Upload
lenhu
View
215
Download
2
Embed Size (px)
Citation preview
bere:architects
73 Poets Road
London N5 2SH
T +44(0)20 7359 4503
www.bere.co.uk
Building Better Buildings / UCL / Technology Strategy Board / Zero Carbon HubMonday, 15th February 2016
2 x BPE studies of Passivhaus domestic projects
Justin Bere twitter: @jbere @berearchitects | www.bere.co.uk
PRESENTATION INCLUDES CONTENT FUNDED BY THE TECHNOLOGY STRATEGY BOARD’S
BUILDING PERFORMANCE EVALUATION PROGRAMME http://goo.gl/ny5vG
bere:architects The Muse54A Newington GreenLondon N16 9PX T +44 (0)20 7241 1064www.bere.co.uk
c b
ere:
arch
itect
s 20
16
Introduction
bere:architects participated in 3 BPE projectsthat were funded by the Technology Strategy Board;
(1) Camden House (domestic)(2) Ebbw Vale social housing (domestic)(3) Mayville / Mildmay Centre (non-domestic)
This presentation focuses on the 2 domestic research projects
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
But fi rst, why I wanted to do the BPE projects:
At the time, we were completing some of the UK’s first Passive House buildings... I wanted:
• To know if our buildings were performing OK• To know if our buildings were healthy• To record occupant responses to their homes• To record whether PH methods “work in the UK”• To know if we could do better next time• Results with veracity given by academic partners
I was hopeful of good results, and I wanted to use the results to influence government, industry and the general public; To encourage them to put together a proper National Plan to address the environmental problems that the human species is causing through careless negligence.
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Camden Passivhaus
PROJECT LEAD: BERE:ARCHITECTS BPE PROJECT PARTNER: UNIVERSITY COLLEGE LONDON DR IAN RIDLEY, LEAD RESEARCHER SAMUEL STAMP, CO-HEATING & FABRIC TESTS WITH DR HECTOR ALTAMIRANO & DR BOB LOWE TSB EVALUATOR: IAN MAWDITT TSB LEAD: FRANK AINSCOW
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Camden Passivhaus
PROJECT LEAD: BERE:ARCHITECTS BPE PROJECT PARTNER: UNIVERSITY COLLEGE LONDON DR IAN RIDLEY, LEAD RESEARCHER SAMUEL STAMP, CO-HEATING & FABRIC TESTS WITH DR HECTOR ALTAMIRANO & DR BOB LOWE TSB EVALUATOR: IAN MAWDITT TSB LEAD: FRANK AINSCOW
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Camden Passivhaus
Ground fl oor plan First fl oor plan
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Camden Passivhaus
Ground floor slab 380mm wood fibre insulation
Walls 280mm mineral wool +100mm
wood fibre insulation
Flat roof 280mm PUR + 120mm mineral
wool insulation
Sloping roof 380mm mineral wool insulation
Terrace 130mm PUR insulation
Heat Recovery Ventilation PAUL Thermos 200DC
Building specification:
Section
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Fabric Performance Data - first BPE results
Design targets
0.6h-1 ACH @50Pa max
0.6h-1 ACH @50Pa max
63.6W/K
Ground slab 0.103W/m2K
Lower wall 0.122W/m2K
0.01W/mK at each
junction
Analysis
Blower door test
Tracer gas tests
Co-heating tests
In-situ U-value heat fl ux
measurements
Thermal bridge analysis
Measured performance
0.44h-1 ACH @50Pa
0.38 ±0.08h-1
35±15W/K (too much sun)
56±5W/K (Sam Stamp’s 2nd test)
0.099±0.013 W/m2K
0.097±0.020 W/m2K
specifi c junction
testing not possible but
analysed with infra-red
thermography
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Fabric Performance Data - first BPE results
“The indication is that the Camden Passivhaus is one of only a few co-heating tested dwellings that meets its design intent.”
“This is a positive refl ection on the design and build quality of the house and is especially encouraging considering the low heat loss that was targetted here.”
Samuel Stamp, UCL Energy PhD research student
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Energy consumption - Specific Heat Demand
(Design target)13.7 kWh/m2Specifi c space heating demand
(Measured performance)12.1 kWh/m2
Camden Passivhaus space heating demand compared to the UK existing housing stock
* Benchmark taken from DomEARM
**
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Energy consumption - Electricity demand
Predicted electricity consumption
Monitored electricity consumption
Occupants away on skiing trip
Solar pump running Solar pump running continuously - fi xed in late continuously - fi xed in late January ‘12January ‘12
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Energy consumption - Electricity & Heat
DHW17%
Space heating25%
Lighting11%
Boiler and pumps16%
Sockets, blinds,appliances
25%
HRV5%
Predicted energy demand
DHW25%
Space heating27%
Lighting4%
Boiler and pumps6%
Sockets, blinds,appliances
32%
HRV6%
Measured energy demand
Solar pump
running
continuously
(fi xed in late
January ‘12)Lights on during the day!
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Monitored vs. predicted space heating demand
Energy consumption - Performance gap?
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Energy consumption - Comparison
Annual energy performance compared with benchmarks (DomEARM)
Annual CO2 emissions compared with benchmarks (DomEARM)
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Energy consumption - Comparison
90
80
72
65 63
0
10
20
30
40
50
60
70
80
90
100
BedZed The Long House One Brighton Camden Passivhaus Princedale Road
kWh/m
2
Total gas and electricity consumption of UK domestic low-energy exemplars
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Comfort - Psychrometric charts - winter
Average daily temperatures
living room 21 - 22 oC
bedroom 19.6 - 20.4 oC
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Comfort - Winter temperatures
5
0
5
10
15
20
25
Tempe
rature
(OC)
Date
Thermal comfort in January
Living room
Bedroom
External
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Comfort - Psychrometric charts - summer
Average daily temperatures
living room 23.5 -24.5 oC
bedroom 21 - 22 oC
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Comfort - Summer temperatures
5
10
15
20
25
30
Tempe
rature
(OC)
Date
Thermal comfort in June
Living roomBedroomExternal
Comparison of PHPP predicted and actual annual overheating
8 8
4
0
2
4
6
8
10
12
14
PHPP predicted Actual (>25C) Actual (>26C)
Overheatin
g%
PHPP LIMIT
8
5
3
0
2
4
6
8
10
12
14
PHPP predicted Actual (>25C)
Overheatin
g%
Oct Mar
Summer (Jun Sep)
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Comfort - BUS overall comfort
ComfoverUnsatisfactory :1 7: Satisfactory
0 10 20 30 40 50 60 70 80 90 100
Percentile
Unsatisfactory: 1
2
3
4
5
6
Satisfactory: 7
20406080
^
v
Comfover
© BUSMethodology 2011 A
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Comfort - Interior air quality
Average CO2 concentration
living room average 667ppm
bedroom average 717ppm
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Comfort - BUS perceived health
HealthLess healthy :1 7: More healthy
0 10 20 30 40 50 60 70 80 90 100
Percentile
Less healthy: 1
2
3
4
5
6
More healthy: 7
20406080
^
v
Health
© BUSMethodology 2011 A
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Lime House - timber framed passivhaus, Ebbw Vale
Lime House, Ebbw Vale
PROJECT LEAD: BERE:ARCHITECTS BPE PROJECT PARTNER: UNIVERSITY COLLEGE LONDON DR IAN RIDLEY, LEAD RESEARCHER CARDIFF UNIVERSITY, CO-HEATING & FABRIC TESTS TSB EVALUATOR: IAN MAWDITT TSB LEAD: FRANK AINSCOW
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Lime House - timber framed passivhaus, Ebbw Vale
Larch House, Ebbw Vale
PROJECT LEAD: BERE:ARCHITECTS BPE PROJECT PARTNER: UNIVERSITY COLLEGE LONDON DR IAN RIDLEY, LEAD RESEARCHER CARDIFF UNIVERSITY, CO-HEATING & FABRIC TESTS TSB EVALUATOR: IAN MAWDITT TSB LEAD: FRANK AINSCOW
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Detailing for a really
draught-free building
Window / wall junction
Eaves detail
General arrangement airtightness strategy drawing
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Progressively staged detailed drawings
Window Jamb Progress Detail Stage 01 Window Jamb Progress Detail Stage 02
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Progressively staged detailed drawings
Window Jamb Progress Detail Stage 04 Window Jamb Progress Detail Stage 03
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Risk management
Wall / fl oor slab detail
Intermediate fl oor detail
Good collaborative approach with site manager
allowed risks to be identifi ed early
Services penetrations
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Never assume!
BT engineer compromised airtightness layer
with incorrect installation; visiting on a day
that the site manager wasn’t on site!
Thermal Image of BT point
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Careful design and commissioning of services
Frost protection unit
Ventilation unit(Paul Focus)
Intake duct
Extract duct
Heat recovery ventilation unit located in the cupboard on the ground fl oor in the Larch house
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Heat recovery ventilation - filter maintenance
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
What we were aiming for
Lime House
Larch House
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Electricity consumption compared to typical
B.14) Time profile of electricity Consumption compared to EST average (Larch)
Average hourly profile of Electricity Consumption with average UK (EST study) profile
0
200
400
600
800
1000
1200
0:00
2:00
4:00
6:00
8:00
10:0
0
12:0
0
14:0
0
16:0
0
18:0
0
20:0
0
22:0
0
Time
W
Larch House EST typical UK Larch excluding Cooker
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Electricity consumption & generation - summer
B.17) Time Profile of average PV generation, Export and Grid Import (Larch)
Average hourly profile of PV system
0
200
400
600
800
1000
1200
1400
1600
1800
2000
0:00
:00
2:00
:00
4:00
:00
6:00
:00
8:00
:00
10:0
0:00
12:0
0:00
14:0
0:00
16:0
0:00
18:0
0:00
20:0
0:00
22:0
0:00
Time
W
Generated Exported Total Consumption Imported
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Electricity consumption & generation - winter
A.18 Time Profile of average PV generation, Export and Grid Import (Lime)
Average hourly profile of PV system Winter
0
200
400
600
800
1000
0:00:0
02:0
0:00
4:00:0
06:0
0:00
8:00:0
010
:00:00
12:00
:0014
:00:00
16:00
:0018
:00:00
20:00
:0022
:00:00
Time
W
Generated Exported Total Consumption Imported
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Excellent air quality results - Lime House
05101520253035404550556065707580859095
100105
12/11/20
1210
:45
12/11/20
1223
:45
13/11/20
1212
:45
14/11/20
1201
:45
14/11/20
1214
:45
15/11/20
1203
:45
15/11/20
1216
:45
16/11/20
1205
:45
16/11/20
1218
:45
17/11/20
1207
:45
17/11/20
1220
:45
18/11/20
1209
:45
18/11/20
1222
:45
19/11/20
1211
:45
20/11/20
1200
:45
20/11/20
1213
:45
21/11/20
1202
:45
21/11/20
1215
:45
22/11/20
1204
:45
22/11/20
1217
:45
23/11/20
1206
:45
23/11/20
1219
:45
24/11/20
1208
:45
24/11/20
1221
:45
25/11/20
1210
:45
25/11/20
1223
:45
26/11/20
1212
:45
27/11/20
1201
:45
27/11/20
1214
:45
28/11/20
1204
:05
28/11/20
1217
:05
29/11/20
1206
:05
29/11/20
1219
:05
30/11/20
1208
:05
30/11/20
1221
:05
01/12/20
1210
:05
01/12/20
1223
:05
02/12/20
1212
:05
03/12/20
1201
:05
03/12/20
1214
:05
04/12/20
1203
:05
04/12/20
1216
:05
05/12/20
1205
:05
05/12/20
1218
:05
06/12/20
1207
:05
06/12/20
1220
:05
07/12/20
1209
:05
07/12/20
1222
:05
08/12/20
1211
:05
09/12/20
1200
:05
09/12/20
1213
:05
10/12/20
1202
:05
Relativ
ehu
midity
(%)
Date (time)
Lime House Interior Relative Humidity (%) 12th November 2012 10thDecember 2012
Living room RH
Master bed RH
Downstairs bathroom RH
Upstairs bath RH
Note: the couple in the Lime house has a new born baby'drying clothes several times a day' .The RH spikes which occur in the bathrooms duringshowers decrease fast, due to adequate ventilation.
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Excellent air quality results - Larch House
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
12/11/2012
10:45
12/11/2012
23:45
13/11/2012
12:45
14/11/2012
01:45
14/11/2012
14:45
15/11/2012
03:45
15/11/2012
16:45
16/11/2012
05:45
16/11/2012
18:45
17/11/2012
07:45
17/11/2012
20:45
18/11/2012
09:45
18/11/2012
22:45
19/11/2012
11:45
20/11/2012
00:45
20/11/2012
13:45
21/11/2012
02:45
21/11/2012
15:45
22/11/2012
04:45
22/11/2012
17:45
23/11/2012
06:45
23/11/2012
19:45
24/11/2012
08:45
24/11/2012
21:45
25/11/2012
10:45
25/11/2012
23:45
26/11/2012
12:45
27/11/2012
01:45
27/11/2012
14:45
28/11/2012
04:05
28/11/2012
17:05
29/11/2012
06:05
29/11/2012
19:05
30/11/2012
08:05
30/11/2012
21:05
01/12/2012
10:05
01/12/2012
23:05
02/12/2012
12:05
03/12/2012
01:05
03/12/2012
14:05
04/12/2012
03:05
04/12/2012
16:05
05/12/2012
05:05
05/12/2012
18:05
06/12/2012
07:05
06/12/2012
20:05
07/12/2012
09:05
07/12/2012
22:05
08/12/2012
11:05
09/12/2012
00:05
09/12/2012
13:05
10/12/2012
02:05
Relativ
ehu
midity
(%)
Date (time)
Larch House Interior Relative Humidity (%) 12th Nov 10th Dec 2012
Living room RH
Master bed RH
Bedroom 3 RH
Upstairs bath RH
©be
re:architects2
012
clothe
sdrying
inthe
airin
gcupb
oard
and
intheup
stairs
bathroom
theRH
inthebathroom
drop
sfasta
fter
show
ers,
with
adeq
uate
ventilatio
n
masterb
edroom
RHspikes
possiblydu
eto
thewindo
ws
beingop
ened
masterb
edroom
RHspikes
possiblydu
eto
thewindo
wsbe
ing
open
ed
* the clothes drying in the bathroom have a lower impact on the internal RH than the showers
* the occasional spikes in RH due to showers, and drying the clothes are quickly cleared by the ventilation system
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Return on investment - if energy prices stable
Code 6 Passivhaus - PAYS BACK THE CAPITAL COST!
Code 5 Passivhaus
Code 4 Passivhaus
Building Regulations minimum standard
50 years
£35,000difference in build-cost inestate quantities
£75,000difference in 50yr value
£180,000
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Return on investment - if 5% energy price-rise
Code 6 Passivhaus - PAYS BACK THE CAPITAL COST!
Code 5 Passivhaus
Code 4 PassivhausBuild
ing Regulatio
ns minim
um standard
50 years
£35,000difference in build-cost inestate quantities
£170,000difference in 50year value!
£300,000
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Return on investment - if 10% energy price-rise
Code 6 Passivhaus
Code 5 PassivhausCode 4 Passivhaus
Buildin
g R
egula
tions
min
imum
sta
ndard
50 years
£35,000difference in build-cost inestate quantities
£870,000difference in 50year value!
£1000,000
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
What did I learn from the BPE projects?
Reassurance that some of the UK’s first PH buildings...
• Were performing OK• Were closing the Performance Gap• Were healthy for occupants and for the environment• Occupants loved living in them• PH methods do indeed “work in the UK”
Also:• I got to learn a huge amount from academic partners• I gained massive respect for the work of BPE academics - their work should be a national priority, and funded as such!• I learnt that we can have a Zero Carbon Britain...• I got ideas of the next steps towards this goal.
c b
ere:
arch
itect
s 20
16
c b
ere:
arch
itect
s 20
16
Footnote
The very encouraging results of our BPE work, lead me to believe that it is possible, as a nation, to respond effectively to the climate change emergency.
If we inspire intelligent, responsible young people to join and lead the construction industry, and if we have a more responsible political environment, and a responsible attitude towards population growth, then we can build and retrofit both domestic and non-domestic buildings that will be capable of working successfully in a 100% renewable energy grid, along with electric transport and other aspects of daily life.
c b
ere:
arch
itect
s 20
16