Upload
ravibhushan17
View
117
Download
5
Embed Size (px)
Citation preview
NICMAR
MSP Report On Construction of
Cooling Tower “Tata Power Unit#5”
Jamshedpur.
MCM 503: COMPUTER WORKSHOP-III
Submitted By
Mr. Ravi Bhushan (221025)
PGP ACM 22nd Batch
(2008-2010)
NATIONAL INSTITUTE OF CONSTRUCTION
MANAGEMENT AND RESEARCH
PUNE
NICMAR
Contents
1. Introduction ………….…3
2. Project Details ………….…3
3. List of Activities ………….…8
4. Technical Features ….…….…..9
5. Data Collected ……….…..11
6. Conclusion …..…….…13
2
NICMAR
Introduction:
Project management is the process of planning, organizing, and managing tasks and resources
to accomplish a defined objective, usually within constraints on time, resources, or cost. A
project plan can be simple, for example, a list of tasks and their start and finish dates written
on a notepad. Or it can be complex, for example, thousands of tasks and resources and a
project budget of crores of rupees. Most projects share common activities, including breaking
the project into easily manageable tasks, scheduling the tasks, communicating with the team,
and tracking the tasks as work progresses.
Cooling tower is one of the complex project in which various activities involves, so more
manpower require than other smaller project of construction. Some activities are critical
which takes more time so we should do proper planning and scheduling to avoid it and make
work faster.
Project Description
To meet the power demands due to TATA STEEL modernisation programme, TPC have
already installed and commissioned one unit of 67.5 MW and three unit of 120MW last unit
was commissioned in October 2005. Power from these units is being fed to TATA STEEL
grid which in turn supplies to steel plant, cement plant, TATA MOTORS, Tinplate co. &
Jamshedpur city. With the anticipated growth, a power deficit of 113.5 MW for Jamshedpur
network by the year 2008-09 is estimated requiring addition of one more unit of 120MW
rating coal based thermal power plant.
Project location-
The 5th unit is in the vacant land available within the existing premises of jojobera power
plant boundary besides availability of coal and water, evacuation of power, features of main
plant equipment including cooling water system, coal and ash handling systems, electrical
systems. Modification to be carried out, environmental aspects, estimates of project cost,
schedule for project implementation and cost generation.
3
NICMAR
Site Topography and Grade Level-
The site for the proposed unit is situated in filled up area covered by slag fill. The ground
level of the proposed site varies from RL 180m to RL 170m. The grade level of the existing
120MW units is at EL 180m. Space available for proposed unit no.5 is almost filled with slag
during construction of unit no 1 to 4.
Major Building and Structures
Station building: general arrangement
1. Station building- The span of the turbine generator and auxiliary equipment bay
would be 24m and that of electrical bay would be 10.5m with the existing station
building of unit no.4. The length of the station building would be 67.5m consisting
of 9 bays of 7.5m.
2. TG bay would be serviced by three floors-
Ground floor-0.0m
Mezzanine floor-5.0m
Operating floor-10.5m
(TG bay-22m, electrical bay-32m)
3. The superstructure would be of structural steel framing with brickwork and pre-
coated metal sheet for side cladding and RCC floor slabs.
4. The turbine generator pedestal would be of reinforced concrete frame structure
and would be isolated from the building foundations and superstructure.
Steam Generator Area and Mill Bay
The mill bay would be would be of structural steel-framed construction, supporting
the steel bunkers. The 10.50m wide bay would have floor for the feeders and for the
trippers.
Chimney
Stack of 150m height from SG area grade level to match with the existing 120MW
units. The height takes into consideration the requirement of Indian Emission
Regulations.
Cooling water pump house
Pump house is provided for CW pumps. The CW pumps are located indoor. Each CW
pump would have an independent sump with provision for installation of stoppage
and coarse screens in the pump chamber.
4
NICMAR
Miscellaneous buildings
s.no Building/structure Sizes(m)LxBxD remarks
1. ESP control room 28x7x4.5 Single storey building. RCC
construction with brick wall for side
cladding. Roof shall be RCC
2. Air washer room 20x15x8
& 13x7.5x5.5
Single storey building at two
locations.Structuralsteelconstruction
with brick wall for side cladding. Roof
shall be of RCC.
3. Fuel oil pump
house
6x6.5x4.5 Extension of existing pump house by
two bays.
4. D.G house 15x7.5x11 Extension of existing DG house by
one bay.
5. Ash slurry sump
and ash slurry pump
house for bottom
ash and fly
ash(common for
unit#4&5)
50x12x7.5 Single storey building. Structural steel
construction with RCC roofing and
brick wall for side cladding.
6. 132kv switchyard
control room
12x6x10 Extension of existing control room.
7. 220kv switchyard
control room
20x13.5x5 Existing building to be demolished
and new building to be constructed.
8. Clarified water
storage tank
25x25x5 3000cu.m capacity CLWST
9. Silo 7.5m diameter 650 tonnes capacity.
5
NICMAR
Cooling Tower for 120MW jojobera thermal power plant
The use of cooling tower is to cool the water in water circulating system. It has two types
induced draft cooling tower and natural draft cooling tower. The above figure shows IDCT
(induced draft cooling tower).
For the above project of cooling tower following are the project details….
Client---Tata Power.
Contractor—Paharpur Cooling Tower.
Number of Cell—5Nos
Contractor Type—EPC (Turnkey)
Project Cost—2cr approx
6
NICMAR
Cooling Tower, CT-5
Capacity: 210m3/hr.
Hot water inlet temp. : 47°C
Cold water outlet temp. : 32°C
Wet bulb temp. : 28°C,
No. of cells: 5
About Paharpur-- Paharpur does not rest r ic t i tse l f to only manufactur ing and
supplying cool ing towers , but bel ieves in the concept of turnkey
responsibi l i ty including t ransport ing to s i te , erect ion, commissioning and
test ing of complete cool ing towers . In the case of concrete cool ing towers
the c ivi l work is undertaken by Paharpur on i ts own. They have a ful l
f ledged civi l design and construct ion department with highly t ra ined and
experienced civi l engineers . They also have experienced personnel in
shipping and erect ion departments .
7
NICMAR
List of Activities: In order to construct the cooling tower, a series of activities will need
to be undertaken. The following activities are part of the project scope:
Civil Work
EXCAVATION
PCC FOR CW BASIN
RCC FOR CW BASIN
CW BASIN WALL INCL. COLUMN
BEAM AT IST LEVEL
UP TO FILL LEVEL
FILL TO ELIMINATOR
ELIM. TO FAN DECK LEVEL
FAN DECK SLAB
FAN CYLINDER
PRE CAST WORKS
APPRON
Mechanical & Electrical work
INTERNAL BITUMIN PAINTING
H.W.PIPING
HAND RAILING
PVC FILL ERECTION
H.W.DISTRIBUTION
ELIMINATOR ERECTION
EQUIPMENT ERECTION
EQUIPMENT EARTHING
CABLE TRAY ERECTION
SLIDE GATE ERECTION
SLUICE GATE ERECTION
BUTTERFLY VALVE ERECTION
TRIAL RUN
COMMISSIONING
Technical Features
8
NICMAR
As per above activities the technical features are as below—
EXCAVATIONS—For excavation purpose excavators are used like Tata Hitachi, JCB are
leading company for this work.
Tata Hitachi--Excavator
PCC FOR CW BASIN—M10 grade of concrete had used for PCC work. Pcc has done only
for surface level purpose of further project work. Transit mixture is useful for concrete
mixing purpose.
9
NICMAR
RCC FOR CW BASIN—M30 grade of concrete has used for RCC work and reinforcement
steel was CRS (corrosion resistive steel). Batching plant was used for mixing purpose of
aggregates and cement. Vibrators were used for compaction purpose and for transporting of
concrete transit mixture and concrete pump were used.
CW BASIN WALL INCL. COLUMN—MS steel were used for shuttering or form work.
Jack and U jack were also used for supporting to column and basin wall’s shuttering.
BEAM AT IST LEVEL & UP TO FILL LEVEL—Tower crane is used for lifting the
materials at high elevation. Concrete has transported through concrete pump, it has no any
problem to carry the concrete till hight of 20m.
PRE CAST WORKS— All necessary beams were cast at ground with precise way and after
(28days) cured it properly, it was lifted at elevated position as per drawing. Again crane was
used for lifting the beams to required position of the structure.
H.W.PIPING—
Hot Water Piping (MS-Steel)
10
NICMAR
TEST OF CONCRETE—before placing of concrete we should do slump test for checking
the workability. Compressive strength should be checked by cube test and by use of
compressive strength machine. We should check for 7days and 28days cube sample of
15x15cmm size.
Cube sample Compressive strength machine
DATA COLLECTION—Calender-CT-calendar assign as project calendar for the cooling tower schedule.Start date- 28/02/2008Finish date-19/03/2009 before levelling of the resources.
Notes—notes are provided in various activities if required.
11
NICMAR
Various activity and Duration
Task name %completion days Start day End day
Resource Allocation:
12
NICMAR
Resource name Type initial Group max unit std.rate over time cost/use
Conclusion:
Microsoft Project is used for planning, scheduling and tracking the project. The critical path
of the project is found out by the software and it can be updated whenever necessary. The
resources available can be allocated depending upon the criticality of the activity. It keeps a
record of all the resources involved in the project and any over allocation and under
allocation is determined by the software.
During this project we learned a lot about several aspects of project management. Some
aspects are the overall planning process, the impact of certain planning decisions,
implementation principles, and working with MS-project. Furthermore, we gained insight in
the subsidy process involved with technical projects. Specifically, subsidies for energy
related projects and projects that concern developing countries. This made this project very
interesting and useful.
13