Upload
natsir-djafar
View
217
Download
0
Embed Size (px)
Citation preview
8/10/2019 31 - Future Developments in Cement
1/33
Future Developmentsby
Frank Gad
International Cement Production Seminar June 2002
8/10/2019 31 - Future Developments in Cement
2/33
What drives future
developments
Demand for VALUE CREATIONDemand for VALUE CREATION
and asustainable FUTUREand asustainable FUTURE
8/10/2019 31 - Future Developments in Cement
3/33
Value creation
NOPATCAPITAL EMPLOYED
NOPATCAPITAL EMPLOYED
WACC
8/10/2019 31 - Future Developments in Cement
4/33
What improves your NOPAT?
Higher sales price More volume Quality products Lower costs:
- fuel- electricity- man power - maintenance costs- raw material costs- training and systems
Higher sales price More volume Quality products Lower costs:
- fuel- electricity- man power - maintenance costs- raw material costs- training and systems
8/10/2019 31 - Future Developments in Cement
5/33
Key numbers for
1.0 m mtpy (3000mtpd) BASIS:105 KWH/MT, 700 KCAL/KG, .05 $/KWH, 40 $/
COAL @ 6500 KCAL/KG POWER COST 5.25 US $/MT FUEL COST 4.30 US $/MT
GROSS PROFIT 40.00 US $/MT LOSS PER 1 DAY STOP 120,000 US $/DAY LOSS PER 1 HOUR STOP 5,000 US $/HOUR
GAIN IN SAVING 10 KWH/MT 500,000 US $/YEAR
GAIN IN SAVING 20 KCAL/KG 123,000 US $/YEA
BASIS:105 KWH/MT, 700 KCAL/KG, .05 $/KWH, 40 $/COAL @ 6500 KCAL/KG
POWER COST 5.25 US $/MT FUEL COST 4.30 US $/MT
GROSS PROFIT 40.00 US $/MT LOSS PER 1 DAY STOP 120,000 US $/DAY LOSS PER 1 HOUR STOP 5,000 US $/HOUR
GAIN IN SAVING 10 KWH/MT 500,000 US $/YEAR
GAIN IN SAVING 20 KCAL/KG 123,000 US $/YEA
Example
8/10/2019 31 - Future Developments in Cement
6/33
Operating CostsUS $ / MT OF CEMENT
BASIS: .O5 US $/KWH, 105 KWH/MT,700 KCAL/KG, 40 US $/MT OF COAL @ 6,500KCAL/KG
RAW MATERIALS : 4.50 US $ / MT FUEL (700 KCAL/KG): 4.30 US $ / MT POWER (105 KWH/MT + DEMAND) : 7.40 US $ / M MANPOWER : 4.30 US $ / MT SPARES & SUPPLIES : 3.50 US $ / MT
TOTAL: 24.00 US $ / MT
BASIS: .O5 US $/KWH, 105 KWH/MT,700 KCAL/KG, 40 US $/MT OF COAL @ 6,500KCAL/KG
RAW MATERIALS : 4.50 US $ / MT FUEL (700 KCAL/KG): 4.30 US $ / MT POWER (105 KWH/MT + DEMAND) : 7.40 US $ / M MANPOWER : 4.30 US $ / MT SPARES & SUPPLIES : 3.50 US $ / MT
TOTAL: 24.00 US $ / MT
Example
8/10/2019 31 - Future Developments in Cement
7/33
Fuel & power usage on a
modern plant @ 300m2/mt FUEL CONSUMPTION POWER CONSUMPT QUARRY 0 KCAL/KG 0 KWH/MT
CRUSHERS 0 -- -- 2.5 -- -- PREBL.+TRANSP. 0 -- -- 1.5 -- -- RAW MILL DEPT. 0-100 -- -- 27.0 -- --
RAW MEAL SILO 0 -- -- 0.5 -- -- KILN FEED 0 -- -- 1.5 -- -- KILN & COOLER 690 ---- 20.0 -- -- COAL MILL 0 -- -- 2.5 -- -- CEMENT MILL 0 -- -- 32.0 -- -- PACK HOUSE 0 ---- 1.0 -- -- OTHER 0 ---- 2.5 -- -- TOTAL 690 KCAL/KG 90.0 KWH/MT
FUEL CONSUMPTION POWER CONSUMPT QUARRY 0 KCAL/KG 0 KWH/MT
CRUSHERS 0 -- -- 2.5 -- -- PREBL.+TRANSP. 0 -- -- 1.5 -- -- RAW MILL DEPT. 0-100 -- -- 27.0 -- -- RAW MEAL SILO 0 -- -- 0.5 -- -- KILN FEED 0 -- -- 1.5 -- -- KILN & COOLER 690 -- -- 20.0 -- -- COAL MILL 0 -- -- 2.5 -- -- CEMENT MILL 0 -- -- 32.0 -- -- PACK HOUSE 0 -- -- 1.0 -- -- OTHER 0 -- -- 2.5 -- -- TOTAL 690 KCAL/KG 90.0 KWH/MT
Example
8/10/2019 31 - Future Developments in Cement
8/33
Sustainable future
Respect for the environment(emission)
Safety (people) Limited resources (substitute fuel
and raw materials)
Respect for the environment(emission)
Safety (people) Limited resources (substitute fuel
and raw materials)
8/10/2019 31 - Future Developments in Cement
9/33
Usage of waste materials
in cement manufacturing SOLID WASTE BURNING (HOT-DISC) FLUID WASTE BURNING (OBA-BURNER) ADDING OF FLYASH TO CEMENT USE OF POZZOLAN USE OF SLAG USE OF INCINERATOR ASH USE OF BONEMEAL
SOLID WASTE BURNING (HOT-DISC)
FLUID WASTE BURNING (OBA-BURNER) ADDING OF FLYASH TO CEMENT USE OF POZZOLAN USE OF SLAG USE OF INCINERATOR ASH USE OF BONEMEAL
8/10/2019 31 - Future Developments in Cement
10/33
HOTDISCHOTDISC
8/10/2019 31 - Future Developments in Cement
11/33
Rotating Disc
Burning Material
Scraper
Inlet for:WasteHot Air Hot Raw Meal
AshesKiln Gases
Raw Meal
Cold Raw Meal Inlet
Waste InletTrimming withRaw Meal
Hot Combustion Air
Outlet for:Combustion GasesHot Raw Meal
Ashes
8/10/2019 31 - Future Developments in Cement
12/33
HOTDISCHOTDISC
E l l
8/10/2019 31 - Future Developments in Cement
13/33
HOTDISCHOTDISC ECONOMY FOR A 3600 MTPD CEMENT PLANT
Fuel Heat Value 6500 Kcal/kg fuel
Operating days per year 330 days
Kiln Fuel 310 Kcal/kg clinker
Calciner Fuel 430 Kcal/kg clinker
Total Fuel Consumption 740 Kcal/kg clinker
Hotdisc Fuel Substitution 215 Kcal/kg clinker (50% of calciner fuel)
Equipment price on installed basis (approx.) 720,000 EUR
Storage and feeding (semi automatic) approx. 700,000 EUR
Total investment 1,420,000 EUR
Example only
PAY BACK TIME = 0.8 YEARS BASED ON 40 EURO/T PRICE DIFFERENTIALPAY BACK TIME = 0.8 YEARS BASED ON 40 EURO/T PRICE DIFFERENTIAL
8/10/2019 31 - Future Developments in Cement
14/33
The environment
SO2, NOx, and CO VOCs, Dioxins/Furans, HCl,
heavy metals, etc. Dust emissions
Hazardous Waste Bypass Dust Regeneration of Dust Permitting Environmental Groups Public Pressure
SO2, NOx, and CO VOCs, Dioxins/Furans, HCl,
heavy metals, etc. Dust emissions
Hazardous Waste Bypass Dust Regeneration of Dust Permitting Environmental Groups Public Pressure
8/10/2019 31 - Future Developments in Cement
15/33
CO Reduction
Separate Air Calciner
Higher Retention Times Regenerative Thermal Oxidizer (RTO)
Feed High Carbon Component(s)Directly to Calciner
Separate Air Calciner
Higher Retention Times Regenerative Thermal Oxidizer (RTO)
Feed High Carbon Component(s)Directly to Calciner
8/10/2019 31 - Future Developments in Cement
16/33
SO 2 Reduction
DeSOx System
Lime Injection Gas Suspension Absorber (GSA)
Micromist ML System Wet Scrubber
DeSOx System
Lime Injection Gas Suspension Absorber (GSA)
Micromist ML System Wet Scrubber
8/10/2019 31 - Future Developments in Cement
17/33
Particulate emission reduction
Use of Baghouses
Ventless Cooler Systems Use of GSA Bypass System Heat Exchangers
Dust Recovery System
Use of Baghouses
Ventless Cooler Systems Use of GSA Bypass System Heat Exchangers Dust Recovery System
8/10/2019 31 - Future Developments in Cement
18/33
Safety
Safety during plant construction
Design safe plants Design for easy maintenance
Reduce local noise, dust, vibrations, etc Automate repetitive work (packing etc.)
Safety during plant construction
Design safe plants Design for easy maintenance
Reduce local noise, dust, vibrations, etc Automate repetitive work (packing etc.)
8/10/2019 31 - Future Developments in Cement
19/33
Capital employed
Built cement plants better, faster
and cheaper De-bottleneck existing plants
Improve efficiency (e-stocking,consultancy, training, systems, people)
Built cement plants better, faster
and cheaper De-bottleneck existing plants
Improve efficiency (e-stocking,consultancy, training, systems, people)
Example only
8/10/2019 31 - Future Developments in Cement
20/33
60
80
100
120
140
160
180
200
220
240
260
280
1000 2000 3000 4000 5000 6000 7000 8000 9000 10000
Capacity (MTPD)
U S $ / M T P Y
LOW COST
NORMAL COST
RECENT JOBS
Total Installed Cost(Country specific)
Example only
8/10/2019 31 - Future Developments in Cement
21/33
Cost distribution
Typical cost distribution new plant
Mechanical 36 %Electrical 7 %Construction 57 %Total 100 %
Typical cost distribution new plant
Mechanical 36 %Electrical 7 %Construction 57 %Total 100 %
Engineering aprox. 6 % in each diciplineMechanical the distribution is aprox. 40/60 propriatary/auxiliary equipEngineering aprox. 6 % in each diciplineMechanical the distribution is aprox. 40/60 propriatary/auxil iary equip
8/10/2019 31 - Future Developments in Cement
22/33
Construction /
equipment costsF=CONSTRUCTION/EQUIPMENT
0
0.5
1
1.5
2
2.5
0 1000 2000 3000 4000 5000 6000
F=C/E
8/10/2019 31 - Future Developments in Cement
23/33
Equipment cost
US$/MTPY
0
102030405060708090
0 1000 2000 3000 4000 5000 6000
US$/MTPY
MTPD
C f d d h d l
8/10/2019 31 - Future Developments in Cement
24/33
Cost of extended schedule
P i i
8/10/2019 31 - Future Developments in Cement
25/33
Power saving in cement
grinding @ 300m2/mt
By installing an ok-mill insteadof a ball mill for cement
grinding a substancial power saving can be obtained
By installing an ok-mill insteadof a ball mill for cement
grinding a substancial power saving can be obtained
C i B ll Mill R ll Mill
8/10/2019 31 - Future Developments in Cement
26/33
Comparison Ball Mill vs Roller Millcement grinding 150 MTPH
System Ball mill OK Roller Mill
Clinker % 95 95Gypsum % 5 5Blaine cm 2/g 4,000 4,000Spec. energy
Mill Drive kWh/t 38.0 20.0Separator kWh/t 0.4 0.4Fans kWh/t 4.5 8.0
System kWh/t 42.9 28.4
Power Savings: 14.5 kWh/Mt cement
Cost Savings: $725,000 USD/yr
P i S t
8/10/2019 31 - Future Developments in Cement
27/33
Pyroprocessing System
Tailor Made Systems High Production Lines Cogeneration of Electricity Waste Management Low Pressure Drop High Efficiency Low NOx, SO2, and CO Computer Control
Tailor Made Systems High Production Lines Cogeneration of Electricity Waste Management Low Pressure Drop High Efficiency Low NOx, SO2, and CO Computer Control
P d ti I
8/10/2019 31 - Future Developments in Cement
28/33
Production Increase
Cyclone Modifications High Efficiency Separators New Calciners High Efficiency Fans Roller Presses Vertical Pregrinders Cooler Upgrade/Cross-bar Cooler
Cyclone Modifications High Efficiency Separators New Calciners High Efficiency Fans Roller Presses Vertical Pregrinders Cooler Upgrade/Cross-bar Cooler
Automation
8/10/2019 31 - Future Developments in Cement
29/33
Automation
Information
Trouble Shooting/Plant Guide Quality
Smooth Operation Energy Control
Refractory Control Manpower
Information Trouble Shooting/Plant Guide Quality Smooth Operation Energy Control
Refractory Control Manpower
WACC
8/10/2019 31 - Future Developments in Cement
30/33
WACC
Source of capital
Tax New financial
solutions (BOT, etc.)
Source of capital
Tax New financial
solutions (BOT, etc.)
What do F L Smidth do?
8/10/2019 31 - Future Developments in Cement
31/33
Global team workGlobal team work
What do F.L.Smidth do?
TechnologicalleadershipTechnologicalleadership
Cost efficiencyCost efficiency
Customer focusCustomer focus
Our mission
8/10/2019 31 - Future Developments in Cement
32/33
Our mission
We want to be your preferredsupplier of service,
technology and equipment
We want to be your preferredsupplier of service,
technology and equipment
8/10/2019 31 - Future Developments in Cement
33/33
Thank youand
Good luck!
Thank youand
Good luck!