Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Option 5 Partial Redevelopment Option A
Preliminary Estimate
Camden Goods Yard (Option 2 - Environmental Improvements)
Dated: 04/04/2018Revision 0
Prepared for :
One Housing GroupPrepared by : Teik Khor
Approved by : Tim Young
Camden Goods Yard
Preliminary Estimate
CONTENTS
1 INTRODUCTION & EXECUTIVE SUMMARY
2 NOTES AND CLARIFICATIONS
3 SUMMARY OF ESTIMATE3.1 Gilbeys yard3.2 Juniper crescent
4 INFORMATION USED IN PREPARING THIS REPORT
5 REVISION LOG
1 INTRODUCTION & EXECUTIVE SUMMARY
1.1
1.2 This Preliminary Estimate is detailed below
A Summary Of Cost
Main Summary £ Total
Juniper Crescent
Environmental Improvements £603,253
Sub Total - £603,253
Gilbeys Yard
Environmental Improvements £495,488
Sub Total - £495,488
Total - £1,098,742
2 NOTES AND CLARIFICATIONS
2.1 Information based on:
2.1.1 The estimate is based on the details provided in PRP document. Design info (option 2), Environmental Improvements
2.1.2
2.2 Our estimate excludes the following:
2.2.1 Professional and legal fees
2.2.2
2.2.3
2.2.4
2.2.5
2.2.6
2.2.7
2.2.8
2.2.9
2.2.10
2.2.11 Flood prevention
2.2.12
2.2.13 Inflation cost.
2.2.14 Removal of asbestos.
2.2.15 Contaminated land remediation.
We have prepared this Preliminary Estimate for the proposed residential development in line with the area schedule Camden Goods Yard (Option 2), Environmental Improvements.
Cost are current as 2Q 2018
Service diversion.
Option 2 Environmental Improvements
Archaeological and cost associated.
Surveys and investigations.
Planning / Building Regulation fees.
Finance charges.
Party Wall matters & Rights of light issues.
Removal of any Japanese Knotweed or other invasive weeds.
Relocating habitat of any protected wildlife on or off site and any surveys (Slow worms, etc.)
VAT.
Local & Mayoral CIL payments, Cross rail levy, Section 278, Section 106 contributions and other contributions.
Camden Goods Yard
Preliminary Estimate
3 Summary of estimate
3.1 Environmental Improvements - Gilbeys Yard
Ref Item Qty Unit Rate Total £ Comment
1.1 Soft landscaping areas (Excluding play areas)
to include:
416 - From approximate measure 40% of total are allocated to
Gilbeys
Preparatory excavation and subbases
Clear and prepare existing soft landscape
areas
416 m2 15.00 6,240
seeded and planted areas
Plant supply, planting, maintenance and 12
month guarantee
Supply and lay new turf 250 m2 9.50 2,371
planted areas
General planting 83 m2 15.00 1,248 Assumed 20% of soft landscape area
Climbing planting 42 m2 15.00 624 Assumed 10% of soft landscape area
Shrub bed planting 42 m2 25 1,040 Assumed 10% of soft landscape area
Trees
Semi-mature root balled tree 10 Nr 450 4,500 Provisional allowance
1.2 Hard Landscaping 1,789
Cobblestone - carefully take up, prepare
base and relay cobblestones on 100mm thick
concrete subbase; including excavation;
pointing etc
1,163 m2 75 87,224 65% assumed as take up and relay existing cobblestone
paving
Marshal Monoblock paving precast concrete
tactile paving slabs on subbase ; including
excavation
626 m3 55 34,442 35% has been assumed as precast concrete block paviours
1.3 Footpaths 1,127
Take up existing and lay enhanced paving 1,127 m2 75 84,540
1.4 Play area
Lano rugby max 60mm monofilament laid on
shock pad on a dynamic base infill with
32kg/m2 sand and 11kg/m2 SBR rubber - IRB
clause 22 complaint ; supply and spread to
required infill rates, 2EW sand and 0.5 - 2mm
SBR rubber.
162 m2 45 7,290
Play equipment, fencing etc 1 item 20,000 20,000 Provisional Sum
Parking bollards 20 Nr 250 5,000
Speed bumps 4 Nr 750 3,000
1.5 Bin stores
removal and provision of new bin stores 6 item 10,000 60,000
and replacement
1.6 CCTV
Gilbeys 10 Nr 2,500 25,000 Hikvision 4K CCTV System with 4 50m Bullet Cameras, 4TB
NVR (Product Code: PK4K344TB ).
1.7 New lighting strategy 16 Nr 2,000 32,000 Provisional for taking and upgrading the current street
light system. Allowed 24 Juniper and 16 Gilbeys
2 Sub total 374,519
2.1 Preliminaries and management costs 14% 52,433 site set up, management, site labour, etc
2.2 Main Contractors design fees & any pre-
construction fees
6% 22,471
2.3 Main Contractors overheads 5% 22,471 assumes a design and build form of contract
2.4 Contingency/Risk 5% 23,594.68
2.5 Construction cost inflation for the pre-
construction and construction periods
0% excluded
K Total Estimated Construction Cost 495,488
Camden Goods Yard
Preliminary Estimate
3 Summary of estimate
3.2 Environmental Improvements - Juniper Crescent
Ref Item Qty Unit Rate Total £ Comment
1.1 Soft landscaping areas (Excluding play areas)
to include:
624 - From approximate measure 60% of total are allocated to
Juniper
Preparatory excavation and subbases
Clear and prepare existing soft landscape
areas
624 m2 15.00 9,360
seeded and planted areas
Plant supply, planting, maintenance and 12
month guarantee
Supply and lay new turf 374 m2 9.50 3,557
planted areas
General planting 125 m2 15.00 1,872 Assumed 20% of soft landscape area
Climbing planting 62 m2 15.00 936 Assumed 10% of soft landscape area
Shrub bed planting 62 m2 25 1,560 Assumed 10% of soft landscape area
Trees
Semi-mature root balled tree 15 Nr 450 6,750 Provisional allowance
1.2 Hard Landscaping 2,684
Junipers marshal Monoblock paving precast
concrete tactile paving slabs on subbase ;
including excavation
2,684 m3 55 147,609
1.3 Footpaths 1,127
Take up existing and lay enhanced paving 1,127 m2 75 84,540
1.4 Play area
Lano rugby max 60mm monofilament laid
on shock pad on a dynamic base infill with
32kg/m2 sand and 11kg/m2 SBR rubber -
IRB clause 22 complaint ; supply and spread
to required infill rates, 2EW sand and 0.5 -
2mm SBR rubber.
162 m2 45 7,290
Play equipment, fencing etc 1 item 25,000 25,000 Provisional Sum
Parking bollards 30 Nr 250 7,500
Speed bumps 6 Nr 750 4,500
1.5 Bin stores
removal and provision of new bin stores 7 item 10,000 70,000
and replacement
1.6 CCTV
Juniper 15 Nr 2,500 37,500 Hikvision 4K CCTV System with 4 50m Bullet Cameras, 4TB
NVR (Product Code: PK4K344TB ).
1.7 New lighting strategy 24 Nr 2,000 48,000 Provisional for taking and upgrading the current street
light system. Allowed 24 Juniper and 16 Gilbeys
E Sub total 455,974
F Preliminaries and management costs 14% 63,836 site set up, management, site labour, etc
G Main Contractors design fees & any pre-
construction fees
6% 27,358
H Main Contractors overheads 5% 27,358 assumes a design and build form of contract
I Contingency/Risk 5% 28,726.35
J Construction cost inflation for the pre-
construction and construction periods
0% excluded
K Total Estimated Construction Cost 603,253
Camden Goods Yard
4. INFORMATION USED IN PREPARING THIS REPORT
Ref Number Rev Title
AA6596_Enviromental scope _DRAFT_.pdf
AA6596_CGY_Draft Design Info
AA6569_Existing Building Measurements_DRAFT
Preliminary Estimate
Option 5 Partial Redevelopment Option A
Preliminary Estimate
Camden Goods Yard (Option 3 - Refurbishment)
Dated: 04/04/2018Revision 0
Prepared for :
One Housing Group
Prepared by : Teik Khor
Approved by : Tim Young
Camden Goods Yard
Preliminary Estimate
CONTENTS
1 INTRODUCTION & EXECUTIVE SUMMARY
2 NOTES AND CLARIFICATIONS
3 SUMMARY OF ESTIMATE
3.1 OPTION A - MINIMUM STANDARD (JUNIPER)
3.2 OPTION A - MINIMUM STANDARD (GILBEYS)
3.3 OPTION B - GOOD PRACTISE (JUNIPER)
3.4 OPTION B - GOOD PRACTISE (GILBEYS)
3.5 OPTION C - BEST PRACTICE (JUNIPER)
3.6 OPTION C - BEST PRACTICE (GILBEYS)
4 INFORMATION USED IN PREPARING THIS REPORT
5 REVISION LOG
1 INTRODUCTION & EXECUTIVE SUMMARY
1.1
1.2 This Preliminary Estimate is detailed below
A Summary Of Cost
Main Summary Nr Units £/unit Total
Construction Cost
Juniper Crescent 120
Minimum Standard £16,977 £2,037,196
Good Practice £69,574 £8,348,924
Best Practice £179,917 £21,590,000
Gilbeys Yard 82
Minimum Standard £16,818 £1,379,059
Good Practice £70,105 £5,748,630
Best Practice £239,981 £19,678,439
Total 202
Minimum Standard £3,416,255
Good Practice £14,097,554
Best Practice £41,268,439
2 NOTES AND CLARIFICATIONS
2.1 Information based on:
2.1.1 The estimate is based on the details provided in PRP document (Option 3) - Refurbishment
2.1.2 Cost are current as 2Q 2018
2.2 Our estimate excludes the following:
2.2.1 Professional and legal fees
2.2.2 Planning / Building Regulation fees.
2.2.3 Archaeological and cost associated.
2.2.4 Finance charges.
2.2.5 Party Wall matters & Rights of light issues.
2.2.6 VAT.
2.2.7 Local & Mayoral CIL payments, Cross rail levy, Section 278, Section 106
2.2.8 Surveys and investigations.
2.2.9 Removal of any Japanese Knotweed or other invasive weeds.
2.2.10 Relocating habitat of any protected wildlife on or off site and any surveys (Slow worms, etc.)
2.2.11 Marketing budget or any purpose build show flats or marketing suite
2.2.12 Carbon Reduction Levy.
2.2.13 Flood prevention
2.2.14 Service diversion.
2.2.15 Inflation cost
2.2.16 Removal of asbestos.
2.2.17 Contaminated land remediation.
Option 3 - Refurbishment
We have prepared this Preliminary Estimate for the proposed residential development in line with the area schedule Camden Goods Yard (Option 3),
Refurbishment
Camden Goods Yard
Preliminary Estimate
Option 3 - Refurbishment
3.1 Summary of estimate OPTION A - MINIMUM STANDARD (JUNIPER)
Existing Units
Ref Item Qty Unit Rate Total £ Comment
1 Minimum standard
1.1 Provision of proprietary draught proofing system
to external doors.
120 nr 85 10,200 The cost reflects the time allowed for the installation of
proprietary draught insulation.
1.2 Supply and lay 200mm ROCKWOOL Twin Roll
mineral wool loft insulation, including all eves
ventilations etc all in accordance with
Manufacturer’s Instructions;
3,550 m2 15 53,252 The area has been calculated based on the total roof area
(please refer to PRP - Existing building measurements). An
assumption has been made that access will be needed to
the loft space.
1.3 Replace boilers with Valliant ecoTEC plus 24kW;
ErP rated A; 7 year warranty; including all
Builders Work in Connection and Smart controls.
120 nr 3,500 420,000 The cost also reflects making good, following the
completion of the works.
1.4 VELFAC 200 ENERGY triple glazing windows,
casement doors and sliding casement doors in
wood / aluminium. Outward opening elements
in wood/aluminium; SBD accredited; Uw value
down to 0.8; 48mm triple glazing; 12-year
warranty
480 nr 1,050 504,000 An assumption has been made for an area of 1.5m2 per
window and the total 4nr windows per unit.
1.5 Scaffolding 9,005 m2 45 405,236
B Sub total 1,392,688
C Preliminaries and management costs 14% 194,976 site set up, management, site labour, etc
D Main Contractors design fees & any pre-
construction fees
8% 111,415
E Main Contractors overheads 9% 152,917 assumes a design and build form of contract
F Contingency/Risk 10% 185,200
G Construction cost inflation for the pre-
construction and construction periods
0% excluded
H Total Estimated Construction Cost 2,037,196
£/unit 16,977
Camden Goods Yard
Preliminary Estimate
Option 3 - Refurbishment
3.2 Summary of estimate OPTION A - MINIMUM STANDARD (GILBEYS)
Existing Units
Ref Item Qty Unit Rate Total £ Comment
1 Minimum standard
1.1 Provision of proprietary draft proofing system to
external doors.
82 nr 85 6,970 The cost reflects the time allowed for the installation of
proprietary draught insulation.
1.2 Supply and lay 200mm ROCKWOOL Twin Roll
mineral wool loft insulation, including all eves
ventilations etc all in accordance with
Manufacturer’s Instructions;
2,150 m2 15 32,249 The area has been calculated based on the total roof area
(please refer to PRP - Existing building measurements). An
assumption has been made that access will be needed to
the loft space.
1.3 Replace boilers with Valliant ecoTEC plus; ErP
rated A; 7 year warranty; including all Builders
Work in Connection and Smart controls.
82 nr 3,500 287,000 The cost also reflects making good, following the
completion of the works.
1.4 VELFAC 200 ENERGY triple glazing windows,
casement doors and sliding casement doors in
wood / aluminium. Outward opening elements
in wood/aluminium; SBD accredited; Uw value
down to 0.8; 48mm triple glazing; 12-year
warranty
328 nr 1,050 344,400 An assumption has been made for an area of 1.5m2 per
window and the total 4nr windows per unit.
1.5 Scaffolding 6,048 m2 45 272,147
B Sub total 942,766
C Preliminaries and management costs 14% 131,987 site set up, management, site labour, etc
D Main Contractors design fees & any pre-
construction fees
8%75,421
E Main Contractors overheads 9% 103,516 assumes a design and build form of contract
F Contingency/Risk 10% 125,369
G Construction cost inflation for the pre-
construction and construction periods
0%excluded
H Total Estimated Construction Cost 1,379,059
£/unit 16,818
Camden Goods Yard
Preliminary Estimate
Option 3 - Refurbishment
3.3 Summary of estimate OPTION B - GOOD PRACTISE (JUNIPER)
Existing units
Ref Item Qty Unit Rate Total £ Comment
1 Good Practise
To include all costs of minimum standard unless
duplication
1,392,688
1.1 Kingspan Optim-R rigid vacuum insulation panel
with a microporous core which is evacuated,
encased and sealed in a thin, gas-tight envelope.
40mm think; 300 x 600mm board size. Including
works to revels etc.
9,005 m2 185 1,665,971 Based on information provided by Kingspan; prices reflect
the cost for specific product.
1.2 Allowance for addressing any thermal bridging
with appropriate detailing.
120 nr 1,000 120,000 Provisional sum.
1.3 Xpelair Muro through the wall heat recovery
ventilation unit for single room incorporate an
80% efficient counter flow heat exchanger; Long
life, low energy DC constant volume motors for
both air intake and extract; Integral display for
fan speed selection and filter/fault function -
continuous operation mode option; Built-in frost
protection function; Removable front fascia for
easy access to filters for cleaning; Automatic
defrost function prevents freezing; Condensate
drain provided to outside of the property; EPP
square wall set.
120 nr 1,450 174,000 Based on information provided by Xpelair; prices reflect
cost for specific product.
1.4 Replacement Thermostatic Radiator Valves;
Drayton RT414 thermostatic radiator valves
provide control of individual room
temperatures. With integral thermostatic
sensing head and reverse flow capability, the
15mm angle.
690 nr 75 51,750 Based on Information shared through Drayton; prices
reflect the cost for specific product. An assumption has
been made that there will be 5nr radiators per flat and 7nr
radiators per house.
1.5 Provision of Photovoltaic panels and control
systems to single houses.
115 nr 3,500 402,500 Based on Information shared through Green Power. An
assumption has been made that there will be 1nr panel
per flat and 2nr panels per house (please refer to PRP -
Existing building measurements).
1.6 Provision of controlled doors with keypad
system to existing bin store doors.
12 nr 200 2,400 Based on benchmarking analysis for mehcanical
combination locks. An assumption has been made for 2nr
double doors before the bin store.
1.7 Provision of additional bin stores to match
existing
6 nr 14,000 84,000 Cost to reflect the construction of bin stores with brick
walls and metal sheet roofing. An assumption has been of
approximate 9m2 per bin store.
1.8 Provision of balconies to apartments currently
without balconies; MKG Systems Cantilever &
Self-Supporting Bolt on Balcony Systems; A
projecting steel-framed/Aluminium balcony
which is bolted on to a building; style to match
existing balconies.
5 nr 15,000 75,000 Based on quote provided by Sapphire; prices reflect the
cost for specific product. An assumption of 2,5m2 has
been made for each Bolt-on balcony.
Camden Goods Yard
Preliminary Estimate
Option 3 - Refurbishment
3.3 Summary of estimate OPTION B - GOOD PRACTISE (JUNIPER)
Existing units
Ref Item Qty Unit Rate Total £ Comment
1.9 Replacement of undersized balconies as above. 115 nr 16,000 1,840,000
1.10 Provision of entrance canopies to houses, steel
framed polyester powder coated finish.
45 nr 1,200 54,000 Based on benchmarking information, the price reflects
entrance canopy to double doors.
B Sub total 5,862,309
C Preliminaries and management costs 14% 820,723 site set up, management, scaffold, site labour, etc
D Main Contractors design fees & any pre-
construction fees
7% 410,362
E Main Contractors overheads 7% 496,538 assumes a design and build form of contract
F Contingency/Risk 10% 758,993
G Construction cost inflation for the pre-
construction and construction periods
0% excluded
Main Summary
H Total Estimated Construction Cost 8,348,924
£/unit 69,574
Camden Goods Yard
Preliminary Estimate
Option 3 - Refurbishment
3.4 Summary of estimate OPTION B - GOOD PRACTISE (GILBEYS)
Existing Units
Ref Item Qty Unit Rate Total £ Comment
1 Good Practise
To include all costs of minimum standard unless
duplication 942,766
1.1 Kingspan Optim-R rigid vacuum insulation panel
with a microporous core which is evacuated,
encased and sealed in a thin, gas-tight envelope,
giving outstanding thermal conductivity, with
the thinnest possible solution to insulation
problems. 40mm think; 300 x 600mm board size.
[note – expensive option]
6,048 m2 185 1,118,828 Based on information provided by Kingspan; prices reflect
the cost for specific product.
1.2 Allowance for addressing any thermal bridging
with appropriate detailing.
82 nr 1,000 82,000 Provisional sum.
1.3 Xpelair Muro through the wall heat recovery
ventilation unit for single room incorporate an
80% efficient counter flow heat exchanger; Long
life, low energy DC constant volume motors for
both air intake and extract; Integral display for
fan speed selection and filter/fault function -
continuous operation mode option; Built-in frost
protection function; Removable front fascia for
easy access to filters for cleaning; Automatic
defrost function prevents freezing; Condensate
drain provided to outside of the property; EPP
square wall set.
82 nr 1,450 118,900 Based on information provided by Xpelair; prices reflect
cost for specific product.
1.4 Replacement Thermostatic Radiator Valves;
Drayton RT414 thermostatic radiator valves
provide control of individual room
temperatures. With integral thermostatic
sensing head and reverse flow capability, the
15mm angle.
462 nr 75 34,650 Based on Information shared through Drayton; prices
reflect the cost for specific product. An assumption has
been made that there will be 5nr radiators per flat and 7nr
radiators per house.
1.5 Provision of Photovoltaic panels and control
systems to single houses.
71 nr 3,500 247,333 Based on Information shared through Green Power. An
assumption has been made that there will be 1nr panel
per flat and 2nr panels per house (please refer to PRP -
Existing building measurements).
1.6 Provision of controlled doors with keypad
system to existing bin store doors.
20 nr 200 4,000 Based on benchmarking analysis for mehcanical
combination locks. An assumption has been made for 2nr
double doors before the bin store.
1.7 Provision of additional bin stores to match
existing
10 nr 14,000 140,000 Cost to reflect the construction of bin stores with brick
walls and metal sheet roofing. An assumption has been of
approximate 9m2 per bin store.
1.8 Provision of balconies to apartments currently
without balconies; MKG Systems Cantilever &
Self-Supporting Bolt on Balcony Systems; A
projecting steel-framed/Aluminium balcony
which is bolted on to a building; style to match
existing balconies.
- nr 15,000 - Based on quote provided by Sapphire; prices reflect the
cost for specific product. An assumption of 2,5m2 has
been made for each Bolt-on balcony.
Camden Goods Yard
Preliminary Estimate
Option 3 - Refurbishment
3.4 Summary of estimate OPTION B - GOOD PRACTISE (GILBEYS)
Existing Units
Ref Item Qty Unit Rate Total £ Comment
1.9 Replacement of undersized balconies as above. 82 nr 16,000 1,312,000
1.10 Provision of entrance canopies to houses, steel
framed polyester powder coated finish.
30 nr 1,200 36,000 Based on benchmarking information, the price reflects
entrance canopy to double doors.
B Sub total 4,036,477
C Preliminaries and management costs 14% 565,107 site set up, management, scaffold, site labour, etc
D Main Contractors design fees & any pre-
construction fees
7%282,553
E Main Contractors overheads 7% 341,890 assumes a design and build form of contract
F Contingency/Risk 10% 522,603
G Construction cost inflation for the pre-
construction and construction periods
0%excluded
H Total Estimated Construction Cost 5,748,630
Main Summary
£/unit 70,105
Camden Goods Yard
Preliminary Estimate
Option 3 - Refurbishment
3.5 Summary of estimate OPTION C - BEST PRACTICE (JUNIPER)
Existing Units
Ref Item Qty Unit Rate Total £ Comment
1 Best practise
To include all costs of minimum standard and
Good Practice unless duplication
5,635,057
1.1 Provision of MVHR – Xpelair Natural Air 180
Mechanical Ventilation with Heat Recovery
(MVHR) unit with pre- heater provides whole-
house ventilation; features 100% summer
bypass and winter defrost functions for year-
round temperature comfort; Heater connection
sockets and the required power board included;
Sound absorbing EPP construction with metal
casing; incl. repolacement ceiling
120 nr 5,500 660,000 Based on information provided by Xpelair; prices reflect
the cost for specific product.
1.2 Conversion of Roof voids to provide additional
habitable rooms including dormer windows.
2,160 m2 3,500 7,559,650 The rate has been calculated based on previous schemes.
1.3 Provision of Smart Building controls to all units. 120 nr 750 90,000 Provisional sum.
1.4 Extra over allowance for upgrading to Hybrid
boiler systems plus solar thermal.
120 nr 2,500 300,000 Provisional sum.
1.5 Provision of Ground source heat pumps.
Provisional allowance.
1 item 150,000 150,000 Provisional Allowance
1.6 Conversion of existing bin stores to Bike Stores. 6 nr 12,500 75,000
1.7 Construction of new stair core to blocks
incorporating lift serving each floor. Provisional
allowance.
6 nr 115,000 690,000 An assumption has been made for 6 person lift.
B Sub total 15,159,707
C Preliminaries and management costs 13% 1,970,762 site set up, management, scaffold, site labour, etc
D Main Contractors design fees & any pre-
construction fees
8% 1,212,777
E Main Contractors overheads 7% 1,284,027 assumes a design and build form of contract
F Contingency/Risk 10% 1,962,727
G Construction cost inflation for the pre-
construction and construction periods
0% excluded
H Total Estimated Construction Cost 21,590,000
I Cost data
£/unit 179,917
Camden Goods Yard
Preliminary Estimate
Option 3 - Refurbishment
3.6 Summary of estimate OPTION C - BEST PRACTICE (GILBEYS)
Existing Units
Ref Item Qty Unit Rate Total £ Comment
1 Best practise
To include all costs of minimum standard and
Good Practice unless duplication
3,885,329
1.1 Provision of MVHR – Xpelair Natural Air 180
Mechanical Ventilation with Heat Recovery
(MVHR) unit with pre- heater provides whole-
house ventilation; features 100% summer
bypass and winter defrost functions for year-
round temperature comfort; Heater connection
sockets and the required power board included;
Sound absorbing EPP construction with metal
casing;
82 nr 5,500 451,000 Based on information provided by Xpelair; prices reflect
the cost for specific product.
1.2 Conversion of Roof voids to provide additional
habitable rooms including dormer windows.
2,160 m2 3,500 7,559,650 The rate has been calculated based on previous schemes.
1.3 Provision of Smart Building controls to all units. 82 nr 750 61,500 Provisional sum.
1.4 Extra over allowance for upgrading to Hybrid
boiler systems plus solar thermal.
82 nr 2,500 205,000 Provisional sum.
1.5 Provision of Ground source heat pumps.
Provisional allowance.
1 item 150,000 150,000 Provisional Allowance
1.6 Conversion of existing bin stores to Bike Stores. 10 nr 12,500 125,000
1.7 Construction of new stair core to blocks
incorporating lift serving each floor. Provisional
allowance.
12 nr 115,000 1,380,000 An assumption has been made for 6 person lift.
B Sub total 13,817,479
C Preliminaries and management costs 13% 1,796,272 site set up, management, scaffold, site labour, etc
D Main Contractors design fees & any pre-
construction fees
8% 1,105,398
E Main Contractors overheads 7% 1,170,340 assumes a design and build form of contract
F Contingency/Risk 10% 1,788,949
G Construction cost inflation for the pre-
construction and construction periods
0% excluded
H Total Estimated Construction Cost 19,678,439
I Cost data
£/unit 239,981
Camden Goods Yard
Preliminary Estimate
Option 3 - Refurbishment
4. INFORMATION USED IN PREPARING THIS REPORT
Ref Number Rev Title
1.1 AA6569 DRAFT PRP - Existing Building Measurements
1.2 AA6596 DRAFT CGY - Design Info
Camden Goods Yard
Preliminary Estimate
Option 3 - Refurbishment
AREA SCHEDULE
Description TOTAL
Juniper A Juniper B Gilbeys A Gilbeys B Gilbeys C Gilbeys D
Houses 10 35 14 7 5 0 71
Flats 18 57 12 4 8 32 131
Total Units 28 92 26 11 13 32 202
Total Flat Cores 18 57 12 4 8 32 131
Level 0 841 2,709 858 376 345 582 5,710
Level 1 841 2,709 839 353 345 571 5,658
Level 2 841 2,709 839 353 345 571 5,658
Level 3 244 945 207 69 142 571 2,178
Total floor Area 2,766 9,073 2,742 1,150 1,176 2,296 19,204
Roof Area (total) 841 2,709 858 376 345 582 5,710
Level 0 208 729 217 102 95 152 1,503
Level 1 208 729 212 96 95 149 1,489
Level 2 208 729 212 96 95 149 1,489
Level 3 88 318 77 35 56 149 722
Total Perimeter 711 2,505 717 329 341 599 5,203
External Wall 213 751 215 99 102 180 1,561
GIA 2,553 8,321 2,527 1,052 1,074 2,116 468
EXTERNAL WALL
UNITS
Juniper Gilbeys
AREA
Option 4 Infill Option A
Preliminary Estimate
Camden Goods Yard (Option 4 - Infill Option A)
Dated: 04/04/2018Revision 0
Prepared for :
One Housing Group
Prepared by : Teik Khor
Approved by : Tim Young
Camden Goods Yard
Preliminary Estimate
CONTENTS
1 INTRODUCTION & EXECUTIVE SUMMARY
2 NOTES AND CLARIFICATIONS
3 SUMMARY OF ESTIMATE
4 BENCHMARK DATA
5 INFORMATION USED IN PREPARING THIS REPORT
6 REVISION LOG
1 INTRODUCTION & EXECUTIVE SUMMARY
1.1
1.2 This Preliminary Estimate amounts to: £3,618,679 excluding commercial
A Summary Of Cost
Main Summary Total M2 £/m2 Abnormal £ £ Total
Juniper Crescent
Private 509 £2,881 £0 £1,466,769
Shared Ownership/ Intermediate Rent 127 £2,831 £0 £360,327
Affordable Reprovison - £2,631 £0 £0
Additional Affordable 382 £2,631 £0 £1,004,602
Sub Total 1,018 £2,831,698
Gilbeys Yard
Private 143 £2,881 £0 £411,341
Shared Ownership/ Intermediate Rent - £2,831 £0 £0
Affordable Reprovision - £2,631 £0 £0
Additional Affordable 143 £2,631 £0 £375,641
Sub Total 286 £786,981
Total 1,304 £2,775 £3,618,679
Commercial
Juniper Crescent - £1,251 £0 £0
Gilbeys Yard - £1,252 £0 £0
Total including commercial 1,304 £2,775 £3,618,679
B Abnormal & Risk Items (Included Above)
Main Summary Qu Unit Rate £ at current day
rates Juniper Crescent
Sub Total £0
Gilbeys Yard
Sub Total £0
Total including commercial £0
2 NOTES AND CLARIFICATIONS
2.1.1 The estimate is based on the details provided in PRP document Infill Option A and schedule of units.
2.1.2
2.2 Our estimate excludes the following:
2.2.1 Professional and legal fees
2.2.2
2.2.3
2.2.4
2.2.5
2.2.6
2.2.7
2.2.8
2.2.9
2.2.10
2.2.11 Marketing budget or any purpose build show flats or marketing suite
2.2.12
2.2.13 Flood prevention
2.2.14
2.2.15 Removal of asbestos.
2.2.16 Contaminated land remediation.
Surveys and investigations.
Planning / Building Regulation fees.
Finance charges.
Party Wall matters & Rights of light issues.
Removal of any Japanese Knotweed or other invasive weeds.
Relocating habitat of any protected wildlife on or off site and any surveys (Slow worms, etc.)
Carbon Reduction Levy.
VAT.
Local & Mayoral CIL payments, Cross rail levy, Section 278, Section 106 contributions and other contributions.
We have prepared this Preliminary Estimate for the proposed residential development in line with the area schedule Camden Goods Yard (option 4), Infill A
Cost are current as 2Q 2018
Service diversion.
Option 4 Infill Option A
Archaeological and cost associated.
Camden Goods Yard
Preliminary Estimate
Option 4 Infill Option ASummary of estimate
3.1 Private Apartment - Typical apartment cost to provide Rate/m2
Ref Item Qty GIA Unit Rate Total £ Comment
0 Facilitating works 1,304 m2 50 65,200 Minimal site preparation works
1 Substructure 1,304 m2 220 286,880 Foundations and ground floor slab
2 Superstructure Traditional external walls, windows, stairs, doors
2.1 Frame 1,304 m2 - -
2.2 Upper Floors 1,304 m2 150 195,600
2.3 Roof 1,304 m2 225 293,400
2.4 Stairs 1,304 m2 25 32,600
2.5 External Walls 1,304 m2 325 423,800
2.6 External Windows and Doors 1,304 m2 110 143,440
2.7 Internal Walls and Partitions 1,304 m2 90 117,360
3 Finishes Ceilings, wall and Floor coverings
3.1 Internal Doors 1,304 m2 60 78,240
3.2 Wall Finishes 1,304 m2 60 78,240
3.3 Floor Finishes 1,304 m2 80 104,320
3.4 Ceiling Finishes 1,304 m2 45 58,680
4 Fittings and Furnishings 1,304 m2 185 241,240 Kitchens, wardrobes, skirtings, window boards, etc
Allowance includes £10k for kitchen
5 Services 1,304 m2 395 515,080 Electrical, mechanical and plumbing; Assumes CHP
Incoming utilities 10 apart. 2,500 25,000
6 External Works 1,304 m2 85 110,840
-
E Sub total 2,769,920
F Preliminaries and management costs 16% 443,187 site set up, management, scaffold, site labour, etc
G Main Contractors design fees & any pre-
construction fees
7%193,894
H Main Contractors overheads 5% 170,350 assumes a design and build form of contract
I Contingency/Risk 5% 178,867.58
J Construction cost inflation for the pre-
construction and construction periods
0%excluded
K Total Estimated Construction Cost 3,756,219
L Cost data
Rate /m2 2,881
-
Camden Goods Yard
4. INFORMATION USED IN PREPARING THIS REPORT
Ref Number Rev Title
AA6569_Existing Building Measurements_DRAFT
AA6596_CGY_Draft Design Info
AA6596_SK027-Infill Opt.A L00 A; SK028-Infill Opt.A L01 A; SK029-Infill Opt.A L02 A; SK030-Infill Opt.A Roof Level A
AA6596_Options Appraisal Schedules_170920
Preliminary Estimate
Camden Goods Yard
5. BENCHMARK DATA Costs updated to 2nd quarter 2018
Private Rate
£/m2 GIA
GML Phase 2b £2,745 West London regeneration scheme
Wharf Road £2,862 Islington cannal side scheme
South Kilburn £2,621 Large regeneration scheme
London Road £2,549 West London scheme
Preliminary Estimate
Option 4 Infill Option A
Preliminary Estimate
Camden Goods Yard (Option 4 - Infill Option B)
Dated: 04/04/2018Revision 0
Prepared for :
One Housing Group
Prepared by : Teik Khor
Approved by : Tim Young
Camden Goods Yard
Preliminary Estimate
CONTENTS
1 INTRODUCTION & EXECUTIVE SUMMARY
2 NOTES AND CLARIFICATIONS
3 SUMMARY OF ESTIMATE
4 BENCHMARK DATA
5 INFORMATION USED IN PREPARING THIS REPORT
6 REVISION LOG
1 INTRODUCTION & EXECUTIVE SUMMARY
1.1
1.2 This Preliminary Estimate amounts to: £5,198,135 excluding commercial
A Summary Of Cost
Main Summary Total M2 £/m2 Abnormal £ £ Total
Juniper Crescent
Private 791 £2,880 £0 £2,277,952
Shared Ownership/ Intermediate Rent 266 £2,830 £0 £752,737
Affordable Reprovision - £2,630 £0 £0
Additional Affordable 668 £2,630 £0 £1,756,206
Sub Total 1,725 £4,786,894
Gilbeys Yard
Private 143 £2,880 £0 £411,241
Shared Ownership/ Intermediate Rent - £2,830 £0 £0
Affordable Reprovision - £2,630 £0 £0
Additional Affordable - £2,630 £0 £0
Sub Total 143 £411,241
Total 1,868 £2,783 £5,198,135
Commercial
Juniper Crescent - £1,251 £0 £0
Gilbeys Yard - £1,252 £0 £0
Total including commercial 1,868 £2,783 £5,198,135
B Abnormal & Risk Items (Included Above)
Main Summary Qu Unit Rate £ at current day
rates Juniper Crescent
Sub Total £0
Gilbeys Yard
Sub Total £0
Total including commercial £0
2 NOTES AND CLARIFICATIONS
2.1.1 The estimate is based on the details provided in PRP document Infill Option B and schedule of units.
2.1.2
2.2 Our estimate excludes the following:
2.2.1 Professional and legal fees
2.2.2
2.2.3
2.2.4
2.2.5
2.2.6
2.2.7
2.2.8
2.2.9
2.2.10
2.2.11 Marketing budget or any purpose build show flats or marketing suite
2.2.12
2.2.13 Flood prevention
2.2.14
2.2.15 Removal of asbestos.
2.2.16 Contaminated land remediation.
Surveys and investigations.
Planning / Building Regulation fees.
Finance charges.
Party Wall matters & Rights of light issues.
Removal of any Japanese Knotweed or other invasive weeds.
Relocating habitat of any protected wildlife on or off site and any surveys (Slow worms, etc.)
Carbon Reduction Levy.
VAT.
Local & Mayoral CIL payments, Cross rail levy, Section 278, Section 106 contributions and other contributions.
We have prepared this Preliminary Estimate for the proposed residential development in line with the area schedule Camden Goods Yard (option 4), Infill B
Cost are current as 2Q 2018
Service diversion.
Option 4 Infill Option B
Archaeological and cost associated.
Camden Goods Yard
Preliminary Estimate
Option 4 Infill Option ASummary of estimate
3.1 Private Apartment - Typical apartment cost to provide Rate/m2
Ref Item Qty GIA Unit Rate Total £ Comment
0 Facilitating works 1,340 m2 50 67,000 Minimal site preparation works
1 Substructure 1,340 m2 220 294,800 Foundations and ground floor slab
2 Superstructure Traditional external walls, windows, stairs, doors
2.1 Frame 1,340 m2 - -
2.2 Upper Floors 1,340 m2 150 201,000
2.3 Roof 1,340 m2 225 301,500
2.4 Stairs 1,340 m2 25 33,500
2.5 External Walls 1,340 m2 325 435,500
2.6 External Windows and Doors 1,340 m2 110 147,400
2.7 Internal Walls and Partitions 1,340 m2 90 120,600
3 Finishes Ceilings, wall and Floor coverings
3.1 Internal Doors 1,340 m2 60 80,400
3.2 Wall Finishes 1,340 m2 60 80,400
3.3 Floor Finishes 1,340 m2 80 107,200
3.4 Ceiling Finishes 1,340 m2 45 60,300
4 Fittings and Furnishings 1,340 m2 185 247,900 Kitchens, wardrobes, skirtings, window boards, etc
Allowance includes £10k for kitchen
5 Services 1,340 m2 395 529,300 Electrical, mechanical and plumbing; Assumes CHP
Incoming utilities 10 apart. 2,500 25,000
6 External Works 1,340 m2 85 113,900
-
E Sub total 2,845,700
F Preliminaries and management costs 16% 455,312 site set up, management, scaffold, site labour, etc
G Main Contractors design fees & any pre-
construction fees
7%199,199
H Main Contractors overheads 5% 175,011 assumes a design and build form of contract
I Contingency/Risk 5% 183,761.08
J Construction cost inflation for the pre-
construction and construction periods
0%excluded
K Total Estimated Construction Cost 3,858,983
L Cost data
Rate /m2 2,880
-
must = zero
Camden Goods Yard
4. INFORMATION USED IN PREPARING THIS REPORT
Ref Number Rev Title
AA6569_Existing Building Measurements_DRAFT
AA6596_CGY_Draft Design Info
AA6596_SK031-Infill Opt.B L00 A; SK032-Infill Opt.B L01 A; SK033-Infill Opt.B L02 A; SK034-Infill Opt.B Roof Level A
AA6596_Options Appraisal Schedules_170920
Preliminary Estimate
Camden Goods Yard
5. BENCHMARK DATA Costs updated to 2nd quarter 2018
Private Rate
£/m2 GIA
GML Phase 2b £2,745 West London regeneration scheme
Wharf Road £2,862 Islington cannal side scheme
South Kilburn £2,621 Large regeneration scheme
London Road £2,549 West London scheme
Preliminary Estimate
Option 5 Partial Redevelopment Option A
We have prepared this Preliminary Estimate for the proposed residential development in line with the area schedule Camden Goods Yard (option 5), Partial Redevelopment Option A
Preliminary Estimate
Camden Goods Yard Estimate (Option 5 Partial Redevelopment Option A) DRAFTDated: 26/10/2017Revision 1
Prepared for :
XXXXXXXXXXXXXXX
Camden Goods YardPreliminary Estimate
CONTENTS
1 INTRODUCTION & EXECUTIVE SUMMARY
2 NOTES AND CLARIFICATIONS
3 SUMMARY OF ESTIMATE
4 BENCHMARK DATA
5 INFORMATION USED IN PREPARING THIS REPORT
6 REVISION LOG
1 INTRODUCTION & EXECUTIVE SUMMARY
1.1
1.2 This Preliminary Estimate amounts to: £75,467,277 excluding commercial
Summary Of Cost
Main Summary Total M2 £/m2 Abnormal £ £ Total Note: Abnormal and Risk items
Juniper Crescent apportioned Private 14,285 £2,828 £1,890,907 £42,291,220Shared Ownership/ Intermediate Rent 1,800 £2,778 £238,215 £5,237,833Affordable Reprovison 8,321 £2,578 £1,101,463 £22,554,602Additional Affordable 1,986 £2,578 £262,911 £5,383,621
Sub Total 26,392 £75,467,277
Gilbeys YardPrivate - £2,828 £0 £0Shared Ownership/ Intermediate Rent - £2,778 £0 £0Affordable Reprovision - £2,578 £0 £0Additional Affordable - £2,578 £0 £0
Sub Total - £0 Excluding Abnormals
Total 26,392 £2,860 £75,467,277 £2,727Commercial
Juniper Crescent 259 £1,251 £0 £324,476Gilbeys Yard - £1,252 £0 £0
Total including commercial 26,651 £2,844 £75,791,753
B Abnormal & Risk Items (Included Above)
Main Summary Qu Unit Rate £ at current day Juniper CrescentDemolition 1 item £300,000 £300,000Additional Reduced level dig 3,500 m3 £140 £490,000Retaining Wall 100 m £10,000 £1,000,000 Provisional pending levels Acoustic Treatments 3,750 m2 £100 £375,000 Provisional railway facing walls Public realm 1,200 m2 £150 £180,000Plant room 239 m2 £1,200 £287,088Podium Deck 1,013 m2 £850 £861,409
Sub Total £3,493,497
Gilbeys Yard
Sub Total £0
Total including commercial £3,493,497
2 NOTES AND CLARIFICATIONS
2.1.1 The estimate is based on the details provided in PRP document (Option 5), Partial Redevelopment Option A.2.1.22.1.3 Assumes CHP to all apartments
2.2 Our estimate excludes the following:2.2.1 Professional and legal fees 2.2.22.2.32.2.42.2.52.2.62.2.72.2.82.2.92.2.102.2.11 Marketing budget or any purpose build show flats or marketing suite2.2.122.2.13 Flood prevention2.2.14
Surveys and investigations.
Planning / Building Regulation fees.
Finance charges.Party Wall matters & Rights of light issues.
Removal of any Japanese Knotweed or other invasive weeds.
Relocating habitat of any protected wildlife on or off site and any surveys (Slow worms, etc.)
Carbon Reduction Levy.
VAT.Local & Mayoral CIL payments, Cross rail levy, Section 278, Section 106 contributions and other contributions.
We have prepared this Preliminary Estimate for the proposed residential development in line with the area schedule Camden Goods Yard (Option 5), Partial Redevelopment Option A
Cost are current as 4Q 2017
Service diversion.
Option 5 Partial Redevelopment Option A
Archaeological and cost associated.
2
Camden Goods YardPreliminary Estimate
Option 5 Partial Redevelopment Option ASummary of estimate
3.1 Private Apartment - Typical apartment cost to provide Rate/m2
Ref Item Qty GIA Unit Rate Total £ Comment
0 Facilitating works 26,392 m2 50 1,319,585 Minimal site preparation works
1 Substructure 26,392 m2 210 5,542,257 Foundations and ground floor slab
2 Superstructure Frame , external walls, windows, stairs, doors2.1 Frame 26,392 m2 250 6,597,925 2.2 Upper Floors 26,392 m2 80 2,111,336 2.3 Roof 26,392 m2 170 4,486,589 2.4 Stairs 26,392 m2 15 395,876 2.5 External Walls 26,392 m2 220 5,806,174 2.6 External Windows and Doors 26,392 m2 110 2,903,087 2.7 Internal Walls and Partitions 26,392 m2 90 2,375,253
3 Finishes Ceilings, wall and Floor coverings3.1 Internal Doors 26,392 m2 60 1,583,502 3.2 Wall Finishes 26,392 m2 60 1,583,502 3.3 Floor Finishes 26,392 m2 80 2,111,336 3.4 Ceiling Finishes 26,392 m2 45 1,187,627
4 Fittings and Furnishings 26,392 m2 185 4,882,465 Kitchens, wardrobes, skirtings, window boards, etcAllowance includes £10k for kitchen
5 Services 26,392 m2 395 10,424,722 Electrical, mechanical and plumbing; Assumes CHPIncoming utilities 292 apart. 2,500 730,000
6 External Works 26,392 m2 55 1,451,544
-
E Sub total 55,492,778
F Preliminaries and management costs 16% 8,878,844 site set up, management, scaffold, site labour, etcG Main Contractors design fees & any pre-
construction fees6%
3,329,567 H Main Contractors overheads 5% 3,385,059 assumes a design and build form of contract
I Contingency/Risk 5% 3,554,312
J Construction cost inflation for the pre-construction and construction periods
0%excluded
K Total Estimated Construction Cost 74,640,560
L Cost dataRate /m2 2,828
-
Option 5 Partial Redevelopment Option A
4. INFORMATION USED IN PREPARING THIS REPORT
Ref Number Rev TitleAA6569_Existing Building Measurements_DRAFTAA6596_CGY_Draft Design InfoAA6596_SK014-Partial Opt. A L00; SK015Partial Opt. A L01; SK016-Partial Opt. A Roof LevelAA6596_Partial Options - Like for like_171026
Preliminary Estimate
4
Option 5 Partial Redevelopment Option A
5. BENCHMARK DATA Costs updated to 4th qu 2017
Private Rate£/m2 GIA
GML Phase 2b £2,745 West London regeneration schemeWharf Road £2,862 Islington cannal side schemeSouth Kilburn £2,621 Large regeneration schemeLondon Road £2,549 West London scheme
Preliminary Estimate
5
Option 5 Partial Redevelopment Option A
Rev Date Detail
1 Revised unit schedule; reduced unit numbers to 292234567
Preliminary Estimate
21/08/2614
6
Option 5 Partial Redevelopment Option A
Preliminary Estimate
Camden Goods Yard Estimate (Option 5 Partial Redevelopment Option B) DRAFTDated: 26/10/2017Revision 1
Prepared for :
XXXXXXXXXXXXXXX
Camden Goods YardPreliminary Estimate
CONTENTS
1 INTRODUCTION & EXECUTIVE SUMMARY
2 NOTES AND CLARIFICATIONS
3 SUMMARY OF ESTIMATE
4 BENCHMARK DATA
5 INFORMATION USED IN PREPARING THIS REPORT
6 REVISION LOG
1 INTRODUCTION & EXECUTIVE SUMMARY
1.1
1.2 This Preliminary Estimate amounts to: £30,982,944 excluding commercial
Summary Of Cost
Main Summary Total M2 £/m2 Abnormal £ £ Total Note: Abnormal and Risk items
Juniper Crescent apportioned Private 5,081 £2,830 £666,892 £15,044,215Shared Ownership/ Intermediate Rent 1,559 £2,780 £204,597 £4,537,511Affordable Reprovison 2,553 £2,580 £335,103 £6,921,226Additional Affordable 1,653 £2,580 £216,906 £4,479,992
Sub Total 10,845 £30,982,944
Gilbeys YardPrivate - £2,830 £0 £0Shared Ownership/ Intermediate Rent - £2,830 £0 £0Affordable Reprovision - £2,830 £0 £0Additional Affordable - £2,830 £0 £0
Sub Total - £0 Excluding Abnormals
Total 10,845 £2,857 £30,982,944 £2,726Commercial
Juniper Crescent - £1,251 £0 £0Gilbeys Yard - £1,252 £0 £0
Total including commercial 10,845 £2,857 £30,982,944
B Abnormal & Risk Items (Included Above)
Main Summary Qu Unit Rate £ at current day Juniper CrescentDemolition 1 item £150,000 £150,000Additional Reduced level dig 250 m3 £140 £35,000Retaining Wall 25 m £10,000 £250,000 Provisional pending levels Acoustic Treatments 1,250 m2 £100 £125,000 Provisional railway facing walls Public realm 350 m2 £150 £52,500Plant room 150 m2 £1,200 £180,000Podium Deck 742 m2 £850 £630,998
Sub Total £1,423,498
Gilbeys Yard
Sub Total £0
Total including commercial £1,423,498
2 NOTES AND CLARIFICATIONS
2.1.1 The estimate is based on the details provided in PRP document (Option 5), Partial Redevelopment Option B.2.1.22.1.3 Assumes CHP to all apartments
2.2 Our estimate excludes the following:2.2.1 Professional and legal fees 2.2.22.2.32.2.42.2.52.2.62.2.72.2.82.2.92.2.102.2.11 Marketing budget or any purpose build show flats or marketing suite2.2.122.2.13 Flood prevention2.2.14
We have prepared this Preliminary Estimate for the proposed residential development in line with the area schedule Camden Goods Yard (Option 5), Partial Redevelopment Option B
Cost are current as 4Q 2017
Service diversion.
Option 5 Partial Redevelopment Option B
Archaeological and cost associated.
Surveys and investigations.
Planning / Building Regulation fees.
Finance charges.Party Wall matters & Rights of light issues.
Removal of any Japanese Knotweed or other invasive weeds.
Relocating habitat of any protected wildlife on or off site and any surveys (Slow worms, etc.)
Carbon Reduction Levy.
VAT.Local & Mayoral CIL payments, Cross rail levy, Section 278, Section 106 contributions and other contributions.
2
Camden Goods YardPreliminary Estimate
Option 5 Partial Redevelopment Option ASummary of estimate
3.1 Private Apartment - Typical apartment cost to provide Rate/m2
Ref Item Qty GIA Unit Rate Total £ Comment
0 Facilitating works 10,845 m2 50 542,255 Minimal site preparation works
1 Substructure 10,845 m2 210 2,277,471 Foundations and ground floor slab
2 Superstructure Frame , external walls, windows, stairs, doors2.1 Frame 10,845 m2 250 2,711,275 2.2 Upper Floors 10,845 m2 80 867,608 2.3 Roof 10,845 m2 170 1,843,667 2.4 Stairs 10,845 m2 15 162,677 2.5 External Walls 10,845 m2 220 2,385,922 2.6 External Windows and Doors 10,845 m2 110 1,192,961 2.7 Internal Walls and Partitions 10,845 m2 90 976,059
3 Finishes Ceilings, wall and Floor coverings3.1 Internal Doors 10,845 m2 60 650,706 3.2 Wall Finishes 10,845 m2 60 650,706 3.3 Floor Finishes 10,845 m2 80 867,608 3.4 Ceiling Finishes 10,845 m2 45 488,030
4 Fittings and Furnishings 10,845 m2 185 2,006,344 Kitchens, wardrobes, skirtings, window boards, etcAllowance includes £10k for kitchen
5 Services 10,845 m2 395 4,283,815 Electrical, mechanical and plumbing; Assumes CHPIncoming utilities 125 apart. 2,500 312,500
6 External Works 10,845 m2 55 596,481
-
E Sub total 22,816,083
F Preliminaries and management costs 16% 3,650,573 site set up, management, scaffold, site labour, etcG Main Contractors design fees & any pre-
construction fees6%
1,368,965 H Main Contractors overheads 5% 1,391,781 assumes a design and build form of contract
I Contingency/Risk 5% 1,461,370.08
J Construction cost inflation for the pre-construction and construction periods
0%excluded
K Total Estimated Construction Cost 30,688,772
L Cost dataRate /m2 2,830
-
Option 5 Partial Redevelopment Option B
4. INFORMATION USED IN PREPARING THIS REPORT
Ref Number Rev TitleAA6569_Existing Building Measurements_DRAFTAA6596_CGY_Draft Design InfoAA6596_SK017-Partial Opt. B L00; SK018 Partial Opt. B L01; SK019-Partial Opt. B Roof LevelAA6596_Partial Options - Like for like_171026
Preliminary Estimate
4
Option 5 Partial Redevelopment Option B
5. BENCHMARK DATA Costs updated to 4th qu 2017
Private Rate£/m2 GIA
GML Phase 2b £2,745 West London regeneration schemeWharf Road £2,862 Islington cannal side schemeSouth Kilburn £2,621 Large regeneration schemeLondon Road £2,549 West London scheme
Preliminary Estimate
5
Option 5 Partial Redevelopment Option B
Rev Date Detail
1 Revised unit schedule; reduced unit numbers to 125234567
Preliminary Estimate
26/10/2017
6
Option 5 Partial Redevelopment Option A
We have prepared this Preliminary Estimate for the proposed residential development in line with the area schedule Camden Goods Yard (option 5), Partial Redevelopment Option A
Preliminary Estimate
Camden Goods Yard Estimate (Option 5 Partial Redevelopment Option C) DRAFTDated: 26/10/2017Revision 1
Prepared for :
XXXXXXXXXXXXXXX
Camden Goods YardPreliminary Estimate
CONTENTS
1 INTRODUCTION & EXECUTIVE SUMMARY
2 NOTES AND CLARIFICATIONS
3 SUMMARY OF ESTIMATE
4 BENCHMARK DATA
5 INFORMATION USED IN PREPARING THIS REPORT
6 REVISION LOG
1 INTRODUCTION & EXECUTIVE SUMMARY
1.1
1.2 This Preliminary Estimate amounts to: £39,062,780 excluding commercial
Summary Of Cost
Main Summary Total M2 £/m2 Abnormal £ £ Total Note: Abnormal and Risk items
Juniper Crescent apportioned Private - £2,827 £0 £0Shared Ownership/ Intermediate Rent - £2,777 £0 £0Affordable Reprovison - £2,577 £0 £0Additional Affordable - £2,577 £0 £0
Sub Total - £0
Gilbeys YardPrivate 6,001 £2,827 £859,903 £17,827,008Shared Ownership/ Intermediate Rent 1,033 £2,777 £147,941 £3,015,390Affordable Reprovision 4,553 £2,577 £652,311 £12,385,180 100m2 deducted for single leasehold
unit Additional Affordable 2,145 £2,577 £307,332 £5,835,201
Sub Total 13,731 £39,062,780 Excluding Abnormals
Total 13,731 £2,845 £39,062,780 £2,701Commercial
Juniper Crescent - £1,251 £0Gilbeys Yard 104 £1,252 £130,823
Total including commercial 13,836 £2,833 £39,193,602
B Abnormal & Risk Items (Included Above)
Main Summary Qu Unit Rate £ at current day Juniper Crescent
Sub Total £0
Gilbeys YardDemolition 1 item £300,000 £300,000Canal Wall Works 84 m £1,500 £126,000Enhanced Elevations 1,000 m2 £500 £500,000Plant room 150 m2 £1,200 £180,000Podium Deck 1,014 m2 £850 £861,487
Sub Total £1,967,487
Total including commercial £1,967,487
2 NOTES AND CLARIFICATIONS
2.1.1 The estimate is based on the details provided in PRP document (Option 5), Partial Redevelopment Option C.2.1.2
2.2 Our estimate excludes the following:2.2.1 Professional and legal fees 2.2.22.2.32.2.42.2.52.2.62.2.72.2.82.2.92.2.102.2.11 Marketing budget or any purpose build show flats or marketing suite2.2.122.2.13 Flood prevention2.2.14
We have prepared this Preliminary Estimate on the area schedule Camden Goods Yard (Option 5), Partial Redevelopment Option C
Cost are current as 4Q 2017
Service diversion.
Option 5 Partial Redevelopment Option C
Archaeological and cost associated.
Surveys and investigations.
Planning / Building Regulation fees.
Finance charges.Party Wall matters & Rights of light issues.
Removal of any Japanese Knotweed or other invasive weeds.
Relocating habitat of any protected wildlife on or off site and any surveys (Slow worms, etc.)
Carbon Reduction Levy.
VAT.Local & Mayoral CIL payments, Cross rail levy, Section 278, Section 106 contributions and other contributions.
2
Camden Goods YardPreliminary Estimate
3.1 Private Apartment - Typical apartment cost to provide Rate/m2
Ref Item Qty GIA Unit Rate Total £ Comment
0 Facilitating works 13,836 m2 50 691,795 Minimal site preparation works
1 Substructure 13,836 m2 210 2,905,537 Foundations and ground floor slab
2 Superstructure Frame , external walls, windows, stairs, doors2.1 Frame 13,836 m2 250 3,458,973 2.2 Upper Floors 13,836 m2 80 1,106,871 2.3 Roof 13,836 m2 170 2,352,101 2.4 Stairs 13,836 m2 15 207,538 2.5 External Walls 13,836 m2 220 3,043,896 2.6 External Windows and Doors 13,836 m2 110 1,521,948 2.7 Internal Walls and Partitions 13,836 m2 90 1,245,230
3 Finishes Ceilings, wall and Floor coverings3.1 Internal Doors 13,836 m2 60 830,153 3.2 Wall Finishes 13,836 m2 60 830,153 3.3 Floor Finishes 13,836 m2 80 1,106,871 3.4 Ceiling Finishes 13,836 m2 45 622,615
4 Fittings and Furnishings 13,836 m2 185 2,559,640 Kitchens, wardrobes, skirtings, window boards, etcAllowance includes £10k for kitchen
5 Services 13,836 m2 395 5,465,177 Electrical, mechanical and plumbing; Assumes CHPIncoming utilities 149 apart. 2,500 372,500
6 External Works 13,836 m2 55 760,974
-
E Sub total 29,081,974
F Preliminaries and management costs 16% 4,653,116 site set up, management, scaffold, site labour, etcG Main Contractors design fees & any pre-
construction fees6%
1,744,918 H Main Contractors overheads 5% 1,774,000 assumes a design and build form of contract
I Contingency/Risk 5% 1,862,700.42
J Construction cost inflation for the pre-construction and construction periods
0%excluded
K Total Estimated Construction Cost 39,116,709
L Cost dataRate /m2 2,827
-
Option 5 Partial Redevelopment Option C
Option 5 Partial Redevelopment Option C
4. INFORMATION USED IN PREPARING THIS REPORT
Ref Number Rev TitleAA6569_Existing Building Measurements_DRAFTAA6596_CGY_Draft Design InfoAA6596_SK020-Partial Opt. C L00; SK021Partial Opt. C L01; SK022-Partial Opt. C Roof LevelAA6596_Partial Options - Like for like_171026
Preliminary Estimate
4
Option 5 Partial Redevelopment Option C
5. BENCHMARK DATA Costs updated to 4th qu 2017
Private Rate£/m2 GIA
GML Phase 2b £2,745 West London regeneration schemeWharf Road £2,862 Islington cannal side schemeSouth Kilburn £2,621 Large regeneration schemeLondon Road £2,549 West London scheme
Preliminary Estimate
5
Option 5 Partial Redevelopment Option C
Rev Date Detail
1 Revised unit schedule; reduced unit numbers to 149234567
Preliminary Estimate
26/10/2017
6
Option 5 Partial Redevelopment Option D
AA6596_SK024-Partial Opt. D L00 A; SK025 Partial Opt. D L01 A; SK026-Partial Opt. D Roof Level A
Preliminary Estimate
Camden Goods Yard Estimate (Option 5 Partial Redevelopment Option D) DRAFTDated: 26/10/2017Revision 1
Prepared for :
XXXXXXXXXXXXXXX
Camden Goods YardPreliminary Estimate
CONTENTS
1 INTRODUCTION & EXECUTIVE SUMMARY
2 NOTES AND CLARIFICATIONS
3 SUMMARY OF ESTIMATE
4 BENCHMARK DATA
5 INFORMATION USED IN PREPARING THIS REPORT
6 REVISION LOG
1 INTRODUCTION & EXECUTIVE SUMMARY
1.1
1.2 This Preliminary Estimate amounts to: £11,781,378 excluding commercial
Summary Of Cost
Main Summary Total M2 £/m2 Abnormal £ £ Total Note: Abnormal and Risk items
Juniper Crescent apportioned Private - £2,831 £0 £0Shared Ownership/ Intermediate Rent - £2,781 £0 £0Affordable Reprovison - £2,581 £0 £0Additional Affordable - £2,581 £0 £0
Sub Total - £0
Gilbeys YardPrivate 1,707 £2,831 £77,901 £4,909,856Shared Ownership/ Intermediate Rent - £2,781 £0 £0Affordable Reprovision 2,116 £2,581 £96,585 £5,558,367Additional Affordable 500 £2,581 £22,818 £1,313,154
Sub Total 4,323 £11,781,378 Excluding Abnormals
Total 4,323 £2,725 £11,781,378 £2,680Commercial
Juniper Crescent - £1,251 £0 £0Gilbeys Yard 121 £1,252 £0 £151,366
Total including commercial 4,444 £2,685 £11,932,743
B Abnormal & Risk Items (Included Above)
Main Summary Qu Unit Rate £ at current day Juniper Crescent
Sub Total £0
Gilbeys YardDemolition 1 item £150,000 £150,000Canal Wall Works - m £1,500 £0Enhanced Elevations - m2 £500 £0Plant room 39 m2 £1,200 £47,304Podium Deck - m2 £850 £0
Sub Total £197,304
Total including commercial £197,304
2 NOTES AND CLARIFICATIONS
2.1.1 The estimate is based on the details provided in PRP document (Option 5), Partial Redevelopment Option D.2.1.2
2.2 Our estimate excludes the following:2.2.1 Professional and legal fees 2.2.22.2.32.2.42.2.52.2.62.2.72.2.82.2.92.2.102.2.11 Marketing budget or any purpose build show flats or marketing suite2.2.122.2.13 Flood prevention2.2.14
Surveys and investigations.
Planning / Building Regulation fees.
Finance charges.Party Wall matters & Rights of light issues.
Removal of any Japanese Knotweed or other invasive weeds.
Relocating habitat of any protected wildlife on or off site and any surveys (Slow worms, etc.)
Carbon Reduction Levy.
VAT.Local & Mayoral CIL payments, Cross rail levy, Section 278, Section 106 contributions and other contributions.
We have prepared this Preliminary Estimate for the proposed residential development in line with the area schedule Camden Goods Yard (Option 5), Partial Redevelopment Option D
Cost are current as 4Q 2017
Service diversion.
Option 5 Partial Redevelopment Option D
Archaeological and cost associated.
2
Camden Goods YardPreliminary Estimate
3.1 Private Apartment - Typical apartment cost to provide Rate/m2
Ref Item Qty GIA Unit Rate Total £ Comment
0 Facilitating works 4,444 m2 50 222,182 Minimal site preparation works
1 Substructure 4,444 m2 210 933,166 Foundations and ground floor slab
2 Superstructure Frame , external walls, windows, stairs, doors2.1 Frame 4,444 m2 250 1,110,912 2.2 Upper Floors 4,444 m2 80 355,492 2.3 Roof 4,444 m2 170 755,420 2.4 Stairs 4,444 m2 15 66,655 2.5 External Walls 4,444 m2 220 977,603 2.6 External Windows and Doors 4,444 m2 110 488,801 2.7 Internal Walls and Partitions 4,444 m2 90 399,928
3 Finishes Ceilings, wall and Floor coverings3.1 Internal Doors 4,444 m2 60 266,619 3.2 Wall Finishes 4,444 m2 60 266,619 3.3 Floor Finishes 4,444 m2 80 355,492 3.4 Ceiling Finishes 4,444 m2 45 199,964
4 Fittings and Furnishings 4,444 m2 185 822,075 Kitchens, wardrobes, skirtings, window boards, etcAllowance includes £10k for kitchen
5 Services 4,444 m2 395 1,755,241 Electrical, mechanical and plumbing; Assumes CHPIncoming utilities 53 apart. 2,500 132,500
6 External Works 4,444 m2 55 244,401
-
E Sub total 9,353,072
F Preliminaries and management costs 16% 1,496,491 site set up, management, scaffold, site labour, etcG Main Contractors design fees & any pre-
construction fees6%
561,184 H Main Contractors overheads 5% 570,537 assumes a design and build form of contract
I Contingency/Risk 5% 599,064.24
J Construction cost inflation for the pre-construction and construction periods
0%excluded
K Total Estimated Construction Cost 12,580,349
L Cost dataRate /m2 2,831
- must = zero
Option 5 Partial Redevelopment Option D
Option 5 Partial Redevelopment Option D
4. INFORMATION USED IN PREPARING THIS REPORT
Ref Number Rev TitleAA6569_Existing Building Measurements_DRAFTAA6596_CGY_Draft Design InfoAA6596_SK024-Partial Opt. D L00 A; SK025 Partial Opt. D L01 A; SK026-Partial Opt. D Roof Level AAA6596_Partial Options - Like for like_171026
Preliminary Estimate
4
Option 5 Partial Redevelopment Option D
5. BENCHMARK DATA Costs updated to 4th qu 2017
Private Rate£/m2 GIA
GML Phase 2b £2,745 West London regeneration schemeWharf Road £2,862 Islington cannal side schemeSouth Kilburn £2,621 Large regeneration schemeLondon Road £2,549 West London scheme
Preliminary Estimate
5
Option 5 Partial Redevelopment Option D
Rev Date Detail
1 Revised unit schedule; reduced unit numbers to 53234567
Preliminary Estimate
26/10/2017
6
Preliminary Estimate
Camden Goods Yard (Full Redevelopment Sc.1)
Dated: 04/04/2018Revision 0
Prepared for :
One Housing Group
Prepared by : Teik Khor
Approved by : Tim Young
Camden Goods Yard
Preliminary Estimate
CONTENTS
1 INTRODUCTION & EXECUTIVE SUMMARY
2 NOTES AND CLARIFICATIONS
3 SUMMARY OF ESTIMATE
4 BENCHMARK DATA
5 INFORMATION USED IN PREPARING THIS REPORT
6 REVISION LOG
1 INTRODUCTION & EXECUTIVE SUMMARY
1.1Total 700 units; 368 Private units, 95 Shared Ownership units, 237 Affordable Rented units
1.2 This Preliminary Estimate amounts to: £168,443,322 excluding commercial
A Summary Of Cost
Main Summary Total M2 £/m2 Abnormal £ £ Total Note: Abnormal and Risk items
Juniper Crescent apportioned Private 23,284 £2,818 £2,521,393 £68,125,684Shared Ownership/ Intermediate Rent 3,316 £2,768 £359,118 £9,537,211Affordable Reprovision 11,839 £2,568 £1,282,038 £31,679,739Additional Affordable 4,405 £2,568 £477,019 £11,787,349
Sub Total 42,844 £121,129,984
Gilbeys YardPrivate 6,001 £2,808 £765,141 £17,614,743Shared Ownership/ Intermediate Rent 3,180 £2,758 £405,398 £9,173,915Affordable Reprovision 7,365 £2,558 £938,953 £19,774,998Additional Affordable 279 £2,558 £35,596 £749,682
Sub Total 16,825 £47,313,338
Total 59,669 £168,443,322
Commercial
Juniper Crescent 259 £1,361 £126 £353,133
Gilbeys Yard 225 £1,361 £126 £306,882
Total including commercial 60,154 £169,103,337
B Abnormal & Risk Items (Included Above)
Main Summary Qu Unit Rate £ at current day
rates Juniper CrescentDemolition 1 item £350,000 £350,000Additional Reduced level dig 5,000 m3 £140 £700,000Retaining Wall 100 m £10,000 £1,000,000Acoustic Treatments 4,338 m2 £100 £433,816Public realm 1,500 m2 £150 £225,000Plant room 239 m2 £1,200 £287,088Podium parking 1,659 m2 £850 £1,410,413Community centre - m2 £3,450 £0Archaeology 1 item £10,000 £10,000Asbestos - allowance 1 item £18,000 £18,000Service Diversions - allowance 1 item £18,000 £18,000Contamination - allowance 1 item £187,250 £187,250
Sub Total £4,639,567
Gilbeys YardDemolition 1 item £250,000 £250,000Canal wall works 84 m £2,500 £210,000Enhanced elevations 1,000 m2 £500 £500,000Archaeology 1 item £5,000 £5,000Podium parking 1,014 m2 £850 £861,487Plant room 202 m2 £1,200 £242,101Asbestos - allowance 1 item £7,000 £7,000Service Diversions - allowance 1 item £7,000 £7,000Contamination - allowance 1 item £62,500 £62,500
Sub Total £2,145,088
Total including commercial £6,784,655
2 NOTES AND CLARIFICATIONS
2.1.1 The estimate is based on the details provided in PRP document Full Redevelopment Sc. 1 and schedule of units.
2.1.22.1.3 Assumes CHP to all apartments
2.1.4 Allowance for fully fitted out Community Centre including fixed and loose Furniture Fittings and Equipment
2.1.5 We have allowed for repair works to the Canal wall only. Full replacement would be an additional £630,000.
2.1.6 The affordable rented units have been priced at OHG's Social Rented specification.
2.1.7 Full sprinklers to all blocks including commercial other than Block E.
2.1.8 Sub divided commercial space to shell as the OHG brief.
2.2 Our estimate excludes the following:2.2.1 Professional and legal fees.2.2.22.2.32.2.42.2.52.2.6
2.2.7
2.2.82.2.9
2.2.102.2.11 Marketing budget or any purpose build show flats or marketing suite
2.2.12
2.2.13 Flood prevention
2.2.14
2.2.15 Removal of asbestos above the £25,000 allowance
2.2.16 Contaminated land remediation above the £250,000 allowance, noting £700,000 included for additional reduced level dig.
We have prepared this Preliminary Estimate for the proposed residential development in line with the area schedule Camden Goods Yard (option 6), Full Redevelopment Sc.1.
Cost are current as 2Q 2018
Full Redevelopment Sc.1
Party Wall matters & Rights of light issues.
Planning / Building Regulation fees.Archaeological and cost associated above the £15,000 allowance.
Relocating habitat of any protected wildlife on or off site and any surveys (Slow worms, etc.)
Finance charges.
VAT.
Local & Mayoral CIL payments, Cross rail levy, Section 278, Section 106 contributions and other contributions.
Carbon Reduction Levy.
Service diversion above the £25,000 allowance
Surveys and investigations.Removal of any Japanese Knotweed or other invasive weeds.
2
Camden Goods Yard
Preliminary Estimate
3 Summary of estimate
3.1 Private Apartment - Typical apartment cost to provide Rate
Ref Item Qty Unit Rate Total £ Comment
0 Facilitating works 5,350 m2 10 53,500 Minimal site preparation works
1 Substructure 5,350 m2 190 1,016,500 Foundations and ground floor slab
2 Superstructure Frame , external walls, windows, stairs, doors
2.1 Frame 5,350 m2 250 1,337,500
2.2 Upper Floors 5,350 m2 80 428,000
2.3 Roof 5,350 m2 170 909,500
2.4 Stairs 5,350 m2 15 80,250
2.5 External Walls 5,350 m2 220 1,177,000
2.6 External Windows and Doors 5,350 m2 110 588,500
2.7 Internal Walls and Partitions 5,350 m2 90 481,500
3 Finishes Ceilings, wall and Floor coverings
3.1 Internal Doors 5,350 m2 60 321,000
3.2 Wall Finishes 5,350 m2 60 321,000
3.3 Floor Finishes 5,350 m2 80 428,000
3.4 Ceiling Finishes 5,350 m2 45 240,750
4 Fittings and Furnishings 5,350 m2 185 989,750 Kitchens, wardrobes, skirtings, window boards, etc
Allowance includes £6k for kitchen
5 Services 5,350 m2 395 2,113,250 Electrical, mechanical and plumbing; Assumes CHP
5.1 Incoming utilities 64 apart. 2,500 160,000
6 External Works 5,350 m2 55 294,250
7 Abnormal (list as appropriate)
7.1 Sprinklers to all Blocks other than E 5,350 m2 45 240,750
E Sub total 11,181,000
F Preliminaries and management costs 14% 1,565,340 site set up, management, scaffold, site labour, etc
G Main Contractors design fees & any pre-
construction fees
6%670,860
H Main Contractors overheads and profit 7% 939,204 assumes a design and build form of contract
I Contingency/Risk 5% 717,820.20
J Construction cost inflation for the pre-
construction and construction periods
0%excluded
K Total Estimated Construction Cost 15,074,224
L Cost data
Rate /m2 2,818
Camden Goods Yard
4. INFORMATION USED IN PREPARING THIS REPORT
Ref Number Rev Title
AA6569_Existing Building Measurements_DRAFT
AA6596_CGY_Draft Design Info
AA6596_SK009-Full Redevelopment Sc.1 L00_B
AA6596_Options Appraisal Schedules_170920
Preliminary Estimate
4
Camden Goods Yard
5. BENCHMARK DATA Costs updated to 2nd quarter 2018
Private Rate
£/m2 GIA
GML Phase 2b £2,745 West London regeneration scheme
Wharf Road £2,862 Islington canal side scheme
South Kilburn £2,621 Large regeneration scheme
London Road £2,549 West London scheme
Preliminary Estimate
5
Preliminary Estimate
Camden Goods Yard (Full Redevelopment Sc.2)
Dated: 04/04/2018Revision 0
Prepared for :
One Housing Group
Prepared by : Teik Khor
Approved by : Tim Young
Camden Goods Yard
Preliminary Estimate
CONTENTS
1 INTRODUCTION & EXECUTIVE SUMMARY
2 NOTES AND CLARIFICATIONS
3 SUMMARY OF ESTIMATE
4 BENCHMARK DATA
5 INFORMATION USED IN PREPARING THIS REPORT
6 REVISION LOG
1 INTRODUCTION & EXECUTIVE SUMMARY
1.1Total 683 units; 368 Private units, 95 Shared Ownership units, 220 Affordable Rented units
1.2 This Preliminary Estimate amounts to: £167,499,223 excluding commercial
A Summary Of Cost
Main Summary Total M2 £/m2 Abnormal £ £ Total Note: Abnormal and Risk items
Juniper Crescent apportioned Private 23,284 £2,818 £2,524,283 £68,128,574Shared Ownership/ Intermediate Rent 3,316 £2,768 £359,529 £9,537,623Affordable Reprovision 11,839 £2,568 £1,283,507 £31,681,209Additional Affordable 4,356 £2,568 £472,248 £11,656,637
Sub Total 42,795 £121,004,043
Gilbeys YardPrivate 6,001 £2,808 £740,304 £17,589,906Shared Ownership/ Intermediate Rent 3,180 £2,758 £392,239 £9,160,755Affordable Reprovision 7,365 £2,558 £908,474 £19,744,519Additional Affordable - £2,558 £0 £0 Note 370m2 underprovision
Sub Total 16,546 £46,495,180
Total 59,341 £167,499,223
Commercial
Juniper Crescent 259 £1,361 £126 £353,133
Gilbeys Yard 272 £1,361 £126 £369,668
Total including commercial 59,871 £168,222,024
B Abnormal & Risk Items (Included Above)
Main Summary Qu Unit Rate £ at current day
rates Juniper CrescentDemolition 1 item £350,000 £350,000Additional Reduced level dig 5,000 m3 £140 £700,000Retaining Wall 100 m £10,000 £1,000,000Acoustic Treatments 4,338 m2 £100 £433,816Public realm 1,500 m2 £150 £225,000Plant room 239 m2 £1,200 £287,088Podium parking 1,659 m2 £850 £1,410,413Community centre - m2 £3,450 £0Archaeology 1 item £10,000 £10,000Asbestos - allowance 1 item £18,000 £18,000Service Diversions - allowance 1 item £18,000 £18,000Contamination - allowance 1 item £187,250 £187,250
Sub Total £4,639,567
Gilbeys YardDemolition 1 item £250,000 £250,000Canal wall works 84 m £2,500 £210,000Enhanced elevations 1,000 m2 £500 £500,000Archaeology 1 item £5,000 £5,000Podium parking 1,014 m2 £850 £861,487Plant room 115 m2 £1,200 £138,029Asbestos - allowance 1 item £7,000 £7,000Service Diversions - allowance 1 item £7,000 £7,000Contamination - allowance 1 item £62,500 £62,500
Sub Total £2,041,016
Total including commercial £6,680,582
2 NOTES AND CLARIFICATIONS
2.1.1 The estimate is based on the details provided in PRP document Full Redevelopment Sc. 2 and schedule of units.
2.1.22.1.3 Assumes CHP to all apartments
2.1.4 Allowance for fully fitted out Community Centre including fixed and loose Furniture Fittings and Equipment
2.1.5 We have allowed for repair works to the Canal wall only. Full replacement would be an additional £630,000.
2.1.6 The affordable rented units have been priced at OHG's Social Rented specification.
2.1.7 Full sprinklers to all blocks including commercial other than Block E.
2.1.8 Sub divided commercial space to shell as the OHG brief.
2.2 Our estimate excludes the following:2.2.1 Professional and legal fees.2.2.22.2.32.2.42.2.52.2.6
2.2.7
2.2.82.2.9
2.2.102.2.11 Marketing budget or any purpose build show flats or marketing suite
2.2.12
2.2.13 Flood prevention
2.2.14
2.2.15 Removal of asbestos above the £25,000 allowance
2.2.16 Contaminated land remediation above the £250,000 allowance, noting £700,000 included for additional reduced level dig.
Relocating habitat of any protected wildlife on or off site and any surveys (Slow worms, etc.)
Finance charges.
VAT.
Local & Mayoral CIL payments, Cross rail levy, Section 278, Section 106 contributions and other contributions.
Carbon Reduction Levy.
Service diversion above the £25,000 allowance
Surveys and investigations.Removal of any Japanese Knotweed or other invasive weeds.
We have prepared this Preliminary Estimate for the proposed residential development in line with the area schedule Camden Goods Yard (option 6), Full Redevelopment Sc.2.
Cost are current as 2Q 2018
Full Redevelopment Sc.2
Party Wall matters & Rights of light issues.
Planning / Building Regulation fees.Archaeological and cost associated above the £15,000 allowance.
2
Camden Goods Yard
Preliminary Estimate
3 Summary of estimate
3.1 Private Apartment - Typical apartment cost to provide Rate
Ref Item Qty Unit Rate Total £ Comment
0 Facilitating works 5,350 m2 10 53,500 Minimal site preparation works
1 Substructure 5,350 m2 190 1,016,500 Foundations and ground floor slab
2 Superstructure Frame , external walls, windows, stairs, doors
2.1 Frame 5,350 m2 250 1,337,500
2.2 Upper Floors 5,350 m2 80 428,000
2.3 Roof 5,350 m2 170 909,500
2.4 Stairs 5,350 m2 15 80,250
2.5 External Walls 5,350 m2 220 1,177,000
2.6 External Windows and Doors 5,350 m2 110 588,500
2.7 Internal Walls and Partitions 5,350 m2 90 481,500
3 Finishes Ceilings, wall and Floor coverings
3.1 Internal Doors 5,350 m2 60 321,000
3.2 Wall Finishes 5,350 m2 60 321,000
3.3 Floor Finishes 5,350 m2 80 428,000
3.4 Ceiling Finishes 5,350 m2 45 240,750
4 Fittings and Furnishings 5,350 m2 185 989,750 Kitchens, wardrobes, skirtings, window boards, etc
Allowance includes £6k for kitchen
5 Services 5,350 m2 395 2,113,250 Electrical, mechanical and plumbing; Assumes CHP
5.1 Incoming utilities 64 apart. 2,500 160,000
6 External Works 5,350 m2 55 294,250
7 Abnormal (list as appropriate)
7.1 Sprinklers to all Blocks other than E 5,350 m2 45 240,750
E Sub total 11,181,000
F Preliminaries and management costs 14% 1,565,340 site set up, management, scaffold, site labour, etc
G Main Contractors design fees & any pre-
construction fees
6%670,860
H Main Contractors overheads and profit 7% 939,204 assumes a design and build form of contract
I Contingency/Risk 5% 717,820.20
J Construction cost inflation for the pre-
construction and construction periods
0%excluded
K Total Estimated Construction Cost 15,074,224
L Cost data
Rate /m2 2,818
Camden Goods Yard
4. INFORMATION USED IN PREPARING THIS REPORT
Ref Number Rev Title
AA6569_Existing Building Measurements_DRAFT
AA6596_CGY_Draft Design Info
AA6596_SK109-Full Redevelopment Sc.2 L00_
AA6596_SK110-Full Redevelopment Sc.2 L01_
AA6596_SK111-Full Redevelopment Sc.2 Set Back Levels
AA6596_Options Appraisal Schedules_170920
Preliminary Estimate
4
Camden Goods Yard
5. BENCHMARK DATA Costs updated to 2nd quarter 2018
Private Rate
£/m2 GIA
GML Phase 2b £2,745 West London regeneration scheme
Wharf Road £2,862 Islington canal side scheme
South Kilburn £2,621 Large regeneration scheme
London Road £2,549 West London scheme
Preliminary Estimate
5
Preliminary Estimate
Camden Goods Yard (Full Redevelopment Sc.3)
Dated: 04/04/2018Revision 0
Prepared for :
One Housing Group
Prepared by : Teik Khor
Approved by : Tim Young
Camden Goods Yard
Preliminary Estimate
CONTENTS
1 INTRODUCTION & EXECUTIVE SUMMARY
2 NOTES AND CLARIFICATIONS
3 SUMMARY OF ESTIMATE
4 BENCHMARK DATA
5 INFORMATION USED IN PREPARING THIS REPORT
6 REVISION LOG
1 INTRODUCTION & EXECUTIVE SUMMARY
1.1Total 683 units; 368 Private units, 95 Shared Ownership units, 220 Affordable Rented units
1.2 This Preliminary Estimate amounts to: £169,050,603 excluding commercial
A Summary Of Cost
Main Summary Total M2 £/m2 Abnormal £ £ Total Note: Abnormal and Risk items
Juniper Crescent apportioned Private 23,284 £2,818 £2,530,732 £68,135,023Shared Ownership/ Intermediate Rent 3,316 £2,768 £360,448 £9,538,541Affordable Reprovision 11,839 £2,568 £1,286,786 £31,684,488Additional Affordable 4,247 £2,568 £461,601 £11,365,993
Sub Total 42,686 £120,724,045
Gilbeys YardPrivate 6,001 £2,808 £709,595 £17,559,197Shared Ownership/ Intermediate Rent 3,180 £2,758 £375,968 £9,144,485Affordable Reprovision 7,365 £2,558 £870,789 £19,706,834Additional Affordable 716 £2,558 £84,664 £1,916,043
Sub Total 17,262 £48,326,558
Total 59,948 £169,050,603
Commercial
Juniper Crescent 259 £1,361 £126 £353,133
Gilbeys Yard 272 £1,361 £126 £369,668
Total including commercial 60,478 £169,773,404
B Abnormal & Risk Items (Included Above)
Main Summary Qu Unit Rate £ at current day
rates Juniper CrescentDemolition 1 item £350,000 £350,000Additional Reduced level dig 5,000 m3 £140 £700,000Retaining Wall 100 m £10,000 £1,000,000Acoustic Treatments 4,338 m2 £100 £433,816Public realm 1,500 m2 £150 £225,000Plant room 239 m2 £1,200 £287,088Podium parking 1,659 m2 £850 £1,410,413Community centre - m2 £3,450 £0Archaeology 1 item £10,000 £10,000Asbestos - allowance 1 item £18,000 £18,000Service Diversions - allowance 1 item £18,000 £18,000Contamination - allowance 1 item £187,250 £187,250
Sub Total £4,639,567
Gilbeys YardDemolition 1 item £250,000 £250,000Canal wall works 84 m £2,500 £210,000Enhanced elevations 1,000 m2 £500 £500,000Archaeology 1 item £5,000 £5,000Podium parking 1,014 m2 £850 £861,487Plant room 115 m2 £1,200 £138,029Asbestos - allowance 1 item £7,000 £7,000Service Diversions - allowance 1 item £7,000 £7,000Contamination - allowance 1 item £62,500 £62,500
Sub Total £2,041,016
Total including commercial £6,680,582
2 NOTES AND CLARIFICATIONS
2.1.1 The estimate is based on the details provided in PRP document Full Redevelopment Sc. 3 and schedule of units.
2.1.22.1.3 Assumes CHP to all apartments
2.1.4 Allowance for fully fitted out Community Centre including fixed and loose Furniture Fittings and Equipment
2.1.5 We have allowed for repair works to the Canal wall only. Full replacement would be an additional £630,000.
2.1.6 The affordable rented units have been priced at OHG's Social Rented specification.
2.1.7 Full sprinklers to all blocks including commercial other than Block E.
2.1.8 Sub divided commercial space to shell as the OHG brief.
2.2 Our estimate excludes the following:2.2.1 Professional and legal fees.2.2.22.2.32.2.42.2.52.2.6
2.2.7
2.2.82.2.9
2.2.102.2.11 Marketing budget or any purpose build show flats or marketing suite
2.2.12
2.2.13 Flood prevention
2.2.14
2.2.15 Removal of asbestos above the £25,000 allowance
2.2.16 Contaminated land remediation above the £250,000 allowance, noting £700,000 included for additional reduced level dig.
We have prepared this Preliminary Estimate for the proposed residential development in line with the area schedule Camden Goods Yard (option 6), Full Redevelopment Sc.3.
Cost are current as 2Q 2018
Full Redevelopment Sc.3
Party Wall matters & Rights of light issues.
Planning / Building Regulation fees.Archaeological and cost associated above the £15,000 allowance.
Relocating habitat of any protected wildlife on or off site and any surveys (Slow worms, etc.)
Finance charges.
VAT.
Local & Mayoral CIL payments, Cross rail levy, Section 278, Section 106 contributions and other contributions.
Carbon Reduction Levy.
Service diversion above the £25,000 allowance
Surveys and investigations.Removal of any Japanese Knotweed or other invasive weeds.
2
Camden Goods Yard
Preliminary Estimate
3 Summary of estimate
3.1 Private Apartment - Typical apartment cost to provide Rate
Ref Item Qty Unit Rate Total £ Comment
0 Facilitating works 5,350 m2 10 53,500 Minimal site preparation works
1 Substructure 5,350 m2 190 1,016,500 Foundations and ground floor slab
2 Superstructure Frame , external walls, windows, stairs, doors
2.1 Frame 5,350 m2 250 1,337,500
2.2 Upper Floors 5,350 m2 80 428,000
2.3 Roof 5,350 m2 170 909,500
2.4 Stairs 5,350 m2 15 80,250
2.5 External Walls 5,350 m2 220 1,177,000
2.6 External Windows and Doors 5,350 m2 110 588,500
2.7 Internal Walls and Partitions 5,350 m2 90 481,500
3 Finishes Ceilings, wall and Floor coverings
3.1 Internal Doors 5,350 m2 60 321,000
3.2 Wall Finishes 5,350 m2 60 321,000
3.3 Floor Finishes 5,350 m2 80 428,000
3.4 Ceiling Finishes 5,350 m2 45 240,750
4 Fittings and Furnishings 5,350 m2 185 989,750 Kitchens, wardrobes, skirtings, window boards, etc
Allowance includes £6k for kitchen
5 Services 5,350 m2 395 2,113,250 Electrical, mechanical and plumbing; Assumes CHP
5.1 Incoming utilities 64 apart. 2,500 160,000
6 External Works 5,350 m2 55 294,250
7 Abnormal (list as appropriate)
7.1 Sprinklers to all Blocks other than E 5,350 m2 45 240,750
E Sub total 11,181,000
F Preliminaries and management costs 14% 1,565,340 site set up, management, scaffold, site labour, etc
G Main Contractors design fees & any pre-
construction fees
6%670,860
H Main Contractors overheads and profit 7% 939,204 assumes a design and build form of contract
I Contingency/Risk 5% 717,820.20
J Construction cost inflation for the pre-
construction and construction periods
0%excluded
K Total Estimated Construction Cost 15,074,224
L Cost data
Rate /m2 2,818
Camden Goods Yard
4. INFORMATION USED IN PREPARING THIS REPORT
Ref Number Rev Title
AA6569_Existing Building Measurements_DRAFT
AA6596_CGY_Draft Design Info
AA6596_SK209-Full Redevelopment Sc.3 L00
AA6596_SK210-Full Redevelopment Sc.3 L00
AA6596_SK211-Full Redevelopment Sc.3 L00
AA6596_Options Appraisal Schedules_170920
Preliminary Estimate
4
Camden Goods Yard
5. BENCHMARK DATA Costs updated to 2nd quarter 2018
Private Rate
£/m2 GIA
GML Phase 2b £2,745 West London regeneration scheme
Wharf Road £2,862 Islington canal side scheme
South Kilburn £2,621 Large regeneration scheme
London Road £2,549 West London scheme
Preliminary Estimate
5
Preliminary Estimate
Camden Goods Yard (Full Redevelopment Sc.4)
Dated: 26/03/2018Revision 0
Prepared for :
One Housing Group
Prepared by : Teik Khor
Approved by : Tim Young
Camden Goods Yard
Preliminary Estimate
CONTENTS
1 INTRODUCTION & EXECUTIVE SUMMARY
2 NOTES AND CLARIFICATIONS
3 SUMMARY OF ESTIMATE
4 BENCHMARK DATA
5 INFORMATION USED IN PREPARING THIS REPORT
6 REVISION LOG
1 INTRODUCTION & EXECUTIVE SUMMARY
1.1
Total 642 units; 328 Private units, 86 Shared Ownership units, 228 Affordable Rented units
1.2 This Preliminary Estimate amounts to: £158,575,022 excluding commercial
A Summary Of Cost
Main Summary Total M2 £/m2 Abnormal £ £ Total Note: Abnormal and Risk items
Juniper Crescent apportioned
Private 19,485 £2,818 £3,540,092 £58,441,544
Shared Ownership/ Intermediate Rent 3,502 £2,768 £636,305 £10,329,312
Affordable Reprovision 11,839 £2,568 £2,150,915 £32,548,617
Additional Affordable 2,628 £2,568 £477,524 £7,226,107
Sub Total 37,455 £108,545,580
Gilbeys Yard
Private 3,783 £2,808 £491,414 £11,112,750
Shared Ownership/ Intermediate Rent 2,198 £2,758 £285,518 £6,346,749
Affordable Reprovision 7,365 £2,558 £956,666 £19,792,711
Additional Affordable 4,754 £2,558 £617,578 £12,777,233
Sub Total 18,100 £50,029,443
Total 55,555 £158,575,022
Commercial
Juniper Crescent 1,385 £1,361 £126 £1,884,567
Gilbeys Yard 218 £1,361 £126 £297,369
Total including commercial 57,158 £160,756,958
B Abnormal & Risk Items (Included Above)
Main Summary Qu Unit Rate £ at current day
rates Juniper Crescent
Demolition 1 item £350,000 £350,000
Additional Reduced level dig 5,000 m3 £140 £700,000
Retaining Wall 100 m £10,000 £1,000,000
Acoustic Treatments 4,338 m2 £100 £433,816
Public realm 1,500 m2 £150 £225,000
Plant room 508 m2 £1,200 £609,120
Podium parking 1,805 m2 £850 £1,533,825
Community centre 499 m2 £3,450 £1,719,825
Archaeology 1 item £10,000 £10,000
Asbestos - allowance 1 item £18,000 £18,000
Service Diversions - allowance 1 item £18,000 £18,000
Contamination - allowance 1 item £187,250 £187,250
Sub Total £6,804,836
Gilbeys Yard
Demolition 1 item £250,000 £250,000
Canal wall works 84 m £2,500 £210,000
Enhanced elevations 1,000 m2 £500 £500,000
Archaeology 1 item £5,000 £5,000
Podium parking 1,506 m2 £850 £1,279,675
Plant room - allowance 25 m2 £1,200 £30,000
Asbestos - allowance 1 item £7,000 £7,000
Service Diversions - allowance 1 item £7,000 £7,000
Contamination - allowance 1 item £62,500 £62,500
Sub Total £2,351,175
Total including commercial £9,156,011
2 NOTES AND CLARIFICATIONS
2.1.1 The estimate is based on the details provided in PRP document Full Redevelopment Sc. 4 and schedule of units.
2.1.2
2.1.3 Assumes CHP to all apartments
2.1.4 Allowance for fully fitted out Community Centre including fixed and loose Furniture Fittings and Equipment
2.1.5 We have allowed for repair works to the Canal wall only. Full replacement would be an additional £630,000.
2.1.6 The affordable rented units have been priced at OHG's Social Rented specification.
2.1.7 Full sprinklers to all blocks including commercial other than Block E.
2.1.8 Sub divided commercial space to shell as the OHG brief.
2.2 Our estimate excludes the following:
2.2.1 Professional and legal fees.
2.2.2
2.2.3
2.2.4
2.2.5
2.2.6
2.2.7
2.2.8
2.2.9
2.2.10
2.2.11 Marketing budget or any purpose build show flats or marketing suite
2.2.12
2.2.13 Flood prevention
2.2.14
2.2.15 Removal of asbestos above the £25,000 allowance
2.2.16 Contaminated land remediation above the £250,000 allowance, noting £700,000
included for additional reduced level dig.
We have prepared this Preliminary Estimate for the proposed residential development in line with the area schedule Camden Goods Yard (option 6), Full Redevelopment Sc.4.
Cost are current as 1Q 2018
Full Redevelopment Sc.4
Party Wall matters & Rights of light issues.
Planning / Building Regulation fees.
Archaeological and cost associated above the £15,000 allowance.
Relocating habitat of any protected wildlife on or off site and any surveys (Slow worms, etc.)
Finance charges.
VAT.
Local & Mayoral CIL payments, Cross rail levy, Section 278, Section 106 contributions and other contributions.
Carbon Reduction Levy.
Service diversion above the £25,000 allowance
Surveys and investigations.
Removal of any Japanese Knotweed or other invasive weeds.
2
Camden Goods Yard
Preliminary Estimate
3 Summary of estimate
3.1 Private Apartment - Typical apartment cost to provide Rate
Ref Item Qty Unit Rate Total £ Comment
0 Facilitating works 5,350 m2 10 53,500 Minimal site preparation works
1 Substructure 5,350 m2 190 1,016,500 Foundations and ground floor slab
2 Superstructure Frame , external walls, windows, stairs, doors
2.1 Frame 5,350 m2 250 1,337,500
2.2 Upper Floors 5,350 m2 80 428,000
2.3 Roof 5,350 m2 170 909,500
2.4 Stairs 5,350 m2 15 80,250
2.5 External Walls 5,350 m2 220 1,177,000
2.6 External Windows and Doors 5,350 m2 110 588,500
2.7 Internal Walls and Partitions 5,350 m2 90 481,500
3 Finishes Ceilings, wall and Floor coverings
3.1 Internal Doors 5,350 m2 60 321,000
3.2 Wall Finishes 5,350 m2 60 321,000
3.3 Floor Finishes 5,350 m2 80 428,000
3.4 Ceiling Finishes 5,350 m2 45 240,750
4 Fittings and Furnishings 5,350 m2 185 989,750 Kitchens, wardrobes, skirtings, window boards, etc
Allowance includes £6k for kitchen
5 Services 5,350 m2 395 2,113,250 Electrical, mechanical and plumbing; Assumes CHP
5.1 Incoming utilities 64 apart. 2,500 160,000
6 External Works 5,350 m2 55 294,250
7 Abnormal (list as appropriate)
7.1 Sprinklers to all Blocks other than E 5,350 m2 45 240,750
E Sub total 11,181,000
F Preliminaries and management costs 14% 1,565,340 site set up, management, scaffold, site labour, etc
G Main Contractors design fees & any pre-
construction fees
6%670,860
H Main Contractors overheads and profit 7% 939,204 assumes a design and build form of contract
I Contingency/Risk 5% 717,820.20
J Construction cost inflation for the pre-
construction and construction periods
0%excluded
K Total Estimated Construction Cost 15,074,224
Rate /m2 2,818
Camden Goods Yard
4. INFORMATION USED IN PREPARING THIS REPORT
Ref Number Rev Title
PDP's drawings no :
Full Redevelopment Sc 4 - Level -01 SK308
Full Redevelopment Sc 4 - Level 00 SK309
Full Redevelopment Sc 4 - Level 01 SK310
Full Redevelopment Sc 4 - Roof Level SK311
Full Redevelopment Sc 4 - Heights Plan SK312
Full Redevelopment Sc 4 - Illustrative Masterplan SK313
Preliminary Estimate
4
Camden Goods Yard
5. BENCHMARK DATA Costs updated to 1st quarter 2018
Private Rate
£/m2 GIA
GML Phase 2b £2,745 West London regeneration scheme
Wharf Road £2,862 Islington canal side scheme
South Kilburn £2,621 Large regeneration scheme
London Road £2,549 West London scheme
Preliminary Estimate
5
Preliminary Estimate
Camden Goods Yard (Full Redevelopment Sc.5)
Dated: 27/03/2018Revision 0
Prepared for :
One Housing Group
Prepared by : Teik Khor
Approved by : Tim Young
Camden Goods Yard
Preliminary Estimate
CONTENTS
1 INTRODUCTION & EXECUTIVE SUMMARY
2 NOTES AND CLARIFICATIONS
3 SUMMARY OF ESTIMATE
4 BENCHMARK DATA
5 INFORMATION USED IN PREPARING THIS REPORT
6 REVISION LOG
1 INTRODUCTION & EXECUTIVE SUMMARY
1.1
Total 667 units; 349 Private units, 86 Shared Ownership units, 232 Affordable Rented units
1.2 This Preliminary Estimate amounts to: £164,014,908 excluding commercial
A Summary Of Cost
Main Summary Total M2 £/m2 Abnormal £ £ Total Note: Abnormal and Risk items
Juniper Crescent apportioned
Private 20,679 £2,818 £3,607,677 £61,872,653
Shared Ownership/ Intermediate Rent 3,502 £2,768 £611,019 £10,304,026
Affordable Reprovision 11,839 £2,568 £2,065,440 £32,463,142
Additional Affordable 2,985 £2,568 £520,700 £8,183,995
Sub Total 39,005 £112,823,816
Gilbeys Yard
Private 4,197 £2,808 £532,976 £12,315,962
Shared Ownership/ Intermediate Rent 2,198 £2,758 £279,137 £6,340,368
Affordable Reprovision 7,365 £2,558 £935,286 £19,771,331
Additional Affordable 4,754 £2,558 £603,776 £12,763,431
Sub Total 18,514 £51,191,092
Total 57,518 £164,014,908
Commercial
Juniper Crescent 1,385 £1,361 £126 £1,884,567
Gilbeys Yard 218 £1,361 £126 £297,369
Total including commercial 59,121 £166,196,844
B Abnormal & Risk Items (Included Above)
Main Summary Qu Unit Rate £ at current day
rates Juniper Crescent
Demolition 1 item £350,000 £350,000
Additional Reduced level dig 5,000 m3 £140 £700,000
Retaining Wall 100 m £10,000 £1,000,000
Acoustic Treatments 4,338 m2 £100 £433,816
Public realm 1,500 m2 £150 £225,000
Plant room 508 m2 £1,200 £609,120
Podium parking 1,805 m2 £850 £1,533,825
Community centre 499 m2 £3,450 £1,719,825
Archaeology 1 item £10,000 £10,000
Asbestos - allowance 1 item £18,000 £18,000
Service Diversions - allowance 1 item £18,000 £18,000
Contamination - allowance 1 item £187,250 £187,250
Sub Total £6,804,836
Gilbeys Yard
Demolition 1 item £250,000 £250,000
Canal wall works 84 m £2,500 £210,000
Enhanced elevations 1,000 m2 £500 £500,000
Archaeology 1 item £5,000 £5,000
Podium parking 1,506 m2 £850 £1,279,675
Plant room - allowance 25 m2 £1,200 £30,000
Asbestos - allowance 1 item £7,000 £7,000
Service Diversions - allowance 1 item £7,000 £7,000
Contamination - allowance 1 item £62,500 £62,500
Sub Total £2,351,175
Total including commercial £9,156,011
2 NOTES AND CLARIFICATIONS
2.1.1 The estimate is based on the details provided in PRP document Full Redevelopment Sc. 5 and schedule of units.
2.1.2
2.1.3 Assumes CHP to all apartments
2.1.4 Allowance for fully fitted out Community Centre including fixed and loose Furniture Fittings and Equipment
2.1.5 We have allowed for repair works to the Canal wall only. Full replacement would be an additional £630,000.
2.1.6 The affordable rented units have been priced at OHG's Social Rented specification.
2.1.7 Full sprinklers to all blocks including commercial other than Block E.
2.1.8 Sub divided commercial space to shell as the OHG brief.
2.2 Our estimate excludes the following:
2.2.1 Professional and legal fees.
2.2.2
2.2.3
2.2.4
2.2.5
2.2.6
2.2.7
2.2.8
2.2.9
2.2.10
2.2.11 Marketing budget or any purpose build show flats or marketing suite
2.2.12
2.2.13 Flood prevention
2.2.14
2.2.15 Removal of asbestos above the £25,000 allowance
2.2.16 Contaminated land remediation above the £250,000 allowance, noting £700,000 included for additional reduced level dig.
Relocating habitat of any protected wildlife on or off site and any surveys (Slow worms, etc.)
Finance charges.
VAT.
Local & Mayoral CIL payments, Cross rail levy, Section 278, Section 106 contributions and other contributions.
Carbon Reduction Levy.
Service diversion above the £25,000 allowance
Surveys and investigations.
Removal of any Japanese Knotweed or other invasive weeds.
We have prepared this Preliminary Estimate for the proposed residential development in line with the area schedule Camden Goods Yard (option 6), Full Redevelopment Sc.5.
Cost are current as 2Q 2018
Full Redevelopment Sc.5
Party Wall matters & Rights of light issues.
Planning / Building Regulation fees.
Archaeological and cost associated above the £15,000 allowance.
2
Camden Goods Yard
Preliminary Estimate
3 Summary of estimate
3.1 Private Apartment - Typical apartment cost to provide Rate
Ref Item Qty Unit Rate Total £ Comment
0 Facilitating works 5,350 m2 10 53,500 Minimal site preparation works
1 Substructure 5,350 m2 190 1,016,500 Foundations and ground floor slab
2 Superstructure Frame , external walls, windows, stairs, doors
2.1 Frame 5,350 m2 250 1,337,500
2.2 Upper Floors 5,350 m2 80 428,000
2.3 Roof 5,350 m2 170 909,500
2.4 Stairs 5,350 m2 15 80,250
2.5 External Walls 5,350 m2 220 1,177,000
2.6 External Windows and Doors 5,350 m2 110 588,500
2.7 Internal Walls and Partitions 5,350 m2 90 481,500
3 Finishes Ceilings, wall and Floor coverings
3.1 Internal Doors 5,350 m2 60 321,000
3.2 Wall Finishes 5,350 m2 60 321,000
3.3 Floor Finishes 5,350 m2 80 428,000
3.4 Ceiling Finishes 5,350 m2 45 240,750
4 Fittings and Furnishings 5,350 m2 185 989,750 Kitchens, wardrobes, skirtings, window boards, etc
Allowance includes £6k for kitchen
5 Services 5,350 m2 395 2,113,250 Electrical, mechanical and plumbing; Assumes CHP
5.1 Incoming utilities 64 apart. 2,500 160,000
6 External Works 5,350 m2 55 294,250
7 Abnormal (list as appropriate)
7.1 Sprinklers to all Blocks other than E 5,350 m2 45 240,750
E Sub total 11,181,000
F Preliminaries and management costs 14% 1,565,340 site set up, management, scaffold, site labour, etc
G Main Contractors design fees & any pre-
construction fees
6%670,860
H Main Contractors overheads and profit 7% 939,204 assumes a design and build form of contract
I Contingency/Risk 5% 717,820.20
J Construction cost inflation for the pre-
construction and construction periods
0%excluded
K Total Estimated Construction Cost 15,074,224
Rate /m2 2,818
Camden Goods Yard
4. INFORMATION USED IN PREPARING THIS REPORT
Ref Number Rev Title
PDP's drawings no :
Full Redevelopment Sc 5 - Level -01 SK408
Full Redevelopment Sc 5 - Level 00 SK409
Full Redevelopment Sc 5 - Level 01 SK410
Full Redevelopment Sc 5 - Roof Level SK411
Full Redevelopment Sc 5 - Heights Plan SK412
Full Redevelopment Sc 5 - Illustrative Masterplan SK413
Preliminary Estimate
4
Camden Goods Yard
5. BENCHMARK DATA Costs updated to 2nd quarter 2018
Private Rate
£/m2 GIA
GML Phase 2b £2,745 West London regeneration scheme
Wharf Road £2,862 Islington canal side scheme
South Kilburn £2,621 Large regeneration scheme
London Road £2,549 West London scheme
Preliminary Estimate
5