42
bere:architects Building Better Buildings / UCL / Technology Strategy Board / Zero Carbon Hub Monday, 15th February 2016 2 x BPE studies of Passivhaus domestic projects Justin Bere twitter: @jbere @berearchitects | www.bere.co.uk PRESENTATION INCLUDES CONTENT FUNDED BY THE TECHNOLOGY STRATEGY BOARD’S BUILDING PERFORMANCE EVALUATION PROGRAMME http://goo.gl/ny5vG bere:architects The Muse 54A Newington Green London N16 9PX T +44 (0)20 7241 1064 www.bere.co.uk

2 x BPE studies of Passivhaus domestic projects±0.020 W/m 2K specifi c junction testing not possible but analysed with infra-red thermography c bere:architects 2016 Fabric Performance

  • Upload
    lenhu

  • View
    215

  • Download
    2

Embed Size (px)

Citation preview

bere:architects

73 Poets Road

London N5 2SH

T +44(0)20 7359 4503

www.bere.co.uk

Building Better Buildings / UCL / Technology Strategy Board / Zero Carbon HubMonday, 15th February 2016

2 x BPE studies of Passivhaus domestic projects

Justin Bere twitter: @jbere @berearchitects | www.bere.co.uk

PRESENTATION INCLUDES CONTENT FUNDED BY THE TECHNOLOGY STRATEGY BOARD’S

BUILDING PERFORMANCE EVALUATION PROGRAMME http://goo.gl/ny5vG

bere:architects The Muse54A Newington GreenLondon N16 9PX T +44 (0)20 7241 1064www.bere.co.uk

c b

ere:

arch

itect

s 20

16

Introduction

bere:architects participated in 3 BPE projectsthat were funded by the Technology Strategy Board;

(1) Camden House (domestic)(2) Ebbw Vale social housing (domestic)(3) Mayville / Mildmay Centre (non-domestic)

This presentation focuses on the 2 domestic research projects

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

But fi rst, why I wanted to do the BPE projects:

At the time, we were completing some of the UK’s first Passive House buildings... I wanted:

• To know if our buildings were performing OK• To know if our buildings were healthy• To record occupant responses to their homes• To record whether PH methods “work in the UK”• To know if we could do better next time• Results with veracity given by academic partners

I was hopeful of good results, and I wanted to use the results to influence government, industry and the general public; To encourage them to put together a proper National Plan to address the environmental problems that the human species is causing through careless negligence.

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Camden Passivhaus

PROJECT LEAD: BERE:ARCHITECTS BPE PROJECT PARTNER: UNIVERSITY COLLEGE LONDON DR IAN RIDLEY, LEAD RESEARCHER SAMUEL STAMP, CO-HEATING & FABRIC TESTS WITH DR HECTOR ALTAMIRANO & DR BOB LOWE TSB EVALUATOR: IAN MAWDITT TSB LEAD: FRANK AINSCOW

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Camden Passivhaus

PROJECT LEAD: BERE:ARCHITECTS BPE PROJECT PARTNER: UNIVERSITY COLLEGE LONDON DR IAN RIDLEY, LEAD RESEARCHER SAMUEL STAMP, CO-HEATING & FABRIC TESTS WITH DR HECTOR ALTAMIRANO & DR BOB LOWE TSB EVALUATOR: IAN MAWDITT TSB LEAD: FRANK AINSCOW

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Camden Passivhaus

Ground fl oor plan First fl oor plan

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Camden Passivhaus

Ground floor slab 380mm wood fibre insulation

Walls 280mm mineral wool +100mm

wood fibre insulation

Flat roof 280mm PUR + 120mm mineral

wool insulation

Sloping roof 380mm mineral wool insulation

Terrace 130mm PUR insulation

Heat Recovery Ventilation PAUL Thermos 200DC

Building specification:

Section

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Fabric Performance Data - first BPE results

Design targets

0.6h-1 ACH @50Pa max

0.6h-1 ACH @50Pa max

63.6W/K

Ground slab 0.103W/m2K

Lower wall 0.122W/m2K

0.01W/mK at each

junction

Analysis

Blower door test

Tracer gas tests

Co-heating tests

In-situ U-value heat fl ux

measurements

Thermal bridge analysis

Measured performance

0.44h-1 ACH @50Pa

0.38 ±0.08h-1

35±15W/K (too much sun)

56±5W/K (Sam Stamp’s 2nd test)

0.099±0.013 W/m2K

0.097±0.020 W/m2K

specifi c junction

testing not possible but

analysed with infra-red

thermography

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Fabric Performance Data - first BPE results

“The indication is that the Camden Passivhaus is one of only a few co-heating tested dwellings that meets its design intent.”

“This is a positive refl ection on the design and build quality of the house and is especially encouraging considering the low heat loss that was targetted here.”

Samuel Stamp, UCL Energy PhD research student

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Energy consumption - Specific Heat Demand

(Design target)13.7 kWh/m2Specifi c space heating demand

(Measured performance)12.1 kWh/m2

Camden Passivhaus space heating demand compared to the UK existing housing stock

* Benchmark taken from DomEARM

**

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Energy consumption - Electricity demand

Predicted electricity consumption

Monitored electricity consumption

Occupants away on skiing trip

Solar pump running Solar pump running continuously - fi xed in late continuously - fi xed in late January ‘12January ‘12

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Energy consumption - Electricity & Heat

DHW17%

Space heating25%

Lighting11%

Boiler and pumps16%

Sockets, blinds,appliances

25%

HRV5%

Predicted energy demand

DHW25%

Space heating27%

Lighting4%

Boiler and pumps6%

Sockets, blinds,appliances

32%

HRV6%

Measured energy demand

Solar pump

running

continuously

(fi xed in late

January ‘12)Lights on during the day!

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Monitored vs. predicted space heating demand

Energy consumption - Performance gap?

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Energy consumption - Comparison

Annual energy performance compared with benchmarks (DomEARM)

Annual CO2 emissions compared with benchmarks (DomEARM)

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Energy consumption - Comparison

90

80

72

65 63

0

10

20

30

40

50

60

70

80

90

100

BedZed The Long House One Brighton Camden Passivhaus Princedale Road

kWh/m

2

Total gas and electricity consumption of UK domestic low-energy exemplars

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Comfort - Psychrometric charts - winter

Average daily temperatures

living room 21 - 22 oC

bedroom 19.6 - 20.4 oC

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Comfort - Winter temperatures

5

0

5

10

15

20

25

Tempe

rature

(OC)

Date

Thermal comfort in January

Living room

Bedroom

External

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Comfort - Psychrometric charts - summer

Average daily temperatures

living room 23.5 -24.5 oC

bedroom 21 - 22 oC

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Comfort - Summer temperatures

5

10

15

20

25

30

Tempe

rature

(OC)

Date

Thermal comfort in June

Living roomBedroomExternal

Comparison of PHPP predicted and actual annual overheating

8 8

4

0

2

4

6

8

10

12

14

PHPP predicted Actual (>25C) Actual (>26C)

Overheatin

g%

PHPP LIMIT

8

5

3

0

2

4

6

8

10

12

14

PHPP predicted Actual (>25C)

Overheatin

g%

Oct Mar

Summer (Jun Sep)

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Comfort - BUS overall comfort

ComfoverUnsatisfactory :1 7: Satisfactory

0 10 20 30 40 50 60 70 80 90 100

Percentile

Unsatisfactory: 1

2

3

4

5

6

Satisfactory: 7

20406080

^

v

Comfover

© BUSMethodology 2011 A

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Comfort - Interior air quality

Average CO2 concentration

living room average 667ppm

bedroom average 717ppm

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Comfort - BUS perceived health

HealthLess healthy :1 7: More healthy

0 10 20 30 40 50 60 70 80 90 100

Percentile

Less healthy: 1

2

3

4

5

6

More healthy: 7

20406080

^

v

Health

© BUSMethodology 2011 A

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Lime House - timber framed passivhaus, Ebbw Vale

Lime House, Ebbw Vale

PROJECT LEAD: BERE:ARCHITECTS BPE PROJECT PARTNER: UNIVERSITY COLLEGE LONDON DR IAN RIDLEY, LEAD RESEARCHER CARDIFF UNIVERSITY, CO-HEATING & FABRIC TESTS TSB EVALUATOR: IAN MAWDITT TSB LEAD: FRANK AINSCOW

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Lime House - timber framed passivhaus, Ebbw Vale

Larch House, Ebbw Vale

PROJECT LEAD: BERE:ARCHITECTS BPE PROJECT PARTNER: UNIVERSITY COLLEGE LONDON DR IAN RIDLEY, LEAD RESEARCHER CARDIFF UNIVERSITY, CO-HEATING & FABRIC TESTS TSB EVALUATOR: IAN MAWDITT TSB LEAD: FRANK AINSCOW

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Detailing for a really

draught-free building

Window / wall junction

Eaves detail

General arrangement airtightness strategy drawing

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Progressively staged detailed drawings

Window Jamb Progress Detail Stage 01 Window Jamb Progress Detail Stage 02

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Progressively staged detailed drawings

Window Jamb Progress Detail Stage 04 Window Jamb Progress Detail Stage 03

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Risk management

Wall / fl oor slab detail

Intermediate fl oor detail

Good collaborative approach with site manager

allowed risks to be identifi ed early

Services penetrations

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Never assume!

BT engineer compromised airtightness layer

with incorrect installation; visiting on a day

that the site manager wasn’t on site!

Thermal Image of BT point

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Careful design and commissioning of services

Frost protection unit

Ventilation unit(Paul Focus)

Intake duct

Extract duct

Heat recovery ventilation unit located in the cupboard on the ground fl oor in the Larch house

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Heat recovery ventilation - filter maintenance

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

What we were aiming for

Lime House

Larch House

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Electricity consumption compared to typical

B.14) Time profile of electricity Consumption compared to EST average (Larch)

Average hourly profile of Electricity Consumption with average UK (EST study) profile

0

200

400

600

800

1000

1200

0:00

2:00

4:00

6:00

8:00

10:0

0

12:0

0

14:0

0

16:0

0

18:0

0

20:0

0

22:0

0

Time

W

Larch House EST typical UK Larch excluding Cooker

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Electricity consumption & generation - summer

B.17) Time Profile of average PV generation, Export and Grid Import (Larch)

Average hourly profile of PV system

0

200

400

600

800

1000

1200

1400

1600

1800

2000

0:00

:00

2:00

:00

4:00

:00

6:00

:00

8:00

:00

10:0

0:00

12:0

0:00

14:0

0:00

16:0

0:00

18:0

0:00

20:0

0:00

22:0

0:00

Time

W

Generated Exported Total Consumption Imported

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Electricity consumption & generation - winter

A.18 Time Profile of average PV generation, Export and Grid Import (Lime)

Average hourly profile of PV system Winter

0

200

400

600

800

1000

0:00:0

02:0

0:00

4:00:0

06:0

0:00

8:00:0

010

:00:00

12:00

:0014

:00:00

16:00

:0018

:00:00

20:00

:0022

:00:00

Time

W

Generated Exported Total Consumption Imported

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Excellent air quality results - Lime House

05101520253035404550556065707580859095

100105

12/11/20

1210

:45

12/11/20

1223

:45

13/11/20

1212

:45

14/11/20

1201

:45

14/11/20

1214

:45

15/11/20

1203

:45

15/11/20

1216

:45

16/11/20

1205

:45

16/11/20

1218

:45

17/11/20

1207

:45

17/11/20

1220

:45

18/11/20

1209

:45

18/11/20

1222

:45

19/11/20

1211

:45

20/11/20

1200

:45

20/11/20

1213

:45

21/11/20

1202

:45

21/11/20

1215

:45

22/11/20

1204

:45

22/11/20

1217

:45

23/11/20

1206

:45

23/11/20

1219

:45

24/11/20

1208

:45

24/11/20

1221

:45

25/11/20

1210

:45

25/11/20

1223

:45

26/11/20

1212

:45

27/11/20

1201

:45

27/11/20

1214

:45

28/11/20

1204

:05

28/11/20

1217

:05

29/11/20

1206

:05

29/11/20

1219

:05

30/11/20

1208

:05

30/11/20

1221

:05

01/12/20

1210

:05

01/12/20

1223

:05

02/12/20

1212

:05

03/12/20

1201

:05

03/12/20

1214

:05

04/12/20

1203

:05

04/12/20

1216

:05

05/12/20

1205

:05

05/12/20

1218

:05

06/12/20

1207

:05

06/12/20

1220

:05

07/12/20

1209

:05

07/12/20

1222

:05

08/12/20

1211

:05

09/12/20

1200

:05

09/12/20

1213

:05

10/12/20

1202

:05

Relativ

ehu

midity

(%)

Date (time)

Lime House Interior Relative Humidity (%) 12th November 2012 10thDecember 2012

Living room RH

Master bed RH

Downstairs bathroom RH

Upstairs bath RH

Note: the couple in the Lime house has a new born baby'drying clothes several times a day' .The RH spikes which occur in the bathrooms duringshowers decrease fast, due to adequate ventilation.

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Excellent air quality results - Larch House

0

5

10

15

20

25

30

35

40

45

50

55

60

65

70

12/11/2012

10:45

12/11/2012

23:45

13/11/2012

12:45

14/11/2012

01:45

14/11/2012

14:45

15/11/2012

03:45

15/11/2012

16:45

16/11/2012

05:45

16/11/2012

18:45

17/11/2012

07:45

17/11/2012

20:45

18/11/2012

09:45

18/11/2012

22:45

19/11/2012

11:45

20/11/2012

00:45

20/11/2012

13:45

21/11/2012

02:45

21/11/2012

15:45

22/11/2012

04:45

22/11/2012

17:45

23/11/2012

06:45

23/11/2012

19:45

24/11/2012

08:45

24/11/2012

21:45

25/11/2012

10:45

25/11/2012

23:45

26/11/2012

12:45

27/11/2012

01:45

27/11/2012

14:45

28/11/2012

04:05

28/11/2012

17:05

29/11/2012

06:05

29/11/2012

19:05

30/11/2012

08:05

30/11/2012

21:05

01/12/2012

10:05

01/12/2012

23:05

02/12/2012

12:05

03/12/2012

01:05

03/12/2012

14:05

04/12/2012

03:05

04/12/2012

16:05

05/12/2012

05:05

05/12/2012

18:05

06/12/2012

07:05

06/12/2012

20:05

07/12/2012

09:05

07/12/2012

22:05

08/12/2012

11:05

09/12/2012

00:05

09/12/2012

13:05

10/12/2012

02:05

Relativ

ehu

midity

(%)

Date (time)

Larch House Interior Relative Humidity (%) 12th Nov 10th Dec 2012

Living room RH

Master bed RH

Bedroom 3 RH

Upstairs bath RH

©be

re:architects2

012

clothe

sdrying

inthe

airin

gcupb

oard

and

intheup

stairs

bathroom

theRH

inthebathroom

drop

sfasta

fter

show

ers,

with

adeq

uate

ventilatio

n

masterb

edroom

RHspikes

possiblydu

eto

thewindo

ws

beingop

ened

masterb

edroom

RHspikes

possiblydu

eto

thewindo

wsbe

ing

open

ed

* the clothes drying in the bathroom have a lower impact on the internal RH than the showers

* the occasional spikes in RH due to showers, and drying the clothes are quickly cleared by the ventilation system

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Return on investment - if energy prices stable

Code 6 Passivhaus - PAYS BACK THE CAPITAL COST!

Code 5 Passivhaus

Code 4 Passivhaus

Building Regulations minimum standard

50 years

£35,000difference in build-cost inestate quantities

£75,000difference in 50yr value

£180,000

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Return on investment - if 5% energy price-rise

Code 6 Passivhaus - PAYS BACK THE CAPITAL COST!

Code 5 Passivhaus

Code 4 PassivhausBuild

ing Regulatio

ns minim

um standard

50 years

£35,000difference in build-cost inestate quantities

£170,000difference in 50year value!

£300,000

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Return on investment - if 10% energy price-rise

Code 6 Passivhaus

Code 5 PassivhausCode 4 Passivhaus

Buildin

g R

egula

tions

min

imum

sta

ndard

50 years

£35,000difference in build-cost inestate quantities

£870,000difference in 50year value!

£1000,000

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

What did I learn from the BPE projects?

Reassurance that some of the UK’s first PH buildings...

• Were performing OK• Were closing the Performance Gap• Were healthy for occupants and for the environment• Occupants loved living in them• PH methods do indeed “work in the UK”

Also:• I got to learn a huge amount from academic partners• I gained massive respect for the work of BPE academics - their work should be a national priority, and funded as such!• I learnt that we can have a Zero Carbon Britain...• I got ideas of the next steps towards this goal.

c b

ere:

arch

itect

s 20

16

c b

ere:

arch

itect

s 20

16

Footnote

The very encouraging results of our BPE work, lead me to believe that it is possible, as a nation, to respond effectively to the climate change emergency.

If we inspire intelligent, responsible young people to join and lead the construction industry, and if we have a more responsible political environment, and a responsible attitude towards population growth, then we can build and retrofit both domestic and non-domestic buildings that will be capable of working successfully in a 100% renewable energy grid, along with electric transport and other aspects of daily life.

c b

ere:

arch

itect

s 20

16