92
Letter of Submittal and Attachments (Volume I) I-64 Widening Exit 200 to 205 From Interstate 295 to Exit 205 (Bottom’s Bridge) Henrico and New Kent Counties, Virginia State Project No.: 0064-043-602 Federal Project No.: NHPP-064-3 (499) Contract ID Number: C00107458DB95 submitted to: Virginia Department of Transportation submitted by: The Lane Construction Corporation in association with: WSP USA Inc. >>ELECTRONIC

4.1 Letter of Submittal...Letter of Submittal and Attachments (Volume I) I-64 Widening Exit 200 to 205 From Interstate 295 to Exit 205 (Bottom s Bridge) Henrico and New Kent Counties,

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

  • Letter of Submittal and Attachments (Volume I)

    I-64 Widening Exit 200 to 205 From Interstate 295 to Exit 205 (Bottom’s Bridge)Henrico and New Kent Counties, VirginiaState Project No.: 0064-043-602Federal Project No.: NHPP-064-3 (499)Contract ID Number: C00107458DB95

    submitted to:

    Virginia Department of Transportation

    submitted by:

    The Lane Construction Corporation in association with:

    WSP USA Inc.

    >>ELECTRONIC

  • 4.1 Letter of Submittal

  • 4.2 Attachments to the Letter of Subm

    ittal

  • I-64 Widening Exit 200 to 205

    4 . 2 A T T A C H M E N T S T O T H E L E T T E R O F S U B M I T T A L Page | 3

    A T T A C H M E N T S T O T H E L E T T E R O F S U B M I T T A L

    4.2.1 Confirmation of SOQ Information

    LANE confirms all information presented in the Statement of Qualifications (SOQ) remains true and accurate in accordance with Part 1, Section 11.4. Please note that the legal name of WSP | Parsons Brinckerhoff, Inc. has been changed to WSP USA, Inc. As demonstrated in the organizational chart presented on the following page, the Team proposed by LANE, including but not limited to our organizational structure, lead contractor, lead designer, key personnel, and other individuals identified pursuant to Part 1, Section 4.2, will remain intact for the duration of the contract. Organizational Chart

    Under the leadership of our Design-Build Manager, Mr. Ryan Terry, the LANE Team is structured to effectively manage and deliver the design and construction of this project. The LANE Team is organized to provide VDOT with a single-source point of contact, responsible for all design and construction activities. Our team organization has a straightforward chain of command, with individual tasks and functional responsibilities clearly identified. This organizational chart identifies key personnel and major functions to be performed for the successful management, design, and construction of the project. No changes have been made to the Offeror’s organizational structure, Lead Contractor, Lead Designer, Key Personnel or other individuals identified in the Offeror’s SOQ (dated December 15, 2016). Though reporting relationships are rigid, the lines of communication within the team will remain fluid and flexible to meet the requirements of each individual project task. In order to prevent unnecessary project delays, at times it may be prudent for other members within the LANE Team to communicate directly with their counterparts at VDOT. This will be directed and authorized in advance by Mr. Terry and the VDOT Project Manager.

    Likewise, there have been no revisions made to the narrative describing the functional relationships among participants for the organizational chart.

    There are no changes from Section 3.3.2 of the SOQ submitted to VDOT and dated December 15, 2016

  • I-64 Widening Exit 200 to 205

    4 . 2 A T T A C H M E N T S T O T H E L E T T E R O F S U B M I T T A L Page | 4

  • I-64 Widening Exit 200 to 205

    4 . 2 A T T A C H M E N T S T O T H E L E T T E R O F S U B M I T T A L Page | 5

    4.2.2 Conceptual Roadway Plans

    The Conceptual Roadway Plans showing the general Project layout are included in Volume II. They include copies of (a) plan view indicating the number of lanes specified in the RFP Information Package, and (b) typical sections of the proposed improvements to I-64. The Conceptual Roadway Plans meet the requirements of the Design Criteria Table (Attachment 2.2 of Part 2) and indicate that the limits of construction are within the existing/proposed right-of- way limits shown in the RFP Conceptual Plans.

    4.2.3 Conceptual Bridge Plans

    The Conceptual Bridge Plans showing the type, size and location for the proposed widened bridge are included in Volume II (RFP Section 4.2.3). Copies of an elevation view, transverse section, and abutment and pier configurations have been provided. The Conceptual Bridge Plans meet all applicable geometric requirements of VDOT’s Structure and Bridge Manual, in Volume V, Part 2.

    4.2.4 Proposal Schedule and Narrative

    The LANE Team has thoroughly evaluated the RFP documents, performed numerous site visits, attended the pre-proposal meeting, participated in proprietary meeting discussions, and held numerous working sessions amongst our design and construction teams in order to plan the most safe and efficient method for completing this Project. Through this progression, we have developed a solution to deliver the Project as outlined on the schedule. This narrative explains how we will deliver a highly successful Project to VDOT and to the satisfaction of all stakeholders.

    4.2.4.1 Proposal Schedule

    The Proposal Schedule is located in Volume II.

    4.2.4.2 Proposal Schedule Narrative

    The LANE Team has developed a Proposal Schedule Narrative for our overall plan to execute the Work. The narrative includes overall sequencing of Project, a description and explanation of the Critical Path, LANE Team’s proposed means and methods, and other key assumptions on which the Proposal Schedule is based. The narrative also explains how the LANE Team plans to optimize the benefits of the D-B delivery method to mitigate known risks, conform to the RFP requirements including MOT restrictions, minimize impacts of construction activities on the environment, and deliver the Project safely and on-time.

    Key Milestone The LANE Team is committed to the Final Completion date of August 22, 2019. The table below identifies Key Milestone dates, which in order to be met, will require coordination not only between the D-B Team, and VDOT but also other reviewing agencies (FHWA, USFWS, etc.). Post award, the LANE Team will implement our assertive D-B approach, local experience, and relationships to potentially improve these dates to meet the Early Completion of May 24, 2019.

  • I-64 Widening Exit 200 to 205

    4 . 2 A T T A C H M E N T S T O T H E L E T T E R O F S U B M I T T A L Page | 6

    Key Milestone Milestone Date

    Proposal Due Date June 20, 2017

    Notice of Intent to Award June 26, 2017

    CTB Approval / Notice to Award July 19, 2017

    Design-Build Contract Execution August 16, 2017

    NTP August 28, 2017

    Scope Validation Period Complete December 25, 2017

    Start of Construction April 19, 2018

    Early Completion / “No Excuse” Incentive May 24, 2019

    Final Completion Date August 22, 2019 Work Breakdown Structure (WBS)

    The WBS is a multi-level, hierarchical arrangement of the work to be performed on the Project. The LANE Team has laid out the WBS to break down the major phases of the Project by Project Element and type of work. The type of work has been broken down by phases, areas and respective components such as Milestones, Project Management, Scope Validation, Environmental/Permitting, ROW, Design, Public Involvement, Utility Relocation, and Construction. The WBS areas for the Project have been developed as a collaborative effort between the design and construction teams by evaluating the components of the Project as a single Project including type of work along the alignments design considerations, and management of the construction efforts.

    Proj

    ect

    Admin

    Design

    Scope Validation Letter

    Early Design Early Design Deliverables

    Final Design Final Design Plans

    Permit Permits

    Procurement

    Construction

    Phase 1 Meadow Rd Overpass

    Phase 2

    Bridge B-624/B-625

    Weight Station

    Phase 3

    Bridge B-624/B-625

    Weight Station

  • I-64 Widening Exit 200 to 205

    4 . 2 A T T A C H M E N T S T O T H E L E T T E R O F S U B M I T T A L Page | 7

    Levels 2, 3, and 4 of the WBS as depicted in the Proposal Schedule include but are not limited to the following items for the respective Project components:

    • Administration: includes the contract milestones, the start and completion milestones of major project components, and monitoring of project durations.

    • Design: includes the development of all design plans, scope validation, utility, permit, ROW acquisition, QA/QC plans, construction plans, etc.

    • Procurement: includes the procurement and fabrication of girders and piles for the Project. • Construction: includes the entire construction scope of the Project, which includes but not limited to:

    MOT, erosion & sediment controls, QA/QC, storm water management, drainage, lighting, ITS, phasing, bridge construction, mill-and-overlay paving, sound barrier wall, and roadway construction.

    Calendars

    The LANE Team uses five different calendars to represent a variety of work scenarios:

    • “Calendar Days” – Based on seven days per week and is used for review periods and milestones. • “5 Days / Week Holiday” – Based on five working days per week and includes standard holidays. Used

    for design activities and work not impacted by adverse weather and holiday restrictions. • “5 Days / Week with Weather & Holidays” – Based on five working days per week, specified holiday

    restrictions, and anticipated weather days. Used for construction activities. • “5 Days / Week Paving” – Based on the “5 Days with Weather & Holidays” with non-working periods

    from December through February. Used for asphalt paving activities. • “5 Days / Week Final Paving” – Based on the “5 Days with Weather & Holidays” with non-working

    periods from December through April. Used for mill-and-overlay and final asphalt paving activities.

    For weather analysis, the LANE Team has reviewed the weather data (January 2012 to December 2016) provided by NOAA observation center at Richmond International Airport, VA. Using on 0.1 inch of participation per day as the threshold for weather impact and taking into consideration of weekends, the LANE Team Schedule accounts the following number of weather days each month:

    Month Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec

    Anticipated Weather

    Days 4 5 5 4 4 6 6 4 4 3 3 5

    The LANE Team will observe the New Year, Memorial Day, 4th of July, Labor Day, Thanksgiving and Christmas holidays from 2017 to 2019, and marks these dates as non-work days in the schedule.

    Activity Identification

    The LANE Team is proposing a smart activity identification system in the Proposal Schedule, in which a unique alphanumeric is utilized. Each activity identification is broken down into five parts: Phase of Work, Work Area, Sub-Location, and Unique Identifier, described in detail below:

  • I-64 Widening Exit 200 to 205

    4 . 2 A T T A C H M E N T S T O T H E L E T T E R O F S U B M I T T A L Page | 8

    As an example is C 000 - 2680.

    Type of Work Phasing Sub-Stage Unique Identifier Types of work for the project with the abbreviations

    Construction phasing of the Project with the abbreviations:

    Stage of construction for Bridge B-624/B-625

    The last four digits in the activity identification structure are numeric increments starting with 1000, and incremented in steps of 10. This is done to leave ample room between activities so that additional activities may be inserted as necessary.

    A = Administration 000 = Project A = Stage 1 D = Design 101, 102, etc… =

    Phase 1 Area 1, Phase 1 Area 2 etc.

    B = Stage 2

    P = Procurement 201, 202, etc… = Phase 2 Area 1, Phase 2 Area 2, etc.

    C = Stage 3 C = Construction

    Plan and Strategy

    The LANE Team has developed a comprehensive MOT/phasing plan to complete the Project in a timely manner. This MOT plan constructs the Project in three phases, and incorporates the bridge widening and retrofitting work seamlessly with roadway operations. The Team’s key strategy for the design and construction is transparency between LANE and VDOT.

    Design

    As indicated in the Design section of the Schedule, we have broken down the design into several deliverable packages based upon the design effort put forth during the RFP design phase. The design packages will consist of the following E&S/SWPPP & MOT/SOC; Roadway, Traffic, ITS & Lighting; Bridge and Structures; separate geotechnical reports for Pavement /Earthwork and Structures/Foundations; Hydrologic & Hydraulic Analysis Report. This allows the Team to “fast track” the design review process making each package discipline specific to avoid delays from other discipline reviews. Each package will progress in the following order:

    1. Interdisciplinary coordination/VDOT over-the-shoulder review; 2. 90% submittal; 3. VDOT Review; 4. Approved for Construction (AFC) plans; 5. Final VDOT review with minor adjustments based on VDOT comments; 6. Release AFC by VDOT.

    A key aspect to this approach is initiating field investigations upon notice to proceed to provide the required windows for geotechnical reports and permits.

    Environmental /Permitting The schedule includes line items for development of SWPPP, JPA, and the VSMP approvals. The beginning of construction is tied to the VPDES and VSMP permits. Again, initiating field investigations and building upon the design work completed during the RFP our Team will work to eliminate impacts and coordinate with approving agencies to mitigate environmental impacts to streamline the approval process.

    ROW Acquisition ROW acquisition will be performed in accordance with state law and VDOT requirements. The initiation of the ROW Acquisition phase is dependent on the Approval of the Acquisition and Relocation Plan and obtaining the Notice to Commence Acquisition from VDOT.

  • I-64 Widening Exit 200 to 205

    4 . 2 A T T A C H M E N T S T O T H E L E T T E R O F S U B M I T T A L Page | 9

    Utility Relocation The LANE Team developed a utility matrix to evaluate the potential utility conflicts in the Project. Based on the result, the LANE Team has adjusted the design to mitigate the conflicts as much as possible. The Proposal Schedule incorporates utility relocation activities necessary to clear existing utilities from the work areas.

    Construction

    The LANE Team’s phases of construction on which this schedule is based, has been developed to mitigate impacts to the traveling public, delays to construction and ultimately, to facilitate successful completion of the project. Some potential delays include (but not limited to): utility relocation, environmental impacts, and right of way acquisition.

    Public Involvement / Public Relations

    In developing the schedule and construction sequences, the LANE Team put public safety first and included measures to limit disruptions to vehicular and pedestrian traffic. In collaboration with VDOT, the LANE Team will develop and utilize a paid advertising and marketing plan (AMP) per RFP Part 2 Section 2.12. Following the Notice to Proceed and during the Scope Validation Period, LANE will write the AMP for final review and approval from VDOT. It will guide Public Involvement activity throughout the Project, from start of construction to project completion.

    Sequence of Construction

    The LANE Team will follow the MOT/phasing plan developed for this Project (refer to the Conceptual Roadway Plans) and will construct the Project in three phases:

    • Phase 1: Involves the mill-and-overlay the existing roadway and the removal of the existing rumble strip on the outside shoulder on I-64. The scope of work also includes tree clearance on the outside shoulder. Following the tree clearance, the LANE Team will install the proposed ITS conduits and structure foundation located on the outside shoulder of I-64.

    • Phase 2: Upon completion of roadway work on I-64, traffic will shift towards the outside shoulder and the widening of I-64 in the median will begin. Work in this Phase includes the installation of MOT and temporary barrier wall, partial demolition of the existing roadway, earth work, drainage, subbase, asphalt paving, and other roadway work. The Team will construct the modification of the existing box culvert and pedestrian tunnel work in the median. The new cross-over will also be constructed before removing the existing one.

    o Bridge B624 and B625: Construction of the inside widening of the bridges will be concurrent with the roadway widening. This allows for continuous flow of traffic through the existing bridges. The scope of bridge work includes the partial demolition of the existing bridge deck, installation of SOE, construction of bridge substructure and superstructure, and approach slab. The substructure of the existing bridges will also be repaired.

    • Phase 3: Completing the Phase 2 roadway and bridge widening work allows the traffic to shift towards the inside lane on the roadway and starts the construction of the proposed sound barriers. At same time, the traffic will shift off the existing bridge deck which allows the remaining work on the existing bridges to be complete. This work includes the removal and replacement of the existing bridge deck, girders, bearing pads, and approach slab. The LANE Team will also install the remaining ITS structure, lighting, and signage, as well as final paving and striping, and mill-and-overlay.

    o Weight Station: The existing acceleration and deceleration lanes for the weight station will be extended. The scope of work includes MOT, demolition of existing roadway, earth work, asphalt paving, guard rail, and lighting.

    Critical Path

    The design critical path that will allow construction to begin is achieving approval of the environmental permits need for the project include Erosion and Sediment Control (E&S), Virginia Stormwater Management Permit

  • I-64 Widening Exit 200 to 205

    4 . 2 A T T A C H M E N T S T O T H E L E T T E R O F S U B M I T T A L Page | 10

    (VSMP), and the USACE Joint Permit Application (JPA). For this reason, we have divided design activities into separate plan packages and progressed design activities for E&S, SWPPP, and MOT/SOC to secure the necessary permits and advance construction activities. Upon notice to proceed, work will begin to identify the limits of disturbance and wetland impacts, to advance the E&S plans so that the JPA process can begin. The MOT/SOC plans are included with this early submittal so that clearing and grading can begin as soon as the JPA and VSMP permits are approved.

    Upon receipt of the JPA and VSMP permit, the Critical Path will switch to the construction phase, which starts with Phase 1 installation E&S and clearing of trees. This is followed by the ITS work on the shoulder. Phase 2 starts upon completion of Phase 1. The LANE Team will install MOT and switch traffic. This followed by the partial demolition of the existing roadway, then earth work, drainage, and subbase. The asphalt paving will start after the winter shut-down. Phase 2 will finish with guardrail construction. Phase 3 construction will start install MOT and switch traffic. The Critical Path will follow the superstructure replacement of Bridge B-624 and B-625, which includes removal and replacement of existing bridge deck and girders. Phase 3 will end with constructing the roadway tie-in to the bridges. Phase 3 completion will drive the Punch List work and the Final Completion of the Project.

    Key Assumptions

    The LANE Team made the following key assumptions on which our Representative Schedule is based:

    • Effective partnering and coordination efforts between the LANE Team, VDOT, the County, the adjacent active contract, and all the stakeholders.

    • Permit /TOY Restriction – Based upon our review of the environmental documents provided in the RFP we do not anticipate any TOY restrictions.

    • Utility Relocation – Based upon our initial design work we have not identified any time sensitive utility relocations. Protecting existing utilities in place, minor service connections for ITS and lighting, and the communications and electrical conduits associated with the pedestrian tunnel will be absorbed in the normal work schedule of activities.

    • ROW Acquisition – Since the three drainage easements identified in the RFP are still being cleared through the environmental approval process, our Team has separated the Right-of-Way plan package in the schedule. This will mitigate any lag time in the environmental process from impacting the deliverable schedule.

    Conclusion

    LANE has developed a Proposal Schedule and Proposal Schedule Narrative that demonstrates our understanding of the complexities and interrelationships of the technical elements of the Project. Additionally, our Proposal Schedule accounts for: internal plan reviews, VDOT plan reviews and approvals, environmental permitting, right of way acquisitions, utility relocations, and construction activities.

    The LANE Team is committed to develop an accurate and robust Baseline Schedule to better serve VDOT, stakeholders, and the traveling public. Once we have notice to proceed and the final design process begins, all team members will actively work to make this project more efficient, high quality and award winning.

  • Appendix

  • Attachment 4.0.1.1 Letter of Subm

    ittal and Attachments Checklist

  • ATTACHMENT 4.0.1.1 I-64 WIDENING EXIT 200 TO 205, CONTRACT ID NO. C00107458DB95

    LETTER OF SUBMITTAL AND ATTACHMENTS CHECKLIST

    1 of 2

    Offerors shall furnish a copy of this Letter of Submittal Checklist, with the page references added, with the Letter of Submittal.

    Technical Proposal Component Form (if any) RFP Part 1 Cross Reference Page

    Reference

    Letter of Submittal and Attachments Checklist Attachment 4.0.1.1 Section 4.0.1.1 Appendix

    Acknowledgement of RFP, Revisions, and/or Addenda

    Attachment 3.6 (Form C-78-

    RFP)

    Sections 3.6, 4.0.1.1 Appendix

    Letter of Submittal NA Sections 4.1 Pages 1-2

    Letter of Submittal on Offeror’s letterhead NA Section 4.1.1 1 Offeror’s official representative information NA Section 4.1.1 1 Authorized representative’s original signature NA Section 4.1.1 2 Declaration of intent NA Section 4.1.2 1 120 day declaration yes Section 4.1.3 1 Point of Contact information yes Section 4.1.4 1 Principal Officer information NA Section 4.1.5 2 Final Completion Date NA Section 4.1.6 2

    Proposal Payment Agreement or Waiver of Proposal Payment Attachment 9.3.1 or 9.3.2 Section 4.1.7 Appendix

    Certification Regarding Debarment Forms

    Attachment 11.8.6(a)

    Attachment 11.8.6(b)

    Section 4.1.8 Appendix

    Written statement of percent DBE participation NA Section 4.1.9 2

  • ATTACHMENT 4.0.1.1 I-64 WIDENING EXIT 200 TO 205, CONTRACT ID NO. C00107458DB95

    LETTER OF SUBMITTAL AND ATTACHMENTS CHECKLIST

    2 of 2

    Technical Proposal Component Form (if any) RFP Part 1 Cross Reference Page

    Reference Attachments to the Letter of Submittal NA Section 4.2 Pages 3-10

    Confirmation that the information provided in the SOQ submittal remains true and accurate or indicates that any requested changes were previously approved by VDOT

    NA

    Section 4.2.1 3

    Organizational chart with any updates since the SOQ submittal clearly identified NA Section 4.2.1 4

    Revised narrative when organizational chart includes updates since the SOQ submittal NA Section 4.2.1 3

    Conceptual Roadway Plans – Plan View NA Section 4.2.2 Volume II Conceptual Roadway Plans – Typical Sections NA Section 4.2.2 Volume II Conceptual Structural Plans – Elevation View NA Section 4.2.3 Volume II Conceptual Structural Plans – Transverse Section NA Section 4.2.3 Volume II Conceptual Structural Plans – Abutment and Pier Configurations NA Section 4.2.3 Volume II

    Proposal Schedule NA Section 4.2.4 Pages 5-10

    Proposal Schedule NA Section 4.2.4.1 Volume II Proposal Schedule Narrative NA Section 4.2.4.2 5-10 Proposal Schedule in electronic format (CD-ROM) NA Section 4.2.4 CD-ROM

  • Attachment 3.6 Form

    C-78-RFP

  • Attachment 9.3.1 Proposal Paym

    ent Agreement

  • Attachment 11.8.6 (a) Debarm

    ent Forms – Prim

    ary Covered Transactions

  • Attachment 11.8.6 (b) Debarm

    ent Forms – Lower Tier Covered Transactions

  • The Lane Construction Corporation14500 Avion Parkway

    Suite 200

    Chantilly, VA 20151

    Tel: (703) 222-5670

    www.laneconstruct.com

  • Letter of Submittal and Attachments (Volume II)

    I-64 Widening Exit 200 to 205 From Interstate 295 to Exit 205 (Bottom’s Bridge)Henrico and New Kent Counties, Virginia

    State Project No.: 0064-043-602Federal Project No.: NHPP-064-3 (499)Contract ID Number: C00107458DB95

    submitted to:

    Virginia Department of Transportation

    submitted by:

    The Lane Construction Corporation in association with:

    WSP USA Inc.

    >>ORIGINAL

  • 4.2.2 Conceptual Roadway Plans

  • TYPICAL SECTIONS I-64

    BL

    POINT OF FINISHED GRADE

    MATCH EXISTING SLOPESLOPE

    EXISTING

    MATCH

    CONST. ALIGNMENT

    CL

    SAWCUT LINE

    PAVED SHLDR. W/ UD-4

    VARIES

    LIMITS, SEE CROSS SECTIONS FOR DETAIL

    THE EBL AND WBL THROUGHOUT THE PROJECT

    SLOPES, ELEVATIONS, AND WIDTHS VARY BETWEEN

    RUMBLE STRIPS

    RUMBLE STRIPS

    *

    NOTES

    *

    1'

    ADDITIONAL EASEMENTS FOR UTILITY

    RELOCATIONS MAY BE REQUIRED

    BEYOND THE PROPOSED RIGHT- OF-

    WAY SHOWN ON THESE PLANS.

    VAR. DITCH BOTTOM

    AQUISITION OF RIGHT OF WAY.

    CONSTRUCTION OR FOR THE

    TO BE USED FOR ANY TYPE OF

    AND UNAPPROVED. THEY ARE NOT

    THESE PLANS ARE UNFINISHED

    10' Min.

    -2%

    PAVEMENT INTACT AND UNDAMAGED.

    PAVEMENT MARKING AND LEAVE UNDERLYING CONCRETE

    PERFORM SAW CUT IN ASPHALT CONCRETE 1' FROM

    NOT TO SCALE

    INSET A

    SEE INSET A

    567

    8

    12

    3

    4

    2

    3

    4

    5

    6

    7

    8

    SMA-12.5 (64E-22)

    2.0" Asphalt Concrete Surface Course,

    SMA-19.0 (64E-22)

    2.0" Asphalt Concrete Intermediate Course,

    BM-25.0D+0.4

    9.0" Asphalt Concrete Base Course,

    Type I, Size No. 21B

    6.0" Aggregate Base Material,

    SMA-12.5D

    2.0" Asphalt Concrete Surface Course,

    IM-19.0D

    2.0" Asphalt Concrete Intermediate Course,

    BM-25.0D

    9.0" Asphalt Concrete Base Course,

    (Connect To UD-4)

    Type I, Size No. 21B

    6.0" Aggregate Base Material,

    2A

    2A

    BL

    POINT OF FINISHED GRADE

    MATCH EXISTING SLOPE

    WIDTH AND NO. OF LANES VARIES

    2" MILLING AND OVERLAY

    SLOPE

    EXISTING

    MATCH

    CONST. ALIGNMENT

    CL

    SAWCUT LINE

    PAVED SHLDR. W/ UD-4

    VARIES

    LIMITS, SEE CROSS SECTIONS FOR DETAIL

    THE EBL AND WBL THROUGHOUT THE PROJECT

    SLOPES, ELEVATIONS, AND WIDTHS VARY BETWEEN

    12' 4'

    RUMBLE STRIPS

    RUMBLE STRIPS

    *6:1 &

    VAR.

    1'

    VAR. DITCH BOTTOM

    10' Min.

    -2%SEE INSET A

    VARIES 24' TO 12'

    1000' TAPER

    1

    PAVEMENT DESIGN (ROADWAY & SHOULDER)

    TOSTATION STATION

    TO1437+01.34 1457+14.42

    TOSTATION STATION

    TO1427+01.34 1437+01.34

    1.

    A 2:1 MAX.

    THE HIGH SIDE SLOPE WILL BE VARIABLE WITH

    4:1 TO 6:1 WITH 6:1 BEING IDEAL IN MOST LOCATIONS.

    LOW SIDE (EBL OR WBL) SLOPE WILL RANGE FROM

    WHERE GUARDRAIL IS REQUIRED

    EXTEND INSIDE SHOULDER 4 FEET ADDITIONAL

    GUARDRAIL TO BE BASED ON LENGTH OF NEED.

    CONST.I-64 EBL

    CONST.I-64 EBL

    POINT OF FINISHED GRADE

    SLOPE

    EXISTING

    MATCH

    BL

    SLOPE

    EXISTING

    MATCH

    RUMBLE STRIPS

    CONST.I-64 WBL

    OF ENTIRE SHOULDER2" MILLING AND OVERLAY

    4" DEPTH AND WIDTH = AS NEEDEDSHOULDER STRENGTHENING (FOR MOT)

    POINT OF FINISHED GRADE

    SLOPE

    EXISTING

    MATCH

    BL

    SLOPE

    EXISTING

    MATCH

    RUMBLE STRIPS

    CONST.I-64 WBL

    OF ENTIRE SHOULDER2" MILLING AND OVERLAY

    4" DEPTH AND WIDTH = AS NEEDEDSHOULDER STRENGTHENING (FOR MOT) WIDTH AND NO. OF LANES VARIES

    2" MILLING AND OVERLAY

    OF ENTIRE SHOULDER2" MILLING AND OVERLAY

    4" DEPTH AND WIDTH = AS NEEDEDSHOULDER STRENGTHENING (FOR MOT)

    OF ENTIRE SHOULDER2" MILLING AND OVERLAY

    4" DEPTH AND WIDTH = AS NEEDEDSHOULDER STRENGTHENING (FOR MOT)

    (I-64 EB - ALL 4 LANES SHIFT WITH 12' INSIDE WIDENING OVER 1000')

    2" MILLING AND OVERLAY

    2" MILLING AND OVERLAY

    TOTAL SHLDR.

    ST'D GS-11

    VAR.

    6:1 &

    0'-12' 4'

    TOTAL SHLDR.

    -2%ST'D GS-11

    VA.

    STATE

    ROUTE PROJECT

    VA.

    REVISEDSTATE

    STATE

    ROUTE PROJECTSHEET NO.

    PROJECT SHEET NO.

    DESIGN FEATURES RELATING TO CONSTRUCTION

    OR TO REGULATION AND CONTROL OF TRAFFIC

    MAY BE SUBJECT TO CHANGE AS DEEMED

    NECESSARY BY THE DEPARTMENT

    SURVEYED BY, DATE

    DESIGN BY

    SUBSURFACE UTILITY BY, DATE

    PROJECT MANAGER

    (TECHNICAL DISCIPLINE)

    (Location), Virginia

    VDOT (Division) or Co. Name

    (TECHNICAL DISCIPLINE)

    (Location), Virginia

    VDOT (Division) or Co. Name

    0064-043-602

    I-64RW-201, C-501

    0064-043-602, PE101,

    12:5413-JUN-2017\\PWICS\ics_workingdir\3264\213077_88\d10745802A.dgn

    JASON WILLIAMS, P.E. (804) 524-6145 (RICHMOND)

    WSP USA (757) 466-1732

  • TYPICAL SECTIONS I-64

    CONST. ALIGNMENT

    CL

    BL

    POINT OF FINISHED GRADE

    SLOPE

    EXISTING

    MATCH

    SAWCUT LINE

    PAVED SHLDR. W/ UD-4

    POINT OF FINISHED GRADE

    SLOPE

    EXISTING

    MATCH

    BL

    SAWCUT LINE

    PROJECT LIMITS, SEE CROSS SECTIONS FOR DETAIL

    SLOPES, ELEVATIONS, AND WIDTHS VARY THROUGHOUT THE

    SLOPE

    EXISTING

    MATCH SLOPE

    EXISTING

    MATCH

    2:1 MAX. 2:1 MA

    X.

    PAVED SHLDR. W/ UD-4

    4'12' 12' 4'

    LOW SIDE WHERE POSSIBLERUMBLE STRIPSRUMBLE STRIPS

    34' CLEARZONE

    RUMBLE STRIPSRUMBLE STRIPS

    0' TO 12', IN SHIFT AREA

    * *6:1 & VAR. 6

    :1 & V

    AR.

    NOTES

    *

    1'

    1'

    ADDITIONAL EASEMENTS FOR UTILITY

    RELOCATIONS MAY BE REQUIRED

    BEYOND THE PROPOSED RIGHT- OF-

    WAY SHOWN ON THESE PLANS.

    VAR. DITCH BOTTOM

    AQUISITION OF RIGHT OF WAY.

    CONSTRUCTION OR FOR THE

    TO BE USED FOR ANY TYPE OF

    AND UNAPPROVED. THEY ARE NOT

    THESE PLANS ARE UNFINISHED

    10' Min.

    10' Min.

    [TANGENT SECTIONS]

    -2%

    -2%

    CURVE SECTIONS BETWEEN THIS STATIONING

    SEE SHEET 2C FOR TYPICALS OF

    PAVEMENT INTACT AND UNDAMAGED.

    PAVEMENT MARKING AND LEAVE UNDERLYING CONCRETE

    PERFORM SAW CUT IN ASPHALT CONCRETE 1' FROM

    NOT TO SCALE

    INSET A

    SEE INSET A

    SEE INSET B

    56

    7

    8

    12

    3

    4

    5 67

    8

    12

    3

    4

    INSET B

    2

    3

    4

    5

    6

    7

    8

    SMA-12.5 (64E-22)

    2.0" Asphalt Concrete Surface Course,

    SMA-19.0 (64E-22)

    2.0" Asphalt Concrete Intermediate Course,

    BM-25.0D+0.4

    9.0" Asphalt Concrete Base Course,

    Type I, Size No. 21B

    6.0" Aggregate Base Material,

    SMA-12.5D

    2.0" Asphalt Concrete Surface Course,

    IM-19.0D

    2.0" Asphalt Concrete Intermediate Course,

    BM-25.0D

    9.0" Asphalt Concrete Base Course,

    (Connect To UD-4)

    Type I, Size No. 21B

    6.0" Aggregate Base Material,

    2B

    2B

    1

    PAVEMENT DESIGN (ROADWAY & SHOULDER)

    TOSTATION STATION

    1.

    A 2:1 MAX.

    THE HIGH SIDE SLOPE WILL BE VARIABLE WITH

    4:1 TO 6:1 WITH 6:1 BEING IDEAL IN MOST LOCATIONS.

    LOW SIDE (EBL OR WBL) SLOPE WILL RANGE FROM

    WHERE GUARDRAIL IS REQUIRED

    EXTEND INSIDE SHOULDER 4 FEET ADDITIONAL

    GUARDRAIL TO BE BASED ON LENGTH OF NEED.

    4" DEPTH AND WIDTH = AS NEEDEDSHOULDER STRENGTHENING (FOR MOT)

    OF ENTIRE SHOULDER2" MILLING AND OVERLAY

    2" MILLING AND OVERLAY 2" MILLING AND OVERLAY

    OF ENTIRE SHOULDER2" MILLING AND OVERLAY

    4" DEPTH AND WIDTH = AS NEEDEDSHOULDER STRENGTHENING (FOR MOT)

    CONST.I-64 EBL

    CONST.I-64 WBL

    TOTAL SHLDR.

    TOTAL SHLDR.

    ST'D GS-11

    ST'D GS-11

    TO1457+14.42 1597+78.46

    -2% ST'D GS-11-2%

    ST'D GS-11

    VA.

    STATE

    ROUTE PROJECT

    VA.

    REVISEDSTATE

    STATE

    ROUTE PROJECTSHEET NO.

    PROJECT SHEET NO.

    DESIGN FEATURES RELATING TO CONSTRUCTION

    OR TO REGULATION AND CONTROL OF TRAFFIC

    MAY BE SUBJECT TO CHANGE AS DEEMED

    NECESSARY BY THE DEPARTMENT

    SURVEYED BY, DATE

    DESIGN BY

    SUBSURFACE UTILITY BY, DATE

    PROJECT MANAGER

    (TECHNICAL DISCIPLINE)

    (Location), Virginia

    VDOT (Division) or Co. Name

    (TECHNICAL DISCIPLINE)

    (Location), Virginia

    VDOT (Division) or Co. Name

    0064-043-602

    I-64RW-201, C-501

    0064-043-602, PE101,

    12:5313-JUN-2017\\PWICS\ics_workingdir\3264\213077_42\d10745802B.dgn

    JASON WILLIAMS, P.E. (804) 524-6145 (RICHMOND)

    WSP USA (757) 466-1732

  • TYPICAL SECTIONS I-64

    ADDITIONAL EASEMENTS FOR UTILITY

    RELOCATIONS MAY BE REQUIRED

    BEYOND THE PROPOSED RIGHT- OF-

    WAY SHOWN ON THESE PLANS.

    AQUISITION OF RIGHT OF WAY.

    CONSTRUCTION OR FOR THE

    TO BE USED FOR ANY TYPE OF

    AND UNAPPROVED. THEY ARE NOT

    THESE PLANS ARE UNFINISHED

    CONST. ALIGNMENT

    CL

    BL BL

    10' Min.

    SAWCUT LINE

    1'

    RUMBLE STRIPS

    PAVED SHLDR. W/ UD-4

    PAVED SHLDR. W/ UD-4

    2:1 MAX.

    2:1 MAX.*6:1 & VAR.

    6:1 & VAR.*

    VAR. DITCH BOTTOM

    SAWCUT LINE

    1'

    RUMBLE STRIPS

    RUMBLE STRIPS

    SUPERELEVATION

    USE CORRECT SLOPE

    MATCH EXISTING

    SLOPE

    MATCH EXISTING

    SLOPE

    MATCH EXISTING

    12' 10' MIN.

    4'4'

    PROJECT LIMITS, SEE CROSS SECTIONS FOR DETAIL

    SLOPES, ELEVATIONS, AND WIDTHS VARY THROUGHOUT THE

    12'

    (SEE NOTE 2)

    TANGENT SECTIONS BETWEEN THIS STATIONING

    SEE SHEET 2B FOR TYPICAL OF

    [CURVE SECTIONS]

    CURVE TO RIGHT

    CONST. ALIGNMENT

    CL

    BLBL

    [CURVE SECTIONS]

    10' Min.

    SAWCUT LINE

    1'

    RUMBLE STRIPSRUMBLE STRIPS

    PAVED SHLDR. W/ UD-4

    PAVED SHLDR. W/ UD-4

    2:1 MAX. 2:1 M

    AX.*

    6:1 &

    VAR.

    6:1 & VAR.*VAR. DITCH BOTTOM

    SAWCUT LINE

    1'

    RUMBLE STRIPS

    RUMBLE STRIPS

    SUPERELEVATIONUSE CORRECT

    SLOPE

    MATCH EXISTING

    SLOPE

    MATCH EXISTING

    SLOPE

    MATCH EXISTING

    12'10' MIN.

    4'4'

    PROJECT LIMITS, SEE CROSS SECTIONS FOR DETAIL

    SLOPES, ELEVATIONS, AND WIDTHS VARY THROUGHOUT THE

    12'

    (SEE NOTE 2)

    CURVE TO LEFT

    TANGENT SECTIONS BETWEEN THIS STATIONING

    SEE SHEET 2B FOR TYPICAL OF

    NOTES

    *

    2.

    1.

    GUARDRAIL TO BE BASED ON LENGTH OF NEED.

    EXTEND INSIDE SHOULDER 4 FEET ADDITIONAL

    WHERE GUARDRAIL IS REQUIRED

    SEE DESIGN EXCEPTION FOR MORE INFORMATION

    REGARDING SUPERELEVATION IN CURVES

    LOW SIDE (EBL OR WBL) SLOPE WILL RANGE FROM

    4:1 TO 6:1 WITH 6:1 BEING IDEAL IN MOST LOCATIONS.

    THE HIGH SIDE SLOPE WILL BE VARIABLE WITH A

    2:1 MAX.

    PAVEMENT INTACT AND UNDAMAGED.

    PAVEMENT MARKING AND LEAVE UNDERLYING CONCRETE

    PERFORM SAW CUT IN ASPHALT CONCRETE 1' FROM

    NOT TO SCALE

    56

    7

    8

    12

    3

    56

    7

    8

    123

    4

    INSET A

    4

    RUMBLE STRIPS

    SEE INSET B

    SEE INSET A

    SEE INSET A

    (Connect To UD-4)

    Type I, Size No. 21B

    6.0" Aggregate Base Material,

    2

    3

    4

    5

    6

    7

    8

    BM-25.0D

    9.0" Asphalt Concrete Base Course,

    IM-19.0D

    2.0" Asphalt Concrete Intermediate Course,

    SMA-12.5D

    2.0" Asphalt Concrete Surface Course,

    Type I, Size No. 21B

    6.0" Aggregate Base Material,

    BM-25.0D+0.4

    9.0" Asphalt Concrete Base Course,

    SMA-19.0 (64E-22)

    2.0" Asphalt Concrete Intermediate Course,

    SMA-12.5 (64E-22)

    2.0" Asphalt Concrete Surface Course, 1

    PAVEMENT DESIGN (ROADWAY & SHOULDER)

    TOSTATION STATION

    TO1457+14.42 1597+78.46

    TO STATIONSTATION

    TO1457+14.42 1597+78.46

    2C

    2C

    4" DEPTH AND WIDTH = AS NEEDEDSHOULDER STRENGTHENING (FOR MOT)

    OF ENTIRE SHOULDER2" MILLING AND OVERLAY

    2" MILLING AND OVERLAY

    2" MILLING AND OVERLAY

    OF ENTIRE SHOULDER2" MILLING AND OVERLAY

    4" DEPTH AND WIDTH = AS NEEDEDSHOULDER STRENGTHENING (FOR MOT)

    CONST.I-64 WBL CONST.

    I-64 EBL

    CONST.I-64 EBLCONST.

    I-64 WBL

    2" MILLING AND OVERLAY

    2" MILLING AND OVERLAY

    OF ENTIRE SHOULDER2" MILLING AND OVERLAY

    4" DEPTH AND WIDTH = AS NEEDEDSHOULDER STRENGTHENING (FOR MOT)

    OF ENTIRE SHOULDER2" MILLING AND OVERLAY

    4" DEPTH AND WIDTH = AS NEEDEDSHOULDER STRENGTHENING (FOR MOT)

    POINT OF ROTATIONPOINT OF FINISHED GRADE

    POINT OF ROTATIONPOINT OF FINISHED GRADE

    POINT OF ROTATIONPOINT OF FINISHED GRADE

    POINT OF ROTATIONPOINT OF FINISHED GRADE

    STD. GS-11STD. GS-11

    TOTAL SHLDR.

    TOTAL SHLDR.

    STD. GS-11

    STD. GS-11SUPERELEVATIONUSE CORRECT

    SEE INSET B

    STD. GS-11

    SLOPE

    MATCH EXISTING STD. GS-11

    TOTAL SHLDR.

    TOTAL SHLDR.

    INSET B

    VA.

    STATE

    ROUTE PROJECT

    VA.

    REVISEDSTATE

    STATE

    ROUTE PROJECTSHEET NO.

    PROJECT SHEET NO.

    DESIGN FEATURES RELATING TO CONSTRUCTION

    OR TO REGULATION AND CONTROL OF TRAFFIC

    MAY BE SUBJECT TO CHANGE AS DEEMED

    NECESSARY BY THE DEPARTMENT

    SURVEYED BY, DATE

    DESIGN BY

    SUBSURFACE UTILITY BY, DATE

    PROJECT MANAGER

    (TECHNICAL DISCIPLINE)

    (Location), Virginia

    VDOT (Division) or Co. Name

    (TECHNICAL DISCIPLINE)

    (Location), Virginia

    VDOT (Division) or Co. Name

    0064-043-602

    I-64RW-201, C-501

    0064-043-602, PE101,

    12:5313-JUN-2017\\PWICS\ics_workingdir\3264\213077_41\d10745802C.dgn

    JASON WILLIAMS, P.E. (804) 524-6145 (RICHMOND)

    WSP USA (757) 466-1732

  • TYPICAL SECTIONS I-64

    CONST. ALIGNMENT

    CL

    VARI

    ES

    LIMITS, SEE CROSS SECTIONS FOR DETAIL

    THE EBL AND WBL THROUGHOUT THE PROJECT

    SLOPES, ELEVATIONS, AND WIDTHS VARY BETWEEN

    POINT OF FINISHED GRADE

    SLOPE

    EXISTING

    MATCH

    BL

    SAWCUT LINE

    SLOPE

    EXISTING

    MATCH

    PAVED SHLDR. W/ UD-4

    4'12'

    RUMBLE STRIPSSTRIPS

    RUMBLE

    NOTES

    *6:1 & VAR.

    *

    1'

    WBL & EBL

    ACCEL & DECEL LANES

    ADDITIONAL EASEMENTS FOR UTILITY

    RELOCATIONS MAY BE REQUIRED

    BEYOND THE PROPOSED RIGHT- OF-

    WAY SHOWN ON THESE PLANS.

    VAR. DITCH BOTTOM

    AQUISITION OF RIGHT OF WAY.

    CONSTRUCTION OR FOR THE

    TO BE USED FOR ANY TYPE OF

    AND UNAPPROVED. THEY ARE NOT

    THESE PLANS ARE UNFINISHED

    10' Min.

    -2%

    4 : 1

    PAVEMENT INTACT AND UNDAMAGED.

    PAVEMENT MARKING AND LEAVE UNDERLYING CONCRETE

    PERFORM SAW CUT IN ASPHALT CONCRETE 1' FROM

    SAWCUT LINE

    NOTE: MILL AND OVERLAY EXISTING RAMPS TO GORE AREA.

    CS-4

    WHERE GUARDRAIL IS REQUIRED

    EXTEND OUTSIDE SHOULDER 4 FEET ADDITIONAL

    GUARDRAIL TO BE BASED ON LENGTH OF NEED.

    NOT TO SCALE

    INSET A

    56

    7

    8

    12

    3

    4

    2

    3

    4

    5

    6

    7

    8

    3

    4

    SMA-12.5 (64E-22)

    2.0" Asphalt Concrete Surface Course,

    SMA-19.0 (64E-22)

    2.0" Asphalt Concrete Intermediate Course,

    BM-25.0D+0.4

    9.0" Asphalt Concrete Base Course,

    Type I, Size No. 21B

    6.0" Aggregate Base Material,

    SMA-12.5D

    2.0" Asphalt Concrete Surface Course,

    IM-19.0D

    2.0" Asphalt Concrete Intermediate Course,

    BM-25.0D

    9.0" Asphalt Concrete Base Course,

    INSET B

    56

    7

    8

    12

    SEE INSET A

    SEE INSET B

    (Connect To UD-4)

    Type I, Size No. 21B

    6.0" Aggregate Base Material,

    PAVEMENT DESIGN (ROADWAY & SHOULDER)

    1

    TOSTATION STATION

    TO1597+78.46 1609+77.46

    12.0'

    10.0' 12.0'

    1'

    EXIST. PAVE.

    A 2:1 MAX.

    THE HIGH SIDE SLOPE WILL BE VARIABLE WITH

    4:1 TO 6:1 WITH 6:1 BEING IDEAL IN MOST LOCATIONS.

    LOW SIDE (EBL OR WBL) SLOPE WILL RANGE FROM

    WHERE GUARDRAIL IS REQUIRED

    EXTEND INSIDE SHOULDER 4 FEET ADDITIONAL

    GUARDRAIL TO BE BASED ON LENGTH OF NEED. 1.

    SLOPE

    EXISTING

    MATCH

    CONST.I-64 WBL

    OF ENTIRE SHOULDER2" MILLING AND OVERLAY

    4" DEPTH AND WIDTH = AS NEEDEDSHOULDER STRENGTHENING (FOR MOT)

    2" MILLING AND OVERLAY

    BL

    CONST.I-64 WBL

    CONST. ALIGNMENT

    CL

    2D

    2D

    STA. 1465+09.99 TO STA. 1475+76.36 WBL (ON RAMP)

    STA. 1501+51.36 TO STA. 1507+98.43 WBL (OFF RAMP)

    STA. 1474+37.45 TO STA. 1480+76.08 EBL (OFF RAMP)

    STA. 1504+77.36 TO STA. 1517+42.46 EBL (ON RAMP)

    POINT OF FINISHED GRADE

    SLOPE

    EXISTING

    MATCH

    BL

    SLOPE

    EXISTING

    MATCH

    RUMBLE STRIPS

    CONST.I-64 EBL

    OF ENTIRE SHOULDER2" MILLING AND OVERLAY

    4" DEPTH AND WIDTH = AS NEEDEDSHOULDER STRENGTHENING (FOR MOT)

    2" MILLING AND OVERLAY

    TOTAL SHLDR.

    STD. GS11

    PAVED SHLDR. W/ UD-4

    TOTAL SHLDR.

    2" MILLING AND OVERLAY

    VA.

    STATE

    ROUTE PROJECT

    VA.

    REVISEDSTATE

    STATE

    ROUTE PROJECTSHEET NO.

    PROJECT SHEET NO.

    DESIGN FEATURES RELATING TO CONSTRUCTION

    OR TO REGULATION AND CONTROL OF TRAFFIC

    MAY BE SUBJECT TO CHANGE AS DEEMED

    NECESSARY BY THE DEPARTMENT

    SURVEYED BY, DATE

    DESIGN BY

    SUBSURFACE UTILITY BY, DATE

    PROJECT MANAGER

    (TECHNICAL DISCIPLINE)

    (Location), Virginia

    VDOT (Division) or Co. Name

    (TECHNICAL DISCIPLINE)

    (Location), Virginia

    VDOT (Division) or Co. Name

    0064-043-602

    I-64RW-201, C-501

    0064-043-602, PE101,

    12:5313-JUN-2017\\PWICS\ics_workingdir\3264\213077_44\d10745802D.dgn

    JASON WILLIAMS, P.E. (804) 524-6145 (RICHMOND)

    WSP USA (757) 466-1732

  • TYPICAL SECTIONS I-64ADDITIONAL EASEMENTS FOR UTILITY

    RELOCATIONS MAY BE REQUIRED

    BEYOND THE PROPOSED RIGHT- OF-

    WAY SHOWN ON THESE PLANS.

    AQUISITION OF RIGHT OF WAY.

    CONSTRUCTION OR FOR THE

    TO BE USED FOR ANY TYPE OF

    AND UNAPPROVED. THEY ARE NOT

    THESE PLANS ARE UNFINISHED

    CONST. ALIGNMENT

    CL

    BL

    10' Min.

    SAWCUT LINE

    1'

    RUMBLE STRIPS

    PAVED SHLDR. W/ UD-4

    PAVED SHLDR. W/ UD-4

    2:1 MAX.

    2:1 MAX.*6:1 & VAR.

    6:1 & VAR.*

    VAR. DITCH BOTTOM

    SAWCUT LINE

    1'

    RUMBLE STRIPS

    RUMBLE STRIPS

    10' Min.

    4'

    4'

    PROJECT LIMITS, SEE CROSS SECTIONS FOR DETAIL

    SLOPES, ELEVATIONS, AND WIDTHS VARY THROUGHOUT THE

    CURVE TO RIGHT

    NOTES

    *

    GUARDRAIL TO BE BASED ON LENGTH OF NEED.

    EXTEND INSIDE SHOULDER 4 FEET ADDITIONAL

    WHERE GUARDRAIL IS REQUIRED

    SEE DESIGN EXCEPTION FOR MORE INFORMATION

    REGARDING SUPERELEVATION IN CURVES

    LOW SIDE (EBL OR WBL) SLOPE WILL RANGE FROM

    4:1 TO 6:1 WITH 6:1 BEING IDEAL IN MOST LOCATIONS.

    THE HIGH SIDE SLOPE WILL BE VARIABLE WITH A

    2:1 MAX.

    PAVEMENT INTACT AND UNDAMAGED.

    PAVEMENT MARKING AND LEAVE UNDERLYING CONCRETE

    PERFORM SAW CUT IN ASPHALT CONCRETE 1' FROM

    NOT TO SCALE

    INSET A

    56

    7

    8

    12

    35

    6

    7

    8

    12

    3

    4

    INSET B

    4

    SEE INSET B

    SEE INSET A

    (Connect To UD-4)

    Type I, Size No. 21B

    6.0" Aggregate Base Material,

    2

    3

    4

    5

    6

    7

    8

    BM-25.0D

    9.0" Asphalt Concrete Base Course,

    IM-19.0D

    2.0" Asphalt Concrete Intermediate Course,

    SMA-12.5D

    2.0" Asphalt Concrete Surface Course,

    Type I, Size No. 21B

    6.0" Aggregate Base Material,

    BM-25.0D+0.4

    9.0" Asphalt Concrete Base Course,

    SMA-19.0 (64E-22)

    2.0" Asphalt Concrete Intermediate Course,

    SMA-12.5 (64E-22)

    2.0" Asphalt Concrete Surface Course,

    2%2%

    BL

    2% 2%

    CONST. ALIGNMENT

    CL

    BL

    14' Min.

    SAWCUT LINE

    1'

    RUMBLE STRIPS

    PAVED SHLDR. W/ UD-4

    PAVED SHLDR. W/ UD-4

    2:1 M

    AX.2:1 MAX.*

    6:1 & VAR.6:1 & V

    AR.*

    VAR. DITCH BOTTOMSAWCUT LINE

    1'

    RUMBLE STRIPS

    RUMBLE STRIPS

    14' Min.

    PROJECT LIMITS, SEE CROSS SECTIONS FOR DETAIL

    SLOPES, ELEVATIONS, AND WIDTHS VARY THROUGHOUT THE

    CURVE TO RIGHT

    RUMBLE STRIPS

    SEE INSET BSEE INSET A

    BL

    PAVED SHLDR. W/ UD-4

    2:1 M

    AX.

    6:1 & V

    AR.*

    SAWCUT LINE

    1'

    RUMBLE STRIPS

    POINT OF FINISHED GRADE

    14' MIN.

    10'

    SEE INSET A

    VAR. DITCH BOTTOMDRAINAGE

    MAINTAIN POSITIVE

    VAR. SUBBASE MAT'L DEPTH

    GUARDRAIL IS REQUIRED 4 FEET ADDITIONAL WHEREEXTEND OUTSIDE SHOULDER

    ON LENGTH OF NEED. GUARDRAIL TO BE BASED

    6:1 &

    VAR.

    2%

    3.6% MAX

    3.6% MAX4.3% MAX4.3% MAX

    RUMBLE STRIPS

    [SUPERELVATED SECTION] [SUPERELVATED SECTION]

    [CROWN SHIFT SECTION]

    [CROWN SHIFT SECTION]

    [REVERSE CROWN SECTION]

    FINISHED GRADE

    POINT OF EXISTING CROWM

    7' MAXEXISTING CROWN

    7' MAX

    FINISHED GRADE

    POINT OF

    2E

    2E

    TO STATIONSTATION

    TO1562+56.38 1570+50.28

    TO STATIONSTATION

    TO1563+50.00 1568+36.68

    TO1550+26.70 1556+50.83

    TO STATIONSTATION

    TO1556+50.83 1563+50.00

    TO STATIONSTATION

    TO STATIONSTATION

    TO1550+26.87 1562+56.38

    1

    PAVEMENT DESIGN (ROADWAY & SHOULDER)

    10' to 13.17'

    10' to 13.17'

    2.

    1.

    CONST. I-64 WBL

    CONST.I-64 EBL

    CONST.I-64 WBL

    CONST.I-64 EBL

    OF ENTIRE SHOULDER 2" MILLING AND OVERLAY

    4" DEPTH AND WIDTH = AS NEEDEDSHOULDER STRENGTHENING (FOR MOT)

    OF ENTIRE SHOULDER2" MILLING AND OVERLAY

    4" DEPTH AND WIDTH = AS NEEDEDSHOULDER STRENGTHENING (FOR MOT)

    4" DEPTH AND WIDTH = AS NEEDEDSHOULDER STRENGTHENING (FOR MOT)

    OF ENTIRE SHOULDER2" MILLING AND OVERLAY

    4" DEPTH AND WIDTH = AS NEEDEDSHOULDER STRENGTHENING (FOR MOT)

    OVERLAY OF ENTIRE SHOULDER2" MILLING AND VARIABLE DEPTH

    POINT OF ROTATIONPOINT OF FINISHED GRADE

    POINT OF ROTATIONPOINT OF FINISHED GRADE

    DEPTH OVERLAY2" MILLING AND VARIABLE

    DEPTH OVERLAY2" MILLING AND VARIABLE

    DEPTH OVERLAY2" MILLING AND VARIABLE

    DEPTH OVERLAY2" MILLING AND VARIABLE

    TOTAL SHLDR.

    TOTAL SHLDR.

    DEPTH OVERLAY2" MILLING AND VARIABLE

    TOTAL SHLDR.

    ST'D GS-11

    ST'D GS-11

    ST'D GS-11

    ST'D GS-11

    ST'D GS-11

    12' to 19'+/- 12' to 19'+/-

    12' to 19'+/- 12' to 19'+/-

    12' to 19'+/-

    VA.

    STATE

    ROUTE PROJECT

    VA.

    REVISEDSTATE

    STATE

    ROUTE PROJECTSHEET NO.

    PROJECT SHEET NO.

    DESIGN FEATURES RELATING TO CONSTRUCTION

    OR TO REGULATION AND CONTROL OF TRAFFIC

    MAY BE SUBJECT TO CHANGE AS DEEMED

    NECESSARY BY THE DEPARTMENT

    SURVEYED BY, DATE

    DESIGN BY

    SUBSURFACE UTILITY BY, DATE

    PROJECT MANAGER

    (TECHNICAL DISCIPLINE)

    (Location), Virginia

    VDOT (Division) or Co. Name

    (TECHNICAL DISCIPLINE)

    (Location), Virginia

    VDOT (Division) or Co. Name

    0064-043-602

    I-64RW-201, C-501

    0064-043-602, PE101,

    12:5413-JUN-2017\\PWICS\ics_workingdir\3264\213077_60\d10745802E.dgn

    JASON WILLIAMS, P.E. (804) 524-6145 (RICHMOND)

    WSP USA (757) 466-1732

  • Ditch

    Wet

    Weather

    Disipator

    Energy

    Cherry

    4"

    Cedar

    6"

    Sign Post in Conc.0.5' x 0.3' Metal

    Rap

    Rip

    Inv. Out = 137.97Inv. In = 138.72In Pl. 18" CMP

    PondD

    etentio

    n

    Rap

    Rip

    In Pl. FESInv. Out = 137.91Inv. In = 138.14In Pl. 15" Conc. PipeIn Pl. FES

    In Pl. FESInv. Out = 133.88Inv. In = 134.33In Pl. 18" Conc. PipeIn Pl. FES

    Inv. Out =

    133.95

    In Pl. 2

    4" Conc. Pipe

    Rim =

    137.95In P

    l. DI

    "Tee" In

    tersecti

    on To

    Box Culvert

    Inv. Out =

    133.43

    In Pl. 14

    4.4'-24

    " Conc. Pip

    e

    Inv. In

    = 133.7

    8Rim =

    137.43In P

    l. DI

    Asphalt

    Wet Weather Ditch

    Asphalt Shoulder

    Asphalt Shoulder

    Grass

    Grass

    Grass

    Site

    Cell Tower

    Gravel

    Tank

    Asphalt

    Plastic Delineators Posts

    Gate

    Metal Sig

    nMetal Sig

    n

    Metal Sig

    n

    Metal Sign

    Twin 8" Oak

    8' Chain Link Fence

    Gums

    6-Sweet

    NOT HELD for

    right-of-way purp

    osesNote: "**

    " denotes existing

    monumentation

    Inv. O

    ut

    = 12

    6.8

    6Flared End Section

    In Pl. 114.5' - 42"

    RCP

    Inv. In =

    134.2

    7Flared End Section

    In Pl. 110.6'-42"

    RCP

    Inv. O

    ut

    = 13

    2.3

    8In

    v. In =

    132.4

    4Top =

    136.8

    3(B)

    Yard Inlet In

    Media

    n

    In Pl. 17

    4.5'-42"

    RCP

    Inv. O

    ut

    = 13

    1.06

    Inv. In =

    131.18

    Top =

    137.3

    3(A)

    Yard Inlet In

    Media

    n

    In Pl. 218.8'-42"

    RCP

    Inv. O

    ut

    = 12

    9.0

    4In

    v. In =

    129.17

    Top =

    135.0

    4Yard Inlet In

    Media

    n

    Inv. O

    ut

    = 12

    6.0

    9Flared End Section

    In Pl. 18

    0.8'-42"

    RCP

    Inv. O

    ut

    = 13

    1.80

    Inv. In =

    131.82

    Top =

    138.2

    1

    (A)

    Grate Inlet In

    Media

    n

    In Pl. 16

    1.7'-30"

    RCP

    Inv. O

    ut

    = 12

    8.3

    6In

    v. In =

    128.4

    3Top =

    134.5

    6(B)

    Yard Inlet In

    Media

    n

    In Pl. 10

    4.7'-30"

    RCP

    Inv. O

    ut

    = 13

    1.70

    Top =

    135.3

    4Yard Inlet In

    Media

    n

    In Pl. 14

    2.4'-30"

    RCP

    Inv. O

    ut

    = 13

    0.11

    Inv. In =

    130.2

    2Top =

    134.9

    3(A)

    Yard Inlet In

    Media

    n

    Conc. Slab55" X 60"

    Project # 0095-043-105, RW203

    Ex. Variable R/W Per VDOT

    SlabConc.

    SlabConc.

    SlabConc.

    SlabConc.

    69.0

    1'R

    M-2

    +43.2

    0

    88.7

    9'

    RM-2

    +47.7

    9

    Project # 0095-043-105, RW203

    Ex. Variable R/W Per VDOT

    92.12'

    IP

    +28.5

    0

    216.9

    9'

    IP

    +42.6

    7 204.15'

    IP

    +37.9

    6

    RM-2

    +75.8

    8

    Flow Inv. = 127.86Top = 134.43Yard Inlet

    Flow Inv. = 126.83Top = 133.93Yard Inlet

    (C) In

    v. O

    ut

    = 12

    6.7

    7(B) In

    v. O

    ut

    = 12

    6.7

    8(A) In

    v. O

    ut

    = 12

    6.8

    2Top =

    133.4

    0Conc. H

    ead

    wall

    Asphalt

    AsphaltAsphalt

    AsphaltAsphalt

    AsphaltAsphalt

    4' Woven Wire Fence

    4' Woven Wi

    re Fence

    4' Woven Wire Fence

    4' Woven Wire Fence

    4' Conc. V-Ditch

    (B)

    Guardrail

    GuardrailAsphalt

    (A)

    (B)

    (C)

    (A)

    (A)

    (B)

    2-4" Cedars

    Asphalt Shoulder

    Asphalt Shoulder

    Asphalt ShoulderAsphalt Shoulder

    Asphalt Shoulder

    Asphalt Shoulder

    Asphalt Shoulder

    Asphalt Shoulder

    Asphalt Shoulder

    Asphalt Shoulder

    Asphalt Shoulder

    Exist. L/A Line

    Exist. L/A Line

    Exist. L/A Line

    Ex. Variable R/W Per VDOT Project # 0095-043-105, RW203

    Exist. L/A Line

    Ex. Variab

    le R/W Pe

    r VDOT Pr

    oject # 00

    95-043-105

    , RW203

    Cedar

    Small C

    edars Cedar

    Grass

    Grass

    Grass

    Grass

    Access Ramp

    Grass

    Grass

    Grass

    Info. Sig

    n Posts (2)

    Access Ramp

    Planted Field

    D.B. 2043, PG. 2005

    29564 ASSOCIATES

    (S74°22'41"E 857.22')

    (S74°22'23"E 359.42')

    COOKE PROPERTIES, L.L.C.

    183.518 Ac.

    D.B. 2566, PG. 1714

    P.B. 84, PG. 244

    P.B. 84, PG. 244

    20.491 Ac.

    (N65°10'11"W 96.16')

    (N81°21'57"W

    638.96')

    (N63°52'19"W 475.80')

    ((N69°21'47"W 464.98')

    6" Cherry6" Cherry

    6" Cherry

    Asphalt Shoulder

    Asphalt Shoulder

    Asphalt Shoulder

    In Pl.

    Underdrain

    Asphalt Sho

    ulder

    N65°07'36"W 96.15'

    S74°21'16"E 359.37'

    Asphalt Shoulder

    Inv. O

    ut

    = 119.9

    8In

    v. In =

    121.18

    In Pl. 15" R

    CP

    Woods

    Woods

    Woods

    Overhead Sig

    n

    Mixed Pines And Hardwoods

    Mixed Pines A

    nd Hardwoods

    E

    E

    E

    E

    EEHH

    EHH

    T

    T

    T

    T

    T

    T

    (SIG)

    Camera Pole #430407FOHH

    THH

    TPED #2630-OWTHH

    EHH

    FOHH

    FOHH, Fiber Marker

    EHH, Elec. Ped. #NN26

    Elec. Box

    23.8

    4

    17.9

    1

    21.97

    27.16

    EH

    HEH

    H

    E

    E

    EE

    HH

    E

    EOI

    PP (N

    o #)

    E

    EE

    E

    EH

    H

    001

    I-64 WBL CONST. BL

    CONSTRUCTION ALIGNMENT CL

    I-64 EBL CONST. BL

    STATION 1396+55.15

    I-64 CONSTRUCTION CENTERLINE

    BEGIN CONSTRUCTION

    OUTLET PROTECTION

    EASEMENT

    DRAINAGE

    PERMANENT

    ex3-1

    ex3-2

    ex3-3

    ex3-4

    ex3-6

    ex3-5

    ex3-7

    ex3-8

    ex4-4

    BMP: Grassed Swale

    BMP: Grassed Swale

    BMP: Grassed Swale BMP: Grassed Swale

    BMP: Grassed Swale

    SWM-6

    SWM-10SWM-11 SWM-12

    SWM-13

    SWM-4

    SWM-5

    SWM-1

    SWM-2

    BMP: Grassed Swale

    BMP: Grassed Swale

    BMP: Grassed Swale

    BMP: Grassed Swale

    VA.

    STATE

    ROUTE PROJECT

    VA.

    REVISEDSTATE

    STATE

    ROUTE PROJECTSHEET NO.

    PROJECT SHEET NO.

    DESIGN FEATURES RELATING TO CONSTRUCTION

    OR TO REGULATION AND CONTROL OF TRAFFIC

    MAY BE SUBJECT TO CHANGE AS DEEMED

    NECESSARY BY THE DEPARTMENT

    SURVEYED BY, DATE

    DESIGN BY

    SUBSURFACE UTILITY BY, DATE

    PROJECT MANAGER

    (TECHNICAL DISCIPLINE)

    (Location), Virginia

    VDOT (Division) or Co. Name

    (TECHNICAL DISCIPLINE)

    (Location), Virginia

    VDOT (Division) or Co. Name

    0064-043-602

    I-64RW-201, C-501

    0064-043-602, PE101,

    13:3713-JUN-2017E:\ics_workingdir\1260\213077_11\d10745803.dgn

    JASON WILLIAMS, P.E. (804) 524-6145 (RICHMOND)

    WSP USA (757) 466-1732

    C

    C

    PAVED SHOULDER

    PROP LIGHT & JB

    LIMITS OF CLEARING

    SWM AREAS

    EXISTING CCTV

    CCTV

    LIMITS IN CUTS

    DENOTES CONSTRUCTION

    LIMITS IN FILLS

    DENOTES CONSTRUCTION

    LEGEND:

    FULL DEPTH PAVEMENT

    CROSSOVER PAVEMENT

    C

    F

    (TYPE I)ROCK CHECK DAM

    TRAVEL LANESMILL & OVERLAY

    PAVED SHOULDERMILL & OVERLAY

    EXISTING PAVEMENTDEMOLITION OF

    12' LANE

    WETLAND BOUNDARY

    C

    1386

    1387

    1388

    1389

    1390

    3386

    3387

    3388

    3389

    3390

    Electric: Dominion Virginia Power

    Gas: Virginia Natural Gas (VNG)

    Sanitry: Henrico County DPU

    New Kent County Public Works

    Telephone: Verizon

    UTILITY OWNERS:

    Traffic: Virginia Department of Transportation

    T.V. : Comcast

    Cox Communications

    Water: Henrico County DPU

    New Kent County Public Works

    Dominion Virginia Power Transmission

    Curve 64_CL_1

    PI = 1397+86.86

    T = 539.17'

    L = 1,078.28'

    R = 44,000.00'

    1392+47.69PC =

    PT = 1403+25.97

    1393

    1394

    1395

    1396

    1397

    1398

    1399

    1400

    1401

    1402

    1403

    1404

    1405

    1406

    1407

    PT

    2393

    2394

    2395

    2396

    2397

    2398

    2399

    2400

    2401

    2402

    2403

    2404

    2405

    2406

    2407

    3397

    3398

    3399

    3400

    3401

    3402

    3403

    3404

    3405

    3406

    3407

    PT

    PT

    Curve 64_EB_1

    PI = 3397+86.20

    T = 538.48'

    L = 1,076.91'

    R = 43,944.00'

    3392+47.72PC =

    PT = 3403+24.63

    Curve 64_WB_1

    PI = 2397+87.50

    T = 539.85'

    L = 1,079.65'

    R = 44,056.00'

    2392+47.65PC =

    PT = 2403+27.30

    V = 70 MPH V = 70 MPH V = 70 MPH

    MA

    TC

    H

    LIN

    E

    ST

    A

    1407

    +50

    SH

    EE

    T

    4

    3A

    REFERENCES

    ( PROFILES, DETAIL & DRAINAGE

    DESCRIPTION SHEETS, ETC. )

    0

    SCALE

    50' 100'3

    3

    Exist. CCTV

    THESE PLANS ARE UNFINISHED

    AND UNAPPROVED AND ARE NOT

    TO BE USED FOR ANY TYPE

    OF CONSTRUCTION OR THE

    ACQUISITION OF RIGHT OF WAY.

    Structure To Be Abandoned

    Structure To Be Removed

    Plugged & Filled

    Pipe To Be Abandoned,

    Pipe To Be Removed

    Or Removed Pipe

    Pay Limit For Abandoned

    CONSTRUCTION ALIGNMENT CL

    I-64 EBL CONST. BL

    Mainline Profile

    64_WB_1

    64_CL_1

    64_EB_1

  • VA.

    STATE

    ROUTE PROJECT

    VA.

    REVISEDSTATE

    STATE

    ROUTE PROJECTSHEET NO.

    DESIGN FEATURES RELATING TO CONSTRUCTION

    OR TO REGULATION AND CONTROL OF TRAFFIC

    MAY BE SUBJECT TO CHANGE AS DEEMED

    NECESSARY BY THE DEPARTMENT

    PROJECT SHEET NO.

    SURVEYED BY, DATE

    DESIGN BY

    SUBSURFACE UTILITY BY, DATE

    PROJECT MANAGER

    (TECHNICAL DISCIPLINE)

    (Location), Virginia

    VDOT (Division) or Co. Name

    E:\ics_workingdir\1260\213077_28\d10745803A.dgn 13-JUN-2017 13:37

    0064-043-602

    I-64RW-201, C-501

    0064-043-602, PE101,

    WSP | Parsons Brinckerhoff (757) 466-1732

    0 FT 50 FT

    0 FT

    10 FT

    3394+00.00 3395+00.00 3396+00.00 3397+00.00 3398+00.00 3399+00.00 3400+00.00 3401+00.00 3402+00.00 3403+00.00 3404+00.00 3405+00.00 3406+00.00 3407+00.00

    139.6

    8

    139.5

    1

    139.3

    9

    139.3

    1

    139.2

    5

    139.19

    139.2

    1

    139.2

    7

    139.3

    6

    139.4

    8

    139.6

    4

    139.8

    7

    140.15

    140.4

    2

    140.6

    8

    140.9

    8

    141.27

    141.56

    141.81

    142.13

    142.4

    7

    142.7

    7

    143.0

    5

    143.3

    5

    143.6

    4

    143.8

    9

    144.15

    EXISTING GRADE

    2395+00.00 2396+00.00 2397+00.00 2398+00.00 2399+00.00 2400+00.00 2401+00.00 2402+00.00 2403+00.00 2404+00.00 2405+00.00 2406+00.00 2407+00.00

    141.27

    141.43

    141.61

    141.89

    142.15

    142.4

    5

    142.8

    0

    143.16

    143.5

    6

    143.9

    3

    144.2

    9

    144.7

    0

    145.11

    145.5

    1

    145.8

    9

    146.2

    9

    146.6

    9

    147.0

    7

    147.4

    9

    147.9

    1

    148.3

    8

    148.7

    6

    149.18

    149.5

    4

    149.9

    0

    150.2

    0

    150.4

    5

    EXISTING GRADE

    0.63 % (APPROX.)

    100_

    105_

    110_

    115_

    120_

    125_

    130_

    135_

    140_

    145_

    150_

    100_

    105_

    110_

    115_

    120_

    125_

    130_

    135_

    140_

    145_

    150_

    3A

    3A

    90_

    95_

    100_

    105_

    110_

    115_

    120_

    125_

    130_

    135_

    140_

    145_

    150_

    155_

    90_

    95_

    100_

    105_

    110_

    115_

    120_

    125_

    130_

    135_

    140_

    145_

    150_

    155_

    MA

    TC

    H

    LIN

    E

    ST

    A 3407+5

    0

    EB

    SH

    EE

    T 4

    AM

    AT

    CH

    LIN

    E

    ST

    A 2407+5

    0

    WB

    SH

    EE

    T 4

    A

    I-64 WB

    I-64 EB

  • In Pl. 17

    4.5'-42"

    RCP

    Inv. In =

    136.16

    Flared End Section

    In Pl. 14

    8.6'-42"

    RCP

    Inv. O

    ut

    = 13

    3.3

    3

    Inv. In =

    133.3

    3

    Top =

    139.7

    0

    (B)

    Grate Inlet In

    Media

    nIn Pl. 18

    0.8'-42"

    RCP

    Inv. O

    ut

    = 13

    1.80

    Inv. In =

    131.82

    Top =

    138.2

    1

    (A)

    Grate Inlet In

    Media

    n

    Metal Sig

    n in Conc.

    0.3' x 0.5'

    Metal Sig

    n in Conc.

    0.4' x 1.1'

    Metal Post in Conc.

    0.4' x 1.1'

    Project # 0095-043-10

    5, RW203Ex. Variable R/W

    Per VDOT

    GarageCinderb

    lock2 Bay

    (Abandoned)

    Dwelling1 Sty. W

    ood Frame

    ShedFrameWood

    ShedFrameWood

    90.3

    0'

    RM-2

    +25.9

    2

    95.3

    2'

    RM-2 +4

    6.0

    9

    PL

    AN

    D

    CO

    NS

    TA

    NC

    E

    MA

    RY

    WE

    ST

    BR

    OO

    K

    J. J. W

    ES

    TB

    RO

    OK

    93.3

    8'

    IP

    +82.3

    9

    139.2

    3'

    IP

    +90.7

    9

    105.9

    5'

    IP

    +62.5

    4

    187.7

    1'

    IP

    +50.3

    5

    141.80'

    IP

    +19.9

    1

    105.9

    5'

    IP

    +62.5

    4

    156.6

    5'

    Pip

    e +3

    4.0

    7

    246.3

    0'

    IP

    +01.34

    104.9

    9'

    RM-2

    +24.0

    1

    PL

    PL

    PL

    Asphalt

    Asphalt Asphalt

    4' Woven Wire Fence

    4' Woven Wire Fence

    4' Woven Wire Fence

    4' Woven Wire Fence

    18"

    Cherry

    18"

    Cherry

    18"

    Cherry

    (A)

    (B)

    2-10"

    Cedars

    Asphalt Shoulder

    Asphalt Shoulder

    Asphalt Shoulder

    Asphalt Shoulder

    Asphalt Shoulder

    Asphalt Shoulder

    Asphalt Shoulder

    Asphalt Shoulder

    Asphalt Shoulder

    Exist. L/A Line

    Ex. Variable R/W Per VDOT Project # 0095-043-105, RW203

    Ex. Variable R/W Per VDOT Project # 0095-043-105, RW203

    Ex. Variable R/W Per VDOT Project # 0095-043-105, RW203

    Exist. L/A Line

    Exist. L/A Line

    Grass

    Grass

    Planted Field

    Cedar

    Grass

    Grass

    Access Ramp

    Pines

    Mixed Medium Woods

    Cedar

    Mixed Large Hardwoods

    Mixed Medium Woods

    Grass

    (S11°2

    9'2

    9"W 446.6

    1')(S75°57'52

    "E 383.72')

    (S71°00'24"E 390.86')

    (S74°22'23"E 359.42')

    W. PARRY WRIGHT, JR.

    5 Ac.

    (N11°13'15"E 513.6

    0')

    AND LILLIAN W. WRIGHTD.B. 536, PG. 348

    AN

    D

    MA

    RY C

    AR

    OL

    YN

    BO

    WYE

    R (S11°2

    7'10"W 531.91')

    HO

    WA

    RD

    ED

    WA

    RD

    BO

    WYE

    R

    (N17°4

    9'3

    4"E 12

    88.4

    7')

    (N55°26'10"W 90.41')

    (N65°01'30"W 468.00')

    (N61°53'58"W 353.94')

    (N61°46'38"W 182.93')

    (N62°28'25"W 277.49')

    COOKE PROPERTIES, L.L.C.

    46.332 Ac.

    (S11°2

    9'2

    9"W 12

    88.3

    4')

    D.B. 2566, PG. 1714

    Shed

    2-2

    1" O

    aks

    Shed

    2-10"

    Apple Trees

    10"

    Apple Tree

    4' Conc. V-Ditch

    1.24

    Ac.

    D.B. 1070, P

    G. 8

    S71°21'33"E 468.06'

    S71°00'57"E 390.64'

    21.18 Ac.

    P.B. 86, PG. 95

    VIENNA FINANCE, INC.D.B. 2303, PG. 760

    S61°50'34"E 186.33'S61°37'19"E 87.12'

    S75°57'30"E 383.76'

    S61°54'36"E 353.89'

    Metal Sig

    n

    Metal Post

    Crape Myrtles

    Woods

    Overhead Sig

    n

    Overhead Sig

    n

    Metal Sign

    EH

    H

    EH

    H

    EH

    H

    EH

    H

    EH

    H

    E

    E

    E

    E

    E

    E

    EOI

    I-64 WBL CONST. BL

    CONSTRUCTION ALIGNMENT CL

    I-64 EBL CONST. BL

    PAVEMENT MARKING PROJECT

    STATION 1411+96.46

    I-64 CONSTRUCTION CENTERLINE

    PE-101, N-501

    BEGIN PROJECT: 0064-043-852

    4-2

    ex4-1

    ex4-3

    ex4-4

    BMP: Grassed Swale

    BMP: Grassed Swale

    BMP: Grassed Swale

    BMP: Grassed Swale

    SWM-3

    SWM-7

    SWM-8

    SWM-13

    SWM-2

    BMP: Grassed Swale

    BMP: Grassed Swale

    48'

    48'

    VA.

    STATE

    ROUTE PROJECT

    VA.

    REVISEDSTATE

    STATE

    ROUTE PROJECTSHEET NO.

    PROJECT SHEET NO.

    DESIGN FEATURES RELATING TO CONSTRUCTION

    OR TO REGULATION AND CONTROL OF TRAFFIC

    MAY BE SUBJECT TO CHANGE AS DEEMED

    NECESSARY BY THE DEPARTMENT

    SURVEYED BY, DATE

    DESIGN BY

    SUBSURFACE UTILITY BY, DATE

    PROJECT MANAGER

    (TECHNICAL DISCIPLINE)

    (Location), Virginia

    VDOT (Division) or Co. Name

    (TECHNICAL DISCIPLINE)

    (Location), Virginia

    VDOT (Division) or Co. Name

    0064-043-602

    I-64RW-201, C-501

    0064-043-602, PE101,

    13:3713-JUN-2017E:\ics_workingdir\1260\213077_12\d10745804.dgn

    JASON WILLIAMS, P.E. (804) 524-6145 (RICHMOND)

    WSP USA (757) 466-1732

    C

    C

    PAVED SHOULDER

    PROP LIGHT & JB

    LIMITS OF CLEARING

    SWM AREAS

    EXISTING CCTV

    CCTV

    LIMITS IN CUTS

    DENOTES CONSTRUCTION

    LIMITS IN FILLS

    DENOTES CONSTRUCTION

    LEGEND:

    FULL DEPTH PAVEMENT

    CROSSOVER PAVEMENT

    C

    F

    (TYPE I)ROCK CHECK DAM

    TRAVEL LANESMILL & OVERLAY

    PAVED SHOULDERMILL & OVERLAY

    EXISTING PAVEMENTDEMOLITION OF

    12' LANE

    WETLAND BOUNDARY

    Electric: Dominion Virginia Power

    Gas: Virginia Natural Gas (VNG)

    Sanitry: Henrico County DPU

    New Kent County Public Works

    Telephone: Verizon

    UTILITY OWNERS:

    Traffic: Virginia Department of Transportation

    T.V. : Comcast

    Cox Communications

    Water: Henrico County DPU

    New Kent County Public Works

    Dominion Virginia Power Transmission

    STRUCTURE

    OVERHEAD SPAN

    REMOVE EXISTING

    (New Arrow-per-Lane Sign)

    SPAN STRUCTURE

    PROP. 113'

    1408

    1409

    1410

    1411

    1412

    1413

    1414

    1415

    1416

    1417

    1418

    1419

    1420

    2408

    2409

    2410

    2411

    2412

    2413

    2414

    2415

    2416

    2417

    2418

    2419

    2420

    3408

    3409

    3410

    3411

    3412

    3413

    3414

    3415

    3416

    3417

    3418

    3419

    3420

    MA

    TC

    H

    LIN

    E

    ST

    A

    1420

    +50

    SH

    EE

    T

    5

    MA

    TC

    H

    LIN

    E

    ST

    A

    1407

    +50

    SH

    EE

    T

    3

    4

    4

    REFERENCES

    ( PROFILES, DETAIL & DRAINAGE

    DESCRIPTION SHEETS, ETC. )

    4A

    0

    SCALE

    50' 100'

    THESE PLANS ARE UNFINISHED

    AND UNAPPROVED AND ARE NOT

    TO BE USED FOR ANY TYPE

    OF CONSTRUCTION OR THE

    ACQUISITION OF RIGHT OF WAY.

    Structure To Be Abandoned

    Structure To Be Removed

    Plugged & Filled

    Pipe To Be Abandoned,

    Pipe To Be Removed

    Or Removed Pipe

    Pay Limit For Abandoned

    Mainline Profile

  • VA.

    STATE

    ROUTE PROJECT

    VA.

    REVISEDSTATE

    STATE

    ROUTE PROJECTSHEET NO.

    DESIGN FEATURES RELATING TO CONSTRUCTION

    OR TO REGULATION AND CONTROL OF TRAFFIC

    MAY BE SUBJECT TO CHANGE AS DEEMED

    NECESSARY BY THE DEPARTMENT

    PROJECT SHEET NO.

    SURVEYED BY, DATE

    DESIGN BY

    SUBSURFACE UTILITY BY, DATE

    PROJECT MANAGER

    (TECHNICAL DISCIPLINE)

    (Location), Virginia

    VDOT (Division) or Co. Name

    E:\ics_workingdir\1260\213077_30\d10745804A.dgn 13-JUN-2017 13:37

    0064-043-602

    I-64RW-201, C-501

    0064-043-602, PE101,

    WSP | Parsons Brinckerhoff (757) 466-1732

    0 FT 50 FT

    0 FT

    10 FT

    3408+00.00 3409+00.00 3410+00.00 3411+00.00 3412+00.00 3413+00.00 3414+00.00 3415+00.00 3416+00.00 3417+00.00 3418+00.00 3419+00.00 3420+00.00

    144.15

    144.4

    2

    144.7

    5

    145.0

    4

    145.3

    5

    145.6

    4

    145.9

    2

    146.2

    0

    146.5

    1

    146.8

    2

    147.14

    147.4

    3

    147.6

    8

    147.9

    9

    148.2

    7

    148.5

    6

    148.7

    9

    149.0

    0

    149.14

    149.2

    5

    149.3

    0

    149.2

    9

    149.2

    3

    149.12

    148.9

    3

    148.6

    8

    148.4

    0

    EXISTING GRADE

    2408+00.00 2409+00.00 2410+00.00 2411+00.00 2412+00.00 2413+00.00 2414+00.00 2415+00.00 2416+00.00 2417+00.00 2418+00.00 2419+00.00 2420+00.00

    150.4

    5

    150.6

    0

    150.8

    3

    150.9

    5

    151.02

    151.03

    151.01

    150.9

    1

    150.7

    2

    150.5

    3

    150.2

    4

    149.9

    2

    149.5

    0

    149.0

    3

    148.5

    4

    148.0

    1

    147.3

    9

    146.7

    6

    146.0

    9

    145.3

    9

    144.7

    2

    144.0

    4

    143.3

    4

    142.6

    9

    142.0

    3

    141.35

    140.6

    6

    0.62 % (APPROX.)0.59 % (APPROX.)

    EXISTING GRADE

    4A

    4A

    95_

    100_

    105_

    110_

    115_

    120_

    125_

    130_

    135_

    140_

    145_

    150_

    95_

    100_

    105_

    110_

    115_

    120_

    125_

    130_

    135_

    140_

    145_

    150_

    100_

    105_

    110_

    115_

    120_

    125_

    130_

    135_

    140_

    145_

    150_

    155_

    100_

    105_

    110_

    115_

    120_

    125_

    130_

    135_

    140_

    145_

    150_

    155_

    I-64 WB

    I-64 EB

    MA

    TC

    H

    LIN

    E

    ST

    A 3407+5

    0

    EB

    SH

    EE

    T 3

    A

    MA

    TC

    H

    LIN

    E

    ST

    A 3420+5

    0

    EB

    SH

    EE

    T 5

    A

    MA

    TC

    H

    LIN

    E

    ST

    A 2407+5

    0

    WB

    SH

    EE

    T 3

    A

    MA

    TC

    H

    LIN

    E

    ST

    A 2420+5

    0

    WB

    SH

    EE

    T 5

    A

  • Inv. O

    ut

    = 12

    0.3

    2

    Flared End Section

    In Pl. 4.3'-24"

    RCP

    Inv. O

    ut

    = 12

    2.3

    5

    Top =

    126.2

    2

    Grate Inlet

    In Pl. 3

    35.3' - 48"

    RCP

    Inv. In =

    128.9

    7

    Flared End Section

    Project # 0095-043-105, RW203

    Ex. Variable R/W Per VDOT

    113.0

    3'

    R/

    W

    Mon +3

    0.6

    9

    (68.3

    0')

    (S16°5

    5'0

    0"W)

    PL

    PL

    PL

    PL

    PLIP

    +18.9

    5

    144.4

    3'

    107.8

    8'

    IP

    +95.6

    3 174.6

    2'

    IP

    +67.5

    2

    IP

    +30.0

    3

    107.9

    7'

    105.9

    5'

    IP

    +62.5

    4

    IP

    +87.9

    7

    141.14'

    Pip

    e +9

    3.6

    8

    140.8

    7'

    PL

    PL

    PL

    PL

    PL

    Asphalt

    AsphaltAsphalt

    Asphalt

    4' Woven Wire Fence

    4' Woven Wire Fence

    4' Woven Wire Fence

    2' Conc. V-Ditch

    12' Flat-Bottom Conc. Ditch4' Conc. V-Ditch

    Asphalt Shoulder

    Asphalt Shoulder

    Asphalt Shoulder

    Asphalt Shoulder

    Asphalt Shoulder

    Asphalt Shoulder

    Asphalt Shoulder

    Asphalt Shoulder

    Exist. L/A Line Exist. L/A Line

    Ex. Variable R/W Per VDOT Project # 0095-043-105, RW203

    Ex. Variable R/W Per VDOT Project # 0095-043-105, RW203

    Exist. L/A Line

    Ex. Variable R/W Per VDOT Project # 0095-043-105, RW203

    Guardrail

    Grass

    Grass

    Mixed Medium Woods

    Mixed Medium Woods

    Grass

    Mixed Medium Woods

    Grass

    Grass

    Grass

    Medium Pines

    LOREN HENRY CODY

    (S64°15'E 154.6')

    (N23°E 118.5

    2')

    W.B. 96, PG. 645D.B. 1251, PG. 133

    D.B. 1173, PG. 262.79 Ac.

    (N17°2

    7'3

    4"E 15

    32.8

    9')

    (N65°16'13"W 105.33') (N65°16'13"W 925.64')

    P.B. 86, PG. 95

    (S71°27'11"E 465.68')

    (S18°0

    9'2

    4"W 617.19')

    (N11°15'18"W 558.8

    8')

    (N10°4

    3'3

    2"E 5.11')

    5.82 Ac.

    (N18°0

    9'2

    4"E 617.19')

    VIENNA FINANCE, INC.D.B. 2303, PG. 760

    (S23°0

    0'W 208.8

    6')

    THOMAS BENNETT LUCK, SR.

    (S64°15'E 204.60')

    1.39 Ac.

    (N23°0

    0'E 564.1')

    AND VIRGINIA CHANDLER LUCKD.B. 2127, PG. 309

    (S16°4

    6'2

    0"W 564.17')

    (S17°27'11"E 419.14')

    (N69°24'13"W 49.85')

    D.B. 2775, PG. 18285.49 Ac.

    RAYMOND C. SPERLAZZAAND CHRISTY D. SPERLAZZA

    4' Conc. V-Ditch

    (S23°0

    8'5

    0"W 10

    9.7

    6')

    5

    Ac.

    AN

    D

    LIL

    LIA

    N

    W. W

    RIG

    HT

    D.B. 5

    36, P

    G. 3

    48

    W. P

    AR

    RY

    WRIG

    HT, J

    R.

    (N17°E 358.0

    6')

    1.63

    Ac.

    D.B. 1732, P

    G. 9

    63

    (S63°47'51"E 129.51')

    (S17°W 543.5

    0')

    S71°39'33"E 925.28'

    N16°4

    9'4

    5"E 10

    9.7

    1'

    S71°17'35"E 105.70'N71°34'15"W 305.19'

    S79°45'22"E

    307.01'

    RO

    BE

    RT

    P. W

    RIG

    HT

    AN

    D

    MA

    RG

    AR

    ET

    F. W

    RIG

    HT

    D.B. 2138, PG. 1690

    IMG/INTERCHANGE A

    SSOCIATES

    (S73°26'31"E

    307.03')

    (N65°16'13"W 305.20')

    LIMITED PARTNERSH

    IP

    82.44 Ac.

    (N73°26'31"W

    501.87')

    D.B. 2168, PG. 6040.92 Ac.

    (N23°0

    8'5

    0"E 10

    9.7

    6')

    IMG/INTERCHANGE ASSOCIATESLIMITED PARTNERSHIP

    (N65°16'13"W 105.33')

    S71°17'35"E 105.70'

    Metal Sig

    n

    12.6' x 7'

    Metal Sig

    n

    Metal Sig

    n

    Metal Sig

    n

    Metal Sig

    n

    Solar Panel

    Pole

    With

    Overhead Sig

    n

    Mixed Pines And Hardwoods

    Mixed Pines And Hardwoods

    LO

    RE

    N

    HE

    NR

    Y C

    OD

    Y

    EH

    H

    EH

    HEH

    HE

    E

    E

    EH

    H

    EH

    H

    EH

    H

    E

    EE

    CONSTRUCTION ALIGNMENT CL

    I-64 WBL CONST. BL

    I-64 EBL CONST. BL

    STATION 1427+01.34

    I-64 CONSTRUCTION CENTERLINE

    PE-101, RW-201, C-501

    BEGIN PROJECT: 0064-043-602

    12':1000' SHIFT

    STATION 3427+00.00

    EBL BASELINE

    BEGIN CONSTRUCTION

    ex5-1

    ex5-2

    ex5-3

    BMP: Grassed Swale SWM-8 SWM-9

    BMP: Grassed Swale

    BMP: Grassed Swale

    BMP: Grassed Swale

    4' Paved Shoulder48'

    48'

    87.7'

    36'

    36'

    VA.

    STATE

    ROUTE PROJECT

    VA.

    REVISEDSTATE

    STATE

    ROUTE PROJECTSHEET NO.

    PROJECT SHEET NO.

    DESIGN FEATURES RELATING TO CONSTRUCTION

    OR TO REGULATION AND CONTROL OF TRAFFIC

    MAY BE SUBJECT TO CHANGE AS DEEMED

    NECESSARY BY THE DEPARTMENT

    SURVEYED BY, DATE

    DESIGN BY

    SUBSURFACE UTILITY BY, DATE

    PROJECT MANAGER

    (TECHNICAL DISCIPLINE)

    (Location), Virginia

    VDOT (Division) or Co. Name

    (TECHNICAL DISCIPLINE)

    (Location), Virginia

    VDOT (Division) or Co. Name

    0064-043-602

    I-64RW-201, C-501

    0064-043-602, PE101,

    13:3713-JUN-2017E:\ics_workingdir\1260\213077_13\d10745805.dgn

    JASON WILLIAMS, P.E. (804) 524-6145 (RICHMOND)

    WSP USA (757) 466-1732

    C

    C

    PAVED SHOULDER

    PROP LIGHT & JB

    LIMITS OF CLEARING

    SWM AREAS

    EXISTING CCTV

    CCTV

    LIMITS IN CUTS

    DENOTES CONSTRUCTION

    LIMITS IN FILLS

    DENOTES CONSTRUCTION

    LEGEND:

    FULL DEPTH PAVEMENT

    CROSSOVER PAVEMENT

    C

    F

    (TYPE I)ROCK CHECK DAM

    TRAVEL LANESMILL & OVERLAY

    PAVED SHOULDERMILL & OVERLAY

    EXISTING PAVEMENTDEMOLITION OF

    12' LANE

    WETLAND BOUNDARY

    Electric: Dominion Virginia Power

    Gas: Virginia Natural Gas (VNG)

    Sanitry: Henrico County DPU

    New Kent County Public Works

    Telephone: Verizon

    UTILITY OWNERS:

    Traffic: Virginia Department of Transportation

    T.V. : Comcast

    Cox Communications

    Water: Henrico County DPU

    New Kent County Public Works

    Dominion Virginia Power Transmission

    STRUCTURE

    OVERHEAD SPAN

    REMOVE EXISTING

    C

    1421

    1422

    1423

    1424

    1425

    1426

    1427

    1428

    1429

    1430

    1431

    1432

    1433

    2421

    2422

    2423

    2424

    2425

    2426

    2427

    2428

    2429

    2430

    2431

    2432

    2433

    3421

    3422

    3423

    3424

    3425

    3426

    3427

    3428

    3429

    3430

    3431

    3432

    3433

    MA

    TC

    H

    LIN

    E

    ST

    A

    1433

    +50

    SH

    EE

    T

    6

    MA

    TC

    H

    LIN

    E

    ST

    A

    1420

    +50

    SH

    EE

    T

    4

    REFERENCES

    ( PROFILES, DETAIL & DRAINAGE

    DESCRIPTION SHEETS, ETC. )

    5A

    5

    50

    SCALE

    50' 100'

    THESE PLANS ARE UNFINISHED

    AND UNAPPROVED AND ARE NOT

    TO BE USED FOR ANY TYPE

    OF CONSTRUCTION OR THE

    ACQUISITION OF RIGHT OF WAY.

    Structure To Be Abandoned

    Structure To Be Removed

    Plugged & Filled

    Pipe To Be Abandoned,

    Pipe To Be Removed

    Or Removed Pipe

    Pay Limit For Abandoned

    Mainline Profile

  • VA.

    STATE

    ROUTE PROJECT

    VA.

    REVISEDSTATE

    STATE

    ROUTE PROJECTSHEET NO.

    DESIGN FEATURES RELATING TO CONSTRUCTION

    OR TO REGULATION AND CONTROL OF TRAFFIC

    MAY BE SUBJECT TO CHANGE AS DEEMED

    NECESSARY BY THE DEPARTMENT

    PROJECT SHEET NO.

    SURVEYED BY, DATE

    DESIGN BY

    SUBSURFACE UTILITY BY, DATE

    PROJECT MANAGER

    (TECHNICAL DISCIPLINE)

    (Location), Virginia

    VDOT (Division) or Co. Name

    E:\ics_workingdir\1260\213077_31\d10745805A.dgn 13-JUN-2017 13:37

    0064-043-602

    I-64RW-201, C-501

    0064-043-602, PE101,

    WSP | Parsons Brinckerhoff (757) 466-1732

    0 FT 50 FT

    0 FT

    10 FT

    3421+00.00 3422+00.00 3423+00.00 3424+00.00 3425+00.00 3426+00.00 3427+00.00 3428+00.00 3429+00.00 3430+00.00 3431+00.00 3432+00.00 3433+00.00 3434+00.00

    140.2

    5

    139.4

    3

    138.5

    8

    137.7

    8

    137.0

    5

    136.2

    6

    135.4

    6

    134.6

    6

    133.8

    7

    133.0

    8

    132.2

    8

    131.48

    130.6

    9

    129.8

    9

    148.4

    0

    148.0

    5

    147.6

    6

    147.2

    3

    146.7

    2

    146.17

    145.5

    6

    144.8

    9

    144.19

    143.4

    4

    142.6

    6

    141.87

    141.07

    140.2

    5

    139.4

    3

    138.5

    8

    137.7

    8

    137.0

    5

    136.2

    6

    135.4

    6

    134.6

    6

    133.8

    7

    133.0

    8

    132.2

    8

    131.48

    130.6

    9

    129.8

    9

    EXISTING GRADE

    2421+00.00 2422+00.00 2423+00.00 2424+00.00 2425+00.00 2426+00.00 2427+00.00 2428+00.00 2429+00.00 2430+00.00 2431+00.00 2432+00.00 2433+00.00

    140.6

    6

    139.9

    6

    139.2

    8

    138.6

    0

    137.9

    1

    137.2

    1

    136.5

    2

    135.8

    4

    135.19

    134.4

    9

    133.8

    1

    133.12

    132.4

    3

    131.77

    131.12

    130.4

    4

    129.7

    4

    129.0

    9

    128.3

    9

    127.6

    8

    126.9

    8

    126.2

    8

    125.6

    4

    124.9

    8

    124.2

    9

    123.6

    4

    122.9

    4

    -1.33 % (APPROX.)

    -1.60 % (APPROX.)

    GRADE

    EXISTING STATION 3427+00.00

    EBL BASELINE

    PE-101, RW-201, C-501

    BEGIN PROJECT: 0064-043-602

    100_

    105_

    110_

    115_

    120_

    125_

    130_

    135_

    140_

    145_

    150_

    100_

    105_

    110_

    115_

    120_

    125_

    130_

    135_

    140_

    145_

    150_

    85_

    90_

    95_

    100_

    105_

    110_

    115_

    120_

    125_

    130_

    135_

    140_

    145_

    150_

    155_

    85_

    90_

    95_

    100_

    105_

    110_

    115_

    120_

    125_

    130_

    135_

    140_

    145_

    150_

    155_

    MA

    TC

    H

    LIN

    E

    ST

    A 3420+5

    0

    EB

    SH

    EE

    T 4

    AM

    AT

    CH

    LIN

    E

    ST

    A 2420+5

    0

    WB

    SH

    EE

    T 4

    A

    MA

    TC

    H

    LIN

    E

    ST

    A 2433

    +50

    WB

    SH

    EE

    T 6

    AM

    AT

    CH

    LIN

    E

    ST

    A 3433

    +50

    EB

    SH

    EE

    T 6

    A

    I-64 EB

    I-64 WB

    5A

    5A

    APPROXIMATE SPLINE GRADE

  • Project # 0064-0

    43-0

    02, P

    E10

    1Ex. Varia

    ble R/

    W per V

    DO

    T

    VDOT Project # 0064-043-002, PE101

    Ex. Variable R/W Per

    In Pl. 52.8' - 36"

    RCP

    Inv. In =

    100.6

    9

    Top =

    104.8

    5

    Head

    wall

    Project # 0095-043-105, RW203

    Ex. Variable R/W Per VDOT

    Inv. O

    ut

    = 98.12

    Top =

    101.96

    Head

    wall

    Project # 0095-043-105, RW203

    Ex. Variable R/W Per VDOT

    ShedWooden

    ShedMetal

    Z

    PL

    PL

    PL

    IP

    +10.6

    6

    27.6

    1'

    Mon +0

    8.7

    4

    92.5

    0'

    Mon +0

    1.38

    326.7

    7'

    Pip

    e +12.2

    5

    298.5

    0'

    IP

    +24.14

    145.13'

    RM-2

    +12.3

    3

    119.5

    6'

    RM-2

    +75.7

    7

    93.8

    2'

    285.9

    5'

    IP

    +19.9

    5

    IP

    +90.0

    3

    277.4

    1'

    119.7

    4'

    Bent

    Pip

    e +4

    5.2

    4

    119.5

    7'

    RM-2

    +15.0

    9

    Z

    PL

    PL

    PL

    PL

    PL

    PL

    PL

    PL

    Asphalt

    Asphalt

    Asphalt

    4' Woven Wire Fence 4' Woven Wire Fence

    3'

    Conc. V-Ditch

    3'

    Conc. V-Ditch

    4' Woven Wire Fence

    4' Conc. V-Ditch4' Conc. V-Ditch

    6' Conc. V-Ditch

    Asphalt

    12.1' Flat-Bottom Conc. Ditch

    Guardrail

    Conc. P

    ad

    Wet Weather Ditch

    Metal Sig

    n in Conc.

    Metal Sig

    n in Conc.

    Asphalt Shoulder

    Asphalt Shoulder

    Asphalt Shoulder

    Asphalt Shoulder

    Asphalt Shoulder

    Asphalt Shoulder

    Asphalt Shoulder

    Asphalt Shoulder

    Asphalt Shoulder

    Ex. Variable R/W Per VDOT Project # 0095-043-105, RW203

    R=756.12' A=272.72'

    Ex. Variable R/W Per VDOT Project # 0064-043-002, PE101

    Exist. L/A Line Exist. L/A Line

    Exist. L/A Line

    Exist. L/A Line

    Medium Pines

    Medium Mixed Wo

    ods

    Medium Mixed Woods

    Medium Pines

    Grass

    Large Hardwoods

    Grass

    Grass

    Medium Pines

    Medium Hardwoods

    Grass

    Medium Mixed Woods

    Guardrail

    (N22°3

    0'E 300')

    DAVID LLEWEL

    LYN HAMPTON

    D.B. 2884, PG.

    416

    (S68°30'E 680')(35')

    4.37 Ac.

    1.15 A

    c.

    D.B. 2753, PG. 1142

    ROLAND A. WHITLOCKAND PATRICIA A. WHITLOCK

    (S23°0

    0'W 687.8

    0')

    (S22°3

    0'W 690.6')

    (N22°3

    0'E 687.8')

    D.B. 1110, PG. 420

    No Recorded Acreage

    3.10 Ac.

    0.455 Ac.

    D.B. 365, PG. 185

    AGNES S. MOSS

    W.B. 86, PG. 1197

    W.B. 86, PG. 1197

    (S22°3

    0'W 79.4')

    AGNES S. MOSS

    Sig

    n

    Gravel

    Gate

    14" Poplar12" Poplar

    14" Poplar

    Dirt Road

    Gravel

    Garage

    (S75°50'

    W 17.16')

    (N43°2

    9'11"E 14

    1.08')

    (N55°12'47"W 113.58')

    (N39°12'58"W 211.34')

    (N41°50'W 140.40')S79°45

    '57"E 501.90

    '

    S79°45'22"E

    307.01'

    S16°4

    7'5

    1"W 15

    3.4

    4'

    D.B. 1227, PG. 91

    AND FRANCIS B. ROBINSWILLIAM A. ROBINS

    D.B. 964, PG. 600

    (N65°16'13"W 305.20')

    (S16°26'07"W

    11.43')

    (R=756.20', L=55.95')

    (N73°26'31"W

    501.87')

    (N73°40'35"W

    387.42')

    (N73°40'35"W

    155.13')

    (S35°2

    4'3

    3"W 965.2

    5')

    2.43 Ac.

    (S23°0

    6'5

    8"W 15

    3.4

    2')

    PATRICIA W. ELLISD.B. 1758, PG. 14

    IMG/INTERCHANGE ASSOCIATESLIMITED PARTNERSHIP

    Metal Post

    Metal Sig

    n

    Metal Sig

    n

    Metal Sig

    n (2)

    Mixed Pines And Hardwoods Mixed Pines And Hardwoods

    Metal Post

    LO

    RE

    N

    HE

    NR

    Y C

    OD

    YW.B. 9

    6, P