9
2010 FIFA World Cup SAPIA readiness submission 19 May 2010

2010 FIFA World Cup SAPIA readiness submission 19 May 2010

Embed Size (px)

Citation preview

2010 FIFA World Cup SAPIA readiness submission

19 May 2010

Presentation outline

Background to the petroleum industry Critical facts about the industry

Industry’s interdependence map

2010 FIFA World Cup readiness

Risk identified and mitigating steps

Transnet Strike – Current Scenario

Potential Impact of Transnet Strike – Worst Scenario

19 May 2010

Critical facts about the industry

The industry is interdependent and shares logistic facilities such as depots, pipelines and rail

Gauteng is the biggest market and will also host the majority of the games. It is critical for the industry to ensure un-interrupted supply for this market

60% of ORTIA jet fuel supply comes from Natref via a dedicated pipeline.

40% of RSA petrol and diesel supply is sourced from inland refineries and the balance from coastal refineries and imports.

Competition commission exemption was granted to allow enhanced logistic planning for the 2010 FIFA World Cup

The industry and DoE are working together through the Ministerial Task Team (MTT) and Logistics Planning Team (LPT) primarily focusing on jet fuel readiness and cooperation on logistics

19 May 2010

The South African liquid fuels Industry interdependence

TransnetPipelinesCrude Oil

Consumer

RefineryTankfarm

CoastalRefineries

RefineryTankfarm

InlandRefineries

StorageDepots

Retail stations

SCI Sasolburg

Secunda

SynfuelsTankfarm

Road tanker

PipelineDJP

(FinalProducts)

TransnetRail

Storage

Storage

Commercial customers

TransnetPipelines

Retail station tank

SBMSingle Buoy Mooring

(Isipingo)

Roadtanker

Storage

Petrol and Diesel Critical sites identified for SWC period Credit card acceptance at critical sites Expected throughput for period to increase by

10% July prices only to be changed on 2nd

Wednesday Additional trucks & drivers secured Depots facilities to be optimised around critical

feeder sites

2010 FIFA World Cup readiness

Jet Fuel 40% increase forecasted in jet fuel

demand Stock levels at ORTIA

19 May – 9.0 days (42 634 m³) Planned end of May – 9 days

Rail from coast Rail increased from 15 RTCs to 40

per day

22 Days to

Kickoff…

Refinery Readiness Refineries status

All Refineries fully operational Jet fuel - Daily injection – 3700 m³ through pipeline from

NatrefCritical plants and equipment identified and closely

monitored Planned stock levels – 7-9 days from May

Imports Products are imported to balance demand.

Shutdowns No planned shutdowns during world cup that will impact fuel

production

Risks identified and mitigating steps

Risk Impact Mitigation

Unplanned ORTIA Jet pipeline shutdown more than 5 days

Stock of Jet depleted to

critical level (less than 3 days

stock)

Likelihood very low and ability

to recover within 2 days

Capacity to build 5 more

days stock at Natref

Unplanned DJP pipeline shutdown more than 3 days

Depots will run dry between 2-

5 days

Gantry congestion at

refineries

Work with Transnet to effect

backup plans

Direct bridging by road to

critical customers

Critical sites running dry Disrupt World Cup logistics

plan and those of soccer fans

Additional trucks and drivers

appointed

Critical maintenance calls at

sites will be closed out

Timing is a crucial factor to effecting mitigation plans for 2010 SWC kick-offTiming is a crucial factor to effecting mitigation plans for 2010 SWC kick-off

Transnet Strike – Current ScenarioUpdate

Rail and Ports are impactedRail fed depots getting full (Tarlton, Rustenburg)Sporadic market stockouts, especially ex Rail supplied depotsRefinery depot gantries – heavily congested (Secunda, Sasolburg)

Prolonged Strike Activity implies:

Dealers will go into “panic mode” – fill up tanks (2005 industry experience relived)More stockouts at service stations and depotsRefineries may shut down due to tanks being fullSupply crisis, threatening country’s economy and the WC2010 event

19 May 2010

Potential impact of Transnet strike – Worst Scenario Assumptions • All Transnet services disrupted: Port, Pipelines & Rail

• Road movement – no impact

Market Refinery

Impact ORTIA empty after 9 days

Service stations will be empty after 3-6

days

Commercial customers also impacted after

2-7 days

Chemical industries highly affected

Eskom affected limited back-up for coal

World Cup severely impacted

Natref at reduced rate for 7 days, and then

shutdown

Total Synfuels shutdown after 5-7 days

Coastal refineries will operate at reduced rate to

complete shutdown

Significant additional costs

Safety impact due to higher risk during start up and

shutdowns of plants

Environmental impact due to flaring of chemical, etc.

Contingency plans Maximize pipe & RTC deliveries to ORTIA

while still operational

Consider tankering at other airports

Allocate supply per region with approval

from DoE ( Potential Market allocation)

Reduced rate to stay online longer

Recommendation Speedy resolution of the strike

Recovery Plans Continued tankering to build up ORTIA

stocks

Push all available final product at the coast

into DJP to Gauteng for SWC

Start up of plants as soon as possible and safely (4-

7 days)

Evaluate all crude and final product import plans

CONTACT INFORMATION:

Maurice RadebeChairman

Office Address: Shanghai House, 52 Wierda Road West, Wierda Valley, Sandton, South Africa

Tel: +27 (0)11 783 7664Fax: +27 (0)11 783 5400

Email: [email protected]