Upload
oscar-cabrera-chirre
View
23
Download
0
Embed Size (px)
Citation preview
PROBABILISTIC APPLICATIONS INPOWER SYSTEM PLANNING
Roy Billinton
University of SaskatchewanCANADA
2
Plan – “a proposed or intended course of action”
Planning – “the act of creating a plan or plans”Planning
Future Uncertainty
3
In order to consider “Uncertainty”
Planning criteria and processes can be designated as being:
“Deterministic” or “Probabilistic”
4
“Deterministic”
To determine: to fixto resolveto settleto regulateto limitto define
- adjective
% Reserve( N-1 )Worst case condition
5
“Probabilistic”
Probability – likelihood of an event, the expected relative frequency of occurrence of a specified eventin a very large collection of possible outcomes.
- adjective
6
Probability a quantitative measure of the likelihood of an event.
a quantitative measure of the uncertainty associated with theevent occurring.
a quantitative indicator ofuncertainty.
7
PROBABILISTIC APPLICATIONS IN POWER SYSTEM PLANNING
Quantitative incorporation of uncertainty in power system planning applications.
Task – to satisfy the future load requirement as economically as possible with a reasonable assurance of continuity and quality.
8
HL I
HL III
HL II
Hierarchical Levels
9
Hierarchical Level I – HL-I
Classical generating capacity planning
Task – plan a generating system to meet the system loadrequirement as economically as possible with anacceptable level of reliability.
GR
GRemote Capacity
External CapacityLoad CharacteristicsUncertainty
Generation Alternatives• Fossil• Hydro• Nuclear• Gas• Renewables
10
Risk Evaluation
Generation Load
RiskLoss of Load Expectation (LOLE)Loss of Energy Expectation (LOEE)Frequency & Duration (F&D)Other Indices
11
Example Reliability Criterion – NERC Region XXX
“Sufficient megawatt generating capacity shall be installed to ensure that in each year for the XXX system the probability of occurrence of load exceeding the available generating capacity shall not be greater, on the average, than one day in ten years. Among the factors to be considered in the calculation of the probability are the characteristics of the loads, the probability of error in load forecast, the scheduled maintenance requirements for generating units, the forced outage rates of generating units, limited energy capacity, the effects of connections to the pools, and network transfer capabilities within the XXX systems.”
12
Comparison of Alternatives Based on System Cost
• Implicit Cost Approach
Lowest overall cost (capital plus maintenance and operating costs) are compared using a fixed reliability criterion.
• Explicit Cost Approach
Lowest overall cost including the societal costs of unreliability.
13
Implicit Cost Approach
LOLELOEE
Peak Load
Criterion
C1 C2
IPLCC
IPLCC – Incremental Peak Load Carrying Capability
14
Explicit Cost Approach
Reliability
Cos
t
Optimum
Total cost
Utility costCustomer cost
Reserve Margin
xxxxxRopt
Overall Cost
Customer CostCustomer Outage Cost
15
Renewable energy sources, such as wind and solar power, behave quite differently than conventional generation facilities.Consider wind as an example: Wind Energy Conversion System (WECS)
Wind Speed (km/h)Po
wer
Out
put (
MW
)
Pr
Vci Vr Vco
01020304050
1 25 49 73 97 121 145Time (hour)
Pow
er O
utpu
t (M
W)
Year 1 Year 2
0102030405060
1 25 49 73 97 121 145Hour
Win
d S
peed
(k
m/h
)
Year 1 Year 2
Wind speeds & power outputs from two consecutively simulated years (the first week of January)
Power Curve Parameters:Cut-in speed (Vci) = 14.4 km/hRated speed (Vr) = 36.0 km/hCut-out speed (Vco) = 80.0 km/h
16
0
0.01
0.02
0.03
0.04
0.05
0 14 28 42 56Wind Speed (km/h)
Pro
babi
lity
0
0.2
0.4
0.6
0.8
1
1.2
Pow
er O
utpu
t (p.
u.)
ProbabilityPower Output
Avg.= 19.4 km/h, S.D.= 10.1 km/h
Year 1
0
0.01
0.02
0.03
0.04
0.05
0 14 28 42 56Wind Speed (km/h)
Pro
babi
lity
0
0.2
0.4
0.6
0.8
1
1.2
Pow
er O
utpu
t (p.
u.)
ProbabilityPower Output
Avg.= 19.6 km/h, S.D.= 10.8 km/h
Year 2
Probability distributions of annual wind speeds for two simulated years
0.000.050.100.150.200.250.300.35
0 4 8 12 16 20 24 28 32 36 40Power Output (MW)
Pro
babi
lity
Average = 9.56 MWCapacity credit = 0.24
Year 1
0.000.050.100.150.200.250.300.35
0 4 8 12 16 20 24 28 32 36 40Power Output (MW)
Pro
babi
lity
Year 2
Average = 10.10 MWCapacity credit = 0.25
Probability distributions of annual power outputs for two simulated years
17
The power output of a WECS can be incorporated in a probability analysis.
0
1
2
3
4
5
6
7
8
0 50 100 150 200 250 300 350 400 500 700
WTG Total Capacity (MW)
LOLE
(Hou
r/ye
ar)
North Battleford Saskatoon ReginaSystem: IEEE-RTSIC = 3,405 MWPL = 2,850 MW
Sequential Monte Carlo Simulation approach:Auto-Regressive Moving Average (ARMA) time series model
Analytical or State Sampling Monte Carlo approaches:Multi-state WECS model
LOLE vs. WTG Capacity
18
R
epla
cem
ent R
atio
Single Wind Site 2 Wind Sites 3 Wind Sites
Not Available (Single Wind Site) Not Available (2 Wind Sites)
0 2 4 6 8
10 12
12MW UnitRemoved
50MW UnitRemoved
100MW UnitRemoved
350MW UnitRemoved
Replacement ratio versus the capacity removed from the IEEE-RTS (single, two and three wind farms)
19
Generating capacity planning has changed considerably due to DEREGULATION and OPEN TRANSMISSION ACCESS.
Greater system uncertainty now exists due to underlying uncertainties in business conditions and opportunities for independent power production.
This increased uncertainty also extends to HL-II and the planning of associated transmission facilities.
20
There are many other areas of probabilistic application in HL-I. These include: Probabilistic production costing
Probabilistic unit commitmentProbabilistic assessment of hydroreservesProbabilistic assessment of spinning andoperating reservesProbabilistic assessment of renewableenergy reservesProbabilistic assessment of load servingentitiesProbabilistic of generation maintenance schedulingProbabilistic demand-side management
21
Hierarchical Level II – HL-II (NH2)
Task – plan a bulk electric system (BES) to serve the load requirement at the BES delivery points as economically as possible with an acceptablelevel of reliability.
The system analysis is considerably more complicated at HL-II than at HL-I and the overall degree of uncertaintyis greater.
22
Reliability
Adequacy Security
Existence of sufficient generation and transmis-sion facilities.
Ability to respond to system disturbances.
23
IEEE-RTSBus 18 Bus
21Bus 22
Bus 17
Bus 16
Bus 19
Bus 20
Bus 23
Bus 13
Bus 12
Bus 11
Bus 24
Bus 3
Bus 9
Bus 10
Bus 6Bus 8
Bus 7
Bus 2
Bus 1
Bus 4
Bus 5
Bus 14Bus
15
30
31
32 33 38
363435 37
2928
242625 23
1918
21
20
16 17
15147
27
2
68
3
1
Cable1013
51211
9
4
22
Cable
230 kV
138 kV
24
IEEE-RTS including Stations
25
Composite System Reliability EvaluationAdequacy
Probability of Load Curtailment (PLC)Frequency of Load Curtailment (FLC)Expected Energy Not Supplied (EENS)Expected Customer Interruption Cost (ECOST)
Probability of Load Curtailment (SPLC)Frequency of Load Curtailment (SFLC)Expected Energy Not Supplied (SEENS)Expected Customer Interruption Cost (SECOST)Severity Index (SI)System Average Interruption Frequency Index (SAIFI)System Average Interruption Duration Index (SAIDI)
BES Load Point Indices:
BES Overall Indices:
26
0
1000
2000
3000
4000
5000
6000
7000
8000
2850 MW 2907 MW 2964 MW 3021 MW
System Peak Load (MW)
EENS
(MW
h/ye
ar)
Bus 18Bus 19
02000400060008000
10000120001400016000
2850 MW 2907 MW 2964 MW 3021 MW
System Peak Load (MW)
EEN
S (M
Wh/
year
) System EENS
Load point EENS (Bus 18 & 19) for the IEEE-RTS at different system peak loads
System EENS for the IEEE-RTS at different system peak loads
27
Composite system (HL-II) reliability assessment can be performed using:
Analytical methods:State enumeration
Monte Carlo techniques:State sampling (non-sequential)State duration sampling (sequential)
28
0.00
0.10
0.20
0.30
0 1 2 3 4 5 6 7 8 9 10SAIFI (occ./yr.)
Prob
abili
ty
0%20%40%60%80%100%
FrequencyCumulative %Total (Priority)
Mean = 1.33S.D. =1.23
0.00
0.10
0.20
0.30
0 3 6 9 12 15 18 21 24 27SAIDI (hrs./yr.)
Prob
abili
ty
0%20%40%60%80%100%
FrequencyCumulative %Total (Priority)
Mean = 5.01S.D. = 5.97
The uncertainty associated with an annual BES index can be appreciated using index probability distributions
Probability distributions of SAIFI and SAIDI for the IEEE-RTS
Determined using state duration sampling (sequential) approach
29
Performance Based Regulation (PBR)
0.5
1
Payment (p.u.)
Reliability Index
0
Reward zone
Penalty zone
2S.D.
2S.D.
2S.D.
2S.D.
Dead zone
Mean value
a b c d
30
0
0.1
0 0.6 1.2 1.8 2.4 3 3.6 4.2 4.8SAIFI (occ./yr.)
Prob
abili
ty
0.0
1.0
PBR
(p.u
.)
Probability PBRMean = 1.33, S.D. = 1.23
ERP = + 0.0526 p.u.
Performance Based Regulation (PBR)
SAIFI distribution for the IEEE-RTS implemented in a PBR framework
31
Security Based Adequacy Evaluation
Success
Healthy
Marginal
At Risk
System Well-Being Framework
Healthy state – all equipment and operating constraints are within limits and there is sufficient margin to serve the total load demand even with the loss of any element (i.e. N-1 deterministic criterion is satisfied.).
Marginal state – the system is still operating within limits, but there is no longer sufficient margin to satisfy the acceptable deterministic criterion.
At risk state – equipment or system constraints are violated and load may be curtailed.
32
Security Based Adequacy Evaluation
Success
Healthy
Marginal
At Risk
System Well-Being Framework
System Well-Being Indices:
Prob{H} Freq{H}
Prob{M} Freq{M}
Prob{R} Freq{R}
33
Security Based Adequacy Evaluation SuccessHealthy
Marginal
At RiskSystem Well-Being
Framework
Cliff
Healthy Marginal
At Risk
34
Bulk system transmission planning in a deregulated open access environment introduces additional uncertainties including:
Market conditionsTransmission congestionPotential Co-Generation and IPPRenewable energy sources
35
Consider the situation in which a wind farm is to be added to the IEEE-RTS.
What is the “best” transmission plan to accommodate this generation addition?
Bus 3
Bus 9
Bus 2Bus
1
Bus 4
Bus 5
16 15147
2
68
3
1
9
4
Cable
138 kV
Regina wind farm (x)
Swift Current wind farm (y)
Cross-correlation (Rxy) = 0.75
B.2 C.
2B.1
C.1
A
Alternative 1: Constructing Line AAlternative 2: Constructing Line B.1Alternative 3: Constructing Line C.1Alternative 4: Constructing Lines B.1 and B.2Alternative 5: Constructing Lines C.1 and C.2
36
21.1919.8626.5021.5924.27DPUI (sys.mins)4.6094.3395.7404.7295.123ECOST (M$/yr)7.758.478.459.458.18EDLC (hrs/yr)2.883.533.054.012.77EFLC (occ/yr)
Alter. 5Alter. 4Alter. 3Alter. 2Alter. 1
Transmission Reinforcement AlternativeOverall SystemReliability
Indices
System reliability indices for the modified IEEE-RTS with the five transmission reinforcement alternatives
Probabilistic Reliability Evaluation
37
There are many areas of probabilistic application in HL-II. These include: Probabilistic stability analysis
Probabilistic load flowProbabilistic fault analysisProbabilistic transfer capabilityProbabilistic assessment of voltagecollapseProbabilistic reactive and voltage controlsettingProbabilistic system expansion planningProbabilistic assessment in a powermarket (i.e. locational marginal price,bilateral transaction, etc.)
38
Hierarchical Level III – HL-III
HL-III analysis is not usually conducted directly and HL-II values can be used as input parameters in a distribution system study.
Distribution system reliability evaluation is well established and relatively easily applied.
In a deregulated environment, customer supply can involve a number of entities and companies. It is important to be able to evaluate the contribution made by each entity to acceptable electric energy supply at the individual customer level.
39
Probabilistic evaluation requires the consistent collection of relevant system and component data.
These data should be collected using comprehensive and consistent definitions thoroughly understood by the participating entities.
Planning involves looking into the future but it is important to appreciate that it is difficult if not impossible to determine where you want to go if you do not know where you have been.