01-10-12 347861 - MANUAL CHIEF42 CB22 30< ROOF INSTALLATION MANUAL FOR CB22 GRAIN STORAGE BIN WARNING! READ THIS MANUAL THOROUGHLY BEFORE INSTALLING OR OPERATING GRAIN BIN. KEEP MANUAL LOCATED FOR QUICK ACCESS AND REFERENCE. CHIEF INDUSTRIES AGRI/INDUSTRIAL DIVISION POST OFFICE BOX 848 4400 EAST 39 TH ST. KEARNEY, NEBRASKA 68848 Phone (800) 359-8833 In Nebraska Call (308) 237-3186 FAX (308) 237-2650 www.chiefind.com

347861 MANUAL CB22 30DG J RIB AGRI.pdf

Embed Size (px)

Citation preview

Page 1: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

01-10-12 347861 - MANUAL CHIEF42 CB22 30< ROOF

INSTALLATION MANUAL

FOR

CB22 GRAIN STORAGE BIN

WARNING!

READ THIS MANUAL THOROUGHLY BEFORE INSTALLING OR OPERATING GRAIN BIN.

KEEP MANUAL LOCATED FOR QUICK ACCESS AND REFERENCE.

CHIEF INDUSTRIES

AGRI/INDUSTRIAL DIVISION

POST OFFICE BOX 848

4400 EAST 39TH

ST.

KEARNEY, NEBRASKA 68848

Phone (800) 359-8833

In Nebraska Call (308) 237-3186

FAX (308) 237-2650

www.chiefind.com

Page 2: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

Page 1 MANUAL CHIEF42 CB22

Manual Revisions

Date: Revision Made

10-17-11 Updated sidewall caulking details on laminated sheets.

01-10-12 Updated Sidewall and Stiffener Gauge Charts

Page 3: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

MANUAL CHIEF42 CB22 Page 2

Page 4: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

Page 3 MANUAL CHIEF42 CB22

Page 5: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

MANUAL CHIEF42 CB22 Page 4

Page 6: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

Page 5 MANUAL CHIEF42 CB22

Grain Bin Specifications

Page 7: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

MANUAL CHIEF42 CB22 Page 6

Page 8: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

Page 7 MANUAL CHIEF42 CB22

Page 9: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

MANUAL CHIEF42 CB22 Page 8

Page 10: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

Page 9 MANUAL CHIEF42 CB22

Page 11: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

MANUAL CHIEF42 CB22 Page 10

Page 12: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

Page 11 MANUAL CHIEF42 CB22

Page 13: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

MANUAL CHIEF42 CB22 Page 12

Page 14: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

Page 13 MANUAL CHIEF42 CB22

Page 15: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

MANUAL CHIEF42 CB22 Page 14

Bin Erection

Chief Industries, Inc. will not assume any responsibility for parts damaged due to faulty or

improper erection procedures.

Chief Industries, Inc. recommends that Bin Jacks be used for all bins taller than 8 rings

and all bins larger than 30’ in diameter.

WARNING:

The allowable lifting capacity of the BIN JACKS must never be exceeded. Always check Bin

weight to insure a safe and trouble free erection.

Grain Bin Color Codes

Chief Grain Bins are color coded based on bin diameter. Components such as Roof Rafters,

Wind Rings, and Base Angle will be marked with the following Color Codes to help identify

them.

Bin Size Color Code Bin Size Color Code

#12 Yellow/Black #22 Blue

#13 Green/Black #24 Brown

#14 Orange/Black #26 Yellow

#16 Red #30 Green

#18 Black #34 Orange

#20 Pink

A. Suggested Erection Equipment

Impact Wrench & Sockets Wrenches Crescent Wrench

Vise Grips Alignment Punches Rubber Mallet

Level Drill and Drill Bits Extension Cords

Ladders Bin Jacks Screw Gun

7/16” bin bolts use 5/8” on the head of the bolt and 11/16” on the nut.

5/16” bin bolts use 1/2” on the head of the bolt and nut.

1/2” bolts in the roof structure use 3/4” on the head of the bolt and nut.

Bolt Buckets are Color Coded with a Dot as Shown Below.

Bolt Size Color Code

5/16” Blue

7/16” Red

1/2” Green

5/8” Yellow

Page 16: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

Page 15 MANUAL CHIEF42 CB22

B. Checking Shipment

Check your shipment at the time of pickup and delivery against the packing list furnished

with the shipment. If a shortage exists or if any damaged material is evident, note such

shortage or damage on the freight bill before you sign for the shipment.

Claims of shortages will not be honored after thirty days from receipt of shipment.

Parts that are short or damaged are the responsibility of the delivering carrier, not the

manufacturer or dealer.

It is advisable to reorder damaged or missing parts immediately so that there will be no

delay in erecting the bin. After receiving the invoice for the reordered material, file a

claim with the delivering carrier at once.

The galvanized panels leave our plant in prime condition; store off the floor in a heated

room if possible. If stored outside, place panels down, off the ground. Upon arrival of

shipment if you are not certain whether or not moisture is present, store panels on edge or

on end allowing 1/4“ air space between panels until dry. Exposure to trapped moisture

can cause white rust, which will void the warranty.

C. Stop and Study

Before beginning erection of the bin, take the time to thoroughly study the construction

methods in this manual. It will save you both time and money.

Important: The peak load capacities listed under Auxiliary Roof Loads must not be exceeded. If your

application will exceed the listed values, contact Chief Industries for recommendations.

Chief Industries makes no warranty concerning parts, accessories or equipment not

manufactured by Chief Industries.

D. Site Selection

Choose a site that has good drainage away from the bin so that water will not stand around

the bin. The soil should be firm and preferably without fill. If fill is required, water and

compact the fill material to avoid uneven settlement. A field investigation of the soil

bearing conditions is recommended especially for larger grain bins where the foundation

loads and floor pressure become large. A licensed engineering firm should be employed to

take soil borings, determine the maximum allowable soil pressure and design the bin

foundations and floor slab accordingly.

Page 17: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

MANUAL CHIEF42 CB22 Page 16

E. Bin Jack Erection

Position the structure you provided to hold the Inner Ring at its approximate height,

centering the Inner Ring on the center of the Bin.

Use at least one Bin Jack per Sidewall Sheet. (For example, on the #18 Bin, use 18 Bin

Jacks, etc.)

The application of one bin jack per sidewall sheet will minimize sidewall distortion during

erection. Failure to use the proper quantity of jacks may result in inward-outward lay of the bin

sidewall or even permanent distortion of the bin sidewall sheets.

The recommendation of at least one Bin Jack per sidewall sheet is based on keeping the bin

round, refer to the warning below, and make sure the lifting capacity of the jack is

sufficient for the weight of the bin. Note that all jacks may not shift equally, Therefore

make sure the lifting capacity rating by the jack manufacturing is met.

WARNING:

If it is necessary to leave the construction site for any length of time before the Bin is

completed and anchored to the concrete, the Bin must be securely tied down.

Page 18: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

Page 17 MANUAL CHIEF42 CB22

F. Assembling Sidewall Sheets

All bolts are washer head bolts with sealing washers S.A.E. Grade 8, with whiz flange

nuts. Grade 8 bolts are marked with six radial lines on the bolt head as shown. If these

descriptions do not correspond with the bolts shipped with the bin, please contact the

customer service department immediately. Do not substitute any other Bolts.

Bin bolts must be TIGHT. The following table contains recommended minimum and

maximum torque values.

BOLT DIA. TORQUE FT. LBS

(INCHES) MINIMUM MAXIMUM

5/16" 22 28

7/16" 60 75

Tighten the bin bolts from the inside of the bin (nut end of the bolt) to eliminate “spin

off” of the sealing washer.

USE ONLY THOSE BOLTS SUPPLIED BY CHIEF INDUSTRIES.

THE SUBSTITUTION OF BOLTS FROM OTHER SOURCES IS NOT PERMITTED.

NOTE: Proper bolting sequence MUST be followed at all times.

Page 19: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

MANUAL CHIEF42 CB22 Page 18

The Titan Sign Sheet must be installed in the second ring as shown in figures below.

(Shown installed on a 2 stiffened bin)

(Shown installed on a 3 stiffened bin)

Install the Titan Sign Sheet by field drilling (6) six ½” holes in the Titan Sign Sheet and

stiffeners as shown above. Bolt the Titan Sign Sheet to the stiffeners with (6) six 7/16” bolts.

Page 20: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

Page 19 MANUAL CHIEF42 CB22

Assembling top ring

Locate the proper gauge of sidewall sheets needed for the top ring from the gauge chart. Lap and

caulk sheets as shown below. Locate top stiffeners and install on top ring.

Note: Top Sheets have special punching on the top of the sheet at the stiffener holes for the

rafter to attach to. Leave bolts out of top (4) stiffener holes until eave brackets are

attached.

Wipe off the outside ends of all the Sidewall Sheets to remove excess oil so that the Strip

Caulking will adhere to the metal. Place the Strip Caulking as near to the vertical inside edge of

sheet at every vertical seam.

On Bins 12 gauge or heavier a horizontal strip of caulking is needed on the inside at the center

bottom of the Sidewall sheet located on the hill near to the bottom holes. This strip of caulking

should fit where the endlap of the next ring Sidewall Sheets bolts up to this location.

Page 21: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

MANUAL CHIEF42 CB22 Page 20

G. Roof Panel Location

The rafters need to be bolted directly behind a top 2 ring stiffener, the roof panel rib will line up

directly above the rafter from the peak to the eave. (There is 1 Rafter and 4 roof panels per

sidewall sheet.) (Note: on 3 stiffened bins, rafters will be on 1 and 2 ring top stiffeners)

Page 22: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

Page 21 MANUAL CHIEF42 CB22

H. Crane and Jack Capacities

Crane Capacity:

The total roof dead load for each of the respective bin roof sizes is shown in the table below.

This weight includes the roof panels and all structural members (roof beams, compression rings,

bolts, ect.)

When determining the crane capacity necessary to erect the roof structure, the booming distance

must be considered. If the cane sizes available will not lift the roof structure (using one crane),

two cranes may be used, utilizing a spreader bar. The spreader bar must be adequately designed

to carry the entire roof dead weight.

Peak Heights

All peak heights listed below are to the bottom of the peak ring from the ground with (2) Titan

sidewall sheet rings installed. Deduct 42 1/2” from the peak heights when only one ring of

sidewall sheets are installed.

Model Peak Height

CB18 20’ - 8 7/8”

CB20 22’ – 6 5/16”

CB22 24’ – 3 3/4”

CB24 26’ – 1 1/8”

CB26 27’ – 10 9/16”

CB30 31’ – 5 7/16”

CB34 35’ – 0 5/16”

WARNING!! OVERLOADING CRANE CAPCITY CAN RESULT IN

SUBSTANCIAL PROPERTY DAMAGE OR SEVERE PERSONAL INJURY.

ALWAYS CHECK CRANE CAPACITY PRIOR TO LIFTING ROOF

STRUCUTRE

Page 23: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

MANUAL CHIEF42 CB22 Page 22

Sidewall Sheet and Stiffener Gauge Chart

Note: All Sidewall and Stiffener gauges in the charts below are for standard bins. If bins are

designed for High Load/Unload rates, concrete pits or Seismic Conditions, Contact Chief

Industries, Inc. for gauge chart needed.

Ring SWS Ring SWS Ring SWS

1 14 16 1 14 16 1 14 16

2 14 16 2 14 16 2 14 16

3 14 18 3 14 18 3 14 18

4 14 16 4 14 16 4 14 16

5 14 16 5 14 16 5 14 16

6 13 14 6 13 14 6 13 14

7 13 14 7 13 14 7 13 14

8 12 12 12 8 12 12 8 12 12

9 12 9 12 12 12 9 12 12

10 11 12 12 10 11 10 11 12 12

11 11 10 10 11 11

12 10 10 10

Ring SWS Ring SWS Ring SWS

1 14 16 1 14 16 1 14 16

2 14 16 2 14 16 2 14 16

3 14 18 3 14 18 3 14 18

4 14 16 4 14 16 4 14 16

5 14 16 5 14 16 5 14 16

6 13 14 6 13 14 6 13 14

7 13 14 7 13 14 7 13 14

8 12 12 8 12 12 8 12 12

9 12 12 9 12 12 9 12 12

10 11 12 10 11 12 10 11 12

11 11 10 10 11 11 10 11 11 10

12 10 12 10 10 10 12 10 10

13 10 8 8 13 10 13 10 8 8

14 10 8 8 14 10

15 9 8 8

Ring SWS Ring SWS Ring SWS

1 14 16 1 14 16 1 14 16

2 14 16 2 14 16 2 14 16

3 14 18 3 14 18 3 14 18

4 14 16 4 14 16 4 14 16

5 14 16 5 14 16 5 14 16

6 13 14 6 13 14 6 13 14

7 13 14 7 13 14 7 13 14

8 12 12 8 12 12 8 12 12

9 12 12 9 12 12 9 12 12

10 11 10 10 11 10 10 11 10

11 11 10 11 11 10 11 11 10

12 10 10 12 10 10 12 10 10

13 10 8 13 10 8 13 10 8

14 10 8 8 14 10 8 14 10 8

15 9 15 9 8 8 15 9 1010

16 9 1010 1010 16 9 16 9 1010 1010

17 9 1010 1010 17 9

18 9 1010 1010

Stiffeners Stiffeners Stiffeners

Stiffeners per Sheet = 2 Stiffeners per Sheet = 2 Stiffeners per Sheet = 2

Stiffeners per Sheet = 2

Stiffeners

Stiffeners per Sheet = 2

CB22-16 SZA CB22-17 SZA CB22-18 SZA

Stiffeners per Sheet = 2

Stiffeners

Stiffeners per Sheet = 2

Stiffeners

CB22-13 SZA CB22-15 SZACB22-14 SZA

Stiffeners

CB22-12 SZA

Stiffeners

CB22-10 SZA

Stiffeners per Sheet = 2

CB22-11 SZA

Stiffeners per Sheet = 2

Stiffeners

Page 24: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

Page 23 MANUAL CHIEF42 CB22

Ring SWS Ring SWS Ring SWS

1 14 16 1 14 16 1 14 16

2 14 16 2 14 16 2 14 16

3 14 18 3 14 18 3 14 18

4 14 16 4 14 16 4 14 16

5 14 16 5 14 16 5 14 16

6 13 14 6 13 14 6 13 14

7 13 14 7 13 14 7 13 14

8 12 12 8 12 12 8 12 12

9 12 12 9 12 12 9 12 12

10 11 10 10 11 10 10 11 10

11 11 10 11 11 10 11 11 10

12 10 10 12 10 10 12 10 10

13 10 8 13 10 8 13 10 8

14 10 8 14 10 8 14 10 8

15 9 1010 15 9 1010 15 9 1010

16 9 1010 16 9 1010 16 9 1010

17 9 1010 1010 17 9 1010 17 9 1010

18 9 18 9 1010 1010 18 9 1010

19 9 1010 1010 19 9 19 9 1010 1010

20 8 88 88 20 8

21 8 88 88

Ring SWS Ring SWS Ring SWS

1 14 16 1 14 16 1 14 16

2 14 16 2 14 16 2 14 16

3 14 18 3 14 18 3 14 18

4 14 16 4 14 16 4 14 16

5 14 16 5 14 16 5 14 16

6 13 14 6 13 14 6 13 14

7 13 14 7 13 14 7 13 14

8 12 12 8 12 12 8 12 12

9 12 12 9 12 12 9 12 12

10 11 10 10 11 10 10 11 10

11 11 10 11 11 10 11 11 10

12 10 10 12 10 10 12 10 10

13 10 8 13 10 8 13 10 8

14 10 8 14 10 8 14 10 8

15 9 1010 15 9 1010 15 9 1010

16 9 1010 16 9 1010 16 9 1010

17 9 1010 17 9 1010 17 9 1010

18 9 1010 18 9 1010 18 9 1010

19 9 1010 19 9 1010 19 9 1010

20 8 88 88 20 8 88 20 8 88

21 8 21 8 88 88 21 8 88

22 8 88 88 22 8 22 8 88 88

23 8 88 88 23 8

24 1313 101010 101010

Stiffeners Stiffeners Stiffeners

CB22-22 SZA CB22-23 SZA CB22-24 SZA

Stiffeners per Sheet = 2 Stiffeners per Sheet = 2 Stiffeners per Sheet = 2

Stiffeners per Sheet = 2 Stiffeners per Sheet = 2 Stiffeners per Sheet = 2

Stiffeners Stiffeners Stiffeners

CB22-19 SZA CB22-20 SZA CB22-21 SZA

Page 25: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

MANUAL CHIEF42 CB22 Page 24

Ring SWS Ring SWS Ring SWS1 14 16 1 14 16 1 14 16

2 14 16 2 14 16 2 14 16

3 14 18 3 14 18 3 14 18

4 14 16 4 14 16 4 14 16

5 14 16 5 14 16 5 14 16

6 13 14 6 13 14 6 13 14

7 13 14 7 13 14 7 13 14

8 12 12 8 12 12 8 12 12

9 12 12 9 12 12 9 12 12

10 11 10 10 11 10 10 11 10

11 11 10 11 11 10 11 11 10

12 10 10 12 10 10 12 10 10

13 10 8 13 10 8 13 10 8

14 10 8 14 10 8 14 10 8

15 9 1010 15 9 1010 15 9 1010

16 9 1010 16 9 1010 16 9 1010

17 9 1010 17 9 1010 17 9 1010

18 9 1010 18 9 1010 18 9 1010

19 9 1010 19 9 1010 19 9 1010

20 8 88 20 8 88 20 8 88

21 8 88 21 8 88 21 8 88

22 8 88 22 8 88 22 8 88

23 8 101010 101010 23 8 101010 23 8 101010

24 1313 24 1313 101010 101010 24 1313 101010

25 1313 101010 101010 25 1313 25 1313 888 888

26 1212 888 888 26 1212

27 1212 888 888

Ring SWS1 14 16

2 14 16

3 14 18

4 14 18

5 14 18

6 13 16

7 13 16

8 12 14

9 12 14

10 11 12

11 11 12

12 10 12

13 10 10

14 10 10

15 9 10

16 9 8

17 9 8

18 9 8

19 9 1010

20 8 1010

21 8 1010

22 8 1010

23 8 1010

24 1313 1010

25 1313 88

26 1212 88 88

27 1212

28 1212 88 88

Stiffeners

Stiffeners per Sheet = 3

CB22-28 SZA

Stiffeners per Sheet = 2 Stiffeners per Sheet = 2

Stiffeners Stiffeners Stiffeners

CB22-25 SZA CB22-26 SZA CB22-27 SZA

Stiffeners per Sheet = 2

Page 26: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

Page 25 MANUAL CHIEF42 CB22

Sidewall Sheet Gauge Color

20 White

18 Orange

17 Light Blue

16 Green

14 Yellow

14 Transition Yellow/Black

13 Brown

12 Dark Blue

11 Pink

10 Black

9 Light Green

8 Red

Note: Sidewall Sheets for Top Ring are also

color coded with GOLD

Sidewall Erection

A. Sidewall Sheets and Stiffeners

NOTE: All sheets must be installed with color code right side down as shown below. Check the

edges of the sheet for traces of the shop color code. The shop color code is always located on the

bottom edge of the sheet. The color codes and their corresponding gauges are listed in the table

below.

Page 27: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

MANUAL CHIEF42 CB22 Page 26

Page 28: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

Page 27 MANUAL CHIEF42 CB22

NOTE: Proper Bolting Sequence Must Be Followed At All Times.

(1) Tighten bolts in top 2 rings and top stiffeners.

(2) Select sheets of the proper gauge for the 3rd ring of the bin. Select proper gauge and

length of stiffeners.

(3) Install stiffener splice plates, to both ends of stiffeners with (2) 7/16” x 1-1/4” Bin

Bolts and whiz flange nuts per splice before securing the stiffener to the bin. Note: On

top stiffeners, splice plate is only required on the bottom end of the stiffener.

(3) Wipe excess oil from ends of the sheets and apply caulking as shown below

(4) Loosely assemble 3rd

ring

(5) Loosely install stiffeners of the proper gauge to the exterior of the bin with 7/16” bin

bolts. Stiffener bolts are always placed with heads inside the bin. Using large

alignment punch, force stiffener up so that splices are tightly compressed. Tighten (4)

four bolts in 3rd

ring to keep stiffeners compressed. Loosely install the (2) 7/16” x 1-

1/4” bolts connecting the stiffener splices to the stiffener splice plate above.

Page 29: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

MANUAL CHIEF42 CB22 Page 28

Note:

Blocks may be used to place under the stiffener splices to compress the stiffener splices.

Note:

Install bolts on sidewall sheets seam that are in the center of stiffener holes before installing

next stiffener.

(6) Lower the bin on to the foundation. This will force the 2 ring stiffeners in 2nd

and 3rd

ring up to splices.

(7) Tighten stiffeners to sheets and stiffener splice to stiffener splice bolts.

(8) Tighten bolts in vertical seams in 3nd

ring.

(9) Tighten bolts in horizontal seams between 2nd

and 3rd

ring beginning at center of sheet

and working both ways.

(10) Add ladder sections as required (See separate Ladder Manual)

(11) Repeat steps 1 thru 10 to add 4th

ring and each additional ring. Proper bolting

sequence must be followed at all times to assure proper assembly.

NOTE: Use 7/16”x1 1/4” bin bolts at bottom sidelap of transition sheets. Use 5/16”x3/4” bin

bolts at the top sidelap at vertical seams of transition sheet.

NOTE: All bins have all 2 ring bottom stiffeners at the bottom, a 1 ring stiffener must be

placed at every other stiffener line in the 3rd

ring.

Page 30: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

Page 29 MANUAL CHIEF42 CB22

Page 31: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

MANUAL CHIEF42 CB22 Page 30

B. Laminated Sheet Installation

(1). All rings, which require laminated sheets (indicated in the sheet and stiffener charts)

must be installed with the endlaps lapped as shown in the endlap detail below.

(2). Select the proper sheet gauge for each ring of the bin as indicated in the stiffener and

gauge chart.

Laminated Sheet Endlap

(3). Lap the bin sheets so that the outside ring of sheets follow this sequence: The right end of

each sheet is always on the outside of the bin and the left end is always on the inside

(looking from the outside). Refer to the endlap detail.

NOTE: This sequence is the same as the single sheet sequence.

(4). Lap the inner ring of the bin sheet so that they follow the same lapping sequence as the

outside ring of sheets. Refer to the endlap detail for lapping sequence.

(5). Follow the bolt installation procedure for bin sheet endlaps and sidelaps.

(6). Install stiffeners as outlined.

Page 32: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

Page 31 MANUAL CHIEF42 CB22

Caulking Detail on Laminated Sheets:

Apply caulking on endlaps as shown and along top horizontal seam in-between laminated sheets.

Page 33: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

MANUAL CHIEF42 CB22 Page 32

Note: Add neoprene washer in-between stiffeners and sidewall sheets on top stiffener hole on all

laminated sheets.

Page 34: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

Page 33 MANUAL CHIEF42 CB22

C. Base Angle Detail

(1) Bolt the base angle to the bottom of the bottom sheet as shown, with either 5/16” x 3/4“ with

a 3/8” flat washer between the whiz nut and the base angle or 7/16” bin bolts.

(2) Install base angle shims under all anchor brackets as shown.

(3) Seal base angle to concrete, using plastic cement or tar sealant. (NOTE: Sealant not supplied

by Chief Industries, Inc.)

Page 35: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

MANUAL CHIEF42 CB22 Page 34

Install Sealing Washers in-between bottom stiffeners and wall sheet on bottom two holes on

stiffener as shown.

Page 36: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

Page 35 MANUAL CHIEF42 CB22

D. One Ring Door

1. Place expandable foam around edges of frames as shown below.

2. Bolt the inner and outer frame to the bin sidewall with 7/16” x 3” bin bolts, making sure to

only place bolts in the holes shown in the detail below. The top eyebrow on the outer frame is to

be placed behind the sheet above the door. The bottom eyebrow is to be placed on the outside of

the sheet below the door. Bolt the inner and outer frames together with (10) 7/16 x 2” bin bolts

with whiz flange nuts.

Page 37: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

MANUAL CHIEF42 CB22 Page 36

Page 38: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

Page 37 MANUAL CHIEF42 CB22

Page 39: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

MANUAL CHIEF42 CB22 Page 38

Page 40: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

Page 39 MANUAL CHIEF42 CB22

2 Ring Door Installation (optional)

Place expandable foam around edges of frames as shown below.

1. Bolt the inner and outer frame to the bin sidewall with 7/16” x 3” bin bolts, making sure

to only place bolts in the holes shown. Bolt the inner and outer frames together with (10)

7/16 x 2” bin bolts with whiz flange nuts.

Page 41: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

MANUAL CHIEF42 CB22 Page 40

Page 42: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

Page 41 MANUAL CHIEF42 CB22

Page 43: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

MANUAL CHIEF42 CB22 Page 42

Page 44: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

Page 43 MANUAL CHIEF42 CB22

Page 45: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

MANUAL CHIEF42 CB22 Page 44

IMPORTANT: All anchors

must be bearing firmly upon

concrete or shimmed to

develop full bearing contact

with concrete foundation

E. Heavy Bin Stiffener Anchor

(1) All bins will have ALL 2 ring bottom stiffeners. Stiffened bins may have two or three

Stiffeners per sidewall sheet depending upon bin size and height.

(2) Bolt anchor brackets to 2-ring bottom stiffeners. DO NOT fully tighten, only finger

tighten at this time.

(3) After the bottom ring is attached, lower the bin carefully, placing all anchor brackets

over the anchor bolts.

(4) When full weight of the bin is on the concrete, shim the anchors as necessary by

sliding shim plates between the concrete and anchor bracket. All anchors must be

bearing upon the concrete or shimmed so that full bearing of the anchor is developed.

NOTE: Anchors placed over aeration trenches must be supported from the bottom of the

trench.

After all anchors brackets are shimmed snuggly, place two square washers over the

anchor bolt and tighten.

Plastic cement or tar sealant should be applied from inside the bin to seal the bottom ring

to concrete. (NOTE: Sealant is not furnished by Chief Industries, INC.)

Page 46: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

Page 45 MANUAL CHIEF42 CB22

Bin Stiffener anchors allow up to 3 anchor bolts to be used at each anchor location. There are (2)

1” diameter and (1) 1-1/2” diameter holes in each Bin Stiffener Anchor.

There are several different combinations that Chief Industries Recommends to anchor the bin to

the foundation.

1. One 1-1/4” x 12” anchor bolt may be used in the 1-1/2” diameter hole, if this is done the

anchor bolt must be pre set in the concrete

2. Two 3/4” x 12” anchor bolts may be used in the two 1” diameter holes. If this is done, at least

one of the two anchor bolts must be pre set in the concrete the second may be drilled in. (It is

recommended that both anchor bolts are pre-set.)

If anchor bolts are not pre set as stated above, and the anchor bolt radius is not held, the bins

warranty may be nullified.

Larger anchor bolts or the use of all three anchor bolts may be required if seismic conditions or

high wind loads exist. Chief Industries should be consulted for proper anchor bolts to be used.

All anchor bolts must project a minimum of 2” above the concrete floor.

All anchor bolts, nuts and washers shall conform to ASTM A307 (specification for carbon steel

threaded standard fasteners) unless otherwise noted. Anchor bolts, nuts and washers are not

provided by Chief Industries, Inc.

IMPORTANT: If expansion type anchor bolts are used to replace damaged anchor

bolts, the bolt radius circle must be checked at replacement locations so that the bin is

round when anchored. Chief Industries recommends using wedge anchors that meet

10,000 LB Pull-Out and 7,500 LB shear criteria.

Anchor Bolt Typical Chord Typical Chord

Radius (2 Stiffened Bins) (3 Stiffened Bins)

CB12 18'-10 5/8" 4'-11 3/16" 3'-3 1/2"

CB13 20'-5 1/4" 4'-11 1/8" 3'-3 7/16"

CB14 21'-11 13/16" 4'-11 1/16" 3'-3 7/16"

CB16 25'-0 15/16" 4'-11" 3'-3 3/8"

CB18 28'-2 3/16" 4'-10 15/16" 3'-3 5/16"

CB20 31'-3 3/8" 4'-10 7/8" 3'-3 5/16"

CB22 34'-4 1/2" 4'-10 7/8" 3'-3 1/4"

CB24 37'-5 11/16" 4'-10 13/16" 3'-3 1/4"

CB26 40'-7" 4'-10 13/16" 3'-3 3/16"

CB30 46'-9 5/16" 4'-10 3/4" 3'-3 3/16"

CB34 52'-11 11/16" 4'-10 11/16" 3'-3 1/8"

Note:

All dimensions are to center anchor bolt.

All dimensions are for standard bins.

Page 47: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

MANUAL CHIEF42 CB22 Page 46

F. Transition Stiffeners

Aeration Trough Transition Stiffener Installations (for flush-floor aeration systems with two or

more fans)

(1) The formed concrete dimensions and the anchor bolt placement are important for the correct

installation of the transition stiffeners. When forming the concrete, the aeration troughs

should be located as specified in Chief’s aeration layout. The anchor bolt locations for the bin

need to be oriented to make sure that the number of anchors over the aeration trough is

minimized. When installing the anchor bolts, the bolt radius and bolt chord must be correct

and they must also be placed according to the details below.

IMPORTANT NOTE: Do NOT install the anchor bolts inside the aeration trench at this

time.

2 Stiffener/Sheet Bins 3 Stiffener/Sheet Bins

(2) When the bin is erected and located correctly (as illustrated above), insert the transition in the

aeration trough. Using the hole in the anchor bracket as a guide, drill a 3/4” hole through the

top of the transition. Slide the transition stiffener inside the transition and line it up with the

previously drilled hole. Loosely install the 5/8” x 1-1/2” A325 bolt. Rotate the transition

stiffener body so that it is centered under the bin wall anchor. See installation detail that

follows.

(3) The transition stiffener must be attached to the foundation with two (2) 5/8” x 6” expansion-

type anchor bolts. The holes for these anchor bolts should now be located. With an acetylene

torch, cut two holes in the bottom of the transition using the holes in the transition stiffener

base plate as guides. (This would mark the location of the anchor bolts in the concrete as

well.)

(4) Remove the transition stiffener and the transition.

Page 48: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

Page 47 MANUAL CHIEF42 CB22

Aeration Trough Transition Stiffener Installation Detail

(5) Locate the two anchor bolt locations (from cutting the holes in the bottom of the transition).

Set the transition stiffener over the locations to insure that the holes line up. Also, check to

insure that the transition stiffener is directly under and in line with the anchor. Make

adjustments if necessary. Drill the two holes for the 5/8” x 6” anchor bolts.

IMPORTANT NOTE: Do NOT install anchor bolts at this time.

(6) Enlarge the two holes in the bottom of the transition to 1” diameter.

(7) Reinstall the transition and slide the transition stiffener into position Loosely install the 5/8”

x 1-1/2” A325 bolt and rectangular washers at the anchor bracket location. The two 5/8” x 6”

expansion-type anchor bolts should now be installed and securely tightened the 5/8” bolts at

the anchor bracket. Caulking should be applied to seal the transition.

IMPORTANT NOTE: Transition stiffeners support the bin anchors. The transition must also

be supported inside the bin. See Chief’s aeration layout for supporting the transition.

Page 49: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

MANUAL CHIEF42 CB22 Page 48

G. Stiffener Upgrades for Goal Post (Optional)

When a goal post is being attached to bin, an extra layer of stiffeners are laminated over standard

stiffeners at goal post location from eave to base, as been is being erected.

Chief recommends that goal post be attached to the sidewall approx. 10’ below the eave of the

tank. (See separate goal post manual for attachment details)

Note: Listed below are the maximum loads that can be applied to upgraded stiffener columns.

16GA stiffener upgrade = 5,000 lbs. per column

14GA stiffener upgrade = 6,000 lbs. per column

2 stiffeners per sidewall

Page 50: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

Page 49 MANUAL CHIEF42 CB22

2 stiffeners per sidewall sheet

3 stiffeners per sidewall sheet

Page 51: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

MANUAL CHIEF42 CB22 Page 50

Page 52: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

Page 51 MANUAL CHIEF42 CB22

Page 53: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

MANUAL CHIEF42 CB22 Page 52

Page 54: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

Page 53 MANUAL CHIEF42 CB22

H. Installing Catwalk to Peak Rings.

Shown is a typical installation of a catwalk to the bin peak. Beams must be placed across peak

ring as shown to support catwalk.

Page 55: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

MANUAL CHIEF42 CB22 Page 54

Wind Rings

Wind Rings

Consult the Chief catalog for the quantity of wind rings required for your bin. The quantity of

wind rings depends on the size of the bin and the application of any accessories (such as a

sidedraw system). For quantities and placement of wind rings required when a Sidedraw System

is installed on the bin, refer to the charts in this manual. The wind rings will be attached to the

sidewall using one bracket per stiffener spaced 58-5/16” apart (38-7/8” on 3 stiffened bins). The

brackets are specially formed and pre-punched to bolt directly to the sidewall stiffener holes. The

wind ring segments will be joined together using a bolted coupler.

NOTE: All wind ring segments are 248” long, and may need field cut to keep couplers in

between brackets.

(1) Working from outside the bin, determine the proper location for installation of the first wind

ring.

(2) Bolt the first wind ring bracket to the sidewall stiffener holes as shown in Detail below using

(2) of the stiffener attachment bolts and nuts with bolt heads on the inside. (Note: Wind ring

brackets may be installed below the endcaps if desired to allow for clearance of ladders and

platforms.)

(3) Move right to the next stiffener and repeat step 2.

(4) When 4 wind ring brackets have been installed, slide the first ring segment through the four

brackets leaving approximately 29 inches of the segment projection past the last bracket.

(5) Repeat step 2 through 3 until four more brackets have been installed.

Page 56: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

Page 55 MANUAL CHIEF42 CB22

(6) Slide the next wind ring segment through the four brackets and butt it firmly against the

previous segment.

(7) Connect pipes together with pipe coupler.

(8) Repeat steps 5 thru 7 until all wind rings have been installed.

(9) Pipes will need to be field cut to length to all the installation of the last wind ring.

(10) Check to see that all bolts in the complete wind ring are tight

Note: Some wind ring pipes may need field cut to allow coupler to land in-between

stiffeners.

Page 57: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

MANUAL CHIEF42 CB22 Page 56

Titan Commercial Bins 5 thru 15 Rings Tall

Drawing is for illustrative purpose only. The quantity and location of wind rings required

depends on the application of any accessories (EX: sidedraw system). On Standard Bins place

wind rings as shown in figure above. Refer to chart on following page for qty. of wind rings

required on standard tanks. (Ex. If only one wind ring is required place on 2nd

ring from eave, if

2 req’d place on 2nd

and 5th

ring, if 3 req’d place on 2nd

, 5h, and 8

th and so on)

Page 58: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

Page 57 MANUAL CHIEF42 CB22

Titan Commercial Bins 16 thru 30 Rings Tall

Drawing is for illustrative purpose only. The quantity and location of wind rings required

depends on the application of any accessories (EX: sidedraw system). On Standard Bins place

wind rings as shown in figure above. Refer to chart on following page for qty. of wind rings on

standard tanks. (Ex. If only one wind ring is required place on 3rd

ring from eave, if 2 req’d place

on 3rd

and 6th

ring, if 3 req’d place on 3rd

, 6th

, and 9th

, and so on)

Page 59: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

MANUAL CHIEF42 CB22 Page 58

BIN

HEIGHT 18 20 22 24 26 30 34

8 0 1 1 1 1 1 1

9 0 1 1 1 2 2 2

10 1 1 1 1 2 2 2

11 1 1 2 2 2 2 2

12 1 1 2 2 2 2 2

13 1 1 2 2 2 2 2

14 1 1 2 2 2 2 3

15 1 1 2 2 2 2 3

16 1 1 2 2 2 2 3

17 2 2 2 2 2 2 3

18 2 2 2 2 2 2 3

19 2 2 2 2 2 2 3

20 2 2 2 2 3 3 3

21 2 2 2 3 3 3 3

22 2 2 2 3 3 3 4

23 2 2 2 3 3 3 4

24 2 2 2 3 3 3 4

25 2 2 3 3 3 4 4

26 2 2 3 3 3 4 5

27 2 3 3 3 3 5 5

28 3 3 3 3 3 5 NA

29 3 3 3 4 3 5 NA

30 3 3 3 4 3 5 NA

BIN SERIES

Wind rings required on standard Commercial Titan Bins

Page 60: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

Page 59 MANUAL CHIEF42 CB22

Wind Ring Placement with Sidedraw Systems

Page 61: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

MANUAL CHIEF42 CB22 Page 60

Standard Total

Bin Ring Wind Rings Wind

Size Height Quantities Rings

10 10 - 18 0 + 1 1

11 10 - 18 0 + 1 1

11 19 - 20 0 + 2 2

12 10 - 18 0 + 1 1

12 19 - 22 0 + 2 2

13 10 - 18 0 + 1 1

13 19 - 23 0 + 2 2

14 10 - 18 0 + 1 1

14 19 - 24 0 + 2 2

16 10 - 15 0 + 1 1

16 16 - 18 1 + 1 2

16 19 - 26 1 + 2 3

18 10 - 16 1 + 1 2

18 17 - 21 2 + 1 3

18 22 - 27 2 + 2 4

18 28 3 + 2 5

20 10 - 16 1 + 1 2

20 17 - 21 2 + 1 3

20 22 - 26 2 + 2 4

20 27 - 29 3 + 2 5

22 10 1 + 1 2

22 11 - 21 2 + 1 3

22 22 - 24 2 + 2 4

22 25 - 28 3 + 2 5

24 10 1 + 1 2

24 11 - 20 2 + 1 3

24 21 - 24 3 + 1 4

24 25 - 28 3 + 2 5

24 29 - 30 4 + 2 6

26 10 - 15 2 + 1 3

26 16 - 19 2 + 2 4

26 20 - 23 3 + 2 5

26 24 - 29 3 + 3 6

26 30 3 + 4 7

30 10 - 15 2 + 1 3

30 16 - 19 2 + 2 4

30 20 - 24 3 + 2 5

30 25 4 + 2 6

30 26 4 + 3 7

30 27 - 30 5 + 3 8

34 10 - 13 2 + 1 3

34 14 - 17 3 + 1 4

34 18 - 21 3 + 2 5

34 22 - 25 4 + 2 6

34 26 - 27 5 + 2 7

Additional

with

Sidedraw System

Page 62: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

Page 61 MANUAL CHIEF42 CB22

Miscellaneous

A. Maintenance Instructions

ROOF: Annual inspection of the roof structure should be made to be sure there is

no holes in the roof panels and all connections are water tight. If leaks

should occur apply weatherproof caulk in the area of concern.

SIDEWALL: Sidewall inspection must also be conducted at least annually. Should leaks

occur apply caulk to area of concern.

Should spoilage occur, thoroughly clean surfaces. If oxidation is present,

remove oxidation and apply corrosive resistance paint.

BASE: Inspect base as often as possible for spoilage, as this is a direct indication

of excess moisture. If spoilage is present, thoroughly clean surface. If

oxidation is present, remove oxidation and apply corrosive resistance

paint. After paint has dried, apply base sealer to effected area.

DOORS: Inspect doors and manholes as often as possible to be sure proper seal is

maintained.

DECALS: Be sure all warning decals are installed in proper locations. Replace all

damaged or unreadable warning decals.

Page 63: 347861 MANUAL CB22 30DG J RIB AGRI.pdf

MANUAL CHIEF42 CB22 Page 62

B. Comment Sheet

Dear Erector:

In an effort to better serve and please you, list below any problems you may have encountered

with your product or the erection procedures in this manual. Also list any suggestions you may

have for improvements.

Erection Manual Problems: ____________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

__________________________________________________

Recommended Solutions:

____________________________________________________________ _____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

__________________________________________________

Product Problems: ____________________________________________________________ _____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

__________________________________________________

Product Improvements Suggestions:

____________________________________________________________ _____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

__________________________________________________

Thank you for your time and reason. All responses will be reviewed by our engineering staff.

Please detach this page and send to: Agri Engineering Department

Chief Industries, Inc.

P.O. Box 848

Kearney, NE 68848-0848