1_review01

Embed Size (px)

Citation preview

  • 7/30/2019 1_review01

    1/6

    500kV Aluminum-Sheathed XLPE Cable in a 96m Vertical Shaft

    U.D.C. [621.315.221.712.027.85: 669.71:678.742.2]: 621.315.232

    He Yongquan*

    Tatsuji Ishibashi**

    Katsuhiko Yamamoto**

    Kazutoshi Abe**

    Tetsuyo Yoneda**

    ABSTRACT: Three 500-kV XLPE cable circuits were supplied and installed in a 96m

    vertical shaft at Tianhuangping Pumped Storage Power Station in the P. R. of China.

    The cable was specially designed to prevent the cable core from slippage and to

    compensate radial expansion and contraction of the thick insulation. A hauling machine

    featuring regenerative braking was developed and utilized to vertically install the cable.

    The cable laying work was carried out by an installation contractor appointed by the

    owner under the supervision of Hitachi Cable, Ltd. The first 500-kV XLPE cable circuit

    was successfully put into service in July, 1998, the second in July, 1999 and the third

    circuit is under construction and will be completed by the end of 1999.

    1 INTRODUCTION

    To cope with increasing peak-power regulation and to

    ensure stability of the power supply in the East China Network,

    East China Electric Power Group Co. and the appointed

    construction firm Tianhuangping Pumped Storage Power

    Station Construction Co. launched the construction of a pure

    pumped storage power plant in 1993. This new power plant,

    Tianhuangping Pumped Storage Power Station (THP), is

    situated in Anji Country Zhejiang Province, which is 260 km

    southwest of Shanghai, a center of high load demand in the

    network (Fig. 1). The main features of THP are (1) a total

    installed capacity of 1800 MW (6300 MW) composed of six

    sets of Francis-type turbine, reversible units installed in an

    underground powerhouse complex: (2) a maximum 607-mgenerating head difference between the upper and lower

    reservoirs: and (3) a water-conveyance system with a conduit

    length to potential head ratio of 2.5. Three 500-kV XLPE cable

    circuits are employed to carry the plant output from the

    underground power house via a 96-m vertical shaft to

    preliminary overhead transmission lines in the network (Fig. 2).

    During the planning stage, both oil-filled cable and XLPE

    cable were considered for use as the main feeders. The XLPE

    cable was finally selected because:

    (1) 500-kV XLPE cables are being used in a number of

    pumped storage power plants in Japan(1).

    (2) XLPE cable has low dielectric loss and superior flame-retardant characteristics due to its oil-free construction.

    (3) High stati c pressure at the bottom of the shaf t and

    complicated control of oil pressure during terminating work

    can be avoided.

    However, prior to installing applying a corrugated aluminum-

    sheathed XLPE cable in the deep vertical shaft, we had to

    satisfy two requirements:

    (1) A mechanical design of the cable that prevents the cable

    core from slipping through the corrugated aluminum sheath.

    3HITACHI CABLE REVIEW No.18 (October 1999)

    * Tianhuangping Pumped Storage Power Station Construction Co.** Hitaka Works, Hitachi Cable, Ltd.

    Fig. 1 Location of Tianhuangping pumped storage power station

    A new power station with an installed capacity of 1800 MW is

    located 260 km southwest of Shanghai.

    Chengdu

    P.R. OF CHINA

    Wuhan

    Beijing

    Guangzhou

    Hongkong

    Shanghai

    TIANHUANGPINGPOWER STATION

    N

    (2) An appropriate cable laying technique that prevents the

    cable from slipping during laying work.

    The first requirement was satisfied by a specially designed

    bedding layer applied to the cable core and lightly compressed

    by the corrugated aluminum sheath. An experimental length of

    the cable was manufactured and subjected to a mechanical

    assessment which showed that no slipping occurred. Thesecond requirement was met by developing a new hauling

    machine with regenerative braking.

    By introducing these techniques, three circuits of 500-kV

    XLPE cables, the total length of which is 2090m, were safely

    and efficiently installed in the 96 m vertical shaft at the power

    station. Following assembly of the sealing ends and the field

    tests, the first 500-kV XLPE cable circuit was completed in

    April and put into service successfully in July, 1998. The

    second circuit was put into commercial operation in July, 1999.

    This paper describes the main features of the cable design

    for vertical installation, the verification of this design, the cable

    laying equipment and the construction of the cable circuits.

  • 7/30/2019 1_review01

    2/6

    4 HITACHI CABLE REVIEW No.18 (October 1999)

    2POWER CABLE SYSTEM DESIGN

    2.1 Cable design for vertical installation

    Table 1 lists the electrical requirements and the site

    conditions to which the cable system was designed. As

    previously mentioned, the salient point of the THP cable

    installation was that the 500-kV aluminum-sheathed XLPE

    cables were installed in a 96-m vertical shaft which lay in the

    middle of the cable route. The total difference in elevation of

    the entire cable route was 105 m (including the aboveground

    switchgear side).In the past several decades, oil-filled cable have mainly

    been utilized in vertical installations where the elevation

    difference was 100m and above(2). On the other hand, as far as

    the authors know, there was no precedent for an application of

    Fig. 2 Power house complex

    and cable route profile

    Three 500-kV XLPE cable

    circuits were installed in a 96-

    m vertical shaft to carry plant

    output to overhead trans-

    mission lines.

    TABLE 1 CABLE SYSTEM PARAMETERSThe 500-kV XLPE cable systems were designed according to the

    parameters shown in the table.

    A LIWV of 1675 kVp was required for cable and accessories.

    500kVXLPEcables

    DoorGIS

    500kVSwitchyard

    Original groundline

    Transformer hall

    Tailgate gallery

    Machine hall

    214.4

    233.1238.9

    228.2

    350.2

    285.0

    216.2

    246 .9I

    II

    III

    I

    II

    III

    IV

    VI

    V

    500kV cable& access

    shaft(8m Dia.) Lower reservoir

    Dimensions in m

    TRF.

    Cross-section of cable &access shaft

    1.6

    0.6

    Elevator

    Platform

    17.0

    8.2

    180.0 29.0

    15.0

    22.4

    24.4

    47.5

    500kV XLPEcables(3 circuits)

    a corrugated aluminum-sheathed XLPE cable to such a deep

    vertical shaft. Since oil-filled cables are often used in vertical

    installations, great attention has been paid to the design of the

    metallic sheath and the hydraulics including accessories.

    However, extensive research has not been conducted on

    slippage of the cable core through the metallic sheath. This is

    because the metallic sheath of the oil-filled cable can be

    applied tightly over the core, and the existence of a gap

    between them is not an issue.

    However, this is not the case with EHV XLPE cable.

    Usually, an EHV XLPE cable is designed to maintain a certainamount of gap between the metallic sheath and the underlying

    component so as not to obstruct the radial expansion of the core

    due to heat. This cable design, including the gap, results in a

    low coefficient of friction between the core and the metallic

    sheath, typically between 0.3 to 0.8 at ambient temperature(3), (4).

    When we committed to the application of the 500-kV

    XLPE cable at THP, we examined how to increase the

    restrictive force on the core a key factor in vertical

    installation. During the cable design, careful attention was paid

    to both the grasping force and to the thermal behavior of the

    thick XLPE insulation. Namely, the 500-kV XLPE cable had to

    satisfy the following diverse conditions simultaneously: (1)restrain the cable core firmly to prevent slippage, even at low

    temperatures during which the core diameter shrinks; and (2) to

    not obstruct the expansion of the cable core at high

    temperature. These conditions were satisfied by developing a

    special bedding layer, the design of which is described in the

    following section.

    2.2 Construction of cable and sealing end

    Table 2 lists the construction specifications and Fig. 3

    shows the appearance of the 500-kV XLPE cable. The cable

    core is composed of an 800 mm 2 copper conductor and 35 mm-

    thick XLPE insulation. The insulation thickness was

    determined according to the required lightning impulse

    Category Items Particulars

    Site

    conditions

    Electrical

    ratings

    Nominal system voltage (U)

    Highest system voltage (Um)

    Lightning impulse withstand voltage (LIWV)

    Switching impulse withstand voltage (SIWV)

    500 kV

    550 kV

    1675 kVp

    1240 kVp

    Three-phase symmetrical fault current

    Single-phase fault current

    System frequency

    Nos. of circuit

    Route length

    Elevation difference at vertical shaft

    Designed ambient temperature

    50 kA for 3 s

    40 kA for 2 s

    50 Hz

    3

    219 m / 222 m / 256 m

    96 m

    14C to 40C

    Transmission capacity for each circuit:

    (a) Rated current

    (b) Max. current for pumping start-up

    873 A (756 MVA)

    890 A (770 MVA)

  • 7/30/2019 1_review01

    3/6

    5HITACHI CABLE REVIEW No.18 (October 1999)

    withstand voltage (LIWV) of 1675-kVp. A specially-designed

    bedding layer (5.7mm thick) and a corrugated aluminum sheath

    were applied over the core. The inner diameter of the

    aluminum sheath was slightly smaller than the outside diameter

    of the bedding in order to obtain the necessary restrictive force

    on the core. The aluminum sheath was protected with a flame

    retardant PVC jacket, followed by a semi-conducting coating.The bedding layer, one of the most significant components

    of this cable, was carefully designed. According to the

    operational conditions of the cable systems, the diameter of the

    core varies by approximately 4mm in the conductor

    temperature range of 14C to 90C. To overcome this core

    variation, lightly-amalgamative cushion tapes, which absorb

    the expansion of the core and woven copper woven semi-

    conductive tape were applied over the core. The amalgamative

    nature of the tape prevents slippage between the core and the

    bedding layer as well as between the tapes. The thickness of

    the bedding layer was selected so that the maximum

    prospective indent by the aluminum sheath did not affect the

    underlying cable core.

    Items Particulars

    Type designation XLPE/CSA/PVC

    Thickness of bedding layer

    Thickness of aluminum sheath

    5.7 mm

    3.9 mm

    Diameter of cable

    Mass per unit length

    * L0I: Limited Oxygen Index

    160 mm

    28 kg/m

    Conductor:

    (1) Cross-section(2) Construction 800 mm

    2

    (copper)Segmental circular

    Insulation

    (1) Material

    (2) Thickness

    Inert gas cured XLPE

    35.0 mm

    Jacket:

    (1) Material

    (2) Thickness

    Flame retardant PVC (L0I*30)

    5.5 mm

    TABLE 2 CONSTRUCTION OF 500-KV XLPE CABLEThe bedding layer was carefully designed to absorb any expansion

    of the core and to grasp the core firmly.

    Fig. 3 Appearance of 500-kV

    XLPE cable

    The diameter and mass per

    unit length are 160-mm and28-kg/m, respectively.

    At the THP power plant, the 500-kV cables were

    terminated with SF 6-gas-type sealing ends on both the

    transformer and the switchgear. Figure 4 illustrates the general

    arrangement of the sealing end, which was composed of

    synthetic-resin bell mouth, silicone-oil-impregnated

    polyethylene sheets as internal insulation, and epoxy insulator

    as external insulation. Expansion and contraction of thesilicone oil volume contained in the sealing end due to

    temperature variation is compensated by a built-in oil reservoir

    made of metallic bellow, which enables a compact and space

    saving installation. The sealing ends were connected to the

    transformer horizontally and to the GIS vertically. On the

    transformer side, spacers were added in the sealing end to

    prevent the cable core from dangling and to maintain the

    specified gap between the internal and external insulations.

    The electrical performance of the cable and the sealing end

    was verified at the manufacturers factory. Sets of the cable and

    sealing-end assemblies were subjected to special and internal

    tests. In the special test, the assembly surpassed all aspects of

    the electrical requirements. The internal test was performed

    spontaneously in order to determine the ultimate characteristics

    of the cable and verified that the characteristics of the newly

    designed cable were of equally high quality to those of the

    manufacturers previous 500-kV XLPE cables (Table 3).

    3CONSTRUCTION DESIGN

    3.1 Mechanical performance and installation design

    To assess the mechanical performance of the cable, an

    experimental length was manufactured. This cable was

    subjected to a series of horizontal and vertical tests. Firstly, a

    1m cable sample was laid horizontally, clamped and the corewas extracted from the cable using a winch through a load cell.

    The required pulling forces were 10kN/m at ambient

    temperature and more than 5 kN/m at 75C (an average

    insulation temperature during actual service). In the latter case,

    the exact force required to extract the core could not be

    measured because slippage between the conductor and the

    insulation occurred. Similar tests were performed on a 3m

    cable sample laid horizontally and a 1m sample laid vertically.

    In both tests, slippage of the conductors occurred prior to any

    measurable core movements. These results imply that the

    ;

    ;

    ; ;

    ;

    ;

    ;

    ;

    ;

    ;

    ;

    ;

    ;

    ;

    ;

    ;

    ;

    ;

    290

    810

    660

    650

    600

    60

    1500

    1755 1620

    Epoxy InsulatorInsulating oil

    Bell mouthOil reservoir

    PE insulating sheetsInsulating flange

    62314 5

    14

    25

    36

    Fig. 4 Structure of 500-kV sealing end

    A combination of bel l mouth and PE sheets pressurized by oilreservoir were employed as an internal insulation.

  • 7/30/2019 1_review01

    4/6

    6 HITACHI CABLE REVIEW No.18 (October 1999)

    designed cable has sufficient grasping force on the core and

    can be considered appropriate for vertical installation.

    Following these preliminary tests, the cable was subjected

    to a vertical installation test involving heat cycles. Two lengths

    of cables were installed in a 15-m-high scaffold construction in

    a snaked formation with pitches of 6m and deflections of (a)

    1.5Ds (Ds: average diameter of aluminum sheath) and (b)

    2.0Ds. The cables were fixed to the scaffolding by holding

    cleats at their axial centers and by sliding cleats at their apexes

    (Fig. 5). Both ends of the cables were set freely. The cables

    were attached with terminals and bonding wires through which

    a circulating current flowed to provide daily heating cycles

    (from ambient temperature to 90C, 8 h ON/16 h OFF). After

    several heating cycles, the longitudinal protrusion and

    contraction of the cable core followed a regular pattern with

    each heating (Fig. 6). A total of 36 heating cycles were applied,

    and neither significant variation of the pattern nor slippage ofthe core were observed in either cables during the entire

    heating process.

    The results of the heating cycles indicate that both snaked

    formations were acceptable. However, the pattern of core

    movement under the deflection of 2.0Ds was more stable. This

    snaked formation was therefore adopted for the THP vertical

    installation. On completion of this test, the cables were

    dismantled and inspected. Undue deformation was not

    observed in the cable components, i.e., the core, the bedding

    layer, and the aluminum sheath. These tests confirmed the

    propriety of the cables mechanical design.

    3.2 Development of laying equipment

    When cables are laid in vertical shafts, they are usually

    threaded into the shaft from top to bottom. The THP cable

    installation followed this traditional method due to the limited

    working space in the underground power house. In previous

    vertical installations, the bond pulling methods use a wire rope,

    a turn pulley and winch installed at the upper mouth of a shaft

    and devices to prevent the cable from rotating (5) (7). However, in

    the THP cable installation, it was difficult to utilize the bond

    pulling method due to there being:

    No appropriate place to install a turn pulley

    Anticipated undue side wall pressure on the cable at the

    bending portion of the upper entry of the shaft.

    TABLE 3 PERFORMANCE OF CABLE AND SEALING ENDSets of cable and sealing end assemblies withstood all the test voltages.

    Category Items Test condition

    Special test

    Internal test

    * d: Dia. of conductor; D: Overall dia. of cable.

    Bending test

    Impulse withstand test at 953C

    AC withstand test at ambient temperature

    Partial discharge test

    Bending test

    Heating cycle

    AC withstand strength test after heating cycle

    Impulse breakdown voltage test after AC test

    Bending dia. 3500 mm [=18(dD)]*3 times

    1675 kVp/10 shots

    AC 480 kV10 h, followed by AC 625 kV/24 h

    P.D. less than 10pC at AC 430 kV & AC 447 kV

    Bending dia. 2450 mm [=13(dD)]*3 times

    (8 h ON/16 h OFF)20 cycles

    AC 1150 kV/2 h, withstood

    More than 2625 kVp

    3

    2

    1

    01

    2

    3

    4

    5

    6

    7

    1 2 3 4 5

    Nos. of heating cycles

    Expansion/contractionlengthof

    coremm

    Contra

    ction

    Expansion

    6 7 8

    Core movement at lower end

    Deflection : 2DsDeflection : 1.5Ds

    Fig. 5 Ex ec ut io n of 15 mhigh vertical installa-

    tion test

    (a) Left: deflection = 1.5 Ds,

    (b) Right: deflection = 2.0 Ds.

    No slippage of the cable core

    was observed during 36

    heating cycles.

    Fig. 6 Expansion/contraction behavior of cable core in vertical

    installation test

    After several cycles, the core movement showed a regular pattern

    until the end of the heating cycles.

  • 7/30/2019 1_review01

    5/6

    7HITACHI CABLE REVIEW No.18 (October 1999)

    With these difficulties in mind, we selected a dispersed

    hauling machine system, which has been successfully used in

    laying aluminum-sheathed EHV cables in steeply-inclined

    tunnels.

    A conventional hauling machine, however, was not suitable

    for the vertical cable laying, since it does not have a brake

    function during running mode (although it does have one insuspended mode). If the conventional hauling machine is used,

    gravity on the cable accelerates the speed of the machine

    caterpillars during running mode, and this acceleration causes

    the cable to fall. So these problems necessitated the

    development of a new hauling machine equipped with a

    regenerating brake. This regenerative braking is achieved by an

    induction generator/motor that is used as a motor during the

    sending operation and is switched to a generator function when

    braking force is required. The generated energy fed back to a

    power source through an inverter produces a maximum braking

    force of 7.4-kN in running mode. Also, a new governing

    system in the hauling machine was developed. This system

    provides speed control supplemented by torque control

    which enables every hauling machine to be synchronized

    without slack in the cable.

    4CONSTRUCTION WORK

    Construction of the 500-kV XLPE cable circuits

    commenced in November, 1997. Prior to cable laying work,

    Hitachi Cable, Ltd. conferred with Shanghai Cable

    Transmission and Distribution Co., an owner-appointed

    installation contractor, on the cable laying procedure including

    familiarization with the new hauling machine. During trial

    operations, the hauling machines and associated main/localcontrol panels were carefully adjusted to eliminate any possible

    problems. After these thorough trials, the laying operation

    commenced.

    The cable drum was set up outdoors in front of the

    aboveground switching room. The cable was transferred from

    the drum to the upper horizontal cable gallery, then lowered

    into the 96-m vertical shaft. Fifteen sets of hauling machines

    were utilized in the laying operation. Among them, seven sets

    were installed on platforms in the vertical shaft which

    supported the weight of the cable (Figs. 7 and 8). The distance

    between the adjacent hauling machines in the shaft was

    determined to provide continuous laying even if one of thehauling machines experienced operating difficulties.

    Furthermore, four sets of the hauling machines set in tandem

    near the upper entry of the shaft could hold the full weight of

    the cable even if some of the hauling machines in the shaft

    became disabled.

    After laying the cable, it was fixed from bottom to top. The

    cable was removed from the hauling machine, lowered slightly

    into the shaft and given initial transverse offsets by cable

    benders, then fixed to the wall of the shaft with cleats. This

    procedure was repeated until the whole length of the cable was

    fixed in the snaked formation. The cable laying and fixing

    operation in the vertical shaft was completed in two days. Dust

    and other contaminants were excluded from the sealing end due

    to stringent quality control assembly procedures. A working

    tent formed a contaminant-free room and an air-conditionerwas installed to maintain temperature and humidity within

    acceptable ranges.

    After assembling the sealing ends, an electrical test was

    performed on the cable jacket. A test voltage of DC 20-kV was

    applied for 15 minutes to confirm the jackets integrity. Then, a

    dielectric security test was performed by an independent testing

    specialist appointed by the owner. An AC test voltage of 365-

    kV (85% of the factory test voltage and 1.26 Uo) generated by

    a frequency-variable resonance device was applied to the cable

    for 10 minutes via a test bushing equipped to the switchgear.

    The voltage tests and other commissioning tests on the first

    circuit were successfully completed in April 1998. The first

    circuit was put into commercial operation in July, 1998. The

    H15

    TRF. Hall

    96m

    Verticalshaft

    Direction of laying

    Cable Gallery

    E.V Floor

    14m

    14m

    Scaffolding

    HaulingMachine

    to : Hauling machines

    Cable Drum

    GIS Room

    H14

    H13

    H12

    H11

    H9

    H8

    H7

    H6 H3

    H2 H1

    H1 H15

    H10

    14m

    14m

    14m

    14m

    25m 30m

    E.V Floor

    E.V Floor

    E.V Floor

    Cable GalleryE.V Floor

    Fig. 7 Arrangement of hauling

    machines

    15 sets of hauling machines were

    effectively dispersed to lower the

    cable into the vertical shaft.

    Fig. 8 Lay ing of 500-

    kV XLPE cable

    in vertical shaft

    Newly developed hauling

    machines were set on

    platforms in the vertical

    shaft.

  • 7/30/2019 1_review01

    6/6

    8 HITACHI CABLE REVIEW No.18 (October 1999)

    Fig. 9 Ext ernal appearance of control build ing in the power

    station

    The first 500-kV XLPE cable circuit in the most advanced pumped

    storage power plant, THP, commenced its operation in July, 1998.

    second circuit was completed and put into service in July, 1999

    (Fig. 9). As for the third circuit, the cable laying work and

    assembly of the sealing end on the switchgear side are

    completed. It is expected that all construction work will be

    completed by the end of 1999, and the THP will then become

    fully operational and reinforce the stability of the power supply

    in the East China Network.

    He Yongquan

    Deputy Chief Engineer, Tianhuangping PumpedStorage Power Station Construction Co.Received BE Degree in Electric Engineering fromZhejiang University in 1969.Chief Supervisor Engineer for EL-Mech., Equipmentinstallation of THP Project.Member of Association of China Hydropower andAssociation of Electric Engineer

    Tatsuji Ishibashi

    Assistant Manager, Power Cable Engineering Dept.,Hitaka Works, Hitachi Cable, Ltd.Received BE Degree in Electric Engineering fromKyoto University in 1983.Currently engaged in design of EHV cables andsystems.Member of IEE of Japan.

    Katsuhiko Yamamoto

    Assistant Manager, Power Cable Accessories &Distribution System Dept., Hitaka Works, HitachiCable, Ltd.Graduated in Electrical Engineering from MatsumotoTechnical High School in 1963.Currently engaged in design of EHV cableaccessories.

    Kazutoshi Abe

    Manager, Engineering & Development Sec., PowerCable Construction Engineering Dept., Hitaka Works,Hitachi Cable, Ltd.Received the BE Degree in Electric Engineering fromYamagata University in 1985.Currently engaged in engineering EHV cablesystems.Member of IEE of Japan.

    Tetsuyo Yoneda

    Assistant Manager, Power Cable Construction Dept.,Hitaka Works, Hitachi Cable, Ltd.Received BE Degree in Electric Engineering fromOsaka University in 1978.Currently engaged in construction of power cablesystems.

    5CONCLUSION

    A 500-kV XLPE cable designed for vertical installation

    was developed and applied in a 96-m vertical shaft in theTianhungping Pumped Storage Power Plant. A hauling

    machine with a regenerating brake was also developed for the

    laying of the cable in deep vertical shaft. The first 500-kV

    XLPE cable circuit was successfully put into service in July,

    1998.

    This successful vertical cable installation will accelerate the

    adoption of EHV XLPE cables in hydropower stations and

    deep underground transmission lines.

    6ACKNOWLEDGMENT

    The authors wish to express their deepest appreciation toShanghai Cable Transmission and Distribution Co. for their

    generous cooperation during every stage of the construction of

    the cable circuits.

    REFERENCES

    (1) K. Ogawa et al., The Worlds First Use of 500-kV XLPE

    Insulated Aluminum Sheathed Power Cables at The

    Shimogo and Imaichi Power Stations, IEEE 89 SM 643-8

    PWRD (1989)

    (2) N. Palmieri and G.M. Lanfranconi, Extra High-Voltage

    Oil-Filled cables (From 300 to 400-kV) Laid in Vertical

    Shafts, CIGRE 21-06, (1973)

    (3) S. Mori et al., Investigation of Thermal Behavior of 275-

    kV XLPE Cable in Vertical Installation, Proceeding of

    Annual Convention 1981 of IEE of Japan, Paper No. 1191

    (in Japanese)

    (4) K. Kaminaga et al., Research and Development of 500-kV

    XLPE Cables - Study on Thermo-mechanical Behavior andInstallation Method, Proceeding of Annual Convention

    1986 of IEE of Japan, Paper No. 1350 (in Japanese)

    (5) C. A. Arkell and W. E. Blake, Installation of E.H.V. Oil

    Filled Cables in Deep Shaft, IEE Conference Publication

    No. 44, pp. 213-217 (1968)

    (6) G. Bazzi et al., 400-kV Cable Installations in Mexico,

    IEEE Trans. PES F77 636-4 (1977)

    (7) M. Nakanishi et al., An Installation of an EHV OF Cable

    Laid in a Vertical Shaft, Sumitomo Electric Technical

    Review No. 121, pp. 31-44. (1982)