FROM PMO TO STRATEGIC PMO, AN INDIRECT APPROACH Philippe Husser

2016 An indirect approach to a strategic PMO

Embed Size (px)

Citation preview

Page 1: 2016 An indirect approach to a strategic PMO

FROM PMO TO STRATEGIC PMO, AN INDIRECT APPROACH

Philippe Husser

Page 2: 2016 An indirect approach to a strategic PMO

From Program MO to Strategic Portfolio MO, an Indirect Approach

1. Three Domains to Explore

2. Seven Snapshots to Share

3. Three Takeaways to Learn

Page 3: 2016 An indirect approach to a strategic PMO

Three Domains to Explore

1. Complexity

2. Indirectness

3. Strategy

Page 4: 2016 An indirect approach to a strategic PMO

Simple systems are

easy to know

Page 5: 2016 An indirect approach to a strategic PMO

Complicated systems can be known by

specialists

Page 6: 2016 An indirect approach to a strategic PMO

Chaotic systems

require a lot of experience

Page 7: 2016 An indirect approach to a strategic PMO

Complex systems

behavior is difficult to

forecast

Page 8: 2016 An indirect approach to a strategic PMO

Large Global Organizations are Complex Adaptive System

Page 9: 2016 An indirect approach to a strategic PMO

Direct approaches fit to simple

targets

Page 10: 2016 An indirect approach to a strategic PMO

Indirect approaches

fit to complex targets

Page 11: 2016 An indirect approach to a strategic PMO

Strategic Approach

in Occident:

Goal Ways

Means

Page 12: 2016 An indirect approach to a strategic PMO

Strategic Approach in

Orient :

Situation Potential Ripeness

Page 13: 2016 An indirect approach to a strategic PMO

An Indirect Approach in Seven Snapshots

1. Program Cause and Approach

2. Local Relays

3. First Benefits

4. Single Version of Truth

5. Tipping Point

6. Strategic Gap

7. Strategic Initiatives

Page 14: 2016 An indirect approach to a strategic PMO

1-Program Cause and Approach

Prerequisite :

Find your “Buddy”

Page 15: 2016 An indirect approach to a strategic PMO

1-Program Cause and Approach

Develop an Attractive

Cause

Page 16: 2016 An indirect approach to a strategic PMO

1-Program Cause and Approach Many Bottom-Up Low-Risk Medium-Impact

Short-Term Initiatives

Page 17: 2016 An indirect approach to a strategic PMO

1-Program Cause and Approach A Series of Top-Down Rapid Risky High-Impact

Medium-Term Events

Page 18: 2016 An indirect approach to a strategic PMO

J. Kotter, Accelerate !

1-Program Cause and Approach a Fast Probe-Sense-Respond Loop

18

Page 19: 2016 An indirect approach to a strategic PMO

2-Create Network of Local Relays

Page 20: 2016 An indirect approach to a strategic PMO

2-Local Relays Develop Human Dynamics

0

2

4

6

8

10

12

Independant ð Interdependant

Egalitarism ð Status

Risk ð Restraint

Direct ð Indirect

Task ð Relationship

Short-term ð Long-term

CN

TH

IN

FR

USA

Source : www.globesmart.com

Page 21: 2016 An indirect approach to a strategic PMO

3-First Benefits Start by Sensing the Environment

Page 22: 2016 An indirect approach to a strategic PMO

3-First Benefits Create a First Shock

# Projectsbefore

# Projects after

Transformation Projects Portfolio

M€ before M€ after

Transformation Projects Investments

Page 23: 2016 An indirect approach to a strategic PMO

3-First Benefits Show Forward-Looking Expected Benefits

2018 2017 2016 2015 2014 2013

Page 24: 2016 An indirect approach to a strategic PMO

3-First Benefits

Avoid Weak Posture

Victim

Rescuer Persecutor

Page 25: 2016 An indirect approach to a strategic PMO

3-First Benefits Adopt Strong

Posture

Creator

Coach Challenger

Page 26: 2016 An indirect approach to a strategic PMO

4-Single Version of Truth Introduce Technology

Page 27: 2016 An indirect approach to a strategic PMO

5-Tipping Point Trusted Data

• Composite

Index

• Benefits

management

• Progress

management

• Risks and

opportunites

Page 28: 2016 An indirect approach to a strategic PMO

5-Tipping Point User Experience

Comes First

Page 29: 2016 An indirect approach to a strategic PMO

5-Tipping Point Identify Power Nodes

Page 30: 2016 An indirect approach to a strategic PMO

5-Tipping Point Cultivate Supporters

Triangle d’or

Engagés

déch

irés révo

ltés

op

po

sants grognons

Passifs

+4

+3

+2

+1

-4 -3 -2 -1

12 4 - -

59 14 4 1

39 15 13 1

7 5 16 2

117 38 33 4

16

78

68

30

Synergy

Antagonism

Page 31: 2016 An indirect approach to a strategic PMO

5-Tipping Point Create Group Progress PMO

Department B

New Merged Department

Department A

Page 32: 2016 An indirect approach to a strategic PMO

6-Strategic Gap Create Need to Bridge the Strategic Gap

# Entities 1 (mono-entity)

1 (mono-process)

Σ (multi-process)

# Process

TRANSVERSAL INITIATIVES

LOCAL INITIATIVES

STRATEGIC INITIATIVES

Σ (multi-entities)

GROUP STRATEGIC INITIATIVES

Page 33: 2016 An indirect approach to a strategic PMO

Source: The Case for Behavioral Strategy, McKinsey 2010

Stability

Action

Social

Interest

Model

Anchoring on former values and status

quo…

Attachment to former leaders, former success,

champion…

Under estimation of what we do not know…

Emotional attachments…

Group think…

6-Strategic Gap Understand Cognitive Biases

Page 34: 2016 An indirect approach to a strategic PMO

7-Group Strategic Initiatives Define Strategic Themes

Empowerment Customer Centricity

Digital

Simplification

Page 35: 2016 An indirect approach to a strategic PMO

7-Group Strategic Initiatives Develop Strategic Initiative Portfolio

Page 36: 2016 An indirect approach to a strategic PMO

Three Takeways

Page 37: 2016 An indirect approach to a strategic PMO

The indirect approach

• PMO Should Consider Complex Adaptive Systems and Chaos Theory

• Chaos theory will have path-breaking effects on transformation programs through changes in the way we use technology (hard side) and work on social phenomena and human dynamics (soft side).

Page 38: 2016 An indirect approach to a strategic PMO

The indirect approach

• PMO should Learn and Execute Dual-Mode Strategies

• Instead of directly confronting the target, install a wide-scope low-risk low-benefits strategy and a focused high-risk, hedged, and high-impact destabilizing strategy.

Page 39: 2016 An indirect approach to a strategic PMO

The indirect approach

• PMO Should Develop an Attracting WIIFM Cause and an Alliance they Lead from Behind

• The most important target is the employee population and success relies on a cause which is attracting to the employees (What’s In It For Me) using local relays as proxies to further your goals.

Page 40: 2016 An indirect approach to a strategic PMO

A Last Word Inspired from Chairman Mao

The laws of project management — this is a problem that anyone directing a project must study and solve.

The laws of transformational project management —this is a problem that anyone directing a transformational project must study and solve.

The laws of transformational project management in your organization — this is a problem that anyone directing a transformational project in your organization must study and solve.

Cf. Mao Tse-tung, Strategic Problems of China’s Revolutionary War (December, 1936)

Page 41: 2016 An indirect approach to a strategic PMO

FROM PMO TO STRATEGIC PMO, AN INDIRECT APPROACH

Philippe Husser - 2016