- Proposal -

2019 BUSINESS PLAN

Mostar, June 2019

Page 2: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

2

CONTENTS

1. Introduction 4

2. ABOUT US 5

2.1. Vision................................................................................................................... 7

2.2. Mission ................................................................................................................ 7

2.3. Strategy ............................................................................................................... 7

3. Swot analysis 8

1. ORGANISATION OF BUSINESS OPERATIONS 10

4.1. CURRENT SITUATION ANALYSIS 11

2. ACTIVITY PLAN OF CONSTRUCTION OF MOTORWAY AND EXPRESS ROAD 14

5.1. SECTION SVILAJ – ODŽAK STAGE II ...................................................................... 20

5.2. SUBSECTION DRIVUŠA - KLOPČE ......................................................................... 20

5.3. SUBSECTION KLOPČE - DONJA GRAČANICA ( TUNNEL PEČUJ ) .............................. 21

5.4. SECTION BUNA - POČITELJ .................................................................................. 21

5.5. EXPRESS ROAD PRAČA – GORAŽDE ( STAGE I ) ................................................... 21

5.6. SUBSECTION VRACA (TUNNEL ZENICA) – DONJA GRAČANICA (TUNNEL PEČUJ) ...... 22

5.7. PUTNIKOVO BRDO – MEDAKOVO ........................................................................... 22

5.8. SECTION POPRIKUŠE – NEMILA ............................................................................ 22

5.9. SUBSECTION NEMILA – VRANDUK ........................................................................ 23

5.10. SUBSECTION VRANDUK - PONIRAK ..................................................................... 23

5.11. SUBSECTION PONIRAK – VRACA ( TUNEL ZENICA ) .............................................. 23

5.12. SECTION TARČIN - IVAN ..................................................................................... 23

5.13. TUNNEL PRENJ (STAGE I ) ................................................................................ 24

5.14. SECTION MOSTAR NORTH – MOSTAR JUG ........................................................... 24

5.15. SECTION MOSTAR SOUTH– KVANJ ................................................................... 25

5.16. SECTION KVANJ - BUNA (TUNNEL KVANJ ) ...................................................... 25

5.17. SECTION POČITELJ - ZVIROVIĆI ......................................................................... 25

5.18. EXPRESS ROAD LAŠVA – NEVIĆ POLJE ............................................................. 26

5.19. MOTORWAY TUZLA - ŽEPČE ............................................................................... 26

5.20. SARAJEVO BYPASS LOT 3B ................................................................................ 27

5.21. REGIONAL ROAD R425A ON THE SECTION TROMEĐA – ZVIROVIĆI ......................... 27

3. BUSINESS ACTIVITY PLAN 27

6.1. Expropriation of the land .................................................................................... 27

6.2. Designing Services ............................................................................................ 33

6.2.1. Designing services financed from own assets ................................................. 33

Page 3: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

3

6.2.2. Services of the designing of the motorway on Corridor Vc and which should be financed from IPA funds or from the assets of WBIF ............................................ 38

6.3. Construction plan ............................................................................................... 39

6.4. Supervision service plan .................................................................................... 48

6.4.1. Engagement of the consultants for the management design ........................... 49

6.5. Management and maintenance......................................................................... 50

6.5.1. Services in the domain of motorway maintenance .......................................... 50

6.5.2. Services in the domain of toll payment ............................................................ 53

6.5.3. Services in the domain of motorway management .......................................... 53

6.6. The other capital investments ........................................................................... 55

6.6.1. Capital investments in the domain of management, maintenance and toll payment ................................................................................................................... 55

6.6.2. Capital investments in the domain of IT .......................................................... 57

6.6.3. The other capital investments ......................................................................... 58

7.1. Revenues .......................................................................................................... 59

7.2. Operational expenditures ................................................................................... 60

7.3. The difference of revenues and expenditures - Financial result ......................... 64

7.4. Employment plan ......................................................................................... 64

8. PROJECTION OF THE FINANCING SOURCES - CREDITS AND NOTES 65

8.2. Review of the planned repayment by the credits ................................................ 67

8.3. Review of the credit obligations - interest ........................................................... 67

8.4. Summary review of the obligations by the credits .............................................. 69

Page 4: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

4

1. Introduction

Public enterprise Autoceste Federacije Bosne i Hercegovine limited liability company

Mostar (hereinafter: JP Autoceste) was registered with court in Mostar on 28 October, 2010

in accordance with the Law on Roads of Federation of Bosnia i Herzegovina ("Official

Gazette of FBiH", 12/10, 16/10 and 66/13), Law on enterprises ("Official Gazette of FBiH",

81/15) and Decision on status issues of Public enterprise Autoceste Federacije Bosne i

Hercegovine limited liability company Mostar made by the Government of Federation of

Bosnia and Herzegovina (Decision V number 593/10 dated 1 July, 2010) on session 149

held on 1 July, 2010 in Sarajevo.

The goal of 2019 Business plan is to determine basic strategic goals of business

operations in order to achieve the best results in infrastructure construction, management and

maintaining motorways and express roads. This Business Plan defines basic principles of

development and business activities of JP Autoceste in the following period are founded and

which refer to:

Business activities of the enterprise should be founded on economic principles

thanks to which long-term profitable business activities will be sustainable and

achieved;

Provide continuity of services of maintaining through their improvement and

upgrading;

Projecting and construction of motorway section lines for which there are

financial sources in order to imply the abovementioned through financial

effects, i.e. achievement of income from services from toll payment. Indirectly,

the impact of motorway will be visible within regional frameworks through better

traffic connection;

Resume activities related to finding optimal sources of income which will

enable the intensity of activities referring to making project documentation to be

increased, land expropriation and continuance of construction of motorway and

express road section lines;

Improve service provided to users through postpaid payment, introducing smart

cards and constant improvement of IT infrastructure in the part referring to

operative support and motorway maintaining;

Continue with activities referring to ensuring assets from different sources,

international credit assets and realisations from the budget of Federation of BiH

or from other sources with goal to build the motorways and express roads of

Federation of BiH more quickly.

All abovementioned activities require certain preconditions necessary for the

realization of this plan to be fulfilled. Taking into the consideration the undefined deadlines

ratification of debt contract with international financial institutions and increase of activities of

PE Autoceste in order to start preparation for construction of new section lines, all planned

business activities will be a subject of continuous monitoring of realisation by administration of

the enterprise. In accordance with the realisation of activities that are included in the Business

plan as well as potential deviation from them, PE Autoceste will consider and make a decision

on amendments of this plan during the year.

Page 5: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

5

2. ABOUT US

Activities of PE Autoceste as well as works and tasks on motorways and express

roads in Federation of BiH are defined by Articles of Association including the following:

Preparation of long-term, mid-term, short-term and annual development plans

and programs, maintaining, protection, reconstruction, construction, restoration

of road and road facilities as well as reports on realisation of those plans and

programs;

Performing works referring to maintaining motorways;

Investment works for studies and projects, restoration, construction,

reconstruction and maintaining of motorways and facilities;

Financial plans proposal and improvement of manner of collecting funds

intended for the needs of construction of motorways and express roads;

Keeping records (database) of motorways, objects, traffic signs and equipment

on motorways as well as of cadastre of motorway land;

Contracting related to reconstruction, construction of, restoration and

maintaining motorways;

Preparation and monitoring of realisation of programme of measures and

activities intended to improve road traffic safety of roads that are being

managed;

Preparation of background for granting concessions and enabling surveillance

by experts and technicians;

Organisation of toll payment system ;

Collecting data and informing public on road conditions and movement of

traffic;

Taking necessary environmental measures;

Organising and providing services to motorway and express road users etc.

The basic task of PE Autoceste is to build motorway on Corridor Vc. The majority of

the branch of Corridor Vc is on the territory of Bosnia and Herzegovina. Total length of

approximately 335 km, the construction of motorway Corridor Vc improves the connection of

BiH with surrounding countries and improves potential for economic growth. The project is

strongly supported by the Government of Federation of BiH and it is expected to enable BiH

better integration with economic and social structures in Europe.

Corridor Vc in BiH includes four main sections, in documents of Government of BiH

called lots, as follows:

Lot 1: Svilaj on the river Sava (connection with the Corridor X) – Doboj Jug;

Lot 2: Doboj Jug – Sarajevo south (Tarčin);

Lot 3: Sarajevo south (Tarčin) – Mostar north;

Lot 4: Mostar north – Bijača at the southern border with Croatia.

Page 6: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

6

Picture 1. Review of route of Corridor Vc and express roads in the Federation of BiH

Part of Corridor Vc passing through the Federation of BiH is 285 km long. In addition

to this, there were plans to build motorway Žepče – Tuzla – Brčko – Orašje as well as several

express roads that would be basis for connecting Federation of BiH with regional and further

international traffic flow through modern roads:

O. n. Relation Type of

road

1. Sarajevo –Zenica – RS – Odžak – Svilaj (Corridor Vc-north) Motorway

2. Sarajevo – Mostar – connection with JJAC Split – Ploče (Koridor Vc-south)

Motorway

3. Počitelj – Stolac – Neum – Trebinje(RS)/Dubrovnik(RC)-border with Montenegro (Adriatic-Ionian motorway)

Motorway

4. Tuzla – Brčko (intersection on Corridor DDS) – Orašje – border with the Republic of Croatia (connection with Corridor X)

Motorway

5. Žepče – Tuzla Motorway

6. Lašva-Travnik-Jajce-Bihać-Velika Kladuša Express road

7. Sarajevo –Goražde – border with RS Express road

8. Mostar – Široki Brijeg – Grude- border with RC Express road

9. Nević Polje– Bugojno – Kupres – Livno – border with RC Express road

Page 7: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

7

2.1. Vision

To create highest-ranking road infrastructure equivalent to the most modern roads in

the world.

2.2. Mission

We build, manage and maintain highest-ranking road infrastructure acting socially

responsible with a special focus on harmonization with environment and traffic safety.

2.3. Strategy

Strategy of PE Autoceste is to do profitable business activities and make positive

financial results through achieving planned goals with high-performing workforce, good

coordination and organisation, quality information system and to indirectly make significant

impact on the whole economic development in their surrounding through improved traffic

connections.

Since the expansion of construction of in the area of Corridor Vc is planned, a

significant impact on the gross domestic product (GDP) in the Federation of BiH can be

expected through increase of employment, expansion of construction industry and production

and sale of construction material necessary for the construction.

Page 8: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

8

3. Swot analysis

The advantage of this enterprise should be in dealing with internal economy,

optimising costs while continuously measuring results. The development and foundations of

business policy of the enterprise seen through prism of analysis of current state should be:

That there is a noted growth dynamic of and development of the enterprise;

Every year market is expended through construction of motorways and supporting

facilities necessary to achieve income from toll payment;

The segment of fee for the use of road land and fee for conducting support

activities on motorways will be expanded;

Professional relationship toward suppliers/contractors and the intention to adhere

to all elements of the contract as well strict inspection of performed works;

Pay special attention to maintenance of motorway and other regular funds;

Improvement of services provided to users through introducing postpaid payment

and smart cards;

Employment and high-quality training for new employees in accordance with

needs of the enterprise;

Wider social interest that company can achieve as initiator of other branches of

economy in BiH;

Socially and environmentally responsible activity.

SWOT analysis represents objective review of strengths and weaknesses as internal

factors and opportunities and threats as external factors.

Page 9: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

9

Strengths

The quality of services

Image and recognisability

Devotion of employers to the success of the enterprise and continuous education

Care toward the community, environment, socially responsible business operations

Developmental orientation and keeping up with world trends in the area of construction of and maintaining motorways

Good corporate management practices

Support of executive and legislative branches of government

Quality management system

Weaknesses

Inability to provide self-financing important developmental projects without external sources of finance

Undefined and long-term process of ratification of agreements and making funds operational per international loan facility

Bad technical solutions due to insufficient or inadequately conducted research leading to amending projects and variations

Litigations in the expropriation procedure enabling entering properties and performance of work in the deadline agreed upon

Opportunities

Keeping up with wishes, needs and expectation of buyers – service users

Making services innovative through use of different systems and payment methods to make use of service easer to service users

Competitive price in comparison taking into consideration the quality of the service

Employment and strengthening of workforce foundation which will be able to adopt acquired knowledge and experience

Expansion of business – technical cooperation with business partners

Achievement of promptness in business operations and introducing modern information system which will enable simpler performance of managerial functions (planning, organising, staffing, management and inspection of business operations and toll payment systems)

Implementation of construction projects (motorways, traffic and technical equipment etc.) in accordance with European directives and standards

Threats

Instable political and economic environment in BiH and region

There is no system framework in BiH for more significant development of economic activities

Non-conformance of legal provisions

Underdeveloped segment of accompanying industries in the area of civil engineering construction

Page 10: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

1. ORGANISATION OF BUSINESS OPERATIONS

Organisation of business operations of PE Autoceste enables conducting business operations from the activities of the enterprise

established by the Law on Roads, Articles of Association and other general documents of the enterprise. Conducting operations is managed

through basic and independent organisational units shaped in a way that enable legal, responsible, efficient and economic business operations of

PE Autoceste.

Traffic management,

monitoring and safety

service (70)

Toll payment service

(190)

Toll payment

inspection service

(5)

Maintenance service

(20) Service for general affairs

and human resources

(20)

Service for representation affairs

(6)

Service for legal

and property affairs

(9)

Service for legal support to the

implementation of

the project

(5)

Service for accounting

affairs (5)

Service for financial affairs

(11)

Service for planning

and analysis

(5)

Marketing service

(1)

Construction service

(11)

Expertise and quality service

(9)

Documentation service

(7)

ASSEMBLY (1)

(SUPPERVISORY BOARD) (5)

MANAGEMENT (9)

ACCOMPANYING SERVICES OF THE CABINET

(40) INTERNAL AUDIT COMMITTEE

(2)

AUDIT COMMITTEE (3)

DEPARTMENT OF LEGAL AFFAIRS

(40)

DEPARTMENT FOR PROJECTING AND CONSTRUCTION

(27)

MANAGEMENT AND MAINTENANCE DEPARTMENT

(285)

DEPARTMENT OF ECONOMIC AND FINANCIAL AFFAIRS

(22)

Page 11: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

4.1. CURRENT SITUATION ANALYSIS

Route of motorway Corridor Vc 335 km long runs from the northern to the southern

border of BiH. It is believed that this route will represent the most frequent travel route with the

greatest number of users of services including transport of goods and passengers.

Until now, 102 km of motorway was build and is being used and they refer to the

following sections, i.e. subsections: Zenica South – Kakanj , Kakanj – Sarajevo North,

Sarajevo North – Sarajevo west, Sarajevo west – Tarčin, Zvirovići – Bijača (from interchange

Međugorje to border checkpoint Bijača) and Svilaj - Odžak.

Construction of aforementioned subsections was funded through credit framework

concluded between Bosnia and Herzegovina and European investment bank, i.e. European

bank for Research and Development, except for the section Kakanj – Sarajevo north which

was funded from the budget of FBiH. A part of Sarajevo bypass, Lot 3a – subsection Butila –

Vlakovo, was funded from PE Autoceste's own assets.

Construction of motorway sections was continued thorough loan facilities including:

KFAED in the amount of 10.5 million KWD for the section Drivuša – Klopče and OFID (OPEC

Fund for International Development) through two loan facilities in the amount of USD 48

million and EUR 24 million for section Klopče – Donja Gračanica.

In addition to the abovementioned, activities were finished and effectiveness of

credit assets by EBRD was achieved in the previous period including:

Loan provided by EBRD in the amount of 80 million Euros for funding construction

section Donja Gračanica (tunnel Pečuj) – tunnel Zenica and subsection Buna –

Počitelj.

Loan EBRD 76 million Euros provided by EBRD for funding construction of section

Svilaj – Odžak stage 2 and subsection Klopče – Donja Gračanica (entrance in tunnel

Pečuj).

In the beginning of 2018 a Law on Amendments to the Law on excise tax of BiH

was adopted and through it income from excise tax on motor fuel was increased to BAM

0,20 per litre of motor fuel and through that conditions for continuation of activities related

to enabling credit assets for construction of motorway were achieved.

Activities related to enabling credit assets of international financial institutions were

continued and they refer to the following:

a) In the previous period loan agreements were signed and the procedure of

obtaining bank debt with following institutions was continued:

OFID (OPEC Fund for International Development) in the amount of approximately 49

million Euros for construction of subsection Vranduk – Ponirak;

EIB in the amount of 50 million Euros for construction of subsection Ponirak – Vraca

(tunnel Zenica);

EIB in the amount of 100 million Euros for construction of subsection Kvanj – Buna;

Page 12: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

12

EBRD in the amount of 180 million Euros for sections Poprikuše – Nemila (70 million

Euros), Tarčin – Ivan (50 million Euros) and Mostar South – Tunnel Kvanj (60 million

Euros).

Creditors and BiH signed loan agreements regarding the abovementioned bank

debts. Loan agreements signed with EIB were ratified and signing subsidiary agreements

and sub-agreements on financing is expected as a condition for achieving effectiveness of

credit assets. Loan agreements made with OFID and EBRD were directed for ratification.

b) Activities related to the negotiations with KFAED were finished (approximately

36 million Euros) related to conditions of giving loans and the Parliament of FBiH

made a Decision on Accepting bank debt. Loan agreement is expected to be signed

in the following period.

c) During 2018 activities related to bank debt were initiated including:

EIB in the amount of 140 million Euros for co-financing of construction of sections

Poprikuša – Nemila (90 million Euros) and Tarčin – Ivan (50 million Euros). EIB

stated that they were ready to participate in funding projects regarding construction of

motorway subsections;

EBRD in the amount of 35 million Euros for financing section Entity border (Putnikovo

brdo 2) – Karuše. There is a plan to start initiative to increase framework of credit

resources in 25 million Euros for subsection Karuše – Medakovo in the following

period.

According to the Memorandum of understanding between entity ministries of traffic

and communications and EBRD signed on 26 February 2018, there were funds planned for

financing construction of motorway on sections Putnikovo brdo – Karuše in the amount of 35

million Euros and Tunnel Ivan – Mostar South in the amount of 240 million Euros.

There is a procedure of achievement of effectiveness of approved WBIF grant funds

for co-financing of construction of section Svilaj – Odžak in the amount of 20.07 million

Euros.

In addition to the abovementioned grant, WBIF applications of BiH are adopted for

financing investment project which refer to the following:

Subsection Ponirak – Vraca (tunnel Zenica) in the amount of 19 million Euros;

Subsection Vraca – Donja Gračanica (Pečuj) in the amount of 12.06 million Euros.

Until the end of 2018, adoption of following applications for grants (which refer to

investment projects) is expected for:

Subsection Tarčin – entrance into tunnel Ivan in the amount of 12,78 million Euros

Subsection tunnel Ivan in the amount of 11,48 million Euros and

Buna – Počitelj in the amount of 8.8, million Euros.

In the following period procedures of achieving effectiveness of grants will be

implemented.

Page 13: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

13

In addition to abovementioned WBIF applications, applications for Technical assistance

referring to sections: Ivan – Ovčari (2.51 million Euros), Ovčari – entrance into tunnel Prenj

(3.05 million Euros) and Počitelj – Zvirovići (5 million Euros) were adopted.

In addition to providing financial resources from international credit assets and their

own assets, PE Autoceste plans realization of infrastructure projects using other financial

resources too. Conclusions of Government of FBiH number: 1239/17 dated 21

September, 2017 - upon the proposal of Federal Ministry of Transport and Communication,

the Information on initiative for financing infrastructure projects from accumulated profit of

public enterprises and Soviet-era debt of Russian Federation was supported.

The abovementioned Conclusion proposes, among other things, financing of

infrastructure projects within the competence of PE Autoceste including:

Express road Lašva – Nević Polje – planned allocation of BAM 100.000.000 from

Soviet-era debt of Russian Federation;

Express road Sarajevo – Goražde – planned allocation of BAM 70.000.000 from

accumulated profit of public enterprises;

Express road Mostar – Široki Brijeg – border with RC – planned allocation of BAM

13.000.000 from accumulated profit of public enterprises;

Motorway Tuzla – Žepče – planned allocation of BAM 65.000.000 from accumulated

profit of public enterprises.

On 27 July 2018, the Government of FBIH made a decision on adoption of program

expenditure of part of assets "Capital transfers to public enterprises - transfer for

construction of motorways and express roads" determined by the Budget of FBiH (adopted

by the Parliament of FBiH) which determines financing construction of express road Lašva –

Nević Polje in the amount of BAM 100 million. Decision on amendment of aforementioned

decision on one part of the section of the express road implementer was changed and the

amount to be allocated to PE Autoceste was decreased to BAM 66 million.

On 12 December 2018, the Government of FBIH Made a decision on adoption of

program of expenditure of part of assets "Capital transfers to public enterprises - transfer for

construction of motorways and express roads" in the amount of BAM 153.000.000.

According to the abovementioned decision, the planned allocations per projects are smaller

in comparison to the abovementioned in the Conclusion of the Government. In the case of

not insurance of assets from the budget for 2019, pre-financing will be perform with the own

assets of PE Autoceste.

In addition to abovementioned sources of financing, in 2018 activities related to two

issuances of notes were started and ended. In late 2018 issuance of notes was

successfully implemented.

With first issuance of notes with the maturity of 2 years there were BAM 48.998.800

collected. The purpose of means collected in the first issuance of notes is predefining

construction of sections of motorway on the Corridor Vc until the final effectiveness of credit

assets is achieved.

The second issuance of notes with the maturity deadline of five years by which

collecting of BAM 30 million failed.

Page 14: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

14

2. ACTIVITY PLAN OF CONSTRUCTION OF MOTORWAY AND EXPRESS ROAD

Graphic display of sections of the Corridor Vc

BAM 13 million from the budget of the Government of FBiH

Not defined

BAM 70 million from the budget of the Government of FBiH

Page 15: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

Table representing plan of construction of motorway and express road in 2019

Table 1

O.n. Section km

Estimated (construction +supervision) value in BAM

(VAT free)

Contracted (construction +supervision) value in BAM

(VAT free)

Source of funding

Percentage (%) of project realization

Note / current status

1 2 3 4 5 6 7 8

Sections under construction

1. Svilaj - Odžak,

Stage II 10.4

The end of construction

work is estimated to

approximately BAM

60.000.000

74.521.049

construction; 1.983.701

supervision

EBRD 76 mil Euros (financing of this section

14,5 mil Euros) and grant funds 19,6 mil Euros

Designing: 100% Main project is implemented. Works referring to the Stage II are mostly finished. Small final works are left to be finished and works on medium voltage power supply and water supply of lay-by and toll station, as well as final account. Planning permission, environmental permit and building permit were obtained for this section.

Expropriation: 100%

construction: 95 %

2. Drivuša - Klopče 2.3

It is estimated that the

contractual amount will

increase

56.046.815

construction; 5.556.423 supervision

KFAED 10.5 mil KD

Designing: 100% Main project is implemented. Construction of this subsection is almost completed. Deadline for construction is already extended. Construction works are almost over and the end is expected in the beginning of 2019. Planning permission, environmental permit and building permit were obtained for this section.

Expropriation: 100%

construction: 97 %

3. Klopče -

D.Gračanica 5.8

It is estimated that the

contractual amount will

increase

180.336.366

construction;

9.149.177 supervision

OFID 24 mil Euros

OFID 48 mil USD EBRD 76 mil

Euros (financing of this section

61,5 mil Euros)

Designing: 100% Main project is implemented. Construction of this subsection is in progress. Because of exceptionally bad geological conditions on the route, it was necessary to amend project documentation. Deadline is expected to be extended until the end of 2019. Planning permission, environmental permit and building permit were obtained for this section.

Expropriation: 100%

construction: 65 %

4. Buna - Počitelj 7.2

42.948.662

construction; 2.564.289

supervision

EBRD 80 mil Euros (out of

which 23,3 mil Euros refer to this section)

Designing: 100% Main project is implemented. Construction contract and services contract referring to monitoring of construction are signed. Official beginning of construction works on this section is on 3 August 2018. Planning permission, environmental permit and building permit were obtained.

Expropriation 100%

construction: 3,5 %

5. ER Prača -

Goražde (Stage I)

13.7 (5.8)

69.999.900

construction; Contract was

Conclusion of the Government of

FBiH - funds from Designing: 100%

Preliminary design is completed - Tunnel 5.8 km long will be constructed according to the model D&B - Yellow FIDIC. Construction contract is signed and because of

Page 16: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

16

not signed for supervision-

approximately estimated to

BAM 3.000.000

profit of public enterprises (BAM

70.000.000); Supervision:

BAM 3.000.000 - own assets of PE

Autoceste

Expropriation: 0% claims during the selection process of monitoring services consultant, the contract has not been signed yet. Environmental permit was obtained for this section and the process of obtaining planning permission.

Construction: 0%

Sections - planned beginning of construction works in 2019

6.

Vraca (tunnel Zenica) – Donja

Gračanica (tunnel Pečuj)

4

112.602.431 construction;

4.742.614 supervision

EBRD 80 mil Euros (out of

which approximately 56,7 mil Euros

refer to this section)

Designing: 100% Preliminary design - yellow FIDIC. Construction contract and services contract referring to monitoring of construction are signed. Planning permission and environmental permit and building permit were obtained for this section (Environmental permit must be renewed in 2019)

Expropriation:99,78%

Construction: 0%

7. Putnikovo brdo -

Medakovo 8.5 124.195.205

EBRD 60 mil Euros

Designing: 0%

Motorway section is divided into two sections: the first: Putnikovo brdo 2 – Karuše and the second: Karuše – Medakovo. The main design for the first section was made in 2010 by the Ministry of transport and communications of BiH and it is necessary to harmonize it with applicable technical specifications. Preliminary design for the second section was made in 2014. After the main design is completed for the whole section, there will be a tender process for choosing contractor. Environmental permit was obtained and it needs to be renewed in 2019. Planning permission was obtained for the second section of Karuše – Medakovo.

Expropriation: 0%

Construction: 0%

8. Poprikuše -

Nemila 5.5 364.148.961

EIB 90 mil Euros EBRD 70 mil

Euros

Designing: 100% Preliminary design is completed. There is a tender process for choosing contractor, monitoring service and technical assistance provider in progress. The contract will be drafted according to the "design & build" (yellow FIDIC) model. Planning permission and environmental permit and building permit were obtained for this section (Environmental permit must be renewed in 2019)

Expropriation:53,32%

Construction: 0%

9. Nemila - Vranduk

5.7 70.409.880

KFAED 36 mil Euros

Designing: 75% Main design is not implemented because of harmonization with requests of local community. There is a tender process for providing monitoring services in

Page 17: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

17

Expropriation: 21%

progress and tender process for choosing contractor is expected after harmonization with local community requests. Planning permission and environmental permit and building permit were obtained for this section (Environmental permit must be renewed in 2019) Construction: 0%

10. Vranduk - Ponirak

5,3 138.238.012 OFID 49 mil

Euros

Designing: 100% Main design is implemented. There is a tender process for choosing contractor and providing monitoring services in progress. Planning permission, environmental permit and building permit were obtained for this section (Environmental permit must be renewed in 2019)

Expropriation:89,32%

Construction: 0%

11. Ponirak - Vraca (tunnel Zenica)

2.7 161.670.864

EIB 50 mil Euros

Designing: 100% Main design is implemented. There is a tender process for choosing contractor, monitoring service and technical assistance provider in progress. Planning permission, environmental permit and building permit were obtained (Environmental permit must be renewed in 2019)

Expropriation:93,37%

Construction: 0%

12. Tarčin - Ivan 6.9 195.583.000

EIB 50 mil Euros (for Lot 1.)

EBRD 50 mil Euros (for Lot 2.)

Designing: 97%

Main design is implemented. Projecting of access road is in the progress. The section in divided into two lots: Lot 1. Tarčin – entrance into tunnel Ivan and Lot 2. tunnel Ivan. There is a tender process for choosing contractor, monitoring service and technical assistance provider in progress for Lot 2. - tunnel Ivan, while the start of tender procedure for Lot 1. Tarčin – entrance into tunnel Ivan is planned for 2019. Environmental permit was obtained for this section and renewal of planning permission and preparation for obtaining building permit are in progress.

Expropriation: 99%

Construction: 0%

13. Tunnel Prenj 12 476.097.965 EXIM 240 mil

Euros

Designing:100% Preliminary design is implemented. According to the nature of the design and necessary technology optimal manner of construction of the tunnel Prenj is according to the international contract “Design and build “(yellow FIDIC). Prior water approval was obtained and obtaining environmental permit is in the progress.

Expropriation: 0%

Construction: 0%

Page 18: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

18

14. Mostar North - Mostar South

15.4 464.062.033

EXIM 240 mil Euros

Designing: 100% Main design is implemented; however, it is necessary to do additional designing. On the other hand, procedure of adoption of spatial plan lead to the change of the route of the design on the wider area around interchange Mostar South because of which making project documentation would also be necessary. Upon the competition of the project, there would be a tender process for choosing contractor and monitoring of construction of this part of the motorway. The contract will be drafted according to the "design & build" (yellow FIDIC) model.

Expropriation: 0%

Construction: 0%

15. Mostar South -

Kvanj 8.5 140.554.831

EBRD 60 mil Euros

Designing: 100 % Preliminary design is completed. EBRD will finance the making of GAP analysis of existing design documentation. After the analysis was carried out, EBRD will give their consent for tender (prequalification) to be announced. The contract will be drafted according to the "design & build" (yellow FIDIC) model). EBRD’s consultants are making GAP analysis and obtaining prior consents.

Expropriation: 0%

Construction: 0%

16. Kvanj - Buna (tunnel Kvanj)

5,2 201.366.923

EIB 100 mil Euros

Designing: 100% Preliminary design is completed. Tender documentation necessary for the prequalification stage. The contract will be drafted according to the "design & build" (yellow FIDIC) model). Tender documentation was prepared for the procurement of technical assistance services for PIU and EIB’s consent to announce is waited for. Obtaining prior consents is in progress.

Expropriation:11,84%

Construction: 0%

17. Počitelj - Zvirovići

11.1 212.945.150 EIB 100 mil

Euros

Designing: 100% Tender process for choosing contractor and supervision of construction is in its final stage and it is expected that the contract will be signed in the following period. Planning permission, environmental permit and building permit were obtained.

Expropriation: 100%

Construction: 0%

Page 19: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

19

18.

Express Road Lašva - Nević

Polje (lot 1. Vitez - Nević Polje)

5 55.000.000

Decision of government of

FBiH on adoption of program of

expense of part of assets "Capital

transfers to public

enterprises" and own assets of PE

AC

Designing: 90% Main design is implemented. Activities related to making a basis for town and country planning are in progress as precondition for obtaining planning permission after which an accelerated implementation of tender process for choosing contractor and supervision will take place. Application for planning permission was submitted long time ago but the adoption of spatial planning documentation of Central Bosnia Canton is awaited. In the meantime the project was changed and divided into sections.

Expropriation: 2,78%

Construction: 0%

19. MW Tuzla -

Žepče 55,4 (5.5)

35.000.000

Conclusion of the government of FBiH - assets from profit of

public enterprises

Designing: 100% Preliminary design is completed. It is necessary to carry out additional geomechanic research at the section Mihatovići-Lukavac L=5.5 km. Since the planned assets are insignificant in comparison to the estimated value of the entire section, the first stage (semi-profile) of subsection Mihatovići – interchange Lukavac will be done. The contract will be drafted according to the "design & build" (yellow FIDIC) model. Environmental permit was obtained.

Expropriation: 0%

Construction: 0%

20. Sarajevo bypass

(Lot 3B) 1,5 21.500.000

Own assets of PE Autoceste

Designing: 100% Main design is implemented. There is a tender process for choosing contractor and monitoring of construction of this section of the motorway. Planning permission, environmental permit and building permit were obtained for this section

Expropriation: 98%

Construction: 0%

21. Regional R425a

Tromeđa - Zvirovići

5.8 5.175.000

Decision of government of FBiH number:

512/2018 (budgetary

assets - BAM 5.000.000 and

own assets of PE AC)

Designing: 100% Main design is implemented. There is a tender process for choosing contractor and monitoring of reparation of this regional road.

Page 20: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

2019 Business plan contains plans for initiating new preparatory activities referring to the

construction of Corridor Vc and express roads in Federation of BiH. Optimisation of motorway

sections and express roads means that in addition to adopted development strategy, maintaining

public roads, and mid-term road maintenance and protection there is also harmonization of strategies

within sector of transport and communications in a way that traffic connection in an optimal manner

from the aspect of investments in construction is settled.

Hereafter there is a review of the most important activities related to the continuation of

construction, preparation for construction as well as activities related to the providing resources for

financing construction:

5.1. SECTION SVILAJ – ODŽAK STAGE II

Length of the section: 10.4 km; Expropriation: 100%

Construction contract referring to construction of section Svilaj - Odžak was signed on 12

September, 2013 with contractor: Joint Venture Strabag AG, Euro-Asfalt d.o.o. Sarajevo and GP

ŽGP d.d. Sarajevo whose contract value is EUR 38.102.007,40 VAT free. There was a contract

referring to monitoring signed on 2 September, 2013 with Aecom Inocsa S.L.U. Spain and whose

contract value is EUR 1.014.250,00 VAT free. For the reasons of optimisation of construction works

and investing costs, construction works were divided into two stages. Stage I included construction

of motorway subgrade to the level of pavement structure as well as facilities on the route and it was

completed in 2015.

Constructions in the Stage II included final construction work referring to surfacing road and

erection of horizontal and vertical traffic signs and they were completed in November 2017. Assets

in the amount of EUR 40 million were provided by EBRD for funding stage II and the assets from

WBIF grant in the amount of 20,09 million Euros were provided too. Assets from the grant will be

used for refinancing costs paid with own assets of PE Autoceste.

Because of problems related to obtaining Building approval referring to ground floor section

of border checkpoint Svilaj, construction works related to Stage II were continued in 2018. The

works are almost over and final construction works are to be finished and final account is to be

settled in 2019.

5.2. SUBSECTION DRIVUŠA - KLOPČE

Length of the section: 2.3 km; Expropriation: 100%

In accordance with procedures of KFAED, on 25 September 2014 a construction contract in

the amount of EUR 28.656.281,50 (VAT free) was signed with a company called Hering d.d. Široki

Brijeg. Contract referring to monitoring of construction was concluded on 23 September 2014 in the

amount of EUR 2.840.954.20 (VAT free) with company Divel d.o.o. Sarajevo. Loan assets in the

amount of KWD 10.5 million (approximately 28 million Euros) were provided.

This subsection and the rest of „Zenica bypass“ is characterised by exceptionally complex

geotechnical conditions on the route which caused certain delays as well as the need to adjust

certain technical solutions especially when it comes to securing slopes at cuts and notches. The end

of construction on this subsection is expected in the beginning of 2019. Approximately 98% of

construction works is finished and they are in their final stage.

Page 21: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

21

5.3. SUBSECTION KLOPČE - DONJA GRAČANICA ( TUNNEL PEČUJ ) Length of the section: 5.8 km; Expropriation: 100%

Construction contract in the amount of EUR 92.204.519,61 VAT free was signed with

consortium Euro-Asfalt d.o.o. & Strabag AG and contract referring to supervision services in the

amount of EUR 4.677.900,00 VAT free was signed with consortium Ipsa – Egis.

Assets for financing constructions and supervision services through loan facilities at OFID

(OPEC Fund for International Development) in the amount of approximately 60 million Euros

through two lending models (USD 48 million and EUR 24 million). Also, funding will be provided

from EBRD's loan in the amount of 36 million Euros whose efficiency was achieved in the beginning

of 2018.

Construction works on the route were done slowly because it was necessary to previously

amend design documentation and this process is almost over. According to the present estimation,

the construction works will last throughout the entire 2019. Until now approximately 65% of works in

comparison to the extended scope of works in new projects which had to be amended due to the

exceptionally bad engineering and geological conditions on the field.

5.4. SECTION BUNA - POČITELJ

Length of the section: 7.2 km; Expropriation: 100%

Construction contract in the amount of 21.959.302 Euros VAT free was concluded on 18

May 2018 with Hering d.d. When it comes to supervision services referring to construction works,

there was a contract concluded with consortium Aecom Inocsa SLU and Aecom d.o.o. The contract

value is 1.311.100 Euros VAT free.

The construction of abovementioned subsection will be funded from loan provided by EBRD

(30 million Euros) and from grants in the amount of 8,8 million Euros. The abovementioned loan

facility was used for funding construction of section Vraca (tunnel Zenica ) – Donja Gračanica

(tunnel Pečuj) too.

Construction works on this section officially began on 3 August 2018.

5.5. EXPRESS ROAD PRAČA – GORAŽDE ( STAGE I )

Length of the section: 5.8 km; Expropriation: 0 %

The total length of section of express road Prača - Goražde is 13.7 km. Stage I of this express

road represents construction of semi-profile of express road covering all its length. Stage II included

completing this road to a full profile of express road and it is not expected to be completed in the

near future. Preliminary design documentation referring to this section of express road is obtained.

Obtaining planning permission is in progress.

Construction contract in the amount of BAM 69.999.900 (VAT free) was signed on 22

September 2018 with Euro Asfalt d.o.o. Because of claims during the selection process of

supervision services consultant, the contract has not been signed yet and the construction works

have not begun. Construction works will be done according to the contract "design and build"

(yellow FIDIC).

In accordance with the conclusion of Government of FBiH number 1239/17 dated 21

September 2017, this project will be funded by assets of accumulated profit of public enterprises in

the amount of BAM 70 million.

Page 22: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

22

5.6. SUBSECTION VRACA (TUNNEL ZENICA) – DONJA GRAČANICA (TUNNEL PEČUJ) Length of the section: 3.9 km; Expropriation: 99.78%

Construction contract referring to the construction of section Vraca – Donja Gračanica in the

amount of 57.572.708.76 Euros VAT free was concluded on 8 November 2018 with contractor:

Cengiz Insaat Sanayi ve Ticaret A.S. Contract referring to supervision services was concluded on

31 July 2018 with consortium Technical S.p.A (leader) and TZI Inžinjering d.o.o. and its contract

value was 2.424.860 Euros VAT free. Construction works will be done according to the contract

"design and build" (yellow FIDIC). Within construction contract referring to construction of this

subsection there will be activities referring to preparing design documents, obtaining building

approval and preparation for construction of route and objects that will be on it. Construction works

on this section was officially planned to occur on 27 November 2018.

The construction of abovementioned subsection will be funded from loan provided by EBRD

(50 million Euros) and from grants in the amount of 12 million Euros. The abovementioned

mentioned loan facility was used for funding construction of section Buna – Počitelj too.

5.7. PUTNIKOVO BRDO – MEDAKOVO Length of the section: 8.5 km; Expropriation: 0%

Motorway section is divided into two parts: the first: Putnikovo brdo – Karuše and Karuše –

Medakovo. Preliminary design for the first part was made in 2010 by the Ministry of communications

and traffic of BiH and it is necessary to harmonize it with applicable technical specifications.

Preliminary design for the second part was made in 2014. After the entire preliminary design is

completed there will be tender process for choosing contractor.

In order to finance construction of the first part of the abovementioned section (Putnikovo brdo

– Karuše), initiative for bank debt in the amount of 35 million Euros was directed to EBRD and there

are plans to direct amendment of the initiative for additional 25 million Euros for financing

subsection Karuše – Medakovo.

5.8. SECTION POPRIKUŠE – NEMILA Length of the section: 5.5 km; Expropriation: 53.32%

Preliminary design for this subsection was finished in 2006 and in 2014 it was analysed with the

goal of its optimisation. During 2017, amendment of design documentation was completed and the

request for obtaining planning permit was submitted. One interchange (interchange Poprikuše) was

planned as the part of the preliminary design as well as one tunnel (tunnel Golubinja, L=3,6 km),

and two viaducts and two bridges. Construction works will be done according to the contract "design

and build" (yellow FIDIC).

In order to finance construction of the first part of the abovementioned section, initiative for

bank debt in the amount of 160 million Euros was directed to EIB (90 million Euros) and EBRD (70

million Euros) and application for grants of WBIF in the amount of 33.47 million Euros was

submitted. Loan contract was concluded with EBRD on 12 September 2018 and it was directed to

ratification process.

In the previous period there were tender processes for choosing contractor and consulting

monitoring services referring to construction and consulting services referring to technical

assistance of Project implementation unit (PIU). Offers were received and evaluation is in the

progress.

Page 23: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

23

5.9. SUBSECTION NEMILA – VRANDUK Length of the section: 5.7 km; Expropriation: 21%;

Preliminary design was completed in 2006 and optimisation of route in 2013. The main

project is not completed because of harmonization with requests of local community.

Negotiations with KFAED in the amount of approximately 36 million Euros for financing the

construction of abovementioned subsection were completed and the Presidency made a decision

on accepting the financing agreement and decision on accepting debts by the Parliament of FBiH. In

the following period it is expected that Financing agreement between the creditor and BiH will be

signed.

In the previous period, the procedure of procurement of consulting services referring to

monitoring was initiated and after the harmonization with the local community it is expected that the

call for tenders for contractor will be announced.

5.10. SUBSECTION VRANDUK - PONIRAK Length of the section: 5.3 km; Expropriation: 89.32%;

Preliminary design was completed in 2006 and optimisation of route in 2013. In 2018 the

main design was completed, planning permit was obtained and the request for obtaining building

permit was submitted.

Assets in the amount of approximately 49 million Euros will be provided by OFID (OPEC Fund

for International Development) for financing of the abovementioned subsection. The loan agreement

was signed on 30 August 2018 and the ratification process took place.

In the previous period tender process for choosing contractor and monitoring services

referring to construction works was initiated. At the beginning of 2019 ending of the procedure and

signing of the contract is expected.

5.11. SUBSECTION PONIRAK – VRACA ( TUNEL ZENICA ) Length of the section: 2,7 km; Expropriation: 93,37%;

Preliminary design was completed in 2006 and optimisation of route in 2013. In 2018 the

main design was completed, planning permit was obtained and the request for obtaining building

permit was submitted.

Assets in the amount of approximately 50 million Euros will be provided by EIB for financing of

the abovementioned subsection. Financing agreement was ratified on 20 September 2018 and in

the following period it is expected that subsidiary agreement and financing subagreement will be

signed as basic conditions for fund efficiency to be achieved. Also, application for grants provided

by WBIF in the amount of 19 million Euros was adopted.

In the previous period tender process for choosing contractor, monitoring services referring

to construction works and technical assistance to PIU was initiated. In 2019 ending of the procedure

and signing of the contract is expected.

5.12. SECTION TARČIN - IVAN Length of the section: 6.9 km; Expropriation: 99%

Page 24: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

24

The main design referring to section Tarčin – Konjic was completed in 2015. Obtaining

planning permit and decision on decision on declaring the public interest is in the progress again

since the previous ones expired. Environmental permit was obtained. After the planning permit is

obtained and the expropriation procedure is completed, requests for obtaining building permit will

be submitted. Subsection Tarčin – Ivan approximately 6.9 km long represents the beginning of the

section itself i.e. connection to the part of the Corridor VC in Tarčin that was already built. There

were two bridges planned to be built on this section, one tunnel (tunnel Ivan L= 1,7 km) as well as

access road to main road M17. The section was divided to two lots: Lot 1 Tarčin – entrance to the

tunnel Ivan and Lot 2 tunnel Ivan.

In order to finance construction of the first part of the abovementioned subsection, bank debt

in the amount of 50 million Euros was directed to EIB (for Lot 1) and one in the amount of 50 million

Euros was directed to to EBRD (for Lot 2). Loan agreement was concluded with EBRD on 12

September 2018 and it was directed to ratification process. Grant in the amount of 23.3 million

Euros was approved.

Tender process referring to Lot 2 is in progress. Conclusion of construction contract,

supervision services and services referring to technical assistance to PIU is expected in the first

quarter of 2019. When it comes to Lot 1 of this motorway subsection, the announcement of call for

tender for contractor, monitoring services and technical assistance to PIU is planned in 2019.

5.13. TUNNEL PRENJ (STAGE I ) Length of the section: 12 km; Expropriation: 0%

In the previous period PE Autoceste conducted optimisation of the route of motorway section

Ovčari - Konjic – Mostar north. Investment and technical documentation referring to this subsection

was completed (preliminary design, environmental impact study, traffic study and geological study).

In the procedure of obtaining environmental permit the project was presented and public hearing

took place in municipalities Konjic and Mostar.

Design referring to the construction of motorway Konjic – Mostar north consists of following

subsections: Ovčari – Konjic, Konjic – entrance into the tunnel Prenj, tunnel Prenj – Salakovac

(Stage I). In accordance with the nature of the design and necessary technology, optimal manner of

construction of the tunnel Prenj is according to the international contract "Design and build" yellow

FIDIC. On 12 February 2016 the government of FBiH made a Decision on model of implementation

of project referring to construction of motorway section Konjic – Mostar North by which it was

determined that the optimal manner of construction would represent model in which bidders make a

financial and technical bid but also financier with whom BiH will conclude loan agreement. Criteria

based on which agreement will be awarded will be the best total offer when expenditure related to

construction and financing is calculated. In 2019 preparatory activities for conducting tender process

are planned.

5.14. SECTION MOSTAR NORTH – MOSTAR JUG Length of the section: 15 km; Expropriation: 0%

Main design related to the section Mostar north - Mostar jug was made in 2010 by the

Ministry of communications and transport of BiH. However, the design does not contain basic

elements which would enable its successful implementation without additional

Page 25: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

25

projecting. On the other hand, procedure of adoption of spatial plan lead to the amendment of

the route of the design in the wider area around the interchange Mostar south because of which it

will also be necessary to make new design documentation.

According to the geological structure of the terrain and nature, correction of the main design

which needs to be done, optimal manner of construction of subsection Mostar north - Mostar south

is in accordance with the model of contract "Design and build", yellow FIDIC, where the contractor

will be enabled not just to make necessary corrections of documentation but also to optimise the

route itself with the goal of decrease of investing costs. Bearing in mind that it is a design for which it

is necessary to allocate significant financial resources, approximately 240 million Euros, optimal

manner of construction would represent a model in which bidders make a financial and technical bid

but also financier with whom BiH will conclude loan agreement. Criteria based on which agreement

will be awarded will be the best total offer when expenditure related to construction and financing is

calculated.

5.15. SECTION MOSTAR SOUTH– KVANJ Length of the section: 8.6 km; Expropriation: 0%

Making of main design is completed. Preparation of documents for obtaining environmental

permit and planning permit is in progress. The manner of construction is planned according to the

contract "Design and build“ (yellow FIDIC) model.

Assets for financing constructions and supervision services were procured through loan facility

at EBRD in the amount of approximately 60 million Euros. Loan agreement was signed on 12

September 2018 and it was directed to ratification process. In addition to that, grant in the amount of

11.9 million Euros was applied for.

In 2019 the beginning of implementation of tender process for doing construction works and

monitoring services.

5.16. SECTION KVANJ - BUNA (TUNNEL KVANJ ) Length of the section: 5.2 km; Expropriation: 11.84%

Making of main design is completed. Preparation of documents for obtaining environmental

permit and planning permit is in progress. The manner of construction is planned according to the

contract "Design and build“ (yellow FIDIC) model.

Assets for financing constructions and supervision services were procured through loan facility

at EIB in the amount of 100 million Euros. Loan agreement was ratified on 2 October 2018 and

signing of subsidiary agreements and sub-agreements on financing is expected in the following

period as a condition for achieving effectiveness of loan assets. In addition to that, grant in the

amount of 20.7 mil Euros was applied for.

In 2019 it is expected that tender process for doing construction works and supervision

services and services related to providing technical assistance to Project Implementation Unit and

there are predictions that this process will be completed by the end of 2019.

5.17. SECTION POČITELJ - ZVIROVIĆI

Length of the section: 11.1 km; Expropriation: 100%

In the previous period tender process of procurement of works related to the construction of

motorway on the section Počitelj – Zvirovići, supervisory services referring to doing works and

consulting services from technical assistance Design

Page 26: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

26

Implementation Unit PE Autoceste (PIU). Contract referring to providing technical

assistance signed in June 2018. Procedure referring to procurement of works is divided into two lots

including Lot 1: Počitelj – beginning of the bridge Počitelj – end of the bridge Počitelj – interchange

Zvirovići and Lot 2: bridge Počitelj. The contract is expected to be signed in the first quarter of 2019.

Assets used for funding the construction works and supervisory services are provided

through bank loan in the amount of 100 million Euros provided by EIB. Loan assets are effective.

5.18. EXPRESS ROAD LAŠVA – NEVIĆ POLJE

Length of the section: 24.5 km; Expropriation: 2.78%

Main design of referring to the express road Lašva – Nević Polje was built and revised in

May 2013. Express road is 24.5 km long and estimated value of the project is approximately 217

million Euros and design documentation referring to it is already made (Main design) and divided

into three subsections.

There is a plan to implement tender process in 2019 referring to choosing the contractor and

supervision of construction works referring to Lot 1 of the section: Vitez – Nević Polje which is

approximately 5 km long. It was necessary to adjust design documentation for the purpose of

integrating this subsection into existing transport network before the rest of the express road is built.

Due to the additional harmonisation of the design with municipal bodies and authorities of Central

Bosnia Canton, implementation of this activity is late but in the following period the end of

preparation of design documentation and tender documentation as well as announcement of

tenders is expected.

On 27 July 2018, the government of FBIH made a Decision on Adopting the Program of

Expenditure of Part of Assets" Capital transfers to public enterprises – transfer for construction of

motorways and express roads“ determined by the Budget of FBiH (adopted by the Parliament of

FBiH) which determined financing the construction of express road Lašva – Nević Polje in the

amount of BAM 100 million. Decision on amendment of the abovementioned decision made on 20

December, 2018 defined that BAM 66 million(which not been used in 2018.) will be allocated for the

construction of part of express road Lašva – Nević Polje whose implementer is PE Autoceste and

that BAM 34 million will be allocated for the part of express road Lašva – Nević Polje – passage

through business zone Vitez whose implementer is PE Ceste FBiH. In the case of not insurance of

assets from the budget FBiH for 2019, pre-financing will be perform with the own assets of PE

Autoceste.

5.19. MOTORWAY TUZLA - ŽEPČE

Length of the section: 56 km; Expropriation: 0%

Preliminary design of this motorway was finished in 2015. Preliminary design documentation

includes 5 interchanges, one interregional hub, 8 tunnels and 35 bridges more than 100 m long. In

accordance with the Conclusion of the Government of FBiH number: 1239/2017 financing of this

design from accumulated profit of public enterprises was planned. In the following period,

investments into the abovementioned section will be conducted in accordance with the Program of

expenditure of part of assets of Government of FBiH. Bearing in mind that planned assets are small

in comparison to the estimated value of the entire section, the assets will be used for construction of

the first stage (semi-profile) of this motorway in the section from the settlement Mihatovići to

Interchange Lukavac (5.5 km),

Page 27: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

27

by which the existing transport network in the area from Šićki Brod to Mihatovići would be

relieved. Implementation of the planned activity depends on whether the assets are ensured.

5.20. SARAJEVO BYPASS LOT 3B Length of the section: 1.5 km; Expropriation: 98%

Preparatory activities for construction of Sarajevo bypass Lot 3B stretching from interchange

Vlakovo to the connection to the roundabout Mostar crossroads were finished in the previous

period. Tender process of procurement of construction works is in progress. Call for tender was

announced in late June 2018 after the Public Procurement Plan was adopted and income from

excise tax was available. After appeals were lodged, the tender process was stopped and continued

for several times. The contract is expected to be signed in the beginning of 2019. Assets for the

abovementioned section will be provided form own assets of PE Autoceste.

5.21. REGIONAL ROAD R425A ON THE SECTION TROMEĐA – ZVIROVIĆI

Length of the section: 5.8 km;

According to the Decision of the Government of FBiH number: 512/2018 dated 12 April 2018

implementation of the design t "Road rehabilitation of regional road R425a, section Tromeđa –

Trebižat“ was approved and PE Autoceste was named implementer of the design. Assets in the

amount of BAM 5 million used for the project implementation will be provided from the Budget of

FBiH. In the case of not insurance of assets from the budget for 2019, financing will be perform with

the own assets of PE Autoceste.

In 2018 there was a call for tender referring to construction work and providing supervision

services announced. Because of appeals that were lodged during the procedure of choosing

contractor, the construction contract has not been signed yet. Tender process referring to choosing

supervision services consultant is in progress.

3. BUSINESS ACTIVITY PLAN

6.1. Expropriation of the land

Land expropriation i.e. real estate expropriation is implemented for the needs of

implementation of designs referring to motorways on Corridor Vc that the Government of FBiH

established were of public interest, other facilities on the motorway and objects for the needs of

management and maintaining motorway and other facilities. Land purchase is done according to the

Law on Expropriation of Federation of Bosnia and Herzegovina (Official Gazette of FBiH, No. 70/07,

36/10, 25/12, 34/16) and the Law on Motorway on the Corridor Vc ("Official Gazette of FBiH“, No.

8/13).

The following table provides review of estimated expropriation value (including total

estimation of land purchase following the regular procedure and purchase according to decisions of

competent court) as well as the percentage of implementation of planned assets

Page 28: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

28

so far and total estimation of expropriation value for 2019 for individual sections/subsections as

follows:

Table 2

O.n. Name of the investment Estimated

expropriation value

Percentage of implementatio

n in comparison to the estimated value 31 Dec

2018 (%)

Percentage of implementatio

n of expropriated

area (%)

2019 plan

1 2 3 4 5 6

Financing with own assets 118.740.000 33.840.000

1. Motorway Putnikovo brdo – Medakovo (8,5 km) 12.000.000 0,00 0,00 4.000.000

2. Motorway Ozimica (Želeća) – Poprikuše (6 km) 9.000.000 0,00 0,00 3.000.000

3. Motorway Poprikuše – Nemila (5,5 km) 5.000.000 78,00 53,32 2.000.000

4. Motorway Nemila – Vranduk (5.7 km) 10.500.000 2,1 21,00 6.000.000

5. Motorway Vranduk – Ponirak (5,3 km) 5.700.000 84,21 89,32 900.000

6. Motorway Ponirak – Vraca (southern exit from tunnel Zenica) (2,7 km)

840.000 94,27 93,37 40.000

7. Motorway Vraca (tunnel Zenica) – Donja Gračanica (tunel Pečuj) (4 km)

13.000.000 90,93 99,78 1.400.000

8. Motorway Konjic – Mostar North (Salakovac stage I – 22 km)

8.000.000 0,00 0,00 1.000.000

9. Motorway Mostar north - Mostar jug (15,4 km) 13.000.000 0,00 0,00 1.000.000

10. Motorway Mostar jug – Kvanj (8,5 km) 12.000.000 0,00 0,00 6.000.000

11. Motorway Kvanj – Buna (tunel Kvanj) (5,2 km) 4.000.000 11,84 10,11 3.500.000

12. Motorway Buna - Počitelj (7,2 km) 5.200.000 91,42 100,00 400.000

13. Motorway Počitelj – Zvirovići (11.1 km) 5.500.000 79,71 100,00 600.000

14. Other sections 7.000.000 0,00 0,00 3.000.000

15. Express road Prača - Goražde (tunnel Hranjen) (13,78 km)

8.000.000 0,00 0,00 1.000.000

16. Express road Lašva – Nević polje (24 km) 41.000.000 3,17 2,78 4.000.000

Financing per the Conclusion of the Government 92.000.000 6.500.000

17. Express road Mostar – Široki Brijeg – border with RC

6.000.000 0,00 0,00 1.000.000

18. Motorway Tuzla - Žepče (56 km) 45.000.000 0,00 0,00 1.500.000

TOTAL: 210.740.000 40.340.000

The following table provides detailed structure of values of expropriation per sections which

encompasses purchase of land and residential facilities according to the expropriation proceedings,

purchase per court proceedings (extra-judicial proceedings and civil procedure) and expenses

related to making elaborate, splitting land units and other fees:

Table 3

Page 29: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

29

O.n. Name of the investment

Purchase following the

regular expropriation

procedure

Purchase according

to the decision

of the competent

court

Making of elaborates,

splitting land units, fees and other

unpredicted costs

Total

1 2 3 4 5 6=(3+4+5)

Financing with own assets 30.090.000 3.134.000 616.000 33.840.000

1. Motorway Putnikovo brdo – Medakovo (8,5 km)

3.700.000 200.000 100.000 4.000000

2. Motorway Ozimica (Želeća) – Poprikuše (6 km)

2.700.000 200.000 100.000 3.000.000

3. Motorway Poprikuše - Nemila 1.700.000 250.000 50.000 2.000.000

4. Motorway Nemila–Vranduk (5,7 km) 5.590.000 339.000 71.000 6.000.000

5. Motorway Vranduk – Ponirak (5,3 km) 750.000 120.000 30.000 900.000

6. Motorway Ponirak – Vraca (tunnel Zenica) (2,8 km)

40.000 0 0 40.000

7. Motorway Vraca (tunel Zenica) – Donja Gračanica (tunnel Pečuj) (4 km)

1.070.000 300.000 30.000 1.400.000

8. Motorway Konjic – Mostar North (Salakovac stage I – 22 km)

880.000 100.000 20.000 1.000.000

9. Motorway Mostar north - Mostar south (15,4 km)

880.000 100.000 20.000 1.000.000

10. Motorway Mostar south – Kvanj (8,5 km) 5.800.000 150.000 50.000 6.000.000

11. Motorway Kvanj – Buna (tunnel Kvanj) (5,2 km)

3.070.000 370.000 60.000 3.500.000

12. Motorway Buna - Počitelj (7,2km) 350.000 45.000 5.000 400.000

13. Motorway Počitelj – Zvirovići (11 km) 390.000 200.000 10.000 600.000

14. Other sections 2.320.000 660.000 20.000 3.000.000

15. Express road Prača - Goražde (tunnel Hranjen) (13,78 km)

850.000 100.000 50.000 1.000.000

16. Express road Lašva – Nević polje (24 km) 3.200.000 700.000 100.000 4.000.000

Financing per the Conclusion of the Government

5.350.000 900.000 250.000 6.500.000

17. Express road Mostar – Široki Brijeg – border with RC

850.000 100.000 50.000 1.000.000

18. Motorway Tuzla - Žepče (56 km) 1.300.000 100.000 100.000 1.500.000

TOTAL: 35.440.000 4.034.000 866.000 40.340.000

Explanation of planned investments:

1. Motorway section Putnikovo brdo – Medakovo (8.5 km) - This section is located in the

municipality of Doboj Jug and Tešanj. The procedure for procurement of elaborate on

expropriation was initiated and its end is expected in the first quarter of 2019 when the

expropriation proceedings themselves will begin. Preliminary design was done and based on it

the value of expropriation was estimated.

2. Motorway section Ozimica (Želeća) – Poprikuše (6 km) - The procedure for procurement of

elaborate on expropriation was initiated and its end is expected in the first quarter of 2019 when

Page 30: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

30

the expropriation proceedings itself will begin. Preliminary design was done and based on it the

value of expropriation was estimated.

3. Motorway Poprikuše – Nemila (5.4 km) – Expropriation proceedings in the previous period was

carried out faster than predicted and the total area of approximately 56.32% of the area

estimated in the elaborate on expropriation was expropriated and the end of expropriation on the

whole subsection is expected in 2019.

4. Motorway subsection Nemila – Vranduk (5.7 km) – An elaborate on expropriation was carried

out in the previous period. There was an expropriation in the previous period referring to the non-

contestable part of the route from Vranduka to the main road M17 (totally expropriated 21%).

Expropriation proceedings are stopped at the moment because agreement with the local

community could not be reached. On the remaining part of the subsection the expropriated area

is quite large because of relocation of main road M-17 where there is a great number of

residential facilities as well as 2 apartment buildings and a petrol station.

5. Motorway subsection Vranduk – Ponirak (5,3 km) – In the previous period in this section all

17 residential facilities related to the partial elaborate of expropriation were expropriated while the

expropriation was finished in 89.32% of anticipated area. The end of the expropriation

proceedings is planned for 2019.

6. Motorway section Ponirak – Vraca (tunnel Zenica) (2.7 km) – When it comes to the

abovementioned section, all Decisions on Expropriation were delivered and 13 agreements on

taxation were signed. 7 residential facilities included in the elaborate on expropriation were

expropriated. Expropriation was finished in 93.37% of anticipated area. The only remaining

subject is planned to be finished in 2019.

7. Motorway section Vraca (tunnel Zenica) – Donja Gračanica (tunnel Pečuj) (4 km) – Total

length of this section (divided into two parts 2.2 km + 1.8 km) is 4 km and according to the

submitted elaborates, the expropriation will be carried out on 302 lots divided to 166 subjects.

Most of the subjects are finished i.e. more than 99% of total suggested area is finished and 100%

of residential facilities were expropriated (40 facilities). There are plans in 2019 to make purchase

according to the additional elaborate on expropriation related to the material depot from the

tunnel and all remaining lots.

8. Motorway section Konjic – Mostar North (Salakovac Stage I – 22 km) – Preliminary design

and studies are finished and obtaining prior water approval and environmental permit is in

progress. Elaborate on expropriation was carried out for subsection which refers to the tunnel

Prenj while elaborate on expropriation for the remaining part of the section will be done within the

main design. Route of the tunnel Prenj and depot is mostly located on the state-owned land.

9. Section Mostar north – Mostar south (15.4 km) – at this moment we do not have date about

route for the abovementioned subsection (relation of state and private property, length of the

tunnel and bridges, number of residential facilities, type and quality of the land etc.), based on the

data we own only approximate value of expropriation on the section can be determined.

10. Motorway subsection Mostar south– Kvanj (8.5 km) - Elaborate on expropriation was finished

in November 2018. Procedure for determining public interest as a precondition for the beginning

the expropriation proceedings was initiated. Elaborate encompasses cadastre municipalities

Blagaj, Gnojnice donje, Ortiješ, Kosor, Malo polje and Hodbina, all of them being in the city of

Mostar. This subsection contains also 2 residential facilities which need to be expropriated and

there is a possibility of expropriation of residential facilities that are near the route. The route

passes through privately owned agricultural land for the most part.

Page 31: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

31

11. Motorway subsection Kvanj – Buna (tunnel Kvanj) (5.2 km) – elaborates for the municipality

Čapljina and the city of Mostar and there was a visit of the field, reports of experts in the field of

civil engineering and agriculture were obtained and a part of agreement with Mostar and all

agreements referring to the municipality Čapljina were concluded. At this moment expropriation

was finished in 11.84% of anticipated area. A part of the elaborate referring to the municipality

Stolac, cadastral municipality Rotimlja was received in November 2018 and their expropriation

will be carried out in 2019. Expropriation is planned to be finished in 2019 for the most part.

12. Motorway subsection Buna - Počitelj (7.2 km) – expropriation was carried out for the most part

of subsection, the contractor was taken to the property and construction work is in progress. On

this subsection, expropriation is 100% implemented with decisions of the Government of FBiH on

early entering the property. The price of the land and the amount of the total fee are known

because all reports of experts in the field of civil engineering and agriculture were obtained. In

2019 there are plans to finish contestable subjects where entering the property is allowed

through agreement or decision of the Government of FBiH and additional expropriation for

overhead power lines for which elaborate was received in November 2018.

13. Motorway subsection Počitelj – Zvirovići (11.1 km) - expropriation proceedings were carried

out for the most part and expropriation is 100% implemented including entering the property

according to the decision of the Governent of FBiH. One part of the subject is not completed and

its competition depends on cantonal i.e. municipal courts. In 2019 the rest of lots are planned to

be expropriated after the remaining judgements and decisions are received.

14. Other sections: Part "other sections" includes sections on which the construction proceedings

are completed, construction work is in progress or the procedure of expropriation is in the final

stage. According to the previous experience amendments of elaborate of expropriation are

possible (because of construction of access roads, interchanges, pipeline, replacement of utility

poles etc.) and for that purpose assets for purchase of real estates in the expropriation

proceedings are planned. Special expenses are expected on parts where the procedure which

was suspended is continued and it is expected that the subjects which were decided based on

appeals/claims will be completed. In 2019 it is expected that expropriation on the section LOT 3

B Sarajevo bypass (1,6 km) will be finished and additional expropriation will be carried out on the

section Tarčin – Tunnel Ivan (6,8 km), southern exit from the tunnel Ivan. Expenditure are also

possible on the following completed sections: Svilaj – Odžak, Donja Gračanica – Drivuša,

Drivuša - Kakanj and Kakanj – Jošanica as well as on the section Vlakovo – Tarčin. For all the

abovementioned it is possible that the payment of the fee will be done in 2019, and the total

amount of anticipated fees for these sections is stated in the table.

15. Section Prača - Goražde (tunel Hranjen) (13.78 km) (express road) - For the section of

express road the Government of FBiH made a Decision on Determining Public Interest as a part

of transport connection of Sarajevo and Goražde. Precondition to start implementing this section

is to male elaborate on expropriation which was made but it will be supplemented because of

changes on the route.

16. Express road section BC Lašva - Nević polje (express road) - When it comes to the section

of express road Lašva - Nević Polje which is 24 km long there are elaborates on appraisal of total

value of expropriation by the expert in the field of civil engineering and agriculture and estimation

of other costs. Expropriation of the land necessary for construction of the express road will be

carried out in the area of the town Zenica, the municipality of Busovača, the municipality of Vitez,

the municipality of Travnik and the municipality of Novi Travnik. In 2018 expropriation to Lot 5

sections began, Exist from the Business Zone Vitez – Nević polje where the expropriation was

implemented in the amount of 2.78 %, and 3 residential facilities were expropriated too.

Page 32: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

32

There is a plan to continue expropriation in 2019 and there is a plan to expropriate, inter alia, the

remaining 27 facilities (residential/business). Expropriation proceedings are currently suspended

and their continuation depends on the obtaining planning permit. In accordance with the decision

of the Government of FBiH on the program of expenditure of assets number 966 dated 27 July,

2018, the expropriation will be funded from current transfers determined by the Budget of FBiH

for 2018 through the program of expenditure.

17. Express road section Mostar – Široki Brijeg – border with RC (express road) – When it

comes to the abovementioned express road section, making of preliminary design is in progress

as well as obtaining the necessary permits. In accordance with the Conclusion of the

Government, the funding will be obtained from accumulated profit of public enterprises of BiH.

18. Motorway section Tuzla - Žepče (56 km) - When it comes to the abovementioned motorway

section, making of preliminary design is in progress as well as obtaining the necessary permits.

In accordance with the Conclusion of the Government, the funding will be obtained from

accumulated profit of public enterprises of BiH.

Incomplete expropriation (easement referring to real estate or lease of property on a land for a

definite time period can be introduced) – when it comes to sections which are planned for 2019 as

well as sections that are already completed or those on which construction works are still in progress

it is possible that expenses related to the incomplete expropriation will occur. Greater costs referring

to incomplete expropriation are expected on the section Buna – Počitelj and Drivuša – Donja

Gračanica. Total amount allocated for the incomplete expropriation is BAM 500.000 (purchase

following the regular procedure of the expropriation).

Representation

Representation of PE Autoceste before competent courts in FBiH is present in civil procedure

and extra-judicial proceedings.

Civil procedure refers to determining tangible and intangible damages that occurred as a

consequence of construction of motorway or as a consequence of traffic on the motorway – tangible

damage i.e. injury in the form of physical and psychological pain. In 2019 there are plans to make

payments in 19 civil cases.

In addition to estimate of the value of purchase of the land and real estate during the regular

procedure, based on the experience from previous years, there was an estimate of values of

purchase of land and real estate in extra-judicial procedures (pursuant to decisions of competent

courts) in the amount of approximately 10% of the purchase following the regular procedure.

Normally, the abovementioned legal proceedings are taken upon the request of parties (previous

owners) when compensation agreement is not concluded with the user of expropriation before the

authority and judicial decision making is requested in order to determine the amount of

compensation referring to real estate.

From previous experience possible legal proceedings from 2019 will not be completed in the

same year because of the slow work and courts overloaded with old cases. Out of total number of

abovementioned extra-judiciary cases on the abovementioned sections, a payment in the amount of

BAM 4.034.000.00 according to decisions of competent courts is planned in 2019 which represents

approximately 10% of total number of assets that were allocated for expropriation.

Support to project implementation

Page 33: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

33

In 2019 there is a plan to meet the liabilities taken in the expropriation proceedings as well

as preventive archaeological research and protection of archaeological sites including:

Table 4

O.nr. Name of the activity Estimated

value of the contract

2019 plan (VAT free)

1 2 3 4

1. Liabilities within works related to expropriation (construction of access roads, banks, small walls etc.)

500.000 300.000

2. Archaeological research and protection of archaeological sites

292.000 292.000

TOTAL: 792.000 592.000

Explanation of planned investments: 1. Those are activities for which Autoceste FBiH are obliged to build access roads, banks,

small walls etc upon the end of expropriation proceedings. Those obligations were taken when

the contract was concluded, some of them are conditioned by court decisions, independent

projects etc. Plan referring to services and works in the Legal support service referring to project

implementation for 2019 encompasses implementation of services and works referring to

obligation within the works related to expropriation (access roads, banks, small walls etc).

Services include services of making design documentation and services referring to official

supervision while works that refer to carrying out construction works relate to access roads,

banks, walls and drainage system. In 2018 tender process for choosing consultant for making

design documentation referring to construction of access roads, banks, walls etc. was carried out.

2. Based on the framework agreement on conducting preventive archaeological research and

protection of archaeological sites and heritage sites on the motorway route Corridor Vc

concluded between PE Autoceste FBiH and Ministry of Culture and sport of FBiH, the

continuation provides a preview of subsections on which conclusion of individual contracts on

preventive archaeological research with Ministry of Culture and sport of FBiH is planned on

following motorway sections: Poprikuše – Donja Gračanica, Tarčin – Ivan, Kvanj – Buna and

Počitelj – Zvirovići.

6.2. Designing Services

2019 Business Plan anticipates competition of making of design documentation referring to

contracts that were signed in the previous period, as well as initiating tender process and making

deals referring to new designs. Services referring to making new designs will be funded from own

assets of PE Autoceste, budget of the Government of FBiH, grants provided by IPA and WBIF funds

and Ministry of communications and transport of BiH.

6.2.1. Designing services financed from own assets

Based on the previous experience, implementation of planned activities will depend on the

success of tender processes that were carried out as well as from adoption of spatial plan of

Federation of BiH and spatial plan with special characteristics that are of importance for the

Federation of BiH – motorway on the Corridor Vc.

Page 34: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

34

Or.No.

Name of the investment

Estimated/ contracted value of the

services(without VAT)

Plan for 2019

(without VAT)

1 2 3 4

Financing by own assets 5.511.957 3.974.000

1. General design and pre-feasibility study of the express road Mostar – Široki Brijeg –border RC - continuation of the activities

388.370 148.000

2. Audit of the Corrections of the existing main design of the express road Lašva – Nević polje in the area of business zones

20.000 10.000

3.

The drafting of the preliminary design and pre-feasibility study of the modernization of the existing road and raising to the level of the express road border of Croatia – Bihać – Ključ 125km

1.936.480 1.600.000

4. Professional counselling for the selection of the technical solutions of modernization of the existing road up to the level of the express road border of Croatia – Bihać – Ključ

51.000 40.000

5. The drafting of the preliminary design and feasibility study for the section of the express road border of Croatia - Bihać - Cazin – V. Kladuša 47km

349.107 300.000

6. Professional counselling for the selection of the technical solutions at the section of the express road Bihać - Cazin – V. Kladuša 47km

51.000 51.000

7. Drafting of the expropriation elaborate for the section of the motorway on Corridor Vc: Putnikovo brdo – Medakovo and Ozimica (Želeća) – Poprikuše (Golubinja);

100.000 100.000

8. Professional counselling for the selection of the technical solutions on the section of the express road Mostar – Široki Brijeg –border of Republic of Croatia;

51.000 10.000

9.

Analysis and adjustment of the existing designs of the motorway Corridor Vc and drafting of the innovated main design: section of Putnikovo brdo – Karuše i Karuše – Medakovo L=8,5km,

1.100.000 1.100.000

10. The main design of the relocation ofDV110kV TS Hadžići - EVP Konjic location Bradina

15.000 15.000

11. The other designs, studies, plans, as well as elaborates for the necessities of obtaining necessary approvals

250.000 250.000

12. The drafting of the Main Design of the express road Prača - Goražde (part of the road) (Conclusion of the Government)

1.200.000 350.000

13. Drafting of the Preliminary and Main design of the express road Mostar – Široki Brijeg – border of the Republic of Croatia

9.500.000 3.000.000

14. The drafting of the Main Design of the motorway: section Medakovo-Ozimica

3.100.000 300.000

15. The drafting of the Main Design of the motorway: section Ozimica-Poprikuše (Žepče south)

2.000.000 200.000

16. Revision of the Main Design of the motorway: section Medakovo-Ozimica

124.000 12.000

Table 5

Page 35: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

35

17. Revision of the Main Design of the motorway: section Ozimica-Poprikuše (Žepče south)

80.000 8.000

Financing by the Conclusion of the Government 1.000.000 500.000

18. Structuring of the design of the section of the motorway Tuzla – Žepče

1.000.000 500.000

TOTAL OF: 21.315.957 7.994.000

Page 36: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

36

Explanation of the planned investment:

1. General design of the corresponding studies of the express road: Mostar – Široki Brijeg

–border of the Republic of Croatia:

Contract for the drafting of the general design and corresponding studies of the express road:

Mostar – Široki Brijeg –border of the Republic of Croatia is signed in June 2017. Within this

contract, in addition to the general design, it is necessary to draft also the corresponding studies

like: Preliminary Environment Impact Assessment, Traffic Study and Preliminary Feasibility

Study. Considering that the deadline for the drafting is 24 months, this activity has taken place

during 2018 and it will finish in 2019.

2. Audit of the Corrections of the existing main design of the express road Lašva – Nević

polje in the area of business zones :

Considering that the main design suffered multiple changes in the process of harmonization with

the spatial plans of SBC and the municipality Vitez, there were delays with the selection of the

consultant. At present, the tender procedure is in the progress for the selection of the auditor of

the main design and until the end of the year is expected the beginning of the realization of this

activity, while the remaining part of the contract will be realized in the beginning of 2019.

3. The drafting of the preliminary design and pre-feasibility study of the modernization of

the existing road and raising to the level of the express road border of Croatia – Bihać –

Ključ 125km:

This section of the express road includes the stretch from the border of Croatia in Izačić across

Bihać to Ključ, that is, until the connection with the entity border. For this section of the express

road in the previous period was not drafted one relevant study-design documentation. Within

this design, it is necessary to draft Preliminary Design with Pre-feasibility study of the

modernization of the existing road, that is, gradual lifting of the level of the existing road up to

the level of the express road. Period for the drafting is 12 months.

4. Professional counselling for the selection of the technical solutions of modernization of

the existing road up to the level of the express way border of Croatia – Bihać – Ključ:

Considering that the Law does not provide the audit of the Preliminary Design, for the purpose

of the quality realization of the design, in the later phase will be engaged external counsellors. It

is planned that their engagement on this design will be continuous during the entire process of

drafting of the design documentation.

5. The drafting of the preliminary design and feasibility study for the section of the express

road bypass Bihać – Cazin – Velika Kladuša –Republic of Croatia:

This section is located at the arm of the express road from Kamenica in the vicinity of Bihać

across Cazin and Velika Kladuša all do way to the border with the Republic of Croatia in the

vicinity of the inhabited place Miljkovići. According to some knowledge, PE Ceste FBiH in the

previous period, performed certain design documentation for this section, but at the level of the

main road, which could serve as a baseline. Within this contract it is necessary to draft a

Preliminary design with the environment, traffic and feasibility study of the modernization of the

part of the existing road and the remaining part of the newly built road, with the possibility of the

gradual lifting of the level of the express road with the intersections above the level.

Page 37: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

6. Professional counselling for the selection of the technical solutions at the section

of the express road Bypass Bihać – Cazin – Velika Kladuša –border of the RC:

During the drafting of the design documentation of the motorway it is anticipated the

inclusion of the external counsellors. It is planned that their engagement on this design

would be continuous during the whole process of the drafting of the design

documentation.

7. Drafting of the expropriation elaborate for the section of the motorway on Corridor

Vc: Putnikovo brdo – Medakovo i Ozimica (Želeća) – Poprikuše (Golubinja);

This item represents a continuance of the activities started in 2018. The design of the

section Putnikovo brdo – Karuše – is done in 2010 and taken over from the Ministry of

Communications and Transport of BiH. It is not performed the expropriation elaborate for

the same. The Preliminary Design of the section Ozimica (Želeća) – Poprikuše

(Golubinja) is in the procedure of adoption of the Spatial Plan of the special markings

which is of significance for the Federation of BiH –Motorway at Corridor Vc, has endured

certain changes and it is necessary to draft a corrections of the existing design in the

length of approximately 1.1km and a new expropriation elaborate.

8. Professional counselling for the selection of the technical solutions on the section

of the express road Mostar – Široki Brijeg –border of the Republic of Croatia;

During the drafting of the design documentation of the express road, it is anticipated the

inclusion of the external counsellors. It is planned that their engagement on this design

would be continuous during the whole process of drafting of the design documentation.

9. Analysis and adjustment of the existing designs of the motorway Corridor Vc:

section Putnikovo brdo – Karuše i Karuše – Medakovo L=8,5km,

Design of the section Putnikovo brdo – Karuše –is done in 2010 and it is taken over from

the Ministry of Communications and transport of BiH. Considering on the previous time

period as well as the need of harmonization with the applicable technical specifications,

it is necessary to perform the analysis and adjustment-correction of the existing designs,

that is, to perform new main design (geodetic designs, geotechnical, the designs of

relocation of the roads, designs of the facilities and installations, environmental and

other studies and etc.,). The Design of Karuše - Medakovo is performed at the level of

the preliminary design and already in 2014 has been procured an urban permit for it. For

this subsection, it is necessary to perform a complete main design. The mentioned

designs should be united and brouth to the same level of elaboration in order to be able

to be contracted to red FIDIC.

10. The main design of relocation ofDV110kV TS Hadžići - EVP Konjic location

Bradina

For the needs of obtaining of the construction permit for the section of the

motorwayTarčin – Ivan, it is necessary to do the design of relocation of the transmission

line pillars.

11. The other unforeseen designs and studies are related on the designs of the access

roads, unforeseen designs of the landslides, new local roads, relocation of installations

and other designs, studies, additional plans of managing the waste as well as the

elaborates for the necessities of procuring of the necessary approvals.

12. The drafting of the Main Design of the express road Prača - Goražde (part of the

road):

By the completion of the drafting of the preliminary design, it is planned the drafting of

the main design of the remaining part of the express road (except the tunnel Hranjen)

Page 38: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

38

from Prače to Goražde. Within the contract it should also be anticipated the audit of the

main design.

13. Drafting of the Preliminary and Main design of the express road :Mostar – Široki

Brijeg – border of RC(L= 63 km):

By the finalization of the drafting of the first part of the design of the preliminary solution,

it is planned a drafting of the preliminary and main design and the corresponding studies

of the express road: Mostar- Široki Brijeg - border of the RC. Within the contract it should

also be anticipated the audit of the main design.

14. The drafting of the Main Design of the motorway section Medakovo-Ozimica

The Design of Medakovo-Ozimica is performed at the level of the preliminary design

and already in 2014 has been procured an urban permit for it. For this subsection, it is

necessary to perform a complete main design in order to be able to be contracted to red

FIDIC.

15.The drafting of the Main Design of the motorway section Ozimica-Poprikuše

For the section of the Ozimica - Poprikuša motorway, a preliminary design is performed

in 2014. For this section, it is necessary to perform a complete main design in order to

be able to be contracted to red FIDIC.

16.Audit of the Main Design motorway section Medakovo-Ozimica

For the purpose of issuing construction permits, in accordance with legal provisions, it

is necessary to perform an audit the main project of this section of the motorway.

17.Audit of the Main Design motorway section Ozimica-Poprikuša

For the purpose of issuing construction permits, in accordance with legal provisions, it

is necessary to perform an audit the main project of this section of the motorway.

18.Structuring of the design of the section of the motorway Tuzla - Žepče

Tuzla – Žepče Motorway is the part of the network of motorways of the Federation of BiH and

it represents a continuance of the future motorway Orašje – Tuzla. The start of the section is

defined by the interchange in the area of the settlement Mihatovići (municipality of Tuzla) and

it includes the territories of the municipalities Lukavac, Banovići, Zavidovići and Žepče where

it is linked with the interregional hub on Corridor Vc.

Until today, it is performed feasibility study, the environmental impact study and the

preliminary design and it is also obtained the Environmental permit.

The estimated value of the construction of this motorway is 800 millions of euros.

Considering that the planned assets of the Government of FBiH) anticipated for the

construction of this motorway are insignificant in relation to the overall investment, it is

imposed the necessity of defining of the priority of the construction and in accordance with it

the adaptation and structuring of the existing design.

With the business plan for these intentions is foreseen 1 million BAM, of which 0.5 million

BAM would be spent in 2019 and the rest of 0.5 millions in 2020.

6.2.2. Services of the designing of the motorway on Corridor Vc and which should be financed from IPA funds or from the assets of WBIF

At the end of 2017 through the Investment Framework for the Western Balkans (WBIF) -

18.round, it is submitted the application for the technical assistance for:

updating of the existing main design of the motorway Ivan - Ovčari;

Page 39: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

39

Drafting of the main design of the motorway Ovčari – tunnel Prenj

After the application has been approved by the European Commission as well as the

sent design assignments to their representatives, the realization of these contracts

should start by mid 2019 in the earliest time.

6.2.3. Design services which should be financed from the assets of the Ministry of

Communications and Transport of Bosnia and Herzegovina

Planned design of the Adriatic-Ionian motorway is financed from the assets of the Ministry of Communications and Traffic of Bosnia and Herzegovina:

Planning and study documentation for the Adriatic -Ionian Motorway

(Počitelj (connection on Corridor Vc) – Neum – Trebinje –border of the Republic

of Montenegro)

6.3. Construction plan

Activity plan of the construction of the subsections of the motorway on Corridor Vc and

express roads is given in the following review:

Table 6

Or.No. Name of the investment (section/subsection)

Estimated/ contracted value of the

services

Plan for 2019

1 2 3 5

Financing by the international credits 2.835.312.844 268.118.005

1. Svilaj - Odžak, Stage II 60.000.000 8.000.000

2. Putnikovo brdo - Medakovo 117.349.800 2.500.000

3. Poprikuše - Nemila 352.413.980 18.879.321

4. Nemila - Vranduk 67.671.718 3.806.534

5. Vranduk - Ponirak 133.544.020 35.055.307

6. Ponirak - Vraca ( tunnel Zenica ) 155.412.208 13.987.099

7. Vraca (tunnel Zenica) - D. Gračanica (tunnel Pečuj) 112.602.431 27.869.102

8. Klopče - Donja Gračanica 235.000.000 58.200.000

9. Drivuša - Klopče 59.000.000 750.000

10. Tarčin - Ivan (Lot 1.) 93.488.674 2.000.000

11. Tarčin - Ivan (Lot 2. tunnel Ivan) 92.901.925 13.935.289

12. Tunnel Prenj 460.597.965 5.000.000

13. Mostar north - Mostar south 457.725.144 5.000.000

14. Mostar South - Kvanj 130.971.264 2.500.000

15. Kvanj - Buna (tunnel Kvanj) 191.866.923 5.753.536

16. Buna - Počitelj 42.948.662 27.916.630

17. Počitelj - Zvirovići (both lots) 205.362.150 36.965.187

Financing by the Conclusion of the Government 160.799.990 32.156.228

Page 40: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

40

18. ER Prača - Goražde (Phase I) 69.999.990 15.749.978

19. MW Tuzla - Žepče 33.000.000 3.156.250

Financing by their own assets 20.200.000 15.503.571

20. ER Lašva - Nević Polje (Lot 1. Vitez - Nević Polje) 53.000.000 10.000.000

21. Sarajevo bypass (Lot 3B) 20.000.000 15.428.571

22. External quality control for the contract on the construction of the section Prača - Goražde (Stage I)

180.000 60.000

23. Regional R425a Tromeđa - Zvirovići 4.800.000 3.250.000

24. External quality control for the contract on the construction of the regional road R425a Tromeđa- Zvirovići

20.000 15.000

TOTAL OF: 3.016.312.834 315.777.804

Page 41: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

41

Explanation of the planned investments:

1. Continuance of the construction of the section Svilaj – Odžak, 10.4 km

The contract with the contractor consortium Strabag AG & Euro-Asfalt d.o.o. & ŽGP

d.d.is signed in November 2013. For construction supervision was engaged Aecom

Inocsa. Considering that by the end of 2017 was not obtained the amendment of the

Approval for the construction of the border crossing Svilaj, these works as well as the

works at the toll station Odžak and the rest stop Vrbovački Lipik are transferred in

2018 with the planned start on 15 March 2018. Considering that the Amendment of

the approval for construction was not obtained in time, the works in the zone of the

Border crossing have started with significant delay. It is made an agreement with the

Indirect Taxation Administration that PE Autoceste to realize their works in the width

of the motorway subgrade, while the remaining number of works at the border

crossing will implement the Administration itself (which is the construction

implementer of the Border crossing Svilaj).By the end of 2018 will be realized a larger

part of works on this section of the motorway, while for 2019 will remain the

completion of some minor final works and to be performed a final calculation.

2. Putnikovo brdo – Medakovo, 8.5 km

The start of the section is located on the entity line in the zone of Putnikovo brdo and

the end on the interchange Medakovo (including the interchange and toll station). In

addition to the open part of the route, the section covers a small part of the tunnel

"Putnikovo Brdo 2" (on the entity line), Karuše interchange, interchange and lateral

toll station Medakovo and three bridges on the crossings across the Usora River.

Within this section would be performed also the regulation of the Usora River as well

as the relocation of the main road M-4. Due to the separate payment system

between RS and FBiH, at this section would be necessary to anticipate also the

construction of the frontal toll station in the vicinity of Karuše interchange. If all

preparatory activities would be quickly finished, the selection of the contractors and

construction supervision would be expected towards the end of 2019.Anticipated

deadline for the execution of works is 24 months.

3. Poprikuše – Nemila, approximately 5.5 km

The construction of this section of the motorway, except the short parts of the open

route include a large tunnel Golubinja of the length of 3.5 km, the bridge over the

Bosna River and the interchange with the toll station "Poprikuše“. In the second

quarter of 2019 is expected a completion of the tender procedure for the selection of

the contractors and construction supervision of the motorway section Poprikuše –

Nemila, with the planned deadline of completion of 42 months and in this way the

works would be completed by mid 2022. The construction of this subsection would be

contracted by the rules of „design and build (yellow FIDIC).

Page 42: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

42

4. Nemila – Vranduk, 5.7 km In the process is the final phase of the drafting of the design documentation (main

design) for the subsection Nemila – Vranduk. The subsection is of the length of 7.3

km and by the larger part is located on the slope of the right side of Bosna River.

Although it is in question a slightly easier terrain, on the certain locations the route

goes into the potential instable parts of the terrain. In addition to the construction of

the motorway, the design of this subsection includes the relocation of the main road

M-17.

Although the phase of harmonizing of the design documentation with the official

representatives of the local community (city of Zenica and LC Nemila) has already

been completed, a certain groups of citizens appeared, which showed discontent by

the position of the motorway route on this subsection and from this reason, the

tender of the construction of this subsection is not yet completed.

If the problems with the local communities are solved in near future and if the activities

on the tender procedure would run according to the forecasts, in the second part of

2019 could be expected the decision on the selection of the most favourable bidder

for the execution of works and construction supervision at this motorway subsection.

Foreseen deadline of the execution of works is 24 months..

5. Vranduk – Ponirak, 5.3 km

This subsection was located at the morphologically demanding terrain in Vrandučka

kotlina, which by the opened route includes a couple of significant facilities: 1 tunnel, 2

bridges, 3 viaducts and larger number of the supportive and protective structures at

the open route. In the process is the procedure of evaluation of the financial offers for

the selection of the most favourable bidder for the construction of this motorway

subsection. If the activities surrounding the completion of the tender procedure would

go by the usual flow, the signing of the contract for the construction and supervision

could be expected at the start of 2019.Anticipated time for the execution of the works

is 24 months.

6. Ponirak - Vraca (tunnel Zenica), 2.7 km

Tender procedure is in the process for the selection of the contractor and the

construction supervision for the subsection Ponirak – Vraca (tunnel Zenica). The

subsection is the length of 2.7 km and of which tunnel Zenica is 2.5 km. The first

stage of the tender procedure (prequalification) is completed and for a long period of

time it is expected the answer („no objection“)of the creditors (EIB),in order to be

requested financial offers from the bidders that have successfully completed the

prequalification. Although the commitment that the tender procedure is completed as

soon as possible, it is expected that the contracts for the construction and supervision

would be signed in the second quarter of 2019. The anticipated time of the execution

of works is 30 months.

7. Vraca (tunnel Zenica) – Donja Gračanica (tunnel Pečuj), approximately 3.9 km

In addition to the open part of the route, the subsection includes the interchange and

toll station Zenica north, one larger viaduct across the settlements Donja Gračanica

(approx. 400 m), tunnel Hum (likewise around 400 m), two shorter viaducts, tunnel

Vraca (approximately 300 m), and connecting roads towards the centre of Zenica. The

contract for the construction of this subsection is signed on 8 November 2018.

Page 43: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

43

The realization of the construction is to be conducted according to the contract

„design and build“(yellow FIDIC), so before the start of the execution of the works on

this subsection should be drafted a design documentation and to obtain necessary

approvals and authorisation for the construction. Anticipated deadline for the

execution of work is 30 months.

8. Klopče – Donja Gračanica, 5.8 km

The works have officially started on 1 June 2016.This subsection is located in the

area with the extremely complex and in the construction sense, with the exceptionally

unfavourable geology that makes difficult the execution of the earthworks and works

for the insurance of the scarps, cuts and fractures. Unfortunately, after the

implementation of anticipated additional research papers by the Contract, it showed

that the technical solutions foreseen by the Basic (Main) design are not adequately

taken into the account such complex engineering and geological conditions of the

terrain, therefore in some parts it was necessary their replacement, what in certain

extent slow down the execution of works.

In 2018, the works were executed on the route and facilities. Works on the route are

conducted very slowly, because it should previously be amended the design

documentation and this process is at the near end. It is clear that due to the weight of

the geological circumstances also on this subsection the contracted deadline will be

breached. According to the assessment, the works at this section will be prolonged

for the entire 2019. At present it is performed approximately 65% of works including,

regarding the expanded scope of works by the new designs which are as it was

mentioned before had to be altered due to extremely bad engineering and geological

circumstances on the field.

9. Drivuša – Klopče, 2.3 km

In 2018 the works were continued on the construction of the subsection Drivuša-

Klopče.The entire course of execution of works has been followed by problems with

the unfavourable engineering and geological characteristics of the terrain, what

caused certain stagnation of works due to the necessity of the amendment of the

design documentation. These problems have led to the breach of the extended

deadline of construction (15 March 2018), with which are additionally burdened the

contractual relations of the realization of this contract. The works at this subsection

are at the near end and the finalization is expected at the beginning of 2019 and also

including there the final calculation of works. At present is performed approximately

98% of works.

10. Tarčin – Ivan (Lot 1.), 4.9 km

The subsection is on the stretch of the already built intersection Tarčin by the entry

into the future tunnel "Ivan“, which in addition to the open part of the route includes

two larger viaducts of the length 500 and 600 m in the zone of the settlement

Raštelica, the rest of the route is located by the Klašanica River in the vicinity of the

main road M-17 and railroad track Sarajevo - Mostar. If the circumstances

surrounding the tender procedure would go according to theforecasts, it is expected

the decision on the selection of the most favourable bidder and the signature of the

contract for the construction of the motorway subsection Tarčin – Ivan (Lot 1.) at the

end of 2019.Anticipated deadline for the execution of works is 18 months.

11. Tarčin – Ivan (Lot 2. – tunnel Ivan), 2.0 km

Page 44: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

44

The subsection includes the tunnel Ivan in the length of 1.7 km with the portal zones

at the entry and exit. Except the tunnel, the integral part of Lot 2 makes a temporary

connection on the main road M-17 including also a temporary toll station on this

connection. If the activities around the tender procedure would take their course

according to the forecasts, in the first quarter of 2019 is expected the decision on the

selection of the most favourable bidder and the signature of the Contract for the

construction of the motorway subsection Tarčin – Ivan (Lot 2. – tunnel

Ivan).Forecasted deadline for the execution of works is 18 months.

12. Tunnel Prenj

In addition to this capital facility in the length of 10.15 km, the construction of this

subsection would include around 1.150 m of the open route from the north side and

approximately 700m from the south side of the tunnel, in total of 12 km. After the

implementation of the tender procedure is planned the start of the construction of

stage I by which is covered the construction of one (right) tunnel pipe with its

necessary equipment, while on the other pipe would be performed excavation and

primary support with the minimum equipment in order for the same to be used as

evacuation. Secondary coating and equipment of the other pipe would be performed

in stage II which was still not planned. Planned deadline of the construction is 60

months. The construction of this capital facility would be contracted according to the

rules „design and build“ (yellow FIDIC).

13. Mostar North – Mostar South, 15.4 km

The section of the motorway Mostar north – Mostar south is of the length of 15.4 km

and most of its part is located on the slope from the east side of the town above its

peripheral settlements: Vrapčići, Zalik, Mazojice and Opine. After the passage

(tunnel) below the settlement Kočine, the route would drop from the slope into the flat

part from the north side of the airport “Mostar“, where it was planned interchange

Mostar south. The route of this section is in its greater part located at the geological

stable karst terrain and due to the morphological circumstances, the route consists of

the couple of tunnels (the most significant are “Oštri rat“ and “Kočine“), and an array

of viaducts of the shorter and medium length.

In 2019 is planned the implementation of the activity on the preparation for the

construction of the subsection Mostar north – Mostar south, however the beginning of

works on the construction of this subsection is expected at the very end of 2019.

Planned deadline of the construction is 42 months. The construction of this capital

facility would be arranged according to the rules “design and build“(yellow FIDIC).

14. Mostar South – Kvanj (8.5 km)

The subsection of the motorway Mostar south - Kvanj is of the length of 8.5 km and

in accordance with the adopted Spatial Plan of the Special Markings of the FBiH and

in its most part is located in the lowland part of the Mostar polje along Mostar airport

all the way to the crossing over the Buna River towards Malo polje. The subsection

starts with Mostar south interchange with which is realized the connection with the

main road M-6.1 and indirectly with M-17,which is located from the north side of the

airport runway and ends directly before the tunnel Kvanj on the neighbour section of

the motorway. Before that the route crosses the hilly parts of Malo polje. From the

facilities on the route are the most important ones: the bridge over Buna River, which

Page 45: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

45

in addition to the river bridges also the costal tourist and recreational belt along the

river, the bridge across Buna River and one viaduct before the end of the section. In

2019 is planned the implementation of the activities on the preparation for the

construction (implementation of the tender procedure), however, the start of work on

the construction of this subsection is expected at the end of 2019. Planned deadline

for the construction of this subsection is 30 months. The construction of this section

should be realized according to the model „design and build“ (yellow FIDIC).

15. Kvanj – Buna (tunnel Kvanj), 5.2 km

Subsection except the tunnel Kvanj in the length of 2.5 km includes also the viaduct

Rotimski potok in the length of 330 m and the rest of approximately 2 km of the open

route. In the next period will be performed preparations for the implementation of the

tender procedure for the selection of the contractors and supervisions on this

motorway subsection. If the activities around the tender procedure would go

according to the forecasts, in the second half of 2019 is expected the decision on the

selection of most favourable bidder and the signature of the Contract for the

construction of the motorway subsection Kvanj – Buna (tunnel Kvanj). The

construction of this subsection would be contracted according to the rules „design and

build“ (yellow FIDIC). Forecasted deadline of the execution of works is 30 months.

16. Buna – Počitelj, 7.2 km

Motorway section Buna – Počitelj was located on the geologically and

morphologically favourable terrain, sufficiently simple for execution, where besides

the open part of the section is built one overpass and one underpass and one resting

spot on both sides. The contract for the execution of works is signed on 25 May

2018. Due to the delay with the obtaining of the Authorisation for the construction, the

official start of work was on 3 August 2018 and vesting into property on 28 August

2018 and in accordance with it will also be moved the initially planned deadline for

the finalization of works. The preparatory works on this section are already completed

and in 2019 is expected a full swing of works. The contracted deadline of the

execution of works is 18 months.

17. Počitelj – Zvirovići, 11.1 km

The construction of this subsection includes the works of the chainage 0+000 up to

11+075 to which in addition to the open part of the route belongs a great bridge

Počitelj (in the length of 975 m), interchange and toll station Počitelj and several

important facilities on the right side of Neretva River of which the most important

ones are the tunnel Počitelj (1.2 km), three viaducts and continuance of the open

route until the interchange Zvirovići. After the renewal of the tender procedure by the

expedited procedure, the evaluation of the offers for the construction of this motorway

subsection is in the progress. According to the renewed tender, the works are divided

into two lots, where lot 1 covered an open route and facilities from the one and the

other banks of the Neretva River while Lot 2 covered the works on the large bridge

Počitelj. If there were no additional complications at the end of this tender procedure,

it can be expected that in the first quarter of 2019 would be signed contracts for the

construction and supervision on this motorway subsection. Final deadline for the

completion of work is 30 months .

18. Prača - Goražde express road (Lot 1. phase I - tunnel Hranjen)

The section of the express road Prača-Goražde is of the total length of 13.7 km.

Stage I of this express road represents the construction of the semiprofile of the

Page 46: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

46

express road on its entire length. Stage II would include the completion of this road

on the express road full profile and its realization is not foreseen in due time.

Tender procedure for the selection of the contractors for the necessities of the

construction (breaching) of the tunnel Hranjen in the length of 5.8 km, as the most

important facility on this express road is completed, the Contract with the contractor

Euro-Asfalt is signed on 22 September 2018.The subject matter of the tender is the

excavation and the primary support of the main and service tunnel pipe with the

portal zone. Due to the difficulties (a few complaints) in the implementation of the

tender for the supervision over the works, which is still not chosen, the works by this

Contract are still not officially opened and that is the main reason of failure of the

planned realization on this design. The realization of the construction will be

implemented according to the contract "design and build“(yelllow FIDIC). After the

drafting of the design documentation and obtaining of the approval for construction,

the start of executing of the construction works is expected at the beginning of the

spring 2019.Foreseen time limit of execution of work is 36 months.

19. Tuzla - Žepče Motorway

For the motorway in the direction of Tuzla -Žepče is made design documentation at

the level of preliminary design. By the plan is anticipated the starting investments for

the construction and supervision in the amount of 40 million BAM (assets of the

accumulated profit of the public enterprises). By this assets would be covered the

expenses of the study and technical documentation, the expenses of expropriation

that represent a significant item and expenses of the construction and supervision on

execution of works. The assets foreseen by the plan enable the construction of the

first stage (semiprofile) of this motorway on the section from the settlement Mihatović

to the interchange Lukavac, with which would be achieved the relieving of the existing

transport network in the zone from Šićki Brod to Mihatovići. Planned assets for the

construction of this motorway subsection are not still operative and that is the basic

reason why the tender procedure for the construction of this section is not initiated.

If the planned activities would take its course without the additional difficulties and

financial assets for the construction are secured, the opening of the works is

expected in the second half of 2019.

20. Express road Lašva - Nević Polje (Lot 1. Vitez – Nević Polje)

Page 47: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

47

Lašva – Nević Polje route is a part of the new expanded European network of the

express roads so called route 2A Okučani (HR) – Banja Luka – Jajce – Travnik –

Lašva.

The section of this express road Lašva – Nević Polje for which has already been

drafted design documentation (main design) is in the length of 24.5 km. In 2019 is

planned the implementation of the tender procedure for the selection of the

contractors and supervision for the construction of Lot 1 Vitez – Nević Polje in the

length of 5 km. In order for this stretch to be integrated in the existing transport

network, it would be necessary to built interchanges on the beginning and at the end

of this subsection through which would be made a connection with the existing

transport infrastructure. For the implementation of this concept was necessary the

adjustment of the design documentation which is currently in the final phase. Due to

delay with the submission of the design documentation, the tender for the

construction of this subsection of the express road is still not published. If the

mentioned problems would shortly be resolved and the tender procedure passes

without delay, the opening of the works on this stretch of the express road could be

expected in the second half of 2019. Indicative time limit for the execution of work is

24 months.

21. Sarajevo bypass (Lot 3B), 1.5 km

The significance of the construction of the mentioned road is based on the need of

transport connection of the Sarajvo bypass with the roads of the lower rank. It is

stretched from the interchange Vlakovo to the access road to the roundabout

Mostarsko raskršće.

This four-track road will be in the length of approximately 1.5 km and in addition to

the open part of the route includes also two viaducts in the length of 145 m. Tender

procedure for the selection of contractors and supervision is in the progress. In

several occasions the tender procedure was interrupted and continued after the filing

the complaints and that is the basic reason of failure to fulfil a planned realization. If

there weren't any problems in the implementation of the tender procedure, in the

beginning of 2019, it is expected the start of realization of works on the construction

of Sarajevo bypass (Lot 3B).

22. and 24. External control for the contract on the construction of the section

Prača – Goražde (tunnel Hranjen) and regional road R425a Tromeđa – Zvirovići

Within the contract for the construction, the Contractor is obligated to organize

Contracting (internal) quality control. The scope of the Contracting quality control is

defined by the Technical specifications by the type and quantity of testing which the

Contractor is obligated to perform. The obligation of the Investor is to provide the

Investors (external) quality control which is by the structure the same to the

Contractors quality control and by the scope is approximately 20-25% of the scope of

the Contractors quality control.

External control is specially contracted when the procurement of the contractor is

performed through local procedures of procurement prescribed by the Law on Public

Procurements of BiH.

23.Rehabilitation of the regional road R425a on the section Tromeđa – Zvirovići,

5.8 km

Page 48: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

48

According to the Decision of the Government of FBiH, it is anticipated the

rehabilitation of the Regional road R425a on the stretch from Tromeđa (Međugorje)

to Zvirovići, with which would be improved the communication connection from

Međugorje as an important tourist place to the interchange Zvirovići, that is, access

road on the motorway of Corridor Vc. Within this contract would be also performed

the medium voltage power supply for the interchange and toll station Zvirovići, on the

section Počitelj – Bijača. Tender for the selection of the contractor and supervision is

performed in the mid 2018. Due to the difficulties (a few complaints) in the

implementation of the tender, the works by this Contract are still not open. It is

expected that the tender will still be successfully finalized and that in 2019 will occur

the realization of this design.

6.4. Supervision service plan

Supervision activity plan on the construction of the motorway subsection on Corridor

Vc and express roads follows the activities on the construction and it is given in the following

review:

Table 7

Or.No. Name of the investment (section/subsection)

Assessed/ contracted

value of services

Plan for 2019

1 2 3 5

Financing by the international credits 111.979.555 16.704.171

1. Putnikovo brdo - Medakovo 6.845.405 250.000

2. Poprikuše - Nemila 11.734.980 1.760.247

3. Nemila - Vranduk 2.738.162 308.043

4. Vranduk - Ponirak 4.693.992 1.760.247

5. Ponirak - Vraca ( tunnel Zenica ) 6.258.656 1.126.558

6. Vraca (tunnel Zenica) - D. Gračanica (tunnel Pečuj) 4.742.614 1.707.341

7. Klopče - Donja Gračanica 9.149.177 3.000.000

8. Drivuša - Klopče 5.556.423 90.000

9. Tarčin - Ivan (Lot 1.) 4.302.826 200.000

10. Tarčin - Ivan (Lot 2. tunnel Ivan) 4.889.575 1.173.498

11. Tunel Prenj 15.500.000 250.000

12. Mostar north - Mostar south 6.336.889 250.000

13. Mostar South - Kvanj 9.583.567 250.000

14. Kvanj - Buna (tunnel Kvanj) 9.500.000 1.674.724

15. Buna - Počitelj 2.564.289 1.538.573

16. Počitelj - Zvirovići (both lots) 7.583.000 1.364.940

Financing by the conclusion of the Government 4.375.000 1.110.000

17. Tuzla - Žepče Motorway 2.000.000 325.000

Financing by their own assets 4.500.000 2.057.143

18. Regionale R425a Tromeđa - Zvirovići 375.000 260.000

Page 49: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

49

19. Lašva - Nević Polje Express Road (Lot 1. Vitez - Nević Polje)

2.000.000 525.000

20. Prača - Goražde Express Road (Stage I) 3.000.000 900.000

21. Sarajevo Bypass (Lot 3B) 1.500.000 1.157.143

Financing by the grant assets 1.983.701 75.000

22. Svilaj - Odžak, Stage II 1.983.701 75.000

IN TOTAL OF: 122.838.256 19.946.314

Explanation of the planned activities:

The activity plan of the selection of the consultants for the services of supervision on

the construction of the motorway and express roads subsections is synchronized with the

planned activities of the selection of the Contractor.

Note: In 2019 is planned the start of construction of the certain sections, therefore it

is planned the disbursement of the advances for the construction and supervision services

for the motorway section. In the above mentioned reviews, by the activities that relate on the

construction and supervision over the construction is stated a planned realization.

6.4.1. Engagement of the consultants for the management design

Engagement plan of consultants for the Design management on the construction of the

motorway subsections on Corridor Vc and express roads follows the activities on the

construction and it is given in the following review:

Table 8

Or.No. Name of the investment

The value of the contract/assessment

in BAM (without VAT)

Plan for 2019 in VAT

(without VAT)

1 2 3 4

Financing by the international credits 6.191.624 1.984.094

1. Poprikuše - Nemila 2.346.996 586.749

2. Tarčin - Ivan (Lot 2. - tunnel Ivan) 1.564.664 531.986

3. Poćitelj - Zvirovići 586.466 216.992

4. Ponirak - Vraca (Tunnel Zenica) 1.173.498 449.282

5. Tunnel Kvanj - Buna 520.000 199.086

Financing by its own funds 960.000 341.009

6. Vraca (tunnel Zenica) - D. Gračanica (tunnel Pečuj) 520.000 160.457

7. Nemila - Vranduk and Vranduk - Ponirak 440.000 180.552

IN TOTAL OF: 7.151.624 2.325.104

Explanation of the planned services:

Page 50: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

50

Due to the scope of the planned activities on the construction of motorway and express

road subsections, it is planned the engagement of the consultants for Design Management -

technical assistance.

Technical assistance is, initially conditioned by the EIB for the designs which are

implemented from the assets of the mentioned bank. That model is due to unifying of the

access of contract management is transferred on the other financiers ( EBRD,OFID ).

In the process is the tender procedure for the selection of consultants for the design

management - technical assistance for the subsections mentioned in the table.

6.5. Management and maintenance

Management and maintenance of the motorway has an exceptionaly important role in

the organization of work of PE Autoceste because the responsibility is concentrated on the

safety and protection of the users of the motorway but also on the collection of the service to

the users of motorway A1.

Main activities on the management and maintenance of the motorway are regular

and winter maintenance of the constructed part of the motorway, the implementation and

monitoring of functioning of the closed collection system, and monitoring and management

of the traffic on the motorway, protection of the motorway from the excessive traffic load,

uncontrolled construction by the motorway, setting up the advertisements and others and all

for the purpose of secure and undisturbed traffic development.

The constructed part of the motorway A1 managed by PE Autoceste FBiH is in the

length of approximately 91 km, and includes the section Zenica south – Tarčin uin the

length of 81 km and the section Međugorje – Bijača in the length of approximately 10

km. In addition to the mentioned sections, PE Autoceste FBiH are in charge also for

management and maintenance of the constructed part of the motorway 1 Butila -

Briješće in the length of approximately 3.5 km. In the next period is expected the

finalization of work and opening to the traffic of the sections of the motorway A1 Svilaj

– Odžak and express road BC1.

6.5.1. Services in the domain of motorway maintenance

Table 9

Or.No. Name of the activities

Contracted/ estimated value of

works/services without VAT

Plan for 2019 without VAT

(BAM)

1 2 3 4

1. Regular and winter maintenance of the motor way and maintenance of the facilities of building construction on the toll stations

3.677.000 3.227.000

2. Works on the repair of the pavement structure, facilities and replacement of the equipment on the facilities

3.712.900 3.456.800

3. Services of the drafting of the design documentation and supervision on the works of the repairs

390.000 380.000

Page 51: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

51

4. Monitoring of the elements of the environment and the reviews of the facilities and structures on the motorway

690.600 557.600

5. Maintenance of the devices and equipment for the fire protection and occupational health and safety

296.000 296.000

6. Maintenance of the electrical and machine installations and devices

400.000 400.000

7. Maintenance of the vehicles and working machinery used by SUiO

142.000 89.000

TOTAL FROM THE DOMAIN OF MAINTENANCE: 9.308.500 8.406.400

Explanation of the planned activities:

1. Regular and winter maintenance of the motor way and maintenance of the

facilities of building construction on the toll stations;

The activity is related on the regular and winter maintenance of the constructed part

of the motorway on the section Zenica south – Tarčin in the length of approximately

81 km and the section Zvirovići – Bijača in the length of approximately 10 km, as well

as the Express Road 1 Butila – Briješće in the length of 4.5 km, as well as the

regular maintenance of the facilities of the collection and maintenance and the

procurement of the material for the exchange in the system of waste water treatment.

2. Works on the repair of the facilities and replacement of the equipment on the

facilities;

The activity includes the repair of the bridge MO6 on the section Podlugovi –

Sarajevo north, fixing the support wall in Tarčin, as well as the works of the repair of

the drainage, removal of the facilities in the protective belt of the motorway, execution

of work and supervision on the replacement of the transitional devices on the

bridges, horticultural landscaping on the motorway, works on the repair of the

landslides at the toll station Sarajevo west.

3. Services of the drafting of the design documentation and supervision on the

works of the repairs;

Services of the drafting of the design documentation relate on the drafting of the

design documentation for the repair of the pavement structure and facilities as well

as the supervision over the repair works, the drafting of 3D model of the route and

design of the noise protection walls, drafting of the designs, studies and elaborates

for the extraordinary/unforeseen activities.

4. Monitoring of the elements of the environment and the reviews of the facilities

and structures on the motorway;

The item is related on the geotechnical monitoring of the existing inclinometer

installations along the motorway as well as the main inspections of the facilities for

bridging and transport structures and control testing of the environmental elements

according to the environmental permits and control measurement of the built-in

geotechnical anchors.

5. Maintenance of the devices and equipment for the fire protection and

occupational health and safety;

It is necessary to regularly conduct periodical reviews and control testing of the

devices for the fire protection as well as the servicing of the system of fire alarm and

gas detection in all facilities where they are installed, regular maintenance of the fire-

Page 52: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

52

fighting vehicles, regular and extraordinary servicing and maintenance of the special

fire-fighting equipment and replacement of the defective doors on SOS recesses in

the tunnels Vukov Gaj and Oštrik.

6. Maintenance of the electrical and machine installations and devices;

Maintenance of the electrical and machine installations and devices is related on the

maintenance of the lightning, transformer substations, medium voltage and low

voltage electric equipment, as well as the air-conditioning, ventilation and heating

and tunnel fans, diesel electrical generators and UPS devices, maintenance of the

air-conditioning system, ventilation, heating and similar.

7. Maintenance of the vehicles and working machinery used by SUiO Item relates on the procurement of the spare parts and regular maintenance for all

vehicles and work machines used by SUiO.

Page 53: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

53

6.5.2. Services in the domain of toll payment

Table 10

Or.No. Name of the activity

Contracted /estimated

value of works/services

without VAT

Plan for 2019 (without VAT)

1 2 3 4

1. Maintenance and follow-up of the system of toll payment on all sections of the motorway A1

2.496.475 1.385.000

2. Material, equipment and devices procurement for the needs of the work of the toll payment system on the motorway A1

657.400 657.400

3. The other activities 391.000 361.000

TOTAL FROM THE DOMAIN OF PAYMENT: 3.544.875 2.403.400

Explanation of the planned activities:

1. Maintenance and follow-up of the system of toll payment on all sections of the

motorway A1;

Activity relates on the maintenance and follow-up of the toll payment system on all

sections of the motorway, maintenance of the backup safety solutions as well as the

services of the receipt of the bank cards on the toll payment system. Considering the

importance and correctness of functioning of the toll payment system on all motorway

sections A1, all activities on the regular, extraordinary and intervention maintenance

of the implemented system of toll payment on the motorway A1 are conducted and

should be conducted continuously. This assessment for 2019 is planned in relation to

the annual contracts as well as the three-year contract for the maintenance of the

software part of the toll payment system on all motorway sections.

2. Material, equipment and devices procurement for the needs of the work of the

toll payment system on the motorway A1;

The activity is related on the procurement of the material, equipment and devices

which are necessary for proper functioning of the toll payment system on the

motorway A1 and includes the procurement of the magnet cards, banking equipment

and spare parts for the needs of toll payment, bank bags for packing money and for

the procurement of the thermal and adding rolls, ribbon tapes of the encoders of

cards, road barriers/bars for ramps of the toll payment, procurement of ACC TAG

devices and other materials and services necessary for functioning of the toll

payment system.

3. The other activities;

The other activities that include items like the procurement of the petroleum products

and other accompanying goods for the official vehicles, maintenance of the hygiene

and cleanness of the facilities of PE Autoceste FBiH, servicing of the internal petrol

stations on COCT Drivuša and COCT Zvirići.

6.5.3. Services in the domain of motorway management

Table 11

Page 54: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

54

Or.No. Name of the activities

Contracted/ estimated value of

works/services without VAT

Plan for 2019 without

VAT(BAM)

1 2 3 4

1. Maintenance of the system of motorway management and remote supervision over the tunnels on all sections of the motorway

5.632.000 2.942.000

2. IT system maintenance for the support of the management system and auxiliary systems

240.100 240.100

3.

Drafting of the design documentation for the expansion of the functionality of the management system and improvement of the safety of the traffic on the motorway

43.000 43.000

4. Activities for the improvement of the safety of the traffic on the motorway

57.000 57.000

TOTAL FROM THE DOMAIN OF MANAGEMENT: 5.972.100 3.282.100

Explanation of the planned activities:

1. Maintenance of the system of motorway management and remote supervision

over the tunnels on all sections of the motorway;

The maintenance of the motorway management system and remote supervision over

the tunnels on all sections of the motorway A1, it is necessary in order that the

system could function correctly and without delay. The activity also includes the

maintenance of the verification video supervision and mandatory training for fire-

fighters and patrolmen. This assessment for 2019 is planned in relation to the annual

contracts as well as the three-year contract for the maintenance of the software part

of the supervisory system and traffic management on all sections of motorway A1.

2. IT system maintenance for the support of the management system and

auxiliary systems;

The activity is related on the IT system maintenance that serves as the support of the

management system and includes: maintenance of the network infrastructure

system, and system for the storage of data and server infrastructure, optical cable of

the main road, rent of the professional industrial links and the installation of the user's

software and accompanying infrastructure for the binding and remote reading of the

built-in digital measurement devices in the transformers substations.

3. Drafting of the design documentation for the expansion of the functionality of

the management system and improvement of the safety of the traffic on the

motorway;

Design documentation for the measurement of the height of the vehicle on the

motorway A1, the drafting of the design documentation for the replacement of the

lightning bodies with the high pressure light bulbs with the lightning bodies in LED

technology as well as the drafting of the design documentation for the improvement

of safety on the motorway.

Page 55: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

55

4. Activities for the improvement of the safety of the traffic on the motorway;

The item includes the removal of the effect of aquaplaning on the bridge M6 of the

section Podlugovi – Sarajevo north, the procurement of BAS standards from the area

of the traffic and technical equipment, the procurement of the temporary traffic

signals and equipment as well as the correction of the fences on the connections of

the route and bridges.

6.6. The other capital investments 6.6.1. Capital investments in the domain of management, maintenance and toll payment

Table 12

Or.No. Name of the activity

Contracted/ estimated value of

works/services without VAT

Plan for 2019 without

VAT(BAM)

1 2 3 4

1. Upgrade of the management system and traffic supervision on the motorway with the implementation of ITS

5.650.000 5.650.000

2. Execution of works on the construction of the walls for the protection from the noise

17.500.000 14.000.000

3. Procurement of the fire-fighting vehicles and equipment for the fire-fighting unit of PE AC

1.800.000 1.800.000

4. Procurement of the working machines, tools and equipment for the maintenance of the motorway

2.061.000 2.061.000

5. Reconstruction and arrangement of the business facilities in the ownership of PE Autoceste FBiH

226.000 226.000

6. Procurement of the equipment for the improvement of the traffic safety on the motorway

1.350.000 1.350.000

7. Hardware and software solutions and services for the needs of IT system

2.195.000 2.195.000

8. Procurement of the electrical equipment and installation for the maintenance of the motorway

528.000 528.000

9.

Drafting of the design documentation for the expansion and improvement of the work of the system in the maintenance and management of the motorway

693.000 693.000

10. Test upgrade of the new technologies in the payment system

300.000 300.000

11. The other capital investments 246.000 246.000

TOTAL OF THE CAPITAL INVESTMENTS : 32.549.000 29.049.000

Explanation of the planned investments:

1. Upgrade of the management system and traffic supervision on the motorway

with the implementation of ITS;

The activity relates on the implementation of the system for the measurement of each

vehicle on the motorway A1, and implementation of ITS on the built-in section of the

Page 56: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

56

motorway Bilješevo – Jošanica, where in the past was not implemented this system

and on the section of the express road Butila – Briješće.

2. Execution of works on the construction of the walls for the protection from the

noise;

The activity relates on the execution and supervision of works on the construction of

the noise barriers on the section Podlugovi – Visoko, as well as execution of works

and supervision over the execution of works on the replacement of the damaged

layers of the pavement structure on the section Podlugovi – Sarajevo north.

3. Procurement of the fire-fighting vehicles and equipment for the fire-fighting

unit of PE AC; PE Autoceste has the obligation to procure fire-fighting vehicles with

the equipment for the fire extinguishing, rescuing in the tunnels and motorways, for

the needs of the professional fire-fighting unit of AC. The members of the

professional fire-fighting unit of AC are in the framework of the operational and other

operations established by the Law on the Fire Protection and Fire-fighting obligated

to provide that in every moment and in all conditions be ready for the timely and

efficiently fire extinguishing and protection and rescuing people and material goods

on the territory of the motorway A1.

4. Procurement of the working machines, tools and equipment for the

maintenance of the motorway;

The item relates on the procurement of the tool for the needs of the maintenance of

the fire-fighting equipment and occupational health and safety, procurement of the

equipment and tools for the maintenance of the payment system, supervision and

motorway management, procurement of the tools, diagnostic tools and small

consumables for the needs of the internal maintenance departments, procurement of

the equipment for the expanded functionality of the camera and devices for the

examination of the drainage system and the procurement of the multipurpose vehicle

for the needs of motorway maintenance .

5. Reconstruction and arrangement of the business facilities in the ownership of

PE Autoceste;

The activity relates on the reconstruction and arrangement of the facilities in the

ownership of PE Autoceste FBiH, the adaptation of the archive storage in Zvirići,

procurement of the furniture for the equipment of the business facility in Briješće, the

drafting of the design of conversion of the premises into the warehouse on COCT

Drivuša and equipment of the warehouse according to the design documentation.

6. Procurement of the equipment for the improvement of the traffic safety on the

motorway;

Procurement of the equipment for the improvement of the traffic safety on the

motorway includes the procurement of the devices for the distraction of the entrance

of the animals on the motorway and the procurement of the blow dampers and the

procurement and installation of the safety rail.

7. Hardware and software solutions and services for the needs of IT system;

The procurement relates on the procurement of the servers and server equipment

(primarily due to the replacement of the old servers and server equipment due to the

expiry of the service life limit), procurement of the network equipment as well as the

other services and equipment for the needs of IT system. It is about the key systems

like: toll payment system, management system and motorway supervision etc.

8. Procurement of the electrical equipment and installation for the maintenance

of the motorway;

Page 57: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

57

Procurement of the electrical equipment and installations for the motorway

maintenance relates on the construction of medium voltage cable connections of TS

as well as the replacement of the lightening bodies with the classical light bulbs with

the lightening bodies in LED technology.

9. Drafting of the design documentation for the expansion and improvement of

the work of the system in the maintenance and management of the motorway;

The item includes the activities which have the purpose of adoption of the systematic

solutions and improvements in the management processes and motorway

maintenance. In addition to the rest is foreseen the drafting of the instructions and

standards for the regular and winter motorway maintenance, the drafting of the

drainage system management plan, the supervision over the implementation of ITS

and the audit of the main design of ITS on the section of the Sarajevo bypass

Briješće-Butile.

10. Test upgrade of the new technologies in the payment system;

Within the framework of the item is planned the testing of the newer and more

contemporary system for the toll payment, which has numerous advantages in

relation on the existing toll payment system, with which would be accelerated and

simplified the payment process and with it also the service quality to the users of the

motorway would be lifted on the higher level.

Test platform for the implementation of RFID technology includes the electronic

payment via RFID sticker( e–TAG ) free flow trolling payment model. It includes

undisturbed movement of the vehicle by the motorway without the need of stopping

or slowing down, in order to be calculated the toll payment. The model is based on

the post-paid calculation.

11. The other capital investments

The item includes the activities related for the improvement of work of the

Department of Logistics, supply management and support to business. The

improvements in work of the toll payment are also planned which would be realized

by the procurement of the smart safes with which would be enabled faster and more

secure depositing money on the bank accounts for the employees . 6.6.2. Capital investments in the domain of IT

Table 13

Or.No.

Name of the Activities

Contracted/ estimated value

of works/services

without VAT

Plan for 2019

without VAT(BAM)

1 2 3 4

1. Procurement of the software solutions and licencing assumptions necessary for the business operations

980.000 960.000

2. Procurement of the computer equipment, printers, MFU/MFP devices, server, network and various other diagnostic equipment and tools

238.000 238.000

3. Procurement of the Document Management System (DMS)

650.000 600.000

IN TOTAL OF: 1.868.000 1.798.000

Explanation of the planned activities:

Page 58: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

58

1. Procurement of the software solutions and licensing assumptions necessary for the

business operations includes the procurement /upgrade of the information systems like

ERP (new software modules for IFIS –Integral Financial Information System, OWIS –

Workflow Document Management System for the new employees and modelling of the

new business processes, procurement of the new Microsoft operation systems by the

expiration of Windows XP and similar). In these activities are included also the

activities on the expansion of the support information infrastructure and GIS for the

needs of the Enterprise.

2. The procurement of the computer equipment printers, MFU/MFP devices, server,

network and other diagnostic equipment and tools includes the activities of the

procurement of the new units, printers, servers, switches, routers and similar equipment

necessary for the work of the local systems. Also, this activity involves the procurement

of the diagnostic equipment (devices for the measurement of the installation quality)

and various tools necessary for the conducting of this work.

3. Document Management system DMS is the process of planning, implementation and

maintenance of Document Management System for the needs of monitoring of the

construction designs as a key factor for the construction of the new sections of the

Motoway Vc. It is planned that the implementation of this system results with the better

coordination of the construction plan as well as the early detection of the short

deadlines or some unplanned delays.

6.6.3. The other capital investments

Table 14

Explanation of the planned activities:

1. Procurement of the official vehicles – Considering the deterioration of the vehicle fleet

and the fact that the higher number of vehicles in PEAC due to the number of the

mileage and deterioration of the parts is no longer safe and cost-effective in the sense

of the investment in the same, it is necessary the procurement of the new vehicles, as

for the safety in the traffic of the employees and for the savings which would be

Or.No. Name of the Activities

Contracted/ estimated value

of works/services

without VAT

Plan for 2019 without

VAT(BAM)

1 2 3 4

1. Procurement of the official vehicles 800.000 800.000

2. Equipment of the achieve storage on Bijača and Mostra 50.000 50.000

3. Procurement of the design, land/facility for the commercial construction in Mostar

2.850.000 2.850.000

4. Procurement of the office furniture 80.000 40.000

5. Main design of the reconstruction of the business facility besides the roundabout Briješće

13.250 1.325

6. Reconstruction of the business facilities Briješće 770.000 770.000

7. Procurement of the furniture for the equipment of the business facility in Briješće

100.000 100.000

TOTAL OF: 4.663.250 4.611.325

Page 59: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

59

realized by the termination of the investment into the deteriorated vehicles. In 2019 is

planned the procurement of 15 passenger vehicles.

2. The equipment of the archieve storage on Bijača and Mostar–it is necessary due to the

satisfying the standards of the archival materials and longterm solution for archiving of

the materials of PE Autoceste.

3. In 2019 is planned the initiation of the activities for the procurement of the designs,

land or the existing facility and design of the existing facility for the residence of the

business premises in Mostar .

4. Procurement of the office furniture - in the fourth quarter of 2018 is initiated the

procurement of the furniture in the amount of BAM 80.000.00. In 2019 is planned to be

signed the contract and to perform the procurement of the same.

5. Main design of reconstruction of the business facility besides the roundabout Briješće -

finalizing of the activity on the drafting of the main design.

6. The activities relate on the reconstruction of the busiiness facility Briješće, execution of

works and supervision over the execution of works. Reconstruction of the business

facility is performed due to the planned relocation of one part of the services of the

Sector for Management and Maintenance and whose work is related for the motorway

route itself.

7. The procurement of the furniture for the equipment of the business facility in Briješće is

planned after the finalization of the activities of facility reonstruction.

6.7. Standardization and work improvement

In 2019 is planned additional optimization of the documentation in accordance with the

requests of the new version of the standards ISO 9001:2015 and ISO 14001:2015. By the

further improvement in this period would be lifted the level of support to the management of

the enterprise and continued improvement of the business organization and working

processes as well as the increase of the reputation of the enterprise. Regular course of the

activities will be reflected in the internal audits two times a year, to the supervisory,

certification and recertification audits of the implemented systems, continued education of

the employees in the enterprise, by the annual surveys of the service users pleasures, by

monitoring the realization of monitoring of the given environmental parameters (noise, water,

ground), by the improvement of the realization of the activities on delivery of the various

types of waste, the preparation and participation in the annual reviews of IMS by the

administration, recognizing the problems in business and proposing the solution for the

same as well as the supervision over the implementation of the initiated corrective

measures, on the basis of the identified discrepancies and improvement proposals.

Internal audits–In accordance with the standards' requests and good business practice

due to the control, promotion and improvement of business are conducted regular audits on

the annual level. The results of the same are proposals for the improvement, removing of the

discrepancies and bases for re-examination by the IMS administration.

7. PROJECTION OF THE REVENUES AND EXPENDITURES

7.1. Revenues

Table 15

Page 60: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

60

Or.No. Name of the revenue Plan for 2019

1 2 3

1. Revenue from excise tax 171.959.040

2. Alignment of the excise tax on fuel 25.000.000

3. Revenue from the toll 37.210.000

4. Revenue from the compensation for the use of the road land 601.495

5. The other revenues 1.000.000

Total of revenues: 235.770.535

In the previous table is displayed the projection of the revenues for 2019. The most

important items of the revenues of PE Autoceste are the revenues from the excise tax and

revenues from the toll.

1. Revenues from the excise tax (toll from the fuel price) are foreseen at the level of

BAM 171.959.040.00. The same are planned on the basis of the actual realization in the

previous period and the projection of the revenues made by the Department for Macro-

economic Analysis of the Indirect Taxation Authority.

2. Alignment of the excise tax– On 10 July 2018 Board of Directors of the Indirect

Taxation Authority BiH adopted a Decision on the interim distribution of the revenues

from the toll for the construction of the motorway and the construction and

reconstruction of the other roads (Official Gazette of BiH number: 50/18) by which is

confirmed the interim distribution of the unpaid revenues from the toll. However, by the

mentioned Decision is defined that from the total revenue from the toll 10% remains on

the sub-account at the Central Bank of BiH and shall serve for the alignment of the

revenues by the establishment of the final methodology of distribution.

By the Decision are also defined the percentages of distribution of the rest of the part of

the revenues (90%) on the entities and District Brčko. According to the experience, this

retained accumulated amount of revenues was allocated to the users of revenues every

two years. According to this is also performed the assessment of the revenues for 2019

by this basis. In the case that in accordance with the Law on Excise Tax of BiH is

adopted the final methodology of the distribution of revenues, it will not come to the

special allocation of these assets but the schedule will be performed monthly on the

basis of the established coefficients without the delaying of the part of the revenues.

3. Revenue from the toll –the projections are based on the model of traffic circulation.

4. Revenues from the compensation for the use of the road land are made on the

basis of the existing contracts for the rental of the land for the service provision and

conducting of the accompanying activities to the users besides the motorways and

express roads (Official Gazette of FBiH 81/10 and 13/13).

5. Under the other revenues are planned the other revenues which are not covered in

advance by the mentioned items and occur periodically as the result of the regular

business (damage payment, foreign exchange gain, revenue from the sale of the tender

documentation and similar).

7.2. Operational expenditures

Table 16

Page 61: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

61

Or.No. Name of the expense Plan 2019

1 2 3

1. Acquisition value of the sold goods 310.900

2. Spent raw materials and material 519.380

3. Spent energy and fuel 1.571.000

4. Spent spare parts 66.000

5. Write-off of the small inventory, packaging and tyres 124.000

6. Salary expenses 15.403.879

7. Expenses of the business trips of the employees 140.000

8. Expenses of the other incomes, compensations and mat. rights of the employees

1.604.365

9. Expenses of the compensations to the other natural persons 177.100

10. Expenses of service maintenance 13.667.000

11. Expenses of the leasing 621.000

12. Expenses of fairs 50.000

13. Expenses of advertisements 104.600

14. Expenses of the other services 374.570

15. Depreciation to the height of the tax deductible expenditures 40.480.000

16. Expenses of provisions for compensations and other benefits 120.000

17. Expenses of provisions for court disputes and damages 272.558

18. Expenses of the non-productive services 649.477

19. Expenses of representation 52.000

20. Expenses of the insurance premiums 120.000

21. Expenses of the payment operations 272.000

22. Expenses of the postal and telecommunication services 311.312

23. Expenses of the taxes, compensations, fees and other charges on the burden of the legal entity

365.008

24. The other non-material expenses 160.000

25. Interests' expenditures 6.473.019

26. The other financial revenues 100.000

In total of expenditures: 84.109.167

The projection of the expenses of business is done on the basis of the individual

projections of the business activities which are planned in 2019, the number of employees,

increase of the values of the fixed assets as well as the new bank debts. Assessments of the

expenses of depreciation are made on the basis of the real parameters of the calculation of

the depreciation on the total fixed assets. The calculation of the interests' expenses on

behalf of the international and domestic loan arrangement is performed on the basis of the

assessed dynamics of withdrawal of the loan assets, data from the available repayment

plans and assessment of the movement of the interest rates. Assessment of all other

expenses of business is performed on the basis of the previous consumption and planned

scope of work in 2019.Individual operational revenues relate on the following:

1. Acquisition value of the sold goods –on this position are planned the expenses of

the sold ACC TAG devices.

Page 62: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

62

2. Spent raw materials and material – this position of expenses includes all material

expenses that relate on the material used in the payment system, office material,

material for the current maintenance of the fixed assets, procurement of the

accompanying IT equipment and the other material expenses.

3. Consumed electrical energy expenses are indicated on the basis of the

assessment of the consumption in the previous year and calculated expenses of the

procurement of the petroleum products.

4. Expense of the spare parts procurement for the maintenance of the vehicle fleet. It

is planned on the basis of the consumption trend in the previous periods.

5. Write-off of the small inventory, packaging and tyres –on this position are

planned expenses related for the procurement of uniforms for the employees and

tyres on the basis of the current contracts and estimated values in the previous

years.

6. Salary expenses and salary compensations are planned on the basis of the

existing number of employees and planned employment in 2019.

7. Expenses of the business trips of the employees are estimated on the basis of

the increase of the number of employees and ancillary expenses related for the

travels on educations and professional training of the employees.

8. Assessment of the expenses of other incomes and material rights of the

employees represents the compensations for nutrition during work - meal allowance,

compensation of expenses of the burial in the case of death, planned costs for

participation fee for seminars, counselling, academic education of the employees,

symposiums and other on database on the existing number and planned increase of

the number of employees.

9. Expenses of the compensations to the other natural persons represent

expenses of compensations to the members to the Supervisory Board, Audit Board

and members of the various commissions and compensations on the basis of the

Service Contract. Planned values are based on the assessed monthly obligations,

that is, on the base of the assessment on the necessary periodical engagement of

the professional staff of various specialities.

10. Expenses of service maintenance are made on the base of the individual

projections of the expenses in the domain of management, payment and motorway

maintenance. On this item are also showed the expenses of computer maintenance,

computer systems and licences, telephone services, physical protection expenses,

regular vehicle maintenance expenses, expenses of the regular repairs in the

facilities of PE Autoceste as well as the services of desinsection, disinfection and

deratization of the toll stations and facilities of PE Autoceste FBiH.

11. Assessment of the lease expenses is conducted on the base of the existing

contracts on the lease of the office area, equipment, land and parking area for the

needs of PE Autoceste FBiH.

12. Expenses of the fair include the expenses of the presentation and promotion of the

company as well as the participation on the conferences related for the topic of road

construction /Mostar fair.

13. Expenses of advertising and sponsorship relate on the graphic design and

printing services (printing of the promotion material and graphical solutions for

electronic media), services of the production and preparations of the

propaganda/documentary programme, production of the archival material during the

Page 63: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

63

construction of sections on Corridor Vc, service agency and leases of the area and

participation at the international, investment and other conferences.

14. The other services include the expenses of the internal and external audit,

certification and supervisory audit, and the drafting of the rulebook, assessment of

the protection plan, rescuing the people and tangible assets from the compulsory and

other accidents, the drafting of the design documentations in the domain of the

maintenance and motorway management, training and professional training of the

employees in the area of motorway management, service provision of monitoring of

the printed and electronic media from the area of BiH that is, the service provision of

pressclipping, services of GPS tracking of the vehicles, regular and periodical

medical examinations of the employees who are distributed to the positions with the

special work conditions, internal calculation of expenses of the motorway for private

vehicles and other.

15. Assessment of the depreciation expenses was performed on the basis of the

known parameters achieved in 2018 and current knowledge on the new

procurements of the fixed assets in 2019.

16. Expenses of provisions for compensations and other benefits – relate on the

provisions for the retirement in accordance with the International Accounting

Standards and applicable Labour Rulebook.

17. Expenses of provisions for court disputes and damages relate on the initiated

court disputes, that is, expenses which by this basis can occur in 2019.

18. Expenses of the non-productive services make the expenses of the utilities,

expenses of cleaning of the offices and the toll stations, expenses of drinking water in

the facilities of PE Autoceste in Mostar and Sarajevo, washing water and sanitary

facilities on the toll stations and offices, notarial, lawyer and audit services, services

of the professional translations and consultancy services for the implementation of

standards.

19. Assessment of the representation expenses was completed on the base of the

average achieved in the previous period and needs for the following period.

20. Expenses of the insurance premiums include the insurance premiums of the fixed

assets, vehicles and insurance premiums from the consequences of the accidents.

21. Compensations for the expenses of the payment operations in the country and

abroad and the other banking services (expenses of loan processing, agent's fee

and others) are planned on the basis of the assessment of the payment operations

and planned applications for new loans.

22. Expenses of the postal (regular and courier mail) and telecommunication

services (fixed and mobile telephony) and Internet services are assessed on the

basis of the average achieved in the previous period taking into account the increase

of the number of employees for the telecommunication services.

23. Expenses of the taxes, compensations, fees and other charges on the burden of

the legal entity make: special compensation for the protection from natural and other

disasters, general water compensation, compensation for the performed registration

and vehicle roadworthiness testing, fee on the prominent firm, utility and

administrative fees, penalties, compensation of the Fund for the professional

rehabilitation and employment of the disability persons, paid VAT for free passes of

the external users and membership fees for the Commercial Chamber of FBiH and

Foreign Trade Chamber of BiH.

Page 64: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

64

24. The other non-material expenses relate on the given scholarships, advertisement

expenses, subscription on the professional literature and daily press and subscription

on electronic media.

25. Interests' expenses – proportionally to the increase of the debts also rise the

liabilities on the basis of the interests of which the largest part goes on the burden of

expenditures due to the fact the shares, for which construction are used loan assets,

are finished and put to use and are also foreseen new short-term debts.

26. The other financial expenditures relate on the possible negative exchange rate

differences, losses from the sale and debiting of the fixed assets, then on the

expenditures on the basis of the correction of the value and write-off of the

receivables, court expenses by the complaints of the third persons, damage

compensation by the decisions of the competent authorities, reduction of the value of

stocks of the material for the payment system and TAG devices and expenditures on

the basis of the corrections of the mistakes from previous years .

7.3. The difference of revenues and expenditures - Financial result

Table 17

Or. No.

Description Plan for 2019

1 2 3

1. Revenues 235.770.535

2. Operational expenses 84.109.167

Financial result (the difference of revenues and expenditures)

151.661.368

7.4. Employment plan

Employment plan by the organizational units

Table 18

Or. No.

Sector/Service Employment plan of the employees

Employment plan of the

trainees

1 2 3 4

1. Office Administration 2 2

2. Designing and Construction Sector 8 2

3. Management and Maintenance Sector 25 5

4. Economic and Financing Affairs Sector 6 2

5. Legal Affairs Sector 6 4

TOTAL OF: 47 15

Page 65: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

65

Bearing in mind the increase of business activities during 2019 in relation to the

present period and which, first of all, relate on: opening of the new construction sites,

preparation for construction (drafting of the tender documentation, completion of the design

documentation, obtaining of the approvals and permits, increased scope on the affairs of

expropriation and representation and similar) and introduction of the new activities that relate

on electronic toll payment -billing system, creation of the real base (purchase of the new

machines and machinery) for performing one part of the services on the maintenance by the

PE Autoceste for which have until now worked contracted suppliers and therefore the

increased scope of affairs of all accompanying services, was made a real projection of

employment of the new staff in the following period.

During 2019, with the employment of the quality staff through public advertising PE

Autoceste will ensure the achievement of the planned results and achievement of the set

goals.

8. PROJECTION OF THE FINANCING SOURCES - CREDITS AND NOTES

In addition to the existing credit arrangements PE Autoceste has also initiated other

activities in relation to the provision of the financial assets at the international financial

institutions and in the following period, the activities on finding the source of assets through

international credit institutions will be continued.

In the next period is planned the continuance of the activities on the achievement of the

effectiveness of the following credit lines at the following international creditors:

OFID (OPEC Fund for the International Development) in the amount of approx.49

million euros for the construction of subsection Vranduk – Ponirak (tunnel Zenica);

EIB in the amount of 50 million euros for the construction of the subsection Ponirak –

Vraca (tunnel Zenica);

EIB in the amount of 100 milllion euros for the construction of the subsection Kvanj -

Buna;

EBRD in the amount of 180 million euros for the construction of the section

Poprikuše – Nemila (70 million euros), Tarčin – Ivan (50 million euros) and Mostar

South – Tunnel Kvanj (60million euros)

Likewise, it is planned also the continuance of the activities on the signing of the agreement

on the loan with the creditors for which in the earlier period was initiated the procedure of the

credit debt namely:

KFAED in the amount of approx. 36 million of euros for the construction of the

subsection Nemila – Vranduk. For the mentioned credit debt are finalized

negotiations and it is adopted the Decision on the acceptance of the debt by the

Parliament of FBiH;

EIB in the amount of 140 million euros for co-financing of the construction of the

sections Poprikuše – Nemila (90million euros) i Tarčin – Ivan (50 million

euros).Referred initiative to the Federal Ministry of Communications and Transport;

EBRD in the amount of 35 million euros for the construction of the subsection

Putnikovo brdo – Karuše. For the above mentioned credit debt, the initiative was

referred to the Federal Ministry of Communications and Transport (on which the

same has given an approval) and has been referred into the further procedure. The

Page 66: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

66

mentioned Initiative will be added with the additional 25 million euros and it will also include the subsection Karuše – Medakovo.

In 2019 are planned to be initiated the initiatives for the debt at EXIM bank for:

construction of the motorway section tunnel Prenj;

construction of the motorway section Mostar north – Mostar south;

It is foreseen, as in the business plans from previous years that PE Autoceste

temporary pre-finance motorway section until the final effectiveness of the credit

facilities, for which are insured additional financial assets collected through I notes

issues (48.99 million BAM) whose purpose was pre-financing of the construction of

the motorway section on Corridor Vc.

PE Autoceste will in the case of insufficiency of assets for its own participation for the

realization of the designs, for the needs of maintenance of the current liquidity, the

construction of the motorway on Corridor Vc or any other reason which would lead to

the non-liquidity of the designs (temporary suspension of withdrawals of the credit

assets or similar) ensure additional financial sources through the increase of the

existing credit frameworks, initiated activities in the part of issuance of the securities,

commercial short-term credits, arrangements or new arrangements with the

international financial institutions.

Likewise, it is important to point out that besides the usual manner of financing of the

construction of Corridor Vc, it will be undertaken activities on finding the other

alternative models of financing and construction, what will depend in great measure

from the abilities of PE Autoceste, that is, the state Bosnia and Herzegovina, that is,

the Federation of BiH, to timely fulfil the potential obligations by the same.

8.1. The review of withdrawals of the credit assets In the next table is given the projection of withdrawals of the credit assets at the international financial institutions for which is confirmed the effectiveness of the assets or the procedure of achievement of the effectiveness is in progress:

Table 19

Or.No. Credit facility Credit assets

(EUR) Credit assets

(BAM)

The plan of credit withdrawal 2019

(BAM)

1 2 3 4 5

1. KFAER 10.5 KVD 29.963.395 58.603.307 840.000

2. OPEC B 24 mill. EUR 24.000.000 46.939.920 25.000.000

3. EBRD 80 mill. EUR 80.000.000 156.466.400 59.000.000

4. EBRD 76 mill. EUR 76.000.000 148.643.080 36.200.000

5. EIB 100 mill. EUR 100.000.000 195.583.000 59.500.000

6. EIB 50 mill. EUR 50.000.000 97.791.500 31.200.000

7. KFAED 36 mill. EUR 36.000.000 70.409.880 11.150.000

8. OFID 49 mill. EUR 49.000.000 95.835.670 36.270.000

9. EIB 100 mill. EUR 100.000.000 195.583.000 25.880.000

10. EBRD 180 mill. EUR 180.000.000 352.049.400 81.940.000

11. EIB 140 mill. EUR 140.000.000 273.816.200 11.800.000

12. EBRD 60 mill. EUR 60.000.000 117.349.800 15.000.000

13. EXIM 240 mill. EUR 240.000.000 469.399.200 47.610.000

IN TOTAL OF: 1.164.963.395 2.278.470.357 441.390.000

Page 67: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

67

In addition to the financing of the construction through international credit facilities, it

is planned pre-financing and assets collected by the issuance of the corporative notes until

the achievement of effectiveness of the certain credit facilities.

8.2. Review of the planned repayment by the credits

Repayment credit projection is completed in accordance with the repayment plans of the same.

Table 20

Contracts for revolving credit facilities are concluded in 2018 and for the same the

contracted deadlines expire in the first half of 2019.

The projection of the repayment of the long-term credits was done on the basis of the

individual repayment plans for the international and domestic credit arrangements.

8.3. Review of the credit obligations - interest

In the next table is given the review of the planned calculation of interests by the existing

credit facilities as well as the credits for which is initiated the procedure of locking the credit

arrangements. The part of the calculated interest on the credits which are spent in the

previous period for the designs which are completed, the capitalization of interest is not

performed, but the same represent the expense of the current period.

Or.No. Credit facility Repayment plan

2019 (EUR) Repayment plan

2019 (BAM)

1 2 3 4

1. EBRD 205 mill. EUR 19.308.711 37.764.557

2. EIB 75 mill. EUR 3.852.154 7.534.158

3. EIB 166 mill. EUR 2.307.692 4.513.454

4. OFID A 48 mill. USD 1.416.431 2.770.298

5. OFID B 24 mill. EUR 857.140 1.676.420

6. KFAED 28 mill. EUR 760.883 1.488.157

7. Razvojna banka FBiH 30 mill. BAM 2.359.808 4.615.384

8. Razvojna banka FBiH 38 mill. BAM 2.590.546 5.066.667

9. Revolving 973-E499-1/18 (Raiffeisen) 3.067.751 6.000.000

10. Revolving 973-E499-3/18 (BBI) 1.022.584 2.000.000

11. Revolving 973-E499-4/18 (BBI) 766.938 1.500.000

12. Revolving 919-E472-2/18 (UniCred.) 2.556.459 5.000.000

13. Revolving 919-E472-3/18 (UniCred.) 2.045.168 4.000.000

14. Revolving 919-E472-6/18 (UniCred.) 1.022.584 2.000.000

15. Revolving 919-E472-7/18 (UniCred.) 1.022.584 2.000.000

16. Revolving 973-E499-2/18 (UniCred.) 1.022.584 2.000.000

17. Revolving 973-E499-5/18 (UniCred.) 766.938 1.500.000

IN TOTAL OF: 46.746.954 91.429.094

Page 68: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

68

Table 21

Or.No. Credit facility Interest

plan (EUR)

Interest plan 2019

(BAM)

Interest Expenses

Interest Capitalization

1 2 3 4 5 6

1. EBRD 205 mill. EUR 755.415 1.477.463 1.477.463 0

2. EIB 75 mill. EUR 515.338 1.007.913 1.007.913 0

3. EIB 166 mill. EUR 1.203.965 2.354.750 2.354.750 0

4. KFAED 28 mill. EUR (Drivuša – Klopče) 530.693 1.037.946 0 1.037.946

5. OFID 24 mill. EUR (Klopče – Donja Gračavnica)

144.000 281.640 0 281.640

6. OFID 48 mill. USD (Klopče – Donja Gračavnica)

1.282.585 2.508.518 0 2.508.518

7. EBRD 76 mill.EUR (Svilaj – Odžak and Klopče – Donja Gračanica)

544.348 1.064.653 0 1.064.653

8. EBRD 80 mill. EUR (Buna – Počitelj and Vraca- Donja Gračanica)

360.000 704.099 0 704.099

9. EIB 100 mill. EUR (Počitelj-Zvirovići) 212.585 415.780 0 415.780

10. EIB 50 mill. EUR (Ponirak – Vraca) 65.600 128.302 0 128.302

11. KFAED 36 mill. EUR (Nemila – Vranduk) 23.775 46.500 0 46.500

12. OFID 49 mill. EUR (Vranduk – Ponirak) 253.089 495.000 0 495.000

13. EIB 100 mill. EUR (Kvanj - Buna) 40.699 79.600 0 79.600

14. EBRD 180 mill. EUR (Poprikuše – Nemila, Tarčin – Ivan i Mostar J. – Kvanj)

225.480 441.000 0 441.000

15. EIB 140 mill. EUR (Porpikuše – Nemila and Ivan – Tarčin)

7.669 15.000 0 15.000

16. EBRD 60 mill. EUR (Putnikovo brdo – Medakovo)

8.283 16.200 0 16.200

17. EXIM 240 mill. EUR (Tunnel Prenj) 56.421 110.350 0 110.350

18. Razvojna banka FBiH 30 mill. BAM 239.860 469.125 469.125 0

19. Razvojna banka FBiH 38 mill. BAM 525.073 1.026.954 1.026.954 0

20. Revolving facilities up to 60 mill. BAM 69.952 136.815 136.815 0

IN TOTAL OF : 7.064.831 13.817.608 6.473.019 7.344.588

In the next table are displayed the obligations for the interests on the basis of the first

issuance of the notes. The totally collected assets of the first issuance of notes are BAM

48.998.800. The assets collected by the issuance of the notes will be used for pre-financing

of the infrastructural designs.

Table 22

Or.No. Description Interest plan for 2019

(BAM) Expenses capitalization

(BAM)

1 2 3 4

1. I issuance of notes 963.330 963.330

IN TOTAL OF: 963.330 963.330

Page 69: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

69

8.4. Summary review of the obligations by the credits

In the next table is given the summary review of the obligations by the credits namely interests and annuities of the certain credit facilities.

Table 23

Or.No. Credit facility Interest

Plan 2019 (BAM)

Credit Repayment 2019 (BAM)

Total of obligations 2019 (BAM)

1 2 3 4 5

1. EBRD 205 mill. EUR 1.477.463 37.764.557 39.242.020

2. EIB 75 mill. EUR 1.007.913 7.534.158 8.542.071

3. EIB 166 mill. EUR 2.354.750 4.513.454 6.868.204

4. KFAED 28 mill. EUR (Drivuša – Klopče) 1.037.946 1.488.157 2.526.103

5. OFID 24 mill. EUR (Klopče – Donja Gračavnica) 281.640 2.770.298 3.051.938

6. OFID 48 mill. USD (Klopče – Donja Gračavnica) 2.508.518 1.676.420 4.184.938

7. EBRD 76 mill. EUR (Svilaj – Odžak and Klopče – Donja Gračanica)

1.064.653 0 1.064.653

8. EBRD 80 mill. EUR (Buna – Počitelj and Vraca- Donja Gračanica)

704.099 0 704.099

9. EIB 100 mill. EUR (Počitelj - Zvirovići) 415.780 0 415.780

10. EIB 50 mill. EUR (Ponirak – Vraca) 128.302 0 128.302

11. KFAED 36 mill. EUR (Nemila – Vranduk) 46.500 0 46.500

12. OFID 49 mill. EUR (Vranduk – Ponirak) 495.000 0 495.000

13. EIB 100 mill. EUR (Kvanj - Buna) 79.600 0 79.600

14. EBRD 180 mill. EUR (Poprikuše – Nemila, Tarčin – Ivan and Mostar J. – Kvanj)

441.000 0 441.000

15. EIB 140 mill. EUR (Porpikuše – Nemila and Ivan – Tarčin)

15.000 0 15.000

16. EBRD 60 mill. EUR (Putnikovo brdo – Medakovo) 16.200 0 16.200

17. EXIM 240 mill. EUR (Tunnel Prenj) 110.350 0 110.350

18. Razvojna banka FBiH 30 mill. BAM 469.125 4.615.384 5.084.509

19. Razvojna banka FBiH 38 mill. BAM 1.026.954 5.066.667 6.093.621

.20. Revolving facilities up to 60 mill. BAM 136.815 26.000.000 26.136.815

IN TOTAL OF: 13.817.608 91.429.094 105.246.702

Besides the obligations for interests, with EBRD's credits there is an obligation and

payment of the fee on the undrawn credit assets in the amount of 0.5% what is estimated to

approx. 1 million BAM for 2019 with the condition that it is fulfilled the planned withdrawal of

the assets. The amount of the fee is capitalized.

9. RECAPITULATION OF THE CAPITAL INVESTMENTS

Table 24

Page 70: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

70

Or.No. Description Plan 2019

1 2 4

A) Investments on the construction of Corridor Vc (bez PDV-a) 386.975.222

1. Purchase of the land 40.340.000

a) financing by their own assets 37.840.000

b) financing by the Conclusion of the Government 2.500.000

2. Designing services 7.994.000

a) financing by their own assets 7.494.000

b) financing by the Conclusion of the Government 500.000

3. Construction 315.777.804

a) financing by the international credits 268.118.005

b) financing by the Conclusion of the Government 18.906.228

c) financing by their own assets 28.753.571

4. Services of the supervision over the construction 19.946.314

a) financing by the international credits 16.704.171

b) financing by the Conclusion of the Government 325.000

c) financing by their own assets 2.842.143

d) financing by grant assets 75.000

5. Project Manager Services 2.325.104

a) financing by the international credits 1.984.095

b) financing by their own assets 341.009

6. The other capital investments financed by their own assets 592.000

a) archaeological research 292.000

b) obligations within expropriation 300.000

B) Capital investments on the motorway management and maintenance 29.049.000

1. Capital investments on motorway management and maintenance (point 6.6.1.of the Business plan) - financing by their own assets

29.049.000

C) Investments into information technologies 1.798.000

1. Procurement: of software solutions and licensed assumptions, computer equipment, printers, MFU/MFP devices, server, network and various other diagnostic equipment and tool Data Management System (DMS) - financing by their own assets

1.798.000

D) The other investments ( financing by their own assets) 4.611.325

1. Procurement of the official vehicles 800.000

2. Equipment of the archive storage on Bijača and Mostar 50.000

3. Procurement of the design, land/facility for the commercial construction in Mostar 2.850.000

4. Procurement of the office furniture 40.000

5. Reconstruction of the commercial facilities Briješće 770.000

6. Main design of the reconstruction of the commercial facility beside the roundabout Briješće

1.325

7. Procurement of the furniture for the equipment of the business facility in Briješće 100.000

Page 71: 2019 BUSINESS PLAN - jpautoceste.ba · 3. Swot analysis The advantage of this enterprise should be in dealing with internal economy, optimising costs while continuously measuring

71

Number: 01- 2164-2 /19 Director:

Date: 24 May 2019 Adnan Terzić, Graduate Engineer

TOTAL OF (A+B+C+D) 422.433.547