Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Environmental Monitoring Report
Semi-Annual Report December 2017
MON: Regional Logistics Development Project
Prepared by the individual national consultant for the Ministry of Road and Transport
Development and the Asian Development Bank.
This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
AUGUST-
DECEMBER
2017
EMR 2017 NO.2
Loan 2719/Grant 0240-MON: Regional
Logistics Development Project – Zamyn-Uud
Logistics Center
12/1/2017
ENVIRONMENTAL
MONITORING REPORT
REGIONAL LOGISTICS DEVELOPMENT PROJECT
I
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
CONTENTS
1 INTRODUCTION ....................................................................................................................... 4
1.1 ABOUT THE REPORT ....................................................................................................... 4
1.2 DESCRIPTION OF THE PROJECT .................................................................................... 4
1.2.1 Background ................................................................................................................. 4
1.2.2 Objectives of the project .............................................................................................. 5
1.2.3 Impact and Outcome ................................................................................................... 6
1.2.4 Outputs ........................................................................................................................ 6
1.2.5 Cost Estimates by Expenditure Category ..................................................................... 7
1.2.6 Description of the Proposed Actions ............................................................................ 8
1.2.7 Construction progress .................................................................................................. 9
2 LEGAL FRAMEWORK ............................................................................................................... 9
2.1 ADB SAFEGUARD POLICY STATEMENT (SPS 2009) ...................................................... 9
2.2 DOMESTIC ENVIRONMENTAL POLICY AND REQUIREMENTS .................................... 13
2.3 CATEGORIZATION OF THE PROJECT ........................................................................... 14
2.4 ENVIRONMENTAL AND SOCIAL RESPONSIBILITIES FOR THE PROJECT ................. 14
3 IMPLEMENTATION OF THE ENVIRONMENTAL MANAGEMENT PLAN ............................... 16
3.1 OBJECTIVES OF THE ENVIRONMENTAL MANAGEMENT PLAN .................................. 16
3.2 INSTITUTIONAL ARRANGEMENTS ON IMPLEMENTATION OF THE EMP ................... 16
3.3 AIR QUALITY MANAGEMENT ......................................................................................... 17
3.4 NOISE AND VIBRATION CONTROL ................................................................................ 18
3.5 WATER MANAGEMENT .................................................................................................. 20
3.6 MANAGEMENT OF SOIL RESOURCES .......................................................................... 21
3.7 PALEONTOLOGICAL AND ARCHEOLOGICAL RESOURCES ........................................ 23
3.8 FLORA ............................................................................................................................. 23
3.9 CAMP MANAGEMENT ..................................................................................................... 23
3.10 WASTE MANAGEMENT .................................................................................................. 24
4 ENVIRONMENTAL MONITORING .......................................................................................... 25
4.1 MONITORING PARAMETERS ......................................................................................... 25
4.2 MONITORING RESULTS ................................................................................................. 25
REGIONAL LOGISTICS DEVELOPMENT PROJECT
II
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
4.2.1 Air quality monitoring ................................................................................................. 25
4.2.2 Soil quality monitoring ................................................................................................ 26
5 SOCIAL IMPACTS AND MANAGEMENT MEASURES ........................................................... 27
5.1 IMPLEMENTATION STATUS OF GENDER SOCIAL REQUIREMENTS .......................... 27
5.2 HEALTH AND SAFETY .................................................................................................... 27
5.3 GRIEVANCE REDRESS MECHANISM AND GRIEVANCE RECORDS ........................... 30
5.4 IMPLEMENTATION STATUS OF SOCIAL IMPACTS ....................................................... 31
6 CONCLUSION ......................................................................................................................... 31
APPENDIX
Appendix 1. Photos ......................................................................................................................... 32
Appendix 2. EMP COMPLIANCE CHECKLIST ............................................................................... 39
Appendix 3. List of construction activities as of december 30, 2017 ................................................ 42
Appendix 4. Contractors’ Environmental Personnels ....................................................................... 43
Appendix 5. List of equipment and machineries mobilized for the 2017 construction season .......... 44
Appendix 6. Contractor’s internal health and safety procedure........................................................ 47
Appendix 7. Government Resolution on the endorsement of geographic coordinates for exploration
and mining area for common minerals ............................................................................................ 49
Appendix 8. Contractor’s Environmental Management Plan ........................................................... 50
Appendix 9. ACCEPTANCE CONTROL SUMMARY ...................................................................... 56
REGIONAL LOGISTICS DEVELOPMENT PROJECT
III
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
ABBREVIATIONS
ADB – Asian Development Bank
MRTD – Ministry of Road and Transportation Development
MET – Ministry Environment and Tourism
RLDP- Regional Logistics Development Project
PIU-Project Implementation Unit
EMR – Environmental Monitoring Report
EIA- Environmental Impact Assessment
GEIA- General Environmental Impact Assessment
DEIA- Detailed Environmental Impact Assessment
DEIAR- Detailed Environmental Impact Assessment Report
EMP- Environmental Management Plan
EMP- Environmental Monitoring Program
IEE-Initial Environmental Examination
ESS – Environment and Social Specialist
H&S – Health and Safety
CEL – Central Envrionmental Laboratory
DAGO- Dornogobi Aimag Governor’s Office
ZSGO-Zamyn Uud Soum Governor’s Office
CW-Construction Work
CSC- Construction Supervision Consultants
TSP-Total suspended particulate
SO2-Sulphur dioxide
NO2 – Nitrogen dioxide
REGIONAL LOGISTICS DEVELOPMENT PROJECT
4
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
1 INTRODUCTION
1.1 ABOUT THE REPORT
This Environmental Monitoring Report summarizes environmental and social protection works
and activities carried out by the Project Implementation Unit, the Contractors, the Supervising
consultant and their environmental staff during the second half of 2017 construction season
between August and December. It also provides evaluation on implementation of the
Environmental Management Plan for the Regional Logistics Development Project during the
reported period.
This report is prepared by the PIU Environmental and Social Consultant E.Hasar with inputs
from the Contractors and the PIU.
The report comprises of following sections:
1. Section 1 provides description of the project including objectives, components and
activities and updates on construction progress.
2. Section 2 describes environmental requirements of both ADB and the government of
Mongolia.
3. Section 3 summarizes environmental management actions undertaken during reported
period.
4. Section 4, provides results of environmental monitoring activities during the reported
period.
5. Section 5 provides implementation of social and H&S measures and GRM.
6. Section 6 provides conclusion of environmental works.
1.2 DESCRIPTION OF THE PROJECT
1.2.1 Background
Mongolia is also a landlocked country, and such countries face greater transportation
challenges. Mongolia has to depend upon the Russian Federation and the PRC for
access to seaports. In recent years, trade flows have been re-oriented from the Russian
Federation so that more than 80% of the imports now come from the PRC through the
southeast border point in Zamyn Uud. Most of Mongolia’s exports also transit through Zamyn
Uud on their way to Tianjin port, the only PRC port available to Mongolia for international trade.
As a consequence, the traffic handled at Zamyn Uud has grown rapidly in recent years.
REGIONAL LOGISTICS DEVELOPMENT PROJECT
5
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
Zamyn Uud is now badly congested, which is delaying imports, exports, and transit traffic.
Although a number of factors contribute to these delays (unavailable rolling stock, change of
gauge, and delays at customs), the main reason is the inadequate logistics in Mongolia,
particularly at Zamyn Uud. Efficient and well-developed logistics are essential for cost-
effective and competitive transportation. Trade logistics—the capacity to connect to
international markets to ship goods—is essential for developing countries to improve their
competitiveness, reap the benefits of globalization, and fight poverty more effectively in
an increasingly integrated world.
The development of the mining sector will create a huge demand in future for transporting coal
and minerals, and this cannot be met by the existing logistics facilities. To address the urgent
need to improve logistics, the Government of Mongolia asked the Asian Development Bank
(ADB) to support the development of multimodal logistics facilities at Zamyn Uud.
1.2.2 Objectives of the project
Recognizing the need for development of intermodal transport and a strong logistics
network in the country to enhance Mongolia’s global competitiveness, the Government
has requested ADB financing for design and construction of a logistics center in Zamyn
Uud with integrated Customs and Quarantine facilities to remove current congestion at
the border. The Zamyn Uud Logistics Center (ZULC) will include a computerized terminal
management system for efficient, safe, and secure intermodal container operations.
The project is consistent with ADB’s country partnership strategy for Mongolia. It will be ADB’s
first intervention in the Mongolia transport sector that emphasizes the integration of
different modes. This will be achieved through the development of a modern logistics facility,
which will lower dwell time, 12 increase efficiency, expand network capacity, achieve optimal
use of the network and assets, and improve staff productivity. All of these will lead to more
efficient transport services.
The project will be implemented in Zamyn Uud, a poor and isolated desert area where rural
people rely mainly on herding livestock. Inadequate and expensive transport services have
limited economic opportunities. The local authorities and people living in the area see
the development of the logistics facility as a way to address this problem and create more
service sector employment in towns. Logistics development is part of the government’s program
for the integrated development of a free economic zone in the area. This facility is expected to
REGIONAL LOGISTICS DEVELOPMENT PROJECT
6
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
play an important role in the economic development of Zamyn Uud and the area, and will enable
and stimulate international, regional, and domestic trade. The proposed project is in line
with the National Development Plan and the government's Regional Development Strategy.
The proposed Project is a construction of Intermodal Logistics Center in Zamyn Uud. The
Project consists of 96.1 ha of land (78.3 for the terminal, 11.8 ha for Customs and other facilities,
6 ha for truck waiting area) and will be part of the larger Mongolia Railway Authority (MRA) site
of 288 ha that is dedicated as the intermodal freight terminal and logistics center. The project
site is 2.2 km from the ADB-funded Regional Road, which is the main north-south road
connecting Mongolia with PRC, designated as CAREC Corridor 4-b.
Geographically, the Project is localized in eastern part of the Gobi Desert near Mongolia
and PRC border. It will be located approximately 9 km from the border crossing with PRC, 5.7
km from center of Zamyn Uud town, and 5 km from the existing UBTZ freight Terminals 1 and 2.
Figure 3 indicates the multimodal facilities, access roads and railway.
Zamyn Uud, a town with a population of about 13,000, is the intermodal interchange point for
traffic coming from the PRC and Mongolia to the Russian Federation and Europe, and vice
versa. It handles road-to-rail, rail-to-rail, and road-to-road traffic. Most of the import traffic
into Mongolia and transit traffic to the Russian Federation coming from the PRC
(including international traffic from Tianjin port) by rail is transshipped to rail. In recent years, the
volume of traffic coming by road from the PRC has increased. Most of this traffic is transshipped
to rail at Zamyn Uud. Only a small portion of the traffic coming by road from the PRC is
directly transshipped by road because there is no paved road between Zamyn Uud and
Ulaanbaatar, or to the Russian Federation border in the north.
1.2.3 Impact and Outcome
The impact of the project is the international and regional trade promoted in Mongolia. The
outcome of the project will be an efficient, competitive, and reliable multimodal transport system
at Zamyn Uud.
1.2.4 Outputs
The output of the project will be the development of a multimodal facility, with facilities for road-
to-road, road-to-rail, and rail-to-rail transshipment at Zamyn Uud. The project will develop
an integrated intermodal container terminal with customs and quarantine facilities, as well as rail
and road access. Terminal equipment and management systems will be procured and installed.
REGIONAL LOGISTICS DEVELOPMENT PROJECT
7
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
Upon completion, the facility will be operated by the private sector through a
management contract. ADB will provide support for institutional capacity strengthening in
the areas of (i) detailed design, (ii) implementation supervision, (iii) staff capacity
development, (iv) environmental management, and (v) selection and execution of a
management contract.
Figure 1. Design layout: Location map of project components and facilities
1.2.5 Cost Estimates by Expenditure Category
The project is estimated to cost $71.6 million, including taxes and duties, contingencies,
and interest and other charges during implementation. Table 2 summarizes the total investment
plan. The cost estimates are based on quantities derived from preliminary engineering designs
and unit rates reflecting market prices for goods and materials.
Table 1: Financing Plan
($ million)
Source Total %
Asian Development Bank (Loan) 40.00 55.8
Asian Development Bank (Grant) 5.00 7.0
Government 26.64 37.2
Total 71.64 100.0
Source: Asian Development Bank estimates
REGIONAL LOGISTICS DEVELOPMENT PROJECT
8
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
1.2.6 Description of the Proposed Actions
40. The Logistics Center will include (see Figure 4):
■ connecting rail lines in Standard (1,435 mm used in PRC) and Russian (1,520 mm used in
Mongolia) gauges;
■ cargo transfer platforms adjoining the rail lines;
■ storage areas adjacent to the platforms;
■ an administration building;
■ facilities for Customs, Health, and Quarantine inspections and processing (11.8 ha)
■ area for the development of warehouses by private sector shippers and logistics operators;
■ waiting area for trucks (6 ha);
■ area for the development of light manufacturing plants (23 ha set aside but no
construction or other development is included in the Project);
■ cargo handling equipment (e.g., reach-stackers, gantry cranes); and
■ IT systems and software that enable efficient management of cargoes and operations.
Private sector participation will be focused on two distinct, but complementary activities:
■ Logistics Center Terminal Operator. A contract will be awarded through International
Competitive Bidding (ICB) to manage and operate terminal operations including to
load/unload wagons, perform inter-gauge transfer, manage container yards and movement
between the yard and the rail side, prepare trains for dispatch, operate entry/exit gate,
maintain and operate all public-funded facilities. These will include utilizing the gantry
cranes and reach stackers to load/unload cargoes from the platforms into/out of the
adjoining storage sheds. The contractor will be responsible for maintaining the Logistics Center,
the terminal yard, and equipment.
■ Logistics Companies. Logistics companies will be allowed to build warehouses in designated
areas in the terminal yard according to strict guidelines for development. These
warehouses and associated handling equipment used to handle cargo within the warehouse
and between the warehouse and the Logistics Center’s storage and handling areas will
represent investments by the private sector. The logistics companies will be tenants of the
REGIONAL LOGISTICS DEVELOPMENT PROJECT
9
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
Logistics Center and as such, pay rent to GOM and service/maintenance charges to the
Terminal Operator.
1.2.7 Construction progress
Construction Progress as of December 30, 2017:
1. Railway: Railway:
1) For the1st time track lifting and tamping, accumulated completion length is 11km;
2) For the 2nd time track lifting and tamping, completed length is 7200m;
3) Complete installation of 3 sets of turnouts for 1435mm gauge and 4 sets of turnouts
for 1520mm gauge
4) Gantry crane: complete backfilling of 2 sides of gantry crane foundation (960m);
complete installation of steel rails (240m).
2. Electricity engineering:
Set-up of 38 pieces of 12m-lamp-poles; Set-up of 13 pieces of 30m-lamp-poles.
3. Laboratory: experiments of compression resistance for concrete block, cement treated
gravels and mortar; sampling and slump experiment of concrete; experiment to sieve
sands; tests for cement content for cement treated gravels; on-site measurement of
compactness.
2 LEGAL FRAMEWORK
2.1 ADB SAFEGUARD POLICY STATEMENT (SPS 2009)
The safeguard policies are operational policies that seek to avoid, minimize or mitigate the
adverse environmental and social impacts of projects including protecting the rights of those
people likely to be affected or marginalized by the development process. ADB’s safeguard
policy framework in the SPS consists of three operational policies on the environment,
indigenous people and involuntary resettlement. ADB has developed Operational Procedures to
be followed in relation to the SPS policies and these are included in the ADB Operations Manual.
The ADB’s Safeguard Policy Statement (SPS), 2009 is applicable to all projects. These projects
can be categorized as A, B, C or FI. Table 2.1 below provides a list of categorization of the
activities related to Environment, Safeguards, as per ADB’s Safeguard Policy Statement 2009
requirements:
REGIONAL LOGISTICS DEVELOPMENT PROJECT
10
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
Table 2: Environment Safeguards Categorization: Definition
Category Environment
A - Significant Investments that anticipate significant adverse environmental impacts that
are irreversible, diverse, or unprecedented. These impacts may affect an
area larger than the sites or facilities subject to physical works.
B - Less Significant Investments with potential adverse impacts that are site-specific, few if any
of them are irreversible, and in most cases mitigation measures can be
more readily designed than for Category A investments.
C - Minimal or impact Investments that have minimal or no adverse environmental impacts.
FI - Financial
Intermediation
Investment of ADB funds through financial intermediaries (FI)
ADB SPS Requirements (SR1): Environment Policy
ADB’s SPS sets out the policy objectives, scope and triggers, and principles for the
environmental safeguards. To achieve the policy objectives and deliver the policy principles,
ADB carries out the actions described in the Policy Delivery Process (subsection B of the SPS).
To help borrowers/clients and their projects achieve the desired outcomes, ADB adopts a set of
specific safeguard requirements that borrowers/clients are required to meet in addressing
environmental and social impacts and risks. ADB staff, through their due diligence, review, and
supervision, will ensure that borrowers/clients comply with these requirements during project
preparation and implementation. These safeguard requirements are as follows:
Objectives: The objective of ADB’s due diligence for the Project loan is that EA ensures the
environmental soundness and sustainability of projects and to support the integration of
environmental considerations into the project decision-making process.
Scope and Triggers: Environmental safeguards are triggered if a project is likely to have
potential environmental risks and impacts.
REGIONAL LOGISTICS DEVELOPMENT PROJECT
11
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
Policy principles:
Use screening process for each proposed project to determine the appropriate extent and type
of environmental assessment so that appropriate studies are undertaken commensurate with
the significance of potential impacts and risks.
Conduct an environmental assessment for each proposed project to identify potential direct,
indirect, cumulative, and induced impacts and risks to physical, biological, socioeconomic
(including impacts on livelihood through environmental media, health and safety, vulnerable
groups, and gender issues), and physical cultural resources in the context of the project’s area
of influence. Assess potential transboundary and global impacts, including climate change. Use
strategic environmental assessment where appropriate.
Examine alternatives to the project’s location, design, technology, and components and their
potential environmental and social impacts and document the rationale for selecting the
particular alternative proposed. Also consider the no project alternative.
Avoid, and where avoidance is not possible, minimize, mitigate, and/or offset adverse impacts
and enhance positive impacts by means of environmental planning and management. Prepare
an environmental management plan (EMP) that includes the proposed mitigation measures,
environmental monitoring and reporting requirements, related institutional or organizational
arrangements, capacity development and training measures, implementation schedule, cost
estimates, and performance indicators. Key considerations for EMP preparation include
mitigation of potential adverse impacts to the level of no significant harm to third parties, and the
polluter pays principle.
Carry out meaningful consultation with affected people and facilitate their informed participation.
Ensure women’s participation in consultation. Involve stakeholders, including affected people
and concerned nongovernment organizations, early in the project preparation process and
ensure that their views and concerns are made known to and understood by decision makers
and taken into account. Continue consultations with stakeholders throughout project
implementation as necessary to address issues related to environmental assessment. Establish
a grievance redress mechanism to receive and facilitate resolution of the affected people’s
concerns and grievances regarding the project’s environmental performance.
REGIONAL LOGISTICS DEVELOPMENT PROJECT
12
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
Disclose a draft environmental assessment (including the EMP) in a timely manner, before
project appraisal, in an accessible place and in a form and language(s) understandable to
affected people and other stakeholders. Disclose the final environmental assessment, and its
updates if any, to affected people and other stakeholders.
Implement the EMP and monitor its effectiveness. Document monitoring results, including the
development and implementation of corrective actions, and disclose monitoring reports.
Do not implement project activities in areas of critical habitats, unless (i) there are no
measurable adverse impacts on the critical habitat that could impair its ability to function, (ii)
there is no reduction in the population of any recognized endangered or critically endangered
species, and (iii) any lesser impacts are mitigated. If a project is located within a legally
protected area, implement additional programs to promote and enhance the conservation aims
of the protected area. In an area of natural habitats, there must be no significant conversion or
degradation, unless (i) alternatives are not available, (ii) the overall benefits from the project
substantially outweigh the environmental costs, and (iii) any conversion or degradation is
appropriately mitigated. Use a precautionary approach to the use, development, and
management of renewable natural resources.
Apply pollution prevention and control technologies and practices consistent with international
good practices as reflected in internationally recognized standards such as the World Bank
Group’s Environmental, Health and Safety Guidelines. Adopt cleaner production processes and
good energy efficiency practices. Avoid pollution, or, when avoidance is not possible, minimize
or control the intensity or load of pollutant emissions and discharges, including direct and
indirect greenhouse gases emissions, waste generation, and release of hazardous materials
from their production, transportation, handling, and storage. Avoid the use of hazardous
materials subject to international bans or phase-outs. Purchase, use, and manage pesticides
based on integrated pest management approaches and reduce reliance on synthetic chemical
pesticides.
Provide workers with safe and healthy working conditions and prevent accidents, injuries, and
disease. Establish preventive and emergency preparedness and response measures to avoid,
and where avoidance is not possible, to minimize, adverse impacts and risks to the health and
safety of local communities.
REGIONAL LOGISTICS DEVELOPMENT PROJECT
13
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
Conserve physical cultural resources and avoid destroying or damaging them by using field-
based surveys that employ qualified and experienced experts during environmental assessment.
Provide for the use of chance find procedures that include a pre-approved management and
conservation approach for materials that may be discovered during project implementation.
2.2 DOMESTIC ENVIRONMENTAL POLICY AND REQUIREMENTS
Mongolia has enacted a comprehensive policy and legal framework for environmental
assessment and management. It has policies, legislation and strategies in place to manage the
protected areas such as national parks, to satisfy its international obligations, and to protect the
quality of the environment for the health and well-being of its citizens. The hierarchy of policies
and legislative provisions for environmental management in Mongolia comprises the
Constitution, international treaties and environment and resource protection laws.
The EIA requirements of Mongolia are regulated by the Law on EIA (1998, amended 2002 and
amended 2012). The terms of the law apply to all new projects, as well as rehabilitation and
expansion of existing industrial, service or construction activities and projects that use natural
resources.
The most recent amendment to the law was adopted in 2012 and will be brought into force in
2013, implemented through a new Environmental Impact Assessment Regulation. The 2012
amendment introduces a requirement for Strategic Environmental Assessment for policy
documents, and increases emphasis on public participation during a general EIA.
The purpose of the EIA law is environmental protection, the prevention of ecological imbalance,
the regulation of natural resource use, the assessment of environmental impacts of projects and
procedures for decision-making regarding the implementation of projects.
The DEIA procedure guide lined by the method approved by the Minister’s order A-117 of MET
in April 2014 and it is required to contain the following chapters: (i) environmental baseline data;
(ii) analysis of extent and distribution of adverse impacts; (iii) measures to minimize, mitigate,
and/or avoid impacts; (iv) alternative methods and technology; (v) risk assessment; (vi)
environmental management plan (EMP); and (vii) stakeholder consultations, including
potentially affected communities.
REGIONAL LOGISTICS DEVELOPMENT PROJECT
14
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
2.3 CATEGORIZATION OF THE PROJECT
The project is classified as environmental category B. The project preparatory TA
consultants prepared a draft IEE, including an environmental monitoring plan and a grievance
redress mechanism. The IEE was submitted to the Ministry of Environment and Tourism for
review and endorsement. The project could have adverse environmental impacts in the
following areas: (i) soil erosion from cut and fill; (ii) deterioration of underground water quality of
adjacent waterways; and (iii) public health and safety, including HIV/AIDS or sexually
transmitted infections. The IEE concluded that the adverse environmental impacts can be
successfully mitigated through the use of best practices and appropriate technologies.
Implementation of the environmental management, mitigation, and monitoring programs
included in the IEE will ensure compliance with ADB and government environmental guidelines
and procedures. Regular monitoring and audits will be conducted to ensure that standards and
regulations are followed.
The site for the logistics terminal is vacant desert land owned by the government. No one
resides on or uses the land. The road that will connect with the main highway to the site does
not require any land acquisition, or demolition of structures or trees. Therefore, the project is
classified as category C for involuntary resettlement. Zamyn Uud does not have any ethnic
minority communities; the area is settled by Khalkh people, the dominant ethnic group
in Mongolia. Some minority households have migrated to Zamyn Uud for work, but they have
been incorporated into the local community. The project is classified as category C for
indigenous peoples.
2.4 ENVIRONMENTAL AND SOCIAL RESPONSIBILITIES FOR THE PROJECT
The Government will ensure that the design, construction, operation and maintenance of the
components of the Project are carried out in accordance with ADB’s Safeguard Policy
Statement (SPS, 2009), applicable laws and regulations of Mongolia, and the IEE.
MRTD will ensure that potential adverse environmental impacts arising from the Project are
minimized by implementing all mitigation and monitoring measures as presented in the
environment management plan (EMP) included in the IEE. The MRTD will ensure that:
(i) EMP is updated after the detailed design prior to implementation of civil works.
(ii) Sufficient resources to implement and record the implementation of the EMP
prepared for the Project are available.
REGIONAL LOGISTICS DEVELOPMENT PROJECT
15
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
(iii) Starting from project commencement, the MRTD will submit semi-annual
environmental monitoring reports prepared by the environment safeguard specialist
to ADB, within 3 months of the end of the period during implementation of the Project.
The report will include, among other things, environmental monitoring data
(baseline and routine), a review of progress made on environmental measures
detailed in the IEE and EMP; as well as problems encountered and remedial
measures taken.
(iv) The quarterly progress report will have a short description of environmental
situation.
(v) Detailed engineering designs, civil works and other contracts for the Project
incorporate applicable environmental mitigation measures identified in the IEE and
EMP.
(vi) The civil works contracts and the construction supervision contract will include
the environmental protection and its monitoring provisions.
(vii) Civil works contractors are supervised to ensure compliance with the
requirements of the EMP. In particular, the civil works contracts will include the
construction workers’ health and safety provisions including HIV/AIDS prevention
activities, and the construction supervision consultant contract will include the
training program on human trafficking for the local police.
(viii) The construction supervision consultant will work as the focal point of the
grievance redress mechanism as prescribed in the IEE.
REGIONAL LOGISTICS DEVELOPMENT PROJECT
16
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
3 IMPLEMENTATION OF THE ENVIRONMENTAL MANAGEMENT PLAN
3.1 OBJECTIVES OF THE ENVIRONMENTAL MANAGEMENT PLAN
The objective of establishing an EMP is not only to propose appropriate mitigation measures,
but also to recommend establishment of institutions ormechanisms to monitor and ensure
compliance with environmental regulations andimplementation of the proposed mitigation
measures. Such institutions andmechanisms will seek to ensure continuously improvement of
environmental protectionand managementduring preconstruction, construction, and operation in
order to prevent,reduce, or mitigate adverse impacts.
The EMP is site-specific, and is focused on the Project components: Multimodal and auxiliary
facilities, access rail and road.
3.2 INSTITUTIONAL ARRANGEMENTS ON IMPLEMENTATION OF THE EMP
The roles of entities involved in environmental management is as follows:
❖ The Ministry of Road and Transportation Development (MRTD) is the Executing
Agency for the Project;
❖ The Project Implementation Unit (PIU) is responsible for overall contract
administration and day-to-day project supervision including environmental
management. The PIU is also responsible for supervising contractors by way of the
Environmental Specifications and Special Environmental Provisions contained in the
civil works contract.
❖ The Environmental and Social Officer within the PIU is responsible for ensuring the
Environmental Management Plan, including monitoring requirements, are implemented
effectively;
❖ As the civil works contractor for construction of Zamyn Uud logistics center China
Railway 21st Bureau Group Co., Ltd is responsible for implementation of the
Environmental management plan.
❖ Construction Supervision Consultants (A Joint Venture -“Soosung Engineering” Co.,Ltd,
“NBCC”LLC and “Geo Zuraglal” LLC) assists PIU in its responsibilities, including
instrumental environmental monitoring of the Project; and prepares quarterly progress
report including environment chapter and semi-annual environment report. All
reports are submitted to EA through PIU and the EA submits them to ADB.
REGIONAL LOGISTICS DEVELOPMENT PROJECT
17
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
3.3 AIR QUALITY MANAGEMENT
As specified in the EMP, following mitigation measures have been implemented in order to
minimize dust and emissions from construction vehicles during the construction period:
❖ All earth material transporting vehicles covered to prevent dust spread
❖ Material storage site should be 300m away from residential areas
❖ All vehicles, Equipment and machinery used for construction shall be regularly maintained
and correctly operated
❖ Water is sprayed on the construction sites and major feeder roads twice a day during dry
season
In addition, to ensure the dust level is controlled, dust monitoring is undertaken at the selected
monitoring spots. Please refer to the air quality monitoring results in Section ..
Below table provides evaluation on implementation of the mitigation measures specified in the
EMP:
Table 3. Implementation status of air quality mitigation measures
Impacts Mitigation measures specified in the EMP Implementation status
Generation of dust
All earthwork vehicles shall be covered to avoid
spillage
Implemented
Material storage site should be 300m away from
residential areas
Implemented
Water will be sprayed on the construction sites and
major feeder roads twice a day during dry season
Implemented
Emissions from
construction vehicles,
equipment and
machinery
All vehicles, Equipment and machinery used for
construction shall be regularly maintained and
correctly operated (including the use of dust filters
or hoods) throughout the project corridor.
Implemented
The contractor has prepared its own site-specific “Air quality management plan” in June 2017.
In accordance with the air quality management plan, the contractor has implemented following
measures to reduce emission of dust and gas:
REGIONAL LOGISTICS DEVELOPMENT PROJECT
18
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
❖ Implemented the hardening treatment of the construction site for the main processing
areas and earthwork stacking. Set up a person responsible for the scene sprinkler dust
and timely clean up the floating soil.
❖ For concrete mixing plant, pile yard and material processing field, set in a place far away
from residential area.
❖ When removing buildings and structures, adopt measures such as separate and
watering. In the prescribed period, clean up the waste, use sprinkler to prevent dust
before earth working.
❖ For construction site, office and living area, it is strictly prohibited to burn all kinds of
waste; implement the environmental sanitation, to prevent all kinds of odor gas
emissions.
❖ Carry out regular sprinkler to reduce dust, and clean garbage on construction site.
❖ Regularly check and maintain equipment, and strictly control the motor vehicle emission
standards. Take central processing for used engine oil. It is forbidden to throw arbitrarily.
❖ When transporting the building materials, garbage, soil, and so on, strengthen the dust
cleaning, shielding, cleaning and so on. Prevent the building garbage, soil scattered,
polluting roads and the surrounding environment.
❖ Avoid low-quality fuel that causes air pollution.
3.4 NOISE AND VIBRATION CONTROL
As specified in the EMP, following mitigation measures have been implemented in order to
minimize noise and vibration:
❖ Plants and equipment used in construction shall strictly conform to local nose standards
❖ Within 200m of the nearest habitation, construction works such as crushing, concrete
mixing and batching, mechanical compaction, etc., will be stopped between 22:00 and
06:00 hours.
Additionally, following measures were implemented to minimize noise disturbance on
surrounding community and construction workers:
❖ Source control: Maintain all exhaust systems in good working order; undertake regular
equipment maintenance;
❖ Provide advance warning to the community on timing of noisy activities.
❖ Noise monitoring regularly to ensure noise levels at construction sites are within the
REGIONAL LOGISTICS DEVELOPMENT PROJECT
19
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
allowed limit
Table 4. Implementation of the mitigation measures specified in the EMP
Impacts Mitigation measures Implementation status
Noise from
construction
equipment
and trucks
Plants and equipment used in construction shall strictly
conform to local noise standards
Implemented
Within 200m of the nearest habitation, construction works
such as crushing, concrete mixing and batching, mechanical
compaction etc., will be stopped between 22:00 and 06:00
hours.
Implemented
Within implementation of its own site-specific EMP, the contractor has performed following
measures:
❖ Construction time is arranged at 6: 30 - 20: 00. The construction needed to operate
continuous construction or night construction due to production technology should be
approved by Supervisor before starting works. And make the greatest efforts do not
interfere with the nearby residents. The project department should assist the
construction team to communicate with surrounding residents.
❖ Strong noise equipment at the construction site should be located on the side away from
the residential area. Try to use environmentally friendly low-noise vibrator, timely
cleaning and maintenance after vibration. When vibrating concrete, it is forbidden to
contact the template with steel. And conduct fast swipe, should be equipped with the
corresponding personnel to control the power cord switch to prevent the vibrator idling.
❖ Artificial noise control measures: to promote civilized construction, to strengthen the
management of artificial noise, to carry out training, to reduce the artificial noise, and
enhance noise awareness of all personnel. Reasonable arrange construction time, the
works that generating much noise should be carried out during daytime. When cleaning
up the repair template, it is forbidden to beat violently. For scaffolding demolition,
handling, repair, etc. It must be gently, up and down around someone to pass, to reduce
man-made noise.
❖ During material transport vehicles into the scene, it is strictly prohibited whistle. loading
and unloading materials must be lightly.
REGIONAL LOGISTICS DEVELOPMENT PROJECT
20
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
❖ During templates erecting, scaffolding support, removal and handling, it should be gently
and delivery, not throwing.
3.5 WATER MANAGEMENT
As specified in the EMP, waste water treatment system was created. The contractor has made
a sewage pit with concrete walls and floor where the waste water from the construction camp
site is collected temporarily. The contractor has agreement with the Waste water treatment plant
of the Zamyn Uud town on removal and transportation of waste water. According to the
agreement the Zamyn Uud WWTP sends its waste water truck to the construction site to draw it
from the sewage pit on monthly basis. One time charge for the such service is 70,000 MNT.
Another mitigation measure specified in the EMP was to establish irrigation system for wind-
and-sand breaks at construction site. This measure is planned to be implemented at the end of
construction period.
Drinking water for construction staff is supplied in 25 litre containers by Saikhan Tsever Us LLC
– a local filtered water distribution firm. The contractor has agreement with Chandmani Badral
LLC which is the main water supply entity for Zamyn Uud town nad operated 11 ground water
wells around the town. Domestic and construction use water is supplied by a pipeline from the
nearest well of Chandmani Badral LLC.
Table 5. Implementation status of mitigation measures specified in the EMP
Impacts Mitigation measures Implementation status
Waste
water
Established irrigation system for wind-and-
sand breaks
Planned at the end of
construction period (2018)
Waste water treatment system Implemented
The contractor has developed its own site-specific water management plan which aims to
strengthen water conservation management, scientifically and rationally use water resources,
improve and standardize the site water system, reduce water waste, protect and improve the
environment,, in strictly accordance with the implementation of ESAP plan, and ultimately to
protect the health of workers and water conservation purposes, better serve the community,
according to "technical specifications" and the characteristics of the project, so as to we prepare
this plan. To implement this plan, following measures were implemented:
REGIONAL LOGISTICS DEVELOPMENT PROJECT
21
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
❖ The construction water, temporary living water and fire-protection water should meet the
requirements.
❖ For the construction water, installed water meter measurement, by the full-time staff
responsible for inspection and maintenance of water pipes, to reduce the water waste.
❖ Site pipeline adopts high-quality materials, in line with the requirements of health and
environmental protection., according to the construction needs of a reasonable
arrangement to achieve that getting water nearby, to avoid damage of water pipes and
water leakage. To ensure the operation of water storage, water distribution and other
water equipment. Set up a person who regularly checks the integrity of the equipment
and report to project department during abnormal condition.
❖ For mixing station and the scene of mixing mortar, the construction site mixer slurry to
set the sedimentation tank, in order to achieve waste water recovery, as far as possible
for water and dust, etc., to improve water recycling rate. To ensure the mixer water
supply pipe without leakage and effective water control device.
❖ Regular check the pipeline and water valve, if the damage is found, it should be promptly
replaced or repaired, so as to avoid pipeline leakage and waste of water resources.
3.6 MANAGEMENT OF SOIL RESOURCES
The contractor has been using 1 borrow pit and 1 quarry site for its construction purposes.
The borrow pit is located in about 3km distance from the camp site in south east direction. The
location of the borrow area is adjacent to the current central waste landfill point of Zamyn-Uud
town. The local soum government is planning to use the borrow pit left by the contractor as a
new waste landfill point for the Zamyn-Uud town once the construction is completed. The quarry
site and crusher are located in 26km distance from the construction camp in north direction.
There are no any permanent settlements in the immediate vicinity of both sites.
The contractor has implemented following measures in order to minimize potential impacts
related to land use and soil erosion:
❖ All truck drivers were instructed to strictly follow the pre-determined deviation road
routes in order to avoid creating multiple dirt tracks
❖ Temporary road was built to avoid making new road branches and the road is used for
transportation of sand and gravel.
REGIONAL LOGISTICS DEVELOPMENT PROJECT
22
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
❖ Borrow pits and quarry sites were chosen in at least 3-5km distance from herder
settlements
Additionally, the contractor has developed its own site-specific soil protection plan within which
they have implemented following measures:
❖ During the construction period, minimize the temporary land occupation, reasonably
arrange the construction progress, and shorten the time of temporary land use.
❖ Set up a special construction sidewalk for construction vehicles and machinery, regularly
implement the inspection and maintenance of vehicles, and collect waste oil to prevent
pollution of soil.
❖ It is strictly forbidden for illegal land acquisition and free spoil, so as not to cause loss of
state-owned land resources.
❖ In the process of construction, we should excavate and transport immediately and then
conduct paving and pressing as soon as possible to reduce soil erosion in construction.
❖ Reduce vegetation destroy in the process of construction and photographed the original
appearance to file.
❖ Service roads were constructed for vehicles and machinery. Vehicles and machinery
were checked and maintained at fix periods.
Below table shows soil protection measures specified in the EMP and implementation status.
Table 6. Implementation status of mitigation measures specified in the EMP
Impact Mitigation measures Implementation status
Soil erosion
The areas of soil clearance should be minimized Implemented
Separation of topsoil from subsoil during the
excavation works; reuse of topsoil as superficial
layer (where possible)
Implemented
Stabilization of embankment slopes and road cuts
by re-vegetation with grazing resistant plant
species
Planned at later stages of
construction
Soil
contamination
Contractor should develop and implement a spill
management plan
Spill prevention measures are
planned in Hazardous Materials
Management Plan and
implemented.
REGIONAL LOGISTICS DEVELOPMENT PROJECT
23
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
3.7 PALEONTOLOGICAL AND ARCHEOLOGICAL RESOURCES
There are no any paleontological and archeological resources in the vicinity of construction sites.
However, in case any chance finds occur during the construction period, the contractor shall
halt/stop construction activity immediately and notify the local administration, Institute of
Paleontology/Archeology and local police of the chance finds. There was no any chance finds
occurred during the reported period.
3.8 FLORA
As specified in the EMP, it is recommended to hire sub-consultant that have experience in
planting trees in arid areas for procurement of seedings and planting them in sand – and
windbreaks on the northern and western sides of the multimodal facilities in order to protect
from drifting sand and soil erosion. The PIU is planning to carry out this activitiy at the end of
construction period.
3.9 CAMP MANAGEMENT
The workers’ camp site is located adjacent to the construction site of the logistics center in
5.7km north of Zamyn Uud town with the main gate facing to the construction site. The camp
site is surrounded with brick walls and consists of 2 office buildings (one for the superivision
engineers and the other for the contractor staffs) and dormitory buildings for the construction
staffs. All buildings in the camp site is 1 storey and are made of brick materials.
As specified in the EMP, the construction camp management shall include management of waste
and spills. Waste collection points, sanitation system, rest rooms, male, female toilets, laundry
room, bathing room, ventilliator, dorms and office rooms are available at the camp site.
Firefighting equipment was installed at the camp (See photos in Appendix 1).
Table 7. Implementation status of mitigation measures specified in the EMP
Impact Mitigation measures Implementation status
Contamination related to lubricants and fuel Sewerage related contamination Waste management
Proper construction camp management in compliance with Construction Camp Management Plan that includes management of waste and spills
Implemented. (The contractor has developed and implemented waste management plan, hazardous materials management plan and established sewage management system)
REGIONAL LOGISTICS DEVELOPMENT PROJECT
24
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
3.10 WASTE MANAGEMENT
As specified in the EMP which was developed back in 2010, it was specified that used oil and
lubricants shall be recycled. Used oil and lubricants are collected in temporary storage deliver to
special agency in Zamyn-Uud. Following solid waste management procedures are implemented
by the contractors:
❖ Domestic and waste construction materials are disposed to a designated waste
collection point nearby the camp site.
❖ Garbage boxes are placed at each office and dormitory rooms and the construction
staff are not allowed to throw any waste at or nearby the construction areas
❖ The contractors have signed "Agreement on waste removal" with the Zamyn Uud soum
civil service agency who sends its waste transport truck to the construction site on
weekly basis. One time waste removal charge is 30,000MNT.
❖ The final destination for the domestic solid waste generated by construction camp sites
and waste construction materials is central landfill site of the Zamyn-Uud town which is
located in about 3km distance from the camp site. This central landfill site is managed
by civil service agency under the local soum administration.
Additionally, the contractor’s internal regulations has enforced following rules:
1.When the mixing station concrete and ready-mixed mortar, the remaining materials are
arranged at the designated site according to the construction site requirements or transported to
the mixing station. It is forbidden to dump arbitrarily.
2. When dealing with paints, flammable materials and toxic chemicals, the mask and goggles
must be worn.
1. For oil-containing solid waste, cars, transport vehicles, excavators, forklifts and other
construction machinery, waste lubricants and waste oil, implement oil change in repair room.
2. Centralized storage for waste oil, regularly transported by the Zamyn-Uud environmental
protection company regularly.
3. The project department registers the solid waste disposal and records it.
REGIONAL LOGISTICS DEVELOPMENT PROJECT
25
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
4 ENVIRONMENTAL MONITORING
The PIU has hired Central environmental laboratory of Mongolia (a state enterprise under MET)
who sent its experts to carry out field sampling works in December 2017. The environmental
monitoring team has conducted dust and noise level measurements and made soil and water
samplings at the selected monitoring spots. Results of the test analysis are shown in below
table.
4.1 MONITORING PARAMETERS
As specified in the project EMP requirements, following parameters for environmental
monitoring measurements were tested in order to identify potential changes in key
environmental parameters:
❖ Air quality: Dust concentration level (m3/mg), contents of NO2 and SO2
❖ Noise emission level (decibel)
❖ Soil contamination: contents of Cd, Pb, Hg, Br, Cr, Zn, Cu, Co, Sr, Rb and Zr
❖ Hygiene inspection: inspection on waste and sewage removal, physical condition of
camp sites, hygiene condition of kitchen and canteen.
4.2 MONITORING RESULTS
4.2.1 Air quality monitoring
Dust measurements were made at the construction site at 3 spots: in front of customs office
building, nearby and maintenance office and at the entrance road junction that were active
construction points in 2017. The monitoring team specialists have measured dust concentration
levels with average value of 30 minute duration. Average dust concentration level is shown in
the below table. The maximum allowed level of dust concentration is 0.1 mg/m3 according
Mongolian Standard on Ambient Air Quality.
Table 8. Air quality measurement results at the construction site, 2017
Air quality measurement locations
Date of sampling
SO2, mg/m3
NO2, mg/m3
TSP РМ10, mg/m3
30 minute average Noise level, Decibel dB
At the front of customs office building
2017.12.14 0.017 0.103 0.079 40
Nearby maintenance office
2017.12.14 0.010 0.092 0.101 42
At the entrance junction
2017.12.14 0.019 0.088 0.104 42
Maximum allowed levels as per MNS 4585:2016
0.450 0.200 0.05 60
REGIONAL LOGISTICS DEVELOPMENT PROJECT
26
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
Measured levels of sulphur dioxide and nitrogen dioxide and noise level were within the
standard level while dust level has exceeded the maximum allowed level at all 3 measurement
spots. It is recommended that the contractor shall intensify water spray at the active
construction spots to reduce the dust level.
4.2.2 Soil quality monitoring
The monitoring team has chosen 3 the active construction spots within the construction site and
made soil samplings. In order to determine potential contamination of soil, 11 most common
types of heavy metals’ contents were tested in the soil samples at the Central environmental
laboratory. The test results in below table shows, the heavy metals contents in the soil samples
were within the standard levels. Based on the laboratory test analysis, it can be concluded that
there is no soil contamination at the construction site.
Table 9. Soil quality test results, 2017
Soil sampling locations
Contents of heavy metals, mg/kg Cd Pb Hg Br Cr Zn Cu Co Sr Rb Zr
At the front of customs office building
0.00 8.2 0.00 0.00 0.00 38.1 27.4 9.3 330.4 256.6 155.6
Nearby maintenance office
1.1 10.5 0.00 0.00 0.00 52.2 27.5 21.7 462.5 311.3 345.7
At the entrance junction
0.4 11.2 0.00 0.00 0.00 32.3 24.1 27.7 466.9 178.7 404.7
Maximum allowed levels as per MNS 5850:2008
3.0 100 2.0 150 300 100 50 800
REGIONAL LOGISTICS DEVELOPMENT PROJECT
27
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
5 SOCIAL IMPACTS AND MANAGEMENT MEASURES
5.1 IMPLEMENTATION STATUS OF GENDER SOCIAL REQUIREMENTS
As specified in the EMP, the project shall encourage employment of local people by ensuring
about 75% of required unskilled labor comes from Zamyn Uud and hiring of women will be
encouraged.
Around 75% of required unskilled labor comes from Zamyn Uud. Hiring women was
encouraged. Currently, a total of 60 Mongolian workers are working, and it covers 30% of total
employees. There are 10 female workers in August 2017, which is an increase compared to the
previous construction season (there were 3 female employees in 2016).
5.2 HEALTH AND SAFETY
The contractor has set up a working group to organize the health and safety management of the
construction site.
Leader: Tang Haibo
Deputy Leaders: Nan Yantao, Qu Guoqiang
Members: Lai Lin, Wang Yanlei, Li Yu, Li Jianmin, Luo Kai, Chen Bo, Ouyang Hui, He Xiqing.
The contractor has developed internal H&S policies and procedures and has setup H&S control
team. Within this regard, following activities were undertaken:
The contractor insisted on safety production working policy of “safety lies the first place;
precaution is given first priority; comprehensive management” in the whole process. The
construction works have entered into a comprehensive implementation including all working
sites.
On August 2nd, 2017, project department organized Consultant team and representatives of
construction organization to go inside construction site and crushing plant to conduct inspection,
giving great importance to examine possible sources of danger, including scaffold, deep pit,
construction electricity, vehicles and driving drivers, construction pioneer road etc. rectification
notices are issued timely for arisen problems. Concerning safety production on site, construction
organization carried out and execute so the level of safety and management and safety
protection achieve certain improvement.
REGIONAL LOGISTICS DEVELOPMENT PROJECT
28
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
Secondly, project department strengthened safety education and training, adopting publicity
slogans and warning boards to carry out safety education for all staff. The contractor organized
construction technicians, staff for special type of operation and different types of works for
different structures to set up a technology and safety disclosure. The ideas that safety enjoys
priority and management should be strict were set up and enhanced. The contractor
strengthened safety construction management and prevented issues of production without
safety awareness during the one hundred days and making clear safety responsibility of all
works in their production.
During the reported period, the on-site usage of protective equipment is strictly inspected. All
on-site workers should take technical disclosure with safety helmet and safety shoes. For steel
structure construction of building, the project department arranged specially assigned safety-
person to inspect and control. When constructing at high altitude or suspending in midair,
workers must wear a safety belt. The safety rope should be hung than the working personnel to
prevent it from swinging or getting knotted. The hook shall be hung on link ring which should be
replaced as soon as any abnormal sign occurs. It is prohibited to throw any objects in the sky.
For works at high place, operation ladder should be set up to keep safe and it is forbidden to
climb on the scaffolding. With respect to placement disorder, scaffold disorder and imprecise
paving of scaffold bottom, we stopped them timely and implemented rectification.
When conducting the excavation of pipelines for electricity, fire-prevention and sewage, set
provisional safety protection facilities, arrange staff to make enclosure with triangular flags and
taft.
As required by Consultant engineers, the contractor purchased safety and warning tapes and
stickers and install signs of warning to prevent large area of base holes exposed and forbidding
irrelevant personnel and cars entering into the site.
Road construction: in the process of subgrade construction, education for vehicle drivers has be
strengthened that the driving of on-site construction should be commanded by special man,
especially for the operation of paving water stable layer. Due to the all-round working condition,
the safety of passengers and working of rolling the road should be given great importance when
the vehicles turn back.
Strict control will be attached to driving speed and overload driving. For drivers who transport
aggregated rocks, we arrange random checks at night to examine whether they are drunk or not
to avoid issues of driving after drinking.
REGIONAL LOGISTICS DEVELOPMENT PROJECT
29
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
Safety & Quality Dpt. assigns full-time safety supervisor to carry out the safety management,
insist on all-day inspection, and fill safety log. Promptly stop the potential safety hazard and
issue the rectification notice, thoroughly eliminating hidden dangers, to ensure safety production.
As for aspects of daily life and security, the contractor enhanced management of staffs’ leaving
from the site due to personal reasons and strictly conducted the management of passport-
lending measure so staffs have to ask for leave and register on record documents so as to
forbid the incident of staff leaving without permission.
All Chinese workers have taken HIV/AIDS, STD, viral hepatitis B and C tests when before
obtaining labor permission. HIV/AIDS handouts have been distributed among the workers of the
Contractor.
Personal protective clothing and equipment were provided to all construction workers.
Caution tape is placed and demarcated during the earthworks as well safety precaution portable
boards and warning signs are placed.
There was no any accidents and injuries occurred during the reported period.
Speed limiting signs were set at each intersection, deceleration strips were set at each turning
intersection of project department and living area. The speeds of vehicles are controlled strictly
in site, and prohibit over-speed and overman.
REGIONAL LOGISTICS DEVELOPMENT PROJECT
30
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
5.3 GRIEVANCE REDRESS MECHANISM AND GRIEVANCE RECORDS
Grievance Redress Mechanism was defined for the project within the ADB IEE.
Figure 2. Grievance Redress Mechanism
Grievances
Grievances Contact Information
Report
Coordination Supervision
Corrective Measures Instruction Construction Information
Grievances
In order to implement IEE Stakeholder Consultation and Participation Plan the Contractor
opened hotline for complaints. No any complaints and grievances were received during the
2017 construction season.
Affected People
Grievance Redress Committee -PIU Environmental and Social Monitoring Specialist
-Construction Supervision Consultant -Aimag Specialized Inspection Department -Soum Environmental Inspector -Local community representative
Soum Environmental Inspector
PIU
Contractors
MRTCUD
Court
ADB
REGIONAL LOGISTICS DEVELOPMENT PROJECT
31
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
5.4 IMPLEMENTATION STATUS OF SOCIAL IMPACTS
Five mitigation measures regarding occupational health and safety and HIV/AIDS were
specified in the EMP. Below table shows implementation status of the H&S mitigation measures.
Table 10. Implementation status of mitigation measures specified in the EMP
Issues/concerns Mitigation measures Timeframe Responsible
party
Implementation status
Occupational
H&S
Occupational H&S in
the construction
industry
Construction
and
operation
stages
Contractor
Implemented
Emergency
Response Plan
Implemented
HIV/AIDS
Training for workers
Contractor
& local
government
Implemented
Awarenes campaign
in ZY
Implemented
Brochure distribution Implemented
6 CONCLUSION
The contractor has implemented mitigation measures specified in the EMP properly during the
reported period. It has employed on-site environmental and safety staffs and hire local
professional laboratories to carry out field monitoring activities (sampling, measurements and
lab test). Overall, the Project has demonstrated a satisfactory level of environmental due
diligence during the 2017 construction season.
REGIONAL LOGISTICS DEVELOPMENT PROJECT
32
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
APPENDIX 1. PHOTOS
Photo 1. Separation of topsoil from subsoil during the excavation works
Photo 2. Workers wear safety protective helmets and gloves
REGIONAL LOGISTICS DEVELOPMENT PROJECT
33
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
Photo 3. Workers wear safety protective helmets and gloves
Photo 4. Workers wear safety protective helmets and gloves
REGIONAL LOGISTICS DEVELOPMENT PROJECT
34
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
Photo 5. Workers wear safety protective helmets and gloves
Photo 6. Environmental monitoring
REGIONAL LOGISTICS DEVELOPMENT PROJECT
35
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
Photo 7. Installation of Fire-protection pipeline
Photo 8. Connection of water supply pipeline
REGIONAL LOGISTICS DEVELOPMENT PROJECT
36
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
Photo 9. Service agency truck from Zamyn Uud draws waste water from sewage pit
Photo 10. Installation of Drainage tank in sewage well manhole all area
REGIONAL LOGISTICS DEVELOPMENT PROJECT
37
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
Photo 11. Collection of construction waste
Photo 12. Collection of construction waste
REGIONAL LOGISTICS DEVELOPMENT PROJECT
38
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
Photo 13. Water spray truck
Photo 14. Earthwork excavation
REGIONAL LOGISTICS DEVELOPMENT PROJECT
39
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
APPENDIX 2. EMP COMPLIANCE CHECKLIST
Table 11. EMP Compliance Checklist
Impact Mitigation measures Implementation status
1.Soil and topography
Soil erosion
The areas of soil clearance should be minimized Implemented
Separation of topsoil from subsoil during the excavation works; reuse of topsoil as superficial layer (where possible)
Implemented
Stabilization of embankment slopes and road cuts by re-vegetation with grazing resistant plant species
Planned at later stages of construction
Soil contamination
Contractor should develop and implement a spill management plan
Spill prevention measures are planned in Hazardous Materials Management Plan and implemented.
2. Air quality
Generation of dust
All earthwork vehicles shall be covered to avoid spillage Implemented
Material storage site should be 300m away from residential areas
Implemented
Water will be sprayed on the construction sites and major feeder roads twice a day during dry season
Implemented
Emissions from construction vehicles, equipment and machinery
All vehicles, Equipment and machinery used for construction shall be regularly maintained and correctly operated (including the use of dust filters or hoods) throughout the project corridor.
Implemented
3. Hydrology
Waste water Established irrigation system for wind-and-sand breaks
Planned at the end of construction period (2018)
Waste water treatment system Implemented
4. Flora
Drifting sand soil erosion
Procurement of seedings and planting them in sand-and windbreaks
Planned at the end of construction period (2018)
5. Noise and vibration
Noise from construction equipment and trucks
Plants and equipment used in construction shall strictly conform to local noise standards
Implemented
Within 200m of the nearest habitation, construction works such as crushing, concrete mixing and batching, mechanical compaction etc., will be stopped between 22:00 and 06:00 hours.
Implemented
6. Paleontological and Archaeological Resources
Encountered during construction
If chance finds occurs, all activities will halt and notification of local administration and Institute of Paleontology
The contractor has raised awareness of workers. No chance finds has occurred in the reported period.
REGIONAL LOGISTICS DEVELOPMENT PROJECT
40
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
7. Construction camp
Contamination related to lubricants and fuel Sewerage related contamination Waste management
Proper construction camp management in compliance with Construction Camp Management Plan that includes management of waste and spills
Implemented. (The contractor has developed and implemented waste management plan, hazardous materials management plan and established sewage management system)
8. Waste management
Used oil and lubricants
Recycling of used oil
Implemented. (The contractor has temporary collection facility of used oil and deliver to the local recycling agency)
9. Health and safety
Occupational H&S
Occupational HS in the construction industry Emergency response plan
The contractor has developed and implemented internal H&S procedures and all staffs were trained on it.
HIV/AIDS Training of workers Awareness campaign Brochure distribution
Implemented
10. Social impacts
Local people employment
About 75% of unskilled labor comes from Zamyn Uud; hiring of women will be encouraged
Implemented
11. Reporting
Reporting to EA and ADB
Quarterly Progress Report will include a chapter for environmental protection
Implemented
REGIONAL LOGISTICS DEVELOPMENT PROJECT
41
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
REGIONAL LOGISTICS DEVELOPMENT PROJECT
42
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
APPENDIX 3. LIST OF CONSTRUCTION ACTIVITIES AS OF DECEMBER 30, 2017
No. Activity Subdivision Unit Contract
Amount
Scheduled
Progress in
this period
Actual
Progress in
this period
Accumulated
Amount Completion
% Extra % Remaining %
1 Highway
Engineering
2 Railway
Engineering
2.1 80%
2.2 Rail Type R50 - Steel Grade:
R320Cr - Broad Gauge m 11057.02 1000 1000 10500 95% 5%
2.3 Design and Supply/Install 190:9
Broad Gauge 1520mm Turnouts nr 5 4 4 4 80% 20%
2.4
Design and Supply/Install 190:9
Standard Gauge 1435mm
Turnouts
Nr 4 3 3 3 75% 25%
2.5 Installation of steel rail of gantry
crane m 1600 240 240 240 15% 85%
2.6 fasteners nr 3200 480 480 480 15% 85%
4 Pipeline
Engineering
5 Electricity
engineering
5.1 External Lighting Sum 1 1 0.4 0.7 70% 30%
REGIONAL LOGISTICS DEVELOPMENT PROJECT
43
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
APPENDIX 4. CONTRACTORS’ ENVIRONMENTAL PERSONNELS
Table 12. On-site environmental personnels
№ Project names Environmental personnel’s
names and position Duties
1 Construction work of Logistics Center in Zamyn Uud
Mr. Zhu Hong, Manager of Safety & Environment and Quality Department
Implement mitigation measures of IEE, DEIA EMP, Stakeholder Consultation and Participation Plan & CEMP
2 Mr. Wang Yan Lei, Specialist of Safety & Environment and Quality Department
REGIONAL LOGISTICS DEVELOPMENT PROJECT
44
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
APPENDIX 5. LIST OF EQUIPMENT AND MACHINERIES MOBILIZED FOR THE 2017
CONSTRUCTION SEASON
Table 13. List of equipment and machineries mobilized in 2017
No. Equipment Quantity Mode Power In
Production Arrival Date
Leaving
Date Remarks
1 Digging Machine 1 PC300-7 180KW yes 2016.3
2 Digging Machine 1 SK260LC-8 137KW yes 2016.5
3 Digging Machine 1 PC200-8 132kw yes 2016.3
4 Digging Machine 1 PC220-7 132kw yes 2016.5
5 Digging Machine 1 PC220-7 132kw yes 2016.5
6 Bulldozer 1 SD160 128KW yes 2016.5
7 Shandui Roller 1 SR20mp 132kw yes 2016.5
8 Xugong Roller 1 XS222J 136kw yes 2017.3
9 Xugong Roller 1
PY190,,length
of levelling tool
3965mm
142KW yes 2016.5
10 Xugong Loader 1 ZL50FN 162KW yes 2016.4
11 Longgong B Loader 1 LG855B 162KW yes 2016.4
12 Longgong D Loader 1 LG855D 162KW yes 2016.10
13 Shandong Jiangong
Loader 1 LG933L 92KW yes 2017.4
14 Shandong Jiangong
Loader 1 ZL12D 24KW yes 2016.10
15 Wode Zhonggong Loader 1 Wode 162KW yes 2016.4
16 Ouman Dump Track 5 TX2531 228kw yes 2016.4
17 Hualing Dump Track 5 Valin 290 213kw yes 2016.5
18 Dongfeng Oil Tank
Truck 1 YC4E160-33 118KW yes 2016.4
19 Dongfeng Watering Cart 1 YC4E160-33 118KW yes 2016.4
20 Forklift 1 Shandong
Lugong 42kw yes 2017.4
21 Brick-Making Machine 1 28kw yes 2017.4
REGIONAL LOGISTICS DEVELOPMENT PROJECT
45
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
22 Stone Crusher 1 Ershi 750/1060 100kw yes 2016.7
23 Paver 1 DTU95C 140kw yes 2016.8
24 Welding Machine 5 yes 2016.7
25 Wind Gun Equipment 1 32kw yes 2016.7
26 Clamp Empty Drill 1 YC2108 33kw yes 2016.7
27 Box Transformer 1 800KV
A yes 2016.7
28 500kw Frequency
Converter 2 yes 2016.7
29 300kw Frequency
Converter 1 yes 2016.7
30 Compensation Cabinet 1 yes 2016.7
31 Toyota Pardo 1 PRADO-
150TXL yes 2016.7
32 Toyota Pickup Truck 1 Hilux Pick-up yes 2016.7
33 Weighbridge 1 SCS-150 yes 2016.9
34 Concrete Mixing Station 1 HZSJH60 yes 2016.7
35 Graded Gravel Mixing
Station 1 MWB500I yes 2016.7
36 Truck-Mounted Crane 1 QY25K5-I yes 2016.7
37 Xugong Loader 1 ZL50GN 162KW yes 2016.7
38 Dongfeng Sprinkler 1 118KW yes 2016.7
39 Rubber-wheel roller 1 CP221 Yes 2017.6.5
40 Loader 1 ZL50CN Yes 2017.8.13
41 Excavator 1 Li
ZAXIS50U Yes 2017.8.13
42 Hoisting machine 1 25t Yes 2017.9.7
43 Single row vehicle 2 Yes 2017.9.10
44 Triple-roll paver 1 Yes 2017.9.22
REGIONAL LOGISTICS DEVELOPMENT PROJECT
46
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
45 Hydraulic ballast tamper 2 YD-22II Yes 2017.9.4
46 Hydraulic track lifting
and lining machine 2
YQBJ-
300K*200II Yes
2017.9.4
47 Rail saw 1 NQG-5III Yes 2017.9.4
48 Rail drilling machine 1 NZG-31 Yes 2017.9.4
49 Flexible axle ballast
tamper 2 NRD-4 Yes
2017.9.4
50 Hand-held ballast tamper 4 ND-5 Yes 2017.9.4
51 Two-head screw machine 2 YLB-700 Yes 2017.9.4
52 One-head screw machine 2 NLB-300 Yes 2017.9.4
53 Straightening and cutting
machine 1 GT6-14 Yes
2017.10.14
54 Excavator 1 HYUNDAI
555W-7 Yes
2017.10.31
55 Truck with crane 1 5T Yes 2017.12.10
REGIONAL LOGISTICS DEVELOPMENT PROJECT
47
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
APPENDIX 6. CONTRACTOR’S INTERNAL HEALTH AND SAFETY PROCEDURE
❖ Equipped with full-time security officers who have a legitimate qualification and sufficient
experience, responsible for on-site safety in production, safety inspection and
management, organization and convening a weekly regular meeting of safety production.
Conduct a comprehensive inspection and record for daily on-site safety, and is
responsible for security technology and technical solutions.
❖ Establish production education and training system, and resolutely implement the "safety
first, prevention first" approach. Regularly conduct education of "safe operation
procedures", strictly implement the safety production system and safety production
reward & punishment system.
❖ Strictly implement the technical solutions of construction site safety management, the
problems should be promptly reported to the relevant departments. No person may alter
the program and measures without authorization.
❖ Establish and implement the system of technology disclosure of safety production.
According to the safety measures and the actual situation of site, the Safety & Quality
Dpt. must give technology disclosure to targeted workers, with both signature s.
❖ Establish acceptance system for machinery, temporary electricity facilities and all kinds
of scaffold. It is forbidden to use items without acceptance or unqualified acceptance.
❖ Safety education system: all personnel must go through safety training including
company training, project training and post training. All workers must get qualified
certificate before working.
Safety precautions
❖ Site workers must wear a helmet, and is strictly prohibited to conduct high-altitude
operations without seat belts, and is strictly prohibited to chase slapstick and drunk work.
It is forbidden to smoke, wear slipper, wear shorts or without naked back.
❖ All kinds of scaffolds should be in strict accordance with the scaffolding safety
technology protection standards and erection specifications. Scaffolding vertical net
adopts green safety netting, safety netting should be stretched straight and closed tight.
❖ For obvious parts of the site, there must be security signs, slogans and publicity notice,
at any time to remind the construction workers pay attention to safety.
❖ On-site, adopt dual power supply system to ensure the power supply. Temporary
distribution lines must be set up according to specifications, overhead lines must be
REGIONAL LOGISTICS DEVELOPMENT PROJECT
48
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
insulated wire, and shall not use plastic cord, be bundled overhead laying and lay along
the ground.
❖ Power distribution system must implement classification of distribution. The internal
equipment of electric brake box must comply with the relevant provisions. Electric
appliance must be reliable and intact. Its selection and constant value must be complied
with the relevant provisions. Switchgear should be marked with the usage. Electric
appliance must be unified style, unified configuration, and unified orange color in box,
and set fence according to provisions. The connection of flow box and the upper level of
the brake box adopts extrapolation connection.
Health protection measures
❖ In accordance with the requirements of technical specifications, arrange labor protection
works. According to the number of each type of work and the nature of labor, Material
Department is responsible for procurement, with adequate and necessary labor
protection supplies. While strengthening the administration and implementing labor
protection measures.
❖ Set a sufficient number of sanitation facilities in living area and maintain hygiene in the
staff dormitory area. Regular check indoor and outdoor hygiene, keep the ground clean,
place daily necessities neatly, keep the room well ventilated and fresh air, plant flowers
in the outdoors to beautify the environment.
❖ Set up living garbage bins at the periphery of the living area. Adopt closed vessel to
collect living garbage, and then unified into the garbage dump, and then transport to the
designated garbage disposal site according to local environmental regulations. It is
strictly forbidden to discard live waste arbitrarily.
❖ In living area, set up a public bathroom with hot and cold water pipes, to ensure that
employees can take a bath after work, to maintain personal hygiene.
REGIONAL LOGISTICS DEVELOPMENT PROJECT
49
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
APPENDIX 7. GOVERNMENT RESOLUTION ON THE ENDORSEMENT OF GEOGRAPHIC COORDINATES FOR EXPLORATION AND MINING AREA FOR COMMON MINERALS
Unofficial translation
GOVERNMENT RESOLUTION ON THE ENDORSEMENT OF GEOGRAPHIC
COORDINATES FOR EXPLORATION AND MINING AREA FOR COMMON MINERALS
3 August 2016 Ulaanbaatar
Number: 14
The following provisions are endorsed by the Government of Mongolia according to the provision 3.3 of the Law on Common Minerals and Law on the Ratification of the Financing Agreement (Regional Logistics Development Project):
1. To endorse geographic coordinates for exploration and mining area for common minerals with the purpose of construction of Regional logistics development project in Zamyn Uud soum of Dornogobi aimag as stated in the attachment.
2. To give the legal body, who is executing the Regional logistics development project, permission to explore and mine common minerals in the area where geographic coordinates were endorsed by this Government resolution.
3. To assign Ts. Dashdorj, Minister for Mining and Heavy Industry and T.Enkhtuvshin, Dornogobi Aimag to assist the legal body, who explores and mines common minerals as stated in the provision 2 of the Government resolution, in accordance with the laws and regulations.
PRIME MINISTER J.ERDENEBAT MINISTER FOR ROAD AND TRANSPORATION DEVELOPMENT D.GANBAT
REGIONAL LOGISTICS DEVELOPMENT PROJECT
50
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
APPENDIX 8. CONTRACTOR’S ENVIRONMENTAL MANAGEMENT PLAN
REGIONAL LOGISTICS DEVELOPMENT PROJECT
51
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
REGIONAL LOGISTICS DEVELOPMENT PROJECT
52
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
REGIONAL LOGISTICS DEVELOPMENT PROJECT
53
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
REGIONAL LOGISTICS DEVELOPMENT PROJECT
54
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
REGIONAL LOGISTICS DEVELOPMENT PROJECT
55
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
REGIONAL LOGISTICS DEVELOPMENT PROJECT
56
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
APPENDIX 9. ACCEPTANCE CONTROL SUMMARY
No. Work Location Work Description Date RFI No. Approved or not
1 BG STABLING TRACK1 CH0+00-
CH12+29.75 2nd-time filling of ballast 2017.11.22 RE-239 Approved
2 BG SPUR TRACK CH0+00-CH9+84.504 2nd-time filling of ballast 2017.11.22 RE-240 Approved
3 Next To 08Road
Installation of fastening
system and fishplate for
gantry crane foundation
(CH8+50-CH10+10)
2017.11.25 RE-241 Approved
4 Next To 06Road
Installation of fastening
system and fishplate for
gantry crane foundation
CH7+20-CH8+00
2017.11.25 RE-242 Approved
5 Next To 08Road
installation of QU100
steel rail for gantry crane
foundation (CH8+50-
CH10+10)
2017.11.25 RE-243 Approved
6 Next To 06Road
installation of QU100
steel rail for gantry crane
foundation CH7+20-
CH8+00
2017.11.25 RE-244 Approved
7 BG TURNROUND CH4+60-CH12+29.56 Broad Gauge 1520 mm
Rail installation 2017.11.27 RE-245 Approved
8 BG STABLING TRACK1 CH0+00-
CH12+29.75
track lifting and tamping
of the railway route for
the 1st time
2017.11.27 RE-246 Approved
REGIONAL LOGISTICS DEVELOPMENT PROJECT
57
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
9 BG TURNROUND CH4+60-CH12+29.56 Installation of fastening
system and fishplate 2017.11.27 RE-247 Approved
10 SG TURNROUND CH0+00- CH30+16.354
track lifting and tamping
of the railway route for
the 2nd time
2017.11.28 RE-248 Approved
11 SG SPUR TRACK CH0+00- CH9+84.501
track lifting and tamping
of the railway route for
the 2nd time
2017.11.28 RE-249 Approved
12 BG SPUR TRACK CH0+00-CH9+84.504
track lifting and tamping
of the railway route for
the 1st time
2017.11.30 RE-250 Approved
13 BG STABLING TRACK1 CH11+59.183
Installation of 1:9 right
turnouts with UIC60 rails
1520mm gauge
2017.11.30 RE-251 Approved
14 BG TURNAROUND CH4+19.989
Installation of 1:9 left
turnouts with UIC60 rails
1520mm gauge
2017.11.30 RE-252 Approved
15 BG TURNAROUND CH4+79.996
Installation of 1:9 left
turnouts with UIC60 rails
1520mm gauge
2017.12.2 RE-253 Approved
16 BG TURNAROUND CH0+00-CH12+29.56 2nd-time filling of ballast 2017.12.4 RE-254 Approved
17 SG TURNAROUND CH26+40.135
Installation of 1:9 right
turnouts with UIC60 rails
1435mm gauge
2017.12.4 RE-255 Approved
18 SG TURNAROUND CH10+05.855 Installation of 1:9 right
turnouts with UIC60 rails
2017.12.5 RE-256 Approved
REGIONAL LOGISTICS DEVELOPMENT PROJECT
58
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
1435mm gauge
19 BG TURNAROUND CH0+00-CH12+29.56
track lifting and tamping
of the railway route for
the 1st time
2017.12.5 RE-257 Approved
20 Next To 08Road
backfilling at the two
sides of gantry crane
foundation CH7+20-
CH8+00
2017.12.8 RE-258 Approved
21 BG TURNAROUND CH0+00-CH12+29.56
track lifting and tamping
of the railway route for
the 2nd time
2017.12.12 RE-259 Approved
22 SG TURNAROUND CH30+16.354-
CH38+15.03
SG TURNAROUND
CH30+16.354-
CH38+15.03
2017.12.12 RE-260 Approved
23 car park 6
connection of the 20m
light pole 2017.11.29
B-EL-2017-201 Approved
24 car park 6
enlarge holes of the 12m
light pole 2017.11.29
B-EL-2017-202 Approved
25
car park 6
excavation
12mLighthouse and install
the light pole
2017.11.29 B-EL-2017-
194-7
Approved
26 car park 6
connection of the 20m
light pole 2017.11.30
B-EL-2017-201-
1 Approved
27 car park 6
enlarge holes of the 12m
light pole 2017.11.30
B-EL-2017-202-
1 Approved
REGIONAL LOGISTICS DEVELOPMENT PROJECT
59
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
28
car park 6
excavation
12mLighthouse and install
the light pole 2017.11.30
B-EL-2017-
194-8
Approved
29 car park 6
connection of the 20m
light pole 2017.12.2
B-EL-2017-201-
2 Approved
30 car park 6
enlarge holes of the 12m
light pole 2017.12.2
B-EL-2017-202-
2 Approved
31 car park 6
connection of the 20m
light pole 2017.12.3
B-EL-2017-201-
3 Approved
32 car park 6
enlarge holes of the 12m
light pole 2017.12.3
B-EL-2017-202-
3 Approved
33 car park 6
connection of the 20m
light pole 2017.12.4
B-EL-2017-201-
4 Approved
34 car park 6
enlarge holes of the 12m
light pole 2017.12.4
B-EL-2017-202-
4 Approved
35 car park 6
connection of the 20m
light pole 2017.12.7
B-EL-2017-201-
5 Approved
36 container area
install the 30m light
pole:L086,L076,
L068,L085,L075,
L074,P073,L072
2017.12.11 B-EL-2017-203 Approved
37 container area
install the 30m light
pole:L086,L076,
L068,L085,L075,
L074,P073,L072
2017.12.12 B-EL-2017-203-
1 Approved
REGIONAL LOGISTICS DEVELOPMENT PROJECT
60
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
38 container area
install the 30m light
pole:L086,L076,
L068,L085,L075,
L074,P073,L072
2017.12.15 B-EL-2017-203-
2 Approved
39
Laboratory- 05 CARPARK of section
34,35,36,37,38 /01 CARPARK of section C
and B
Test of compressive
strength C32/40 concrete
pavement 28day
2017.11.21 M-L-17-523-1 Approved
40
Laboratory- concrete of 1st layer for
foundation gantry crane rail CH09+30-
CH10+10
Test of compressive
strength C30 concrete
28day
2017.11.21 M-L-17-524-1 Approved
41 Laboratory- heavy equipment station the
foundation 2nd of TX4,TX5
Test of compressive
strength C30 concrete
28day
2017.11.21 M-L-17-525-1 Approved
42 Laboratory- container area 1400㎡
Test for
1st compressive strength o
f cement stabilized base
28day
2017.11.21 M-L-17-526-1 Approved
43 Laboratory- 05 CARPARK of section 38 and
T /01 CARPARK of section B
Test of compressive
strength C32/40 concrete
pavement 28day
2017.11.22 M-L-17-528-1 Approved
44
Laboratory- Heating 、Water Supply and Fire-
protection pipeline concreting of concrete
trenches cover plate
Test of compressive
strength C40 concrete
28day
2017.11.22 M-L-17-529-1 Approved
45
Laboratory- foundation of gantry crane rail
concreting of foundation cushionCH15+00-
CH16+00
Test of compressive
strength BM100 concrete
28day
2017.11.22 M-L-17-530-1 Approved
REGIONAL LOGISTICS DEVELOPMENT PROJECT
61
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
46 Laboratory-container area 4000㎡
Test for
1st compressive strength o
f cement stabilized base
28day
2017.11.22 M-L-17-531-1 Approved
47
Laboratory- 05 CARPARK of section 34,36
/01 CARPARK of section D and B/01B
ROAD CH00+00-CH03+30
Test of compressive
strength C32/40 concrete
pavement 28day
2017.11.23 M-L-17-532-1 Approved
48
Laboratory- concrete of 1st layer for
foundation of gantry crane rail CH10+10-
CH10+90
Test of compressive
strength C30 concrete
28day
2017.11.23 M-L-17-533-1 Approved
49
Laboratory- Heating 、Water Supply and Fire-
protection pipeline concreting of concrete
trenches cover plate
Test of compressive
strength C40 concrete
28day
2017.11.23 M-L-17-534-1 Approved
50 Laboratory- container area 1320㎡(1st) ,
300㎡ 2nd
Test for compressive stren
gth of cement stabilized b
ase 28day
2017.11.23 M-L-17-535-1 Approved
51
Laboratory-concrete of 2nd layer for
foundation of gantry crane rail CH07+20-
CH08+00
Test of compressive
strength C30 concrete
07day
2017.11.23 M-L-17-572 Approved
52
Laboratory- 05 CARPARK of section 35, 37
/01 CARPARK of section D and A/02 ROAD
CH00+60-CH03+40
Test of compressive
strength C32/40 concrete
pavement 28day
2017.11.24 M-L-17-536-1 Approved
53
Laboratory- concrete of 1st layer for
foundation of gantry crane rail CH10+90-
CH11+70
Test of compressive
strength C30 concrete
28day
2017.11.24 M-L-17-537-1 Approved
54 Laboratory- container area 5000㎡ Test for 2nd
compressive strength of ce
2017.11.24 M-L-17-538-1 Approved
REGIONAL LOGISTICS DEVELOPMENT PROJECT
62
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
ment stabilized base
28day
55 Laboratory- No.2 Culvert Concreting for
foundation
Test of compressive
strength BM250 concrete
28day
2017.11.26 M-L-17-539-1 Approved
56 Laboratory- administering building the
foundation of EP088-EP094,LV126-LV113
Test of compressive
strength BM200 concrete
28day
2017.11.26 M-L-17-540-1 Approved
57
Laboratory- foundation of gantry crane rail
concreting of foundation cushionCH16+00-
CH16+50
Test of compressive
strength BM100 concrete
28day
2017.11.26 M-L-17-541-1 Approved
58
Laboratory- concrete of 1st layer for
foundation of gantry crane rail CH11+70-
CH12+50
Test of compressive
strength C30 concrete
28day
2017.11.26 M-L-17-542-1 Approved
59
Laboratory-Customs inspections and bonded
warehouse building :the foundation of
electricity well LV130-LV134,EP211,
LV001,LV002,LV006,EP222,
LV012,EP088,EP210
Test of compressive
strength M20(BM200)
concrete 07day
2017.11.26 M-L-17-573 Approved
60
Laboratory- Administration Building Concrete
in suspended slabs 、concrete in staircases、
concrete in columns and beams
Test of compressive
strength BM250 concrete
28day
2017.11.27 M-L-17-543-1 Approved
61
Laboratory- container area 1120㎡
Test for
2nd compressive strength
of cement stabilized base
28day
2017.11.27 M-L-17-544-1 Approved
REGIONAL LOGISTICS DEVELOPMENT PROJECT
63
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
62
Laboratory-01B CARPARK of section E and
C/05 CARPARK of section 36/01B ROAD
CH00+00-CH01+80
Test of compressive
strength C32/40 concrete
pavement (28 day)
2017.11.27 M-L-17-545-1 Approved
63
Laboratory-foundation of gantry crane rail
concreting of foundation cushionCH06+80-
CH08+00
Test of compressive
strength BM100 concrete
(28day)
2017.11.28 M-L-17-546-1 Approved
64
container area 300m2
Test for 2nd compressive
strength of cement
stabilized base (28day)
2017.11.28 M-L-17-547-1 Approved
65
Laboratory-01B CARPARK of section E and
C/01 CARPARK of section B,2 and 18/01B
ROAD CH01+30-CH03+20
Test of compressive
strength C32/40 concrete
pavement 28day
2017.11.29 M-L-17-548-1 Approved
66
Laboratory-custom inspection & bonded
warehouse building footings and pads
Test of compressive
strength BM250 concrete
28day
2017.11.29 M-L-17-549-1 Approved
67
Laboratory-concrete of 1st layer for foundation
of gantry crane rail CH12+50-CH14+10
Test of compressive
strength C30 concrete
28day
2017.11.29 M-L-17-550-1 Approved
68
Laboratory-concrete of 1st layer for foundation
of gantry crane rail CH13+30-CH14+10
Test of compressive
strength C30 concrete
28day
2017.11.30 M-L-17-551-1 Approved
69
Laboratory-01B CARPARK of section E,D
and C/01 CARPARK of section B,4 and
11/01B ROAD CH00+60-CH03+20
Test of compressive
strength C32/C40 concrete
pavement 28day
2017.12.01 M-L-17-552-1 Approved
70 Laboratory-01B CARPARK of section E and
C/01 CARPARK of section 4 and 11/01B
Test of compressive
strength C32/40 concrete
2017.12.02 M-L-17-553-1 Approved
REGIONAL LOGISTICS DEVELOPMENT PROJECT
64
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
ROAD CH00+60-CH03+20 pavement 28day
71
Laboratory-No.2 Culvert Concrete protective
cover
Test of compressive
strength BM250 concrete
28day
2017.12.02 M-L-17-554-1 Approved
72
Laboratory-container area the foundation of
EP089,EP090,EP206,LV120,LV112,
LV126-LV128,LV140,LV142,LV144
Test of compressive
strength M20 BM200
concrete 28day
2017.12.02 M-L-17-555-1 Approved
73
Laboratory-01B CARPARK of section
A ,Band E/01 CARPARK of section 4
Test of compressive
strength C32/40 concrete
pavement 28day
2017.12.03 M-L-17-556-1 Approved
74
Laboratory-container area the foundation of
EP206, LV112,LV126-LV128,LV140,
LV142,LV144
Test of compressive
strength M20 BM200
concrete 28day
2017.12.03 M-L-17-557-1 Approved
75
Laboratory-concrete of 1st layer for foundation
of gantry crane rail CH14+10-CH15+70
Test of compressive
strength C30 concrete
28day
2017.12.03 M-L-17-558-1 Approved
76
Laboratory-container area 800m2
Test for 3rd layer
compressive strength of
cement stabilized base
28day
2017.12.03 M-L-17-559-1 Approved
77
Laboratory-01B CARPARK of section C and
E/01 CARPARK of section 18
Test of compressive
strength C32/40 concrete
pavement 28day
2017.12.04 M-L-17-560-1 Approved
78
Laboratory-concrete of 1st layer for foundation
of gantry crane rail CH07+20-
CH08+00/CH14+90-CH15+70
Test of compressive
strength C30 concrete
28day
2017.12.04 M-L-17-561-1 Approved
REGIONAL LOGISTICS DEVELOPMENT PROJECT
65
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
79
Laboratory-container area 3000m2
Test for 3rd layer
compressive strength of
cement stabilized base
28day
2017.12.04 M-L-17-562-1 Approved
80
Laboratory-foundation of gantry crane rail
concreting of foundation cushion CH06+00-
CH06+80
Test of compressive
strength BM100 concrete
28day
2017.12.06 M-L-17-563-1 Approved
81
Laboratory-administration building :the
foundation of EP061-EP062,LV016,EP207-
EP209,LV123,LV125,EP220,EP093,EP094
Test of compressive
strength M20(BM200)
concrete 28day
2017.12.06 M-L-17-564-1 Approved
82 Autoclaved aerated concrete
walls of the administration
building 2017.12.7 17-057 Approved
83
Laboratory-foundation of gantry crane rail
concreting of foundation cushion CH06+00-
CH06+80
Test of compressive
strength BM100 concrete
28day
2017.12.07 M-L-17-567-1 Approved
84
railway
UIC60-9 Simple Turnout
and related accessories
(Bolt,Nut,Steel Frog,Rail
Pad,Spring Bar,Gusset
Plate,Heavy Spring
2017.12.08 17-058 Approved
85
Laboratory-CENTRAL HEATING
BUILDING AND COAL ASH STORAGE
Concrete in walls 250 thick
Test of compressive
strength C30 concrete
28day
2017.12.09 M-L-17-568-1 Approved
86
Laboratory- concrete of 1st layer for
foundation of gantry crane rail CH14+90-
CH15+70
Test of compressive
strength C30 concrete
28day
2017.12.10 M-L-17-569-1 Approved
REGIONAL LOGISTICS DEVELOPMENT PROJECT
66
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017
87
Laboratory- concrete of 2nd layer for
foundation of gantry crane rail CH08+50-
CH10+10
Test of compressive
strength C30 concrete
28day
2017.12.10 M-L-17-570-1 Approved
88
Laboratory- container area:the foundation of
the cold storage platform
Test of compressive
strength BM100 concrete
28day
2017.12.10 M-L-17-571-1 Approved
89
Laboratory-concrete of 2nd layer for
foundation of gantry crane rail CH07+20-
CH08+00
Test of compressive
strength C30 concrete
28day
2017.12.14 M-L-17-572-1 Approved
90
Laboratory-Customs inspections and bonded
warehouse building :the foundation of
electricity well LV130-LV134,EP211,
LV001,LV002,LV006,EP222,
LV012,EP088,EP210
Test of compressive
strength M20(BM200)
concrete 28day
2017.12.17 M-L-17-573-1 Approved
REGIONAL LOGISTICS DEVELOPMENT PROJECT
67
ENVIRONMENTAL MONITORING REPORT FOR AUGUST- DECEMBER 2017