MR(Material Requisition) MR No. : MR-D15021-PME100-006
Project Name : LP Steam Renewal Project eTEC E&C Limited
eTEC E&C Limited A4(210X297)
Contents of Bidding Documents
1. GENERAL
2. ITEMS AND QUANTITES
3. PROPOSAL REQUIREMENTS
4. SCOPE OF WORK SUPPLY
5. SPECIAL NOTE
6. INSPECTION
7. ENCLOSED DOCUMENTS
MR(Material Requisition) MR No. : MR-D15021-PME100-006
Project Name : LP Steam Renewal Project eTEC E&C Limited
eTEC E&C Limited A4(210X297)
1. GENERAL
The scope of quotation will be manufacturing and supply of the Condensate Pump to be
used for LP Steam Renewal Project which will be located in Gunsan, Chollabukdo,
Republic of Korea.
2. ITEMS AND QUANTITIES
No. Item No. Description Quantity
1 6CN-PP-0003A/B CONDENSATE PUMP 2
TOTAL 2 sets
3. PROPOSAL REQUIREMENTS
3.1 GENERAL CONDITIONS
1) All quotations shall be for the exact conditions as set forth in the drawings, specifications and description of material, equipment and/or services attached hereto. If there are deviations and/or omissions of any kind, your proposal must expressly call attention to the Purchaser under a separate heading titled "Deviation List," reference subject document number in order to be considered.
2) A prospective Bidder requiring any clarification of the bidding documents may notify eTEC in writing or by e-mail at the mailing address indicated in the bidding document. eTEC will respond in writing to any request for clarification of the bidding document.
3) Failure to furnish all information required by the bidding documents or submission of a bid not substantially responsive to the bidding documents in every respect will be at the Bidder’s risk and may result in rejection of its bid.
4) eTEC shall not allow any price extra necessitated by failure of the Bidder to comply with the technical specifications, unless such exceptions are clearly set forth in the quotation.
5) The Bidder shall bear all costs associated with the preparation and submission of its bid, and eTEC will in no case be responsible or liable for these costs, regardless of the conduct or outcome of the bidding process.
MR(Material Requisition) MR No. : MR-D15021-PME100-006
Project Name : LP Steam Renewal Project eTEC E&C Limited
eTEC E&C Limited A4(210X297)
6) All drawings, specifications, and technical information provided shall be treated as confidential. Bidders shall not permit any of such drawings, specifications, or information to be shown or disclosed to anyone other than those who need it in connection with this inquiry.
3.2 PRICING
Price shall be broken down as follows:
■ Price breakdown (Equipment proper with accessories)
■ Inspection & test at shop & site
■ Packing and transportation to the site
■ Government inspection and approval
■ Spare parts for erection and commissioning
■ Spare parts for (2) year(s) operation (option)
■ Special tools for erection, operation and maintenance, if required
■ Supervisory service for erection and test operation (* Man day)
3.3 PROPOSAL DOCUMENT TE BE SUBMITTED BY BIDDERS
■ Outline and arrangement drawings showing dimension and loading data of equipment
■ Assembly DWG
■ Data sheet
■ Performance Curves
■ Foundation information
■ Electric load list
■ Terminal point list with description
■ Spare part list for commissioning and start-up
■ Recommended spare part list for 2 years operation
■ Sub-vendor list
■ Overall manufacturing schedule with delivery date
■ Bill of material for equipment (if required)
■ System configuration diagram
■ Reference / Experience list
■ Technical catalogue and brochure of proposed equipment
■ Deviation list against inquiry specification
MR(Material Requisition) MR No. : MR-D15021-PME100-006
Project Name : LP Steam Renewal Project eTEC E&C Limited
eTEC E&C Limited A4(210X297)
CORRESPONDENCE
PROPOSAL SUBMITTAL (WITH PRICE, 1 SET)
Your proposal is to be mailed to:
Address : 6F, Songahm Bldg, 246 Yangjae-daero, Seocho-gu, Seoul,
134-747, Korea
Attention : Young-Sik, Yoon, Purchasing Team, eTEC E&C
Telephone : 02-489-8236
Fax : 02-489-8992
e-Mail : [email protected]
TECHNICAL CLARIFICATION((WITHOUT PRICE, 1SET)
Any questions of an engineering or technical nature required to submit a proposal for the equipment herein can be obtained by contacting:
Address : 38-10, Soryong-Dong, Gunsan-Si, Jeollabuk-Do, 573-879,
Korea
Attention : Mechanical Manager, W.K.JEON, eTEC E&C
Mechanical Manager, S.W.PARK , eTEC E&C
: Mechanical Engineer, K.E.RO , eTEC E&C
Telephone : 070-4333-7944/02- 489-9124/02-489-9045
e-Mail : [email protected]
MR(Material Requisition) MR No. : MR-D15021-PME100-006
Project Name : LP Steam Renewal Project eTEC E&C Limited
eTEC E&C Limited A4(210X297)
4. SCOPE OF WORK AND SUPPLY
4.1 Scope of Work
■ Basic design
■ Detail engineering
■ Procurement of equipment and material
■ Design & Calculation
■ Manufacturing
■ Test & Inspection of equipment in the vendor shop & site
■ Painting
■ Protection & Packing
■ In-Land Transportation
■ Acid Cleaning, If Required
■ Assembling
□ Insulation Work
□ Insulation Support Ring, If Required
■ Supervision for Installation
■ Mechanical & performance guarantee
■ Start-Up Service
■ All Permission for Regulation, If Any
□ Reimburse
□ Including quotation price as fixed lump price
■ Documentation as per “ vendor print to be submitted “
■ For a more detailed of "scope of supply", Check the document No. LP-ME-SP-2004
MR(Material Requisition) MR No. : MR-D15021-PME100-006
Project Name : LP Steam Renewal Project eTEC E&C Limited
eTEC E&C Limited A4(210X297)
4.2 Scope of Supply
■ Total 2 sets of “Condensate pump” in accordance with Technical Specification
(DOC. NO : LP-ME-SP-2004, “Technical Specification for Condensate Pump”)
■ Auxiliaries and accessories necessary for proper operation & maintenance
■ All auxiliary piping & instrument material(including wiring) within battery limits
■ Name plate with bracket (Material: 304 Stainless steel)
■ Earth lugs (Material: 304 Stainless steel)
■ Lifting lugs (Material: 304 Stainless steel)
■ Lubricant initial charges
■ Counter flange, gasket, bolt & nuts
■ Anchor bolts & nuts
■ Materials for installation
■ Local pressure gauges
■ Electrical, Instrument & Control items
■ Spare parts for installation, commissioning and start up
■ Spare parts for two (2) year operation (Option)
■ Special tools, if any
■ Test equipment, if any
■ For a more detailed of "scope of supply", Check the document No. “LP-ME-SP-2004.”
MR(Material Requisition) MR No. : MR-D15021-PME100-006
Project Name : LP Steam Renewal Project eTEC E&C Limited
eTEC E&C Limited A4(210X297)
5. SPECIAL NOTE
NO ITEM CONTENTS REMARK
1 Guarantee
1) Performance (Flow, Head, etc)
2) Efficiency /Power Consumption (BHP @ rated flow )
3) Delivery : 2016.11.30
2 Completion of
Vendor Print
1) Loading data & outline drawing
: After PO 1 weeks
2) Vendor print (IFA) : 2016.06.03
3 Liquidated Damages
1) Delivery delay(for equip. & VPIS)
: Refer to General terms and conditions
2) Liquidated damages for Performance
: Contract amount x Liquidation efficiency (%)
4 NPSH Test After NPSH test, vendor should be submitting the report of NPSH test.
※ Note
1) Liquidated damages for performance (Efficiency)
LD = [(Guaranteed efficiency – Test efficiency)/ Guaranteed efficiency] x Contract amount
2) Mechanical Running Test
Vendor Must carry out the mechanical running test over four(4) hours per each pump.
6. INSPECTION
INSPECTION & TEST
1) The Bidder shall arrange and perform the tests, examinations and inspection according to the required codes and standards, and then submit the reports to eTEC. Also refer to each technical specification for the requirement in detail.
2) Tests, examinations and inspection witnessed and/or approved by the Owner, eTEC does not relieve the Bidder of his obligation to provide his own quality control and inspection of the materials and equipment to assure himself that the purchaser’s requirements are met.
3) In the event that materials cannot be identified as to specifications, or reasonable doubt exists as to its identity, the Bidder shall carry out verification tests under the purchaser’s and/or his representative’s instruction at Bidder’s expense.
4) Re-inspection costs incurred by the purchaser and/or his representative due to failure of the Bidder’s materials and equipment, or both shall be charged to the Bidder.
MR(Material Requisition) MR No. : MR-D15021-PME100-006
Project Name : LP Steam Renewal Project eTEC E&C Limited
eTEC E&C Limited A4(210X297)
7. ENCLOSED DOCUMENTS (See attachments)
7.1 Bid Format
Description Doc. No. Rev. No. Sh’t No.
■ Deviation list - - 1
■ Spare part List for start-up & commissioning
- - 1
■ Spare part List for 2 years operation
- - 1
■ Special tool list - - 1
□ Sub vendor list - - -
□ Lubricant list - - -
■ Vendor data requirements - - 1
■ Bidder Data Sheet - A
7.2 Technical Specification
Description Doc. No. Rev. No. Sh’t No.
■ Tech. Spec. for COP LP-ME-SP-2004 A 16
■ Basic Engineering Design Data LP-PR-SP-1001 A 17
■ Specification for Piping Design Criteria
LP-PI-SP-0001 0 31
■ Specification for Piping Material
LP-PI-SP-0002 0 83
■ Specification for Painting LP-PI-SP-0003 0 28
■ Technical Specification for MV & LV motor
LP-EL-SP-4005 A 22
■ Butt weld end preparations and transitions
Later - -
■ Technical Spec. for Package(I&C)
LP-IC-SP-5005 0 50
■ P&ID for Condensate System LP-PR-DW-1012 A 1
■ Plot Plan - - 2
■ Sub-Vendor list (I&C) - - 3
■ Sub-Vendor list (Electrical) - - 1
■ Terminal point for I&C - - 1
VENDOR DATA REQUIREMENTS
REQUSITION NO. MR-D15021-PME100-006 SPEC NO. LP-ME-SP-2004 ITEM NO. EQUIPMENT NAME 6CN-PP-0003A/B CONDENSATE PUMP
DRAWING AND DATA REQUIRED (SEE NOTES BELOW)
COPIES WITH BID
COPIES FOR
APPROVAL
FINAL COPIES REQ’D
WITHOUT APPROVAL
OTHERPRINTS CD
1. Dimensional Outline Drawings 2 6 6 1
2. Cross Sectional Drawing 2 6 6 1
3. Component and/or Detail Drawings 6 6 1
4. Detailed Parts List 6 6 1
5. Loading Diagrams and Anchor plan 2 6 6 1
6. Hydraulic Calculation Sheet 6 6 1
7. BHP Calculation Sheet 2 6 6 1
8. NPSH Calculation Sheet 6 6 1
9. Schematic Piping Drawings for M/S 6 6 1
10. Completed Equipment Data Sheets 2 6 6 1
11. Performance Curve 2 6 6 1
12. Motor Data Sheet 6 6 1
13. Thermal limit curve, Time current curve for Motor - Over 100 KW or High Voltage Motor
6 6 1
14. Lubricant List 6 6 1
15. Recommended Two(2) Years Spare parts 2 6 6 1
16. Catalog Information, Cuts, etc. 2 6
17. (*)Manufacturer’s Inspection and Data Reports
6 1
18. Quality Plan(inc. Inspection & Test Plan) 6 6 1
19. Inspection & Test Report 6 1
20. Installation, Operation, Maintenance Manual 6 1
21. Mill sheet or Corrosion Test Data 6
22. (*)Shipping schedule and Packing List 6 1
23. Weight List of Fabricated Parts and/or Unit Shipping Weight
6 6 1
24. Manufacturing Schedule 2 6 6 1
25. Sub-Vendor List 2 6 6 1
26. (*)Gorverment permission document
27. All Document & Certificates for Pressure vessel -WPS & PQR, Calculation, Hyd Test/NDE report -ASME Stamp
28. Certificates for Safety valves
29. Certificates for Electrical components 6
NOTE: (*) Data indicated must be furnished when material or equipment is ready for inspection or shipment. OTHER REQUIREMENTS: 1. Cost of above data must be included in quotation. 2. Drawing and data “For Approval” are required within ( 2 ) weeks after order is placed. 3. “Certified Correct” final data drawings are required within 1 week after return of Approval data and drawing.
LP-PROJECT
TECHNICAL SPECIFICATION FOR
CONDENSATE PUMP
(DOC. NO. : LP-ME-SP-2004)
Rev. : A Page : 2 of 16
CONTENTS
1. GENERAL .......................................................................................................................... 3
2. SCOPE OF SUPPLY ......................................................................................................... 3
3. CODES AND STANDARDS .............................................................................................. 6
4. TECHNICAL REQUIREMENTS ........................................................................................ 7
5. INSPECTION & TEST ..................................................................................................... 11
6. QUALITY ASSURANCE .................................................................................................. 14
7. SPARE PARTS / CONSUMABLES /SPECIAL TOOLS .................................................. 14
Attachment #1 Condensate Pump Data Sheet
LP-PROJECT
TECHNICAL SPECIFICATION FOR
CONDENSATE PUMP
(DOC. NO. : LP-ME-SP-2004)
Rev. : A Page : 3 of 16
1. GENERAL
This specification covers the minimum requirements for engineering, and purchasing of
Condensate Pump(6CN-PP-0003A/B) and the relevant accessories. This item shall be
supplied for use in the LP Steam Renewal Project.
2. SCOPE OF SUPPLY
2.1. GENERAL
The contents of this specification have been made in detail as possible to maximize the
accuracy of the Vendor’s quotation. The Vendor should use his expert knowledge, review
this specification and add or delete equipment to meet the intent of required system.
The Vendor must address every paragraph of this specification in his quotation and either
confirms it applicable or gives clear alternate with price and price additions to meet
specified requirements.
Failure to comply with any part of this specification does not relieve the Vendor from system
responsibility.
Chinese and Indian products can not be delivered without client permission..
2.2. SCOPE OF WORK
The Vendor shall furnish the following equipment and services in accordance with the
requirements of this specification.
2.2.1 General
NO Pump Designation Quantity Unit
1 Condensate Pump (6CN-PP-0003A/B) 2 Set(s)
LP-PROJECT
TECHNICAL SPECIFICATION FOR
CONDENSATE PUMP
(DOC. NO. : LP-ME-SP-2004)
Rev. : A Page : 4 of 16
2.2.2 Work to be provided by Supplier
1) Two(2) canned type condensate pump sets complete with shaft seal system and lube
oil device
2) Drive motors and coupling with accessories
3) All internal piping & valve required for drains, vents, sealing, lubrication and mechanical
balancing line within the terminal point
4) Base plate for the pump and motor
5) Design and supply of support accessories such as base plates, sole plates, sub-sole
plates, shims, wedges, foundation bolts and nuts
6) Pump and motor bearing temperature element with Thermowells, Transmitters, junction
boxes and all measuring instruments within the terminal points
7) Restriction orifices, flow gauges, filters, check valves, valves and piping for pump shaft
seal
8) Vibration monitoring devices
9) Welding rods required for the interconnecting piping between the equipments within the
Supplier's scope
10) Field gauges and root valves
11) Special tools for installation, commissioning, operation and maintenance
12) Technical supervision for installation, start-up and commissioning
13) All documentations including installation, maintenance and operation manuals
14) Shaft sealing(mechanical type) system
15) Grounding terminal lug
16) All flanges, gasket, bolts and nuts (include counter flange)
17) Vent and drain valves as required
LP-PROJECT
TECHNICAL SPECIFICATION FOR
CONDENSATE PUMP
(DOC. NO. : LP-ME-SP-2004)
Rev. : A Page : 5 of 16
18) Consumable parts and/or materials for storage, installation, startup and testing
19) Special tools for erection and maintenance
20) Spare parts for two(2) years operation (Option)
21) Spare parts for erection & commissioning
22) Surface preparation and shop painting for corrosion prevention and protection.
23) Field touch-up paints, if necessary
24) Local panel(On/Off/Emergency) and field gauges
25) All tests and inspections of the equipment in the Supplier's shop
26) Lifting lugs, assembly clips or other attachments as required facilitating erection,
assembly and maintenance
27) All noise prevention measures to meet the noise limits, if necessary
28) Lubricant for initial filling
29) All safety devices necessary for protecting the equipment
30) Packing for shipping
31) Transportation to jobsite
32) Platform for maintenance (Motor etc.)
2.2.3 Work to be provided by Purchaser
1) Unloading and storage at job site
2) Erection, installation and start-up of equipment at site
3) All piping, valves, hangers, supports and fittings external to the Supplier's terminal point
4) Instruments and control wiring external to the Supplier's terminal point
5) External power wiring to the Supplier's terminal point
6) Design and construction of civil (concrete) foundation
LP-PROJECT
TECHNICAL SPECIFICATION FOR
CONDENSATE PUMP
(DOC. NO. : LP-ME-SP-2004)
Rev. : A Page : 6 of 16
7) Cooling water, if required, to the Supplier's terminals
8) Local control station
9) Source power supply and its cables up to the MCC
10) Field touch-up painting works
11) Distributed control system (DCS)
2.3. TERMINAL POINT
The Supplier's terminal points shall include, but not limited to the following ;
1) Suction flanges/connections of the pump, inlets
2) Discharge flanges/connections of the pump outlets
3) Seal water supply and drain flanges/connections on the pumps
4) Outlet flanges/connections of high point vents valve
5) Terminal boxes of the instrumentation and control elements
6) Anchor bolts of the equipment support system
7) Cooling Water supply & return flange for Condensate Pump Motor Bearing Coolers
Terminal Point list shall be submitted at detail design stage.
3. CODES AND STANDARDS
The following codes, standards, and specification shall be considered as a part of this
specification. All documents shall be the latest editions in force on the data of issuance of
this specification. Refer to Attachment #1 Basic Engineering Design Data.
ANSI American National Standards Institute
API American Petroleum Institute
ASME American Society of Mechanical Engineers
LP-PROJECT
TECHNICAL SPECIFICATION FOR
CONDENSATE PUMP
(DOC. NO. : LP-ME-SP-2004)
Rev. : A Page : 7 of 16
ASTM American Society of Testing & Materials
AWS American Welding Society
AWWS American Water Works Association
HI Hydraulic Institute
SSPC Steel Structures Painting Council
IEC International Electro technical Commission
IEEE Institute of Electrical and Electronic Engineers
ISA Instrument Society of America
ISO International Organization for Standardization
NEMA National Electrical Manufacturers Association
NFPA National Fire Protection Association
UL Underwriter's Laboratory
KS Korean Industrial Standards
BS British Standard
4. TECHNICAL REQUIREMENTS
4.1. General Specification
4.1.1 Condensate Pump
1) No. of Units : 100% x 2
2) Type : Vertical, Canned, Centrifugal
3) Capacity, m3/h : 242 /Pump
4) TDH, m : 57
5) Differential Pressure, kg/cm2 : 5.64
LP-PROJECT
TECHNICAL SPECIFICATION FOR
CONDENSATE PUMP
(DOC. NO. : LP-ME-SP-2004)
Rev. : A Page : 8 of 16
6) Suction Pressure, kg/cm2.g : -0.91
7) Discharge Pressure, kg/cm2.g : 4.73
8) Pumping temp. ℃ : 45
9) NPSHav., m : 0 (at the pump suction nozzle center line)
The NPSH required shall not exceed the available for the full operating flow range.
10) Specific. Gravity : 0.9902
11) Material
- Casing : A743 CA-15 or Equivalent
- Barrel : A240 TP304 or Equivalent
- Impeller : A743 CA-15 or Equivalent
- Shaft : A276 TP420 or Equivalent
- Shaft Sleeve : A276 TP420 or Equivalent
- Wear ring : A276 TP420 or Equivalent
12) Installation : Outdoor
4.2. Detail Technical Requirement
4.2.1 General
1) The condensate pumps shall be of the vertical, wet suction, canned type, with
mechanical seals.
2) Running clearance shall meet the requirements of API 610, latest edition.
3) The NPSH available of pumps shall be designed to ensure safe and steady operation
without excessive vibration and cavitations. The NPSH available shall be at least 30%
more than the NPSH required.
4) The pump shall be made to minimize air leakage between shaft sleeves and shaft.
LP-PROJECT
TECHNICAL SPECIFICATION FOR
CONDENSATE PUMP
(DOC. NO. : LP-ME-SP-2004)
Rev. : A Page : 9 of 16
5) The pump rotating part is to be statically and dynamically balanced after assembly in
the shop.
6) The best efficiency point of pump shall be as near as possible to the rated operating
condition. The pump shut-off head shall not be not less than 120% of design point.
7) Can dimension and static head of impeller in can shall be designed by Supplier.
8) The pump total discharge head shall increase continuously from design point to shut-off
head so pumps are capable of continuously operating individually or in parallel under all
load conditions.
9) Critical speed of pumps shall be separated from the normal operating speed by 20% of
normal operating speed.
10) The pump casing shall be arranged to permit removal of pump internals by
disconnection all piping connections and the flange at the can to head joint. Piping
connections shall conform to shut-off pressure rating raised face for discharge and
suction flange.
11) The pump shaft bearings shall be flexible inserted hard metal bearings lubricated by
pumped medium or Supplier’s standard bearing
12) The pumps shall be equipped with packed stuffing boxes bearing against hardened
stainless steel shaft sleeves. The sleeves shall be locked to the shaft to prohibit its
turning on the shaft.
13) A suitable adjustable coupling of adequate capacity shall be provided to permit vertical
adjustment of the pump impeller. The coupling shall be removable for maintenance
access to the rotating assembly.
14) Replaceable wear rings shall be provided on the bowls and the impellers adjustable.
15) All nozzles and related parts for connecting to Purchaser's piping shall be capable of
LP-PROJECT
TECHNICAL SPECIFICATION FOR
CONDENSATE PUMP
(DOC. NO. : LP-ME-SP-2004)
Rev. : A Page : 10 of 16
withstanding reasonable reactions imposed by properly designed connecting piping.
16) The pump shall be so designed and constructed as to permit convenient inspection,
adjustment, repair and replacement of all parts subject to erosion or other deterioration
or otherwise requiring such attention.
17) Lifting eyebolts shall be provided.
18) The pump shall be design so that the condensate being pumped is not contaminated
with any oil or foreign matter.
19) The pump shall be specifically designed and constructed for condensate service and
shall have ample provision for shaft sealing and for suction casing venting or equalizing
connections.
20) Bidder shall indicate minimum flow(Under 30% of rated flow) at which each pump can
operate continuously without causing damage. Bidder shall also indicate the continuous
maximum allowable run-out flow for each pump.
4.2.2 Piping
Piping shall be designed in accordance with Supplier's standard, unless otherwise stated in
this specification and Piping Material Specification.
4.2.3 Electrical
1) Local on/off Switch shall be installed for control the pumps.
2) All electrical equipment provided by the Supplier shall be in accordance with Supplier's
standard unless otherwise stated in this specification.
3) The Supplier shall furnish all motors and motor auxiliaries in accordance with the ’Tech Spec
for MV & LV Motor’.
4.2.4 Instrumentation and Controls
Refer to ‘I&C Technical Specification for Package’.
LP-PROJECT
TECHNICAL SPECIFICATION FOR
CONDENSATE PUMP
(DOC. NO. : LP-ME-SP-2004)
Rev. : A Page : 11 of 16
4.2.5 Material
Materials shall be selected in accordance with Supplier's standard, unless otherwise stated
in this specification.
4.2.6 Surface Preparation and Painting
Surface Preparation and Painting shall be conducted in accordance with the ‘Cleaning and
Painting Specification.
5. INSPECTION & TEST
5.1. SHOP TEST AND INSPECTION
Tests and inspections shall be in accordance with applicable codes and standards and this
specification. Tests and inspections not covered by above requirements shall be performed
in accordance with manufacturer's standards. These test and inspection reports shall be
submitted to owner.
5.1.1. Test and inspection items
The equipment, parts and materials shall be tested and inspected, but not be limited to, the
followings.
1) Material test
All major materials for pressure boundary application shall be tested in accordance with
applicable code and standards.
2) Hydrostatic tests
Each assembled system shall be flushed clean and hydrostatically tested as adequate.
Tubing, piping connections welds, valve stems, and seats shall be checked for leaks.
No detectable leakage shall be permitted. All leaks shall be repaired and the equipment
retested. The vendor shall protect instruments from excess pressure during hydrostatic
LP-PROJECT
TECHNICAL SPECIFICATION FOR
CONDENSATE PUMP
(DOC. NO. : LP-ME-SP-2004)
Rev. : A Page : 12 of 16
testing. The hydrostatic test pressure shall be 1.5 times of the design pressure. The
pressure shall be continuously maintained for a minimum time of 30 minutes. Water
used for testing shall contain less than 200 ppm total halogens.
Following this test, the instrument devices shall be connected and tested for 5 min or
longer using the lowest nameplate working pressure of the instruments under test. The
vendor shall be responsible for the proper protection of the instruments.
Piping, tubing, valves, and fittings shall be blown dry with oil-free air or nitrogen, after
which the system inlet and drain connections shall be plugged.
Hydrostatic test shall be made for each pump casing in accordance with applicable code
and standard.
3) Welding inspection
All welding, welding procedure qualifications, electrodes, welding material, preheat and
post weld heat treatment, and welder or welding operator performance test shall be in
accordance with ASME B3l.1 and/or AWS D1.1.
4) Non-destructive Examination
All welds of pressure containing parts shall be examined by radiographic or ultrasonic,
magnetic particle and/or liquid penetration test in accordance with applicable code and
standards.
NDE personnel shall be qualified and certified for each examination method in
accordance with the requirements of SNT-TC-1A or equivalent.
5) Visual and dimensional inspection
In addition to code requirements, all components shall be visually examined prior to
assembly and painting. Welds and components shall appear sound and without defects,
rough edges shall be trimmed and ground smoothly.
LP-PROJECT
TECHNICAL SPECIFICATION FOR
CONDENSATE PUMP
(DOC. NO. : LP-ME-SP-2004)
Rev. : A Page : 13 of 16
All major components shall be checked dimensionally in accordance with the applicable
code & standard before sub-assembly and final assembly.
All components which interface with owner supplied equipment shall be checked after
assembly to verify that all dimensions involved in the interface agree with those shown in
the approved outline drawings. Where dimensions do not agree with those shown on the
drawings and adjustments cannot be made, the vendor shall inform owner of the
discrepancy and mutually agreeable solution shall be obtained prior to shipment.
6) Operation Test
An operating test shall be made to ensure the correctness of the wiring and piping and
the proper functioning of all equipment.
The tests shall include introducing into all analytical equipment a solution having known
chemical properties and recording the output.
7) NPSH test
NPSH test shall be performed in accordance with Hydraulic Institute Standards, using
cold water on one pump of each type specified. The test shall be performed for at least
five different flows, including rated flow, 15 percent above rated flow, maximum flow (run
out): and 10 percent below minimum flow, sufficiently divergent to establish a NPSH
curve over the useful range of the pump.
8) Field Test
The vendor shall conduct a recheck of system performance to verify that it meets the
specified requirements after installation of the equipment. Any reset or recalibration of
instruments which may be required shall be accomplished by the vendor. The vendor
shall furnish the services of a qualified engineer to provide technical direction and
consumable materials for start-up and field testing of the equipment.
LP-PROJECT
TECHNICAL SPECIFICATION FOR
CONDENSATE PUMP
(DOC. NO. : LP-ME-SP-2004)
Rev. : A Page : 14 of 16
6. QUALITY ASSURANCE
The Vendor shall establish and perform Quality Assurance Program in compliance with the
QA requirements;
Inspection and test plan (ITP)
Inspection points such as hold, witness and review
Owner or his designee reserve the right to perform audit, surveillance and inspection in
order to verify the implementation of QA Program for the equipment purchased in
accordance with this specification.
The Vendor shall submit Quality Assurance Program Manual test and inspection plans and
procedures (except for shop test and inspection procedures) for review and acceptance
prior to preceding the effective activities.
Shop tests and inspections shall be performed in accordance with procedures approved by
Vendor. The shop test and inspection procedures shall be submitted on request to Owner.
7. SPARE PARTS / CONSUMABLES /SPECIAL TOOLS
7.1. General
The Supplier shall provide the list with itemized unit prices using the owner’s form of the
spare parts, consumables and special tools.
The spare parts and special tools shall include those necessary items, which are to be
reasonably enough in terms of the items and quantities, and shall be at least equal to or
more than those contracted in his past reference plants. The reference plants shall have the
capacities equal to or larger than this plant. In addition, the vendor shall provide the
evidence document for the owner’s evaluation thereof.
During two(2) years after turnover, the vendor shall provide at the supplier’s expense when
LP-PROJECT
TECHNICAL SPECIFICATION FOR
CONDENSATE PUMP
(DOC. NO. : LP-ME-SP-2004)
Rev. : A Page : 15 of 16
additional spare parts and/or special tools are required due to the shortage and/or not
included in the “Two(2) years’ spare parts” and “Special tools” provided by the vendor and
also shall make restitution for the losses, if any.
7.2. Commissioning Spares and Consumables
The Supplier shall provide the list with itemized unit prices using the owner’s form of the
commissioning spares and consumables for the gas chromatograph and shall include the
total price within the fixed firm price portion.
In general it shall be understood that all parts, materials, consumables etc. including
chemicals and lube oils, to be consumed or replaced during installation, commissioning,
start-up and test run prior to the plant turnover to the Owner.
7.3. Operational Spares
1) Two(2) Years’ Spare Parts (Option)
The Supplier shall provide the spare parts list with itemized unit prices for the two(2)
years’ operation of the gas chromatograph in accordance with following instructions in
the owner’s form.
2) Recommended Spare parts
The Supplier shall add the additional items and quantities requested by the owner during
the technical clarification, and the vendor shall suggest reasonable unit prices for them.
The unit prices suggested in this category shall be the same as the unit prices of the
identical items listed in the two(2) years’ operational spares.
7.4. Special Tools
The Supplier shall provide the list with itemized unit prices using the owner’s form of the
LP-PROJECT
TECHNICAL SPECIFICATION FOR
CONDENSATE PUMP
(DOC. NO. : LP-ME-SP-2004)
Rev. : A Page : 16 of 16
special tools required for installation, checking, testing, inspection, operation, repair and
maintenance of the gas chromatograph and shall include the total price within the Fixed
Firm price portion.
12 PAGE 1 OF 1
3 CONTRACT NO. MR-D15021-PME100-006 ITEM NO. 6CN-PP-0003A/B SPEC./CODE NO. LP-ME-SP-2004
4 CLIENT GUNJANG ENERGY Co., Ltd REQ. NO. A
5 LOCATION GUSAN, KOREA NUMBER OF REQ'D 100% x 2 sets
6 SERVICE OF UNIT CONDENSATE PUMP BY DATE
7 OPERATION CONDITIONS EACH PUMP PERFORMANCE AT RATED8 LIQUID NAME Condensate water TRUE DENSITY * Kg/l PROPOSAL CURVE NO. *
9 HYDROCARBON □ YES □ NO PARTICLE DIA. * mm NPSH REQ'D * m
10 PUMPING TEMP 45.35 ℃ VAPOR PRESS. AT P.T. * kg/cm2a NO. OF STAGE *
11 SPECIFIC GRAVITY AT P.T. 0.9902 CAPACITY m3/h ROTATING SPEED * rpm
12 VISCOSITY AT P.T. 0.6133 CP DISCH. PRESS. kg/cm2g DESIGN EFFICIENCY * %
13 CORROSIVE (IF ANY) . SUC. PRESS. -0.91 kg/cm2g BHP AT RATED * Kw
14 COMPOUND DIFF. PRESS. kg/cm2 MAX. BHP RATED IMP. * Kw
15 SOLIDS (IF ANY) ; NAME DIFF. HEAD m MAX. HEAD RATED IMP. * m
16 CONTENT %wt NPSH AVAILABLE 0 m MIN. CONTINUOUS * m3/h
17 CORR. ALLOW. mm CAPACITY HYD. * kw ROTATION FROM CPLG. END ■ CW □ CCW
18 CONSTRUCTION MATERIALS19 NOZZLES NOM. SIZE RATING FACING POSITION API CLASS 12% Chrome Steel
20 SUCTION CASING A743 CA15 or Eq.
21 DISCHARGE IMPELLER A743 CA15 or Eq.
22 CASE-MOUNT ; □ CENTERLINE □ FOOT □ BRACKET ■ VERT. □ JACKET SHAFT A276 TP420 or Eq.
23 -SPLIT ; □ HOR ■ VERT □ BARREL TYPE VOLUTE ; □ SGL. □ DBL. □ DIFFUSER CASEWEARING *
24 -PRESS. ; MAX. ALLOW * kg/cm2g amb ℃ HYDRO. TEST * kg/cm2g IMP. WEARING *
25 JACKET -CASING ; □ YES □ NO -CONNECT ; □ VENT □ DRAIN □ GAUGE SHAFT SLEEVE A276 TP420 or Eq.
26 - STUPPING BOX W/S.GLAND ; □ YES □ NO
27 IMPELLER DIA. ; RATED * mm MAX./MIN. * mm CASING GASKET PTFE(Liquid Type)
28 TYPE ; * MOUNT. ; □ BETWEEN BRGS □ OVERHUNG BASE PLATE C.S
29 BEARING TYPE ; RADIAL * THRUST * JACKET - CASING *
30 LUBE ; □ RING OIL □ FLOOD □ OIL MIST □ FLINGER □ PRESS. □ LABYRINTH OIL SEAL - STUFFING BOX W/S.GLAND *
31 COUPLING ; TYPE * MFR'S TYPE NO. * SHOP TESTS32 DRIVER HALF MTD. BY ; ■ PUMP MFR. □ DRIVER MFR. □ PURCHASER □ NON-WIT. PERF. ■ WIT. PERF.
33 DRIVER ; ■ DIR. □ GEAR □ V-BELT BASE PLATE ; ■ COMMON □ SEPARATE □ NON-WIT. HYDRO ■ WIT. HYDRO.
34 SHAFT SEAL □ NPSH REQ'D ■ WT. NPSH
35 TYPE OF SEALING ; □ GLAND PACKING ■ MECHNICAL SEAL ■ SHOP INSPECTION
36 GLAND PACKING SIZE N/A MATERIAL N/A NO. OF RING N/A ■ DISMANTLE & INSP. AFTER TEST
37 MECH. SEAL TYPE ; □ SINGLE □ DOUBLE □ BALANCED □ UNBALANCED OTHER
38 □ INSIDE □ OUTSIDE □ PUMPING RING □ THROTTLE BUSHING VERTICAL PUMP39 API CODE * MFR. * SUMP DEPTH * m
40 MATERIALS ; SEAL RING * STATOR RING * MIN. SUBMERGENCE REQ'D * m
41 SHAFT PACKING * STATOR PACKING * COLUMN PIPE ■ FLANGED □ THREADED
42 AUXILIARY PIPING LINE SHAFT □ OPEN □ ENCLOSED
43 CW PIPE PLAN * □ CS □ SS □ TUBING □ PIPE BRGS BOWL *
44 TOTAL COOLING WATER REQ'D * m3/h SIGHT F.l. REQ'D * LINE SHAFT *
45 PACKING COOLING INJECTION REQ'D TOTAL N/A m3/h N/A kg/cm2g BRGS LUBE ■ WATER □ OIL □ GREASE
46 SEAL FLUSHPIPING PLAN * □ CS □ SS □ TUBING □ PIPE FLOAT & ROD □ CS □ SS □ BRONZE
47 EXTERNAL SEAL FLUSH FLUID * QUANTITY * m3/h * kg/cm2g □ NONE □ FLOAT SWITCH
48 AUXILIARY SEAL PLAN * □ CS □ SS □ TUBING □ GLOBE V/V W/P.G PUMP THRUST UP * Kg
49 AUX. SEAL QUENCH FLUID * DOWN * Kg
50 MOTOR DRIVER PAINTING51 RATED HP * Kw SPEED * rpm HAZARDOUS RATING N/A PRIMER : *
52 SERVICE FACTOR 1.15 FRAME * VOLTS/PHASE/CYCLE FINAL : *
53 MFR. * BEARINGS * LUBE * LOCATION □ INDOOR ■ OUTDOOR
54 TYPE INDUCTION INSUL. F FULL LOAD AMPS * A APPROX. WT. PUMP & BASE * Kg
55 ENC TEMP. RISE * ℃ LOCKED ROTOR AMPS * A MOTOR * Kg TURBINE Kg
56 REMARKS57 1. "*" Means Vendor to status
585960616263 A
64 REVISION NO. DATE NOTES PREP'D CHK'D CHK'D APPR'D
MDS-001 REV.1
CONDENSATE PUMP DATA SHEET
2016-04-15
DN300 150# RF SIDE
242
4.73
5.64
57
RFDN200 150# SIDE
*
A240 TP304
TEFC / IP55
T.W.KIMS.W.PARKIssued for Approval16.04.22 K.E.RO
BARREL