were completed, the construction equipments were under normal operation according to standard procedures. Daily or weekly logs of supervision were kept. g. Irregular maintenance on the vehicles and construction machinery. h. Regularly inspecting the cable lines in the construction area to eliminate the safety hazard. And i. Related disease prevention knowledges were frequently posted, such as H7N9 bird flu.
viii.Landscape: The phase III subproject is not within the scope of the scenic area, so
the natural landscape was not significantly impacted. The construction equipment
11
and material was only temporarily stored, will be recovered after completion. Main mitigation measures are shown as below:
a. The village houses were rented as office space and for living. Construction sheds were built along the sides of the road, so the landscape was not affected. b. Rented houses were equipped with garbage pool. The community sanitation management department regularly collected then transported to the landfill for disposal. c. Trucks with bulk materials were covered with canvas in order to keep the vehicle clean and tidy as possible. d. No new path was built to avoid the destruction of land or vegetation. e. Mixing station and material yard were leased with local existing equipment and facilities, and will be recovered after completion. And
ix.Cultural Heritage: No any cultural heritage was found within the scope of at a radius
of 25 km around the construction sites.
E. Analysis of Environmental Monitoring Results
27. During this monitoring period, field onsite sampling and laboratory testing was undertaken by Yunnan Science and Technology Research Institute of Highways (YSRI), the subordinate of the YHAB, albeit not a third party or nationally accredited environmental testing agency (neither mandatory for Category C project monitoring nor required in the EMP). YSRI designated environmental specialists with professional sampling and testing equipment &instruments for this assignment to provide quantitative construction site environmental status information to some extent.
28. Water quality monitoring: Phase III subproject road maintenance involve only one river (Chi’na River), while the other maintenance sections do not involve any river, reservoir or any other surface water body. Chi’na River should meet the Class III standards of Environmental Quality Standards for Surface Water (GB 3838-2002, see Table 2). YSRI conducted on-site sampling and monitoring on Chi’na River. The monitoring results are indicated as follows (see Table 3).
Table- 1 Environmental Quality Standards for Surface Water(GB3838-2002)
Unit:mg/L, except PH dimensionless
No. Item Class III
1 CODCr ≤20
2 pH 6-9
3 DO ≥5.0
4 NH3-N ≤1.0
12
Table- 2 Water Quality Monitoring Results of Phase III Subproject
Unit:mg/L
Sub-components
Monitoring Point
Monitoring Date CODcr pH DO NH3-N SS
Phase III
Section: S202(270.575-282.875)
Chi’na River
Pre-construction Period (24 Aug 2016)
19 8 8 0.2 18
Construction Period (18 Sept. 2017)
15 8 8 0.2 65
Construction Period (21 Nov. 2017)
17 8 8 0.2 76
Class IV, Environmental Quality Standards for Surface Water
(GB3838-2002)
30 6-9 3 1.5
Compliance Status Complied with
29. Evaluation of water quality monitoring results. The monitoring results of the above river show its water quality can meet the classes III of Surface Water Environmental Quality Standards (GB3838-2002). At the same time, it also shows that the water quality during construction of the phase III subproject is no worse than that pre-construction.
30. Air quality monitoring. The main pollutants in the construction period are dust and
asphalt. Along the road, the Class II standard in the Ambient Air Quality Standard "(GB3095 - 2012) should be complied with, as shown in Table 4. YSRI undertook on-site air quality monitoring. The results are as follows (see Table 5).
Table- 3 Ambient Air Quality Standard (GB3095-2012)
Unit:mg/ m3
Item Sampling Period Class II, Standard Limit
PM10 Daily Average 0.15
NO2 Daily Average 0.12
SO2 Daily Average 0.15
13
Table- 4 Air Quality Monitoring Results of Phase III Subproject
Unit: mg/m3
Sub-components Monitoring
Point Indictor PM10 NO2 SO2
Phase III
Section:S202(270.575-
282.875) Tianba town
Construction Period (18 Sept. 2017)
0.1 0.02 0.06
Construction Period (21 Nov. 2017)
0.12 0.02 0.04
Class II 0.15 0.12 0.15
Compliance Status Complied with
Section: S202(150-160) Dadegang village
Pre-construction Period (25 August 2016)
0.11 0.01 0.01
Construction Period (19 Sept. 2017)
0.10 0.01 0.08
Construction Period (22 Nov. 2017)
0.12 0.02 0.06
Class II 0.15 0.12 0.15
Compliance Status Complied with
Section: S207(28-42) Wulong town
Pre-construction Period (26 August 2016)
0.10 0.01 0.01
Construction Period (10 Sept. 2017)
0.09 0.01 0.02
Construction Period (23 Nov. 2017)
0.10 0.03 0.01
Class II 0.15 0.12 0.15
Compliance Status Complied with
Section:G324(2451.5-2484.0) Jiangtou Village
Pre-construction Period (27 July 2016)
0.04 0.01 0.01
Construction Period (21 Sept. 2017)
0.11 0.01 0.01
Construction Period (2 Nov. 2017)
0.11 0.02 0.01
Class II 0.15 0.12 0.15
14
Sub-components Monitoring
Point Indictor PM10 NO2 SO2
Compliance Status Complied with
Section:G320(2745.3-2755.3) Xiaoshao village
Pre-construction Period (30 August 2016)
0.10 0.02 0.01
Construction Period (22 Sept. 2017)
0.07 0.02 0.01
Construction Period (29 Dec. 2017)
0.10 0.01 0.01
Class II 0.15 0.12 0.15
Compliance Status Complied with
Section: G214(2542+000 ~
2563+000) Shaojie village
Construction Period (26 Sept. 2017)
0.09 0.02 0.01
Construction Period (6 Dec. 2017)
0.09 0.01 0.02
Class II 0.15 0.12 0.15
Compliance Status Complied with
Section: S303(47+588 ~
60+588)
Gaozhai village of
Renhe town
Construction Period (29 Sept. 2017)
0.09 0.01 0.02
Construction Period (13 Dec. 2017)
0.10 0.01 0.02
Class II 0.15 0.12 0.15
Compliance Status Complied with
Section:G323(1609.9-
1668.932) Guichao village
Construction Period (6 Sept. 2017)
0.11 0.02 0.01
Construction Period (21 Dec. 2017)
0.13 0.01 0.01
Class II 0.15 0.12 0.15
Compliance Status Complied with
31. Evaluation of air quality monitoring results. The atmospheric impact scope is mainly focused within the 50m near both sides of the RoWs. The construction (road maintenance) period lasted short with very limited impact. From the above data, the air monitoring indicators, PM10, NO2 and SO2, before construction and construction period,
15
had little change and both were better than Class II standard in the Ambient Air Quality Standard "(GB3095 - 2012). It shows that the construction activity has no serious influence on the surrounding air quality after taking effective mitigation measures, such as timely sprinkling water to suppress dust.
32. Noise monitoring: The construction noise has a certain effect on the sound
environment quality, which is mainly caused by the construction machinery and vehicles.
33. For phase III Subproject, the Class 4a standard in the Standards for Acoustic Environmental Quality (GB3096-2008) (see Table 6) should be complied with. During construction phase, Emission Standard of Environment Noise for Boundary of
Construction Site(GB12523-2011(see Table 7) is applicable. The main noise source
during the construction period sees Table 8, and the noise monitoring results are shown in Table 9.
Table- 5 Environmental quality standard for noise (GB3096-2008)
Unit:dB (A)
Acoustic environment functional area
Noise Limit LAeq(dB)
Daytime Nighttime
Class 4a 70 55
1
Table- 6 Emission standard of environment noise for boundary of construction site
(GB12523-2011)
Daytime (LAeq(dB)) Nighttime(LAeq(dB))
70 55
Table- 7 Major Noise Source
Period Major Noise Source
Noise Limit LAeq(dB)
Daytime Nighttime
Construction
Period
All kinds of vehicles 70 55
All kinds of vehicles, concrete mixer, etc. 70 55
Bulldozer, excavator, paver 75 55
16
Table- 8 Noise Monitoring Results of the Environmental Sensitive Receptors Along
Phase III Subproject
Unit: dB (A)
Period/ Sub-components Time Environmental
Sensitive Receptors
Distance to
road center line(m)
LAeq(dB) Compliance
Status Monitoring Value
Standard limit
Phase III
Section:S202(270.575-
282.875)
9:00-17:00, 18 Sept. 2017, Daytime
Yangchang village 15 54 70
Complied with
Xuanwei 4th middle school 30 51 60
Complied with
Shuchang village 20 48 70
Complied with
Tianba town 18 50 70
Complied with
9:00-17:00, 21 Nov. 2017, Daytime
Yangchang village 15 53 70
Complied with
Xuanwei 4th middle school 30 50 60
Complied with
Shuchang village 20 50 70
Complied with
Tianba town 18 51 70
Complied with
Section: S202(150-160) 9:00-17:00, 19 Sept. 2017, Daytime
Dadegang village 5 58 70
Complied with
Xiaodegang village
5 57 70 Complied
with
9:00-17:00, 22 Nov. 2017, Daytime
Dadegang village 5 56 70
Complied with
Xiaodegang village
5 55 70 Complied
with
Section: S207(28-42) 9:00-17:00, 10 Sept. 2017, Daytime
Wulong town 15 56 70 Complied
with
Nanyan village 15 48 70 Complied
with
Lugu village 15 48 70 Complied
with
9:00-17:00, 23 Nov. 2017, Daytime
Wulong town 15 52 70 Complied
with
Nanyan village 15 47 70 Complied
with
Lugu village 15 45 70 Complied
with
Section:G324(2451.5-
2484.0)
9:00-17:00, 21 Sept. 2017, Daytime
Shuijinpo village
20 47 70 Complied
with
Anjiatian village 15 49 70
Complied with
Jiangtou village 15 50 70
Complied with
Baohong village 20 44 70
Complied with
17
Period/ Sub-components Time Environmental
Sensitive Receptors
Distance to
road center line(m)
LAeq(dB) Compliance
Status Monitoring Value
Standard limit
9:00-17:00, 2 Nov. 2017, Daytime
Shuijinpo village
20 50 70 Complied
with
Anjiatian village 15 51 70
Complied with
Jiangtou village 15 49 70
Complied with
Baohong village 20 46 70
Complied with
Section:G320(2745.3-
2755.3)
9:00-17:00, 22 Sept. 2017, Daytime
Songming prison 20 46 70
Complied with
Xiaoshao village 30 43 70
Complied with
9:00-17:00, 29 Dec. 2017, Daytime
Songming prison 20 44 70
Complied with
Xiaoshao village 30 42 70
Complied with
Section: G214 (2542+000~
2563+000)
9:00-17:00, 26 Sept. 2017, Daytime
Xiyi village 20 51 70 Complied
with
Gazhi village 15 45 70 Complied
with
Shaojie village 10 46 60 Complied
with
9:00-17:00, 6 Dec. 2017, Daytime
Xiyi village 20 46 70 Complied
with
Gazhi village 15 45 70 Complied
with
Shaojie village 10 46 60 Complied
with
Section: S303 (47+588 ~
60+588)
9:00-17:00, 29 Sept. 2017, Daytime
Gaozhai village 20 49 70 Complied
with
Hongde village 25 46 70 Complied
with
Akexi village 10 50 60 Complied
with
9:00-17:00, 13 Dec. 2017, Daytime
Gaozhai village 20 45 70 Complied
with
Hongde village 25 43 70 Complied
with
Akexi village 10 52 60 Complied
with
Section:G323(1609.9-
1668.932)
9:00-17:00, 6 Sept. 2017, Daytime
Pingban village 10 46 70 Complied
with
Longmen Village
10 45 70 Complied
with
Guichao school 40 42 60 Complied
with
9:00-17:00, 21 Dec. 2017, Daytime
Pingban
village 10 49 70
Complied with
Longmen
Village 10 47 70
Complied with
Guichao
school 40 44 60
Complied with
18
34. Evaluation of noise monitoring results. 24 representative monitoring points were set along the phase III subproject. The main noise source during construction period is social traffic noise and construction machinery noise. Because construction is prohibited at night, construction machinery noise has little effect on the surrounding residents. All the monitoring result meets national standards.
F. Institutional Capacity Building and Training
35. To strengthen the implementation of the project, an ADB loan PMO was established in the Maintenance Department under YHAB. During the project implementation, the PMO is in charge of overall supervision on technical, quality, environmental, social and safety aspects, and responsible for implementing the environmental protection requirements in the approved EMP, and supervising the contractor's daily environmental mitigation and monitoring and preparing quarterly progress reports.
36. The PMO was led by the deputy director (a senior engineer) of Maintenance Department
under YHAB, and designated a full-time senior engineer and other environmental, social, and safety experts. The Department is responsible for coordination and supervision among the IA, the constructors the CSCs, and supervision and inspection of environmental mitigation measures in the EMP.
37. The PMO, the phase III subproject IAs, CSCs, and the constructors assigned EHS staffs.
38. Before construction, the PMO, the constructors, CSCs, and the relevant departments undertook the relevant training on environmental management plan and road safety.
39. In order for implement the mitigation measures and environmental monitoring, before
entering construction sites and during construction period, ADB's environmental experts/loan implementation environmental consultant/YHAB/phase III subproject IAs provided training related to environmental protection to the CSCs and constructors. The training was mainly focused on implement the mitigation measures and environmental monitoring. Training activities were held in the onsite project management office meeting room. Training activities include the following aspects:
a. Understanding and application of internationally accepted environmental management practices.
b. Compliance monitoring method, required equipment and methods. c. Compliance monitoring information analysis. d. Environmental safeguards enforcement methods and measures. e. Training contents include case studies and field trips.
19
IV. Public Consultation, Information Disclosure and Grievance Redress
Mechanism
A. Public Consultation, Information Disclosure
40. During Jul. to Dec. 2017, YSRI carried out two rounds of public opinion survey to the public along the phase III subproject. The below questions asked are as follows: (i) Do you think there is any impact of the noise and dust generated during construction on your production and life? (ii) During the construction period, is there any influence on your trip due to traffic control? (iii) Any impact on your farmland and crops during the construction period? (iv)How do you think the constructors to take measures to mitigate environmental pollution? (v) Should overloading vehicles be controlled?
41. A total of 146 villagers/residents alongside the along the phase III subproject were
consulted, including 43 women or 36 ethnic minorities, as shown in the below Table 10. The main feedback is as follows:
a) The residents expressed support for the maintenance program and hoped that good road conditions could give their jobs, more conveniences, and more opportunities to improve the quality of life.
b) The residents hoped to repair the road as soon as possible, and the poor road conditions lasted for many years and have brought a lot of adverse effects to their work and life, such as rainy days and dust.
c) It is desirable to have the opportunity to participate in construction activities or to provide other services to increase economic income.
d) The respondents thought that pollution was minor during the construction period, and the duration was short and acceptable.
e) Hoped to help solve some practical problems (such as drainage, safety, etc.). All the above comments and recommendations (especially for the above (e)) have been passed to YHAB/IAs/contractors.
Table- 9 List of Persons Consulted With
No. Name Gender Minorities Profession Name of Village
Phase III
Section: S202(270.575-282.875) ,18 Sept. 2017
1 Konɡ Yɑhuɑ Female Han Villager
Wenhe village, Haidai Town
2 Zhɑnɡ Qionɡhuɑ Female Yi Driver
Shiba village, Haidai Town
3 Dinɡ Henɡhui Male Han Villager
Jijie village, Banqiao Town
4 He Dɑoqiɑnɡ Male Han Repairman
Yueliangtian village, Haidai Town
5 Konɡ Chunyɑn Female Han Villager
Shuchang village, Haidai
20
No. Name Gender Minorities Profession Name of Village
Town
6 Mo Yunpin Male Han Driver
Jichang village, Yangchang Town
7 Li Jixiɑn Female Han Driver
Dasongshu village, Yangchang Town
8 Sun Yinɡhe Male Han Businessman Luosuo village
9 Zhɑo Yonɡtuɑn Male Han Lorry driver Mide village
10 Huɑnɡ Meifen Female Han Gas Station Staff Tiɑnba town
Section: S202(270.575-282.875) ,30 Dec. 2017
1 Zhɑnɡ Decɑi Male Han Shop owner Haidai Town
2 Luo Guifen Female Han Villager Tiɑnba town
3 Konɡ Weimou Male Han Villager Shuchang village, Haidai Town
4 Wɑnɡ Xiɑofenɡ Female Han Villager Luosuo village
5 Xu Xinɡe Female Han Shop owner Mide village
6 Zhou Chenɡfɑ Male Han Driver Xiaoqu Village
7 Zhu Shun Male Han Villager
Xiaoqu Village
8 Qiɑn Li Female Han Villager
Mide village
9 Chen Yun Male Han Doctor Jichang village, Yangchang Town
10 Wɑnɡ Xinɡ Male Han Villager Qingshui village
Section: S202(150-160) , 19 Sept. 2017
1 Cui Zhipinɡ Male Han Villager Dagɑnɡde village
2 Mɑ Bɑoqiɑnɡ Male Hui Shop owner Dagɑnɡde village
3 Mɑ Li Female Hui Shop owner Dagɑnɡde village
4 Shi Zulonɡ Male Han Shop owner Dagɑnɡde village
5 Li Zhufen Female Han Villager Xiɑogɑnɡde village
6 Yɑnɡ Linɡfen Female Yi Villager Xiɑogɑnɡde village
7 Cɑo Xiɑohuɑn Female Han Villager Xiɑogɑnɡde village
8 Zhɑnɡ Qiɑnɡ Male Han Villager Xiɑogɑnɡde village
21
No. Name Gender Minorities Profession Name of Village
9 Zhenɡ Shɑoyonɡ Male Han Businessman Meijiabei village
10 Niɑn Degui Male Han Worker Meijiabei village
Section: S207(28-42), 10 Sept. 2017
1 Wɑnɡ Qiɑofu Male Zhuang Villager Shuaizhai Village, Goujie town
2 Xionɡ Jinyonɡ Male Zhuang Villager Guiche Village, Goujie town
3 Donɡ Xiɑohonɡ Male Zhuang Villager Nanyan Village
4 He Lihui Male Zhuang Villager Nanyan Village
5 Liu Yɑnshenɡ Male Han Villager Bayda Village
6 Yuɑn Shuliɑnɡ Male Han Businessman Sanheyin Village
7 Liu Xiɑoliɑnɡ Male Zhuang Villager Hongbeng Village
8 Chen Shɑnlin Male Han Driver Luopinɡ county
Section: S207(28-42), 14 Dec. 2017
1 Liɑnɡ Jiɑshenɡ Male Han Villager Banjiang Street, Wulong Township
2 Xionɡ Jinyonɡ Male Zhuɑnɡ Villager Guiche Village, Goujie town
3 Donɡ Xiɑohonɡ Male Zhuɑnɡ Villager Guiche Village, Goujie town
4 Zhɑnɡ Decɑi Male Han Villager Naxia Village, Gaoliang town , Shizong county
5 He Lihui Male Zhuɑnɡ Villager Nanyan Village
6 Fu Shichɑo Male Han Villager Sheli village
7 Yuɑn Shuliɑnɡ Male Han Shopper Sanheyin Village
8 Mr. Wang Male Han Villager Guiche Village, Goujie town
9 Wɑnɡ Qinɡsonɡ Male Han Driver Shizong county
Section: G324(2451.5-2484.0) , 21 Sept. 2017
1 Gɑo Yɑninɡ Male Han Hotel owner Goujie town
2 Chen Honɡgɑnɡ Male Han Villager Relongtan village , Muxing Community
3 Sun Xutɑo Male Han Worker Yiliang Gas Station
4 You Yupinɡ Male Han Worker Xinchen Gas Station
5 Huɑnɡ Yuɑnlin Male Han Businessman Dahoubu village
22
No. Name Gender Minorities Profession Name of Village
6 Li Hɑiquɑn Male Han Villager Qixing village
7 Xu Ronɡgui Male Han Villager Tangjiawan village
8 Xionɡ Jiɑnlin Male Han Villager Qixing village
9 Bi Mɑoxiɑnɡ Male Han Businessman Qingshan village
10 Mɑ Conɡan Male Han Villager Qixing village
11 Li Cuizhen Female Yi Villager Xiaohoubu village
Section: G324(2451.5-2484.0) , 30 Dec. 2017
1 Li Fenɡmei Female Han Villager Qingshan Village
2 Xu Qinɡdenɡ Male Han Businessman Qingshan Village
3 Bi Mɑoxiɑnɡ Male Han Villager Qingshan Village
4 Tiɑn Peiyun Male Han Businessman Qingshan Village
5 Mɑ Zhonɡlu Male Han Villager Qixing village
6 Xu Ronɡgui Male Han Villager Tangjiawan village
7 Donɡ Gɑohui Male Han Businessman Qixing village
8 Ruɑn Xuebin Male Han Villager Relongtan village
9 Honɡ Yonɡ Male Han Villager Xiaodoukou village
10 He Zhonɡyun Male Han Villager Xiaodoukou village
Section: G320(2745.3-2755.3) , 22 Sept. 2017
1 Tɑn Zhonɡchun Female Han Villager Xinnong village
2 Li ancestor Female Han Villager Xinnong village
3 Huɑnɡ Yunxiɑnɡ Female Han Villager Bajia villages
4 Yɑnɡ Jiyinɡ Female Han Villager Xinnong village
5 Bi Guihuɑ Female Han Villager Xinnong village
6 Jin Huifen Female Han Villager Suomeiao Village
7 Zhu Honɡshun Male Han Villager Suomeiao Village
8 Shen Zhonɡhonɡ Male Han Villager Xinnong village
9 Zhou Bɑofen Female Han Villager Xiaoshao village
23
No. Name Gender Minorities Profession Name of Village
10 Yɑnɡ Yonɡhe Male Han Villager Xiaoshao village
Section: G320(2745.3-2755.3) , 30 Dec. 2017
1 Hu Yushenɡ Male Han Villager Xiaoshao village
2 Zhu Ronɡ Male Han Villager Xiaoshao village
3 Zhɑo Wenjiɑo Female Han Villager Xiaoshao village
4 Zhou Zilonɡ Male Han Villager Xiaoshao village
5 Tɑn Luxiɑn Female Han Villager Xinnong village
6 Mɑo Yunyonɡ Male Han Villager Xinnong village
7 Jiɑnɡ Yun Male Han Villager Xinnong village
8 Shen Ronɡxinɡ Male Han Villager Xinnong village
9 Shen Zhonɡyou Male Han Villager Xinnong village
10 Zhɑnɡ Yuhui Female Han Villager Xinnong village
Section: G214(2542-2563), 26 Sept. 2017
1 Chɑ Zhuɑnɡ Male Yi Villager Shaojiezhong village
2 Chɑ Chunchenɡ Male Yi Villager Shaojie village
3 Yɑnɡ Chenɡlin Male Han Villager Shaojiezhong village
4 Shi Guogui Male Yi Villager Shaojieshang village
5 Yɑnɡ Shidiɑn Male Han Villager Shaojieshang village
6 Chɑ Xuewɑnɡ Male Yi Villager Dujia village
7 Wɑnɡ Shɑoyinɡ Male Han Villager Sanjia Village
8 Xu Xuediɑn Male Han Villager Xiyi Village
9 Shi Yuɑnyɑo Male Han Villager Yongbao village
10 Pu Xinɡhui Female Yi Villager Yanzitou Village
Section: G214(2542-2563), 27 Dec. 2017
1 Luo Kɑihe Male Yi Villager Banahe Village
2 Luo Yuronɡ Male Yi Villager Banahe Village
3 Luo Yuren Male Yi Villager Banahe Village
24
No. Name Gender Minorities Profession Name of Village
4 Chɑ Jun Male Yi Villager Dujia village
5 Li Wenbin Male Yi Villager Dujia village
6 Li Wenchɑnɡ Male Yi Villager Dujia village
7 Shi Guoxiu Female Yi Villager Shaojiezhong village
8 Zi Honɡxiu Female Yi Villager Shaojieshang village
9 Zi Guohuɑ Female Yi Villager Haizi village
10 Xiɑ Fenɡ Male Han Villager Minɡzishɑn village
Section: S303(47.588-60.588), 29 Sept. 2017
1 Chen Chunwu Male Han Villager Shangping Village, , Renhe Town
2 Wɑnɡ Fuxiɑnɡ Male Han Villager Shangping Village, , Renhe Town
3 Wɑnɡ Fuliɑn Female Han Villager Longtan village, Renhe Town
4 Luo Shunyinɡ Female Han Villager Xiaobingxi Village
5 Zhɑo Youyɑn Female Han Villager Xiaobingxi Village
6 Yɑnɡ Jinmei Female Han Villager Dabingxi Village
7 Guo Fenɡxiɑn Female Han Villager Dabingxi Village
8 Wɑnɡ Yunkun Female Han Villager Xiaping Village, , Renhe Town
9 Wɑnɡ Yunfen Female Han Villager Xiaping Village, , Renhe Town
10 Wɑnɡ Yinyuɑn Male Han Villager Longtan village, Renhe Town
Section: S303(47.588-60.588),29 Dec. 2017
1 Liu Guofu Male Han Villager Shangping Village
2 Liu Guozhonɡ Male Han Villager Xiaobingxi Village
3 Ni Ronɡcɑn Male Han Villager Shangping Village
4 Guɑn Kouxiɑnɡ Male Han Villager Shangping Village
5 Shɑ Guyun Male Susu Villager Xiaobingxi Village
6 Zhou Xinɡhɑi Male Han Villager Xiaobingxi Village
7 Yɑnɡ Wenhui Female in the first place
Villager Xiaobingxi Village
8 Wɑnɡ Fuxiɑnɡ Male Han Villager Shangping Village
25
No. Name Gender Minorities Profession Name of Village
9 Chen Chunwu Male Han Villager Shangping Village
10 Zhɑo Youyɑn Femal
e Han Villager Xiaobingxi Village
Section: G323(1609.9-1668.932), 6 Sept. 2017
1 Zhɑnɡ Zhenbo Male Han Villager Guichao town
2 Liu Honɡ Female Han Villager Guichao town
3 Xu Xiɑopɑn Female Han Villager Guichao town
4 Liɑnɡ Chɑnɡchenɡ Male Yao Villager Guichao town
5 Zhɑnɡ Guoqinɡ Male Han Villager Guichao town
6 Yɑnɡ Jiɑshun Male Yao Villager Guichao town
7 Mɑ Lili Female Han Worker Funinɡ county
Section: G323(1609.9-1668.932), 29 Dec. 2017
1 Quɑn Shimei Female Miao Villager Longmen village
2 Xionɡ Lizhi Female Miao Villager Longmen village
3 Xie Qinwei Male Yi Villager Longmen village
4 He Yunkun Male Han Villager Longmen village
5 Huɑnɡ Shɑojin Male Yao Villager Feiluo village
6 Wei Guɑnɡchenɡ Male Yao Villager Feiluo village
7 Xie Penɡ Male Han Villager Feiluo village
8 Luo Yuɑnpenɡ Male Han Villager Lonɡpang village
9 Zhɑnɡ Jiɑn Male Han Villager Lonɡpang village
10 Liɑnɡ Yonɡzhɑo Male Han Villager Lonɡpang village
B. Grievance Redress Mechanism (GRM)
42. YHAB established environmental GRM, and publicized the relevant information, such as phones numbers, etc.
43. During construction, the constructors and the relevant village committees have not
received any complaint on environmental protection or safety issue.
44. The procedures of GRM are shown as below.
26
Figure 2 Procudures of Project GRM
45. The basic grievance redress steps are described below and shown in Figure 4. The ESSU will be responsible for facilitating, tracking and reporting grievance resolution at each step:
Step 1: The affected person should first try to resolve the issue of concern directly with the contractor and the local village committee. A solution must be presented within five days. If successful, no further follow-up is required.
Step 2: If there is no resolution the person can file the grievance with the county office of YHAB, the Maintenance Section or the Prefecture level Office the General Section. A resolution must be reached within two weeks
Step 3: If no resolution is found the complainant can take the next step and contact
the county or prefecture government offices where resolution will be required within two weeks.
Resolve issue with
contractor or village
committee
STEP 1
STEP 2
Resolve issue with
YHAB Maintenance or
General Section
Resolve issue with
Prefecture Government
STEP 3
5 days
2 weeks
2 weeks
ESSU to
facilitate
and track
resolution
and report
to ADB
27
V. Conclusions and Suggestions
46. During construction, the phase III subproject IAs, the constructors and CSCs had taken the corresponding environmental impact mitigation measures in the EMP. The construction noise, dust and wastewater, and other impacts on the surrounding environment were reduced to a minimum.
47. Through field inspection, the constructors strengthened environmental protection, water
conservation, safety and other aspects according to relevant national environmental protection laws and regulations, ADB's SPS (2009) and the EMP. No land acquisition, demolition, road widening, occupation of farmland and other resettlement issue were identified. The environmental impacts of the component during the construction period were limited, and the construction period was short. With the completion of the component, the pollution will be eliminated in time, and the environment will revert to the state better than the original. From the point of view of the whole process of construction, the constructors strictly abided by the provisions, actively took mitigation measures to reduce pollution. So it obtained the strong support of the local community and the village. Through carrying out public consultation, the local residents were satisfied with the Project. During this period, no any pollution complaint did occur.
48. Suggestions: (i) Local villagers were hired, and their mobility was frequent. To address their
potential safety issue, it is recommended that safety and environmental protection awareness education should be carried out to improve safety and environmental awareness of the villagers and construction workers then to reduce environmental pollution and ecological damage. And (ii) More frequently watering at the sections nearby the villages and towns is recommended to reduce dust from construction.
28
Appendix 1: Summary of Potential Environmental Impacts and the Mitigation Measures Implemented
(As of December 2017)
Environmental Issue Mitigation Measures
Compliance Status Proposed Corrective Action
1. PRECONSTRUCTION PERIOD
1.1 Lack of environmental technical capacity within YHAB and its General and Maintenance Sections in environmental assessment and design, management, supervision and reporting.
1.1 YHAB will establish a unit, the ESSU, to manage environmental, social and safety aspects of maintenance projects. The ESSU will be staffed by 3 full-time suitably qualified people. ADB will support international and national environmental consultancy services to develop and deliver a 5-day environmental assessment and management training workshop for YHAB staff and a 2-day workshop for first year Contractors.
Complied with. ESSU was established prior to loan effectiveness. YHAB training was completed during detailed design and prior to bidding. Contractor training was undertaken on appointment.
Not applicable
1.2 Translation of IEE, EMP, contract clauses and other templates for use by General and Maintenance Sections,
1.2 ESSU will provide the design team with translated copies of IEE, EMP and templates and check relevant clauses have been included.
YHAB/ESSU will provide the successful contractor with translated copies of IEE/EMP and assist contractor to prepare the Construction Environmental Work Plan (CEWP).
General Section will provide the Maintenance Section site engineer with the IEE, EMP and other templates for use in their inspection process. Given the uncertainty of inspection qualifications , the workshops as defined above will be held at the six General Section offices
Complied with or to be complied with. Translated during detailed design stage and provided instructions prior to contractor field mobilization. As part of the above item 1.1, workshops were held in Dali, Wenshan, Yuxi, Baoshan, Qujing, Kunming, Lincang, and Lijiang prefecture General Sections.
Not applicable
1.3 Consideration of IEE/EMP in preparation of the detailed design and bid documents.
1.3 ESSU will check that design and bid documents are responsive to key environmental, social and safety considerations.
Complied with.
Not applicable
1.4 Optimise design and planning of works to minimise impacts
1.4 During detailed design YHAB will incorporate mitigation measures defined in the IEE as follows:: 1. minimize the removal of mature trees from roadsides; 2. optimise traffic management to minimise access
restrictions
Complied with.
Not applicable
29
Environmental Issue Mitigation Measures
Compliance Status Proposed Corrective Action
3. provide step-by-step guidance on environmentally acceptable bridge and culvert replacement methods
1.5 Announcement of subproject with road signs
1.5 Four weeks before work begins announce the project on roadside sign(s), at a location(s) easily accessible by the public. Signs should be presented in a language that can be understood by affected people, in Yunnan, there may be a need to provide signs in multiple languages.
At the same time, provide information on the construction activity via the Maintenance Section
Complied with. At both ends (boundaries) of the project. 3-4 weeks before the start of work
Not applicable
2. CONSTRUCTION PERIOD
2.1 Preparation of Environmental Documentation
2.1.1 Technical environmental capacity of Contractor to prepare the CEWP and to implement all mitigation and monitoring measures
2.1.1 Contractor team will include a specialist with environmental assessment experience to prepare the CEWP and obtain all relevant permits. The contractor will not be permitted to mobilize the workers without an approved CEWP and the appropriate permits in place.
Complied with. Prior to the start of the construction work.
Not applicable
2.2 Soils, Earthworks & Erosion
2.2.1 Management of earthworks transport and Storage procedures, including cleaning; leading to dust and air pollution
2.2.1 Large volumes of crushed quarry rock, aggregate and sand may be transported to and/or stored in the work site. These operations and storage areas will be constantly exposed to the elements and will create primarily dust during the frequent windy conditions, and some silty runoff.
Dust will be managed by daily use of watering trucks, subject to availability of water.
All topsoil needs to be collected, stored and reused to rehabilitate/revegetate the areas disturbed. This is applicable only to projects with IEEs
Complied with. Construction roads were enclosed with colored fence. Hauling vehicles were not overloaded, and covered with waterproof canvas. The constructors sprayed water with sprinklers at 2 times a day. In the vicinity of the villages and the schools, the frequencies of watering were increased.
Not applicable
2.2.2 Erosion control and slope stabilization, risk of land slip and chronic erosion at cuts and water crossings.
2.2.2 Contractor will be required to know the subsoil materials that are being cut into and excavated and have ready appropriate plans to stop land slippage and erosion,. At water crossings where structures are to be upgraded, careful replacement and use of gabions with culverts and bioengineering methods for rapid
Complied with. Based on an analysis of soil conditions by contractor and consultation with the General Sections’ hydrology and geotechnical
Not applicable
30
Environmental Issue Mitigation Measures
Compliance Status Proposed Corrective Action
revegetation and slope stabilization will be used. Bioengineering approaches to be explored as described in Annex D.
experts, construction activities were limited on the original road, without building a new road.
2.2.3 Slope slippage and landslide zones left unaddressed
2.2.3 In any road sections where maintenance takes place and where there is a history of landslides and slope slippage, the contractor will be required to report any such conditions (if not already known) to the Maintenance Section and propose a costed remedial action, then undertake this work to stabilize the road and reduce risk of failure; including bioengineering solutions, metal netting and other proven methods.
Not applicable. Not applicable
2.2.4 Risk of erosion, landslide and destruction of landscape from side borrow operations
2.2.4 Any need for borrow material outside of the RoW will be subject to local environmental approvals and procedures and should also be carried out in consultation with ADB. Bioengineering approaches should be considered.
Not applicable. No borrow pit is required.
Not applicable
2.2.5 Side casting of waste by Contractor degrading down-slope area and blocking/ contaminating water body
2.2.5 Side casting of waste earthen materials is not permitted where slope is more than 5% and a side cast waste materials cannot be easily stabilized and prevented from eroding during a rain event, or extend outside the road RoW.
Complied with. No waste dumping.
Not applicable
2.2.6 Handling of contaminated construction waste materials
2.2.6 When encountering contaminated materials or it is a construction waste, contractors will follow PRC national and provincial requirements, consulting with EPBs if needed
Complied with.
Not applicable
2.2.7 Inappropriate disposal of spoil from construction work leading to contamination
2.2.7 Contractors will be required to: a) attempt to recycle all clean spoils material where possible and b) consider composting or b) dispose of all other material at sites approved by the local EPB.
Complied with. No soil dumping.
Not applicable
2.3 Poor Contractor Operating Procedures
2.3.1 Failure to adhere to construction related good housekeeping practices, including solid and sanitary waste management
2.3.1 Contractors will adhere to standard good housekeeping practices as defined in the contract Terms & Conditions and Contract Specifications. Special considerations will be given to 1. management of construction waste and water 2. equipment lubricants and fuel, including management
and collection of waste oils and fuel particularly
Complied with. Solid waste was collected in certain places and transported regularly. Renting nearby farmers’ houses.
Not applicable
31
Environmental Issue Mitigation Measures
Compliance Status Proposed Corrective Action
related to refuelling depots, maintenance areas and diesel generator sets
3. Sewage will require latrines or chemical toilets with complete clean up after the construction is complete.
4. Garbage will be collected and properly disposed of after recycling and sorting,
This work will be completed in accordance with PRC, regulations and standards which the contractor will be expected to know. Also, the contractor shall orient all construction workers in basic sanitation and health care issues, and on the specific hazards of their work and will need to certify to that effect at the start of the construction period. 5. Once the site is no longer needed the contractor must
fully decommission it, with special emphasis on waste removal and clean up of any spills or hazardous materials plus any necessary revegetation.
Septic tank was equipped with. Fecal sewage and catering wastewater were discharged separately. Not affecting surface water.
2.3.2 Management of bitumen storage, asphalt, sealcoat and concrete production facilities to avoid leakage, dust and air pollution for community in vicinity
2.3.2 YHAB has indicated that no new facilities will be needed, but
for smaller jobs bitumen will be stored at the worksites. Under these conditions, the contractor will be required to provide secure locations for storage, handing and safe disposal of any worksite bitumen supplies. PRC’s hazardous materials handling regulations ( as defined in IEE, Section II) will be adhered to.
Complied with.
Not applicable
2.3.3 Management of petroleum products such as fuel, lubricants and bitumen to avoid spill and contamination.
2.3.3 Contractor will be required to have the following spill prevention measures in place at all work sites: 1. all fuelling to be done on a concrete surface provided
with spill catch surfaces that can be cleaned and all spilled fuel recovered and recycled based on discussions with fuel supplier.
2. All repair and maintenance work must either be done on a concrete surface with oil spill catch basin or oil catch pans must be provided at all service areas and training provided to all ‘mechanics’.
3. All fuel use areas where spills and leakage is possible, e.g. the generator, must have drip basins installed to prevent any leakage. These recovered materials must be recycled.
Complied with.
Not applicable
32
Environmental Issue Mitigation Measures
Compliance Status Proposed Corrective Action
4. A fuelling areas must be equipped with proper non-drip fuel nozzles
5. All fuel tanks must have means for containment of accidental spills.
6. All bitumen handling must not permit any material from leaking to the ground, including transfer areas and any areas where bitumen is transported in drums.
7. Bitumen drums must be stored in a dry covered secure place where no leakage to water or ground is possible. Drums must be recycled at least once a year.
8. Any spills must be cleaned up and contaminated soils and water treated according to PRC regulations and standards within 24 hours of the occurrence.
2.3.4 Overloading of construction vehicles leading to damage to existing roads
2.3.4 The tonnage of material hauled must not exceed the road capacity. If the material mobilization causes damage of the road, then contractor must repair it immediately.
Complied with. No overloading in all materials hauling roads.
Not applicable
2.3.5 No or inadequate consideration for recycling and reuse of construction ‘wastes’ by the contractor
2.3.5 The contractor will need to demonstrate that an attempt has been made to reuse, recycle, convert by composting construction wastes such as asphalt, wooden materials, plant materials and other benign organic matter
Complied with.
Not applicable
2.3.6 Work Duration 2.3.6 Contractors will be encouraged to complete the work as quickly as possible, consulting with local communities on best timing and agreeing to such a timetable
Complied with.
Not applicable
2.4 Surface Water, Drainage and Water Pollution
2.4.1 Modification of surface drainage during culvert and bridge replacement and/or raising of horizontal road alignment
2.4.1 When modifying or interfering with surface drainage of any sort the contract will have to undertake the following: 1. All culverts must be sized at or larger than the one
being replaced and with care about slope and erosion protection at inflow and outflow. All construction materials at the entrance of culverts must be removed so as not to provide any obstruction. Culvert removal and replacement will be done when there are low flows or no water in the channel and during the dry months of the year. Confirm culverts are clear of
Complied with. No bridge or culvert involved. Drainage ditch built. Well maintenance to keep smooth.
Not applicable
33
Environmental Issue Mitigation Measures
Compliance Status Proposed Corrective Action
debris on completion. 2. Bridges will be repaired and widened and as such
there will be machinery at least at the water edge. Maximum care is needed to avoid degradation of the river, stream shore and to undertake excessive excavation at the shore and in the water (at least not when there is water in the stream). Demolition must be done in a way that prevents large chunks of material from falling into the river. Stabilization of disturbed crossing banks must take place as part of the construction work and include filter fabric, gabions and preferably bioengineering techniques.
3. Where horizontal alignments are raised to reduce flooding, extra care is needed to ensure that all drainage channels convey water properly. The contractor must undertake a surface drainage inventory of the future raised road sections, identifying where there will be new culverts or where existing culverts need to be replaced or relocated. This inventory needs to be submitted to the supervising engineer.
4. When modifying the existing drainage system through culvert replacement, the contractor must minimize flood risk by carefully confirming that all works to be undertaken will not flood roadside properties due to improper design or construction practices. The contractor will be required to fully rehabilitate property damaged due to flooding.
2.4.2 Management of contaminated construction wastewater
2.4.2 Where drainage from a construction site involves more than 20 linear meters of roadway, a drainage channel into a grassed area of some detention area allowing an suspended sediment and minor contaminants to settle, must be prepared by the contractor(s).
Complied with.
Not applicable
2.4.3 Fuel storage for generators powering the asphalt plant, aggregate preparation plant, and for vehicles and avoidance of leakage of hazardous materials into surface and
2.4.3 All fuel storage sites must be checked daily for leaks and held in an impervious site where spilled/leaking material can be collected.
Complied with. Had taken measures to prevent oil spills. Without refueling facilities, equipment
Not applicable
34
Environmental Issue Mitigation Measures
Compliance Status Proposed Corrective Action
groundwater. onsite and vehicle cleaning is not in the construction site, but in the vehicle washing area outside construction site.
2.4.4 Air pollution 2.4.4 TPM, SO2 and NO2 will be monitored once a month. Two samples will be taken (one during the morning traffic peak, and one when construction has stopped for the day) at each of six stations along the road.
Complied with. PM10, SO2 and NO2 were monitored.
Not applicable
2.5 Air and Noise Pollution
2.5.1 Construction-period air pollution
2.5.1 Emissions will be kept to a minimum by: 1. ensuring that the contractor’s fleet of vehicles are
properly maintained according to manufacturers specifications; and
2. use acceptable fuel and haul loads within specified limits.
3. Vehicle idling time limits to no more than 2 minutes and
4. equipment maintenance specifications will be imposed through construction inspection and regular reporting,
5. Dust control at the construction site will be particularly stringently controlled by watering, setting strict speed limits of no more than 30kph in or near settled areas, and sweeping of paved haul roads.
6. Equipment such as the diesel generator will be included in the emission control program and will be and regularly tuned to prevent excessive TPM pollution.
Complied with.
Not applicable
2.5.2 Dust and noise from road milling machine
2.5.2 Due to respirable silica dust from cutter heads, contractor needs to have water spray nozzles on milling machine a) directed at the point of cutting and the drum, one nozzle every 30-40 cm and b) nozzles along the conveyor on both sides every ½ meter. Avg. water flow should be around 24L/min. Alternative is to provide dust masks to all operators and workers supporting the milling operation
Complied with.
Not applicable
2.5.3 Managing dust, noise and drainage associated with earthworks and haul roads.
2..5.3 Mitigation will involve 1. enforcing a speed limit of 30 kph within 500m of any
village and the use of chemical dust suppressants at
Complied with.
Not applicable
35
Environmental Issue Mitigation Measures
Compliance Status Proposed Corrective Action
least on road for 500m on either side of a village, Same approach is to be taken if the other site is used.
2. restricting operating hours through roadside villages and settlements to between hours of 0800 and 1800.
2.5.4 Excessive Noise 2.5.4 At the same locations and times that surface water quality is tested, noise measurements will be completed, but with site variations focused on sensitive receptors such as schools, residential areas and health care facilities. Measurement frequency will be the same as for air quality
Complied with.
Not applicable
2.6 Flora and Fauna
2.6.1 Protection of roadside trees and shelter belt planting along roadsides
2.6.1 For each section of the road, contractors are required to develop a sketch map of the location number and species of trees along the roadside that are located within the area likely to be cleared. In areas where there are large trees creating a treed/shaded corridor, designers will be contacted and alternative designs, such as narrowing the carriageway and transforming this area into a roadside rest area should be discussed and an option found that requires the minimum tree loss. Any tree removed will be replaced by replanting several (>2) young trees of the same species.
Complied with.
Not applicable
2.6.2 Selection of landscape species and management of arisings
2.6.2 Specify native species of local provenance that are appropriate for the local setting for any new areas of landscaping.
Ensure that any invasive species cleared during landscape works are managed in accordance with PRC regulations and standards.
Consider opportunities for establishing composting facilities at General and Maintenance Sections, to enable recycling of green waste.
Complied with.
Not applicable
2.7 Cultural Sites and Local Communities
2.7.1 Loss of physical cultural resources
2.7.1 Since all the work is within existing RoWs and in previously disturbed soil, the risk of loss of historical or cultural relics is highly unlikely. However when widening roads in villages and towns, contractors will have to meet with local mayor to consult about any possible past relics or foundations of old buildings along the road. Contractor
Not applicable so far.
Not applicable
36
Environmental Issue Mitigation Measures
Compliance Status Proposed Corrective Action
will also need to consult the database on archaeological sites in Yunnan, retained with the Provincial Cultural Relics Department as well as the County Cultural Relics Bureau. Any finds during works must be reported to the Maintenance Section Head and all construction work stopped until authorities have inspected the site.
2.7.2: Loss of access for roadside residents
2.7.2 Contractor shall provide safe and convenient passage for vehicles and pedestrians to and from side roads and properties connecting the project road/area, whether public or private. Work that affects the use of side roads and existing access shall not be undertaken without provision of adequate alternate routes; to the prior satisfaction of the Engineer and affected persons.
Complied with.
Before construction, a notice had been issued. During the period of limited access, traffic control persons were responsible for directing traffic. On construction sites, public signs were established to provide phone numbers and other information of the IA, supervisors, and constructors.
Not applicable
2.7.3 Traffic/access diversions and road dust management
2.7.3 Temporary bypasses will be constructed with the approval of the Engineer and in consultation with affected persons.
The temporary traffic detours shall be kept free of dust by frequent sweeping or application of water.
Complied with.
Not applicable
2.7.4 Spread of Vector-Born Diseases
2.7.4 Contractors will be required to conduct rigorous inspections of the work sites to be sure that there are no stagnant waters. This will include removal of items such as old tires, drums and other receptacles where water can collect. These are all breeding grounds for malaria, encephalitis and dengue fever mosquitoes.
Complied with.
Not applicable
2.7.5 Community safety 2.7.5 In order to protect the safety of communities on the construction zone contractors will need to provide appropriate traffic management, lighting, management of excavations and making communities aware of any particular hazards.
Complied with.
Not applicable
2.7.6 Hiring locally 2.7.6 Contractors will be encouraged to hire at least unskilled labour locally
Complied with.
Not applicable
2.7.7 Work outside the RoW 2.7.7 Construction activities may, in rare instances, be necessary outside the RoW. Where this becomes necessary, the use of land outside the RoW must be
Not applicable
Not applicable
37
Environmental Issue Mitigation Measures
Compliance Status Proposed Corrective Action
planned and agreed with owners of the affected land and properties prior to the start of the construction
2.8 Occupational Health And Safety
2.8.1 Protecting the workforce and maintaining a safe working environment
2.8.1 Contractor to implement adequate traffic management measures, including safety cones, marking and use of traffic control personnel to maintain a safe environment for workforce and community.
Contractor must provide safety vests, hard hats and protective footwear for all workers handling heavy materials, and working with caustic and hazardous materials such as concrete, asphalt, paints, cleaning agents, herbicides and pesticides.
Contractor must provide protective masks to milling machine operators, and anyone working in the area of the milling machine dust- with masks of a micron size, capable of capturing dust down to 2 microns.
Contractor must provide high-visibility clothing for workers at sites that have active traffic. Any works at night should be adequately lit and high visibility clothing worn.
The contractor should provide basic training on use of protective clothing and equipment
Complied with. Providing workers with health knowledge. Setting traffic signs on construction site. Community hospitals providing health counseling and disease prevention knowledge to the villagers. Providing safety equipment for construction workers. Traffic control personnel responsible for directing traffic.
Not applicable
2.8.2 Medical facilities and assistance
2.8.2 Contractor must have first aid services available to all staff and workers at all times;
Contractor must have at least one emergency treatment specialist on call at all times and available for emergency treatment as required.
Complied with. Not applicable
2.8.3 Storage, handing and use of toxic and/or hazardous materials
2.8.3 Handling of all caustic, petroleum based materials, and other
hazardous materials, such as pesticides/herbicides and cleaning agents, must be done, wearing protective footwear and clothing and application on steep slopes avoided
Storage of such materials must be protected from the weather, clearly marked and safe from potential tampering and theft. Transport of such materials will be made according to PRC regulations and standards including pre-notification of shipment to local EPB
Complied with. Not applicable
2.8.4 Provision of sanitary toilet facilities
2.8.4Contractor must provide sanitary toilet for all full-time workers on the construction site and make sure it is
Complied with. Not applicable
38
Environmental Issue Mitigation Measures
Compliance Status Proposed Corrective Action
serviced daily.
2.8.5 Control of movement of large equipment and handling of construction items
2.8.5 Ensure large vehicles have safety equipment such as reverse alarms and assistants are available to provide traffic control and direction when large equipment is moved on the construction site. Demarcate work areas and use traffic cones as needed.
Complied with. Not applicable
2.8.6 Child Labour 2.8.6 No Children (less than 16 year of age ) can work on any contract
Complied with. Not applicable
2.8.7 Records of Safety and Health
2.8.7 The Contractor shall maintain such records and make such reports concerning safety, health, and welfare of persons and damage to property available for inspection as the Engineer may from time to time prescribe
Complied with. Not applicable
2.8.8 Reporting of Accidents 2.8.8 The Contractor shall report to the Engineer details of any accident as soon as possible after its occurrence. In the case of any fatality or serious accident, the Contractor shall, in addition, notify the Engineer immediately by the quickest available means
Not applicable. Not applicable
2.8.9 Provision of Potable Water 2.8.9 The contractor shall provide potable water to all staff working on the worksite and at all times
Complied with. Not applicable
2..8.10 Working into the night and disturbing communities ( see also 2.2.5)
2.8.10 Generally contractors will be restricted to work only during the daylight hours. However consultation and agreement with local communities will allow for modifications. Contractor consultation with subproject corridor communities will be important
Complied with. No construction at night.
Not applicable
3. OPERATING PERIOD
3.1 Increased risk of pedestrian accidents due to improved roads, faster speeds and greater traffic volume
3.1 The project includes a road and community safety programme, which will include various mitigation measures to control traffic speed, reduce hazards and to increase awareness of local communities.
Post-maintenance consultation with local communities is proposed to check that provisions are adequate.
Not yet due. Not applicable
3.2 Diverted traffic damaging roads and endangering communities
3.2 A number of the subprojects parallel toll road and it has been observed that under these conditions, improvements to non tolled roads results in truck traffic shifting to avoid tolls. To prevent that YHAB will install height barriers at both entrances to the affected roads
Not yet due. Not applicable
3.3 Social and community-based enhancements in support of
3.3 YHAB will support financial incentives for transport entities to re-establish public transport services along
Not yet due. Not applicable
39
Environmental Issue Mitigation Measures
Compliance Status Proposed Corrective Action
positive impacts subproject roads and will monitor roads to assess changes in the provision of public transportation.
40
Appendix 2 ESSU’s Quarterly Compliance Checklist for Phase II, III and IV Subproject Roads (Reporting period: Q3 and Q4 2017, abstract)
Environmental Issue Applicable
Subproject during this reporting
period
Location Time Frame By whom Implementation status
Implementation
Supervision
By when Measures undertaken during this reporting period
Compliance status and corrective action needed
1. PRECONSTRUCTION PERIOD
1.1
Lack of environmental technical capacity within YHAB and its General and Maintenance Sections in environmental assessment and design, management, supervision and reporting.
Category C Phase IV subproject
Headquarters of the General Sections involved
ESSU will be established prior to loan effectiveness. YHAB training will be completed during detailed design and prior to bidding. Contractor training will be on appointment.
YHAB YHAB Nov 2017 1.1 Confirm that YHAB and Contractor training is carried out during the relevant timescales.
Complied with.
No need corrective action
1.2
Translation of IEE, EMP, contract clauses and other templates for use by General and Maintenance Sections,
Category C Phase IV subproject
As part of 1.1 Workshop will be held in General Sections
Translate during detailed design stage and provide instructions prior to contractor field mobilization. To be determined
ESSU YHAB Nov 2017 1.2
Confirm that Chinese version of IEEs and EMPs are with the General and Maintenance Sections of YHAB
Confirm that bid documents contain environmental clauses tailored to the project conditions as well as a general set
Complied with.
No need corrective action.
1.3
Consideration of IEE/EMP in preparation of the detailed design and bid documents.
Category C Phase IV subproject
NA Before the bid documents for Section 3 and 6 contracts are completed
ESSU YHAB Nov 2017 1.3
Confirm that design and bid documentation reflect IEE and EMP recommendations.
Complied with.
No need corrective action plan
1.4
Optimise design and planning of works to minimise impacts
Category C Phase IV subproject
1. At any locations where mature trees will be cut down
2. At all sites along an existing road
3. N A
Design and implementation planning for subprojects
ESSU, YSRI
YHAB Apr 2017 1.4 Monitor to verify that best practices and environmentally acceptable design elements including engineering methods are used in the engineering design documentation.
Complied with.
No need corrective action plan
41
Environmental Issue Applicable Subproject during this reporting
period
Location Time Frame By whom Implementation status
Implementation
Supervision
By when Measures undertaken during this reporting period
Compliance status and corrective action needed
1.5
Announcement of subproject with road signs
Category C Phase IV subproject
At both ends (boundaries) of the project
3-4 weeks before the start of work
Maintenance Section
General Section
Mar 2017 1.5
Confirm that the sign has been established and inform local residents to select other alternative routes in time
Complied with.
No need corrective action plan
2. CONSTRUCTION PERIOD
2.1 Preparation of Environmental Documentation
2.1.1
Technical environmental capacity of Contractor to prepare the CEWP and to implement all mitigation and monitoring measures
Category C
Phase III subproject
NA Prior to the start of the construction work.
Contractor ESSU/ YHAB
Apr 2017 2.1.1
Meet with contractor’s environmental expertise and discuss all issues and confirm level of involvement in the job throughout the construction period.
Complied with.
No need corrective action plan
2.2 Soils, Earthworks & Erosion
2.2.1
Management of earthworks transport and Storage procedures, including cleaning; leading to dust and air pollution
Category C
Phase III subproject
Anywhere where there is material moved, earthworks cutting and filling
Throughout the construction period
Contractor ESSU/ YHAB
Through Jul to Dec 2017 2.2.1
During construction inspections, confirm earthworks and dust are being managed, including use of tarpaulins by trucks hauling fine materials, watering and use of chemical suppressants along the haul road sections at villages and that a speed limit of 30 km/per hour is enforced.
Applicable to Category C, only when larger earthworks involved
Complied with.
No need corrective action plan
2.2.2
Erosion control and slope stabilization, risk of land slip and chronic erosion at cuts and water crossings.
Category C
Phase III subproject
Based on an analysis of soil conditions by contractor and consultation with the General Sections hydrology and geotechnical
Throughout the construction period
Contractor ESSU/ YHAB
Through Jul to Dec 2017 2.2.2
Undertake regular inspection to confirm that slope stabilization and standard erosion protection method are being used by the contractor for all work where there is clearing of topsoil, cutting and filling
Complied with.
No need corrective action plan
42
Environmental Issue Applicable Subproject during this reporting
period
Location Time Frame By whom Implementation status
Implementation
Supervision
By when Measures undertaken during this reporting period
Compliance status and corrective action needed
expertise
2.2.3
Slope slippage and landslide zones left unaddressed
Category C
Phase III subproject
Roadsides Prior to the start of maintenance work in that road section
Contractor ESSU/ YHAB
Through Jul to Dec 2017 2.2.3
Identify landslide, unstable slope areas and inspect on rehabilitation and stabilization
Complied with.
No need corrective action plan
2.2.4
Risk of erosion, landslide and destruction of landscape from side borrow operations
Category C
Phase III subproject
Along any stretches where road will be raised and fill is needed, particularly in areas with long visual distances
Throughout the construction period
Contractor ESSU/ YHAB
Through Jul to Dec 2017 2.2.4
Undertake inspections to determine the type of borrow operations the contractor is applying and ensure that roadside borrowing is not taking place and is always out of the visual field from the road.
Complied with.
No need corrective action plan
2.2.5
Side casting of waste by Contractor degrading down-slope area and blocking/ contaminating water body
Category C
Phase III subproject
On all Project Roads
Throughout construction
Contractor ESSU/ YHAB
Through Jul to Dec 2017 2.2.5
Contractor report on waste materials management and location of any side casting reviewed and inspection completed. If excessive side casting clean up required. An inspection report, including photos must be filed.
Complied with.
No need corrective action plan
2.2.6
Handling of contaminated construction waste materials
Category C
Phase III subproject
Where existing road materials are to be excavated
Throughout construction
Contractor ESSU/ YHAB
Through Jul to Dec 2017 2.2.6
Examine contractor’s reports on the management of contaminated construction materials; follow up by a discussion with local citizens in areas where such issues are likely.
Complied with.
No need corrective action plan
2.2.7
Inappropriate disposal of spoil from construction work leading to contamination
Category C
Phase III subproject
On all Project Roads
Throughout construction
Contractor ESSU/ YHAB
Through Jul to Dec 2017 2.2.7
Contractor prepares a statement indicating disposal method and location for cleared materials.
Complied with.
No need corrective action plan
2.3 Poor Contractor Operating Procedures
2.3.1 Category C All work sites,
construction
During the construction period
Contractor ESSU/ YHAB
Through Jul to Dec 2017 2.3.1.
Complied with.
No need corrective
43
Environmental Issue Applicable Subproject during this reporting
period
Location Time Frame By whom Implementation status
Implementation
Supervision
By when Measures undertaken during this reporting period
Compliance status and corrective action needed
Failure to adhere to construction related good housekeeping practices, including solid and sanitary waste management
Phase III subproject
maintenance yards and any other areas operated by the contractor and involved in the project
Using a monitoring checklist, confirm that the items as listed in the EMP; Mitigation Measures Table Item 2.1.3 [1-4] are fully implemented.
action plan
2.3.2
Management of bitumen storage, asphalt, sealcoat and concrete production facilities to avoid leakage, dust and air pollution for community in vicinity
Category C
Phase III subproject
At any bitumen storage and heating areas
Throughout the construction period
Contractor ESSU/ YHAB
Through Jul to Dec 2017 2.3.2
Confirm that sighting specification for both asphalt and concrete plants are according to PRC’s Regulation and Specifications, but also that are at least as far away from settlement areas as defined in the mitigation table.
Bitumen storage and handling is done without spillage
Complied with.
No need corrective action plan
2.3.3
Management of petroleum products such as fuel, lubricants and bitumen to avoid spill and contamination.
Category C
Phase III subproject
At any work camps, maintenance yards and any other areas that the contractor uses or subcontractor use during the construction period
Throughout the construction period
Contractor ESSU/ YHAB
Through Jul to Dec 2017 2.3.3
Using the monitoring checklist, the 8 specific spill and contamination prevention measures listed in item 2.3.3 of the Mitigation Table will be assessed and reported on. Any non-compliance will be rectified immediately.
Complied with.
No need corrective action plan
2.3.4
Overloading of construction vehicles leading to damage to existing roads
Category C
Phase III subproject
All materials haul roads
At all times Contractor Maintenance Section
Through Jul to Dec 2017 2.3.4
Contractor to provide waybills—or record book entries of materials hauled as required by Maintenance Section and/or ESSU inspector(s)
Complied with.
No need corrective action plan
2.3.5
No or inadequate consideration for recycling and reuse of construction ‘wastes’ by the contractor
Category C
Phase III subproject
At construction sites were spoils exist
Throughout construction
Contractor Maintenance Section
Through Jul to Dec 2017 2.3.5
The contractor will need to demonstrate that an attempt has been made to reuse, recycle, convert by composting construction wastes
Complied with.
No need corrective action plan
44
Environmental Issue Applicable Subproject during this reporting
period
Location Time Frame By whom Implementation status
Implementation
Supervision
By when Measures undertaken during this reporting period
Compliance status and corrective action needed
such as asphalt, wooden materials, plant materials and other benign organic matter
2.3.6
Work Duration
Category C
Phase III subproject
All construction sites
Throughout construction
Contractor Maintenance Section
Through Jul to Dec 2017 2.3.6
General or Maintenance section to discuss work duration with selected contractor and urge rapid completion—then track progress based on inspection reports
Complied with.
No need corrective action plan
2.4 Surface Water, Drainage and Water Pollution
2.4.1
Modification of surface drainage during culvert and bridge replacement and/or raising of horizontal road alignment
Category C
Phase III subproject
1. At all existing culvert sites and where new culverts are specified in the design drawings
2. At all bridges which will need widening and repair
3. Along any road sections where vertical alignments are to be raised via the addition of fill material and where the draining system is to be modified.
Throughout the construction period
Contractor ESSU/ YHAB
Through Jul to Dec 2017 2.4.1
The Construction inspector(s) will inspect and verify that adequate drainage works and protection have been provided: specifically that the four mitigation measures defined in 2.4.1 of the Mitigation Table are fully implemented in a timely manner.
Clearing of all culverts, confirming that they have not been blocked with construction materials will be completed
Complied with.
No need corrective action plan
2.4.2
Management of contaminated construction wastewater
Category C
Phase III
All construction sites where silt runoff is
Throughout the construction period
Contractor ESSU/ YHAB
Through Jul to Dec 2017 2.4.2
Inspect large construction sites to verify drainage water management scheme
Complied with.
No need corrective
45
Environmental Issue Applicable Subproject during this reporting
period
Location Time Frame By whom Implementation status
Implementation
Supervision
By when Measures undertaken during this reporting period
Compliance status and corrective action needed
subproject possible action plan
2.4.3
Fuel storage for generators powering the asphalt plant, aggregate preparation plant, and for vehicles and avoidance of leakage of hazardous materials into surface and groundwater.
Category C
Phase III subproject
All Storage and handling sites
Daily check Contractor ESSU/
YHAB Through Jul to Dec 2017 2.4.3
Request inspection reports from contractor and undertaken spot audits of the asphalt plants and fuel storage sites for any work lasting more than 2 months and requiring on a mobile asphalt plant.
Complied with.
No need corrective action plan
2.5 Air and Noise Pollution
2.5.1
Construction-period air pollution
Category C
Phase III subproject
Anywhere at construction sites where vehicles of the contractor or under the contractors control, such as subcontracted trucks and hauling materials
Throughout the construction period
Contractor ESSU/ YHAB
Through Jul to Dec 2017 2.5.1
Using a monitoring checklist confirm that the six mitigation actions defined in 2.5.1 of the Mitigation Table are being implemented.
Complied with.
No need corrective action plan
2.5.2
Dust and noise from road milling machine
Category C
Phase III subproject
At any site where asphalt milling to take place
Prior to start of any milling work
Contractor ESSU/ YHAB
Through Jul to Dec 2017 2.5.2
Inspect milling machine operations and check for dust suppression and operator masks-
Complied with.
No need corrective action plan
2.5.3
Managing dust, noise and drainage associated with earthworks and haul roads.
Category C
Phase III subproject
1-2. All access roads and haul routes for materials movement, particularly through
Throughout the construction period
Contractor ESSU/ YHAB
Through Jul to Dec 2017 2..5.3
Obtain written confirmation from contractor that the mitigation measures defined are being implemented
Confirm operating period restriction , but consider any agreements made with
Complied with.
No need corrective action plan
46
Environmental Issue Applicable Subproject during this reporting
period
Location Time Frame By whom Implementation status
Implementation
Supervision
By when Measures undertaken during this reporting period
Compliance status and corrective action needed
settlement areas, villages and towns
communities
2.5.4
Excessive Noise
Category C
Phase III subproject
Two samples will be taken (one during the morning traffic peak, and one when construction has stopped for the day) along each road.
Monthly cycle for 4 subproject roads
Contractor or retained specialist consultant
ESSU/YHAB
Through Jul to Dec 2017 2.5.4
Review noise data provided by contractor and confirm validity
Complied with.
No need corrective action plan
2.5.5
Air pollution
Category C
Phase III subproject
Two samples will be taken (one during the morning traffic peak, and one when construction has stopped for the day) along each road.
Monthly cycle for 4 subproject roads
Contractor or retained specialist consultant
ESSU/YHAB
Through Jul to Dec 2017 2.5.5
Review sampling results and confirm acceptable standards being maintained.
Complied with.
No need corrective action plan
2.6 Flora and Fauna
2.6.1
Protection of roadside trees and shelter belt planting along roadsides
Category C
Phase III subproject
Along any section of the road were trees are encroaching into the area to be cleared for widening
Prior to any clearing taking place
Contractor ESSU/ YHAB
Through Jul to Dec 2017 2.6.1
Inspection of cutting plan and confirmation of consultation with local Forestry Dept., then review and record re-planting/revegetation efforts.
Complied with.
No need corrective action plan
2.6.2
Selection of landscape species and management of arisings
Category C
Phase III
At any site where landscape management
Design During clearance works
Contractor ESSU/YHAB
Through Jul to Dec 2017 2.6.2
Review landscape specifications proposed for subprojects. Review at which General
Complied with.
No need corrective
47
Environmental Issue Applicable Subproject during this reporting
period
Location Time Frame By whom Implementation status
Implementation
Supervision
By when Measures undertaken during this reporting period
Compliance status and corrective action needed
subproject takes place. Maintenance Sections composting facilities can be established.
action plan
2.7 Cultural Sites and Local Communities
2.7.1
Loss of physical cultural resources
Category C
Phase III subproject
Locally important cultural heritage sites and features, particularly in ethnic minority areas and within 200m of any town or village along a project road.
During the construction period and ahead of excavation at any such site Prior to earth moving in these areas
Contractor ESSU/ YHAB
Through Jul to Dec 2017 2.7.1
Confirm that all roadside cultural and historical sites have been identified and all proper procedures according to PRC regulations have been adhered to.
Complied with.
No need corrective action plan
2.7.2:
Loss of access for roadside residents
Category C
Phase III subproject
Along any project roads—where residences, businesses, etc. lead directly onto road where maintenance is taking place
Prior to the start of any work on each road
Contractor ESSU/ YHAB
Through Jul to Dec 2017 2.7.2
Confirm that contractor(s) has re-established existing road access for roadside residents impacted.
Complied with.
No need corrective action plan
2.7.3 Traffic/access diversions and road dust management
Category C
Phase III subproject
As defined by the YHAB representative on the job
Implemented at start of any work where traffic diversion or access reduction is expected
Contractor ESSU/ YHAB
Through Jul to Dec 2017 2.7.3
Inspect traffic management at diversion sites and time delays and record diversion staff functions
Complied with.
No need corrective action plan
2.7.4
Spread of Vector-Born Diseases
Category C
Phase III subproject
All construction sites, particularly these were excavation has taken place.
Within 5 days of any rain event capable of leaving ponded water. Throughout the construction period.
Contractor ESSU/ YHAB
Through Jul to Dec 2017 2.7.4
Inspect all construction sites where earth removal can lead to ponding of stagnant water, particularly during the rainy season and where construction materials are stored in the open. Request immediate clean up and visual inspection for mosquito larvae.
Complied with.
No need corrective action plan
48
Environmental Issue Applicable Subproject during this reporting
period
Location Time Frame By whom Implementation status
Implementation
Supervision
By when Measures undertaken during this reporting period
Compliance status and corrective action needed
2.7.5 Community safety
Category C
Phase III subproject
All construction sites involving a larger work area and period of more than or equal to 7 days
Prior to start of a construction activity
Contractor ESSU/ YHAB
Through Jul to Dec 2017
2.7.5
In order to protect the safety of communities on the construction zone contractors will need to provide appropriate traffic management, lighting, management of excavations, making communities aware of any particular hazards.
Complied with.
No need corrective action plan
2.7.6 Hiring locally
Category C
Phase III subproject
For all work contracts
Immediately after contractor mobilization
Contractor YHAB Through Jul to Dec 2017
2.7.6 Obtain written statistics on number of local hires
Complied with.
No need corrective action plan
2.7.7 Work outside the RoW
Category C
Phase III subproject
Communities and/or owners affected
At least 2 weeks prior to start of work
Contractor ESSU Through Jul to Dec 2017
2.7.7 Confirm that consultation and proper steps were taken prior to working outside RoW
Complied with.
No need corrective action plan
2.8 Occupational Health And Safety
2.8.1 Protecting the workforce and maintaining a safe working environment
Category C
Phase III subproject
All work sites All the time Contractor ESSU/ YHAB
Through Jul to Dec 2017 2.8.1
Complete a weekly occupational health and safety inspection reporting on all safety matters defined in Items 2.8.1-2.8.9—using a simple checklist provided—as this form.
Complied with.
No need corrective action plan
2.8.2 Medical facilities and assistance
Category C
Phase III subproject
All construction sites
All the time Contractor ESSU/ YHAB
Through Jul to Dec 2017 2.8.2
See above,
For Category C projects, very small work force and short duration, inputs, return to home each day..
Complied with.
No need corrective action plan
2.8.3 Storage, handing and use of toxic and/or hazardous materials
Category C
Phase III subproject
For all construction operations
At any time during the construction period
Contractor ESSU/ YHAB
Through Jul to Dec 2017 2.8.3
inspection of the storage areas and application sites of toxic materials to be undertaken
Complied with.
No need corrective action plan
2.8.4 Provision of sanitary toilet facilities
Category C
All work sites operated by contractor and
At all times during the construction period
Contractor ESSU/ YHAB
Through Jul to Dec 2017 2.8.4
Complied with.
No need corrective
49
Environmental Issue Applicable Subproject during this reporting
period
Location Time Frame By whom Implementation status
Implementation
Supervision
By when Measures undertaken during this reporting period
Compliance status and corrective action needed
Phase III subproject
without existing facilities
See above: action plan
2.8.5 Control of movement of large equipment and handling of construction items
Category C
Phase III subproject
The entire construction operation
At all times throughout the construction period
Contractor ESSU/ YHAB
Through Jul to Dec 2017
2.8.5 See above
Complied with.
No need corrective action plan
2.8.6 Child Labour
Category C
Phase III subproject
Everywhere the contractor is involved
At all times Contractor ESSU/ YHAB
Through Jul to Dec 2017
2.8.6 Confirm that child labour is not practiced by examining the labour hire records
Complied with.
No need corrective action plan
2.8.7 Records of Safety and Health
Category C
Phase III subproject
Everywhere the contractor is involved
At all times Contractor ESSU/ YHAB
Through Jul to Dec 2017
2.8.7 See above
Complied with.
No need corrective action plan
2.8.8 Reporting of Accidents
Category C
Phase III subproject
For all work sites
Weekly Contractor ESSU/ YHAB
Through Jul to Dec 2017
See above Complied with.
No need corrective action plan
2.8.9; Provision of Potable Water
Category C
Phase III subproject
All construction sites
All the time Contractor ESSU/ YHAB
Through Jul to Dec 2017 2.8.9
Confirm that this is provided at all times and is accessible to all workers
Complied with.
No need corrective action plan
2..8.10 Working into the night and disturbing communities ( see also 2.2.5)
Category C
Phase III subproject
All construction sites within 500 m of a community or sensitive facility such as hospital or school
All the time Contractor ESSU/YHAB
Through Jul to Dec 2017
2.8.10
Verify that contractor is abiding by working hour restrictions as agreed in contract and with local communities
Complied with.
No need corrective action plan
3. OPERATING PERIOD
3.1 Increased risk of pedestrian accidents due to improved roads, faster speeds and greater traffic volume
Category C
Phase II subproject
In village and towns where the roads will be improved
Planned during the detailed design stage and installed during the construction period then completed at the start of operations
General Section; Maintenance Section
ESSU/ YHAB
Through Jul to Dec 2017 3.1
Inspect urban areas where road has been improved, survey re average speed and define what speed management measures have been
Complied with.
No need corrective action plan
50
Environmental Issue Applicable Subproject during this reporting
period
Location Time Frame By whom Implementation status
Implementation
Supervision
By when Measures undertaken during this reporting period
Compliance status and corrective action needed
installed.
3.2 Diverted traffic damaging roads and endangering communities
Category C
Phase II subproject
Where the road parallels expressways
Immediately before the improved roadway becomes operational
General Section and ESSU
YHAB Through Jul to Dec 2017
3.2
Confirm construction of the height barriers and report to YHAB
Complied with.
No need corrective action plan
3.3 Social and community-based enhancements in support of positive impacts
Category C
Phase II subproject
Communities where special support provided by YHAB for re-establishing public transport services
Within 6 months of improved road being operational and continuing for 1 year
General Section and ESSU
YHAB Through Jul to Dec 2017 3.3
Conduct the survey as defined in 3.1 and report results in annual operating period report
Complied with.
No need corrective action plan
51
Appendix 3: Site Photos
Phase III- Section: S202 (270.575-282.875)
Picture A3- 1 Pavement construction Picture A3-2 Ditch construction
Picture A3- 3 Half cross section construction Picture A3-4 Water-spraying
52
Phase III- Section: S207(28-42)
Picture A3- 5 Construction announcement Picture A3- 6 Maintenance personnel directing traffic
Picture A3- 7 Water-spraying Picture A3-8 Safety signboard
53
Phase III- Section: G324(2451.5-2484.0)
Picture A3- 9 Completed pavement Picture A3- 10 Completed pavement
Picture A3- 11 Pavement construction site Picture A3- 12 partially completed pavement
54
Phase III- Section: G320(2745.3-2755.3)
Picture A3- 13 Ditch Picture A3- 14 Safety warning mark
Picture A3- 15 Enclosed ditch t Picture A3- 16 Completed pavement
55
Phase III- Section: G214(2542+000~2563+000)
Picture A3- 17 Half cross section construction Picture A3- 18 Stockpiled quarry
Picture A3- 19 Onsite Safety Training Picture A3- 20 Consulting hired villagers
56
Phase III- Section: S303 (47+588~60+588)
Picture A3- 21 Safety warning mark Picture A3- 22 Site Construction
Picture A3- 23 Retaining wall constructed Picture A3- 24 Diverting traffic
Picture A3- 25 Partially completed road Picture A3- 26 Consult roadside villagers
57
Phase III- Section: G323(1609.9-1668.932)
Picture A3- 27 Pavement construction Picture A3- 28 Pavement construction(2)
Picture A3- 29 Pavement construction(3)