Upload
wesjam777
View
224
Download
0
Embed Size (px)
Citation preview
8/3/2019 2010 Bridging 4pp
http://slidepdf.com/reader/full/2010-bridging-4pp 1/4
Electronics Manufacturing Plant, Juarez, Mex
Poly Canyon Village at Cal Poly, San Luis Obispo High End Multi-Story Co-op, Atlanta, Geo
Georgia Tech’s New Campus at Savannah
Bridging Reducing the Owner’s risks and costs in quality construct
8/3/2019 2010 Bridging 4pp
http://slidepdf.com/reader/full/2010-bridging-4pp 2/4
Details about the projects shown on the cover
Georgia Tech’s New Campus at Savannah. 3 Buildings Brookwood was both designer (Owner’s Design Consultant)
and the Owner’s Development Manager. The original budget or construction was $21,155,860. However, the price came
in at $19,643,685 with competitive bids based on the Bridging Contract Documents (BCDs). There were no Contractor
initiated change orders and no claims against the Owner (The University Financing Foundation, a 501c3). The acility is
leased to Georgia Tech which has the right to purchase.
Poly Canyon Village at Cal Poly, San Luis Obispo , Brookwood Group frst provided consultation on project
procurement methods and fnancing plus ull Program Management. Project has been very successul with students as
well as in all other respects. Bridging type contract was awarded in amount o the original project budget with several
betterments including LEED Gold included in the price. Cal Poly exec points out that the project was completed “on spec,on budget, on schedule” with no contractor initiated change orders.
Electronics Manuacturing Plant, Juarez, Mexico , Brookwood provided Development Management including site
procurement, design services (Owner’s Design Consultant) and project management or Scientifc Atlanta (now part o
Cisco Systems).. The frst hal o the space (50K s) was occupied 7 months ater the client frst discussed the project with
Brookwood. Remaining 50K s was occupied 3 months later. Original budget: $8mm. Contract award price (competitive
bids on BCDs): $7,346,800. One Contractor initiated change order: $38,310. No delays or costs to the Owner or fxing
several minor “bugs” discovered ater occupancy.
High End Multi-Story Co-op, Atlanta, Georgia , The Wakefeld in the Buckhead area o Atlanta. Brookwood owners
were the developers. Brookwood carried out the design as the Owner’s Design Consultant as well as ull Development
Management including site search/purchase, arranging fnancing, carrying out marketing, and management o
construction. Project was completed in 16 months on schedule. Contract award price:$15,183,000. One Contractor
initiated change order: $8,400. No claims against Owner (Developer). There were several “bugs” promptly corrected by
Contractor at no cost to owners.
The Bridging Method
Bridging is the only project delivery method that provides the owner with a fxed, “all up” price orthe construction with the Owner having only about hal o typical design time and design costs atrisk.
In act, it is the only method that will provide those Owners who cannot rely upon relationships in procuring
construction a dependable price based on less than 100% complete “working drawings and specications”.
The construction price under Bridging, when properly executed, is not only as dependable or the Owneras a price based on nal Contract Documents under the traditional Design-Bid-Build method, it is moredependable because the Owner’s exposure to unexpected change orders due to errors or omissions in thenal “working drawings” and specications is dramatically reduced. All too oten, change orders amountto more than was budgeted or them. In projects carried out by Brookwood Group using Bridging, totalcontractor-initiated change orders have not exceeded 1% o the contract price on any project, with theaverage being under 0.3% o the contract price.
Bridging usually saves 4-5% or more in contract prices anddramatically reduces:
unexpected high Change Order costs.•
claims against the Owner.•
delays/costs/disputes or fxing the ever present post•
construction “bugs”.
Construction also goes aster and smoother under Bridging, andadditional acceleration procedures work easily with this method.
Yet all o these advantages or the project owner are realized withBridging without any loss o :
opportunity or creativity.•
control o design.•
control o design details.•
quality o engineering.•
quality o construction.•
BRIDGING ORG CHART
LINES OF REPORTING
CONTRACT LIINES
INTERNAL or EXTERNAL
OWNER
DESIGN-BUILD
CONTRACTOR
CONTRACTOR’S
AE
OWNER’S
PROGRAM
MANAGER
OWNER’S
DESIGN
CONSULTANT
8/3/2019 2010 Bridging 4pp
http://slidepdf.com/reader/full/2010-bridging-4pp 3/4
How the Bridging Method WorksStep 1: A designer or design team isselected as the Owner’s Design Consultant(“ODC”), sometimes reerred to as the“Bridging Architect” (Figure 1). TheODC goes through Schematic Design in
the same way an architect would do intraditional design services, with reviewsand approvals by the Owner. Typically, theproject budget and schedule would alsobe reconrmed at this point (Figure 2).
Step 2. In this phase the ODC with its consulting engineers as well as the Program Manager (i there is one) preparesthe Bridging Contract Documents (“BCDs”). While this will typically require about the same level o eort as thepreparation o “Design Development” documents required in the traditional Design-Bid-Build method, BCDs are quitedierent rom “DD” documents. They will be much more complete in many aspects, usually the architectural, andmuch less complete in others, typically some elements o the engineering. However, i the BCDs are properly preparedollowing Bridging methodology, the contract provides highly dependable protection o the design intent and o thecontract price. In Bridging this is achieved with a design-build type o contract as opposed to a traditional constructioncontract, though Bridging is not Design-Build in the way Design-Build is typically carried out. (Figure 3).
Step 3. The Owner can then receive competitive, xed-price proposals based on the BCDs or the ull project or a 2-stepaward contract. In this way the Contractor (who has its own architects/engineers by sub-contract or as employees) hasthe complete responsibility or both the construction and the nal drawings and specications and their being incompliance with the BCDs and or their completeness, accuracy and code compliance.
Step 4. I the Owner is now readyto proceed, the Owner would thenauthorize the preparation o Con-struction Documents (“CDs”) by theContactor and its AEs. As this work proceeds the ODC will review thesedocuments or compliance with theBCDs.
Step 5. Upon proper completion o the CDs, the Owner may proceed withthe construction or terminate thecontract with the Contractor withoutcause by payment or the CDs. The CDsthen belong to the Owner. I Ownerchooses to proceed construction isauthorized.
Step 6. During the construction theODC and Program Manager (i thereis one) would also represent theOwner with on-site observation o the work, seeing that construction is
in compliance with both the CDs andthe BCDs, authorizing the monthlyprogress payments and nal paymentto Contractor.
These Bridging Contract Documents(Figure 3) must ully protect the design,the quality, and the Owner fnancially,while allowing the proposing contractor as much latitude as is prudent in order toget the best price.
Bridging may also be easily combined with CM-at-Risk for better results from
CM-at-Risk.
BRIDGING METHOD
* laboratory, medical, detention, scientific, information technology, etc.
Finish Hardware
Specialty Hardware,Equipment & Details *
HVAC System
Fire Protection System
Plumbing System
Electrical Systems
Lighting Fixtures,Switches/Outlets, Etc.
Cabinetwork
Elevators
Interior Finishes(with Schedule)
Site Development
Foundations
Internal Structure ofExterior Wall Construction
Floor & Ceiling PlansBuilding Sections
Doors & Windows(With Schedules)
Structure, Floor& Roof Systems
Architectural Ext. Design/
Controlling Details
Other Details
Plumbing Fixtures
Security Electronics
Supply & Return Grilles
Equal toSD & DDEqual toSD & DD
100%CD
0 10 30 60 80 100%20 70 905040
8/3/2019 2010 Bridging 4pp
http://slidepdf.com/reader/full/2010-bridging-4pp 4/4BR-HE-101001-ASD
Bridging Protects the Owner Better Than Other MethodsBridging solves problems that owners oten encounter with the three most commonly used project delivery methods (“Design-Bid-Build”, “Design-Build” and “CM-at-Risk”). While all three o these methods have advantages, they each have serious aws in terms o protecting the best interests o the Owner (and/or User). The pros and cons o each are discussed below.
Advantages: Logical and orderly process, well understood throughout the industry. Ownerhas a rm price based on complete contract documents beore authorizing construction.Architect and Engineers have direct proessional relationship with the Owner.
Disadvantages: Takes too long and costs the Owner too much to obtain a reasonablydependable total price. Method assumes that architects and engineers have the bestknowledge o construction methods and costs, which is rarely the case. Assumes that theContract Documents (nal drawings and specications) are ree o errors and omissions,which is humanly impossible.
Advantages:Contractor brings construction know-how to the design process rom the outsetand has ull responsibility or both the design and the construction
Disadvantages: There is a clear and serious conict-o-interest between the Owner and theArchitect and Engineers. GMPs issued on less than 100% complete working drawings andspecications are not contractually enorceable. Under this method it is oten difcult or theOwner to obtain true competition on price or ully equivalent quality and details.
Advantages: Contractor (“CM”) enters the process relatively early so as to provide costing,scheduling and construction method inormation to the Owner’s Architect and Engineerswhile design is still in development. Contractor is compensated by ee and obtainscompetitive prices rom subs. Contractor provides a “Guaranteed Maximum Price” (GMP) atone or more points during the design process.
Disadvantages: A GMP based on less than 100% complete drawings and specications isnot contractually enorceable and can be misleading to the Owner. In many cases therecan be a conict due to the “CM” using the same subs on other projects concurrently withthe CM serving as traditional general contractor on the other project.
LINES OF REPORTING
CONTRACT LIINES
INTERNAL or EXTERNAL
CM-at-RISK
OWNER
CM-at-RISK
OWNER’S
PROGRAM
MANAGER
ARCHITECT& ENGINEERS
LINES OF REPORTING
CONTRACT LIINES
INTERNAL or EXTERNAL
DESIGN BUILD
OWNER
DESIGN-BUILD
CONTRACTOR
OWNER’S
PROGRAM
MANAGER
ARCHITECT& ENGINEERS
GMP Final Confirmation
CM CONSULTS LONG LEADSGMP
The Bridging method o construction project delivery was developed primarily by George T. Heery FAIA RIBA FCMAA, Chairmano Brookwood Group. The name “Bridging” was originally coined in August o 1989 by S. Shepherd Heery, now President/CEOo Brookwood Group, who pointed out that the method “bridged” over many o the problems that Owners oten encounter indesign and construction programs. For more inormation on Bridging go to www.BridgingMethod.com where more inormation
can also be ound on Bridging/CM-at-Risk in the Downloads section.
DESIGN BID BUILD
LINES OF REPORTING
CONTRACT LIINES
INTERNAL or EXTERNAL
OWNER
CONTRACTOR
OWNER’S
PROGRAM
MANAGER
ARCHITECT& ENGINEERS