26
Key Considerations for the Attachment of Facades to Structures James Parker, PE, SE Simpson Gumpertz & Heger Inc. www.FindYourTechnology.com 2 3 4 5 6

2010.09.08 - Key Considerations for the Attachments of Facades to Structures

Embed Size (px)

DESCRIPTION

fachadas en estructuras

Citation preview

Page 1: 2010.09.08 - Key Considerations for the Attachments of Facades to Structures

Key Considerations for the Attachment

of Facades to Structures

James Parker, PE, SE

Simpson Gumpertz & Heger Inc.

www.FindYourTechnology.com 2

3 4

5 6

Page 2: 2010.09.08 - Key Considerations for the Attachments of Facades to Structures

7

University of Massachusetts Medical Center

8

AISC Design Guide 22

9

Design Guide Objective

� To assist the practicing engineer in achieving

slab edge and spandrel beam details for

steel frames that are:

� Structurally sound

� Durable

� Economical

� Accommodating of façade requirements

Today’s Agenda

1. Fundamentals of Façade Performance

2. Design Criteria

3. Roles and Responsibilities

4. Tolerances

5. Slab Edges

6. Spandrel Beams

7. Masonry Veneer, PC Panels, Aluminum

Curtain Walls

10

Three Key Take-Aways1. The design team needs to develop a

strategy for façade attachment and the

SER has a role in its development.

2. The current ASCE 7 and IBC have

explicit criteria for façade attachments

especially for seismic considerations.

3. The façade attachment strategy chosen

by the team will affect the design of slab

edges and spandrel beams.

11 12

Fundamentals of Façade Performance

The building envelope encloses the building,

controlling the transmission of air, water, heat,

sound, and light both into and out of the building.

Page 3: 2010.09.08 - Key Considerations for the Attachments of Facades to Structures

13

The Façade and the Building Enveloperoofing

walls

foundations

doors

windows

all interfaces

14

Fundamentals of Façade Performance

ReservoirReservoirReservoir BarrierBarrierBarrierCavityCavityCavity

15

0 1000 A.D. 20001000 B.C.2000

Time Line

Load Bearing Masonry

Contemporary Curtain Walls

Transitional Masonry

16

0 1000 A.D. 20001000 B.C.2000

Load Bearing Masonry

1250 B.C. 430 B.C. 530 A.D.

1220 to

1472

A.D.1796

17

Load Bearing Masonry

• Walls are Thick

• Walls Support all Loads

• Floor “Rides” with Walls

18

Load Bearing Masonry

• Walls Functions

as a Reservoir

Page 4: 2010.09.08 - Key Considerations for the Attachments of Facades to Structures

19

0 1000 A.D. 20001000 B.C.2000

Transitional Masonry

Time Line

20

1900 19501890 1910 1920 1930 1940

Transitional Masonry Buildings

21

Transitional Masonry Buildings

� Masonry Walls Still

Thick

� Floor & Wall Loads

Carried by

Structural Frame

�Wall Still Functions

as a Reservoir

22

Transitional Masonry Buildings

23 24

Page 5: 2010.09.08 - Key Considerations for the Attachments of Facades to Structures

25

0 1000 A.D. 20001000 B.C.2000

Contemporary Curtain Walls

Time Line

26

Contemporary Curtain Walls

20001950 1960 1980 199019701918

27

Contemporary Curtain Walls

• Floor Loads Carried by Frame

• “Skin” Transfers Wind Loads to the Frame

• “Skin” Employs a Drainage Plane and Back-up Waterproofing

28

Contemporary Curtain Walls

• “Skin” and Frame

Detailed to

Accommodate

Differential Movement

29

Functional Components of the Exterior

Wall System

� Cladding

� Joints

� Insulation

� Water barriers and air

barriers

� Structure

� Interior finishes

30

Concepts for Control of Water

Infiltration

� Barrier Walls

� Internal Drainage

Planes

� Cavity Walls

� PE Rain Screens

Page 6: 2010.09.08 - Key Considerations for the Attachments of Facades to Structures

31

Barrier Walls

� Still used today

�Old EIFS

�GFRC panels

� Precast wall panels

(but a bit of a reservoir

too.)

32

Internal Drainage Planes

� Stucco

� Drainable EIFS

� Wood siding

33

Cavity Walls

� Brick veneer

� Stone veneer

34

Pressure Equalized Rain

Screens� Terracotta cladding

� Stone cladding

� Metal panel cladding

35

Problems Associated with Support

and Anchorage

� Anchors or support clips interrupt the flashing or

water barrier without proper repair.

� Anchors causing conditions of poor drainage.

� Anchors not stiff enough to prevent differential

movement that tears barriers.

� Damage to barriers during erection and

installation.

� Constructability issues, coordination of trade

issues.

36

General Design Criteria

Façade/Wall System Criteria

1. structural integrity;

2. provisions for movement; and

3. envelope performance.

Page 7: 2010.09.08 - Key Considerations for the Attachments of Facades to Structures

37

Primary Criteria for Attachment

� Structural Integrity

� Accommodating Movement

� Durability

� Accounting for Tolerances and Clearances

� Constructability

� Economy

38

Conflicting Ideas

39

Example Resources(there are others)

� Building codes

� 2006 IBC

� ASCE 7-05

� Material Standards/

Organizations

� AISC

� PCI

� ACI

� BIA

� TMS

� Façade Trade

Associations

� AAMA, Aluminum

Curtain Walls for

example

� Papers, Texts

40

Structural Integrity

RedundancyDuctility

Strength

41

Gravity Loads

� Façade dead load� Need to understand materials and system

� Façade live loads� Horizontal projections

� SER usually needs to estimate before wall is designed.

� Window washing activities.

42

Gravity Load Eccentricities

Page 8: 2010.09.08 - Key Considerations for the Attachments of Facades to Structures

43

Wind Loads

44

Wind Loads

� Wind tunnel testing

45

Wind Loads

� Negative pressures combined with gravity eccentricities often control attachment design.

46

Seismic Requirements

1. Seismic Forces

2. Relative Displacements

3. Ductility

47

Seismic Loads

48

Seismic Loads

Page 9: 2010.09.08 - Key Considerations for the Attachments of Facades to Structures

49

Seismic Loads

50

Seismic Loads

51

Seismic Loads

52

Seismic Loads

53

Seismic Loads

54

Seismic Loads

Page 10: 2010.09.08 - Key Considerations for the Attachments of Facades to Structures

55

Seismic LoadsRelative Seismic Displacement

56

Relative Seismic Displacement

57 58

Forces from Restraint

� Best to avoid restraint

altogether.

� Predicting restraint

forces inexact.

� Cracking

� Creep

� Attachment stiffness.

� Watch out for

inadvertent restraint.

Bldg. Exp. Joint

Slotted Insert

Panel Joint

This bolt

fractured and

panel fell.

59

Accommodating Relative Movement

� Spandrel deflections,

� Spandrel rotations,

� Column shortening,

� Bracket deflections,

� Inter-story dirft,

� Façade thermal,

� Façade moisture,

� Façade deformation

due to forces.

60

Accommodating Relative Movement

Page 11: 2010.09.08 - Key Considerations for the Attachments of Facades to Structures

61

Accommodating Relative Movement

� Rules of thumb and code provisions for

flexural stiffness control façade material

cracking.

�L/360; L/600; etc.

62

Accommodating Relative Movement� Joint criteria may control –example:� Say ¾ inch joint; allowable movement of ¼ inch, M=.33

� Say thermal and moisture is 1/8 inch; leaving 1/8 inch for structural movement.

� Say design load movement from 50% LL; then 100% LL allowable movement = ¼inch.

� This is L/960 and L/1440 on 20 ft and 30 ft spans, respectively.

Add slide of protruding sealant

63 64

Accommodating Relative Movement

Inter-story Drift from Lateral Loads

� Common drift limits:

�Wind� H/400 (.0025H); or H/500 (.002H)

�Seismic� .025 H (10 times wind!)

� For a 12 ft story height:�Wind – 0.36 inches (but not less than ½”)

�Seismic – 3.6 inches

65

Accommodating Relative Movement

66

Accommodating Relative Movement

Page 12: 2010.09.08 - Key Considerations for the Attachments of Facades to Structures

67

Inter-Story Drift: Corners

68

Limit States

� Code prescribed forces for safety:

�50 yr. recurrence interval for wind

�475 yr. recurrence interval for seismic

� Attachments must safely accommodate

forces.

� Joints must prevent hazardous damage;

falling hazards.

69

Limit States

� Serviceability checks may allow lower

forces and drifts; for example joint sealant

movements.

� ASCE 7-02 Commentary suggest: D +

0.5L + 0.7W

�0.05 annual probability of being exceeded.

�0.72 probability of being exceeded in 25 yrs.

�0.92 probability of being exceeded in 50 yrs.

70

Shear and Flexural Deformations

71

Tolerances and Clearances

� Tolerances:

�Permissible amount of deviation from a

specified criterion: dimension, shape, location.

� Clearances:

�Space purposely provided between two parts

to allow for movement, accommodate

tolerances and provide access.

72

Durability of the Attachment

� Attachments are usually hard to

inspect.

� Consider what happens if the

wall leaks.

� Consider how likely the wall is to

leak over time.

� Special attention to thin steel

parts or steel fasteners.

Page 13: 2010.09.08 - Key Considerations for the Attachments of Facades to Structures

Constructability and Economy

73 74

Summary of Criteria

� For Attachments:

�Structural Integrity

�Accommodating Movement

�Durability

�Accounting for Tolerances and Clearances

�Constructability and Economy

75

Responsibilities for Façade

Attachments for New Buildings

� Owner

� Architect

� SER

� SSE

• Fabricator, Erector

• CM, GC

• Façade Contractor(s)

76

Responsibilities

� SER (Structural Engineer of Record)

�For this presentation, we mean the design

professional responsible for the structural

design of the primary building structure.

� SSE (Specialty Structural Engineer)

�For this presentation, we mean the design

professional responsible for the structural

design of the façade and/or façade

attachments to the primary structure.

77

Responsibility

� The design of the façade elements and

their attachments are often NOT in the

scope of the SER responsible for the

primary building frame.

�Yet the SER must understand the façade

system and the strategy for attachment to

design the primary structure.

78

Responsibility

� The performance specified elements

including attachments will often be

designed by the SSE working for the

contractor (but could part of the design

team).

�The SSE may not become involved until after

the frame is designed, even fabricated, and

even erected!

Page 14: 2010.09.08 - Key Considerations for the Attachments of Facades to Structures

79

SER

� It’s in the project’s and SER’s best interest

to consult with the Architect about façade

attachments.

� Provides anticipated structural

movements.

� Designs frame and slab edge consistent

with attachment strategy.

80

SER

� Structural drawings/specifications

� Delineate the structural elements from the attachment

items by the SSE.

� Indicate the assumptions/limitations of the locations

and magnitudes of the façade attachment loads.

� Indicate the fabrication and erection tolerances of the

frame.

� Provides sufficient adjustability in structural frame

details for façade attachment strategy chosen.

81

Masonry

Veneer

Example

SER

SSE

Arch.

82

Story-tall PC

Panel Example

SER

SSE

Arch.

SSE

SER

83

Column Supported PC Spandrel

Panel Example

SSE

SER

SSE

SER

SSE

84

Curtain Wall

Example

SSE

SSE

SER

SER

Page 15: 2010.09.08 - Key Considerations for the Attachments of Facades to Structures

85

Summary

� Communicate!

� Façade attachments are difficult because

every member of the design team has a

significant role in the planning, designing

and coordination.

86

Accommodating Construction

Tolerances and Clearances

Adjustability must be provided between the

structural details and façade attachment details

to achieve a façade erected within acceptable

tolerances relative to the theoretical plane.

University of Southern Indiana

87

Tolerances and Clearances

� Tolerances:

�Permissible amount of deviation from a

specified criterion: dimension, shape, location.

� Clearances:

�Space purposely provided between two parts

to allow for movement, accommodate

tolerances and provide access.

88

Types of Tolerances

� Material Production Tolerances

� Fabrication and Assembly Tolerances

� Erection and Installation Tolerances

� Accumulated Tolerances

The AISC Design Guide includes summaries

of major façade materials and components.

The AISC Design Guide includes summaries

of major façade materials and components.

89

Accumulated Tolerances

� Unlikely that all tolerances will vary to the

maximum allowed and all occur in the

same direction.

� However, no statistical data is usually

available to the designer about the

distribution of variation.

90

Recommendations for Accumulated

Tolerances

� Understand the sources of variability.

� Understand the consequence of exceeding the

tolerance provisions in the details.

� Understand the costs associated with providing

means to accommodate the variability.

� For each project, the team should develop a

design criteria for addressing façade

accumulated tolerances.

Page 16: 2010.09.08 - Key Considerations for the Attachments of Facades to Structures

91

Slab Edge Conditions

The slab edge detail is an important

consideration when designing for façade

attachments.

92

Factors that Influence the Design

� Type, weight and

location of façade

� Amount of slab

overhang

� Slab or deck capacity

� Application of façade

loads

� Similar conditions (or

not)

93

Two Fundamental Approaches

� The slab or deck

cantilevers and picks

up load.

� The designer does

not count on the slab

or deck to carry loads.

Approach 1

Approach 2

94

Approach 1: Slab Cantilever Resolves

Eccentricity

95

Design of Slab Overhang

96

Design of Slab Overhang

Page 17: 2010.09.08 - Key Considerations for the Attachments of Facades to Structures

97

Approach 2: Slab Cantilever Does Not

Resolve Eccentricity

98

Kickers

1

99

“Roll” Beams

100

Design of Steel Spandrel Beams

The design of the spandrel beam is more than

selecting a wide flange shape that meets flexural

strength and stiffness criteria.

101

General Design Considerations

� Flexural Strength

� Composite or

Noncomposite?

� Part of a Moment

Frame?

� Any weak axis

bending?

102

General Design Considerations

� Flexural Stiffness

� Precomposite DL

� Post-composite DL

� Façade load

� Superimposed DL

� Superimposed LL

� Floor vibrations

� Creep, long-term

�Weak axis loads

Page 18: 2010.09.08 - Key Considerations for the Attachments of Facades to Structures

103

General Design Considerations

� Torsion?

� Resolved at columns?

� Kickers?

� Roll beams?

� Rotation and projected

translations?

104

General Design Considerations

� Connection to

Columns

� Simple shear?

� Special copes, non

standard?

� Horizontal forces?

� Torsional forces?

105

General Design Considerations

� Spandrel dimensions

� Depth

� Flange width

� Flange thickness

� Project consistency

106

General Design Considerations

� Centerline location

� Column connections?

�Minimize façade

eccentricities?

� Clearances for

adjustments?

107

Deflection and Movement Limitations

� Curvature

� L/360, L/400, L/600,

etc.

� Absolute magnitude

for joints

� Must consider rotation

as well as vertical

deformations

108

Designing for Torsion

Page 19: 2010.09.08 - Key Considerations for the Attachments of Facades to Structures

109 110

Kickers remove torsion

111

Kickers reduce torsion –

torsion in spandrel between

kickers.

112

Roll beam reduces torsion.

Torsion in spandrel between

roll beam and columns.

113

Design approaches

� Detailed guidance on

torsional stresses and

rotations of bare steel

wide-flange shapes.

� Rotation about center

of shape.

114

Design approaches

Page 20: 2010.09.08 - Key Considerations for the Attachments of Facades to Structures

115

Center of Rotation

116

Slab Resisting Torsion

117

Effects of Rotation at Slab

118

Modified Flexural Analogy

119

Appendix A Study

� Three models� FEM

�Modified DG #9

�Modified Flex. Analogy

� Two spans� 10 ft

� 30 ft

� Two load shapes� Concentrated

� Uniform

120

Conditions with Torsion

Page 21: 2010.09.08 - Key Considerations for the Attachments of Facades to Structures

121

Options for Increasing Rotation Resistance

122

Masonry Cavity Walls

The strategy for supporting masonry cavity walls

starts with the decision for the location of the

horizontal movement joints.

123

Volume Change

124

Good Movement Joints

125

Movement Joints

126

Elevation

Strategies: Punched

Openings

Page 22: 2010.09.08 - Key Considerations for the Attachments of Facades to Structures

127

Strategies:

Strip Windows

Elevation

128

Strategies:

Shelf at Slab

Elevation

129

Vertical Movements

Design Vertical

Movements

Design Vertical

Movements

Note: Column shortening is important too for tall

building’s bottom story.

130

Top of Wall Connections

131

Plan Locations Of Hangers

132

Potential Problems

� Inadequate provisions for the shelf angle adjustment cause the masonry to have too little bearing on the shelf angle.

� Inadequate provisions for the shelf angle adjustment cause the masonry cavity to be too wide for the specified masonry ties.

� Flashing design does not accommodate projection of bolts or fasteners into the cavity at the shelf angle.

Page 23: 2010.09.08 - Key Considerations for the Attachments of Facades to Structures

133

Potential Problems

� Inadequate soft joint size causes over

compression of sealant so that it bulges out.

� Inadequate clearance between the bottom of the

shelf angle and the top of the masonry veneer

results in bearing of the shelf angle onto the

masonry due to spandrel deflections.

� Support details for the shelf angles at corners

and atypical conditions are not clearly

documented in the design.

134

Precast Concrete Wall Panels

The most important strategy for support of

precast concrete panels is to support the weight

of each panel on no more than two points.

135

General Description

136

Strategies For Support

137

Seismic Forces

138

Field Adjustability

Page 24: 2010.09.08 - Key Considerations for the Attachments of Facades to Structures

139

Fire Safing

� Approved materials

� Securely installed

� Prevents passage of

flame and hot gases.

140

Potential Problems

� Erection sequence: brackets, blockouts,

and embedment plate coordination.

� Cantilevers without sufficient stiffness

which may deflect or rotate significantly

during erection.

� Division of responsibilities for designing

and providing attachment and support

components.

141

Potential Problems� Joints in architectural elevations are not

coordinated with the points of load

application to the primary structure as

anticipated by the SER.

� Attachment details by the SSE designing

the attachments are such that the precast

panels deliver moments or otherwise load

the primary structure with eccentric loads

not anticipated by the SER designing the

primary structure.142

Potential Problems� Kickers that resolve eccentricity apply loads to lightweight roof elements, such as bar joists, which are not designed for the kicker loads and this result in unexpected rotations and flexibility of the precast support.

� Tie back connections are attached to clip angles fastened to the bottom of the bottom flange of spandrel beams without consideration to the effects on the spandrel beam.

143

Aluminum Curtain Walls

Often the most important part of the aluminum

curtain wall design is anchorage adjustability to

the base building structure.

144

Strategies for Support

� Easily accessible attachments

� Adjustability

� Limit eccentricity

� Block-outs of fire proofing

� Factory drilled bolt holes in curtain wall

� Welded field connections

Page 25: 2010.09.08 - Key Considerations for the Attachments of Facades to Structures

145

Strategies for Support

146

Movement

� Critical to performance

� 4 to 5 times frame

temperatures

� L/175 common design

for out-of-plane

� L/360 common design

for in-plane

147

Field Adjustability

148

Field Adjustability

149

Attachments

150

Potential Problems

� Large gaps between the anchors and the primary building structure can result in excessive bending stresses.

� Coordination of locations for adjustment – If vertical and horizontal adjustments are to be made solely in the attachments of the curtain wall system to the primary building structure, slotted holes must be long enough to account for all of the required adjustment.

� If the curtain wall designer is relying on adjustments being made through the primary building structure rather than his attachments, the slotted holes that are provided may be inadequate in length.

Page 26: 2010.09.08 - Key Considerations for the Attachments of Facades to Structures

151

Potential Problems

� Coordination of bolted attachments to the

primary building structure. Locations of bolt

holes for curtain wall attachment should be

coordinated with the steel fabricator so that

holes can be made in the shop. Holes should

not be burned in the field.

� Mullion splices (responsibility of the SSE) –

should properly account for volume changes and

movement of the primary building structure.

152

Key “Take-Aways”

1. The design team needs to develop a strategy, or

strategies, for supporting the façade elements from the

primary frame.

2. Given this strategy, the team needs to communicate

responsibilities and scope.

3. The SER needs to know the façade attachment strategy

and needs enough information from the façade designer

to anticipate the impact on the primary frame.

4. The SER needs to communicate the relevant frame

performance characteristics (principally deformations).

153

Key “Take-Aways”

5. The SER should strive to develop slab edge and spandrel beam designs that are consistent with the façade attachment strategy.

6. Tolerances, façade movements and frame movements need to be considered in total. Strategy and responsibility need to be clearly communicated and accepted.

7. The SER’s documents for the primary structure should indicate pertinent assumptions about façade attachment loads.

Questions?