RFq 2015-8027; Generator Services
ATTACHMENT A
Contractor’s Fee Submission Form
PARTS/SUPPLIES AND MATERIALS
Description Percentage added to Contractor’s wholesale cost
Supplies and Parts __________ %
Equipment __________ %
“On Shelf” Products __________ %
AMP Address
Manufac-
turer Model Spec
Serial/
Accessories
TransferSwitch
Manufacturer Model Spec
Quote forMaintenan
for one yea
80
Trailer Mounted/Warehouse1088 W Liberty Kohler 50ROZJ 189303 318129 - - - $_______
211Beechwood330 Forest Ave Kohler 50ROZJ81 189303 318131 Kohler K-168341-225 K040536 $_______
211Maple Towers601 Maple Ave Kohler 200ROZD81 132409 338720 Kohler K-168341-260 L.S. A1733 $_______
212Riverview House2538 Hackberry St Kohler 50ROZJ81 189303 318130 Kohler K-168341-150 FA95343-2 $_______
212San Marco1601 Madison Road Kohler 80ROZJ 189519 338478 Kohler K-164341-0150 K50962 $_______
213Park Eden2610 Park Ave Kohler 50ROZJ71 189303 318211 Kohler K-166341-150 K43178 $_______
213President784 Greenwood Ave Kohler 80ROZJ 189546 396057 Kohler K-564341-0260 K78698 $_______
213 Redding Apts3700 Reading Rd Kohler 100ROZJ81 189629 385131 Kohler K-168341-400 K71789 $_______
215Stanley Row 'A'1609 Linn Kohler 125ROZJ81 189708 295954 ASCO E940360047XC 36645-3001 $_______
215Stanley Row 'B'-11609 Linn Kohler 180ROZJ81 189928 338415 Kohler K-168341-260 K50680 $_______
215 Stanley Row 'B' -2 Onan 60DGCV 90379M 1970647699 Onan 07225 H970646914 $_______
216Pinecrest3951 W Eighth St Kohler 50ROZJ81 189303 318132 Kohler K-168341-150 K422122 $_______
218
Marquette/EnglishWoods1999 Sutter Ave Generac
9A10245-Sor 32858-12638 125KW AD201267SNA
GeneracASCO
90A04245-WE940326097-C
99463015672277480FP89241 $_______
AH
Baldwin Grove1111 SpringfieldPike Generac SD0050G363 50KW 2094845 - SD0050G363 - $_______
AH
Reserve on S.Martin7363 Main Street Kohler 230REOZJE
GM66100-GA4 SGM322DJZ Kohler
KSP-DCVA-0400S SGM3228LL $_______
Total Annual Cost (firm, fixed price inclusive of all costs) for two maintenance services per year: $_______Do you offer 24-hour on call service to respond to emergencies? _____
Service rates: $__________/hour between 8 am and 5 pm Monday through Friday (firm, fixed rate inclusive of all costs)$__________/hour for after hours or holidays
8/17/2019 361341781
2/3
RFq 2015-8027; Generator Services
DISCOUNT OFFERED FOR EARLY PAYMENT: ______ % if invoice paid within ____ days of
properly submitted invoice as stated in the RFq.
Performance Standards.For each time the Contractor is late to arrive for a scheduled service, the Contractor’s fee may be reduced
10%.
The Property Manager or Maintenance Supervisor may waive the fee reduction at their discretion after
discussing extenuating circumstances with the Contractor. Such waiver shall be in writing at the time of
the service.
8/17/2019 361341781
3/3
RFq 2015-8027; Generator Services
PROPOSER’S STATEMENT
The undersigned proposer hereby states that by completing and submitting this Form and all other
documents within this submittal, he/she is verifying that all information provided herein is, to the best of
his/her knowledge, true and accurate, and that if the Authority discovers that any information enteredherein to be false, such shall entitle the Authority to not consider or make award or to cancel any awardwith the undersigned party. Further, by completing and submitting the response, the undersigned is
thereby agreeing to abide by all terms and conditions pertaining to this RFq as issued by the Authority,
either in hard copy or on the noted Internet System. Upon issuance of award to proposer, CMHA isaccepting Contractor’s offer contained in the submittal and this Fee Submission. No other contractual
documents will be necessary or accepted unless specifically expressed in the notification of contract
commencement. The Contract commences upon CMHA’s issuance of a Notice of ContractCommencement, which may or may not be in the form of a copy of the Contract Documents, unless said
notice expressly states otherwise, in those instances, Contract Commencement occurs in accordance withthe notification. Pursuant to all RFq Documents including attachments, this Fee Submission Form, and
pursuant to all Documents submitted, the undersigned proposes to supply the Authority with theservices described herein for the fee(s) submitted pertaining to this RFq.
Date: __________________, 2015
Company: _________________________________________________________
Address: __________________________________________________________
City, State, Zip _____________________________________________________
By: ______________________________________________________________
(Signature of Offerer)
By: _____________________________ Title: _________________________
(Print Name)
Fed Tax ID: ___________________________