CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGA HINAI DENGAN JALAN BUNGA KACA
PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMUR LAUT, PULAU PINANG.
SENARAI KANDUNGAN DOKUMEN TENDER
SEKSYEN PERKARA MUKA SURAT
1 BAHAGIAN A
a) Senarai dokumen wajib yang perlu dikemukakan oleh pentenderBagi tujuan penilaian tender
b) Mendapatkan maklumat tambahan dokumenwajib bagi tujuanPenilaian perolehan kerja
c) Senarai semakan mengemukakan tender untuk kegunaan pretenderd) Kenyataan tender ( tender notice )e) Arahan kepada pretender
Appendix B ( EMP )f) Peringatan Mengenai Kesalahan Rasuah & Surat Akuan Pembida
BAHAGIAN B
a) Borang tender ( JKR 203B-Pind. 5/2008 )b) Boring-borang maklumat yang perlu dilengkapi oleh petender
( lampiran A1-A10 )
BAHAGIAN C
a) Surat setuju terima tender ( JKR203D-Pind. 1/2011 )BAHAGIAN D
a)Standard form of contract PWD form 203A ( rev.1/2010 )b)Special provision to the conditions of contract
Variation in prices of materials
1
1-2
1-7
1-2
1-17
B1-B6
1-2 & 1 -2
1-10
A1/1/4-A10/1/1
1-5
1- 6 & 50 - 53
ACPC2-1-
ACPC2-27
1
7/28/2019 3.1. Senarai Kandungan Dokumen Tender
2/3
CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGA HINAI DENGAN JALAN BUNGA KACA
PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMUR LAUT, PULAU PINANG.
SENARAI KANDUNGAN
SEKSYEN PERKARA MUKA SURAT
I BAHAGIAN F
a) Method Of Measurement And Pricing Factors
a) Bills of quantityi. Summary of bills of quantitiesii. Bills of quantities
b) Daywork rates ( labour and plants )c) Proposed programme of worksd) Contractors management and site supervisory staffe) Registration of workersf) Particulars of registered sub-contractorsg) List of construction plantsh) Appendix A
MM1/1 MM 11/6
1/1
BQ8 BQ 12
SPA / 1 - 7
SPC / 1
SPD / 1
SPE / 1
SPF / 1
SPG / 1
1 - 3
2
7/28/2019 3.1. Senarai Kandungan Dokumen Tender
3/3
CADANGAN PEMBINAAN JALAN SAMBUNGAN DI JALAN BUNGA HINAI DENGAN JALAN BUNGA KACA
PIRING SEKITAR SRJK ( C ) HUN BIN, DAERAH TIMUR LAUT, PULAU PINANG.
SENARAI KANDUNGAN
SEKSYEN PERKARA MUKA SURAT
II
III
BAHAGIAN F
a) Appendix 1 E Computer System And Other Requirementb) Appendix 1 F Fitting And Furniture For P.D. Officesc) Appendix 1G Programme Using Critical Path Method ( CPM )d) Appendix 1H As Build Drawings And Road Assets Inventorye) Borang Jaminan Untuk Bon Perlaksanaan ( Lampiran B )f) Borang Jaminan Untuk Bayaran Pendahuluan ( Lampiran C )
BAHAGIAN F
a) Senarai Lukisanb) Lukisan
S1E-1 S1E-5
S1F/1/4 S1F/4/4
SIG /1/1