2 Major Component of Ddcmis

  • Upload
    sam

  • View
    219

  • Download
    0

Embed Size (px)

Citation preview

  • 7/31/2019 2 Major Component of Ddcmis

    1/49

    24 May 2012 PMI Revision 00 1

    (DIGITAL DISTRIBUTEDCONTROLS AND

    MANAMAGEMENTINFORMATIONSYSTEMS)

    IN POWER PLANT

  • 7/31/2019 2 Major Component of Ddcmis

    2/49

    24 May 2012 PMI Revision 00 2

  • 7/31/2019 2 Major Component of Ddcmis

    3/49

  • 7/31/2019 2 Major Component of Ddcmis

    4/49

    24 May 2012 PMI Revision 00 4

    INTEGRATED PLANT OPERATION THROUGH FULLYINTERCHANGEABLE OPERTAOR WORK STATIONS(OWS) FOR SG, TG AND BALANCE OF PLANT

    (SOMETIMES THIS MAY NOT BE POSSIBLE DUE TOPACKAGING CONCEPT)

  • 7/31/2019 2 Major Component of Ddcmis

    5/49

    24 May 2012 PMI Revision 00 5

    PROVISION OF EXTENSIVE SELF-DIAGNOSTICS

    USE OF LARGE VIDEO SCREENS FOR

    PROJECTIONS OF VARIOUS PLANT MIMICSETC.

    PROVISION OF FAULT ALARM ANALYSIS TOGUIDE THE OPERATOR TO THE MOST LIKELYEVENT

    PROVISION OF TREND ALARMS

  • 7/31/2019 2 Major Component of Ddcmis

    6/49

    24 May 2012 PMI Revision 00 6

    PROVISION OF SAFETY HARDWARE FORBURNER MANAGEMENT SYSTEMS

    PROVISION OF FAIL-SAFE HARDWARE FOR

    TURBINE PROTECTION SYSTEM

    PROVISION OF ADEQUATE RELIABILITY ANDAVAILABILITY WITH PROPER REDUNDANCY IN

    SENSOR, I/O AND CONTROLLER.

  • 7/31/2019 2 Major Component of Ddcmis

    7/49

    24 May 2012 PMI Revision 00 7

    HMIREDUNDANT

    SERVERS

    Redundant

    F.G.Controllers

    ENGG.STN.

    FOR CONTROL SYS.

    HMIENGG. STN

    FOR HMI

    PROCONTROL

    SYSTEM

    Measurement system / I/O

    subsystem

    I.P. BUS Max. 4nos. rdundant

    maxDNA

    SYSTEM

    MMI LAN

  • 7/31/2019 2 Major Component of Ddcmis

    8/49

    24 May 2012 PMI Revision 00 8

  • 7/31/2019 2 Major Component of Ddcmis

    9/49

    24 May 2012 PMI Revision 00 9

    CONTROL SYSTEM

    MAN-MACHINE INFORMATION AND PLANT

    INFORMATION SYSTEM (MMIPIS)

    REDUNDANT DATA COMMUNICATION SYSTEM

    (DCS)

  • 7/31/2019 2 Major Component of Ddcmis

    10/49

  • 7/31/2019 2 Major Component of Ddcmis

    11/49

    24 May 2012 PMI Revision 00 11

  • 7/31/2019 2 Major Component of Ddcmis

    12/49

    24 May 2012 PMI Revision 00 12

    CONTROL SYSTEM

    PROGRAMMING & MMIPIS M & S

    CONFIGURATION SYSTEM CLOCK

    SG- C&I BOP- C&I TG- C&I

    SYSTEM SYSTEM SYSTEM

    DCS

  • 7/31/2019 2 Major Component of Ddcmis

    13/49

    24 May 2012 PMI Revision 00 13

    SG-C&I SYSTEM

    CONSISTS OF BURNER MANAGEMENTSYSTEM(BMS), SOOT BLOWER CONTROLSYSTEM (SBC), SECONDARY AIR DAMPER

    CONTROL SYSTEM (SADC), AUXILIARY PRDSCONTROLS (APRDS)

    FOR BMS, SAFETY SYSTEM HARDWARE IS

    SPECIFIED, i.e. THE HARDWARE , WHICHMEETS THE REQUIREMENT OF RELEVANTNFPA AND VDE STANDARDS`

  • 7/31/2019 2 Major Component of Ddcmis

    14/49

    24 May 2012 PMI Revision 00 14

    SG-C&I SYSTEM

    TRIPLE REDUNDANT CONFIGURATION FOR THEFURNACE PROTECTION (MFT) PORTION OF BURNERMANAGEMENT SYSTEM(BMS)

    FOR SBC,SADC,APRDS,MILL & OIL ELEV.SEQUENCE, INTERLOCK AND PROTECTION,CONFIGURATION SIMILAR TO OLCS/CLCS(DESCRIBED LATER)

    FOR MILL & OIL ELEV. LOGICS, SAFETY SYSTEMHARDWARE SHALL BE USED

  • 7/31/2019 2 Major Component of Ddcmis

    15/49

    24 May 2012 PMI Revision 00 15

    TG-C&I SYSTEM

    CONSISTS OF TURBINE PROTECTION SYSTEM(TPS), AUTOMATIC TURBINE RUN-UP SYSTEM(ATRS), AUTOMATIC TURBINE TESTING

    SYSTEM(ATT), ELECTRO- HYDRAULIC TURBINECONTROL SYSTEM (EHTC) FORMAIN & BFPTURBINE, TURBINE STRESS CONTROL SYSTEM(TSCS), GLAND STEAM PRESSURE CONTROL

    GENERATOR SEAL OIL, PRIMARY WATER &HYDROGEN CONTROL SYSTEM (RECENTADDITION).

  • 7/31/2019 2 Major Component of Ddcmis

    16/49

    24 May 2012 PMI Revision 00 16

    TG-C&I SYSTEM

    TRIPLE REDUNDANT OR 2 X 100 % REPEATEDTWICE CONFIGURATION FOR THE TURBINEPROTECTION SYSTEM(TPS). FOR THIS,SAFETY SYSTEM HARDWARE / FAIL-SAFEHARDWARE SHALL BE USED

    FOR OTHERS, CONFIGURATION SIMILAR TO

    OLCS/CLCS (DESCRIBED LATER) TO BE USED

  • 7/31/2019 2 Major Component of Ddcmis

    17/49

    24 May 2012 PMI Revision 00 17

    BOP-C&I SYSTEM

    CONSISTS OF OPEN LOOP CONTROL SYSTEM(OLCS) AND CLOSED LOOP CONTROL SYSTEM(CLCS)

    OLCS -THE SEQUENCE CONTROL, INTERLOCK OF OFALL THE PLANT SYSTEMS WHICH ARE NOT COVEREDIN THE SG-C&I AND TG-C&I. THIS INCLUDES MAJORAUXILIARIES LIKE FD/ID/PA FANS, AIR-PREHEATER,

    BFP/CEP/CWP/ BCWP , DMCWP/CLCWP ANDELECTRICAL BREAKERS.

  • 7/31/2019 2 Major Component of Ddcmis

    18/49

    24 May 2012 PMI Revision 00 18

    BOP-C&I SYSTEM

    (CLCS) -THE MODULATING CONTROL FOR VARIOUS

    IMPORTANT PLANT PARAMETERS, LIKE FW FLOW

    (DRUM LEVEL), FURNACE DRAFT, COMBUSTION

    CONTROL (FUEL FLOW AND AIR FLOW), PA HDR

    PRESSURE CONTROL,

    DEAERATOR/HOTWELL/HEATER LEVEL CONTROLS

    ETC.

  • 7/31/2019 2 Major Component of Ddcmis

    19/49

    24 May 2012 PMI Revision 00 19

  • 7/31/2019 2 Major Component of Ddcmis

    20/49

    24 May 2012 PMI Revision 00 20

    MAN-MACHINE INTERFACE AND

    PLANT INFORMATION SYSTEM LATEST STATE-OF-THE-ART WORKSTATIONS /PCs AND

    SERVERS BASED ON OPEN-ARCHITECTURE ANDINDUSTRY STANDARD HARDWARE AND SOFTWARE TO

    ENSURE BETTER CONNECTIVITY.

    e.g. HARDWARE FROM COMPAQ/DIGITAL, HP, SUNMICRO-SYSTEM OR OTHER MAJOR SUPPLIERS (LESSDEPENDENCE ON THE C&I SYSTEM SUPPLIER IN THE

    LONG RUN) OPERATING SYSTEM WINDOWS-2000, OPEN-VMS OR

    UNIX.

  • 7/31/2019 2 Major Component of Ddcmis

    21/49

    24 May 2012 PMI Revision 00 21

    MAN-MACHINE INTERFACE AND

    PLANT INFORMATION SYSTEM 64/ 32-BIT SERVER/OWS WITH HIGH-SPEED ANDLARGE MEMORY (256/512 MB RAM, 8 GB HDD FORSERVER AND 128/256 MB RAM AND 4/6 GB HDD FOROWS) TO ENSURE FAST RESPONSE

    PROVISION OF LVS

    CONNECTION TO OTHER SYSTEM THROUGHSTATIONWIDE WAN

  • 7/31/2019 2 Major Component of Ddcmis

    22/49

    24 May 2012 PMI Revision 00 22

    VPC OPERATION

    OTHER OPERATOR INFORMATIONS THROUGHVARIOUS DISPLAYS

    ALARMS, LOGS, HISTORICAL AND LONG TERMSTORAGE.

    PERFORMANCE AND OTHER CALCULATIONS

  • 7/31/2019 2 Major Component of Ddcmis

    23/49

    24 May 2012 PMI Revision 00 23

  • 7/31/2019 2 Major Component of Ddcmis

    24/49

  • 7/31/2019 2 Major Component of Ddcmis

    25/49

    24 May 2012 PMI Revision 00 25

  • 7/31/2019 2 Major Component of Ddcmis

    26/49

    24 May 2012 PMI Revision 00 26

  • 7/31/2019 2 Major Component of Ddcmis

    27/49

    24 May 2012 PMI Revision 00 27

  • 7/31/2019 2 Major Component of Ddcmis

    28/49

    24 May 2012 PMI Revision 00 28

  • 7/31/2019 2 Major Component of Ddcmis

    29/49

    24 May 2012 PMI Revision 00 29

  • 7/31/2019 2 Major Component of Ddcmis

    30/49

    24 May 2012 PMI Revision 00 30

  • 7/31/2019 2 Major Component of Ddcmis

    31/49

    24 May 2012 PMI Revision 00 31

  • 7/31/2019 2 Major Component of Ddcmis

    32/49

    24 May 2012 PMI Revision 00 32

    Software

    Driver

    Software

    Driver

    Software

    Driver

    Software

    Driver

    OPC OPC OPC OPC

    Display

    Application

    Trend

    Application

    Report

    Application

    OPC OPC OPC

    OPC Solves the Problem

  • 7/31/2019 2 Major Component of Ddcmis

    33/49

    24 May 2012 PMI Revision 00 33

  • 7/31/2019 2 Major Component of Ddcmis

    34/49

    24 May 2012 PMI Revision 00 34

    SEQUENCE OF EVENT (SOE ) AND ANNUNCIATION

    SYSTEMFUNCTIONS

    ORIGINALLY THESE USED TO BE STAND-ALONESYSTEM (DIODE AUCTIONEERING, DBTC ETC

    REQUIRED) NOW INTEGRATED -THEREFORE THE DIODE

    AUCTIONEERING, DBTC ETC NOT REQUIRED

    SOE - 1mS RESOLUTION, STORAGE OF REPOTRS FOR

    LONG DURATION ANNUNCIATION LOGIC THROUGH OLCS/CLCS

    CONTROLLERS.

  • 7/31/2019 2 Major Component of Ddcmis

    35/49

    24 May 2012 PMI Revision 00 35

    SYSTEM

    PROGRAMMINGFACILITY

  • 7/31/2019 2 Major Component of Ddcmis

    36/49

  • 7/31/2019 2 Major Component of Ddcmis

    37/49

    24 May 2012 PMI Revision 00 37

    Graphical object-orientedconfiguration software tool

    Includes self-documentation

    of configuration True object-orientedfeatures includingencapsulation and

    inheritance Library of standard

    algorithms or objects

    C

    Object-Oriented Configuration

  • 7/31/2019 2 Major Component of Ddcmis

    38/49

    24 May 2012 PMI Revision 00 38

    MASTER & SLAVECLOCK SYSTEM

  • 7/31/2019 2 Major Component of Ddcmis

    39/49

    24 May 2012 PMI Revision 00 39

    MASTER & SLAVE CLOCK SYSTEM

    RECEIVES TIME SYNCHRONISATIONSIGNALS EITHER FROM THE GEO-

    POSITIONARY SATELITE (NPL SIGNAL)

    DISTRIBUTES THIS SIGNAL TO THE MMIPIS

    AND THE CONTROL SYSTEM.

  • 7/31/2019 2 Major Component of Ddcmis

    40/49

    24 May 2012 PMI Revision 00 40

  • 7/31/2019 2 Major Component of Ddcmis

    41/49

    24 May 2012 PMI Revision 00 41

    POWER SUPPLY SYSTEM

    CABLING & TERMINATION OTHER

    SG/TG C&I SYSTEM/ EQUIPMENT

    PACKAGING CONCEPTS- SCOPE OF

    SUPPLY OF C&I SYSTEM/PACKAGE

  • 7/31/2019 2 Major Component of Ddcmis

    42/49

    24 May 2012 PMI Revision 00 42

    OPERATION PHILOSOPHY , CONTROLAREA AND BACK-UPINSTRUMENTATION & GEOGRAPHICALDISTRIBUTION - COMBINED CYCLEPLANTS

    REDUNDANCY

    DESIGN CRITERIA

  • 7/31/2019 2 Major Component of Ddcmis

    43/49

    24 May 2012 PMI Revision 00 43

    CONTROL SYSTEM POWER SUPPLY TWO SETS OF DC POWERSUPPLIES - ONE SET FOR SG/TG-C&I AND OTHER FOR BOP-C&IEACH WITH 2 X 100 % CHARGER AND 2 X 100 % BATTERY.

    OTHER IMPORTANT AC LOADS LIKE MMIPIS, PANELINSTRUMENTS, ANALYSERS ETC. SHALL BE POWERED FROM

    UPS COMPRISING OF 2 X 100 % CHARGER, 2 X 100 %INVERTER AND 1 X 100 % BATTERY.

    HEAVY DUTY Ni-Cd BATTERIES HAVE BEEN ENVISAGED FORLONGER LIFE & LESSER MAINTENANCE

  • 7/31/2019 2 Major Component of Ddcmis

    44/49

    24 May 2012 PMI Revision 00 44

    EXTENSIVE GROUPING OF SIGNALS BY LARGE

    SCALE USE OF JBs AT STRATEGIC LOCATIONS

    USE OF CABLES WITH HIGHER NO OF PAIRS

    USE OF CAGE-CLAMP CONNECTION FOR SYSTEM

    CABINETS, MARSHALLING PANELS & OUTGOING

    SIDE OF JBs, CJS BOXES etc.

    USE OF PLUG-IN SOCKET AND CONNECTORS FOR

    TRANSMITTERS, SWITCHES, LS/TS etc.

  • 7/31/2019 2 Major Component of Ddcmis

    45/49

    24 May 2012 PMI Revision 00 45

    FLAME MONITORING SYSTEM

    COAL FEEDER C&I

    ELECTROMATIC SAFETY VALVES

    FURNACE TEMP PROBES

    ACCOUSTIC PYROMETER FOR FURNACE TEMP PROFILE BOILER FLAME ANALYSIS SYSTEM

    COAL BUNKER LEVEL MONITORING SYSTEM

    ELECTRONIC DRUM/SEPARATOR LEVEL MONITORING SYSTEM

    TURBINE SUPERVISORY SYSTEM

    TDBFP TURBINE SUPERVISORY SYSTEM

    IN PACKAGED SYSTEM, THESE ARE UNDER SG & TG PACKAGES.

  • 7/31/2019 2 Major Component of Ddcmis

    46/49

    24 May 2012 PMI Revision 00 46

    CENTRALISED OPERATION OF MAIN PLANT THROUGH OWS & LVS

    OFF-SITE PLANTS TO BE CONTROLLED FROM THEIR LOCALSTATIONS WITH STATION-WIDE LAN DATA LINK

    MINIMUM BACKUP INSTRUMENTATION (ORIGINALLY

    CONSERVATIVE, NOW REDUCED. CRITERIA - HANDLINGEMERGENCY & SAFE SHUT-DOWN)

    GEOGRAPHICAL DISTRIBUTION - ALTHOUGH NOT VERY USEFULFOR POWER PLANTS AS COMPARED TO PROCESS/INDUSTRIES,BEING ADOPTED FOR FEW AREAS WHERE SIGNALS ARECONCENTRATED (REDUCTION OF CABLING, MUCH LESSERECTION & COMMISSIONING TIME)

  • 7/31/2019 2 Major Component of Ddcmis

    47/49

    24 May 2012 PMI Revision 00 47

    PROVENNESS

    SUPPLIERS EXPERIENCE

    SYSTEM EXPERIENCE

    PROVENNESS VS OBSOLESCENCE

    RELIABILITY AVAILABILITY

    HARDWARE QUALITY (PUBLISHED MTBF etc.)

    CONFIGURATION

    REDUNDANCY

    FAULT TOLERANCE

    STANDARDISATION AND UNIFORMITY OF H/W

    SAME SERIES & FAMILY OF H/W AS FAR AS POSSIBLE

    DIFFICULTIES BECAUSE OF PACKAGING CONCEPTS &RESPOSIBILITY CENTRE & INTERFACES (EVEN IN TURNKEYPACKAGE)

  • 7/31/2019 2 Major Component of Ddcmis

    48/49

    24 May 2012 PMI Revision 00 48

    OPERABILITY DESIGN CONCEPT - FAIL SAFE ETC. FALSE TRIP VS SAFETY OPERATOR CONVENIENCE DURING NORMAL RUNNING &

    EMERGENCY MANAGEMENT REPORTING

    MAINTAINBILITY STANDARDISATION (AS INDICATED ABOVE) MODULAR DESIGN AND EXPANDABILITY DIAGNOSTIC, FAULT IDENTIFICATION AND FAULT TOLERANCE GUARD AGAINST OBSOLESCENCE AVAILABILTY OF SPARES

    OTHER CRITERIA UNIT OPERATION PHILOSOPHY MARKET TRENDS AND EVOLUTION OF INFORMATION

    TECHNOLOGY FEEDBACKS FROM EXISTING SYSTEMS

  • 7/31/2019 2 Major Component of Ddcmis

    49/49