Mesquite Office Overton Office 731 Turtleback Rd 615 N. Moapa Valley Mesquite, NV 89027 Overton, NV 89040 Tel. (702) 346-5710 Tel. (702) 397-2512 Fax (702) 345-2318 Fax (702) 397-2799 Overton Power District No. 5 is a non-profit political subdivision of the State of Nevada. The District was created by the Public Utilities Commission of Nevada as a quasi-municipal special improvement district of the State of Nevada on October 28, 1935. The District’s service area encompasses the northeast quadrant of Clark County, Nevada which includes the City of Mesquite and the unincorporated towns of Bunkerville, Logandale, Moapa and Overton. The District also serves the Moapa Band of Paiutes, Valley of Fire State Park and the northeast portion of the Lake Mead National Recreation Area. Providing reliable power to enhance business opportunities and the quality of life of our customers, today and tomorrow. Dedicated to enhancing the lives of our customers by providing modern services, excellent customer service, and by delivering safe, high quality and reliable power at the lowest reasonable cost. ABOUT US OUR VISION OUR MISSION OVERTON POWER DISTRICT No. 5 COMMERCIAL BUSINESS BROCHURE FREQUENTLY ASKED QUESTIONS 1. What voltages do you provide? OPD provides voltages of 120/208, 277/480 up to a 1200 amp service size, and 120/240 up to 600 amp services. 2. How much will it cost to get power to my property? OPD is a non-profit, and all installations will be completed at the cost of materials and labor. Cost will vary by project depending on the location of the nearest power supply. The best way to get this information is by calling the Overton Power District No. 5 Engineering Department. See the contact list in this brochure for an engineer in your area. 3. Can I use a contractor for my project? OPD has a non-compete attitude toward work that does not affect our system integrity. Customers are encouraged to seek multiple bids from licensed contractors for the installation of underground and secondary power. To further clarify what portions of your project can be completed by a contractor contact an engineer in your area. 4. How long does it take to get power? It generally takes two (2) to four (4) weeks after plans have been submitted to the Engineering Department for service to be connected. If your project requires equipment that OPD does not have in its inventory, please see question 6 referencing equipment lead times. 5. What is the process to get power? This brochure contains a check list of requirements for new customers. You can also view the OPD Construction standards and specifications book at: www.opd5.com/specs 6. Upon payment, how long does it take to get electrical equipment? Typically, transformers and switches take two (2) to three (3) months once the order is placed. Lead times for equipment may vary. 7. Below are the transformer sizes (min/max) available from OPD. Single Phase, 50 KVA - 167 KVA 120/240 Three Phase 75 KVA - 500 KVA 120/208 Three Phase 75 KVA - 1500 KVA 277/480 RENEWABLE GENERATION & REBATE LIMITS Small Commercial Generator Size: The sum total of installed generation for small commercial customers shall be limited to a maximum of 10 kW. Customer generation exceeding 10 kW is permitted only by special contract with the District. The OPD rebate is up to $2,500 and is in addition to any state or federal rebates. Large Commercial Generator Size: The sum total of installed generation for large commercial customers shall be limited to a maximum of 25 kW. Customer generation exceeding 25 kW is permitted only by special contract with the District. The OPD rebate is up to $5,000 and is in addition to any state or federal rebates. The complete Net Metering policy can be found at www.opd5.com/net-metering-policy/ NOTES —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— www.opd5.com

2016 08-17 OPD NEW COMMERCIAL BROCHURE FINAL (002) · OPD provides voltages of 120/208, 277/480 up to a 1200 amp service size, and 120/240 up to 600 amp services. 2. How much will

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 2016 08-17 OPD NEW COMMERCIAL BROCHURE FINAL (002) · OPD provides voltages of 120/208, 277/480 up to a 1200 amp service size, and 120/240 up to 600 amp services. 2. How much will

Mesquite Office Overton Office 731 Turtleback Rd 615 N. Moapa Valley Mesquite, NV 89027 Overton, NV 89040 Tel. (702) 346-5710 Tel. (702) 397-2512 Fax (702) 345-2318 Fax (702) 397-2799

Overton Power District No. 5 is a non-profit political subdivision of the State of Nevada. The District was created by the Public Utilities Commission of Nevada as a quasi-municipal special improvement district of the State of Nevada on October 28, 1935. The District’s service area encompasses the northeast quadrant of Clark County, Nevada which includes the City of Mesquite and the unincorporated towns of Bunkerville, Logandale, Moapa and Overton. The District also serves the Moapa Band of Paiutes, Valley of Fire State Park and the northeast portion of the Lake Mead National Recreation Area.

Providing reliable power to enhance business opportunities and the quality of life of our customers, today and tomorrow.

Dedicated to enhancing the lives of our customers by providing modern services, excellent customer service, and by delivering safe, high quality and reliable power at the lowest reasonable cost.

ABOUT US

OUR VISION

OUR MISSION

OVERTON POWER DISTRICT No. 5 COMMERCIAL BUSINESS BROCHURE

FREQUENTLY ASKED QUESTIONS 1. What voltages do you provide? OPD provides voltages of 120/208, 277/480 up to a 1200 amp service size, and 120/240 up to 600 amp services.

2. How much will it cost to get power to my property? OPD is a non-profit, and all installations will be completed at the cost of materials and labor. Cost will vary by project depending on the location of the nearest power supply. The best way to get this information is by calling the Overton Power District No. 5 Engineering Department. See the contact list in this brochure for an engineer in your area. 3. Can I use a contractor for my project? OPD has a non-compete attitude toward work that does not affect our system integrity. Customers are encouraged to seek multiple bids from licensed contractors for the installation of underground and secondary power. To further clarify what portions of your project can be completed by a contractor contact an engineer in your area. 4. How long does it take to get power? It generally takes two (2) to four (4) weeks after plans have been submitted to the Engineering Department for service to be connected. If your project requires equipment that OPD does not have in its inventory, please see question 6 referencing equipment lead times.

5. What is the process to get power? This brochure contains a check list of requirements for new customers. You can also view the OPD Construction standards and specifications book at: www.opd5.com/specs 6. Upon payment, how long does it take to get electrical equipment? Typically, transformers and switches take two (2) to three (3) months once the order is placed. Lead times for equipment may vary. 7. Below are the transformer sizes (min/max) available from OPD. Single Phase, 50 KVA - 167 KVA 120/240 Three Phase 75 KVA - 500 KVA 120/208 Three Phase 75 KVA - 1500 KVA 277/480 RENEWABLE GENERATION & REBATE LIMITS

Small Commercial Generator Size: The sum total of installed generation for small commercial customers shall be limited to a maximum of 10 kW. Customer generation exceeding 10 kW is permitted only by special contract with the District. The OPD rebate is up to $2,500 and is in addition to any state or federal rebates. Large Commercial Generator Size: The sum total of installed generation for large commercial customers shall be limited to a maximum of 25 kW. Customer generation exceeding 25 kW is permitted only by special contract with the District. The OPD rebate is up to $5,000 and is in addition to any state or federal rebates. The complete Net Metering policy can be found at www.opd5.com/net-metering-policy/

NOTES

—————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— —————————————————————————————— ——————————————————————————————

www.opd5.com

Page 2: 2016 08-17 OPD NEW COMMERCIAL BROCHURE FINAL (002) · OPD provides voltages of 120/208, 277/480 up to a 1200 amp service size, and 120/240 up to 600 amp services. 2. How much will

RATE SCHEDULE Effective Oct 1, 2012

Small General Service Monthly Base Charge $21.50 Energy Charge First 1000 kWh $0.0870 Next 1000 kWh $0.0940 Over 2000 kWh $0.1010 Large General Service Monthly Base Charge $35.00 Demand Charge All kW $9.01 Energy Charge All kWh $0.0684

MEET OUR ENGINEERS

Boyd Evans Engineering Coordinator Mesquite Area [email protected] Tel. (702) 345-1108 Fax (702) 345-2318 Cell (702) 491-5134

Beady Long Staking Engineer Mesquite Area [email protected] Tel. (702) 345-1109 Fax (702) 345-2318 Cell (702) 219-0664

Brett Gale Staking Engineer Overton Area [email protected] Tel. (702) 397-3033 Fax (702) 397-2799 Cell (702) 232-5133

Luke Whitney Staking Engineer Overton Area [email protected] Tel. (702) 397-3022 Fax (702) 397-2799 Cell (702) 236-3612

NEW METER CONNECTION FEES Amps/Volts 200/208 400/208 600/208 Meter Cost $600.00 $750.00 $1,450.00 Customer Service Fee $25.00 $25.00 $25.00 Labor & Equipment* $150.00 $150.00 $150.00 Connect Fee $1,131.24 $2,262.47 $3,393.71 Substation Fee $1,080.80 $2,161.60 $3,242.40 Total $2,987.04 $5,349.07 $8,261.11 ______________________________________________________ Amps/Volts 200/480 400/480 600/480 Meter Cost $600.00 $750.00 $1,450.00 Customer Service Fee $25.00 $25.00 $25.00 Labor & Equipment* $150.00 $150.00 $150.00 Connect Fee $2,610.55 $5,221.09 $7,831.64 Substation Fee $2,494.15 $4,988.31 $7,482.46 Total $5,879.70 $11,134.40 $16,939.10

*Labor & Equipment cost may vary

MESQUITE AREA

OVERTON AREA

NEW CONSTRUCTION CHECKLIST

☐ A completed application for service. ☐ A parcel number and/or street address of the service

location. ☐ Voltage and load size in amps. Load size is equal to

main breaker rating. ☐ For a new installation we will need a plot map. The

plot map can be on a disk in Auto Cad 2010 or newer format, or can be sent by e-mail to an Engineer. If the property is in an existing sub division, a copy of your surveyed plot map is sufficient.

☐ When you have everything that is listed above contact one of the Staking Engineer’s listed below for an appointment. Please bring all the previous documents to your appointment with the Engineer.

☐ Pay Engineering fee if applicable. Engineering will not be done until fees are paid.

☐ Determine applicable connection fees. ☐ A job estimate will be provided to you when

Engineering is done with the design for your project. ☐ Upon receipt of your job estimate, please review.

Contact Engineering if there are any design conflicts that may need to be resolved.

☐ Pay the job estimate and connection fees in full. No work will be done until job estimate and impact fees are paid.

☐ Engineers will complete the project staking. ☐ A staking map and notice will be issued to you from

Overton Power to proceed. ☐ You may begin electrical installation. ☐ Inspections must be scheduled two (2) working days

in advance. To schedule an inspection call Armando Baeza Monday - Thursday at (702) 375-4360 or (702) 345-1112. Inspections are done in accordance with our Internet Construction Spec Book Guidelines available on our website:

www.opd5.com/construction ☐ Contact your Overton Power Engineer when you are

ready for HV conductor to be pulled and/or circuits to be energized.