Dubna modules assembly status (October 14 2013) Straw manufacture: current serial number is # 6527 for CH2 M2 X-Y 900 straws are glued for CH4 M1 U-V 900 straws are ready for CH4 M2 X-Y 776 straws are manufactured CH2 M1 U-V status CH2 M2 X-Y status CH4 M1 U-V status - PowerPoint PPT Presentation
Citation preview
Apr 20, 2023 S.Movchan Straw manufacturing and QC 1
Dubna modules assembly status (October 14 2013)
Straw manufacture:• current serial number is # 6527• for CH2 M2 X-Y 900 straws are glued
• for CH4 M1 U-V 900 straws are ready • for CH4 M2 X-Y 776 straws are manufactured
CH2 M1 U-V status
CH2 M2 X-Y status
CH4 M1 U-V status
CH2 M1 U-V delivery to CERN
Presented by S.Movchan
Apr 20, 2023 S.Movchan Straw manufacturing and QC 2
Straws
900 straws for CH2 M2 X-Y (2-nd Dubna module) are glued:# (2990-3567) ~ 400 pc# (3568-4394) - 50 pc# (4395-4842) ~ 450pc
900 straws for CH4 M1 U-V (3-d Dubna module) are ready:# (4843-5750)
776 straws for CH4 M2 X-Y (4-th Dubna module) are manufactured:
# (5751-6527)
Apr 20, 2023 S.Movchan Straw manufacturing and QC 3
CH2 M1 U-V status
Apr 20, 2023 4
Dubna assembly site (LHEP, bld.217)CH2 M1 U-V
Module vacuum test:Leak ~ 500 mbar*cm3/min
finish of straw gluing (07/02/2013) Start – 28/09/2012
Quality controlby laser
Apr 20, 2023 S.Movchan Straw manufacturing and QC 5
Module removed from assembly tooling (June 2013)
Apr 20, 2023 S.Movchan Straw manufacturing and QC 6
CH2 M1 U-V: U-coordinate gas leak test
Leak:15 mBar/3 days at
P=1.4 Bar
Apr 20, 2023 S.Movchan Straw manufacturing and QC 7
CH2 M2 X-Y status
Apr 20, 2023 8
CH2 M2 X-Y installed for assembly (July 16 2013)
Microworld physics, Gomel, 2013
Apr 20, 2023 S.Movchan Straw manufacturing and QC 9
CH2 M2 X-Y status: all straws glued(October 14 2013)
8 layers glued
Apr 20, 2023 10
CH2 M2 X-Y: straw pre-tension check
sensor
Microworld physics, Gomel, 2013
Example: Y, layer 1
F=(1.75-1.95) kG
Apr 20, 2023 11
CH2 M2 X-Y: straw position check
Microworld physics, Gomel, 2013 +/- 100 m
top
middle
bottom
Example: Y, layer 1
Apr 20, 2023 S.Movchan Straw manufacturing and QC 12
CH4 M1 U-V: vacuum test in progress
Apr 20, 2023 S.Movchan Straw manufacturing and QC 13
Preparation for module delivery to CERN:
Shocklog device and dumping pads
4 pc
Apr 20, 2023 S.Movchan Straw manufacturing and QC 14
CH2 M1 U-V delivery to CERN
4 safety bolts: frame max shift is limited dL = 10 mm
Apr 20, 2023 S.Movchan Straw manufacturing and QC 15
Shocklog
2 shocklog with 2 different thresholds will be used
Apr 20, 2023 S.Movchan Straw manufacturing and QC
Conclusion
Straw manufacture:• 900 straws are glued in the CH2 M2 X-Y• 900 straws are ready for CH4 M1 U-V• 776 straws are manufactured for CH4 M2 X-Y
CH2 M1 U-V: • straw gluing and wiring – done• final assembly – done• tests (HV, gas leak) – in progress• delivery to CERN – October 2013
CH2 M2 X-Y: • straw gluing – done• wiring – October 2013• final assembly – November 2013• tests (HV, gas leak) – December 2013• delivery to CERN – January 2014
“Straw 2” installation – Feb-March 2014
Apr 20, 2023 S.Movchan Straw manufacturing and QC 17