Upload
piyuesh-goyal
View
6
Download
0
Embed Size (px)
DESCRIPTION
cp
Citation preview
CAPACITY PLANNING
CAPACITY PLANNING
Introduction
Capacity can be defined as the maximum
output rate that can be achieved by a facility.
The facility may be an
entire organization,
a division, or
only one machine.
Introduction
Planning for capacity in a company is usually performed at two levels, each corresponding to either
strategic or
tactical decisions.
The first level of capacity decisions is strategic and long-term in nature.
This is where a company decides what investments in new facilities and equipment it should make.
Introduction
Because these decisions are strategic in nature, the company will have to live with them for a long time.
Also, they require large capital expenditures and will have a great impact on the companys ability to conduct business.
The second level of capacity decisions is more tactical in nature, focusing on short-term issues that include planning of workforce, inventories, and day-to-day use of machines.
Importance of Capacity Planning
Importance of Capacity Planning
Capacity planning is the process of establishing
the output rate that can be achieved by a
facility.
If a company does not plan its capacity correctly, it may find that it either does not have enough
output capability to meet customer demands or has too much capacity sitting idle.
In a bakery for example, not having enough capacity would mean not being able to produce
enough baked goods to meet sales.
Importance of Capacity Planning
The bakery would often run out of stock, and customers might start going somewhere else.
Also, the bakery would not be able to take advantage of the true demand available.
On the other hand, if there is too much capacity, the bakery would incur the cost of an unnecessarily large facility that is not being
used, as well as much higher operating costs than necessary.
Importance of Capacity Planning
Planning for capacity is important if a company wants to grow and take full
advantage of demand.
At the same time, capacity decisions are
complicated because they require long-term commitments of expensive resources, such
as large facilities.
Once these commitments have been made, it is
costly to change them.
Importance of Capacity Planning
Think about a business that purchases a larger facility in anticipation of an increase in demand,
only to find that the demand increase does
not occur.
It is then left with a huge expense, no return on its investment, and the need to
decide how to use a partially empty
facility.
Importance of Capacity Planning
Another issue that complicates capacity planning is the fact that capacity is usually
purchased in chunks rather than in smooth increments.
Facilities, such as buildings and equipment, are
acquired in large sizes, and it is virtually
impossible to achieve an exact match between current needs and needs based on
future demand.
Importance of Capacity Planning
Because of the uncertainty of future demand, the overriding capacity planning
decision becomes one of whether to
purchase a larger facility in anticipation of
greater demand or to expand in slightly
smaller but less efficient increments.
Each strategy has its advantages and disadvantages.
When To & How Much
When to increase capacity and how much to increase it are critical decisions.
Three basic strategies for the timing of capacity expansion are:
1. Capacity lead strategy .
2. Capacity lag strategy.
3. Average capacity strategy
(Smoothing with inventories)
Leading & Lagging Strategies
Average Capacity Strategy
1. Capacity Lead Strategy
Capacity is expanded in such a way that there is
always sufficient capacity to meet forecast demand.
Capacity is expanded in anticipation of demand growth.
This aggressive strategy is used to lure customers from competitors who are capacity
constrained or to gain a foothold in a rapidly
expanding market.
1. Capacity Lead Strategy
It also allows companies to respond to unexpected surges in demand and to provide
superior levels of service during peak demand periods.
2. Capacity Lag Strategy
Capacity is expanded in such a way that the demand is always equal to or greater than capacity.
Capacity is increased after an increase in demand has been documented.
This conservative strategy produces a higher return on investment but may lose customers in the process.
It is used in industries with standard products and cost-based or weak competition.
2. Capacity Lag Strategy
The strategy assumes that lost customers will return from competitors after capacity has
expanded.
3. Average Capacity Strategy
Capacity is increased in such a way that the
current capacity plus accumulated inventory can always supply demand.
Capacity is expanded to coincide with average expected demand.
This is a moderate strategy in which managers are certain they will be able to sell at
least some portion of expanded output, and
endure some periods of unmet demand.
3. Average Capacity Strategy
Approximately half of the time capacity leads
demand, and half of the time capacity lags demand.
Advantages/Disadvantages
Advantages Disadvantages
Capacity-leading Strategy
1. Always sufficient capacity to meet demand, therefore revenue is maximised and customers satisfied.
2. Most of the time there is a capacity cushion which can absorb extra demand if forecasts are pessimistic.
3. Any critical start-up problems with new plants are less likely to affect supply to customers.
1. Risks of greater (or even permanent) over-capacity if demand does not reach forecast levels.
2. Capital spending on plant early.
Advantages/Disadvantages
Advantages Disadvantages
Capacity-lagging
Strategy
1. Always sufficient demand to keep the plants working at full capacity, therefore, unit costs are minimised.
2. Over-capacity problems are minimised if forecasts are optimistic.
3. Capital spending on the plants is delayed.
1. Insufficient capacity to meet demand fully, therefore, reduced revenue and dissatisfied customers.
2. No ability to exploit short-term increases in demand.
3. Under-supply position even worse if there are start-up problems with the new plants.
Advantages/Disadvantages
Advantages Disadvantages
Smoothing-with-
inventories Strategy
1. All demand is satisfied, therefore, customers are satisfied and revenue maximised.
2. Utilisation of capacity is high and therefore costs are low.
3. Very short-term surges in demand can be met from inventories.
1. The cost of inventories in terms of working capital requirement can be high.
2. This is especially serious at a time when the company requires funds for its capital expansion.
3. Risks of product deterioration and obsolescence.
Measuring Capacity
Measuring Capacity
Although our definition of capacity seems
simple, there is no one way to measure it.
Different people have different
interpretations of what capacity means, and the units of measurement are often very
different.
Table shows some examples of how capacity might be measured by different organizations.
Measuring Capacity
Type Of Business Input Measures Of Capacity
Output Measures Of Capacity
Car Manufacturer Labour hours Cars per shift
Hospital Available beds per month
Number of patients
Pizza shop Worker hours per day No of pizzas per day
Retail store Floor space in sq feet Revenues per day
Electricity company Generator size Megawatts of electricity generated
Measuring Capacity
Note that each business can measure capacity
in different ways and that capacity can be measured using either inputs or outputs.
Output measures, such as the number of cars
per shift, are easier to understand.
However, they do not work well when a company produces many different kinds of
products.
Measuring Capacity
For example, if a television factory produces only one basic model, the weekly capacity could
be described as 2000 televisions.
A government office may have the capacity to print and post 500,000 tax forms per week.
In each case, an output capacity measure is the most appropriate measure because the output
from the operation does not vary in its nature.
Measuring Capacity
But when a much wider range of outputs places varying demands on the process, output
measures of capacity are less useful.
Here input capacity measures are frequently used to define capacity.
For example, the hospital measures its capacity
in terms of its input resources (say beds), because there is not a clear relationship
between the number of beds it has and the
number of patients it treats.
Measuring Available Capacity
Measuring Available Capacity
Suppose that on the average we can make 20 cakes per day.
However, if we are really pushed, such as during holidays, maybe we can make 30 cakes per day.
Which of these is our true capacity?
We can make 30 cakes per day at a maximum, but we cannot keep up that pace for long.
Saying that 30 per day is our capacity would be misleading.
Measuring Available Capacity
On the other hand, saying that 20 cakes per day is our capacity does not reflect the fact that
we can, if necessary, push our production to 30
cakes.
Through this example you can see that
different measures of capacity are useful because they provide different kinds of
information.
Measuring Available Capacity
Following are two of the most common measures of capacity:-
1. Design capacity
2. Effective capacity
1. Design capacity
Design capacity is the maximum output rate that can be achieved by a facility under ideal conditions.
In our example, this is 30 cakes/day. Design capacity can be sustained only for a
relatively short period of time. A company achieves this output rate by using
many temporary measures, such as overtime, over-staffing, maximum use of equipment, and subcontracting.
2. Effective capacity
Effective capacity is the maximum output rate that can be sustained under normal conditions.
These conditions include realistic work schedules and breaks, regular staff levels, scheduled machine maintenance, and none of the temporary measures that are used to achieve design capacity.
Effective capacity is usually lower than design capacity.
In our example, effective capacity is 20 cakes/day.
Measuring Effectiveness of
Capacity Use
Regardless of how much capacity we have, we
also need to measure how well we are utilizing it.
Capacity utilization simply tells us how much of
our capacity we are actually using.
Certainly there would be a big difference if we
were using 50%of our capacity, meaning our facilities, space, labour, and equipment, rather
than 90%.
Capacity Considerations
Capacity utilization can simply be computed as the ratio of actual output over capacity:
Utilization = actual output rate
capacity
Capacity Considerations
However, since we have two capacity measures, we can measure utilization relative to either
design or effective capacity
Utilizationeffective =
Utilizationdesign =
actual output
effective capacity
actual output
design capacity
Example
In the bakery example, we have established that design capacity is 30 cakes per day and
effective capacity is 20 cakes per day. Currently,
the bakery is producing 27 cakes per day. What
is the bakerys capacity utilization relative to both design and effective capacity?
Expanding Capacity
When expanding capacity, management has to choose between one of the following two
alternatives:
1. Purchase one large facility, requiring
one large initial investment.
2. Add capacity incrementally in smaller
chunks as needed.
Expanding Capacity
One Step Expansion
Incremental Expansion
Time
Units
Expanding Capacity
The first alternative means that we would
have a large amount of excess
capacity in the beginning and that our initial costs would be high.
We would also run the risk that demand might
not materialize and we would be left with
unused overcapacity.
On the other hand, this alternative allows us to be prepared for higher demand in the future.
Expanding Capacity
Our best operating level is much higher with this alternative, enabling us to operate
more efficiently when meeting higher demand.
Our costs would be lower in the long run, since one large construction project typically costs less than many smaller construction projects due to startup costs.
Thus, alternative 1 provides greater rewards but is more risky.
Expanding Capacity
Alternative 2 is less risky but does not offer the same opportunities and flexibility.
It is up to management to weigh the risks
versus the rewards in selecting an alternative.
Capacity Considerations
We have seen that changing capacity is not as simple as acquiring the right amount of
capacity to exactly match our needs.
The reason is that capacity is purchased in discrete chunks.
Also, capacity decisions are long term and strategic in nature.
Capacity Considerations
Some of the important implications of capacity that a company needs to consider when
changing its capacity are:
1. Economies of Scale
2. Diseconomies of Scale
3. Focused Factories
4. Subcontractor Networks
1. Economies of Scale
Every production facility has a volume of output
that results in the lowest average unit cost.
This is called the facilitys best operating
level .
Figure illustrates how the average unit cost of output is affected by the volume produced.
You can see that as the number of units
produced is increased, the average cost per
unit drops.
1. Economies of Scale
Output Produced in Units
Ave
rage
Un
it C
ost
Economies of Scale Diseconomies of Scale
Best Operating Level
1. Economies of Scale
The reason is that when a large amount of goods is produced, the costs of production are
spread over that large volume.
These costs include the fixed costs of buildings and facilities, the costs of materials, and processing costs.
The more units are produced, the larger the number of units over which costs can be
spreadthat is, the greater the economies of scale .
1. Economies of Scale
The concept of economies of scale is very well known.
It basically states that the average cost of a unit produced is reduced when the amount of output is increased.
You use the concept of economies of scale in your daily life.
Suppose you decide to make cookies in your kitchen. Think about the cost per cookie if you make only five cookies.
1. Economies of Scale
There would be a great deal of effortgetting the ingredients, mixing the dough,
shaping the cookiesall for only five cookies.
2. Diseconomies of Scale
What if you continued to increase the number of cookies you chose to produce?
For a while, making a few more cookies would not require much additional effort.
However, after a certain point there would be so much material that the kitchen would
become congested. You might have to get someone to help
because there was more work than one person could handle.
2. Diseconomies of Scale
You might have to make cookies longer than
expected, and the cleanup job might be
much more difficult.
You would be experiencing diseconomies
of scale .
Diseconomies of scale occur at a point
beyond the best operating level, when the cost of each additional unit made
increases.
2. Diseconomies of Scale
Operating a facility close to its best operating level is clearly important because of the impact
on costs.
However, we have to keep in mind that
different facility sizes have different
best operating levels.
2. Diseconomies of Scale
In our cookie example, we can see that the number of cookies comfortably produced by
one person in a small kitchen would be much lower than the number produced by
three persons in a large kitchen.
Figure shows how best operating level varies between facilities of different sizes.
2. Diseconomies of Scale
Output Produced in Units
Ave
rage
Un
it C
ost
Small
Medium
Large
3. Focused Factories
The concept of the focused factory holds that a
production facility works best when it focuses
on a fairly limited set of production objectives.
This means, for example, that a firm should
not expect to excel in every aspect of manufacturing performance: cost, quality,
delivery speed and reliability, changes in
demand, and flexibility to adapt to new
products.
3. Focused Factories
Rather, it should select a limited set of tasks that contribute the most to corporate
objectives.
For example, consider a company that competes on using the highest quality
component parts in its products.
Due to the high quality of parts, the company
may not be able to offer the final product at
the lowest price.
3. Focused Factories
In this case, the company has made a trade-
off between quality and price.
Similarly, a company that competes on making each product individually based on
customer specifications will likely not be
able to compete on speed.
Here, the trade-off has been made between
flexibility and speed.
3. Focused Factories
One way that large facilities with multiple products can address the issue of trade-offs is using the concept of plant-within-a-plant (PWP), introduced by well-known Harvard professor Wickham Skinner.
The PWP concept suggests that different areas of a facility be dedicated to different products with different competitive priorities.
These areas should be physically separated from one another and should even have their own separate workforce.
3. Focused Factories
As the term suggests, there are multiple plants within one plant, allowing a company to
produce different products that compete on
different priorities.
For example, hospitals use PWP to achieve specialization or focus in a particular area, such
as the cardiac unit, radiology, surgery, or
pharmacy.
4. Subcontractor Networks
Another alternative to having a large production facility is to develop a large network of subcontractors and suppliers who perform a number of tasks.
This is one of the fastest-growing trends today.
Companies are realizing that to be successful in todays market, they need to focus on their core capabilitiesfor example, by hiring third parties or subcontractors to take over tasks that the company does not need to perform itself.
4. Subcontractor Networks
Companies such as American Airlines and Procter & Gamble have hired outside firms to manage noncritical inventories.
Also, many companies are contracting with suppliers to perform tasks that they used to perform themselves.
A good example is in the area of quality management.
Historically, companies performed quality checks on goods received from suppliers.
4. Subcontractor Networks
Today, suppliers and manufacturers work together to achieve the same quality standards,
and much of the quality checking of incoming
materials is performed at the suppliers site.
Another example can be seen in the auto
industry, where manufacturers are placing more responsibility on suppliers to perform
tasks such as design of packaging and
transportation of goods.
4. Subcontractor Networks
By placing more responsibility on
subcontractors and suppliers, a manufacturer can focus on tasks that are critical
to its success, such as product development
and design.
Making Capacity Planning Decisions
The three-step procedure for making capacity planning decisions is as follows
1. Identify Capacity Requirements
2. Develop Capacity Alternatives
3. Evaluate Capacity Alternatives
1. Identify Capacity Requirements
Long-term capacity requirements are identified
on the basis of forecasts of future demand.
Companies look for long-term patterns such as
trends when making forecasts.
However, long-term patterns are not enough at this stage.
Planning, building, and starting up a new facility
can take well over five years.
Much can happen during that time.
1. Identify Capacity Requirements
When the facilities are operational, they are
expected to be utilized for many years into the future.
During this time frame numerous changes
can occur in the economy, consumer base,
competition, technology, and demographic factors, as well as in
government regulation and political
events.
1. Identify Capacity Requirements
Following are the key steps performed while identifying the capacity requirements:
a)Forecasting Capacity
b)Capacity Cushions
c)Strategic Implications
1.a. Forecasting Capacity
Capacity requirements are identified on the basis of forecasts of future demand.
Forecasting at this level is performed using qualitative forecasting methods as already discussed.
Qualitative forecasting methods, such as executive opinion and the Delphi method , use subjective opinions of experts.
These experts may consider inputs from quantitative forecasting models that can numerically compute patterns such as trends.
1.a. Forecasting Capacity
However, because so many variables can influence demand at this level, the experts use their judgment to validate the quantitative
forecast or modify it based on their own knowledge.
One way to proceed with long-range demand forecasting at this stage is to first
forecast overall market demand.
Then the company can estimate its market share as a percentage of the total.
1.a. Forecasting Capacity
From that we can compute an estimate of
demand for our company for next few years
by multiplying the overall market demand with the percentage held by our company.
That forecast of demand can then be
translated into specific facility
requirements.
1.b. Capacity Cushions
Companies often add capacity cushions to their regular capacity requirements.
A capacity cushion is an amount of capacity added to the needed capacity in order to provide greater flexibility.
Capacity cushions can be helpful if demand is greater than expected.
Also, cushions can help the ability of a business to respond to customer needs for different products or different volumes.
1.b. Capacity Cushions
Finally, businesses that operate too close to their maximum capacity experience many costs
due to diseconomies of scale and may
also experience deteriorating quality.
1.c. Strategic Implications
Finally, a company needs to consider how much
capacity its competitors are likely to have.
Capacity is a strategic decision, and the position of
a company in the market relative to its competitors is very much determined by its
capacity.
At the same time, plans by all major competitors to increase capacity may signal the
potential for overcapacity in the industry.
1.c. Strategic Implications
Therefore, the decision as to how much capacity to add should be made carefully.
2. Develop Capacity Alternatives
Once a company has identified its capacity
requirements for the future, the next step is to develop alternative ways to modify its
capacity.
One alternative is to do nothing and re-evaluate the situation in the future.
With this alternative, the company would not be able to meet any demands that exceed
current capacity levels.
2. Develop Capacity Alternatives
Choosing this alternative and the time to re-
evaluate the companys needs is a strategic
decision.
The other alternatives require deciding whether to purchase one large facility now or
add capacity incrementally, as discussed earlier
in the slides.
3. Evaluate Capacity Alternatives
Decision Trees
There are a number of tools that we can use to evaluate our capacity alternatives but the most popular of these tools is the decision tree.
Decision trees are useful whenever we have to evaluate interdependent decisions that must be made in sequence and when there is uncertainty about events.
For that reason, they are especially useful for evaluating capacity expansion alternatives given that future demand is uncertain.
3. Evaluate Capacity Alternatives
Decision Trees
Remember that our main decision is whether to purchase a large facility or a small one with the
possibility of expansion later.
A decision tree is a diagram that models the
alternatives being considered and the possible
outcomes.
Decision trees help by giving structure to a
series of decisions and providing an objective
way of evaluating alternatives.
3. Evaluate Capacity Alternatives
Decision Trees
Decision trees contain the following information:
1. Decision points. These are the points in time when decisions, such as whether or not to expand, are made. They are represented by squares, called nodes.
2. Decision alternatives. Buying a large facility and buying a small facility are two decision alternatives. They are represented by branches or arrows leaving a decision point.
3. Evaluate Capacity Alternatives
Decision Trees
3. Chance events. These are events that could affect the value of a decision. For example, demand could be high or low. Each chance event has a probability or likelihood of occurring. For example, there may be a 60 percent chance of high demand and a 40 percent chance of low demand. Remember that the sum of the probabilities of all chances must add up to 100 percent. Chance events are branches or arrows leaving circular nodes.
3. Evaluate Capacity Alternatives
Decision Trees
4. Outcomes. For each possible alternative an outcome is listed. In our example, that may be
expected profit for each alternative (expand
now or later) given each chance event (high
demand or low demand).
Decision Trees EXAMPLE
Mr ABC, the owner of XYZ Company, has determined that he needs to expand the facility.
The decision is whether to expand now with a
large facility, incurring additional costs and
taking the risk that demand will not materialize,
or expand now on a smaller scale, knowing that
he will have to consider expanding again in
three years.
Decision Trees EXAMPLE
He has estimated the following chances for demand:
The likelihood of demand being high is 0.70.
The likelihood of demand being low is 0.30.
He has also estimated profits for each alternative:
Large expansion has an estimated profitability of either $300,000 or $50,000, depending on whether
demand turns out to be high or low.
Decision Trees EXAMPLE
Small expansion has a profitability of $80,000, assuming that demand is low.
Small expansion with an occurrence of high demand would require considering whether to expand
further. If he expands at that point, his profitability is
expected to be $200,000. If he does not expand
further, profitability is expected to be $150,000.
Develop a decision tree to solve Mr ABCs problem.
Decision Trees SOLUTION
Procedure for Drawing a Decision Tree:
1. Draw a decision tree from left to right. Use
squares to indicate decisions and circles
to indicate chance events.
2. Write probability of each chance event in
parentheses.
3. Write out the outcome for each alternative in the right margin.
1
High Demand (0.7)
High Demand (0.7)
Low Demand (0.3)
Low Demand (0.3)
Expand
Dont Expand
$300,000
$50,000
$80,000
$200,000
$150,000
2
Decision Trees SOLUTION
We drew the decision tree from left to right.
To evaluate it, we work backward, from right to
left, to determine the expected value (EV) .
EV is a weighted average of the chance events, where each chance event is given a probability
of occurrence.
We start with the profitability of each alternative, working backward and selecting the
most profitable alternative.
Decision Trees SOLUTION
For example, at node 2 we should decide to expand further, because the profits from that
decision are higher ($200,000 versus $150,000).
EV of profits at that point is written below node 2.
This is the expected value if we decide on a small expansion and high demand occurs.
1
High Demand (0.7)
High Demand (0.7)
Low Demand (0.3)
Low Demand (0.3)
Expand
Dont Expand
$300,000
$50,000
$80,000
$200,000
$150,000
2
$200,000
Decision Trees SOLUTION
To compute the expected value ( EV) of the small expansion, we evaluate it as a weighted
average of estimated profits given the
probability of occurrence of each chance event:
EVsmall expansion = 0.30($80,000) + 0.70($200,000)
= $164,000
Decision Trees SOLUTION
Similarly for large expansion:
EVlarge expansion = 0.30($50,000) + 0.70($300,000)
= $225,000
The large expansion gives the higher expected value.
This means that Mr ABC should pursue a large expansion now.
Decision Trees Q 1
The owner of Hackers Computer Store is considering what to do with his business over
the next five years. Sales growth over the past
couple of years has been good, but sales could
grow substantially if a major electronics firm is
built in his area as proposed. Hackers owner sees three options. The first is to enlarge his
current store, the second is to locate at a new
site, and the third is to simply wait and do
nothing.
Decision Trees Q 1
The decision to expand or move would take little time, and, therefore, the store would not
lose revenue. If nothing were done the first year
and strong growth occurred, then the decision
to expand would be reconsidered. Waiting
longer than one year would allow competition
to move in and would make expansion no
longer feasible.
Decision Trees Q 1
The assumptions and conditions are as follows: a) Strong growth as a result of the increased population
of computer fanatics from the new electronics firm has a 55 percent probability.
b) Strong growth with a new site would give annual returns of $195,000 per year. Weak growth with a new site would mean annual returns of $115,000.
c) Strong growth with an expansion would give annual returns of $190,000 per year. Weak growth with an expansion would mean annual returns of $100,000.
d) At the existing store with no changes, there would be returns of $170,000 per year if there is strong growth and $105,000 per year if growth is weak.
Decision Trees Q 1
e) Expansion at the current site would cost $87,000.
f) The move to the new site would cost $210,000.
g) If growth is strong and the existing site is enlarged
during the second year, the cost would still be
$87,000.
h) Operating costs for all options are equal
Develop a decision tree to solve this problem.
1
2
Move
Expand
Do Nothing
Strong Growth (0.55)
Strong Growth (0.55)
Strong Growth (0.55)
Weak Growth (0.45)
Weak Growth (0.45)
Weak Growth (0.45)
Expand
Do Nothing
R - MC
R - MC
R - EC
R - EC
R - EC
R
R
R (Revenue)
MC (Move Cost)
EC (Expand Cost)
Decision Trees Q 1
ALTERNATIVE REVENUE $ COST $ VALUE $
Move to new location, strong growth 195,000 5 = 975000 210,000 765,000
Move to new location, weak growth
Expand store, strong growth
Expand store, weak growth
Do nothing now, strong growth, expand next year
Do nothing now, strong growth, do not expand next year
Do nothing now, weak growth
Decision Trees Q 1
ALTERNATIVE REVENUE $ COST $ VALUE $
Move to new location, strong growth 195,000 5 = 975000 210,000 765,000
Move to new location, weak growth 115,000 5 = 575000 210,000 365,000
Expand store, strong growth 190,000 5 = 950000 87,000 863,000
Expand store, weak growth 100,000 5 = 500000 87,000 413,000
Do nothing now, strong growth, expand next year
170,000 1 + 190,000 4
87,000 843,000
Do nothing now, strong growth, do not expand next year
170,000 5 = 850000 0 850,000
Do nothing now, weak growth 105,000 5 = 525000 0 525,000
= 930000
1
2
Move
Expand
Do Nothing
Strong Growth (0.55)
Strong Growth (0.55)
Strong Growth (0.55)
Weak Growth (0.45)
Weak Growth (0.45)
Weak Growth (0.45)
Expand
Do Nothing
765,000
365,000
863,000
413,000
843,000
850,000
525,000
R (Revenue)
MC (Move Cost)
EC (Expand Cost)