2014 Recipients Workshop

The CDBG Program and its successful completion

September, 2014

Page 2: 2014 Recipients Workshop

Congratulations,

September 2014

You’ve won a Grant – Now What?

Topics we’ll discuss today: Key Players and their roles. Minimum Property Standards and Building

Codes. Housing Inspections. Work Write-ups, Cost Estimates, Scope of

Work. Bidding Procedures. Elements of a Construction Contract. Oversight of the work.

Page 3: 2014 Recipients Workshop

The Players and their roles

September 2014

The Program Director Develop and administer the program. Supervise a competent and efficient staff. Effectively communicate with elected

officials, program participants, and contractors.

Address local groups and gatherings. Ensure all reports, documents, and

paperwork are submitted on time. May or may not be an employee of the local

governing body.

Page 4: 2014 Recipients Workshop

The Players and their roles

September 2014

The Rehabilitation Advisor Construction and construction costing

experience is a MUST. Proficient in inspection procedures. Develop clear and coherent work write-ups,

specifications, and cost estimates. Knowledgeable of Lead Based Paint regulations. Communicate with all levels of the community –

especially contractors. Possess a pleasant and outgoing personality – or

at least be able to give that impression for a couple of hours at a time.

Page 5: 2014 Recipients Workshop

The Players and their roles

September 2014

The Appraiser The appraiser is not usually a

fulltime employee but rather a competent resource.

He/she should be well experienced and well respected in the local community.

He/she should be certified by the Ga. Real Estate Appraisers Board.

Page 6: 2014 Recipients Workshop

The Players and their roles

September 2014

The General Contractor This person can help your program receive

national recognition or put you in jail. They can be the best or the worst part of your program!

He/she should be a respected member of the community with a good reputation.

Construction experience and especially with rehab projects is essential.

Due diligence is highly recommended.

MORE ON THIS PERSON LATER.

Page 7: 2014 Recipients Workshop

Minimum Property Standards and Building Codes

September 2014

Georgia Building Codes The State of Georgia currently follows

the International Residential Code for One and Two Family Dwellings, 2006 edition with Georgia Amendments.

This is sometimes referred to as 2006 CABO One and Two Family Dwelling Code.

Page 8: 2014 Recipients Workshop

Minimum Property Standards and Building Codes

September 2014

Minimum Property Standards (MPS) –Defined.

A set of standards, created or adopted by the local governing body, that sets forth minimal conditions specific to property, structures, or environs within the community and describe what is “descent, safe, and sanitary”.

Page 9: 2014 Recipients Workshop

Minimum Property Standards and Building Codes

September 2014

Minimum Property Standards may also: function as a base line of materials

used, material properties, structural design, etc.

may exceed Georgia building codes but may not hold a lower standard.

Page 10: 2014 Recipients Workshop

Minimum Property Standards and Building Codes

September 2014

Minimum Property Standards may define: What materials may and/or may not be

used. The properties of the material (e.g.

grade of lumber, PSI rating of concrete, durability of roof shingles, etc.).

How the materials will be installed, used, or applied.

May be associated with certain zoning regulations.

Page 11: 2014 Recipients Workshop

Minimum Property Standards and Building Codes

September 2014

Minimum Property Standards

Sample MPS may be obtained from a variety of sources including some off-the-shelf software programs.

You may develop you own MPS, however, make sure that they do not compromise other related standards or Georgia codes.

Page 12: 2014 Recipients Workshop

Minimum Property Standards and Building Codes

September 2014

Minimum Property StandardsIn the absence of a local MPS, you may

opt to adopt one of the following model codes: Uniform Building Code (ICBO). National Building Code (BOCA). Standard Southern Building Code

(SBCCI). FHA Minimum Property

Standards.

Page 13: 2014 Recipients Workshop

Housing Inspections

September 2014

Preliminary worko Have a working knowledge of Ga. Building Codes

and local MPS.o Do a walk around to get the feeling of the

structure.o Take lots of photographs of interior rooms – with

notations.o Take photographs of all four exterior elevations.o Depending upon extent of work required, a floor

plan is a good idea. Take accurate interior and exterior measurements.

o If you have the capability, do an CAD drawing of the structure, or do a good quality scaled pencil drawing.

Page 14: 2014 Recipients Workshop

Housing Inspections

September 2014

Preliminary work (continued)o Make copious notes, memory joggers,

dimensions, and material attributes (e.g. color. material, texture, etc.). You’ll need them later – guaranteed!

o Prepare a tool box of tools you’ll likely need: flashlight, good screwdriver set, pliers, pocket knife, probing tools, measuring tape, and writing pad.

o Treat the owner with utmost respect. Respect the furnishings and décor.

o Don’t touch anything you don’t intend to inspect.

Page 15: 2014 Recipients Workshop

Housing Inspections

September 2014

Lead Based Paint (LPB)o Consult a certified Lead Based Paint Assessor

prior to any rehab if:o The structure was built before 1978.o If you suspect the presence of LPB (e.g.

antique doors in newer homes).o If the age of the home cannot be precisely

determined and children under 6 or pregnant/fecund females are in residence.

o If the age of the home cannot be precisely determined and there is an reasonable expectation of such residents in the future.

Page 16: 2014 Recipients Workshop

Housing Inspections

September 2014

Who performs a general home inspection?o Your Rehab Advisor.o City or county building inspector.o Experienced builder or general

contractor – Can not bid on work!o Pro Bono engineer or architecto A Certified Home Inspector.

Page 17: 2014 Recipients Workshop

Housing Inspections

September 2014

What is inspected?o Basically … everything.o Health and safety issues should take first

priority.o ADA issues.o Code and MPS violations.o Structural issues.o Incipient problems.o Site and topographical issues.o General Property Improvements (GPI)

under certain conditions.

Page 18: 2014 Recipients Workshop

Work Write–ups, Cost Estimates, and Scopes of Work

September 2014

What is a Work Write-up?o A Work Write-up (WWU) is a document

that provides the home owner and Program Director a complete description of what work will be required – compare this to a “Scope of Work”.

o A WWU should be created by your Rehab Advisor or a qualified inspector.

Page 19: 2014 Recipients Workshop

Work Write–ups, Cost Estimates, and Scopes of Work

September 2014

A WWU should accurately describe:o Each task to be done.o Location of each task (e.g. inside closet

door, bedroom #2, toilet in bathroom #1).

o An estimate of area involved (e.g. square yards, linear feet, squares, etc.).

o A WWU should be typed in a good, clear, easy to understand format.

o List and number each item separately.

Page 20: 2014 Recipients Workshop

Work Write–ups, Cost Estimates, and Scopes of Work

September 2014

Cost Estimateso A Cost Estimate is a document that tells

the Rehab Advisor the approximate cost of each item on each project.

o A good deal of experience is required to develop a good cost estimate.

o Don’t let a potential contractor do the Cost Estimate it happens!

o Cost Estimates should never be shown to anyone (except staff) even after job completion.

Page 21: 2014 Recipients Workshop

Work Write–ups, Cost Estimates, and Scopes of Work

September 2014

Scope of Work – the Contractor’s list of tasks to be completed.

o The Scope of Work is basically the same as the Work Write-up and contains the same information without to unit cost.

o It’s a good practice to have the home owner sign and date the bottom of each page of the Scope of Work.

Page 22: 2014 Recipients Workshop

Specifications

September 2014

A Specification describes precisely the attributes of any particular component of a task. (Example: a kitchen countertop)

o Specific material: Formica, cultured marble, Corian.

o Color.o Texture.o Style: Drop-in sink, formed sink.o Precise Dimensions.o Other relevant information.

Page 23: 2014 Recipients Workshop

Specifications

September 2014

o The home owner should have input in the Specification – use caution here!

o Specific brand names and model numbers.o It’s advisable to have the home owner sign or

initial any sample:o Color chip.o Carpet or vinyl flooring.o Counter top sample.o Roof shingles.

Lack of attribute specifications is the major cause of contractual disputes.

Page 24: 2014 Recipients Workshop

Bidding and Procurement

September 2014

Finding Contractorso Advertise your program in local papers.o Post ads at locations frequented by

contractors.Home Depot, Lowes, etc.Building materials supply houses.

City or county building permits offices.Other local communities using grant

monies.o Create a list of pre-screened contractors

and share with other agencies.o Publish “Invitation to Bid” in news papers.

Page 25: 2014 Recipients Workshop

Bidding and Procurement

September 2014

Contractors: Evaluate this person as if he was going to marry your daughter!

o Review data on Principle owner.o Review financial references.o Ensure proof of insurance.o Obtain Tax ID number.o Research other business names. Principle owner

may have owned.o HUD debarment list…. Mandatory.o Obtain past customer list – select some and call.

MUST HAVE CURRENT STATE LICENSE!

Page 26: 2014 Recipients Workshop

Bidding and Procurement

September 2014

Bidding ProcessTwo options given to home owner as to which type of bidding process they prefer “Open, Free, and Competitive” bid process. “Negotiated” bid process.

Form 20-A, 20-B, or 20-C should be completed and signed depending upon owners choice of “Open, Free, and Competitive” or “Negotiated” option and whether rehab or reconstruction

Page 27: 2014 Recipients Workshop

Bidding and Procurement

September 2014

“Open, Free, and Competitive”

Prepare a “Bid Package” to include:o A “Contractors Bid Packet” (See Form 6).o Address of property and Owners name.o “General Conditions” and “Special Conditions” (See

Exhibit “F2a” & “F2b”).o “Bid and Proposal Form” (Exhibit “F2d”).o Complete Scope of Work.o Scale drawings (Exhibit “F2f”).o Date, time, and location of bid opening if appropriate.o Terms and Conditions of Rehabilitation Assistance.o Draw Schedule.

Page 28: 2014 Recipients Workshop

Bidding and Procurement

September 2014

“Open, Free, and Competitive”o Bid Package should preferably be picked-up at

program office.o Log of contractors showing date and time of receipt.o Consider on-site meeting to answer questions.o Do not alter “Scope of Work” at this point. Changes

will handled with a Change Order later.o If you have post meeting questions, inform all

bidders.

Seek out as many contractors as possible.

Ask those choosing not to bid to provide your office a short note on letter head stating “NO BID” on so-and-so contract.

Page 29: 2014 Recipients Workshop

Bidding and Procurement

September 2014

“Negotiated”

o Home owner may select contractor of their choice so long as contractor meets all program eligibility requirements.

o Negotiated contractors bid must be within 10% of cost estimate or be negotiated to within that amount.

ORo Home owner agrees to pay the amount over the

10% limit.o Failing to meet these requirements, project must

be re-bid.

Page 30: 2014 Recipients Workshop

Bidding and Procurement

September 2014

Receiving the Bids:o NEVER OPEN A BID ENVELOPE BEFORE BID

OPENING DATE AND TIME!o Upon receiving the bid response, make certain the

envelope is sealed.o If not sealed, initial across the envelope flap and

tape over the initials with clear tape while in view of contractor or other witness.

o Ensure contractors name, project address, and bid opening date and time are noted on the outside.

o Write or stamp date and exact time of receipt and sign receivers name.

o Enter received bid into contractor log.

Page 31: 2014 Recipients Workshop

Bidding and Procurement

September 2014

Opening the Bids:o Establish date and time of opening.o Invite home owner, responding contractors or

other interested parties should be welcome.o Ensure one witnessing staff member is present.o Do not award bid at contract opening!o You do not have to accept the lowest bid.o Be aware of “Low Ball” bids.o Home owner should make final decision.o Bids in excess of 10% above or below cost

estimate should be discarded.o Any bid in excess of 20% above cost estimate

must have DCA approval prior to contract award.

Page 32: 2014 Recipients Workshop

Bidding and Procurement

September 2014

One last thing about bids.

Don’t even think about revising cost estimates to match received bids.

Page 33: 2014 Recipients Workshop

Awarding the Contract

September 2014

The Contract:o The “Guidelines for Residential Rehabilitation”

contains a good section on the elements of a Construction Contract.

o Exhibits “F1”, “F2a”, and F2b” provide an outline.o A “Notice to Commence” or “Notice to Proceed” must

be issued prior to starting work (Form 10).o A sample of a “General Contractor Invoice” (Form 11)

more frequently called a “Request for Draw” should be included. Expect the contractor to use this format.

o Include the “Draw Schedule” in the contract.o Include a sample of a “Release and Waiver of Claim

for Subcontractor or Material Supplier” (Form 11). This is more commonly referred to as a “Mechanics Lien”.

Page 34: 2014 Recipients Workshop

Awarding the Contract

September 2014

The Contract:

o Federal Contractual Requirements:Contractor should provide certification that he/she will abide by all the regulations and provisions as set forth in:

o The Davis/Bacon Act.o The Contract Work Hours and Safety

Standards Act.o The Copeland Anti-Kickback Act.o The Health and Safety Act.

o ;

Page 35: 2014 Recipients Workshop

Contract Oversight

September 2014

Review work on a regular basis to ensure specifications are met.

Document all site visits and inspections.

Ensure Safety measures have been taken.

NEVER verbally agree to a Change Order.

Change Orders must be signed by all parties.

Inspect work prior to approving a Draw Request.

Never vary from the “Scope of Work” without a Change Order.

Page 36: 2014 Recipients Workshop

Grievance and Arbitration

September 2014

Establish a clearly defined Grievance and Arbitration procedure in your Policies and Procedures Statement.

Include this Statement in the Contract between the home owner and contractor.

90% of all grievances can be resolved at this level.

IF YOU DON’T HAVE A WELL WRITTEN WORK WRITE-UP: YOU’RE ALREADY IN TROUBLE!

Page 37: 2014 Recipients Workshop

Monitoring for compliance

September 2014

All programs are required to be monitored. Monitoring are usually scheduled in

advance but may be subject to review without notice.

You are responsible for organization and maintenance of all records.

A Contractual obligation between a recipient and a third party (i.e. Consultant) does not absolve the recipient of ultimate accountability for all aspects of the grant.

Page 38: 2014 Recipients Workshop

Notice

September 2014

There is a revision to the Financial Plan (Exhibit H) that now requires the address of the participant along with the Unit Number and Owner’s Name. The new format is to be found in the Rehab and the Recipients’ Manuals. When applying for a Grant Modification, please use these new forms.

Page 39: 2014 Recipients Workshop

Grant Modifications

September 2014

A Grant Modification will be required when seeking:1. Grant Adjustment Request.2. Modification of Scope.3. Rehabilitation to Reconstruction.4. Addition and/or substitution of a unit.5. Expansion or modification of Target

Area.

Page 40: 2014 Recipients Workshop

Speaking of Grants Modifications . . .

September 2014

When seeking a Grant Modification, you must now provide a full synopsis of the current status of the entire grant including: • a unit by unit status (complete, in

progress, drop out, over income, ineligible, etc.).

• if Multi-activity, please provide a current status of all other activities.

Page 41: 2014 Recipients Workshop

Grant Modifications

September 2014

If changing a unit from Rehab to Recon . . .

ORadding a new Rehab or Recon not previously identified as a target unit, you must:• Submit a “Rehab Feasibility Test Form”.

• Photographs with narratives.• Final Cost Estimates.• Seek a “Grant Modification” as noted above.

Page 42: 2014 Recipients Workshop

Policies and Procedures

September 2014

Prior to beginning any Housing activity, DCA will now require each grant recipient to submit a final version of their Policies and Procedures Statement to DCA for review and approval.

NO DRAWS WILL BE MADE UNTIL APPROVAL IS RECEIVED.

Page 43: 2014 Recipients Workshop

Illegal Immigration Reform and Enforcement Act of 2011

September 2014

You are Required to obtain proof of lawful presence. See “Exhibit L”

Accepted forms of documentation are indicated.

Must be obtained prior to determination of program eligibility.

MUST be incorporated into grantees “Policies and Procedures”

Page 44: 2014 Recipients Workshop

Illegal Immigration Reform and Enforcement Act of 2011

September 2014

Construction Contractors who are under contract WITH THE LOCAL GOVERNMENTAS A DIRECT PARTY TO THE CONTRACT must participate in the E-Verify system to document the Lawful Presence of all employees of the company AND subcontractors.

This usually will only apply to public works projects.

Page 45: 2014 Recipients Workshop

September 2014

Under O.C.G.A 50-36-1, The Illegal Immigration Reform and Enforcement Act of 2011, (including House Bill 2 and House Bill 87) you are required to obtain proof of lawful presence in order to obtain a “Public Benefit” as defined in this law. This includes (but is not limited to )types of housing and housing related assistance. The appropriate form may be found in Exhibit L (page 156), the accepted forms of documentation immediately follow. This Affidavit must be obtained prior to determination of program eligibility and all documentation (the completed form and supporting documentation) must be located in the participants file. This agreement and understanding MUST be incorporated into the Policies and Procedures of the award grantee.

Page 46: 2014 Recipients Workshop

Notices

September 2014

Monitoring: Emphasis on File Organization. All appropriate Signatures. Quality of Work Write-Ups especially

“Specifications”. Necessity of “Change Orders”. Progress performance.

Page 47: 2014 Recipients Workshop

QUESTIONS?