30
2013 Interim Results SZEx Stock Code: 002202 HKEx Stock Code: 2208

2013 Interim Results - TodayIR · 2013-08-26 · China Wind Outlook Cautiously Optimistic Although new installations remained slow in 1H2013, ... Market share is based on installations,

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 2013 Interim Results - TodayIR · 2013-08-26 · China Wind Outlook Cautiously Optimistic Although new installations remained slow in 1H2013, ... Market share is based on installations,

2013 Interim Results

SZEx Stock Code: 002202 HKEx Stock Code: 2208

Page 2: 2013 Interim Results - TodayIR · 2013-08-26 · China Wind Outlook Cautiously Optimistic Although new installations remained slow in 1H2013, ... Market share is based on installations,

Agenda

Section 1 Industry Overview

Section 2 Business Performance

Section 3 Financial Performance

Section 4 Company Outlook

Page 1

Page 3: 2013 Interim Results - TodayIR · 2013-08-26 · China Wind Outlook Cautiously Optimistic Although new installations remained slow in 1H2013, ... Market share is based on installations,

China Wind Outlook Cautiously OptimisticAlthough new installations remained slow in 1H2013, the full-year 2013 is still expected to improve relative to full-year 2012

Source:Actual and cumulative installations: China Wind Energy Association; Target installations: China Wind Energy Roadmap 2050.

China Annual Installed Capacity (GW)

Page 2

Most industry participants are cautiously optimistic that 2013-15 annual installations will exceed 2012 installations of 13 GW.

• According to preliminary data from the Chinese Wind Energy Association, 1H2013 installations were 5.5 GW, level with 5.5 GW in 1H2012.

• Although 1H2013 was weak, wind farm development activity is expected to accelerate in 2H2013.

3.36.2

13.8

18.9 17.6

13.0

5.5

5.8 12.125.8

44.762.4

75.3

2007 2008 2009 2010 2011 2012 2013E 2014E 2015E

Actual Installations Forecast Installed Capacity

Cumulative Installed Capacity Forecast Cumulative Capacity

12th Five-Year Plan Targets 100 GW by 2015

5.5 1H12

5.5 1H13

Page 4: 2013 Interim Results - TodayIR · 2013-08-26 · China Wind Outlook Cautiously Optimistic Although new installations remained slow in 1H2013, ... Market share is based on installations,

Large Pipeline of Wind Farm Projects in ChinaLarge-scale project in Hami, Xinjiang, was added since approval authority was decentralized to the provincial level, bringing approved projects to over 90 GW

Source: Company estimates.

Wind Projects Approved for Construction Under China’s 12th 5-Year Plan (GW)

• A large-scale wind farm project was approved in Hami, Xinjiang, in July 2013, after authority was delegated to the provincial governments in May 2013, bringing total approved projects to 90.4 GW.

• Goldwind expects developers will continue to build the “three batches”, even now that approval authority has been decentralized to the provincial government level.

• Goldwind estimates that nearly 60% of projects have not yet been tendered or begun construction.Page 3

90.4 GW Proposed Projects

26.8 GW 25.8 GW

28.7 GW

9.0 GW

First Batch July 2011

Second Batch March 2012

Third Batch March 2013

Other ApprovedOct '12 - Jul '13

Northwest

North China

Southwest

East China

South China

Central China

Northeast

Inner Mongolia

75%

Tend

ered

39%

Tend

ered

11%

Tend

ered

33%

Tend

ered

3.0 Gansu

6.0 Hami

Page 5: 2013 Interim Results - TodayIR · 2013-08-26 · China Wind Outlook Cautiously Optimistic Although new installations remained slow in 1H2013, ... Market share is based on installations,

Due decentralized approval authority and an ample project pipeline, the project approval

process is no longer an obstacle to development.

Public Tenders Double in 1H2013Public tenders increased 2x in 1H2013 versus 1H2012, suggesting a stronger near-term outlook for the wind industry. However, activity is still lower than in 1H2011.

Source: Company estimates.

Quarterly Domestic Public Tenders (GW)

Page 4

July 2011: 1st batch26.8 GW

March 2012: 2nd batch16.8 GW

3Q12: Additional projects6.8 GW

4Q12: Additional projects5.2 GW

March 2013: 3rd batch28.0 GW

8.4

3.9 3.0

5.5

2.2 2.2 1.4

2.5 3.8

5.0

1Q11 2Q11 3Q11 4Q11 1Q12 2Q12 3Q12 4Q12 1Q13 2Q13

1H11: 12.3GW

1H12: 4.4GW

1H13: 8.8GW+100% vs.1H12

- 64%vs. 1H11

Page 6: 2013 Interim Results - TodayIR · 2013-08-26 · China Wind Outlook Cautiously Optimistic Although new installations remained slow in 1H2013, ... Market share is based on installations,

China Policy Update – Recent DevelopmentsRecent announcements supportive of wind power include prepayment of the supplemental tariff and wind project approval decentralization

Source: Government announcements. Page 5

NEA announced that it’s drafting the final version of the renewable portfolio standard, setting requirements for renewable power consumption by province starting in 2015.

15% 8%10% 4% 2%

Renewable Portfolio Standard

Proposed renewable power consumption quota:

China issued RMB 14.8 billion of advance payments to provinces for the supplemental tariff covering wind, solar, and bioenergy power. The largest amount, RMB 9.3 billion, was for wind power. China’s Ministry of Finance has issued a list of renewable energy projects covered by the supplemental tariff, including 1,134 wind projects with 63.8 GW of capacity. Advance payment of the supplemental tariff is expected to improve the liquidity of wind farm operators.

Supplemental Tariff

On May 15th 2013, the State Council announced the decentralization of wind project approval authority from the NDRC to local governments.

Approval Decentralization

Improving Grid Bottlenecks

In March 2013 the NEA issued a notice calling for relevant state agencies and energy corporations to use wind power consumption and utilization a key performance indicator.

Page 7: 2013 Interim Results - TodayIR · 2013-08-26 · China Wind Outlook Cautiously Optimistic Although new installations remained slow in 1H2013, ... Market share is based on installations,

China Grid UpdateTwo of 17 transmission projects under 12th 5-year plan have been completed and may begin operation this year. Three more should be completed next year.

Source: Government announcements. Note: Transmission routes are approximate. Page 6

Key Planned Transmission Lines3 Horizontal - 3 VerticalOther Key Transmission LinesUnder construction

Scheduled to Start 2013Approval Expected 2013

137 GW transmission capacity planned for construction through 2015, however the schedule for

completion is still not clear.

Completed

Page 8: 2013 Interim Results - TodayIR · 2013-08-26 · China Wind Outlook Cautiously Optimistic Although new installations remained slow in 1H2013, ... Market share is based on installations,

Source: China Electricity Council,China Renewable Energy Engineering Institute, China National Renewable Energy Centre.

Wind Power Utilization Improved in 1H13China’s wind power utilization improved as more wind power was accepted by the power grid. Wind equipment utilization improved 9% compared to last year.

China Average Wind Power Utilization Rate (Hours)

2,077 2,0471,875 1,893

1,010 1,101

2009 2010 2011 2012 1H2012 1H2013

Wind utilization improved during the first half of 2013 due to:

• Growth in national power demand encouraged higher wind power consumption at the provincial level;

• Better thermal power peaking capability allowed for better utilization of wind power.

National wind curtailment rate: 12% 10%

Page 7

Page 9: 2013 Interim Results - TodayIR · 2013-08-26 · China Wind Outlook Cautiously Optimistic Although new installations remained slow in 1H2013, ... Market share is based on installations,

Agenda

Section 1 Industry Overview

Section 2 Business Performance

Section 3 Financial Performance

Section 4 Company Outlook

Page 8

Page 10: 2013 Interim Results - TodayIR · 2013-08-26 · China Wind Outlook Cautiously Optimistic Although new installations remained slow in 1H2013, ... Market share is based on installations,

Goldwind Product LineOur next generation of wind turbines are designed to meet demand in low-wind, coastal and offshore markets

Source: Company filings.

Low

-Win

dO

ffsh

ore

Suit

abili

ty

Strong domestic demand for turbines that perform well in low wind speed

China targets 5 GW of offshore installations by 2015. PMDD well suited for offshore.

Products specialized for challenging environments continue to drive sales

Product Platforms 1.5 MW 2.5 MW 3.0 MW

Rotor Diameters (m) 70, 77, 82, 87, 93 109, 112, 121 121

Low Wind SpeedClass IIIB: 87/1500

Ultra-Low Wind SpeedClass S: 93/1500

Medium Wind SpeedClass IIA: 109/2500

Low Wind SpeedClass IIIA: 112/2500Class IIIB: 121/2500

Low Wind SpeedClass IIIB: 121/3000

• Low temperature• High temperature• High altitude• Low wind speed• Ultra-low wind• Coastal

• Coastal • Coastal & Intertidal• Offshore

• Coastal & Intertidal• Offshore

• Low wind speed• Coastal• Offshore

• Low wind speed• Coastal• Offshore

Status

Installed (MW)

Commercial Commercial In Prototype

12,741 MW 540 MW 18 MW

Page 9

87/1500Musselshell,

Montana, USA

6.0 MW

TBD

• Offshore

In Development

-

• Offshore

Page 11: 2013 Interim Results - TodayIR · 2013-08-26 · China Wind Outlook Cautiously Optimistic Although new installations remained slow in 1H2013, ... Market share is based on installations,

Goldwind leads domestic wind marketDespite China’s challenging competitive environment, Goldwind leads the domestic market by delivering high quality and cost-efficient products and services

China Market Share

Page 10Source: Chinese Wind Energy Association.

2012 1H2013 (Preliminary)

Goldwind19.5%

United Power15.7%

Sinovel9.3%

Ming Yang8.7%

Xiangtan6.9%

Shanghai Electric

6.3%

Envision4.2%

Gamesa3.8%

Dongfang Electric

3.6%

Vestas3.2%

Other18.8%

Goldwind23.3%

United Power14.6%

Ming Yang, 10.1%Xiangtan

9.3%

Shanghai Electric

8.5%

Sinovel, 7.1%

Hai Zhuang5.7%

Envision 4.5%

Gamesa2.5%

Dongfang Electric

2.4%Other11.9%

Market share is based on installations, not sales which are realized upon delivery. Goldwind installed 1,280 MW during 1H13 or 23.3% of market share in 1H13, versus 19.5% in 2012.

First half market share data may not be representative of full-year performance.

Page 12: 2013 Interim Results - TodayIR · 2013-08-26 · China Wind Outlook Cautiously Optimistic Although new installations remained slow in 1H2013, ... Market share is based on installations,

Wind Turbines Sales VolumesDespite lingering weakness in domestic wind equipment demand during the first half of 2013, Goldwind maintains a positive outlook for full-year 2013

Source: Company filings.

Realized External Sales Volumes (MW)• Realized external sales reflected

weak demand in the domestic wind market during the first half of 2013.

• Realized external sales volumes decreased 8.2% to 662 MW in 1H2013 from 721 MW in 1H2012.

• Large-capacity units (2.5 MW and 3.0 MW) represented 17% of external sales in 1H2013, up from 5% in 1H12.

Page 11

854 444 154

519

1,592

3,851

2,882

2,216

549

3 >

224

368

<113

1,373

2,036

4,007

3,106

2,583

1H2013662

2008 2009 2010 2011 2012 1H13

2.5 MW & 3.0 MW1.2 MW & 1.5 MW750 kW

1H2012721

1H20111,211

Page 13: 2013 Interim Results - TodayIR · 2013-08-26 · China Wind Outlook Cautiously Optimistic Although new installations remained slow in 1H2013, ... Market share is based on installations,

Average Domestic Public Bidding Price for 1.5 MW units (RMB/kW)

• Average domestic public bidding price for 1.5 MW units has returned to RMB 3,800-3,900 per kW

• Domestic ASP widely expected to remain stable or increase in the near-term

Goldwind 1.5 MW Achieved Significant PremiumGoldwind commands a premium in the domestic market due to superior quality, performance, reliability and services

Note: Data include VAT and excludes bids from foreign manufacturers. No public bidding in July 2012.

Source: Internal company estimates.Page 12

Dec-103,950

Mar-113,785

Jun-113,615

Sep-113,816

Dec-113,711

Mar-123,744

Jun-123,747

Sep-123,762

Dec-123,801

Mar-133,788

Jun-133,925

Dec-10 Mar-11 Jun-11 Sep-11 Dec-11 Mar-12 Jun-12 Sep-12 Dec-12 Mar-13 Jun-13

Average Goldwind

Page 14: 2013 Interim Results - TodayIR · 2013-08-26 · China Wind Outlook Cautiously Optimistic Although new installations remained slow in 1H2013, ... Market share is based on installations,

Backlog Strong at 8,089 MegawattsDue to a high level of public tenders during the first half of 2013, Goldwind’s backlog increased substantially

Source: Company filings.

Wind Turbine Order Backlog (MW)

Page 13

• Goldwind reported a total backlog of 8,089MW as of 30 June 2013, up 5.7% from 7,655 MW as of 31 March 2013.

• Backlog under final contract of 4,550 MW represented 56% of the total backlog. Successful bids represented the remaining 44%.

2,765

3,9314,400

4,839 5,017

4,0864,576 4,550

3,816 2,397 1,877

2,967 2,564

2,515

3,0793,539

6,580 6,327 6,277

7,806 7,581

6,600

7,6558,089

31 Dec 2010 31 Dec 2011 31 Mar 2012 30 June 2012 30 Sep 2012 31 Dec 2012 31 Mar 2013 30 June 2013

Successfully bidUnder final contract

Percent 1.5 MW73% 79% 77% 82%

Page 15: 2013 Interim Results - TodayIR · 2013-08-26 · China Wind Outlook Cautiously Optimistic Although new installations remained slow in 1H2013, ... Market share is based on installations,

Backlog Aging AnalysisA large majority of Goldwind’s contracted backlog dates from 2011 or later

Source: Company data.

Backlog Under Final Contract According to Year Contract Signed

Page 14

• 92% of the 4,550 MW of backlog under final contract as of 30 June 2013 was signed in 2011-2013.

• 8% of contracted backlog dates from 2009 and 2010.

• Project delays are most often due to lack of grid connection agreement.

92%

2009 20092010 2010

2011

2011

2012

2012

2013

2012-12-31 2013-6-30

4,550 MW

4,086 MW

Page 16: 2013 Interim Results - TodayIR · 2013-08-26 · China Wind Outlook Cautiously Optimistic Although new installations remained slow in 1H2013, ... Market share is based on installations,

Backlog by LocationGoldwind’s domestic backlog is particularly strong in China’s Northwest and North regions, where curtailment rates have improved

Page 15

Goldwind’s Total Backlog by Location

• Goldwind’s backlog is concentrated in provinces with acceptable levels of wind power utilization, such as Shanxi in North China and Xinjiang in Northwest China.

• Wind farm development has increased in Hami in anticipation of 8 GW of newly installed transmission capacity from South Hami, Xinjiang to Zhengzhou, Henan.

Source: Company data. Note: The backlog includes Goldwind’s backlog for internal sales and Vensys’ backlog.

Over 60%

Xinjiang

Northwest Ex. IM

North China

Inner Mongolia

Northeast South China

International Other China

Xinjiang

Page 17: 2013 Interim Results - TodayIR · 2013-08-26 · China Wind Outlook Cautiously Optimistic Although new installations remained slow in 1H2013, ... Market share is based on installations,

International Backlog AnalysisGoldwind’s international backlog is located in both mature and growth markets, such as Europe, South America, and Australia

Page 16

• Goldwind’s international backlog was 361 MW as of 30 June 2013, compared to 221 MW as of 30 June 2012.

• International contracts represent 7.9% of Goldwind’s backlog under final contract.

International Backlog by Region (MW)

Source: Company data. Note: The backlog includes Goldwind’s backlog for internal sales and Vensys’ backlog.

Total = 361MW

129

10089

44

South America Europe Oceania Asia

Page 18: 2013 Interim Results - TodayIR · 2013-08-26 · China Wind Outlook Cautiously Optimistic Although new installations remained slow in 1H2013, ... Market share is based on installations,

Agenda

Section 1 Industry Overview

Section 2 Business Performance

Section 3 Financial Performance

Section 4 Company Outlook

Page 17

Page 19: 2013 Interim Results - TodayIR · 2013-08-26 · China Wind Outlook Cautiously Optimistic Although new installations remained slow in 1H2013, ... Market share is based on installations,

Annual & Semiannual Financial ResultsRevenues decreased 6.5% in 1H2013 compared to 1H2012 due to lower wind turbine volumes. Gross margin increased and net profit achieved reasonable level.

Source: Company filings. Annual data are in accordance with IFRS. Net profit is net profit attributable to owners of the company.

Revenues (RMB millions) Gross Profit (RMB millions)

Net Profit (RMB millions)Gross Margin (%)

Page 18

Annual Semi-annual Annual Semi-annual

Annual Semi-annual Annual Semi-annual

3,808 6,305 5,172 3,451 3,227

10,667

17,475

12,756 11,225

2009 2010 2011 2012 1H13

923 1,552

1,085 459 599

2,758

4,021

2,0571,592

2009 2010 2011 2012 1H13

538 773

425 72 93

1,208

1,517

182

81

2009 2010 2011 2012 1H13

24.2% 24.6%

21.0%

13.3%

18.6%

25.9%23.0%

16.1%14.2%

2009 2010 2011 2012 1H13

Page 20: 2013 Interim Results - TodayIR · 2013-08-26 · China Wind Outlook Cautiously Optimistic Although new installations remained slow in 1H2013, ... Market share is based on installations,

Quarterly Revenues, Gross Margin, and Net Profit2Q13 revenues and gross profit improved due to stronger wind turbine deliveries

Source: Company filings. Quarterly data are in accordance with PRC GAAP. Net profit is net profit attributable to owners of the company.

Quarterly Revenues (RMB millions) Quarterly Gross Profit (RMB millions)

Quarterly Net Profit (RMB millions)Quarterly Gross Margin (%)

Page 19

1,856

3,339

4,226

3,423

1,700 1,784

2,463

5,378

951

2,295

1Q11 2Q11 3Q11 4Q11 1Q12 2Q12 3Q12 4Q12 1Q13 2Q13

411

692651

374

186

295

407

852

170

443

1Q11 2Q11 3Q11 4Q11 1Q12 2Q12 3Q12 4Q12 1Q13 2Q13

22.1%20.7%

15.4%

10.9% 11.0%

16.5% 16.5% 15.9%17.9%

19.3%

1Q11 2Q11 3Q11 4Q11 1Q12 2Q12 3Q12 4Q12 1Q13 2Q13

206219

190

-8

6

66

-34

115

3260

1Q11 2Q11 3Q11 4Q11 1Q12 2Q12 3Q12 4Q12 1Q13 2Q13

Page 21: 2013 Interim Results - TodayIR · 2013-08-26 · China Wind Outlook Cautiously Optimistic Although new installations remained slow in 1H2013, ... Market share is based on installations,

Business Segment ResultsNon-manufacturing business segments provide diversification and growth

Notes: Financial data are in accordance with IFRS.

Gross Profit (% of total GP)Revenues (RMB millions)

• Non-manufacturing segments increased to 12.2% of revenues in 1H2013, up from 7.6% in 1H2012.

Page 20

• Non-manufacturing segments represented 24% of gross profit in 1H2013, up slightly from 23% in 1H2012.

95% 96%92%

87%

77% 75%

2%> 1%> 4%5%

12%4%

3%> 3%> 4% 8% 11%20%

2009 2010 2011 2012 1H12 1H13

WTG R&D, Manufacturing and SalesWind Power ServicesWind Farm Investment, Development and Sales

215 293 363 392

162 208 104

178 139 252

102186

2009 2010 2011 2012 1H12 1H13

WTG R&D, Manufacturing and Sales

Wind Power Services

Wind Farm Investment, Development and Sales

10,347

17,005

12,25410,581

3.0% 2.7%3.9%

5.7%

Perc

ent

of T

otal

2,833

12.2%

7.6%

3,188

Page 22: 2013 Interim Results - TodayIR · 2013-08-26 · China Wind Outlook Cautiously Optimistic Although new installations remained slow in 1H2013, ... Market share is based on installations,

572.2 585.9

740.0 605.3 558.3 522.0

1,029.6

1,252.9

31 Dec 2011 30 Jun 2012 31 Dec 2012 30 Jun 2013

Attributable Installed CapacityAttributable Under Construction Capacity

Wind Farm Development and SalesGoldwind stepped up its investment in wind farm development

Source: Company filings.

Wind Farm DivestituresAttributable Wind Farm Capacity (MW)

• Goldwind sold its ownership stake in two wind farms with 134.7 MW of attributable capacity during 1H2013.

• Total installed wind farm capacity was 981.5 MW and attributable installed capacity was 605.3 MW as of 30 June 2013.

• Goldwind accelerated wind farm development during 1H2013, reporting 1,252.9 MW of attributable capacity under construction at the end of the period.

Page 21

155.8

244.8

117.5 134.7

443.8 411.8

259.5 133.9

2010 2011 2012 1H2013

Wind farm capacity sold (MW)Gain on sale of wind farms (million RMB)

Page 23: 2013 Interim Results - TodayIR · 2013-08-26 · China Wind Outlook Cautiously Optimistic Although new installations remained slow in 1H2013, ... Market share is based on installations,

Net Operating Cash FlowOperating cash flow was negative during the first half as the Company purchased inventory in anticipation of second half deliveries

Note: Quarterly data are in accordance with PRC GAAP.

Net Cash Flow From Operations (RMB millions)

• Net operating cash flow is typically negative during the first half as the company orders inventory to fulfill scheduled deliveries.

Page 22

1Q10 2Q10 3Q10 4Q10 1Q11 2Q11 3Q11 4Q11 1Q12 2Q12 3Q12 4Q12 1Q13 2Q13

2011

- RMB 4,133 million

2010RMB 186 million

2012

RMB 2,500 million

1H2013

- RMB 1,221 million

Page 24: 2013 Interim Results - TodayIR · 2013-08-26 · China Wind Outlook Cautiously Optimistic Although new installations remained slow in 1H2013, ... Market share is based on installations,

Source: Company filings. Notes: Data are in accordance with IFRS. Data adjusted for intersegment elimination.

Capex Reflects Development Strategy

Segment Capital Expenditures (RMB millions)

1,80487%

2,49574%

2,69081%

2,62580%

67284%

1,94196%

<4.5

<7.7 <5.0 <22

<0.5

<0.4 270

892 631 613

130

85

2,078

3,395 3,327 3,260

803

2,026

2009 2010 2011 2012 1H12 1H13

WTG R&D, Manufacturing and SalesWind Power ServicesWind Farm Investment, Development and Sales

Spending on wind farm development increased dramatically in 1H2013 as the company commenced construction on new domestic and international projects

Page 25: 2013 Interim Results - TodayIR · 2013-08-26 · China Wind Outlook Cautiously Optimistic Although new installations remained slow in 1H2013, ... Market share is based on installations,

Conservative Capital StructureDue to inventory restocking and the timing of payments, Goldwind’s cash balance decreased during 1H2013

Source: Company filings. Financial data are in accordance with PRC GAAP.

Cash and Total Debt (RMB millions)

Page 24

• Cash decreased in 2H2013 due to inventory restocking in preparation for second half deliveries. The timing of payments, such as accounts payable, also affected cash as of 30 June 2013.

• Total debt was stable at RMB 6.4 billion as of 30 June 2013, versus RMB 6.5 billion as of 31 March 2013. Net debt increased to RMB 1.7 billion from RMB 0.7 billion over the same period.

Cash

Total Debt

Net Debt -281 -2,249

-1,441 -395

961

-691 -1,694

31 Dec 2011 31 Mar 2012 30 Jun 2012 30 Sept 2012 31 Dec 2012 31 Mar 2013 30 Jun 2013

7,613 7,070

5,417 5,730 6,962

5,784 4,685

7,894 6,346

3,883 3,148 3,021 3,493 3,394

2,972

2,975 2,977 2,979 2,982 2,984

Cash Bank Debt Corporate Bonds due 2015

Page 26: 2013 Interim Results - TodayIR · 2013-08-26 · China Wind Outlook Cautiously Optimistic Although new installations remained slow in 1H2013, ... Market share is based on installations,

Agenda

Section 1 Industry Overview

Section 2 Business Performance

Section 3 Financial Performance

Section 4 Outlook

Page 25

Page 27: 2013 Interim Results - TodayIR · 2013-08-26 · China Wind Outlook Cautiously Optimistic Although new installations remained slow in 1H2013, ... Market share is based on installations,

Strategic Goals for 2013Goldwind strives to be a global leader in the development and utilisation of clean energy

Diversify our Product PortfolioSustain the competitive advantages of our existing products (1.5 MW & 2.5 MW) and speed development of new products and services, such as the 6.0 MW wind turbine.

Improve Customer Service CapabilitiesBroaden sales channels and leverage our comprehensive business model to expand our market reach.

Strengthen Core Competitive CapabilitiesEstablish high standards and benchmarking, improve management and enhance the core competitive capabilities of each business unit.

Provide Comprehensive Wind Power SolutionsFully leverage the synergies of our comprehensive wind power solutions, including wind turbine R&D, wind turbine sales, and wind services to provide customers with integrated wind power solutions. Accelerate expansion in higher value-added segments of the wind power value chain.

Page 26

Page 28: 2013 Interim Results - TodayIR · 2013-08-26 · China Wind Outlook Cautiously Optimistic Although new installations remained slow in 1H2013, ... Market share is based on installations,

Goldwind Prepared For Offshore Market GrowthGoldwind completed 100 MW Rudong coastal wind farm in early 2013, taking another major step toward large-scale offshore development

Source: Company filings.

2012

Goldwind completed 1st

50 MW Rudong

intertidal wind farm

2007

Goldwind installed

China’s first offshore

prototypeInstalled in

Bohai

2010China held

first offshore tender of

1GW to be installed offshore Jiangsu

2011

China sets an offshore

target of 5 GW by 2015 and 30 GW

by 2020

2010

Goldwind installed 2.5 MW

prototypes offshore Jiangsu

Page 27

2010

Goldwind won 200 MW

of first offshore

concession

2011

Goldwind won 1st 50

MW of Rudong

intertidal project

2013

NDRC upgraded

offshore wind power to

encouraged

2011

NEA begins central

coordination of China’s

wind industry

2012

Goldwind completed 2nd

50 MW Rudong

intertidal wind farm

Goldwind Offshore Milestones

Industry Offshore Milestones

Page 29: 2013 Interim Results - TodayIR · 2013-08-26 · China Wind Outlook Cautiously Optimistic Although new installations remained slow in 1H2013, ... Market share is based on installations,

Page 28

DISCLAIMER

This document does not constitute, or form part of any offer for subscription or sale of, or solicitation of any offer to subscribe for or sale of any securities of Xinjiang Goldwind Science & Technology Co., Ltd. (the Company), nor shall it be construed as calculated to invite any such offer, nor shall it form the basis of, nor can it be relied on in connection with, or act as an inducement to enter into any contract or commitment whatsoever. Accordingly, any decision in connection with the subscription or acquisition of securities of the Company pursuant to or in connection with any offering must be made solely on the basis of the information to be contained in the prospectus or other offering circular to be issued by the Company in connection with such offering; and no representation is made by the Company in respect of any information in this document, except as contained in such prospectus or offering circular.

FORWARD-LOOKING STATEMENTS

This presentation contains certain forward-looking statements with respect to the financial condition, results of operations andbusiness of the Company, the wind industry in the PRC and certain of the plans and objectives of the management of the Company. Such forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results of performance of the Company to be materially different from any future results or performance expressed or implied by such forward-looking statements. Such forward-looking statements were based on assumptions regarding the Company’s present and future business strategies and the political and economic environment in which the Company and its subsidiaries operate currently and will operate in the future. Reliance should not be placed on these forward-looking statements, which reflect the view of the Company’s management as of the date of this presentation only.

Page 30: 2013 Interim Results - TodayIR · 2013-08-26 · China Wind Outlook Cautiously Optimistic Although new installations remained slow in 1H2013, ... Market share is based on installations,

Corporate Contacts:Ms. Jinru MaVice President, Secretary of the Board, and Corporate Secretary

Ms. Kathryn Tsibulsky, CFAInvestor Relations Manager [email protected]

Jessie WangInvestor Relations [email protected]

Shane SunInvestor Relations Specialist [email protected]

SZEx Stock Code: 002202 HKEx Stock Code: 2208