12
2016 | 1st Quarter Report May 2016 Omaha Combined Sewer Overflow Control Program Implementation Phase

2016 1st Quarter Report - Omaha CSO · timely and accurate project information. The Program is also providing additional neighborhood benefits, above the improved sewer system. Public

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 2016 1st Quarter Report - Omaha CSO · timely and accurate project information. The Program is also providing additional neighborhood benefits, above the improved sewer system. Public

2016 | 1st Quarter ReportMay 2016

Omaha Combined Sewer Overflow Control ProgramImplementation Phase

Page 2: 2016 1st Quarter Report - Omaha CSO · timely and accurate project information. The Program is also providing additional neighborhood benefits, above the improved sewer system. Public

MRWWTP was built in 1964 and treats an overall average of 25 MGD of wastewater. When the CSO Program improvements are completed, this facility will handle up to 150 MGD.

New Municipal Headworks for the Missouri River WWTP Improvements–Schedule B1 project

Significant improvements to Missouri River Wastewater

Treatment Plant (MRWWTP) have been completed to

improve water quality in the Missouri River. Two of the

three construction projects are nearly complete. When

all three projects are complete, the MRWWTP will

provide treatment for high-strength industrial waste

during wet weather events (Schedule A), the primary

and secondary treatment capacities will be increased to

150 MGD and 64 MGD (Schedule B1), and flows above

64 MGD will be disinfected and dechlorinated prior to

discharge to the Missouri River (Schedule B2). In addi-

tion to the significant improvements to water quality,

the project will also reduce odor impacts to the public

and achieve resources recovery/energy generation from

the additional solids removed from the waste stream,

and replace aging plant infrastructure. Schedule A is in

operations, Schedule B1 is 98% complete, and Schedule

B2 will be in operation by mid-2019.

With the maximizing of flow to the MRWWTP from

upstream projects, disinfection of the discharge from

Combined Sewer Overflow (CSO) 102, and separate

treatment of the high-strength industrial waste, the

reduction in pollutant loading to the Missouri River is

approximately 50%.

In addition to the direct improvements to the MRWWTP,

the Bank Stabilization project received construction

notice-to-proceed in March. This project is necessary to

stabilize the bank to prevent damage to the treatment

plant as well as allow for construction of the treatment

elements under the B2 project in this area.

Additional information on this project can be found in the Appendix.

2 Omaha Combined Sewer Overflow Control Program | Implementation Phase

PROJECT SPOTLIGHT

Page 3: 2016 1st Quarter Report - Omaha CSO · timely and accurate project information. The Program is also providing additional neighborhood benefits, above the improved sewer system. Public

1st Quarter 2016

HIGHLIGHTS » Saddle Creek RTB Value Engineering analysis is projected to be complete

in April to identify cost saving opportunities. Bids were opened for the

Saddle Creek Early Soils construction project, which was substantially

under the engineer’s estimate. Construction NTP was given in March.

» All work at Lauritzen Gardens is complete. Final paperwork is being

processed for the pond lining project.

» Hitchcock Park Green Infrastructure Project was broken out of the 42nd

and Q Street project and is expected to bid late this fall for a summer 2017

construction notice to proceed (NTP.) This has opportunity for increased

small emerging business (SEB) participation and cost savings.

» Gilmore Avenue Detention Pond & Albright Park Landscaping is expected

to bid late this fall, for a spring construction NTP.

» Communicated with Nebraska Department of Environmental Quality

(NDEQ) regarding concerns related to higher project costs for Missouri

River Waste Water Treatment Plant (MRWWTP) Improvements, Minne Lusa

Stormwater Conveyance Sewer, and Saddle Creek Retention Treatment

Basin (RTB.)

Adams Park Landscaping Improvement project is nearing final completion. The above rendering depicts the completed project with plant selections.

IN THIS REPORT

PROJECT SPOTLIGHT. . . . . . . 2

HIGHLIGHTS . . . . . . . . . . . . . . . 3

PROGRAM OVERVIEW. . . . . . 4

GOAL REVIEW. . . . . . . . . . . . . . 5

BUDGET DETAILS . . . . . . . . . . 9

PROJECTS UNDER

CONSTRUCTION . . . . . . . . . . 10

KEY ACTIVITIES . . . . . . . . . . . 12

For additional information regarding

the Omaha CSO Program, please visit

www.OmahaCSO.com/contact to

complete and submit an online comment

form, or call the CSO Program Hotline at

(402) 341-0235.

A city of Omaha Public Works Initiative

www.OmahaCSO.com Clean Solutions for Omaha Quarterly Report | 1st Quarter 2016 3

HIGHLIGHTS

Page 4: 2016 1st Quarter Report - Omaha CSO · timely and accurate project information. The Program is also providing additional neighborhood benefits, above the improved sewer system. Public

2020

CSO

Solutions

Goal 1: Regulatory Compliance.

Meet specific regulatory

requirements as

identified by the EPA

and NDEQ.

• Complete

implementation of

CSO Solutions within

schedule identified

• Reduce pollutant discharge to

the Missouri River and Papillion Creek

Goal 3: Community Acceptance.

Maintain continuous public dialogue,

provide information and pursue

opportunities for multiple benefits in

CSO Solutions.

Goal 2: Economic Affordability.

Minimize cost impact to ratepayers

by completing CSO Control Options

within or under budget.

The Program schedule, which began in 2006, is shown below. The final implementation is targeted for

2027. The Program is divided into two groups: Major Projects and Sewer Separation Projects. Project

implementation was selected based on its positive effect on water quality, supporting development,

its priority in the construction sequence, and cost. The schedules were further coordinated to allow for

concurrent construction. A list of projects by LTCP phase is located in the Appendix.

GOALSIn order to comply with the

requirements of the Clean Water

Act, the United States Environmental

Protection Agency (EPA) CSO Control

Policy of 1994, and Administrative

Consent Order with the NDEQ, the

City of Omaha developed a Long

Term Control Plan (LTCP) that outlines

an action plan to control overflows

from its combined sewer system. The

purpose of the Omaha CSO Control

Program (Program) Implementation

Phase is to ensure that CSO projects

outlined in the City of Omaha’s LTCP

are constructed, operational and

are implemented in a cost effective

manner by 2027.

CSO PERMIT IS VALID THROUGH OCTOBER 2020

The CSO permit was recently approved by

NDEQ in September 2015 with a reduction

in requirements that reduce the cost to the

city and in support of Omaha’s Program. The next required CSO permit renewal is in October 2020.

4 Omaha Combined Sewer Overflow Control Program | Implementation Phase

PROGRAM OVERVIEW

Program Schedule

Page 5: 2016 1st Quarter Report - Omaha CSO · timely and accurate project information. The Program is also providing additional neighborhood benefits, above the improved sewer system. Public

Phase Project Name

20

09

20

10

20

11

20

12

20

13

20

14

20

15

20

16

20

17

20

18

20

19

20

20

20

21

20

22

20

23

20

24

20

25

20

26

20

27

1 Missouri River WWTP Improvements /

Collection System Improvements

2 Saddle Creek Retention Treatment Basin /

Collection System Improvements

3A Minne Lusa Stormwater Conveyance

System and Detention Basin

3B Paxton Blvd Stormwater Conveyance

Sewer, 41st to 49th (ML-105-13A Phase 2)

4 Deep Tunnel / Missouri River Retention

Treatment Basin

Project Phase

20

09

20

10

20

11

20

12

20

13

20

14

20

15

20

16

20

17

20

18

20

19

20

20

20

21

20

22

20

23

20

24

20

25

20

26

20

27

Phase 1

Phase 2

Phase 3

Phase 4

Phase 5

Phase 6

Phase 7

(continued on page 6)

Regulatory Compliance includes two items; 1) implement projects within the identified

schedule, and 2) reduce pollutant discharge to the Missouri River and Papillion Creek.

SCHEDULEThe following charts show the implementation milestones and project status, with a list of

projects by phases located in the Appendix. All regulatory milestones have been met to date.

Goal 1: Regulatory Compliance

MAJOR PROJECTS

SEWER SEPARATION ELEMENT

CURRENT STATUS OF PROJECTS

Current Status

Notice to Proceed to Consultant for Final Design

Notice to Proceed to Constructor

Operationally Complete

Bid Advertisement

All Construction Projects Complete

14completed projects

38

2514current: study & design

future projects

combined or removed

8current: bid / construction

www.OmahaCSO.com Clean Solutions for Omaha Quarterly Report | 1st Quarter 2016 5

GOAL 1 REVIEW

Page 6: 2016 1st Quarter Report - Omaha CSO · timely and accurate project information. The Program is also providing additional neighborhood benefits, above the improved sewer system. Public

In bid or

current construction

$236.5M

Completed

$84MIn design

$393M

Significant and early reduction in CSO bacteria loading to the Missouri River and Papillion Creek have occurred, but continued program implementation is necessary.

Goal 1: Regulatory Compliance(Continued)

STATISTICS

As of March 2016,

$264M has been

paid out for

completed construction.

REDUCTION OF POLLUTANTS AND OVERFLOW EVENTSCompleted projects have reduced bacteria

loading by approximately 21% to date in the

receiving waters of the Missouri River and

Papillion Creek. Additionally,

» No sewer overflows now occur at five CSOs

(206, 209, 104, 113 and 116); and

» CSO 211 and 103 have significant

reductions in overflow occurrences.

COMPANIES ENGAGED:

Original

LTCP Projects

92

Construction

Packages

Multiple packages benefit

additional contractors

120

Delivered thro

ug

hConsultant Firms

(Including Subcontracted Companies)

76*City Small BusinessesReceiving Contracts(through end of 2015)

28General and Small Business

Contracts Awarded toOmaha Companies

Over 80%General ContractorsReceiving Contracts

15

* Unique businesses may have multiple contracts.

6 Omaha Combined Sewer Overflow Control Program | Implementation Phase

GOAL 1 REVIEW

Page 7: 2016 1st Quarter Report - Omaha CSO · timely and accurate project information. The Program is also providing additional neighborhood benefits, above the improved sewer system. Public

Engineering Estimate

Bid Awards

10%Cost

Reductions

$30 Million

Developed a more workable, flexible andoperable CSO control plan for the 2014 LTCP Update, along with a potential for savings of

CONSTRUCTION COST STATISTICS

LEGISLATIVE ACTION IN SUPPORT OF THE PROGRAMLB 413 was recently passed to allow NDEQ to consider financial capability, affordability, future growth, other investments and other relevant economic/ social/ environmental conditions when issuing an National Pollutant Discharge Elimination System (NPDES) Permit. This will be evaluated for its benefit to the CSO Program.

VALUE ENGINEERING TO IMPLEMENT COST-EFFECTIVE SOLUTIONSAdditional funding sources have been identified along with identified construction cost savings.

RATEPAYER ASSISTANCEWhen the LTCP was approved it marked the start of a ratepayer assistance plan to help low income and fixed income households with the rate increases necessary to fund the Program.

From January 2015 through March of 2016, over $930,000 has been provided in assistance. Ratepayers are eligible if they receive Low Income Heat and Energy Assistance (LIHEAP) from their utility. This has kept administrative costs to a minimum and provided the maximum benefit to those who need it.

Economic Affordability is the minimization of the cost impact to the ratepayers.

Construction costs have been contained, as shown in the following metrics.

Goal 2: Economic Affordability

Secured

$70 Millionin low interest loansfrom the State

Received

$2.9 Millionfrom Nebraska WaterSustainability Fund

Saved

$15+ Millionthrough implementation of Green Infrastructure solutions which have also enhanced the community

Based on Engineering Estimates, the CSO Program has realized a 10% in cost reduction in contract bids awarded to date.

www.OmahaCSO.com Clean Solutions for Omaha Quarterly Report | 1st Quarter 2016 7

GOAL 2 REVIEW

Page 8: 2016 1st Quarter Report - Omaha CSO · timely and accurate project information. The Program is also providing additional neighborhood benefits, above the improved sewer system. Public

Goal 3: Community Acceptance

equivalent blocks

of replaced street

linear feet of

new trails

equivalent new

driveways

new trees

equivalent blocks of

replaced sidewalk

153 1,225

270 227

165

curb ramps acres of park/open

space enhanced

432 22

Community Acceptance is providing continuous open dialogue with the public along with

timely and accurate project information. The Program is also providing additional

neighborhood benefits, above the improved sewer system.

Public Meetings Held

0 5 10 15 20 25

2014

2015

2016

20

22

0 (to Date)

PUBLIC INFORMATION

The CSO Program hosts a public website and provides

updates via Twitter to provide up-to-date information to

the ratepayers. This includes a Contractor’s Corner, which

identifies upcoming bidding opportunities.

Website and Twitter Statistics

Users 25,420

Web pages viewed 87,570

Visits (all users) 33,511

Twitter followers 48

ADDITIONAL PUBLIC BENEFITSTo date, the completed Program construction projects have provided a total Community Enhancement value of

over $18.6 Million, as identified below:

STAKEHOLDER ENGAGEMENTPublic meetings were held to provide

information and discussion about upcoming

construction projects and the Program.

8 Omaha Combined Sewer Overflow Control Program | Implementation Phase

GOAL 3 REVIEW

Page 9: 2016 1st Quarter Report - Omaha CSO · timely and accurate project information. The Program is also providing additional neighborhood benefits, above the improved sewer system. Public

Actual Cost Total Capital Cost (2015 Dollars)0

100M

200M

300M

400M

500M

600M

700M

800M

900M

$1B

$1.1B

Program Management$120.6 million

Sewer Separation

$566.1 million

Conveyance$334.5 million

Facilities$1.02 billion

Miscellaneous Projects

$139.7 million

$38.9 million

$154.6 million $167.9 million

$3.2 million

$79.4 million

2009 2027

$2.171 billion$443.8 million

Actual Cost Total Program Cost (2015 Dollars)

The CSO Program is maintaining schedule and budget

to meet current regulatory and financial expectations.

Spent to Date: 20.5%Estimated Complete: 21.5%

PROGRAM BUDGET STATUS

PROGRAM CAPITAL ALLOCATION

THE PROGRAM CONTINUES TO MEET ALL REGULATORY MILESTONES. WHILE A SIGNIFICANT AMOUNT OF PROGRESS HAS BEEN MADE TOWARDS PROGRAM IMPLEMENTATION, THERE IS STILL MUCH TO DO.

Program Management: Management and

administration of Program related activities

Sewer Separation: Sewer projects that will

reduce flows to the combined sewer system

Conveyance1: Minne Lusa Stormwater

Collector Projects and South Interceptor Force

Main (SIFM)

Facilities1: Deep tunnel, Missouri River

Wastewater Treatment Plant (MRWWTP), high

rate treatment, lift station, and storage structure

projects

Miscellaneous: Miscellaneous study related

projects

1 The combination of Conveyance and Facilities constitutes most of the Major Projects.

BUDGET DETAILS

www.OmahaCSO.com Clean Solutions for Omaha Quarterly Report | 1st Quarter 2016 9

BUDGET DETAILS

Page 10: 2016 1st Quarter Report - Omaha CSO · timely and accurate project information. The Program is also providing additional neighborhood benefits, above the improved sewer system. Public

Missouri River

Missouri River

COLE CREEK

BRIDGESTREET

MINNELUSA

BURT-IZARD

PAPILLIONCREEKNORTH

SADDLECREEK

PAPILLION CREEKSOUTH

OHERN/MONROE

SOUTH INTERCEPTOR

LEAVENWORTH

30

th S

t

Dodge St

Center St

10

th S

t

24

th S

t2

4th

St

42

nd

St

42

nd

St

72

nd

St

72

nd

St

L Street

Q Street

Maple St

Sa

dd

le C

ree

k

Ab

bo

tt D

r

Eppley Airfield

Carter Lake

City Council District 1

City Council District 2

City Council District 3

City Council District 4

City Council District 5

City Council District 6

City Council District 7

CSO Study Basins

North Segment

Completed Projects

Current Projects

LEGEND

Y

UW

Q

AABB

J

Z

T

The figure above, and corresponding table to the right identify the projects currently under construction. Each of these projects has

a corresponding detail write-up in the Appendix. Additional tables in the Appendix identify details on all active projects, as well as a

table that lists completed projects.

10 Omaha Combined Sewer Overflow Control Program | Implementation Phase

PROJECTS UNDER CONSTRUCTION

Page 11: 2016 1st Quarter Report - Omaha CSO · timely and accurate project information. The Program is also providing additional neighborhood benefits, above the improved sewer system. Public

CURRENT PROJECTS KEY PROJECT NAME CM CURRENT ESTIMATE AT COMPLETION % CHANGE

ORDER

J Improvements to the

Missouri River WWTP–

Schedule B1$60,642,505 4.8%

QSouth

Interceptor Force

Main-North Segment$21,550,000 <1%

TSpring Lake Park,

Sewer Separation$10,273,732 8.7%

Spring Lake Park,

Landscaping$596,650 0%

U

John Creighton

Boulevard (JCB) &

Miami Street Phases 1

& 2 Sewer Separation

and Adams Park

$21,222,069 19.8%

Adams Park

Landscaping

Improvements

Project

$598,137 0%

W Nicholas Street Phase

2 to 23rd and Grace$19,765,428 <-1%

YCole Creek CSO 204

Sewer Separation

Phase 1$3,990,526 0%

ZGilmore Avenue Sewer

Separation Phase 1

and 2$10,000,000 <1%

AA Saddle Creek RTB

Early Soil RemovalMarch 2016 NTP —

BB Vinton Street

Green Infrastructure$1,040,309 0%

www.OmahaCSO.com Clean Solutions for Omaha Quarterly Report | 1st Quarter 2016 11

Page 12: 2016 1st Quarter Report - Omaha CSO · timely and accurate project information. The Program is also providing additional neighborhood benefits, above the improved sewer system. Public

KEY ACTIVITIESBelow is a list of key activities for the past quarter and upcoming

quarter. A full list is included in the Appendix.

2015 4TH QUARTER KEY ACTIVITIESRegulatory

» Held quarterly meeting with NDEQ

and EPA to discuss Program progress.

» Discussed with NDEQ regarding concerns related to

higher project costs for MRWWTP Improvements,

Minne Lusa Stormwater Conveyance Sewer, and

Saddle Creek RTB.

Program

» Continued to look for ways to save money for

the ratepayers while still meeting the objectives

and requirements of the Clean Water Act and

expectations of the public.

» Held internal workshops to identify Program

cost savings.

Project

» Prepared Bid Advertisement for MRWWTP Schedule

B2 (expected bid opening in May)

» Held public meeting for:

› Cole Creek 204 Phase 2 (30% Design)

» Prepared professional services contracts for:

› Nicholas Street Sewer Separation Phase 3

› SC RTB Supplemental Final Design efforts

› Burt-Izard Lift Station Final Design efforts

› Riverview Lift Station Final Design efforts

» Issued RFP for MRWWTP Special Inspections

» Issued NTP for:

› Saddle Creek RTB Early Soils Project

› MRWWTP Bank Stabilization

UPCOMING 2016 2ND QUARTER KEY ACTIVITIESRegulatory

» Continue to hold quarterly meetings with NDEQ

and EPA to discuss Program progress.

» Continue discussion with NDEQ on Saddle Creek RTB

path forward.

Program

» Continue to look for ways to save money for the

ratepayers while still meeting the objectives and

requirements of the Clean Water Act.

Project

» Open bids for MRWWTP Schedule B2 (expected

in May)

» Public meeting for Fontenelle Park Improvement

is scheduled for April 5th

» Public meeting for Missouri Avenue Phase 2 is

scheduled for April 14th

» Conduct interviews and select consultant for

MRWWTP B2 Special Inspections

» Complete construction for Saddle Creek RTB Early

Soils Project

12 Omaha Combined Sewer Overflow Control Program | Implementation Phase

KEY ACTIVITIES