22 Cost Estimating for Turnarounds

Embed Size (px)

Citation preview

  • 8/11/2019 22 Cost Estimating for Turnarounds

    1/8

    Cost estimating for turnarounds

    Turnarounds are major eventsfor re neries and other petro -chemical facilities. Theytypically cost signi cant sums ofoperational expense (opex) and capi -tal expense (capex) money to

    execute. They cause lost opportunitycost through lost production whilethe facility is shut down. If poorlymanaged, turnarounds offer signi -cant risk of accidents. If poorlyexecuted, they can also be the causeof signi cant production disruptionafter startup, due to leaks and otherproduction trips. Hence, there is apotential to save signi cant sums ofmoney, by ensuring turnarounds arerun correctly.

    However, despite the large poten -tial for saving money, there has,until recently, been very little focusin the turnaround world on makingsure turnarounds are run cost ef -ciently or on nding ways toimprove cost estimating and execu -tion skills. In the past seven to eightyears, this attitude has begun tochange and turnaround teams are beginning to look at how they canimprove. One potentially rich sourceof ideas on how to improve is forthe turnaround teams to examinehow their capital project brethrenestimate and execute projects. In thecapital project world, the potentialfor leaving money on the tabledue to poor project estimating andexecution has meant that decades oftime and effort have been spent, andcontinue to be spent, on developingtechniques to ensure that estimationand execution is carried outef ciently.

    This article focuses on cost estima -tion. It does not presume to provideall the answers on how to improve

    C st stim t s f y tu u s c l ck ccu cy, but l ss s lf m c pit l p j ct stim ti g c ul imp v m tt s

    Gordon LawrenCe Asset Performance Networks

    turnaround cost estimates. Rather, itattempts to lay the groundwork fora discussion on how to improve costestimating in process facility turna -rounds. It highlights the point thatcost estimating in the turnaround

    world is currently not very accurate.It then goes on to look at ideas onhow to improve cost estimate accu -racy, by looking at ideas that might be adapted from the capital projectworld. In particular, it looks at thestage gate approval system, thedevelopment of scope and estimate bases for different levels of estimateaccuracy, and at the development ofallowances for known unknownsand contingency for unknown

    unknowns. Finally, it makes somesuggestions for the next steps indeveloping better turnaround costestimates.

    wh t is p c ss i ust ytu u ?A turnaround (in the context of theprocess industries) is de ned by theAmerican Petroleum Institute as aplanned, periodic shutdown (total orpartial) of a... process unit or plantto perform maintenance, overhauland repair operations and to inspect,test and replace process materialsand equipment. 1 Re neries andother petrochemical facilities thatrun on a continuous rather than a batch production cycle must, everyfew years, shut down operations toprovide access to the productionunits in order that essential mainte -nance, modi cation and inspectionwork can be carried out that couldnot be done while the units are in

    operation.Turnarounds are events that areplanned well in advance and

    typically take place on a four-to-sixyear cycle. The length of a typicalturnaround execution phase (ie, theperiod when the facility is shutdown and hydrocarbon free) isusually around three-to- ve weeks.

    The scope of a turnaround typi -cally includes: Inspection of equipment tocompany regulations or governmen -tal rules Inspection of pipework for corro -sion and erosion damage, bothinternal (process weak points) andexternal (corrosion under insulation,or CUI) Cleaning, repair and maintenanceof equipment, pipework and instru -

    mentation (pulling and cleaning heatexchanger tube bundles, repairingleaks in pipework or checking ofpressure relief valves) Minor upgrades and modi cationsto the facilities (items controlledunder the management of change[MoC] procedures) Tie-ins for capital projects.

    Hist ic lly p stim ti x cuti f ci cy

    Historically, there was a tendencyamong operating companies to viewturnarounds as an inevitable andnecessary evil, and to accept thatthey would cost what they costand take as long as they take.However, in recent years, there has been a growing recognition that thisattitude leaves money on the tablein the form of the opportunity costof lost production while the facilityis shut down for longer than neces -sary; and unnecessarily excessive

    expenditure of money during theturnaround, through running theturnaround inef ciently.

    www.eptq.com PTQ Q1 2012 33

    Reprinted fromPetroleum Technology QuarterlyQ1 2012www.eptq.com

  • 8/11/2019 22 Cost Estimating for Turnarounds

    2/8

    www.eptq.com PTQ Q1 2012 35

    results in a 50% accuracy estimate,the following conceptual designstage results in a 30% estimate, andthe nal basic design stage results ina 10% estimate. Hence, the focus ofthe stage is in developing a scope basis to meet the estimate basisrequirements for the level of accu -racy intended The project cannot proceed to thenext stage without rst goingthrough a stage gate review to checkwhether it has achieved the requiredscope and estimate basis Full funding of the project isusually only received at the end ofthe third, basic design phase.

    The focus, therefore, in the capitalproject world is on calculating Howmuch money do we need in order tocarry out this scope?.

    Tu u sIn the turnaround world, there has been a movement in recent yearstowards a form of stage gated

    approach, in an attempt to improvefront-end de nition. However, thesystem is not yet as clearly de nedas in the capital project world.

    There are some key differences inthe way the approach is applied.The length of each stage is (more orless) xed, based on the amount oftime remaining until the turnaround

    In order to improve turnaroundef ciency, there is a need to examinethe estimation of costs for turna -rounds, the estimation of scheduletime, and the ef ciency of planningand execution of the turnaround.This article focuses on the rst ofthose three areas, the estimation ofcosts.

    accu cy f tu u c ststim t s

    A cost estimate needs to be accuratein order to provide managementwith the information needed todecide how to proceed, to allowcash ow planning and to aid in

    rm control of expenditure.In a survey of conference partici -

    pants at the Turnaround IndustryNetworking Conference (TINC)

    Europe, held in March 2011 inAmsterdam, The Netherlands, 2 83%of respondents said that their turna -round control budget was intendedto be a 10% estimate (see Figure 1). 3 The remaining 17% said that theirestimate was supposed to includesuf cient contingency/reserve thatit was a not to exceed number.None said that their budget wasintended to be a 30% estimate.

    We then took a sample of 93 recent

    turnarounds and in each casecompared the total actual cost forthe turnaround (including both capi -tal and maintenance work) with thecontrol budget. Figure 2 plots theover- or under-run of the actualcosts, expressed as a percentage ofthe control budget. It shows themean (the horizontal bar) and 80%con dence range (the vertical bar) ofthe results in our sample set andcompares it to the results we wouldhave expected if the cost estimatestruly were 10%, or if they were30%.

    Based on the results shown inFigure 2, we can say that turnaroundcost budgets tend, on average, tounder-estimate the actual cost byaround 16% (the distance of themean bar from the 100% point)and the budgets themselves show avariability of closer to 30% accu -racy than their purported 10%accuracy (the vertical line shows the

    80% con dence range around themean).Clearly, there is an opportunity to

    improve cost estimating accuracy inturnarounds.

    C mp i g c pit l p j cts ithtu u sCost estimating of capital projects inthe process industries has gonethrough a number of improvementsover the years. It may well be thatsome of the lessons and devicesused in capital projects can providea basis from which to develop asystem for better turnaroundestimates.

    St g g t sC pit l p j ctsIn the capital project world, it is nowgenerally accepted that front-endde nition is the key to a successfulproject. In order to achieve goodfront-end de nition, capital projectteams have largely moved toward astage gated approach, whereby thedesign proceeds through threedistinct stages of ever-improving

    scope de nition.4

    Key points are: The length of each stage is a func -tion of the work required to becompleted in that stage The culmination of each stage is acost estimate, with the estimatesgetting more accurate with eachsucceeding stage. Generally speak -ing, the feasibility stage of a project

    120

    160

    170

    150140

    130

    110

    100

    90

    80

    70

    Theoretical range

    10% estimate

    Theoretical range

    30% estimate

    Turnaround

    actual costs

    P90

    P10

    Mean

    N=93

    A c t u a l

    t u r n a r o u n

    d c o s t s a s a

    p r o p o r

    t i o n o f

    t h e

    b u

    d g e

    t , %

    60

    Figu 2Accuracy of turnaround control estimates: expectation and reality

    Figu 1 Expectation of accuracy in turnaround control estimates: vox populi

  • 8/11/2019 22 Cost Estimating for Turnarounds

    3/8

    starts. Generally, by about 1412months before the turnaround, the

    rst review of status will be held. Asecond review may be held aroundnine-to-six months before and thelast review about three-to-twomonths before.

    The stages are not focused onscope de nition for cost estimatesof a given accuracy. Instead of theissuance of an estimate marking theend of a stage, the ends of thesestages are delineated by their prox -imity to the start date of theturnaround. There are guidelineson what level of scope de nitionshould be expected at each of theseturnaround stage gates, but theseguidelines are not as universallyadopted as their counterparts areon capital projects.

    By the nature of a turnaround,refusing to let a turnaround teamproceed to the next stage because itis insuf ciently prepared at the timeof the stage gate review is notusually a feasible option. The budgettends to be xed back at the 30%or even 50% estimate stage.Consequently, with turnarounds, thefocus tends to be on How muchscope can we carry out for thisamount of money? rather than the

    capital project paradigm of Howmuch money do we need in order tocarry out this scope?.

    Sc p b sis stim t b sisIn this section, we make a distinc -tion between the scope basis (thelevel of de nition of the designdeliverables and documents) andthe estimate basis (the methodologyused to calculate costs, based onthose deliverables).

    C pit l p j ctsIn the world of process industrycapital projects, the scope basisand the estimate basis are bothrelatively well de ned for variouslevels of estimate accuracy, from50% down to 10% or better. Onewell-known example of where thisis documented is AACE InternationalRecommended Practice No. 18R-97. 5 Lawrence also lists typical require -ments. 4 (Table 1 and Table 2 are

    adapted from Lawrence, 2008.) Inaddition, it is accepted practice todocument the cost estimate in a

    www.eptq.com PTQ Q1 2012 37

    written basis of estimatedocument.

    e ly stim t : 50% ugh fm g ituIn capital projects, the rst cost

    estimates are usually highly deter -ministic, using high-level factoringmethods rather than the stochastic

    approach of calculating from the bottom up. The cost of a facility istypically factored off such details as,for example, the production capacityof the new facility, with adjustmentsmade for in ation and location. Such

    estimates generally have little interms of scope basis, often merelyan outline of the facility capacity

    T bl 1

    50% ROMestimate

    General project data

    Engineering deliverables

    Project scopedescription

    Facility capacity

    Facility location

    Ground surveys

    Projectexecution plan

    Contract strategy

    Project schedule

    Cost estimating plan

    Plot plans

    Process flow diagrams

    Utility flow diagrams

    Project execution plan

    P&IDs

    Heat and materialbalances

    Processequipment list

    Utility equipment list

    Electrical single linediagram

    Process engineersequipment datasheets

    Mechanical engineers

    equipment datasheetsEquipment generalarrangement

    Block flow diagrams

    30% ROMestimate

    10%control

    estimate

    General

    General

    None

    None

    None

    Outline

    None

    None

    None

    NoneNone

    None

    None

    None

    None

    None

    None

    None

    None

    Assumed

    Assumed

    Level Imilestones

    Defined

    Defined

    Defined

    Defined

    Defined Defined

    Defined

    Level III detailedresourceloaded

    schedule

    Defined

    Defined

    Defined

    Defined

    Specific

    Complete

    Complete

    Complete

    Complete

    Complete

    Complete

    Complete

    Complete

    Complete

    Complete

    Complete

    Complete

    Complete

    Complete

    Complete

    Specific

    Preliminary

    Preliminary

    Preliminary

    Preliminary

    Preliminary

    Preliminary

    Preliminary

    Preliminary

    Preliminary

    Preliminary

    Preliminary

    Preliminary

    Level IIpreliminary

  • 8/11/2019 22 Cost Estimating for Turnarounds

    4/8

    the previous turnaround scope, andthe estimate basis uses that historicaltotal cost.

    C c ptu l stim t : 30%On turnarounds, teams appear toaim to have the overall scope frozenand challenged by this point.However, this has not always beenachieved. In terms of deliverabledocuments for the scope basis, themechanical workpacks are usuallydeveloped. The estimate basis is amix of deterministic and stochastic,as the mechanical work packs arecosted (in-house) in some detail, butthe other work (electrical, instru -mentation scaffolding, insulation,and so on) is usually factored off themechanical costs, using historicalfactors.

    auth is ti /c t l stim t : 10%Some turnaround teams do nowhave all discipline scopes developedand externally costed. However, inour experience, the number of teamsthat take their estimates to this levelof detail are relatively few, despitethe fact that most teams claim theircontrol estimates are 10% or better.

    w k b k st uctu

    C pit l p j ctsAll companies have their own varia -tions on how they prefer to breakdown costs within the estimate.Indeed, the work breakdown struc -ture (WBS) may differ slightly, fromproject to project, depending on thescope. Nevertheless, at a high level,there is a measure of agreementacross the industry on how to breakdown capital project costs. The breakdown tends to be as shown inTable 3.

    Tu u sAt present, there is no clear, commonagreement across the process indus -tries on a high-level WBS forturnaround costs. Most turnaroundteams split costs into direct costs costs that can be speci cally assignedto a cost object, such as an item ofexisting plant and indirect costs costs that cannot easily be directlyattributed to a cost object. However,

    the de nition of what should beconsidered direct or indirect costvaries from site to site (presumably

    38 PTQ Q1 2012 www.eptq.com

    required. The estimate basis relieson historical data of the total cost ofthe entire facilities rather thandetailed cost data.

    C c ptu l stim t : 30%In capital projects, a considerableamount of work would be completedon the scope basis, coming close tofreezing the overall scope and devel -

    oping many of the design drawings by the time this estimate wasprepared.

    The estimate basis would havemoved from a high-level, determin -istic estimate to a mix of thestochastic and deterministic, and theteam moves towards Lang factors orother, similar methods to calculatethe project cost (factoring off oneelement of the project scope, mosttypically the equipment cost).

    auth is ti /c t l stim t : 10%By this stage, the scope basis on acapital project is generally verydetailed, with completed P&IDs,order speci cations for major equip -ment and so forth. The estimate basis is now stochastic, built bottomup from the material take-offs andusing market cost data rather thanhistorical database information.

    Tu u s

    There appears to be no documentequivalent to AACE InternationalRecommended Practice No. 18R-97

    for process industry turnarounds. Inthe absence of such a document, wehave informally surveyed a numberof turnarounds to look at the vari -ous scope and estimate bases used by the turnaround teams to developestimates of nominal accuracies of50%, 30% and 10%.

    The rst problem we have encoun -tered is that there is some variation

    in the methods used. Second, theconcept of writing down a detailedbasis of estimate document issomething that still has to take rootin the turnaround world; hence,understanding how each estimatewas developed is dif cult. (We wereoccasionally given documentsdescribed by the team as the basisof estimate, but these were gener -ally extremely simple, high-levelnotes on the estimate spreadsheetitself rather than a formal anddetailed document.) Nevertheless,we have attempted to provide ageneral overview of the methods being used by turnaround teams forthe various estimates.

    e ly stim t : 50% ugh f m g ituThe early estimate is frequentlymerely the cost of the last turna -round, adjusted for in ation, withperhaps an educated guess as to

    how the scope may have grown orshrunk since the last turnaround.The scope basis is therefore merely

    T bl 2

    50% ROMestimate

    30% estimate 10% controlestimate

  • 8/11/2019 22 Cost Estimating for Turnarounds

    5/8

    because of different internal account -ing practices).

    The costs of owner supervision aregenerally agreed to be indirect, sinceat any hour of the day a team could be supervising work on a range ofexisting plant areas. Contractedlabour on tasks that can be assignedto speci c existing plant items isgenerally categorised as direct cost.Furthermore, tracking this cost byplant unit/area and by equipmentclass/type and by equipmentnumber is relatively common.

    However, costs such as rentedequipment (cranes, heat exchanger bundle pullers, and so on) are lessconsistently assigned to either director indirect categories, presumably because such items can only some -times be attributed to a speci c plant

    item (for instance, if a crane is onlyneeded to work on a speci c item).

    Theoretically, it should be possibleto assign bulk material (pipe, valves,for instance) to speci c plant itemsand hence categorise the material asdirect. However, this is not alwaysdone. One would logically expectconsumable materials such as weld -ing rods to be indirect costs becauseof the dif culty of assigning them tospeci c plant items. However, the

    situation can be clouded by the fact

    40 PTQ Q1 2012 www.eptq.com

    T bl 3

    Home Office

    Field

    Capital

    Expense

    Allowances forunknown unknowns

    Allowances forknown unknowns

    Direct

    Design

    Engineering

    Equipment

    Contingency

    Commissioning

    Operations staff

    Bulk materials

    Construction labour

    Constructionmanagement/supervision

    Temporary facilities,craneage, scaffold, etc

    Designallowances

    on eachline item

    Escalationallowances

    on eachline item

    Projectmanagement/supervision

    Indirect

    that consumables and bulk materialsoccasionally are not separated.

    all c s f u c t i tyAny cost estimate, by nature of it being an estimate, requires funds forthe uncertain elements of the scope.These uncertain elements can bedivided into known unknownsand unknown unknowns. Theknown unknowns are allowancesfor items or quantities that the esti -mator knows, from historicalevidence, will be needed in a speci cline item of the estimate. Theunknown unknowns are the itemsor quantities that were under-esti -mated or completely overlooked inthe estimate. The estimator does notknow exactly in which line item thefunds will be needed, but history

    tells the estimator that some fundswill be needed to bring the estimateto the P50 point. These unknownunknowns are contingency funds.The need for contingency is a hotlydebated subject, but has beendiscussed elsewhere 6 and we do notpropose to explore this topic here.

    C pit l p j ctsK u k sThe known unknowns in capital

    projects take the form of design

    allowances allocated to each lineitem for the known unknown ofthat line item (for instance, wastagein the piping material take-off,design development in equipment).

    The amount of design allowanceto include is usually determinedthrough expert judgment based onhistorical data.

    U k u k sContingency is for the unknownunknowns in the estimate (forinstance, it is discovered duringconstruction that the need for anelectrical transformer was over -looked in the design).

    As discussed by Burroughs & Juntima, 7 the amount of contingencyto include is typically calculated inone of four ways: As a predetermined percentage(of the base estimate) Through expert judgment (gutfeeling/experience) based on histori -cal data Through a Monte Carlo-typereview of the cost effect of expectedrisks Through use of a regressionmodel, based on historical data.

    Tu u s

    In the case of funds for uncertainty,there is a little more general agree -ment than perhaps in other areas ofestimating for turnarounds, in asmuch as it is generally accepted thatfunds are needed for unknownitems.

    K u k sIn turnarounds, the knownunknowns are (a) emerging work(work to repair items that have broken/failed between the comple -tion of the estimate and the start ofthe turnaround); and (b) discoverywork (repair work that is discov -ered during the turnaround onceequipment or pipework is openedup for detailed inspection).

    In common with the design allow -ances on capital projects, estimatesof likely emerging work and discov -ery work should (in theory) becalculable and assigned to speci cestimate line items. (For instance, we

    can expect other X valves to fail between now and the shutdown, or based on past experience we should

  • 8/11/2019 22 Cost Estimating for Turnarounds

    6/8

    expect that the trays in column Zwill be discovered to be damagedwhen we open it up.)

    However, what we have observedis that very often such items are notreported in the estimate to this levelof detail. Instead, they tend to belisted as single line items on theirown. In addition, anecdotally, weobserve that very often the discov -ery work in particular appears to beunderestimated an optimismabout what is likely to be foundseeming to prevail.

    The amount of emerging workallowance and discovery workallowance appears to be calculatedon the basis of experience fromprevious turnarounds or from inti -mate knowledge of the state of thefacility. But when it is based on

    experience of previous turnarounds,this experience is rarely backed up by hard numbers, showing whatwas spent in previous turnaroundsas a percentage of the base scopecost.

    U k u k sIn turnarounds, just as in capitalprojects, a contingency for the itemsthat were overlooked or completelyunforeseen at the time of the esti -

    mate issue is required. (For instance,money was included in the discov -ery work allowance to spend threedays repairing trays in column X, because the column was old andwas operating at low throughput.However, it took two days longerthan expected to repair the trays incolumn X. That extra two days costcomes out of contingency.)

    Whereas in capital projects contin -gency is calculated on the basis ofone of four methods, each of whichhas at least some logical foundationto it, in turnarounds we observe thatcontingency often appears to becalculated simply as the difference between the current base estimateplus discovery and emerging workallowances and the original, roughestimate quoted to management(assuming the rough estimate to bea higher number!).

    Qu ti c ti f tu u

    ll c sWe then looked further into howmuch allowance for uncertainty was

    included by turnaround estimators

    and how much was actually used.

    H much is i clu ?The rst problem that we encoun -tered in this study was that whilemost turnaround teams recognisethe three main areas of uncon rmedscope that need funding as being (1)emerging work, (2) discovery workand (3) contingency for the unfore -seen, few teams clearly differentiate between them in their estimates.

    Indeed, in a survey that we carriedout, out of 216 turnarounds, only 34(or 16%) could give a clear differen -tiation in their cost estimate betweenthese three areas and the mainestimate.

    Nevertheless, from the data gath -ered we are able to show (see Figure3) that teams typically include a total

    of just under 13% of the base esti -

    mate (where base estimate = thetotal cost estimate before the threeuncertainty allowances are included)as a total of all three allowanceamounts.

    That funding breaks down in turninto an average of 16% for emergingwork, 38% for discovery and 46%for contingency (see Figure 4).

    H much is sp t?We then attempted to look at how

    much in each category is typicallyconsumed. From this information, wehoped to begin developing guidelineson calculating how much should beincluded in an estimate. However,we found that although some teamshave begun to track the consumptionof the three elements in their actualcosts this practice is still immaturewithin the turnaround community.

    Without historical data on actualexpenditure in these three catego -ries, it is impossible to close theloop and begin developing guide -lines on how much should beincluded in each category in anestimate.

    C clusi sTh p bl mCurrently, turnaround cost estimatesare inaccurate in that, on average,turnaround costs overrun their esti -mates. They are also highlyunpredictable in the level of their

    inaccuracy (that is, the overrundoes not remain within the claimed10% accuracy of most estimates).

    16

    22

    20

    18

    14

    12

    10

    8

    6

    T o t a l a l l o w a n c e s a s p r o p o r

    t i o n

    o f t h e

    b a s e e s t

    i m a t e ,

    %

    Emerging work + discovery work+ contingency

    4

    +1SD

    1SD

    Mean

    N=38

    Figu 3Uncertainty allowance included in estimate

    Contingency38%

    Emergingwork 16%

    Discoverywork 38%

    N=34

    Figu 4 Breakdown of uncertaintyallowance into emerging, discovery andcontingency

    www.eptq.com PTQ Q1 2012 41

  • 8/11/2019 22 Cost Estimating for Turnarounds

    7/8

    Furthermore, there is no clearagreement on the de nition ofwhat information a cost estimateshould be based upon in order toallow it to be de ned as a 10%estimate.

    There are no guidelines on how tocalculate uncertainty allowances foremerging work, discovery work andcontingency. Nor are many teamsgathering the actual cost expendi -ture data that would allow suchguidelines to be developed in thefuture.

    L i g f m c pit l p j ctsThe capital project world historicallyhad similar problems with cost esti -mating. Over the years, it hasimproved through: Tying estimates to stage gates Clearly de ning the scope basisand estimate basis required for acertain level of estimate accuracy Using similar work breakdownstructures, allowing comparison benchmarking of data Gathering data on allowances foruncertainty and developing logicalmethodologies for estimating thoseallowances.

    The turnaround world has already begun to learn from capital projects

    by copying the stage gate approach.There seems to be little reason tosuppose that turnaround teamscannot continue to learn from capitalprojects in order to develop turna -round-speci c standards for scope basis, estimate basis and calculationof allowances.

    r c mm ti s f imm i tcti

    If the estimation of turnarounds isto become more accurate andpredictable, we recommend that, asa rst step, a series of actions should be adopted within the turnaroundcommunity.

    d th sc p stim t b sisThere should be wide agreement onwhat the scope and estimate basisis for calling an estimate 50%, 30%or 10% accurate. The capital projectscommunity has such agreement indocuments referred to earlier.

    Suggested outline versions for turn -arounds are given in Tables 4and 5, respectively.T bl 4

    42 PTQ Q1 2012 www.eptq.com

    50% ROMestimate

    General turnaround scope data

    Engineering deliverables

    30% ROMestimate

    10%control

    estimate

    Equipment count

    Turnaround premises

    Risk Based Inspection(RBI) data

    Maintenance turnaroundbacklog

    Listing littledefinition

    Baseline

    no markup

    None

    None

    None

    NoneNone

    None

    Originalbaseline

    None

    Listing highlevel, based

    on assetmanagement

    strategy

    95%complete

    99%complete

    60-70%complete

    99%complete

    Hazard and Operabilitystudy (HAZOP)

    Listing highlevel

    60-70%complete

    100%complete

    Plant engineering designchanges (expense)

    Listing notall inclusive

    60-80%complete

    100%complete

    Leak Detection AndRepair (LDAR)

    Listing preliminary

    Listing preliminary

    Partial

    markup

    Partial

    turnaroundmarkups

    Partial fornew capital

    Completelisting

    Previous turnaroundscope

    Plot plans

    logistics markups

    Plant engineeringdesign packages

    Major capital projectengineering design

    Flare minimisation plan

    Heat transfer data

    Utility plan

    Oils plan

    P&ID markups

    Process engineeringdesign basis for plant

    engineering capital

    Turnaround boundaries

    Listing 90%Listing 90%Listing 90%

    Process Hazard Analysis(PHA)

    Listing highlevel

    60-70%complete

    100%complete

    Management Of Change(MOC) design changes

    40-60%complete

    100%complete

    Complete

    Complete

    Complete

    Complete

    Complete

    Complete

    Complete

    Complete

    Preliminary

    100%complete

    100%complete

    80-90%complete

    100%complete

    Preliminary

    80-90%complete

    100%complete

    Capital projects 80-90%complete

    100%complete

    Listing

    Listing

    Listing variousstages

    Partial

    Partial

    Partial

    None CompletePartial

    None CompletePartial

    Preliminary

    Partial

    NoneStartup procedures

    maintenance(new equipment)

    CompletePartial

    Baseline none for new

    capital

    Original EquipmentManufacturer (OEM)

    specifications & drawingsComplete

    Preliminary

    Plant projects

  • 8/11/2019 22 Cost Estimating for Turnarounds

    8/8

    St is th wBSMove towards a common standardlayout for cost estimates. The capitalprojects community has such astandard (see Table 3). A suggestedoutline version for turnarounds isshown in Table 6.

    T ck th u c t i ty ll c sIf the turnaround community isever to develop even rudimentaryrules of thumb for estimatingemerging work, discovery workand contingency for the unforeseen,it must begin to track expenditurein these areas. This will require tworesponses from the community: awillingness to differentiate clearlythe three categories in cost esti -mates; and a willingness toaccurately track actual expenditure

    from these three categories duringa turnaround.

    Ti th stim t s t th st g g t sIn the world of capital projects, thestage gate culminates in a cost esti -mate. Currently, the typical reviewstages for preparation and planningof a turnaround are not tied to a costestimate. Tying the estimate andstage gate together could improvereview of planning and preparation

    progress.r c mm ti s f l g -t m

    xt st psThis article covers only the rst stepsin improving the accuracy andpredictability of turnaround costestimates. Further steps need to betaken. Once there is common agree -ment on the minimum standard ofscope basis and estimate basis forturnaround estimates, and onceturnaround teams begin gatheringactual uncertainty allowance data,the community will then be in aposition to begin developing logicalmethodologies for calculating moreaccurately the required level ofallowance for uncertainty in emerg -ing work, discovery work andcontingency for each turnaround.

    ack l g m tsThe author would like to acknowledge theencouragement offered during the preparation

    of this article by Bobby Vichich, Vice President,Turnarounds, at Asset Performance Networks,as well as the invaluable advice (particularly,

    but not only, relating to Table 4) of John Casper,Senior Consultant and Subject Matter Expertfor Turnarounds and Capital Projects, at AssetPerformance Networks.

    r f c s1 http://www.api.org/aboutoilgas/sectors/re ning/re nery-turnaround.cfm.2 http://ap-networks.com/latest-news/tinc-europe-2011-summary.html.3 We are very aware of the fact that in recent years the preference within project costestimating circles is not to talk of a typical10% or 30% estimate, but rather to talkof classes of estimates. This is because ofthe need to recognise that for the same levelof scope de nition, two projects could havedifferent levels of estimate accuracy becauseof the inherent risks in their characteristics. Forexample, a new technology project probablycarries more risk than a similar-sized projectexpanding an existing plant. However, the

    turnaround world has not yet reached thatlevel of sophistication. Hence, for the survey,we used terms that are readily recognised, suchas 10% estimate.

    T bl 6

    4 Lawrence G R, Stage gated approval processes a practical way to develop and lter capitalinvestment ideas, Pharmaceutical Engineering,vol 20, No 2, March/April 2008.5 AACE International Recommended PracticeNo. 18R-97; cost estimate classi cation system,as applied in engineering, procurement, andconstruction for the process industries.6 Lawrence G R, The use and misuse ofcontingency or why cutting contingencymakes projects more expensive, not less.Pharmaceutical Engineering , vol 27, No 5, Sept/Oct 2007.7 Burroughs S E, Juntima G,Exploring Techniques for Contingency Setting , AACE InternationalTransactions, Washington DC, 2004.

    G L c is a Senior Consultant withAsset Performance Networks, Amsterdam.He holds a bachelors degree in chemicalengineering from Heriot-Watt University,Edinburgh, a masters in biochemical

    engineering from Birmingham University, andan MBA from Strathclyde University BusinessSchool, Glasgow.Email: [email protected]

    www.eptq.com PTQ Q1 2012 43

    Mechanicalwork

    Other disciplines

    Cost of the lastTA, adjusted for

    inflation

    Quantities formechanical workfrom workpacks,but then priced

    in-house

    Other disciplinesfactored frommechanical,

    based on history

    Quantities for alldisciplines

    calculated andpriced by

    contractors,based on

    workpacks

    50% ROMestimate

    30% ROMestimate

    10% controlestimate

    Home Office

    Field(during

    shutdownperiod)

    Allowances forunknown unknowns

    Allowances forknown unknowns

    Direct(broken down by

    unit/area, equipmenttype and equipment

    number

    Field (before theshutdown period)

    Emergingwork

    allowanceson each line

    item

    Discoverywork

    allowanceson each line

    itemIndirect

    Contingency

    Consumables

    Equipment

    Bulk materials

    Turnaround planningand preparation

    Turnaround fieldlabour

    Pre-turnaround fieldwork

    Equipment rental cranes, scaffold, etc

    Logistics, temporaryfacilities, etc.

    Turnaroundmanagement/ supervision

    Direct

    Indirect

    Maintenance

    Capital projects

    T bl 5