RAPAT KOORDINASI PENGELOLAAN BANJIR SEMARANG DIREKTORAT PENGAIRAN DAN IRIGASI KEMENTERIAN NEGARA PPN/BAPPENAS JAKARTA, 21 APRIL 2009

20090421 Pendahuluan Banjir Semarang

Embed Size (px)

DESCRIPTION

drainase

Citation preview

Logs PowerPoint Template

RAPAT KOORDINASIPENGELOLAAN BANJIR SEMARANGDIREKTORAT PENGAIRAN DAN IRIGASI KEMENTERIAN NEGARA PPN/BAPPENASJAKARTA, 21 APRIL 20091AGENDA RAPATPEMBUKAAN DAN PENGANTAR DISKUSI PEMBAHASAN LOAN IP-534PEMBAHASAN GRANT INA 384-3DISKUSI DAN TANYA JAWABKESIMPULAN RAPAT2PENGANTAR DISKUSIBencana banjir Januari Februari 2009 berdampak pada wilayah Pantura, khususnya Kota Semarang dan sekitarnyaPerkiraan kerugian (sementara) banjir di wilayah Pantura tahun 2009:

SektorPerkiraan KerusakanPerkiraan Kerugian (Pantura Jawa)Perkiraan Kerugian(Jawa Tengah)Transportasi (Jalan)69,8 kmRp. 145,1 MRp. 97,6 MPerumahan17.330 unitRp. 141,8 MRp. 115 MPertanian18.378 haRp. 1,3 TRp. 476,4 MSumber Daya Air tersebarRp. 223,15 MRp. 133,9 MTOTALRp. 1,180 MRp. 822,9 MSumber: Dit. KKDT, Bappenas, 2009Penanganan banjir Semarang dan sekitarnya merupakan masalah mendesak dan menjadi prioritas pemerintah. Beberapa proyek pengendalian banjir di wilayah Semarang saat ini a.l. Loan IP-534 IWRFMP dan Hibah INA 384-3 3

LOKASI IWRFMP (IP-534)USULAN LOKASI POLDER SEMARANG4INTEGRATED WATER RESOURCES AND FLOOD MANAGEMENT PROJECT FOR SEMARANG (IP-534)TUJUAN:Menyediakan air baku untuk masyarakat dan industri, melindungi daerah rawan banjir (termasuk peningkatan sistem drainase) di Kota SemarangBIAYA: 16,302 juta (US$ 98,23 juta)DURASI:8 Tahun (Maret 2006 Desember 2013)PELAKSANA:Ditjen Sumber Daya Air dan Ditjen Cipta Karya, Dep. PULOKASI:Kota Semarang dan sekitarnya STATUS:Proyek telah berlangsung empat tahun dari rencana 8 tahun5KOMPONEN KEGIATAN IWRFMP (IP-534)Component A: West Floodway/Garang River Improvement Works (10/2008 04/2012)

Sub-component A-1West Floodway/Garang River Improvement (Section -0.628km to 4.908km and 5.086km to 9.517km (9,607m)

2. Sub-component A-2Flood monitoring facilities

3.Sub-component A-3Rehabilitation of Simongan Weir (Section 4.908km to 5.086km)

4.Sub-component A-4Raising of Railway Bridge over West Floodway (3.700km) subject to the approval of DGWR, MPW, and DG of Railway, Ministry of Transportation (MoT)PROGRES KEGIATAN6KOMPONEN KEGIATAN IWRFMP (IP-534)Component B: Jatibarang Multipurpose Dam Construction (10/2008 04/2012)

Sub-component B-1Dam Body including Appurtenant Structures ConstructionOperation and Maintenance Building and Goa Kreo Bridge Construction

2. Sub-component B-2Procurement and installation of hydropower station

3.Sub-component B-3Community based Conservation of Greenbelt area and Pilot Project for Improvement of Catchment area

PROGRES KEGIATAN7KOMPONEN KEGIATAN IWRFMP (IP-534)Component C: Urban Drainage System Improvement Works (12/2008 06/2012)

Sub-component C-1Semarang River Improvement work

2. Sub-component C-2Asin Drainage System Improvement work

3.Sub-component C-3Bandarharjo Drainage System Improvement work

PROGRES KEGIATAN8KOMPONEN KEGIATAN IWRFMP (IP-534)Component D:Consulting Services (12/2006 12/2012)

Sub-component D-1 Water Resources (DGWR)Pre-construction Stage process for Component A and B2. Construction Stage process for Component A and B3. Transfer of Knowledge process for Component A and B4. Non-structural Measures for Disaster Management process for Component A and B5. Non-structural Measures for Watershed Management process for Component A and B

2. Sub-component D-2.1 Urban Drainage (DG Cipta Karya)Pre-construction Stage for Component CConstruction Stage for Component CTransfer of Knowledge for Component CNon-structural Measures for Urban Drainage and Water Supply

Sub-component D-2.2 Water Supply (DG Cipta Karya)1. Transfer of Knowledge for Component C2. Study on Water Supply

PROGRES KEGIATAN9PROGRES IMPLEMENTASI IWRFMP IP-534Pelaksanaan proyek mengalami kendala terkait proses pembebasan lahan, audit, dan koordinasi antarinstansi.Terdapat backlog sebesar 5,7 persen (dari target komulatif 2008 sebesar USD 9,72 juta baru terealisasi USD 4,11 juta) *)Total penyerapan proyek hanya 4,2 persen dalam waktu 4 tahun (waktu terpakai 26,9 persen) *)Diperlukan evaluasi dan koordinasi di Pusat untuk menyelesaikan masalah dan mempercepat pelaksanaan proyek. *) Sumber: Monitoring PHLN Dep. PU, Desember 200810HIBAH PEMERINTAH BELANDAKerjasama Indonesia-Belanda melalui Partners for Water, a.l melalui hibah INA 384-3 Development Pilot Polder Semarang and Guideline Polder Development.Hibah ini mengusulkan penanganan polder di Kali Banger.Bentuk kegiatan a.l. pembuatan tanggul, pompa, bendung, pengerukan, retention basin dan kegiatan lain.

11

USULAN KEGIATAN PROYEK POLDER SEMARANG12PROGRES INA 384-3Studi telah menghasilkan usulan detail desain dan konsep O&M. Total usulan biaya (base cost) sebesar Rp 78,8 M (USD 7,16 juta).Diperlukan kesepakatan di internal Pemerintah dan Pemerintah Daerah mengenai tindak lanjut pelaksanaan proyek, antara lain:Sumber pendanaan (APBN, APBD, atau Loan)Implementation Arrangement (koordinasi, instansi pelaksana, sharing pembiayaan)Proses sosialisasi dan pengusulan proyekPotensial lender antara lain dari JICA dan Pemerintah Belanda (apabila menggunakan loan) 13PENGANTAR DISKUSILaporan dan Presentasi:Detail progres kegiatan IWRFMP Usulan Polder SemarangPembahasan tindak lanjut percepatan implementasi proyek IWRFMP Semarang Pembahasan rencana pengelolaan Polder Semarang (Kali Banger)Upaya integrasi kegiatan dan dukungan instansi terkaitRencana tindak selanjutnya

14SELESAI

Selamat Berdiskusi15