11
City of Seattle Pedestrian Advisory Board SPAB Briefing David Burgesser April 10, 2019 2020-2024 PMP Implementation Plan Update and Progress Report

2020-2024 PMP Implementation Plan Update and …...City of Seattle Pedestrian Advisory Board SPAB Briefing David Burgesser April 10, 2019 2020-2024 PMP Implementation Plan Update and

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 2020-2024 PMP Implementation Plan Update and …...City of Seattle Pedestrian Advisory Board SPAB Briefing David Burgesser April 10, 2019 2020-2024 PMP Implementation Plan Update and

City of SeattlePedestrian Advisory Board

SPAB BriefingDavid BurgesserApril 10, 2019

2020-2024 PMP Implementation Plan Update and Progress Report

Page 2: 2020-2024 PMP Implementation Plan Update and …...City of Seattle Pedestrian Advisory Board SPAB Briefing David Burgesser April 10, 2019 2020-2024 PMP Implementation Plan Update and

City of SeattlePedestrian Advisory Board

Presentation Overview

•PMP Background

• Implementation Plan Role

•Project Prioritization Process

•Progress Report

•Cost Effective Walkways

•Next Steps

Page 3: 2020-2024 PMP Implementation Plan Update and …...City of Seattle Pedestrian Advisory Board SPAB Briefing David Burgesser April 10, 2019 2020-2024 PMP Implementation Plan Update and

City of SeattlePedestrian Advisory Board

PMP Background

• Plan updated in 2017

• Vision: “Seattle is the most walkable and accessible city in the nation.”• Goals, objectives, strategies and actions to achieve vision

• Six performance measure to gauge progress

• Establishes new system for prioritizing ped investments• Priority Investment Network (PIN)

• Proximity to transit and schools

• Establishes base scoring using safety and health/equity factors

Page 4: 2020-2024 PMP Implementation Plan Update and …...City of Seattle Pedestrian Advisory Board SPAB Briefing David Burgesser April 10, 2019 2020-2024 PMP Implementation Plan Update and

City of SeattlePedestrian Advisory Board

Priority Investment Network

Page 5: 2020-2024 PMP Implementation Plan Update and …...City of Seattle Pedestrian Advisory Board SPAB Briefing David Burgesser April 10, 2019 2020-2024 PMP Implementation Plan Update and

City of SeattlePedestrian Advisory Board

Implementation Plan

• 5-year work plan and project list

• Project prioritization framework

• Progress report• Updated performance measures

• PMP strategy and action progress

• Project delivery updates

Page 6: 2020-2024 PMP Implementation Plan Update and …...City of Seattle Pedestrian Advisory Board SPAB Briefing David Burgesser April 10, 2019 2020-2024 PMP Implementation Plan Update and

City of SeattlePedestrian Advisory Board

Prioritization Process

Arterials Non-ArterialsSignalized

Intersections

Unsignalized

Intersections

Scoring Factors Points

Safety 60

Health/Equity 40

Age-Friendly 13

Urban Villages 15

Distance Score (Off-Street Only) 30

Scoring Factors Points

Safety 60

Health/Equity 40

Age-Friendly 13

BPSA 5

Crossing the

Roadway

Along the Roadway

Page 7: 2020-2024 PMP Implementation Plan Update and …...City of Seattle Pedestrian Advisory Board SPAB Briefing David Burgesser April 10, 2019 2020-2024 PMP Implementation Plan Update and

City of SeattlePedestrian Advisory Board

Progress Report and Highlights

• 2018 progress:• 34.75 blocks of new sidewalk

• 14.5 blocks cost effective

• 20.25 blocks traditional

• 13 crossing improvements

• 17.1 block equivalents of sidewalk repair

• Expansion of education and encouragement efforts to promote pedestrian safety

• Completed scoping for coordinated pedestrian wayfinding system

• Began implementation of Streets Illustrated pedestrian standards

Page 8: 2020-2024 PMP Implementation Plan Update and …...City of Seattle Pedestrian Advisory Board SPAB Briefing David Burgesser April 10, 2019 2020-2024 PMP Implementation Plan Update and

City of SeattlePedestrian Advisory Board

Cost Effective Walkways

S Wallace St b/w 59th Ave S and Dead End

3rd Ave NE b/w NE 97th St andNE 100th St

Terry Ave N b/w John St andThomas St

Page 9: 2020-2024 PMP Implementation Plan Update and …...City of Seattle Pedestrian Advisory Board SPAB Briefing David Burgesser April 10, 2019 2020-2024 PMP Implementation Plan Update and

City of SeattlePedestrian Advisory Board

Cost Effective Walkways

NE 110th St b/w 35th Ave NEand 36th Ave NE

S Byron St b/w MLK Jr Way Sand Rainier Ave S

Ashworth Ave N b/w N 122nd

St and N 125th St

Page 10: 2020-2024 PMP Implementation Plan Update and …...City of Seattle Pedestrian Advisory Board SPAB Briefing David Burgesser April 10, 2019 2020-2024 PMP Implementation Plan Update and

City of SeattlePedestrian Advisory Board

10

Date Activity/action

April 10, 2019 1st SPAB briefing

April-June 2019 Development of plan updates

June 2019 Provide draft project list and implementation plan to SPAB

July 10, 2019 2nd SPAB briefing

September 1, 2019 2020-2024 Implementation Plan due to Council

Next Steps

Page 11: 2020-2024 PMP Implementation Plan Update and …...City of Seattle Pedestrian Advisory Board SPAB Briefing David Burgesser April 10, 2019 2020-2024 PMP Implementation Plan Update and

City of SeattlePedestrian Advisory Board

Questions & Comments?

[email protected]| (206) 684-8058

http://www.seattle.gov/transportation/pedestrian_masterplan/

www.seattle.gov/transportation