43
1 ArevaEPRDCPEm Resource From: HOTTLE Nathan (AREVA) [[email protected]] Sent: Monday, September 16, 2013 5:50 PM To: Snyder, Amy Cc: Miernicki, Michael; RANSOM Jim (AREVA); LEIGHLITER John (AREVA); UYEDA Graydon (AREVA); GUCWA Len (EXTERNAL AREVA); RYAN Tom (AREVA); DELANO Karen (AREVA); ROMINE Judy (AREVA) Subject: Response to U.S. EPR Design Certification Application RAI No. 412, FSAR Ch. 3, Supplement 12 Attachments: RAI 412 Supplement 12 Response US EPR DC.pdf Amy, AREVA NP Inc. (AREVA NP) provided a schedule for a technically correct and complete response to RAI 412 on June 24, 2010. On August 27, 2010, AREVA NP submitted Supplement 1 to provide an INTERIM response to Question 03.07.02-73. AREVA NP submitted a revised schedule for Question 03.07.02-74 in Supplement 2 and Supplement 3 on September 15, 2010, and November 15, 2010, respectively. On January 27, 2011, AREVA NP submitted Supplement 4 to provide a revised schedule for Question 03.07.02-74. On February 11, 2011, AREVA NP submitted Supplement 5 to provide a revised schedule for Question 03.07.02-73. AREVA NP submitted Supplement 6 on March 22, 2011, to provide a revised schedule for Question 03.07.02-74. On May 2, 2011, AREVA NP submitted Supplement 7 to provide a revised schedule for Question 03.07.02-73. AREVA NP submitted Supplement 8 on May 12, 2011, to provide a final response for Question 03.07.02-74. AREVA NP submitted Supplement 9 on June 13, 2011, to provide a final response for Question 03.07.02-73. AREVA NP submitted Supplement 10 on June 18, 2013, to provide a revised schedule and response for Question 03.07.02-74. AREVA NP submitted Supplement 11 on August 15, 2013, to provide a revised schedule and response for Question 03.07.02-74. The attached file, “RAI 412 Supplement 12 Response US EPR DC.pdf” provides a technically correct, complete and final response to Question 03.07.02-74, as committed. Appended to this file are the affected pages of the U.S. EPR Final Safety Analysis Report in redline-strikeout format which support the response to RAI 412 Question 03.07.02-74. The following table indicates the respective pages in the response document, “RAI 412 Supplement 12 Response US EPR DC.pdf,” that contain AREVA NP’s response to the subject question. Question # Start Page End Page RAI 412 — 03.07.02-74 2 28 This concludes the formal AREVA NP response to RAI 412, and there are no questions from this RAI for which AREVA NP has not provided responses. Sincerely, Nathan Hottle AREVA Inc. 3315 Old Forest Road Lynchburg, VA 24501 Phone 434-832-3864 Mobile 434-485-4239 [email protected]

2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

1

ArevaEPRDCPEm Resource

From: HOTTLE Nathan (AREVA) [[email protected]]Sent: Monday, September 16, 2013 5:50 PMTo: Snyder, AmyCc: Miernicki, Michael; RANSOM Jim (AREVA); LEIGHLITER John (AREVA); UYEDA Graydon

(AREVA); GUCWA Len (EXTERNAL AREVA); RYAN Tom (AREVA); DELANO Karen (AREVA); ROMINE Judy (AREVA)

Subject: Response to U.S. EPR Design Certification Application RAI No. 412, FSAR Ch. 3, Supplement 12

Attachments: RAI 412 Supplement 12 Response US EPR DC.pdf

Amy, AREVA NP Inc. (AREVA NP) provided a schedule for a technically correct and complete response to RAI 412 on June 24, 2010. On August 27, 2010, AREVA NP submitted Supplement 1 to provide an INTERIM response to Question 03.07.02-73. AREVA NP submitted a revised schedule for Question 03.07.02-74 in Supplement 2 and Supplement 3 on September 15, 2010, and November 15, 2010, respectively. On January 27, 2011, AREVA NP submitted Supplement 4 to provide a revised schedule for Question 03.07.02-74. On February 11, 2011, AREVA NP submitted Supplement 5 to provide a revised schedule for Question 03.07.02-73. AREVA NP submitted Supplement 6 on March 22, 2011, to provide a revised schedule for Question 03.07.02-74. On May 2, 2011, AREVA NP submitted Supplement 7 to provide a revised schedule for Question 03.07.02-73. AREVA NP submitted Supplement 8 on May 12, 2011, to provide a final response for Question 03.07.02-74. AREVA NP submitted Supplement 9 on June 13, 2011, to provide a final response for Question 03.07.02-73. AREVA NP submitted Supplement 10 on June 18, 2013, to provide a revised schedule and response for Question 03.07.02-74. AREVA NP submitted Supplement 11 on August 15, 2013, to provide a revised schedule and response for Question 03.07.02-74. The attached file, “RAI 412 Supplement 12 Response US EPR DC.pdf” provides a technically correct, complete and final response to Question 03.07.02-74, as committed. Appended to this file are the affected pages of the U.S. EPR Final Safety Analysis Report in redline-strikeout format which support the response to RAI 412 Question 03.07.02-74. The following table indicates the respective pages in the response document, “RAI 412 Supplement 12 Response US EPR DC.pdf,” that contain AREVA NP’s response to the subject question. Question # Start Page End Page RAI 412 — 03.07.02-74 2 28

This concludes the formal AREVA NP response to RAI 412, and there are no questions from this RAI for which AREVA NP has not provided responses. Sincerely, Nathan Hottle AREVA Inc. 3315 Old Forest Road Lynchburg, VA 24501 Phone 434-832-3864 Mobile 434-485-4239 [email protected]

Page 2: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

2

From: RYAN Tom (RS/NB) Sent: Thursday, August 15, 2013 10:41 AM To: [email protected] Cc: '[email protected]'; ANDERSON Katherine (External AREVA NP INC.); DELANO Karen (RS/NB); LEIGHLITER John (RS/NB); LEWIS Ray (External RS/NB); ROMINE Judy (RS/NB); SHEPHERD Tracey (RS/NB); WILLIFORD Dennis (RS/NB); LOSEKE Brian (EP/PE); HOTTLE Nathan (EP/PE) Subject: Response to U.S. EPR Design Certification Application RAI No. 412, FSAR Ch. 3, Supplement 11 Amy, AREVA NP Inc. (AREVA NP) provided a schedule for a technically correct and complete response to RAI 412 on June 24, 2010. On August 27, 2010, AREVA NP submitted Supplement 1 to provide an INTERIM response to Question 03.07.02-73. AREVA NP submitted a revised schedule for Question 03.07.02-74 in Supplement 2 and Supplement 3 on September 15, 2010, and November 15, 2010, respectively. On January 27, 2011, AREVA NP submitted Supplement 4 to provide a revised schedule for Question 03.07.02-74. On February 11, 2011, AREVA NP submitted Supplement 5 to provide a revised schedule for Question 03.07.02-73. AREVA NP submitted Supplement 6 on March 22, 2011, to provide a revised schedule for Question 03.07.02-74. On May 2, 2011, AREVA NP submitted Supplement 7 to provide a revised schedule for Question 03.07.02-73. AREVA NP submitted Supplement 8 on May 12, 2011, to provide a final response for Question 03.07.02-74. AREVA NP submitted Supplement 9 on June 13, 2011, to provide a final response for Question 03.07.02-73. AREVA NP submitted Supplement 10 on June 18, 2013, to provide a revised schedule and response for Question 03.07.02-74. AREVA received comments on the advanced response to this question from NRC staff on June 25, 2013 and discussed those comments with NRC staff on July 11, 2013. AREVA requires additional time to complete incorporation of NRC staff comments into the final response to this RAI question. An updated schedule for the final response to RAI 412 Question 03.07.02-74 is provided below:

Question # Advanced Response Date

NRC Comment Date

Final Response Date

RAI 412 — 03.07.02-74 June 18, 2013-A June 25, 2013-A September 17, 2013 Sincerely, Tom Ryan Manager, US EPR DCD Regulatory Affairs AREVA NP An AREVA and Siemens company 7207 IBM Drive - CLT2B Charlotte, NC 28262 Phone: 704-805-2643, Cell : 704-292-5627 Fax: 434-382-6657

From: KOWALSKI David (RS/NB) Sent: Tuesday, June 18, 2013 9:54 AM

Page 3: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

3

To: [email protected] Cc: [email protected]; ANDERSON Katherine (External AREVA NP INC.); DELANO Karen (RS/NB); LEIGHLITER John (RS/NB); LEWIS Ray (External RS/NB); ROMINE Judy (RS/NB); RYAN Tom (RS/NB); SHEPHERD Tracey (RS/NB); VANCE Brian (RS/NB); GUCWA Len (External RS/NB); KOWALSKI David (RS/NB); WILLIFORD Dennis (RS/NB); LOSEKE Brian (EP/PE) Subject: Response to U.S. EPR Design Certification Application RAI No. 412, FSAR Ch. 3, Supplement 10 Amy, AREVA NP Inc. (AREVA NP) provided a schedule for a technically correct and complete response to RAI 412 on June 24, 2010. On August 27, 2010, AREVA NP submitted Supplement 1 to provide an INTERIM response to Question 03.07.02-73. AREVA NP submitted a revised schedule for Question 03.07.02-74 in Supplement 2 and Supplement 3 on September 15, 2010, and November 15, 2010, respectively. On January 27, 2011, AREVA NP submitted Supplement 4 to provide a revised schedule for Question 03.07.02-74. On February 11, 2011, AREVA NP submitted Supplement 5 to provide a revised schedule for Question 03.07.02-73. AREVA NP submitted Supplement 6 on March 22, 2011, to provide a revised schedule for Question 03.07.02-74. On May 2, 2011, AREVA NP submitted Supplement 7 to provide a revised schedule for Question 03.07.02-73. AREVA NP submitted Supplement 8 on May 12, 2011, to provide a final response for Question 03.07.02-74. AREVA NP submitted Supplement 9 on June 13, 2011, to provide a final response for Question 03.07.02-73. As discussed with NRC during a conference call on June 11, 2013, AREVA NP committed to provide NRC a revised schedule and response for Question 03.07.02-74. The schedule for a technically correct and complete revised response to Question 03.07.02-74 is provided below.

Question # Advanced Response Date

NRC Comment Request Date

Final Response Date

RAI 412 — 03.07.02-74 June 28, 2013 August 6, 2013 August 15, 2013 Sincerely, David Kowalski for

Dennis Williford, P.E. U.S. EPR Design Certification Licensing Manager AREVA NP Inc. 7207 IBM Drive, Mail Code CLT 2B Charlotte, NC 28262 Phone: 704-805-2223 Email: [email protected]

From: RYAN Tom (RS/NB) Sent: Monday, June 13, 2011 8:40 AM To: 'Tesfaye, Getachew' Cc: BENNETT Kathy (RS/NB); DELANO Karen (RS/NB); HALLINGER Pat (EXT); ROMINE Judy (RS/NB); BREDEL Daniel (EP/PE); WILLIAMSON Rick (EP/PP); WILLIFORD Dennis (RS/NB); CORNELL Veronica (External RS/NB) Subject: Response to U.S. EPR Design Certification Application RAI No. 412, FSAR Ch. 3, Supplement 9 Getachew,

Page 4: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

4

AREVA NP Inc. (AREVA NP) provided a schedule for a technically correct and complete response to RAI 412 on June 24, 2010. On August 27, 2010, AREVA NP submitted Supplement 1 to provide an INTERIM response to Question 03.07.02-73. AREVA NP submitted a revised schedule for Question 03.07.02-74 in Supplement 2 and Supplement 3 on September 15, 2010, and November 15, 2010, respectively. On January 27, 2011, AREVA NP submitted Supplement 4 to provide a revised schedule for Question 03.07.02-74. On February 11, 2011, AREVA NP submitted Supplement 5 to provide a revised schedule for Question 03.07.02-73. AREVA NP submitted Supplement 6 on March 22, 2011, to provide a revised schedule for Question 03.07.02-74. On May 2, 2011, AREVA NP submitted Supplement 7 to provide a revised schedule for Question 03.07.02-73. AREVA NP submitted Supplement 8 on May 12, 2011, to provide a final response for Question 03.07.02-74. The attached file, “RAI 412 Supplement 9 Response US EPR DC.pdf” provides a technically correct, complete and final response to Question 03.07.02-73, as committed. Appended to this file are the affected pages of the U.S. EPR Final Safety Analysis Report in redline-strikeout format which support the response to RAI 412 Question 03.07.02-73. The following table indicates the respective pages in the response document, “RAI 412 Supplement 9 Response US EPR DC.pdf,” that contain AREVA NP’s response to the subject question. Question # Start Page End Page RAI 412 — 03.07.02-73 2 15

This concludes the formal AREVA NP response to RAI 412, and there are no questions from this RAI for which AREVA NP has not provided responses. Sincerely, Tom Ryan for Dennis Williford, P.E. U.S. EPR Design Certification Licensing Manager AREVA NP Inc. 7207 IBM Drive, Mail Code CLT 2B Charlotte, NC 28262 Phone: 704-805-2223 Email: [email protected]

From: WELLS Russell (RS/NB) Sent: Thursday, May 12, 2011 4:32 PM To: Tesfaye, Getachew Cc: CORNELL Veronica (External RS/NB); BENNETT Kathy (RS/NB); DELANO Karen (RS/NB); ROMINE Judy (RS/NB); RYAN Tom (RS/NB) Subject: Response to U.S. EPR Design Certification Application RAI No. 412, FSAR Ch. 3, Supplement 8 Getachew, AREVA NP Inc. (AREVA NP) provided a schedule for a technically correct and complete response to RAI 412 on June 24, 2010. On August 27, 2010, AREVA NP submitted Supplement 1 to provide an INTERIM response to Question 03.07.02-73. AREVA NP submitted a revised schedule for Question 03.07.02-74 in Supplement 2 and Supplement 3 on September 15, 2010, and November 15, 2010, respectively. On January 27, 2011, AREVA NP submitted Supplement 4 to provide a revised schedule for Question 03.07.02-74. On February 11, 2011, AREVA NP submitted Supplement 5 to provide a revised schedule for Question 03.07.02-73. AREVA NP submitted Supplement 6 on March 22, 2011, to provide a revised schedule for Question 03.07.02-74. On May 2, 2011, AREVA NP submitted Supplement 7 to provide a revised schedule for Question 03.07.02-73.

Page 5: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

5

The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response to Question 03.07.02-74, as committed. Appended to this file are the affected pages of the U.S. EPR Final Safety Analysis Report in redline-strikeout format which support the response to RAI 412 Question 03.07.02-74. The following table indicates the respective pages in the response document, “RAI 412 Supplement 8 Response US EPR DC.pdf,” that contain AREVA NP’s response to the subject question. Question # Start Page End Page RAI 412 — 03.07.02-74 2 25

The schedule for a technically correct and complete response to the remaining question is unchanged and is provided below. Question # Interim Response Date Response Date RAI 412 — 03.07.02-73 August 29, 2010 (Actual) July 1, 2011

Sincerely, Russ Wells U.S. EPR Design Certification Licensing Manager AREVA NP, Inc. 3315 Old Forest Road, P.O. Box 10935 Mail Stop OF-57 Lynchburg, VA 24506-0935 Phone: 434-832-3884 (work) 434-942-6375 (cell) Fax: 434-382-3884 [email protected]

From: WELLS Russell (RS/NB) Sent: Monday, May 02, 2011 10:29 AM To: Tesfaye, Getachew Cc: CORNELL Veronica (External RS/NB); BENNETT Kathy (RS/NB); DELANO Karen (RS/NB); ROMINE Judy (RS/NB); RYAN Tom (RS/NB) Subject: Response to U.S. EPR Design Certification Application RAI No. 412, FSAR Ch. 3, Supplement 7 Getachew, AREVA NP Inc. (AREVA NP) provided a schedule for a technically correct and complete response to RAI 412 on June 24, 2010. On August 27, 2010, AREVA NP submitted Supplement 1 to provide an INTERIM response to Question 03.07.02-73. AREVA NP submitted a revised schedule for Question 03.07.02-74 in Supplement 2 and Supplement 3 on September 15, 2010, and November 15, 2010, respectively. On January 27, 2011, AREVA NP submitted Supplement 4 to provide a revised schedule for Question 03.07.02-74. On February 11, 2011, AREVA NP submitted Supplement 5 to provide a revised schedule for Question 03.07.02-73. AREVA NP submitted Supplement 6 on March 22, 2011, to provide a revised schedule for Question 03.07.02-74. Due to changes in the schedule for FSAR Sections 3.7 and 3.8 as discussed with NRC, the schedule for Question 03.07.02-73 is being revised. The schedule for the remaining question is unchanged. The schedule for a technically correct and complete response to the remaining questions is provided below.

Page 6: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

6

Question # Interim Response Date Response Date RAI 412 — 03.07.02-73 August 29, 2010 (Actual) July 1, 2011 RAI 412 — 03.07.02-74 N/A May 12, 2011

Sincerely, Russ Wells U.S. EPR Design Certification Licensing Manager AREVA NP, Inc. 3315 Old Forest Road, P.O. Box 10935 Mail Stop OF-57 Lynchburg, VA 24506-0935 Phone: 434-832-3884 (work) 434-942-6375 (cell) Fax: 434-382-3884 [email protected]

From: WELLS Russell (RS/NB) Sent: Tuesday, March 22, 2011 5:35 PM To: 'Tesfaye, Getachew' Cc: CORNELL Veronica (External RS/NB); BENNETT Kathy (RS/NB); DELANO Karen (RS/NB); ROMINE Judy (RS/NB); RYAN Tom (RS/NB) Subject: Response to U.S. EPR Design Certification Application RAI No. 412, FSAR Ch. 3, Supplement 6 Getachew, AREVA NP Inc. (AREVA NP) provided a schedule for a technically correct and complete response to RAI 412 on June 24, 2010. On August 27, 2010, AREVA NP submitted Supplement 1 to provide an INTERIM response to Question 03.07.02-73. AREVA NP submitted a revised schedule for Question 03.07.02-74 in Supplement 2 and Supplement 3 on September 15, 2010, and November 15, 2010, respectively. On January 27, 2011, AREVA NP submitted Supplement 4 to provide a revised schedule for Question 03.07.02-74. On February 11, 2011, AREVA NP submitted Supplement 5 to provide a revised schedule for Question 03.07.02-73. The schedule for Question 03.07.02-74 is being revised to allow AREVA NP additional time to address NRC comments. The schedule for the remaining question is unchanged. The schedule for a technically correct and complete response to the remaining questions is provided below. Question # Interim Response Date Response Date RAI 412 — 03.07.02-73 August 29, 2010 (Actual) May 12, 2011 RAI 412 — 03.07.02-74 N/A May 12, 2011

Sincerely, Russ Wells U.S. EPR Design Certification Licensing Manager AREVA NP, Inc. 3315 Old Forest Road, P.O. Box 10935 Mail Stop OF-57

Page 7: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

7

Lynchburg, VA 24506-0935 Phone: 434-832-3884 (work) 434-942-6375 (cell) Fax: 434-382-3884 [email protected]

From: BRYAN Martin (External RS/NB) Sent: Friday, February 11, 2011 3:06 PM To: 'Tesfaye, Getachew' Cc: DELANO Karen (RS/NB); ROMINE Judy (RS/NB); BENNETT Kathy (RS/NB); CORNELL Veronica (External RS/NB) Subject: Response to U.S. EPR Design Certification Application RAI No. 412, FSAR Ch. 3, Supplement 5 Getachew, AREVA NP Inc. (AREVA NP) provided a schedule for a technically correct and complete response to RAI 412 on June 24, 2010. On August 27, 2010, AREVA NP submitted Supplement 1 to provide an INTERIM response to Question 03.07.02-73. AREVA NP submitted a revised schedule for Question 03.07.02-74 in Supplement 2 and Supplement 3 on September 15, 2010, and November 15, 2010, respectively. On January 27, 2011, AREVA NP submitted Supplement 4 to provide a revised schedule for Question 03.07.02-74. The schedule for Question 03.07.02-73 has changed. The schedule for the remaining question is unchanged. The schedule for a technically correct and complete response to the remaining questions is provided below. Question # Interim Response Date Response Date RAI 412 — 03.07.02-73 August 29, 2010 (Actual) May 12, 2011 RAI 412 — 03.07.02-74 N/A March 23, 2011

Sincerely, Martin (Marty) C. Bryan U.S. EPR Design Certification Licensing Manager AREVA NP Inc. Tel: (434) 832-3016 702 561-3528 cell [email protected]

From: BRYAN Martin (External RS/NB) Sent: Thursday, January 27, 2011 11:47 AM To: 'Tesfaye, Getachew' Cc: DELANO Karen (RS/NB); ROMINE Judy (RS/NB); BENNETT Kathy (RS/NB); CORNELL Veronica (External RS/NB) Subject: Response to U.S. EPR Design Certification Application RAI No. 412, FSAR Ch. 3, Supplement 4

Getachew, AREVA NP Inc. (AREVA NP) provided a schedule for a technically correct and complete response to RAI 412 on June 24, 2010. On August 27, 2010, AREVA NP submitted Supplement 1 to provide an INTERIM response to Question 03.07.02-73. AREVA NP submitted a revised schedule for Question 03.07.02-74 in Supplement 2 and Supplement 3 on September 15, 2010, and November 15, 2010, respectively.

Page 8: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

8

The schedule for Question 03.07.02-74 is being revised to allow additional time for AREVA NP to address NRC comments. The schedule for the remaining question is unchanged. The schedule for a technically correct and complete response to the remaining questions is provided below. Question # Interim Response Date Response Date RAI 412 — 03.07.02-73 August 29, 2010 (Actual) February 17, 2011 RAI 412 — 03.07.02-74 N/A March 23, 2011

Sincerely, Martin (Marty) C. Bryan U.S. EPR Design Certification Licensing Manager AREVA NP Inc. Tel: (434) 832-3016 702 561-3528 cell [email protected]

From: BRYAN Martin (External RS/NB) Sent: Monday, November 15, 2010 4:45 PM To: 'Tesfaye, Getachew' Cc: DELANO Karen (RS/NB); ROMINE Judy (RS/NB); BENNETT Kathy (RS/NB); CORNELL Veronica (External RS/NB); 'Miernicki, Michael' Subject: Response to U.S. EPR Design Certification Application RAI No. 412, FSAR Ch. 3, Supplement 3

Getachew, AREVA NP Inc. (AREVA NP) provided a schedule for a technically correct and complete response to RAI 412 on June 24, 2010. On August 27, 2010, AREVA NP submitted Supplement 1 to provide an INTERIM response to Question 03.07.02-73. AREVA NP submitted a revised schedule for Question 03.07.02-74 in Supplement 2 on September 15, 2010. The schedule for Question 03.07.02-74 is being revised to allow additional time for AREVA NP to address NRC comments. The schedule for the remaining question is unchanged. The schedule for a technically correct and complete response to the remaining questions is provided below. Question # Interim Response Date Response Date RAI 412 — 03.07.02-73 August 29, 2010 (Actual) February 17, 2011 RAI 412 — 03.07.02-74 N/A January 28, 2011

Sincerely, Martin (Marty) C. Bryan U.S. EPR Design Certification Licensing Manager AREVA NP Inc. Tel: (434) 832-3016 702 561-3528 cell [email protected]

Page 9: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

9

From: BRYAN Martin (External RS/NB) Sent: Wednesday, September 15, 2010 9:42 AM To: 'Tesfaye, Getachew' Cc: DELANO Karen (RS/NB); ROMINE Judy (RS/NB); BENNETT Kathy (RS/NB); CORNELL Veronica (External RS/NB) Subject: Response to U.S. EPR Design Certification Application RAI No. 412, FSAR Ch. 3, Supplement 2

Getachew, AREVA NP Inc. (AREVA NP) provided a schedule for a technically correct and complete response to RAI 412 on June 24, 2010. On August 27, 2010, AREVA NP submitted Supplement 1 to provide an INTERIM response to Question 03.07.02-73. The schedule for Question 03.07.02-74 is being revised to allow additional time for AREVA NP to interact with the NRC. The schedule for the remaining question is unchanged. The schedule for a technically correct and complete response to the remaining questions is provided below. Question # Interim Response Date Response Date RAI 412 — 03.07.02-73 August 29, 2010 (Actual) February 17, 2011 RAI 412 — 03.07.02-74 N/A December 13, 2010

Sincerely, Martin (Marty) C. Bryan U.S. EPR Design Certification Licensing Manager AREVA NP Inc. Tel: (434) 832-3016 702 561-3528 cell [email protected]

From: BRYAN Martin (External RS/NB) Sent: Friday, August 27, 2010 5:13 PM To: 'Tesfaye, Getachew' Cc: DELANO Karen (RS/NB); ROMINE Judy (RS/NB); BENNETT Kathy (RS/NB); CORNELL Veronica (External RS/NB) Subject: Response to U.S. EPR Design Certification Application RAI No. 412, FSAR Ch. 3, Supplement 1-INTERIM

Getachew, AREVA NP Inc. (AREVA NP) provided a schedule for a technically correct and complete response to RAI 412 on June 24, 2010. The attached file, “RAI 412 Supplement 1 Response US EPR DC - INTERIM.pdf” provides a technically correct and complete INTERIM response to 1 of the remaining 2 questions, as committed. The following table indicates the respective pages in the response document, “RAI 412 Supplement 1 Response US EPR DC- INTERIM.pdf,” that contain AREVA NP’s response to the subject questions. Question # Start Page End Page RAI 412 — 03.07.02-73 2 2

Page 10: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

10

The schedule for a technically correct and complete response to the remaining questions is provided below. Question # Interim Response Date Response Date

RAI 412 — 03.07.02-73 August 29, 2010 (Actual-

August 27, 2010) February 17, 2011

RAI 412 — 03.07.02-74 N/A September 20, 2010 Sincerely, Martin (Marty) C. Bryan U.S. EPR Design Certification Licensing Manager AREVA NP Inc. Tel: (434) 832-3016 702 561-3528 cell [email protected]

From: BRYAN Martin (EXT) Sent: Thursday, June 24, 2010 2:00 PM To: 'Tesfaye, Getachew' Cc: DELANO Karen V (AREVA NP INC); ROMINE Judy (AREVA NP INC); BENNETT Kathy A (OFR) (AREVA NP INC); VAN NOY Mark (EXT); CORNELL Veronica (EXT); RYAN Tom (AREVA NP INC); GARDNER George Darrell (AREVA NP INC) Subject: Response to U.S. EPR Design Certification Application RAI No. 412, FSAR Ch. 3

Getachew, Attached please find AREVA NP Inc.’s response to the subject request for additional information (RAI). The attached file, “RAI 412 Response US EPR DC.pdf” provides a schedule since a technically correct and complete response to the 2 questions is not provided. The following table indicates the respective pages in the response document, “RAI 412 Response US EPR DC.pdf” that contain AREVA NP’s response to the subject questions. Question # Start Page End Page RAI 412 — 03.07.02-73 2 2 RAI 412 — 03.07.02-74 3 3 A complete answer is not provided for 2 of the 2 questions. The dates provide are based upon the civil/structural re-planning activities and revised RAI response schedule presented to the NRC during the June 9, 2010, Public Meeting, and to allow time to interact with the NRC on the responses. Prior to submittal of the final RAI response, AREVA NP will provide an interim RAI response that includes:

(1) a description of the technical work (e.g., methodology) (2) U.S. EPR FSAR revised pages, as applicable

The schedule for a technically correct and complete response to these questions is provided below. Question # Interim Response Date Response Date RAI 412 — 03.07.02-73 August 29, 2010 February 17, 2011 RAI 412 — 03.07.02-74 N/A September 20, 2010

Page 11: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

11

Sincerely, Martin (Marty) C. Bryan U.S. EPR Design Certification Licensing Manager AREVA NP Inc. Tel: (434) 832-3016 702 561-3528 cell [email protected]

From: Tesfaye, Getachew [mailto:[email protected]] Sent: Friday, May 28, 2010 8:11 AM To: ZZ-DL-A-USEPR-DL Cc: Chakravorty, Manas; Hawkins, Kimberly; Miernicki, Michael; Patel, Jay; Colaccino, Joseph; ArevaEPRDCPEm ResourceSubject: U.S. EPR Design Certification Application RAI No. 412(4744), FSAR Ch. 3 Attached please find the subject requests for additional information (RAI). A draft of the RAI was provided to you on May 25, 2010, and on May 27, 2010, you informed us that the RAI is clear and no further clarification is needed. As a result, no change is made to the draft RAI. The schedule we have established for review of your application assumes technically correct and complete responses within 30 days of receipt of RAIs. For any RAIs that cannot be answered within 30 days, it is expected that a date for receipt of this information will be provided to the staff within the 30 day period so that the staff can assess how this information will impact the published schedule.

Thanks, Getachew Tesfaye Sr. Project Manager NRO/DNRL/NARP (301) 415-3361

Page 12: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

Hearing Identifier: AREVA_EPR_DC_RAIs Email Number: 4688 Mail Envelope Properties (8D35DF68A379A34E8526B758FDCFC04218A8CE) Subject: Response to U.S. EPR Design Certification Application RAI No. 412, FSAR Ch. 3, Supplement 12 Sent Date: 9/16/2013 5:50:13 PM Received Date: 9/16/2013 5:50:34 PM From: HOTTLE Nathan (AREVA) Created By: [email protected] Recipients: "Miernicki, Michael" <[email protected]> Tracking Status: None "RANSOM Jim (AREVA)" <[email protected]> Tracking Status: None "LEIGHLITER John (AREVA)" <[email protected]> Tracking Status: None "UYEDA Graydon (AREVA)" <[email protected]> Tracking Status: None "GUCWA Len (EXTERNAL AREVA)" <[email protected]> Tracking Status: None "RYAN Tom (AREVA)" <[email protected]> Tracking Status: None "DELANO Karen (AREVA)" <[email protected]> Tracking Status: None "ROMINE Judy (AREVA)" <[email protected]> Tracking Status: None "Snyder, Amy" <[email protected]> Tracking Status: None Post Office: FUSLYNCMX03.fdom.ad.corp Files Size Date & Time MESSAGE 26347 9/16/2013 5:50:34 PM RAI 412 Supplement 12 Response US EPR DC.pdf 901328 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: Recipients Received:

Page 13: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

Response to

Request for Additional Information No. 412 (4744), Revision 0, Supplement 12

5/28/2010

U.S. EPR Standard Design Certification AREVA NP Inc.

Docket No. 52-020 SRP Section: 03.07.02 - Seismic System Analysis

Application Section: 03.07.02

QUESTIONS for Structural Engineering Branch 2 (ESBWR/ABWR Projects) (SEB2)

Page 14: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

AREVA NP Inc. Advanced Response to Request for Additional Information No. 412, Supplement 12 U.S. EPR Design Certification Application Page 2 of 28 Question 03.07.02-74:

RAI from Audit 4/26-30, 2010

As part of the staff review of the SSI analysis of the Nuclear Island (NI) Common Basemat Structure, AREVA was asked to describe how seismic fluid-structure interaction was considered for those structures containing water in the NI (e.g., the IRWST, the spent fuel pool, etc.). AREVA stated that the entire mass of water is treated as a lumped mass which is added to the mass of the structure in which it is contained. In general the staff was satisfied with the method described but to ensure the analysis and design of the NI meets the requirements of GDC 2 for earthquake design and that the loads due to the seismic response of the water have been properly determined, the staff requests that AREVA provide the following information regarding fluid/structure interaction:

1. Describe how the contained water is modeled in the seismic analysis of the NI;

2. If convective loads are ignored, provide the basis for not considered them:

3. Justify the freeboard is sufficient to accommodate sloshing in the IRWST;

4. Provide the basis for water level assumptions when determining the effects of sloshing;

5. If they exist, describe the effect of sloshing loads; and,

6. Evaluate potential overspill in Spent Fuel Pool.

Provide the basis for not considering a seismic hydrodynamic impact load on the bottom of the spent fuel pool, the IRWST, or any other significant pool or tank in the NI, due to the response of the water from an earthquake acting in the vertical direction.

Response to Question 03.07.02-74:

The Response to RAI 412, Question 03.07.02-74 is being resubmitted in its entirety. This Response incorporates operating basis earthquake (OBE) structural damping for the generation of in-structure response spectra (ISRS) for the Nuclear Island (NI) as described in the Response to RAI 370, Question 03.07.01-27. This Response incorporates soil-structure interaction (SSI) analysis direct method results as described in the Response to RAI 320, Question 03.07.02-63.

1. Hydrodynamic loads are developed using the methodology provided in TID-7024 (Reference 1; see page 22 of this document), Chapter 6 and Appendix F for the NI pools shown in Table 03.07.02-74-1. Hydrodynamic loads for the Essential Service Water Building (ESWB) pool will be provided in the Response to RAI 335, Question 03.08.04-10.

Attachment 1 of this Response demonstrates the development of hydrodynamic loads, natural frequencies, and hydrodynamic forces on the pool walls and slab for the spent fuel pool (SFP).

As described in Reference 1, the total pressures on the walls are determined by combining impulsive and convective loadings. The impulsive loading is affected by the flexibility of the walls, but the convective loading is insensitive to flexibility of the pools. For the impulsive load, the zero period accelerations (ZPAs) of individual pool walls are used, which inherently consider the flexibility of the elements. More specifically, ZPAs at the mid-span and mid-height of the pool walls are determined from seismic analysis and applied (at a minimum -

Page 15: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

AREVA NP Inc. Advanced Response to Request for Additional Information No. 412, Supplement 12 U.S. EPR Design Certification Application Page 3 of 28

more conservative values were applied for some pools) to the entire pool wall for all pools except for the Emergency Feedwater 2/3 pools (LAR 2/3 pool). For this pool, the ZPAs at nodes along the middle two-thirds of the pool wall width at the mid-height of the pool were averaged and applied to the entire pool wall. For the convective load, the natural frequency of sloshing water is determined using Reference 1, Equation 6.8, and the corresponding acceleration is based on 0.5 percent damping (refer to Reference 1, Section 6.6). The ISRS at approximate pool wall mid-height elevation were used to determine the corresponding accelerations for the entire pool wall.

Figures 03.07.02-74-1 through 03.07.02-74-3 show the hydrodynamic forces in a pool resulting from a horizontal earthquake, and represented by a combination of the following:

− Impulsive (P0) and convective (P1) forces acting on the pool walls.

− Impulsive (Pb0) and convective (Pb1) forces acting on the pool slab.

For each pool, the impulsive and convective pressures are calculated for the horizontal (X and Y) direction in 3.28 feet (1 meter) depth increments (refer to Table 03.07.02-74-1). The singular acceleration value for each wall (described above) is used at each depth increment along the height. The total pressure is then obtained by adding the convective pressure to the impulsive pressure at each increment.

The hydrodynamic pressure on the slab and walls resulting from a vertical earthquake is calculated in accordance with ASCE 4-98, Equation 3.5-7, using the fluid mass density multiplied by the vertical ZPA as a function of water depth below the surface. The vertical ZPA of pool slabs is less than 1 g for six of the seven pool sets. The maximum enveloped vertical ZPA for the Emergency Feedwater LAR 2/3 Pool is 1.11 g; however, surface plots of the slab ZPA show that the average ZPA over the entire area is less than 1 g for all load cases. More specifically, only two load cases show vertical accelerations greater than 1 g at any location (approximately four percent of pool floor area is between 1 g and 1.11 g). Contour plots of these two cases are shown in Figure 03.07.02-74-4 and Figure 03.07.02-74-5. No water mass impact on the pool slab resulting from vertical seismic excitation is expected.

The design of the NI uses the dynamic model, superstructure static model, and basemat model. In the superstructure static finite element model (FEM), seismic loads are applied statically in six directions (east, west, north, south, up, and down), and the square root of the sum of the squares (SRSS) method is used for combining directional seismic loads as described in U.S. EPR FSAR Tier 2, Section 3.8.3.4.4. In each direction, a set of hydrodynamic pressure loads are simultaneously applied on the walls and slab. As shown on Figure 03.07.02-74-3, when the earthquake moves toward the east, the east wall is pushed outward, the west wall is pulled inward, the east half slab is pushed downward, and the west half slab is pulled upward. The application of hydrodynamic loads accounts for the rotational effects of water motion. For SFP rack loads, refer to the Response to RAI 335, Question 03.08.04-10. The hydrodynamic pressure methodology of the pools is also discussed in Response to RAI 335, Question 03.08.04-10.

For U.S. EPR pools, the water does not impact slabs in a vertical earthquake because the vertical ZPAs are less than 1 g (see explanation above). One-hundred percent water mass was used in the slab vertical pressure and wall horizontal pressure calculation (refer to Attachment 1 of this Response, Table 03.07.02-74-A13).

Page 16: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

AREVA NP Inc. Advanced Response to Request for Additional Information No. 412, Supplement 12 U.S. EPR Design Certification Application Page 4 of 28

The SSI time history model develops the ZPAs for the superstructure static model. In the dynamic model, fluid mass on the pool walls and slab is included based on tributary mass contribution. For example, one half of the water mass is added to each wall and total water mass is added to the slab. For the SFP, the total fuel/racks assembly mass is added to the slab in addition to the fluid total mass, conservatively neglecting racks occupying volume.

The basemat model develops loads on the basemat. The hydrodynamic mass applied to the basemat model is identical to the mass applied in the dynamic model. Table 03.07.02-74-4 provides the water weight, impulsive weight and force, convective weight and force, total hydrodynamic weight (impulsive plus convective), and other relevant parameters. The ratio between hydrodynamic weight and water weight is approximately equal to one. The water weight applied to the dynamic model is approximately the same as the calculated hydrodynamic weight based on Reference 1, except for surge pools. For the surge pools, the actual water level is less than the dynamic model in Table 03.07.02-74-4. The additional water weight of the surge pools in the dynamic model is approximately 0.07 percent of the total NI weight (concrete plus water), and is negligible.

There is no water in the reactor pool during operation. The reactor pool has no mass in the dynamic model and no loads in the superstructure static model. Detailed design of these walls includes the effects of static and hydrodynamic loads calculated using the methodology in Reference 1.

U.S. EPR FSAR Tier 2, Section 3.8.4 will be revised to clarify the hydrodynamic load analysis methodology.

2. Convective loads are included in the hydrodynamic loads for the static FEM, as described in the Response to Item 1. Figure 03.07.02-74-1 and Figure 03.07.02-74-2 show the total hydrodynamic wall pressure distributions for SFP, including impulsive and convective pressures. The contribution from convective mode to the total hydrodynamic load is negligible for the SFP and other NI pools, except for smaller or shallow pools such as the surge pool and in-containment refueling water storage tank (IRWST). Table 03.07.02-74-1 shows the wall frequencies and pressures for NI pools.

3. See the Response to Item 4.

4. The freeboard values (d0) are determined using the analyzed water levels in Table 03.07.02-74-3. The maximum water levels in the pools are checked against the analyzed water levels, and the difference is negligible as shown in Table 03.07.02-74-3.

5. Sloshing height (dmax) is calculated in accordance with Reference 1, Equation 6.11, and compared to the available freeboard (d0) for each pool to determine if water spillage in an open pool or ceiling impact in a covered pool occurs. The enveloped 0.5 percent damping ISRS for the entire building were used to calculate the sloshing height and hydrodynamic wall pressures of the specific pools. These wall pressures are applied to the superstructure static model for critical section design. The sloshing analysis results in Table 03.07.02-74-2 show that no spillage in open pools and no ceiling impact in covered pools occur.

6. See the Response to Item 1.

Page 17: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

AREVA NP Inc. Advanced Response to Request for Additional Information No. 412, Supplement 12 U.S. EPR Design Certification Application Page 5 of 28 FSAR Impact:

U.S. EPR FSAR Tier 2, Section 3.8.4.4.1 will be revised as described in the response and indicated on the enclosed markup.

Page 18: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

AREVA NP Inc. Advanced Response to Request for Additional Information No. 412, Supplement 12 U.S. EPR Design Certification Application Page 6 of 28

Table 03.07.02-74-1—Wall Frequencies and Hydrodynamic Average Pressures

Nuclear Island Pools

Pool Size Bottom Elevation2

Hydrodynamic Mode

Wall Frequency

(Hz)

Average Wall

Pressure (psf)

Lx (ft)

Ly (ft)

h1 (ft) X Y X Y

Spent Fuel Pool (Open) 51.67 29.36 45.60 +16’-9”

Impulsive ZPA ZPA 1053 765 Convective 0.22 0.3 25 14

Emergency Feedwater

Pool 2 and 3 (Enclosed)

21.33 27.23 26.90 -14’-9” Impulsive ZPA ZPA 239 341

Convective 0.35 0.31 20 25

Emergency Feedwater

Pool 1 and 4 (Enclosed)

28.21 22.97 26.90 -14’-9” Impulsive ZPA ZPA 934 330

Convective 0.30 0.34 20 18 Surge Pool 2

and 3 (Enclosed)

8.2 11.48 10.09 +68’-11” Impulsive ZPA ZPA 348 402

Convective 0.56 0.47 19 32 Surge Pool

1 and 4 (Enclosed)

10.5 13.12 6.89 +68’-11” Impulsive ZPA ZPA 173 185

Convective 0.49 0.43 29 48 In-containment

Refueling Water Storage

Pool (Enclosed)

35.43 82.68 12.37 -20’-7 ½ “ Impulsive ZPA ZPA 171 171

Convective 0.24 0.24 41 41

Reactor Pool (Open) 23.29 76.44 41.67 +20’-9“

Impulsive ZPA ZPA 467 797

Convective 0.33 0.18 11 45

Notes:

1. Normal water height.

2. Bottom of foundation for Safeguards Buildings is -41’-5” and Reactor Building is -35’-6”.

Page 19: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

AREVA NP Inc. Advanced Response to Request for Additional Information No. 412, Supplement 12 U.S. EPR Design Certification Application Page 7 of 28

Table 03.07.02-74-2—Sloshing Height Based on Updated Accelerations

Nuclear Island Pools Direction

Convective Acceleration

Sa (g)

Sloshing Height dmax (ft)

Free-board do (ft)

If dmax > do, Overspill or Ceiling

Impact? Spent Fuel Pool

(Open) X 0.05 1.17 1.64 No Overspill Y 0.09 1.28

Emergency Feedwater Pool 2

and 3 (Enclosed)

X 0.14 1.60 1.64 No Ceiling Impact

Y 0.11 1.51

Emergency Feedwater Pool 1

and 4 (Enclosed)

X 0.08 1.08 1.64 No Ceiling Impact

Y 0.11 1.27

Surge Pool 2 and 3

(Enclosed)

X 0.35 2.67 8.29 No Ceiling Impact

Y 0.30 2.71 Surge Pool 1 and

4 (Enclosed)

X 0.23 1.55 3.60 No Ceiling Impact

Y 0.25 2.16

In-containment Refueling Water

Storage Pool (Enclosed)

X 0.06 0.96 6.17 No Ceiling Impact

Y 0.06 2.16

Reactor Pool (Open)

X 0.10 1.15 1.64 No Overspill Y 0.0375 1.26

Page 20: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

AREVA NP Inc. Advanced Response to Request for Additional Information No. 412, Supplement 12 U.S. EPR Design Certification Application Page 8 of 28

Table 03.07.02-74-3—Normal and Maximum Water Level of Pools

Nuclear Island Pools

Analyzed Water Level (ft)

Max. Water Level (ft)

Difference (ft)

Water Depth (ft)

Spent Fuel Pool (Open) 62.34 62.66 0.33 45.6

Reactor Pool (Open) 62.34 62.66 0.33 41.7

In-containment Refueling Water

Storage Pool (Enclosed)

-7.81 -7.71 0.10 12.4

Emergency Feedwater Pool

2 and 31

(Enclosed)

26.90 26.90 0.00 26.9

Emergency Feedwater Pool

1 and 41 (Enclosed)

26.90 26.90 0.00 26.9

Surge Pool 2 and 32

(Enclosed) 78.97 78.97 0.00 10.1

Surge Pool 1 and 42

(Enclosed) 75.79 75.79 0.00 6.9

Notes:

1. For emergency feedwater pools, the maximum water level at overflow pipe elevation was conservatively used to calculate the pool loads.

2. Maximum required surge volume for surge tanks is 925 ft3. The water level analyzed is based on a volume of 950 ft3 (normal and maximum water levels).

Page 21: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

AR

EV

A N

P In

c.

Adv

ance

d R

espo

nse

to R

eque

st fo

r Add

ition

al In

form

atio

n N

o. 4

12, S

uppl

emen

t 12

U.S

. EP

R D

esig

n C

ertif

icat

ion

App

licat

ion

P

age

9 of

28

Ta

ble

03.0

7.02

-74-

4—Se

ism

ic L

oad

Com

paris

ons

for N

ucle

ar Is

land

Poo

ls

Nuc

lear

Isla

nd P

ools

1

W

(kip

s)2

Impu

lsiv

e M

ode

Con

vect

ive

Mod

e

W0+

W1 (k

ips)

7 (W

0+W

1) /W

8SA

SSI

Wei

ght/W

0+W

19W

1/W010

P 1/P

011W

0 (k

ips)

3P 0

(kip

s)4

W1

(kip

s)5

P 1

(kip

s)6

X-D

irect

ion

Seis

mic

S

pent

Fue

l Poo

l 44

48

3416

28

69

1318

66

47

34

1.06

0.

97

0.39

0.

02

Em

erge

ncy

Feed

wat

er P

ool 2

&3

1005

87

2 36

6 21

0 29

10

81

1.08

0.

99

0.24

0.

08

Em

erge

ncy

Feed

wat

er P

ool 1

&4

1121

88

9 11

91

308

25

1197

1.

07

0.99

0.

35

0.02

S

urge

Poo

l 2&

3 61

53

83

13

5

66

1.08

1.

36

0.25

0.

06

Sur

ge P

ool 1

&4

61

40

30

24

5 64

1.

05

1.46

0.

59

0.18

IR

WS

T 23

30

926

343

1410

85

23

36

1.00

1.

06

1.52

0.

25

Rea

ctor

Poo

l 47

70

4429

31

45

702

70

5132

1.

08

0.00

0.

16

0.02

To

tal

10

625

8027

39

85

285

1461

0

Y

Dire

ctio

n Se

ism

ic

Spe

nt F

uel P

ool

4448

40

38

3796

75

5 68

47

93

1.08

0.

96

0.19

0.

02

Em

erge

ncy

Feed

wat

er P

ool 2

&3

1005

80

8 40

4 26

7 29

10

75

1.07

0.

99

0.33

0.

07

Em

erge

ncy

Feed

wat

er P

ool 1

&4

1121

95

3 52

4 25

2 28

12

05

1.08

0.

99

0.26

0.

05

Sur

ge P

ool 2

&3

61

47

66

18

5 65

1.

06

1.37

0.

39

0.08

S

urge

Poo

l 1&

4 61

34

26

28

7

63

1.03

1.

48

0.83

0.

27

IRW

ST

2330

40

3 14

9 18

07

108

2210

0.

95

1.12

4.

49

0.73

R

eact

or P

ool

4770

27

62

1547

21

63

87

4925

1.

03

0.00

0.

78

0.06

To

tal

90

45

6512

52

90

332

1433

6

Not

es:

Col

umn

1 N

ucle

ar Is

land

poo

ls.

Col

umn

2:

Act

ual w

ater

wei

ght.

Page 22: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

AR

EV

A N

P In

c.

Adv

ance

d R

espo

nse

to R

eque

st fo

r Add

ition

al In

form

atio

n N

o. 4

12, S

uppl

emen

t 12

U.S

. EP

R D

esig

n C

ertif

icat

ion

App

licat

ion

P

age

10 o

f 28

Col

umn

3:

Impu

lsiv

e w

eigh

t, W

o (R

efer

ence

1, E

quat

ion

6.1)

.

Col

umn

4:

Impu

lsiv

e fo

rce,

Po (

Ref

eren

ce 1

, Equ

atio

n 6.

4).

Col

umn

5:

Con

vect

ive

wei

ght,

W1 (

Ref

eren

ce 1

, Equ

atio

n 6.

5).

Col

umn

6:

Con

vect

ive

forc

e, P

1 (R

efer

ence

1, E

quat

ion

6.8-

6.10

). S

ee T

able

03.

07.0

2-74

-2 fo

r the

ass

ocia

ted

conv

ectiv

e ac

cele

ratio

n va

lues

.

Col

umn

7:

Hyd

rody

nam

ic W

eigh

t = Im

puls

ive

Wei

ght +

Con

vect

ive

Wei

ght.

Col

umn

8:

Sta

tic W

eigh

t Rat

io =

Hyd

rody

nam

ic W

eigh

t / A

ctua

l Poo

l Wat

er w

eigh

t.

Col

umn

9:

Dyn

amic

Wei

ght R

atio

= W

eigh

t in

Sys

tem

for A

naly

sis

of S

oil S

truct

ure

Inte

ract

ion

(SA

SS

I) M

odel

/ H

ydro

dyna

mic

W

eigh

t (no

wat

er in

RP

dur

ing

oper

atio

n).

Col

umn

10:

Con

vect

ive

Mas

s R

atio

= C

onve

ctiv

e W

eigh

t / Im

puls

ive

Wei

ght.

Col

umn

11:

Con

vect

ive

Load

Rat

io =

Con

vect

ive

Load

/ Im

puls

ive

Load

.

Page 23: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

AREVA NP Inc. Advanced Response to Request for Additional Information No. 412, Supplement 12 U.S. EPR Design Certification Application Page 11 of 28

Figure 03.07.02-74-1—SFP Impulsive and Convective Wall Pressure Distributions in the X Direction

Page 24: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

AREVA NP Inc. Advanced Response to Request for Additional Information No. 412, Supplement 12 U.S. EPR Design Certification Application Page 12 of 28

Figure 03.07.02-74-2—SFP Impulsive and Convective Wall Pressure Distributions in the Y direction

Page 25: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

AREVA NP Inc. Advanced Response to Request for Additional Information No. 412, Supplement 12 U.S. EPR Design Certification Application Page 13 of 28

Figure 03.07.02-74-3—Hydrodynamic Pressure in Pool due to Horizontal Acceleration

Page 26: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

AREVA NP Inc. Advanced Response to Request for Additional Information No. 412, Supplement 12 U.S. EPR Design Certification Application Page 14 of 28

Figure 03.07.02-74-4—Detailed LAR Pool ZPAz for Soil Case 1n5ah

Page 27: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

AREVA NP Inc. Advanced Response to Request for Additional Information No. 412, Supplement 12 U.S. EPR Design Certification Application Page 15 of 28

Figure 03.07.02-74-5—Detailed LAR Pool ZPAz for Soil Case 5ah

Page 28: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

AREVA NP Inc. Advanced Response to Request for Additional Information No. 412, Supplement 12 U.S. EPR Design Certification Application Page 16 of 28

Attachment 1: Spent Fuel Pool Example

Accelerations (aX, aY, and aZ) for the impulsive mode are based on the ISRS ZPA values specific to the SFP walls/slabs. Accelerations for the convective mode and sloshing height calculations are based on natural frequencies, as discussed in Item 5 of this Response, which used localized 0.5 percent damping ISRS.

The accelerations from the enveloped Fuel Building (FB) ISRS described in this Response were used in calculating the hydrodynamic loads in this Attachment, and applied to the superstructure static model used for design of critical sections.

1.0 Hydrodynamic Load in Spent Fuel Pool

According to Reference 1, the horizontal acceleration of fluid in a tank or pool generates hydrodynamic forces acting outward on one side of the pool and inward on the other side. The seismically-induced fluid motion developed in a pool is represented by a combination of impulsive force, P0, and convective force, P1, acting on the pool walls and the combination of impulsive force, Pb0, and convective force, Pb1, acting on the pool slab, as shown on Figure 03.07.02-74-3.

In order to use Reference 1, Equation 6.4 or Equation F.47 to obtain impulsive pressures on pool walls and slab, the corresponding ZPA of the pools must be obtained.

The hydrodynamic pressure on the pool walls and slab resulting from vertical seismic acceleration (aZ) is calculated using a similar formula to that used for hydrostatic calculation as follows:

Pz = ρwater aZ d

1.1 Seismic Accelerations of Spent Fuel Pool Structure

East or West Wall

According to Reference 1, impulsive force, P0, is created by a certain portion of the fluid, of weight W0, acting as if it were rigidly connected to the walls.

Using ISRS for elevation +14.80m (near the mid-height of pool water), the maximum ZPA in the X direction is as follows:

aX = 0.84g

North or South Wall

Using ISRS for elevation +14.80m (near the mid-height of pool water), the maximum ZPA in the Y direction is as follows:

aY = 0.94g

Page 29: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

AREVA NP Inc. Advanced Response to Request for Additional Information No. 412, Supplement 12 U.S. EPR Design Certification Application Page 17 of 28 Pool Slab

The flexibility of the pool slab is considered in generating vertical response spectra. The ZPA for the pool slab at elevation +4.2m in the Z direction obtained from the ISRS is as follows:

aZ = 0.45g

1.2 Hydrodynamic Pressure of Spent Fuel Pool due to Seismic Load in X Direction

East or West Wall

As shown in Section 6.5 of Reference 1 for slender tanks with h > 1.5l, the impulsive pressures, P0, has to be further divided into two zones. The upper portion of water with a depth of 1.5l is considered to be in fluid motion and Equation F.47 of Reference 1 can be used to find impulsive pressures, P0, as a function of water depth below the surface (d), as follows:

���

���

��

���

���

���−=

hl

hd

hdhuP 3tanh3

21 2

00 �ρ for d = 0 to 1.5l

where 0u� = aX = 0.84g, l = 15.75/2 = 7.875m = 25.84 ft, and h = 1.5l = 11.81m (rounded to 12m)

The lower portion of water (below 12m) tends to respond as a completely constrained fluid (refer to Reference 1), and the impulsive pressure is calculated using the following equation:

luP 00 �ρ=

Based on these equations, the impulsive pressures at 3.28 ft increments along the height of wall are calculated and shown in Table 03.07.02-74-A1.

Convective force, P1, is created by a certain portion of the fluid moving as if it were a solid oscillating mass flexibly connected to the walls with a maximum sloshing height of dmax, as shown on Figure 03.07.02-74-3. The natural frequency of sloshing fluid can be found by Equation 6.8 or Equation F.57 of Reference 1 as follows:

95.158.1tanh58.12 =���

���=

lh

lgω

Hzf 22.02

==π

ω

where g = 32.2 ft/sec2, l = 25.84 ft, and h = 45.6 ft.

The maximum acceleration in X direction for 0.5 percent damping ratio at 0.22 Hz obtained from the ISRS for elevation +14.8m is as follows:

Sa1 = 0.05g

Page 30: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

AREVA NP Inc. Advanced Response to Request for Additional Information No. 412, Supplement 12 U.S. EPR Design Certification Application Page 18 of 28 This acceleration can be used to determine �h as follows:

A1 = Sa1/ω2= (0.05)(32.2)/1.95 = 0.824 ft Equation 5.4 or F.65 of Reference 1.

���

���=

lh

lA

h58.1tanh58.1 1θ = 0.05 rad. Equation 6.9 or F.70 of Reference 1.

The maximum sloshing height, dmax, of water surface can be estimated by Equation 6.11 or F.78b of Reference 1 as follows:

���

������

����

�−

=

lh

lg

ld

h

58.1tanh1

527.0

2

max

θω

= 1.17 ft < d0 = 1.64 ft

No overspill is identified.

To determine convective pressures, P1, at X= −l or X= +l, as a function of water height above the pool bottom, (h-d), Equation F.62 of Reference 1 is used. For determining the maximum value of P1, the term of (sinωt) is set equal to 1 and, consequently, removed from the equation as follows:

( )h

lh

ldh

lP θωρ 22

1 58.1sinh

58.1cosh

25

3

=

Based on the P1 equation, the convective pressures at 3.28 ft increments along the height of wall are calculated and shown in Table 03.07.02-74-A2.

Table 03.07.02-74-A3 shows the total hydrodynamic pressures on the east or west wall, which are obtained by adding the results from Table 03.07.02-74-A1 and Table 03.07.02-74-A2.

Pool Slab

The pressure on the pool bottom (Pb0) produced by the impulsive force (P0) in X direction can be obtained using Equation F.48 of Reference 1, expressed as a function of distance from the centerline of the pool (X) as follows:

hl

hX

huPb 3cosh

3sinh

23

00 �ρ=

where 0u� = aX = 0.84g, l = 7.875m = 25.84 ft, and h = 13.9m = 45.6 ft.

Page 31: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

AREVA NP Inc. Advanced Response to Request for Additional Information No. 412, Supplement 12 U.S. EPR Design Certification Application Page 19 of 28 Based on the Pb0 equation, the impulsive pressures at 3.28 ft increments from the centerline of the pool bottom are calculated and shown in Table 03.07.02-74-A4.

The pressure on the pool bottom (Pb1) produced by the convective force (P1) in X direction can be obtained using Equation F.74 of Reference 1, expressed as a function of distance from the centerline of the pool (X) as follows:

lh

tlX

lXlP hb

25sinh

sin31

25

21 3

221

ωθωρ��

���

���

���−=

where ���

���=

lh

lA

h58.1tanh58.1 1θ Equation 6.9 of Reference 1.

A1 = Sa1/ω2 Equation 5.4 or F.65 of Reference 1.

By setting the term (sinωt) to 1, substituting θh, and A1, Equation F.74 of Reference 1 for Pb1 can be rewritten as the following:

lh

lS

lX

lXlP

a

b 58.1cosh

58.1

31

25

21

132

1��

���

���

���−= ρ

where Sa1 = 0.05g.

Based on the Pb1 equation, the convective pressures at 3.28 ft increments from the centerline of the pool bottom are calculated and shown in Table 03.07.02-74-A5.

Table 03.07.02-74-A6 shows the total vertical pressure on the pool slab resulting from impulsive and convective pressures in the X direction, which is obtained by adding the results from Table 03.07.02-74-A4 and Table 03.07.02-74-A5.

1.3 Hydrodynamic Pressure of Spent Fuel Pool due to Seismic Load in Y Direction

North or South Wall

As described in Section 6.5 of Reference 1 for slender tanks with h > 1.5l, the impulsive pressures, P0, has to be further divided into two zones. The upper portion of water with a depth of 1.5l is considered to be in fluid motion, and Equation F.47 of Reference 1 can be used to find impulsive pressures, P0, as a function of water depth below the surface (d) as follows:

���

���

��

���

���

���−=

hl

hd

hdhuP 3tanh3

21 2

00 �ρ for d = 0 to 1.5l

Page 32: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

AREVA NP Inc. Advanced Response to Request for Additional Information No. 412, Supplement 12 U.S. EPR Design Certification Application Page 20 of 28

where 0u� = ay = 0.94g, l = 4.475m = 14.68 ft, and h = 1.5l = 6.7m (rounded to 7m).

The lower portion of water (below 7m) tends to respond as a completely constrained fluid (refer to Reference 1), and the impulsive pressure is calculated using the following equation:

luP 00 �ρ=

The calculated impulsive pressure at 3.28 ft increments along the height of the wall are shown in Table 03.07.02-74-A7.

For convective pressure calculation, the natural frequency of sloshing fluid can be found by Equation 6.8 or Equation F.57 of Reference 1 as follows:

47.358.1tanh58.12 =���

���=

lh

lgω

Hzf 30.02

==π

ω

where g = 32.2 ft/sec2, l = 14.68 ft, and h = 45.6 ft.

The maximum acceleration in Y direction for 0.5 percent damping ratio at 0.30 Hz obtained from the ISRS for elevation +14.8m is as follows:

Sa1 = 0.09g

where ���

���=

lh

lA

h58.1tanh58.1 1θ = 0.09 Equation 6.9 or F.70 of Reference 1.

A1 = Sa1/ω2= (0.09)(32.2)/3.47 = 0.836 ft Equation 5.4 or F.65 of Reference 1.

The maximum sloshing height, dmax, of the water surface can be estimated by Equation 6.11 or F.78b of Reference 1 as follows:

���

������

����

�−

=

lh

lg

ld

h

58.1tanh1

527.0

2

max

θω

= 1.28 ft < d0 = 1.64 ft

There is no overspill identified.

Convective pressures at 3.28 ft increments along the height of wall are calculated using the following equation, and the results are shown in Table 03.07.02-74-A8:

Page 33: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

AREVA NP Inc. Advanced Response to Request for Additional Information No. 412, Supplement 12 U.S. EPR Design Certification Application Page 21 of 28

( )h

lh

ldh

lP θωρ 22

1 58.1sinh

58.1cosh

25

3

=

Table 03.07.02-74-A9 shows the total hydrodynamic pressures on the south or north wall, which are obtained by combining the results from Table 03.07.02-74-A7 and Table 03.07.02-74-A8.

Pool Slab

The pressure on the pool bottom (Pb0) produced by the impulsive forces in Y direction can be obtained using Equation F.48 of Reference 1, expressed as a function of distance from the centerline of the pool (Y) as follows:

hl

hY

huPb 3cosh

3sinh

23

00 �ρ=

where 0u� = aY = 0.94g, l = 4.475m = 14.68 ft, and h = 13.9m = 45.6 ft.

Based on the Pb0 equation, the impulsive pressures at 3.28 ft increments from the centerline of the pool bottom are calculated and shown in Table 03.07.02-74-A10.

Convective pressures at 3.28 ft increments from the centerline of the pool bottom are calculated using the equation below and the results are shown in Table 03.07.02-74-A11.

lh

lS

lY

lYlP

a

b 58.1cosh

58.1

31

25

21

132

1��

���

���

���−= ρ

where Sa1 = 0.09g.

Table 03.07.02-74-A12 shows the total vertical pressure on the pool slab resulting from impulsive and convective pressures in the Y direction, which is obtained by combining the results from Table 03.07.02-74-A10 and Table 03.07.02-74-A11.

1.4 Hydrodynamic Pressure of Spent Fuel Pool due to Seismic Load in the Z Direction

The hydrodynamic pressure because of the seismic load in the Z direction is calculated using the following formula, and the results are shown in Table 03.07.02-74-A13.

Pz = ρ aZ d

where aZ = 0.45g, and d = depth of fluid.

Page 34: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

AREVA NP Inc. Advanced Response to Request for Additional Information No. 412, Supplement 12 U.S. EPR Design Certification Application Page 22 of 28 2.0 Loading Pit and Transfer Pit

The loading pit and transfer pit are two small areas adjacent to the SFP and are separated from the SFP with access hatches. When the hatches are open, the loading pit and transfer pit become part of SFP. Instead of developing separate sets of loads for these two small pit areas, it is conservative to apply the loads developed for the larger SFP to the two smaller pool areas.

For walls:

The floors of the loading pit and transfer pit are located at Elevations +31.8 ft and +19.5 ft, respectively, which are higher than the floor of the SFP at Elevation +16.7 ft. The hydrostatic and hydrodynamic water pressures on the walls for SFPs is used for the loading pit and transfer pit up to water depths as follows:

Water Height of Loading Pit, h1 = 30.5 ft.

Water Height of Transfer Pit, h2 = 42.8 ft.

For slabs:

The SFP hydrostatic pressure and hydrodynamic pressure resulting from seismic loading in the Z direction near water depths, h1 and h2, are used for the loading pit and transfer pit slabs.

Because the loading pit and transfer pit are located in the SFP corners, maximum values of hydrodynamic pressures resulting from seismic loading in horizontal directions at the SFP slab corner near water depths, h1 and h2, are conservatively used for the loading pit and transfer pit slabs.

References:

1. TID-7024, “Nuclear Reactors and Earthquakes,” United States Atomic Energy Commission, 1963

Page 35: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

AREVA NP Inc. Advanced Response to Request for Additional Information No. 412, Supplement 12 U.S. EPR Design Certification Application Page 23 of 28

Table 03.07.02-74-A1—Impulsive Pressure on East or West Wall of Spent Fuel Pool in the X Direction

Depth (ft) d P0 from to (ft) (psf) 0.00 3.28 1.64 122 3.28 6.56 4.92 351 6.56 9.84 8.20 559 9.84 13.12 11.48 746

13.12 16.40 14.76 913 16.40 19.68 18.04 1058 19.68 22.97 21.33 1183 22.97 26.25 24.61 1287 26.25 29.53 27.89 1370 29.53 32.81 31.17 1433 32.81 36.09 34.45 1474 36.09 39.37 37.73 1495 39.37 42.65 41.01 1395 42.65 45.60 44.13 1395

Table 03.07.02-74-A2—Convective Pressure on East or West Wall of Spent

Fuel Pool in the X Direction

Depth (ft) d P1 from to (ft) (psf) 0.00 3.28 1.64 63 3.28 6.56 4.92 51 6.56 9.84 8.20 42 9.84 13.12 11.48 35

13.12 16.40 14.76 29 16.40 19.68 18.04 24 19.68 22.97 21.33 20 22.97 26.25 24.61 16 26.25 29.53 27.89 14 29.53 32.81 31.17 12 32.81 36.09 34.45 11 36.09 39.37 37.73 9 39.37 42.65 41.01 9 42.65 45.60 44.13 9

Page 36: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

AREVA NP Inc. Advanced Response to Request for Additional Information No. 412, Supplement 12 U.S. EPR Design Certification Application Page 24 of 28

Table 03.07.02-74-A3—Total Hydrodynamic Pressure on East or West Wall of Spent Fuel Pool in the X Direction

Depth (ft) d Pwx from to (ft) (psf) 0.00 3.28 1.64 185 3.28 6.56 4.92 402 6.56 9.84 8.20 601 9.84 13.12 11.48 781

13.12 16.40 14.76 941 16.40 19.68 18.04 1082 19.68 22.97 21.33 1203 22.97 26.25 24.61 1304 26.25 29.53 27.89 1384 29.53 32.81 31.17 1445 32.81 36.09 34.45 1485 36.09 39.37 37.73 1505 39.37 42.65 41.01 1404 42.65 45.60 44.13 1404

Table 03.07.02-74-A4—Vertical Pressure on Spent Fuel Pool Slab due to

Impulsive Force in the X Direction

Distance (ft) X Pb0 from to (ft) (psf) 0.00 3.28 1.64 87 3.28 6.56 4.92 264 6.56 9.84 8.20 444 9.84 13.12 11.48 631

13.12 16.40 14.76 828 16.40 19.68 18.04 1038 19.68 22.97 21.33 1264 22.97 25.84 24.40 1494

Page 37: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

AREVA NP Inc. Advanced Response to Request for Additional Information No. 412, Supplement 12 U.S. EPR Design Certification Application Page 25 of 28

Table 03.07.02-74-A5—Vertical Pressure on Spent Fuel Pool Slab due to Convective Force in the X Direction

Distance (ft) X Pb1 from to (ft) (psf) 0.00 3.28 1.64 1 3.28 6.56 4.92 2 6.56 9.84 8.20 4 9.84 13.12 11.48 5

13.12 16.40 14.76 6 16.40 19.68 18.04 7 19.68 22.97 21.33 8 22.97 25.84 24.40 8

Table 03.07.02-74-A6—Vertical Pressure on Pool Slab due to Hydrodynamic

Force in the X Direction

Distance (ft) X Psx from to (ft) (psf) 0.00 3.28 1.64 88 3.28 6.56 4.92 266 6.56 9.84 8.20 448 9.84 13.12 11.48 636

13.12 16.40 14.76 835 16.40 19.68 18.04 1045 19.68 22.97 21.33 1272 22.97 25.84 24.40 1502

Page 38: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

AREVA NP Inc. Advanced Response to Request for Additional Information No. 412, Supplement 12 U.S. EPR Design Certification Application Page 26 of 28

Table 03.07.02-74-A7—Impulsive Pressure on North or South Wall of Spent Fuel Pool in the Y Direction

Depth (ft) d P0 from to (ft) (psf) 0.00 3.28 1.64 133 3.28 6.56 4.92 369 6.56 9.84 8.20 566 9.84 13.12 11.48 724

13.12 16.40 14.76 842 16.40 19.68 18.04 921 19.68 22.97 21.33 960 22.97 26.25 24.61 887 26.25 29.53 27.89 887 29.53 32.81 31.17 887 32.81 36.09 34.45 887 36.09 39.37 37.73 887 39.37 42.65 41.01 887 42.65 45.60 44.13 887

Table 03.07.02-74-A8—Convective Pressure on North or South Wall of

Spent Fuel Pool in the Y Direction

Depth (ft) d P1 from to (ft) (psf) 0.00 3.28 1.64 59 3.28 6.56 4.92 42 6.56 9.84 8.20 29 9.84 13.12 11.48 21

13.12 16.40 14.76 14 16.40 19.68 18.04 10 19.68 22.97 21.33 7 22.97 26.25 24.61 5 26.25 29.53 27.89 4 29.53 32.81 31.17 3 32.81 36.09 34.45 2 36.09 39.37 37.73 1 39.37 42.65 41.01 1 42.65 45.60 44.13 1

Page 39: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

AREVA NP Inc. Advanced Response to Request for Additional Information No. 412, Supplement 12 U.S. EPR Design Certification Application Page 27 of 28

Table 03.07.02-74-A9—Total Hydrodynamic Pressure on North or South Wall of Spent Fuel Pool in the Y Direction

Depth (ft) d Pwy from to (ft) (psf) 0.00 3.28 1.64 192 3.28 6.56 4.92 411 6.56 9.84 8.20 596 9.84 13.12 11.48 745

13.12 16.40 14.76 857 16.40 19.68 18.04 931 19.68 22.97 21.33 968 22.97 26.25 24.61 892 26.25 29.53 27.89 891 29.53 32.81 31.17 890 32.81 36.09 34.45 889 36.09 39.37 37.73 889 39.37 42.65 41.01 889 42.65 45.60 44.13 888

Table 03.07.02-74-A10—Vertical Pressure on Spent Fuel Pool Slab due to Impulsive Force in the Y Direction

Distance (ft) Y Pb0 from to (ft) (psf) 0.00 3.28 1.64 128 3.28 6.56 4.92 387 6.56 9.84 8.20 652 9.84 13.12 11.48 927

13.12 14.68 13.90 1138

Table 03.07.02-74-A11—Vertical Pressure on Spent Fuel Pool Slab due to

Convective Force in the Y Direction

Distance (ft) Y Pb1 from to (ft) (psf) 0.00 3.28 1.64 0 3.28 6.56 4.92 1 6.56 9.84 8.20 1 9.84 13.12 11.48 1

13.12 14.68 13.90 1

Page 40: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

AREVA NP Inc. Advanced Response to Request for Additional Information No. 412, Supplement 12 U.S. EPR Design Certification Application Page 28 of 28

Table 03.07.02-74-A12—Total Vertical Pressure on Spent Fuel Pool Slab due to Hydrodynamic Force in the Y Direction

Distance (ft) Y Psy from to (ft) (psf) 0.00 3.28 1.64 129 3.28 6.56 4.92 388 6.56 9.84 8.20 653 9.84 13.12 11.48 928

13.12 14.68 13.90 1139

Table 03.07.02-74-A13—Hydrodynamic Pressure on Walls and Slab of

Spent Fuel Pool due to Seismic Load in the Z Direction

Depth (ft) d Pz from to (ft) (psf) 0.00 3.28 1.64 47 3.28 6.56 4.92 142 6.56 9.84 8.20 237 9.84 13.12 11.48 332

13.12 16.40 14.76 427 16.40 19.68 18.04 522 19.68 22.97 21.33 617 22.97 26.25 24.61 712 26.25 29.53 27.89 807 29.53 32.81 31.17 902 32.81 36.09 34.45 997 36.09 39.37 37.73 1092 39.37 42.65 41.01 1187 42.65 45.60 44.13 1277 Slab 45.60 1320

Page 41: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

U.S. EPR Final Safety Analysis Report Markups

Page 42: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

U.S. EPR FINAL SAFETY ANALYSIS REPORT

Tier 2 Revision 6—Interim Page 3.8-115

[Seismic Category I concrete structural elements and their connections are detailed for ductility in accordance with ACI 349-2001, Chapter 21.]*

Structural Stiffness Considerations

Conservative values of concrete creep and shrinkage are used in the design of other Seismic Category I structures. Moments, forces, and shears are obtained on the basis of uncracked section properties in the analysis. However, in sizing the reinforcing steel required, the concrete is not relied upon for resisting tension. Thermal moments are modified by cracked-section analysis using analytical techniques, when the state of loading indicates the development of cracks.

The effect of local wall and floor slab flexibility is included where the analysis indicates the existence of this condition. The concrete section properties used in calculating the amplified seismic forces include an appropriate level cracking for the particular element under consideration. The amplified forces are also used in the design of the structural members that support the flexible element.

Section 3.8.4.6 describes methods used to confirm that concrete properties satisfy design requirements.

Seismic Structural Damping

Seismic analysis of other Seismic Category I structures uses the following SSE structural damping values as recommended by RG 1.61.

Structure Type Percent of Critical Damping

� Welded Steel 4

� Bolted Steel, Slip Critical Connections 4

� Bolted Steel, Bearing Connections 7

� Reinforced Concrete 7

Hydrodynamic Loads

Hydrodynamic loads are applied to the walls and floors of the spent fuel pool and liquid storage tanks in the SBs and in the ESWBs to account for the impulsive and convective effects of the water moving and sloshing in the tanks as a result of seismic excitation. These loads are considered as part of the seismic SSE loads, and components of these loads in the three orthogonal directions are combined in the same manner as other seismic loads. The requirements of ASCE Manual No. 58, USAEC TID-7024, and other proven methods are used to determine hydrodynamic loadings. For the impulsive mode of the NI Pools, the Zero Period Acceleration (ZPA) of the envelope of the soil cases is used to determine hydrodynamic pressure. The horizontal

03.07.02-74

Page 43: 2013/09/16 Areva EPR DC - Response to U.S. EPR Design ...5 The attached file, “RAI 412 Supplement 8 Response US EPR DC.pdf” provides a technically correct, complete and final response

U.S. EPR FINAL SAFETY ANALYSIS REPORT

Tier 2 Revision 6—Interim Page 3.8-116

ZPA is taken from the pool wall, and the vertical ZPA is taken from the pool floor. The locations were selected to capture the flexibility of the walls and floors. For the impulsive mode of the ESWB Pools, the wall frequency was determined and the appropriate horizontal acceleration is selected from the five percent damped ISRS (with all soil cases enveloped in the ISRS). The horizontal ISRS ��� determined from the location on the walls at mid-height of the water. The vertical ZPAs are used for vertical accelerations, and are taken from the pool floor (building foundation). Hydrodynamic pressures are then determined using these accelerations.For the impulsive mode of the NI Pools, the enveloped Zero Period Acceleration (ZPA) of the tank is used to determine hydrodynamic pressure. The tank structural flexibility is included in values obtained from the In-Structure Response Spectra (ISRS). For the convective mode of the NI Pools and the ESWB Pools, the natural frequency of sloshing water is determined and the corresponding acceleration is based on 0.5 percent damping.

In the static FEM, hydrodynamic loads are applied statically in each of six directions (i.e., east, west, north, south, up, and down). The hydrodynamic loads due to a horizontal earthquake are a combination of impulsive and convective forces simultaneously acting on the pool walls and slabs, accounting for the rotational effects of water motion. The hydrodynamic pressure on the slab and walls due to a vertical earthquake are calculated using the fluid mass density, multiplied by the vertical spectral acceleration of each pool slab location as a function of water depth below the surface.

For the spent fuel pool, the combined rack and hydrodynamic loads including rack sliding/impact loads are applied separately in the static FEM. The combined loads need to be higher than the whole pool seismic analysis results, considering the rack, fluid, and pool dynamic interaction. The impact, friction, and/or hydrodynamic peak instantaneous loads due to rack rocking/sliding will be considered in a local design for punching shear and bending checks.

Design for hydrodynamic loads is within the elastic range of concrete and steel members and elements.

Thermal Analysis and Design

Normal thermal loads (To) are considered in the analysis and design of other Seismic Category I structures. Abnormal pipe break accident thermal loads (Ta) are considered to have no effect on the overall structure of other Seismic Category I structures and are only considered in local analyses.

For concrete structures, the requirements of ACI 349, Appendix A, ACI 349.1R, or thermal analysis computer programs or similar procedures are used to evaluate thermally induced forces and moments. When considering the combined effects of

03.07.02-74