EPIC FOR POWER SUPPLY PROJECT THROUGH SUBMARINE CABLES FROM RAS LAFFAN TO HALUL SITE ACCEPTANCE TEST FOR 132kV GIS Client Qatar Petroleum Document No. 3433-HW08-2-05-0003-F01 Contractor LSC / L&T Date / Rev. 05/03/2015 / Rev. - 1 Location Page No 1 of 2 Equipment Tag Test Date Make Name / Type of Equipment Serial Number Rating Power Voltage Current DESIGN AND VISUAL CHECKS 1. Check List Sr. No. Particulars Status / Remarks 1 Check each name plate according to drawing 2 Check space heater for wire continuity 3 Check setting of thermostat for space heater 4 Check door closing properly 5 Check earthing state door and frame 6 Check all signal / indication lamps 7 Check all limit switches of door, DS / ES etc. 8 Check Phase marking as per approved drawing 9 Check interlock lever for operation 10 Check number mark on cables 11 Check CT lugs / wires are connected as per approved drawing 12 Check for conformity of control cable connection and identification label. 13 Check all components labels are L&T Vendor LSC QP Signature Name Designati on Date

3433-HW08-2-05-0003-F01

Embed Size (px)

DESCRIPTION

132KV GIS-PD

Citation preview

EPIC FOR POWER SUPPLY PROJECT THROUGH SUBMARINE CABLES FROM RAS LAFFAN TO HALUL

SITE ACCEPTANCE TEST FOR 132kV GIS

Client

Qatar Petroleum

Document No.

3433-HW08-2-05-0003-F01

Contractor

LSC / L&T

Date / Rev.

05/03/2015 / Rev. - 1

Location

Page No

1 of 1

Equipment Tag

Test Date

Make

Name / Type of Equipment

Serial Number

Rating

Power

Voltage

Current

DESIGN AND VISUAL CHECKS

1. Check List

Sr. No.

Particulars

Status / Remarks

1

Check each name plate according to drawing

2

Check space heater for wire continuity

3

Check setting of thermostat for space heater

4

Check door closing properly

5

Check earthing state door and frame

6

Check all signal / indication lamps

7

Check all limit switches of door, DS / ES etc.

8

Check Phase marking as per approved drawing

9

Check interlock lever for operation

10

Check number mark on cables

11

Check CT lugs / wires are connected as per approved drawing

12

Check for conformity of control cable connection and identification label.

13

Check all components labels are placed

14

Check for pad locks are placed where as required

15

Check earthing is connected as per approved drawing

16

Check for paint condition wherever applicable

2. Test Equipments used

Sr. No.

Equipment / Instrument

Make

Equip. Sr. No.

Calibration due date

Remarks:

L&T

Vendor

LSC

QP

Signature

Name

Designation

Date