2013 Michigan Bridge Conference Bridge Field Services Update Matthew J. Chynoweth, P.E. March 20, 2013
DEQ Bridge Painting Consent Order Update:
In second year of Consent Order for Bridge Painting Typically CO’s last two years before terminated DEQ attended 2013 Bridge Paint School Over 50 attendees, mix of MDOT, Local Agency and
Consultant groups Currently working with DEQ to update hazardous
management training through DEQ webinars and meetings with Compliance Specialists
Pay special attention to bridge paint project while under order
While the CO is “mild”, noncompliance could still result in major implications and fines.
Bridge Construction Inspection Training Updates:
Bridge Deck Inspection Beam erection, reinforcing steel placement Shear developers, haunch grades, positive and negative
moments Pour sequencing, finishing machine set up (Bidwell), forming,
placing and curing BOHIM 2007-02
Form 1138 Reinforcing computations Form 1131 Depth checks Form 1125 Permit to Place Form 1174B Report of Concrete Placed Bridge Deck Construction Checklists
706 Standard Specifications
Bridge Construction Inspection Training Updates:
Additional emphasis this year on the following: Setting haunch grades Pour Sequences and negative moment regions Stay-In-Place forms Cold Weather Protection 706.03.J
Below 50 degrees but above 40 degrees per National Weather Service use Ordinary Protection (tarpaulins, straw, other approved methods)
Below 40 degrees for more than 8 consecutive hours apply low temperature protection (insulated forms, heating and housing) to maintain concrete/form temperature of at least 40 degrees
If temp falls below 15 degrees heat and house superstructure concrete Concrete temperature of 40 degrees is critical for curing period
Bridge Construction Inspection Training Updates:
Bridge Rehabilitation Construction Bridge Scoping Substructure patching and repair Construction of new bearing surfaces Pin and Hanger rehab and replacement Structural steel repairs Concrete beam repair Expansion joint design, theory, replacement and installation Bridge deck patching Concrete deck rehab, LMC and SFMC overlays Epoxy overlays and healer sealers Total deck replacement
Welded Pile Splice Update: BOHIM Field Splicing of Steel Foundation Piles Special Provision to replace subsection 705.03.C.2.d Special Provision for Quality Control Plan for Welding
Pile Contractor QC plan Updated 1161L for MDOT QA
Field Manual for Pile Welding Comprehensive reference document for field welding
Pay Item Splice, Steel Pile created
Bridge Field Services Advisories:
Bridge Patching Concrete Testing
Final Inspection of Support Structures
Mechanical Reinforcement Splicing
Materials Acceptance on Local Agency Projects
Precast Three-Sided and Arch Culverts
www.michigan.gov/MDOT - Manuals, Guides, Advisories and Memos
Post Construction critical needs:
23 CFR 650.315 states: (c) For existing bridge modifications that alter previously recorded data and for new bridges, enter the SI&A data into the State or Federal agency inventory within 90 days after the completion of the work for State or Federal agency bridges and within 180 days after the completion of the work for all other bridges. This includes taking vertical underclearance
measurements, and sending form to Bridge Management Unit for SI&A update.
Post Construction critical needs:
Form 1120:
Post Construction critical needs: Form 1190:
MDOT ABC Policy Update:
MDOT ABC Policy Update:
Currently working on updates to the MDOT Bridge Design Manual and other publications
Guidance given on design and construction considerations
MDOT ABC Policy Update:
Surfaces µ (static) µ
(kinetic)
Steel on steel 0.74 0.57
Glass on glass 0.94 0.40
Metal on Metal (lubricated)
0.15 0.06
Ice on ice 0.10 0.03
Teflon on Teflon 0.04 0.04
Tire on concrete 1.00 0.80
Tire on wet road 0.60 0.40
Tire on snow 0.30 0.20
MDOT ABC Policy Update:
Currently working on updates to MDOT Project Scoping Manual for evaluation of ABC/PBES techniques with respect to: Site and Structure considerations Work zone Safety and Mobility Cost Technical Feasibility Seasonal Constraints and Project Schedule Environmental Issues
MDOT ABC Policy Update:
Achieve industry buy-in Will be developing ABC workshop with industry in late 2013 Allow time to become comfortable and knowledgeable
using PBES.
Think like a Contractor Consider equipment capabilities and capacities Means and methods to be more thoroughly developed
during the design phase Blur the line between design and construction
Plan a Program of Projects Build Momentum – a clear signal to the industry that the
business model is changing.
MDOT ABC Policy Update:
Challenges: Lack of Knowledge and Experience
Detailing Connections Tracking Durability Designing Curvilinear Geometry Accounting for Negative Moment Continuity
Availability of Precast Contractors Designing element size for transport and site
erection (limiting weight) Contractor Proposing to go Back to CIP After Award
MDOT ABC Policy Update:
Three bridge slide projects proposed for 2014 US-131 over 3 Mile Road in Grand Region M-50 over I-96 in Grand Region M-100 over RR in University Region
Others being discussed in MDOT Bridge Committee
meetings
MDOT ABC Policy Update: GRS Bridges
Pilot project in design Phase in Ionia County: Keefer Hwy over Sebewa Creek
MDOT incentivized by providing Geotechnical
Engineering services to County
Bridge Design is investigating standard superstructure details
2013 Bridge Inspection Workshop
3/19/2013 23 MDOT Bridge Inspection Updates
2013 Bridge Inspection Workshop
MDOT Bridge Inspection Updates 3/19/2013 24
2013 NBIP Review - Status
Metrics in Full Compliance:
Qualifications • Metrics 2-5 Qualifications (Inspectors, Load Raters, etc.) Timeliness • Metric 8 Underwater Inspection Timeliness (Low Risk) • Metric 9 Underwater Inspection Timeliness (High Risk) Procedures • Metric 12 Quality Inspections • Metric 17 Underwater Inspection • Metric 18 Scour Critical Bridge • Metric 19 Complex Bridge Inspection
Inventory • Metric 22 Prepare and Maintain • Metric 23 Update Data (Avg. 16 Days)
2013 Bridge Inspection Workshop
3/19/2013 MDOT Bridge Inspection Updates 25
2013 NBIP Review - Status
Metrics we are Actively Improving:
Timeliness • Metric 6 Routine Inspections (Lower Risk) • Metric 7 Routine Inspections (Higher Risk) • Metric 10 Fracture Critical Inspections • Metric 11 Frequency Criteria
Procedures • Metric 13 Load Rating • Metric 14 Post or Restrict • Metric 15 Bridge Files • Metric 16 Fracture Critical Inspection • Metric 20 QA/QC • Metric 21 Critical Findings
Bridge Development Update Rebecca Curtis, PE Michigan Department of Transportation Bridge Management Engineer 2013 Michigan Bridge Conference
Bridge Development Update
Load Rating Plan of Corrective Action Update Technical Assistance for Load Ratings Metrics 13 and 14 MAP-21 and Expanded NHS Element Level Inspection – What is it? MiBridge Update Questions
Load Rating Plan of Corrective Action
Local Agencies had over 1600 bridges to rate as part of the Tier 1 requirements
Tier 1 was comprised of bridges with no load ratings Tier 1 Load Ratings were due on December 31st,
2012
How did we do?
Load Rating Plan of Corrective Action
14% 17% 22%
93%
0%
20%
40%
60%
80%
100%
1/1/11 4/1/11 7/1/11 10/1/11 1/1/12 4/1/12 7/1/12 10/1/12 1/1/13
% of Local Agency Ratings Complete by Date
Load Rating Plan of Corrective Action
Tier 2 is comprised of bridges in poor condition Load Ratings must be reviewed or updated to
account for the poor condition Tier 2 Load Ratings are due on December 31st,
2014 Tier 2 was already 20% complete on January 1st Remember that as this Tier is tied to inspections, it
likely makes sense to include the load rating with the inspection rather than waiting until December of 2014
Technical Assistance for Load Rating
Bridge Advisory 2012-01 July 2012 MBIS/MBRS Update and Coding Revisions
Bridge Advisory 2012-02 October 2012 Guidance for “Judgment” ratings
Bridge Advisory 2012-03 October 2012 Corrugated Metal Pipe spreadsheet
Technical Assistance for Load Rating
Bridge Load Rating Program Support with MTU Center for Technology and Training
2012 Accomplishments 6 Virtis Training Workshops 3 Webinars Over 240 technical assistance cases
2013 Plans User Needs Survey 1-2 additional Virtis Workshops Webinars on advanced load rating topics Continued technical support and license facilitation
Metrics 13 and 14
Metric 13 – Conditional Compliance due to the Load Rating action plan being underway
Metric 14 – Post or Restrict In the 2011 Review, there were 56 Structures with
Item 41 coded “B” In the 2012 Review, there were 60 Structures (taken
December 17th, 2012 Currently there are 183 Structures coded “B”
MAP-21 and Expanded NHS
Asset Management MAP-21 requires a Risk Based Asset Management
Plan 18 month deadline for FHWA to define the process
and 18 month transition period Performance Goals Penalties applied is more than 10% by deck area of
the NHS is Structurally Deficient for the prior 3 years 18 month deadline for FHWA to establish additional
performance measures and standards and 12 month for States to set targets
MAP-21 and Expanded NHS
Expanded NHS Local Agencies have 151 NHS Structures which is
5.5% by Count or 5.4% by Deck Area Statewide The Local NHS Structures are owned by 26 different
agencies Element Level Inspection Beginning in October of 2014, all NHS bridges must
have Element Level Inspection The Federal SI&A Manual will need to be updated
Element Level Inspection
National Bridge Inventory general condition ratings assigned by inspectors for major components
FHWA reviewing whether Element Level Inspection should be extended to Non-NHS bridges
MDOT is currently updating the Michigan Element Inspection Manual (Pontis Manual) to conform with the AASHTO Guide Manual
Element Level Inspection
Element Level Inspection
NBI Item Inspection Fair Condition Do nothing - $0.00 Rehabilitate all of the
bananas - $3.00 Element Level Inspection
7 bananas 4 good bananas 3 rotten bananas
Rehabilitate only the rotten bananas - $1.28
Source – Development of Bridge Preservation with a Bridge Management System, Paul Jensen, Montana DOT
Element Level Inspection
MDOT collects both NBI and Element level data
NBI data Network or System level
analysis Monitoring Network Goals Information for high level,
executive, legislature, transportation commission
Element level data Project level analysis Prioritizing bridge projects Managing bridge elements Information for bridge
engineers and practitioners Element level data still requires
a needs indicator
MiBridge Update
MBIS and MBRS are being combined into one system
Display and Entry of SI&A Data and Scour Action Plans in MBRS – Estimated April, 2013
Update for new Element Level Inspection – Estimated End of 2013 to Early 2014
MBIS and MBRS consolidation complete and MiBridge released – Early 2014
Questions? Rebecca Curtis, PE Michigan Department of Transportation Bridge Management Engineer 2013 Michigan Bridge Conference