Upload
jorge-humberto-herrera
View
214
Download
0
Embed Size (px)
Citation preview
Science and Risk-Based Commissioning and Qualification
Applied Risk Management In a 21stCentury GMP Environment
David Dolgin Senior Quality Program Manager Global Quality Systems Abbott
Topics
• Introduction and Background • Transition to Science and Risk Based
Approaches • Linking C&Q to the Process
Validation Lifecycle • Recent ISPE Guidance
Agenda – Thursday Morning – 19 May 2012
• Background (8:30-9:00) • Transitional Approaches (9:00-10:30) • Process Validation and Legacy Systems
(10:45-11:30) • Recent ISPE Guidance Documents
(11:30-12:00)
Science and Risk-Based Commissioning and Qualification
Introduction and Background
David Dolgin Senior Quality Program Manager Global Quality Systems Abbott
What is a Science and Risk Based Approach?
A science and risk based approach to Qualification of applicable systems and facilities consists of: • The identification and control of risks to product quality • Formality and documentation commensurate with risk • The use of Good Engineering Practices (GEP) to verify installation and operation of systems • Verification that system performance meets product and process user requirements
A Brief History of C&Q…
Qualification of Systems and Facilities Validation of
Manufacturing and Supporting Processes
Validation Quality Systems have traditionally described two separate but related activities:
Qualification – A Broken Process One-Size-Fits-All Approach Emphasis on Documentation – Not
Process Requirements Absent or Incomplete Assessment of
Risks to Product Quality & Patient Safety
IQ/OQ More Intensive Than PQ Organizations Refused to Leverage
Commissioning “Deviations” for Trivial Items “Change-is-Bad” Attitude Driven by
Cost / Time Inhibited Innovation & Continuous Improvement
A Road Forward…
ISPE Baseline Guide 5 (2001) “Pharmaceutical cGMPs for the 21st Century – A Risk Based
Approach” – FDA (2004) ISPE White Paper – “Risk Based Qualification for the 21st
Century” (2005) ICH Q9 Quality Risk Management (2006) ASTM E 2500 “Standard Guide for Specification, Design, and
Verification of Pharmaceutical and Biopharmaceutical Manufacturing Systems and Equipment” (2007)
ISPE Good Practice Guide – “Science and Risk Based Approach for the Delivery of Facility Systems and Equipment” (2011)
ISPE Good Practice Guide – “Applied Risk Management in C&Q” (2011)
10 Principles for Risk-Based Qualification 1. Focus on that which affects product quality 2. Process User Requirements key to acceptability (IQ/OQ subordinate
to PQ) 3. Risk assessments and process knowledge used to identify critical
elements 4. Only critical features/functions to be qualified 5. All activities must contribute value 6. Risk-based asset delivery – not “cookbook” requirements 7. Value-added documents based on technical merit 8. Use of supplier documentation 9. Test planning (and one-time testing) 10. Foster innovation – all change is not bad
ISPE White Paper “Risk Based Qualification for the 21st Century” March 2005
ICH Q9 – Two Key Principles “The evaluation of the risk
to quality should be based on scientific knowledge and ultimately link to the protection of the patient.”
“The level of effort, formality, and documentation of the quality risk management process should be commensurate with the level of risk.” (my emphasis)
ASTM E 2500-07
• First consensus standard using science and risk-based approach to verification
• “Verification” is an umbrella term taken from regulation (“…verified as fit for intended use…”) and used to describe both commissioning and qualification
• ASTM does away with IQ and OQ as mechanisms and goes straight from commissioning to PQ
• Redefines Quality and Engineering roles – QA is assurance not control – an audit role, not a direct management or execution role
Design Review Change Management
Risk Management
Good Engineering Practice
Figure 1 – The Specification, Design, and Verification Process
Operation
Product Knowledge Process Knowledge
Regulatory Company Quality
Requirements Specification and Design Verification Acceptance
and Release
ASTM E 2500-07 Process Flow
Verification as Qualification
Qualified as Suitable For Intended Use Basis for Suitability:
Process Requirements, Risk Control
FAT Verification Work
SAT Verification Work
Commissioning Verification Work
Figure 2 from “Solving the Terminology Conundrum” Pharmaceutical Engineering, July/August 2008
Qualification -“Traditional” vs. RBA Traditional Approach • User Requirements not
Formally Documented • Protocols Developed from
“Templates” • IQ/OQ Protocols
“Preapproved” • Commissioning not Leveraged • Engineering and “Validation”
Personnel Often Distinct • Emphasis on Documents – Not
System Performance
RBA Based on ASTM E 2500 • Process Requirements
Documented, Approved • Risk Assessments Determine
Critical Aspects of E/F/U Design • Engineering Testing
(“Commissioning”) Verification • All Documents with Technical Merit
Used as Evidence of Fitness for Use
• Emphasis on Meeting Process Requirements
Risk Based C&Q - Challenges and Opportunities Opportunities • Cheaper • Faster • Focused on Patient Risk • Resource Reallocation Possible • Foster Innovation
Challenges • ASTM not yet fully vetted with all global
agencies • GEP and ECM are prerequisites • Both Quality and Engineering units must
“buy-in” • Commissioning documentation Quality
standards must be set and achieved
Pro’s Con’s
Industry Needs Going Forward
• Regulators who walk-the-talk on risk based approaches
• Industry that understands the opportunities and responsibilities – not simply viewing RBA’s as chance to “do more with less”
• Continued leadership from key industry groups and participation of “big pharma” in an evolutionary process
• QA units that understand that more is not necessarily better
• Good Engineering Practices – and Good Engineers
Actual photo of risk based revalidation paperwork for a legacy control system (on right) vs. previous revalidation “testing everything”
Time & $$$ to
Focus on Critical Quality Issues
Eyes on the Prize