Integrating IW Live Pro in BristolWaterCWMAG Autumn Conference 2017
Rebecca Willey
27 October 2017 1
Bristol Water Model Build Program• Objective: The project is to complete all 12 model builds including calibration and
migrated into InfoWorks Live
• Models extracted and basics built using bespoke extract tool
27 October 2017 2
Demand Area Analysis
27 October 2017 3
• Performed within IW 17.5 Demand Area Grid
• Model function uses live data to calculate inflows, outflows and net flow
• Around 1400 flows, pressures and levels assigned to the models
Demand Area Analysis
27 October 2017 4
• Points in GIS transferred to lines cause bounding link issues
Demand Area Analysis
27 October 2017 5
• Highlights network discrepancies
Calibration
27 October 2017 6
• Initially flow for DMA and operational sites using linked live flow.
• Control update from site FDS’.
• Calibration of the models is vital for IW Live
IW Live
27 October 2017 7
• Very early stage of development and use
• Currently Tetbury model running every hour
• Updates process area for us to look into