Upload
shahpinkal
View
217
Download
0
Embed Size (px)
Citation preview
7/30/2019 1_review01
1/6
500kV Aluminum-Sheathed XLPE Cable in a 96m Vertical Shaft
U.D.C. [621.315.221.712.027.85: 669.71:678.742.2]: 621.315.232
He Yongquan*
Tatsuji Ishibashi**
Katsuhiko Yamamoto**
Kazutoshi Abe**
Tetsuyo Yoneda**
ABSTRACT: Three 500-kV XLPE cable circuits were supplied and installed in a 96m
vertical shaft at Tianhuangping Pumped Storage Power Station in the P. R. of China.
The cable was specially designed to prevent the cable core from slippage and to
compensate radial expansion and contraction of the thick insulation. A hauling machine
featuring regenerative braking was developed and utilized to vertically install the cable.
The cable laying work was carried out by an installation contractor appointed by the
owner under the supervision of Hitachi Cable, Ltd. The first 500-kV XLPE cable circuit
was successfully put into service in July, 1998, the second in July, 1999 and the third
circuit is under construction and will be completed by the end of 1999.
1 INTRODUCTION
To cope with increasing peak-power regulation and to
ensure stability of the power supply in the East China Network,
East China Electric Power Group Co. and the appointed
construction firm Tianhuangping Pumped Storage Power
Station Construction Co. launched the construction of a pure
pumped storage power plant in 1993. This new power plant,
Tianhuangping Pumped Storage Power Station (THP), is
situated in Anji Country Zhejiang Province, which is 260 km
southwest of Shanghai, a center of high load demand in the
network (Fig. 1). The main features of THP are (1) a total
installed capacity of 1800 MW (6300 MW) composed of six
sets of Francis-type turbine, reversible units installed in an
underground powerhouse complex: (2) a maximum 607-mgenerating head difference between the upper and lower
reservoirs: and (3) a water-conveyance system with a conduit
length to potential head ratio of 2.5. Three 500-kV XLPE cable
circuits are employed to carry the plant output from the
underground power house via a 96-m vertical shaft to
preliminary overhead transmission lines in the network (Fig. 2).
During the planning stage, both oil-filled cable and XLPE
cable were considered for use as the main feeders. The XLPE
cable was finally selected because:
(1) 500-kV XLPE cables are being used in a number of
pumped storage power plants in Japan(1).
(2) XLPE cable has low dielectric loss and superior flame-retardant characteristics due to its oil-free construction.
(3) High stati c pressure at the bottom of the shaf t and
complicated control of oil pressure during terminating work
can be avoided.
However, prior to installing applying a corrugated aluminum-
sheathed XLPE cable in the deep vertical shaft, we had to
satisfy two requirements:
(1) A mechanical design of the cable that prevents the cable
core from slipping through the corrugated aluminum sheath.
3HITACHI CABLE REVIEW No.18 (October 1999)
* Tianhuangping Pumped Storage Power Station Construction Co.** Hitaka Works, Hitachi Cable, Ltd.
Fig. 1 Location of Tianhuangping pumped storage power station
A new power station with an installed capacity of 1800 MW is
located 260 km southwest of Shanghai.
Chengdu
P.R. OF CHINA
Wuhan
Beijing
Guangzhou
Hongkong
Shanghai
TIANHUANGPINGPOWER STATION
N
(2) An appropriate cable laying technique that prevents the
cable from slipping during laying work.
The first requirement was satisfied by a specially designed
bedding layer applied to the cable core and lightly compressed
by the corrugated aluminum sheath. An experimental length of
the cable was manufactured and subjected to a mechanical
assessment which showed that no slipping occurred. Thesecond requirement was met by developing a new hauling
machine with regenerative braking.
By introducing these techniques, three circuits of 500-kV
XLPE cables, the total length of which is 2090m, were safely
and efficiently installed in the 96 m vertical shaft at the power
station. Following assembly of the sealing ends and the field
tests, the first 500-kV XLPE cable circuit was completed in
April and put into service successfully in July, 1998. The
second circuit was put into commercial operation in July, 1999.
This paper describes the main features of the cable design
for vertical installation, the verification of this design, the cable
laying equipment and the construction of the cable circuits.
7/30/2019 1_review01
2/6
4 HITACHI CABLE REVIEW No.18 (October 1999)
2POWER CABLE SYSTEM DESIGN
2.1 Cable design for vertical installation
Table 1 lists the electrical requirements and the site
conditions to which the cable system was designed. As
previously mentioned, the salient point of the THP cable
installation was that the 500-kV aluminum-sheathed XLPE
cables were installed in a 96-m vertical shaft which lay in the
middle of the cable route. The total difference in elevation of
the entire cable route was 105 m (including the aboveground
switchgear side).In the past several decades, oil-filled cable have mainly
been utilized in vertical installations where the elevation
difference was 100m and above(2). On the other hand, as far as
the authors know, there was no precedent for an application of
Fig. 2 Power house complex
and cable route profile
Three 500-kV XLPE cable
circuits were installed in a 96-
m vertical shaft to carry plant
output to overhead trans-
mission lines.
TABLE 1 CABLE SYSTEM PARAMETERSThe 500-kV XLPE cable systems were designed according to the
parameters shown in the table.
A LIWV of 1675 kVp was required for cable and accessories.
500kVXLPEcables
DoorGIS
500kVSwitchyard
Original groundline
Transformer hall
Tailgate gallery
Machine hall
214.4
233.1238.9
228.2
350.2
285.0
216.2
246 .9I
II
III
I
II
III
IV
VI
V
500kV cable& access
shaft(8m Dia.) Lower reservoir
Dimensions in m
TRF.
Cross-section of cable &access shaft
1.6
0.6
Elevator
Platform
17.0
8.2
180.0 29.0
15.0
22.4
24.4
47.5
500kV XLPEcables(3 circuits)
a corrugated aluminum-sheathed XLPE cable to such a deep
vertical shaft. Since oil-filled cables are often used in vertical
installations, great attention has been paid to the design of the
metallic sheath and the hydraulics including accessories.
However, extensive research has not been conducted on
slippage of the cable core through the metallic sheath. This is
because the metallic sheath of the oil-filled cable can be
applied tightly over the core, and the existence of a gap
between them is not an issue.
However, this is not the case with EHV XLPE cable.
Usually, an EHV XLPE cable is designed to maintain a certainamount of gap between the metallic sheath and the underlying
component so as not to obstruct the radial expansion of the core
due to heat. This cable design, including the gap, results in a
low coefficient of friction between the core and the metallic
sheath, typically between 0.3 to 0.8 at ambient temperature(3), (4).
When we committed to the application of the 500-kV
XLPE cable at THP, we examined how to increase the
restrictive force on the core a key factor in vertical
installation. During the cable design, careful attention was paid
to both the grasping force and to the thermal behavior of the
thick XLPE insulation. Namely, the 500-kV XLPE cable had to
satisfy the following diverse conditions simultaneously: (1)restrain the cable core firmly to prevent slippage, even at low
temperatures during which the core diameter shrinks; and (2) to
not obstruct the expansion of the cable core at high
temperature. These conditions were satisfied by developing a
special bedding layer, the design of which is described in the
following section.
2.2 Construction of cable and sealing end
Table 2 lists the construction specifications and Fig. 3
shows the appearance of the 500-kV XLPE cable. The cable
core is composed of an 800 mm 2 copper conductor and 35 mm-
thick XLPE insulation. The insulation thickness was
determined according to the required lightning impulse
Category Items Particulars
Site
conditions
Electrical
ratings
Nominal system voltage (U)
Highest system voltage (Um)
Lightning impulse withstand voltage (LIWV)
Switching impulse withstand voltage (SIWV)
500 kV
550 kV
1675 kVp
1240 kVp
Three-phase symmetrical fault current
Single-phase fault current
System frequency
Nos. of circuit
Route length
Elevation difference at vertical shaft
Designed ambient temperature
50 kA for 3 s
40 kA for 2 s
50 Hz
3
219 m / 222 m / 256 m
96 m
14C to 40C
Transmission capacity for each circuit:
(a) Rated current
(b) Max. current for pumping start-up
873 A (756 MVA)
890 A (770 MVA)
7/30/2019 1_review01
3/6
5HITACHI CABLE REVIEW No.18 (October 1999)
withstand voltage (LIWV) of 1675-kVp. A specially-designed
bedding layer (5.7mm thick) and a corrugated aluminum sheath
were applied over the core. The inner diameter of the
aluminum sheath was slightly smaller than the outside diameter
of the bedding in order to obtain the necessary restrictive force
on the core. The aluminum sheath was protected with a flame
retardant PVC jacket, followed by a semi-conducting coating.The bedding layer, one of the most significant components
of this cable, was carefully designed. According to the
operational conditions of the cable systems, the diameter of the
core varies by approximately 4mm in the conductor
temperature range of 14C to 90C. To overcome this core
variation, lightly-amalgamative cushion tapes, which absorb
the expansion of the core and woven copper woven semi-
conductive tape were applied over the core. The amalgamative
nature of the tape prevents slippage between the core and the
bedding layer as well as between the tapes. The thickness of
the bedding layer was selected so that the maximum
prospective indent by the aluminum sheath did not affect the
underlying cable core.
Items Particulars
Type designation XLPE/CSA/PVC
Thickness of bedding layer
Thickness of aluminum sheath
5.7 mm
3.9 mm
Diameter of cable
Mass per unit length
* L0I: Limited Oxygen Index
160 mm
28 kg/m
Conductor:
(1) Cross-section(2) Construction 800 mm
2
(copper)Segmental circular
Insulation
(1) Material
(2) Thickness
Inert gas cured XLPE
35.0 mm
Jacket:
(1) Material
(2) Thickness
Flame retardant PVC (L0I*30)
5.5 mm
TABLE 2 CONSTRUCTION OF 500-KV XLPE CABLEThe bedding layer was carefully designed to absorb any expansion
of the core and to grasp the core firmly.
Fig. 3 Appearance of 500-kV
XLPE cable
The diameter and mass per
unit length are 160-mm and28-kg/m, respectively.
At the THP power plant, the 500-kV cables were
terminated with SF 6-gas-type sealing ends on both the
transformer and the switchgear. Figure 4 illustrates the general
arrangement of the sealing end, which was composed of
synthetic-resin bell mouth, silicone-oil-impregnated
polyethylene sheets as internal insulation, and epoxy insulator
as external insulation. Expansion and contraction of thesilicone oil volume contained in the sealing end due to
temperature variation is compensated by a built-in oil reservoir
made of metallic bellow, which enables a compact and space
saving installation. The sealing ends were connected to the
transformer horizontally and to the GIS vertically. On the
transformer side, spacers were added in the sealing end to
prevent the cable core from dangling and to maintain the
specified gap between the internal and external insulations.
The electrical performance of the cable and the sealing end
was verified at the manufacturers factory. Sets of the cable and
sealing-end assemblies were subjected to special and internal
tests. In the special test, the assembly surpassed all aspects of
the electrical requirements. The internal test was performed
spontaneously in order to determine the ultimate characteristics
of the cable and verified that the characteristics of the newly
designed cable were of equally high quality to those of the
manufacturers previous 500-kV XLPE cables (Table 3).
3CONSTRUCTION DESIGN
3.1 Mechanical performance and installation design
To assess the mechanical performance of the cable, an
experimental length was manufactured. This cable was
subjected to a series of horizontal and vertical tests. Firstly, a
1m cable sample was laid horizontally, clamped and the corewas extracted from the cable using a winch through a load cell.
The required pulling forces were 10kN/m at ambient
temperature and more than 5 kN/m at 75C (an average
insulation temperature during actual service). In the latter case,
the exact force required to extract the core could not be
measured because slippage between the conductor and the
insulation occurred. Similar tests were performed on a 3m
cable sample laid horizontally and a 1m sample laid vertically.
In both tests, slippage of the conductors occurred prior to any
measurable core movements. These results imply that the
;
;
; ;
;
;
;
;
;
;
;
;
;
;
;
;
;
;
290
810
660
650
600
60
1500
1755 1620
Epoxy InsulatorInsulating oil
Bell mouthOil reservoir
PE insulating sheetsInsulating flange
62314 5
14
25
36
Fig. 4 Structure of 500-kV sealing end
A combination of bel l mouth and PE sheets pressurized by oilreservoir were employed as an internal insulation.
7/30/2019 1_review01
4/6
6 HITACHI CABLE REVIEW No.18 (October 1999)
designed cable has sufficient grasping force on the core and
can be considered appropriate for vertical installation.
Following these preliminary tests, the cable was subjected
to a vertical installation test involving heat cycles. Two lengths
of cables were installed in a 15-m-high scaffold construction in
a snaked formation with pitches of 6m and deflections of (a)
1.5Ds (Ds: average diameter of aluminum sheath) and (b)
2.0Ds. The cables were fixed to the scaffolding by holding
cleats at their axial centers and by sliding cleats at their apexes
(Fig. 5). Both ends of the cables were set freely. The cables
were attached with terminals and bonding wires through which
a circulating current flowed to provide daily heating cycles
(from ambient temperature to 90C, 8 h ON/16 h OFF). After
several heating cycles, the longitudinal protrusion and
contraction of the cable core followed a regular pattern with
each heating (Fig. 6). A total of 36 heating cycles were applied,
and neither significant variation of the pattern nor slippage ofthe core were observed in either cables during the entire
heating process.
The results of the heating cycles indicate that both snaked
formations were acceptable. However, the pattern of core
movement under the deflection of 2.0Ds was more stable. This
snaked formation was therefore adopted for the THP vertical
installation. On completion of this test, the cables were
dismantled and inspected. Undue deformation was not
observed in the cable components, i.e., the core, the bedding
layer, and the aluminum sheath. These tests confirmed the
propriety of the cables mechanical design.
3.2 Development of laying equipment
When cables are laid in vertical shafts, they are usually
threaded into the shaft from top to bottom. The THP cable
installation followed this traditional method due to the limited
working space in the underground power house. In previous
vertical installations, the bond pulling methods use a wire rope,
a turn pulley and winch installed at the upper mouth of a shaft
and devices to prevent the cable from rotating (5) (7). However, in
the THP cable installation, it was difficult to utilize the bond
pulling method due to there being:
No appropriate place to install a turn pulley
Anticipated undue side wall pressure on the cable at the
bending portion of the upper entry of the shaft.
TABLE 3 PERFORMANCE OF CABLE AND SEALING ENDSets of cable and sealing end assemblies withstood all the test voltages.
Category Items Test condition
Special test
Internal test
* d: Dia. of conductor; D: Overall dia. of cable.
Bending test
Impulse withstand test at 953C
AC withstand test at ambient temperature
Partial discharge test
Bending test
Heating cycle
AC withstand strength test after heating cycle
Impulse breakdown voltage test after AC test
Bending dia. 3500 mm [=18(dD)]*3 times
1675 kVp/10 shots
AC 480 kV10 h, followed by AC 625 kV/24 h
P.D. less than 10pC at AC 430 kV & AC 447 kV
Bending dia. 2450 mm [=13(dD)]*3 times
(8 h ON/16 h OFF)20 cycles
AC 1150 kV/2 h, withstood
More than 2625 kVp
3
2
1
01
2
3
4
5
6
7
1 2 3 4 5
Nos. of heating cycles
Expansion/contractionlengthof
coremm
Contra
ction
Expansion
6 7 8
Core movement at lower end
Deflection : 2DsDeflection : 1.5Ds
Fig. 5 Ex ec ut io n of 15 mhigh vertical installa-
tion test
(a) Left: deflection = 1.5 Ds,
(b) Right: deflection = 2.0 Ds.
No slippage of the cable core
was observed during 36
heating cycles.
Fig. 6 Expansion/contraction behavior of cable core in vertical
installation test
After several cycles, the core movement showed a regular pattern
until the end of the heating cycles.
7/30/2019 1_review01
5/6
7HITACHI CABLE REVIEW No.18 (October 1999)
With these difficulties in mind, we selected a dispersed
hauling machine system, which has been successfully used in
laying aluminum-sheathed EHV cables in steeply-inclined
tunnels.
A conventional hauling machine, however, was not suitable
for the vertical cable laying, since it does not have a brake
function during running mode (although it does have one insuspended mode). If the conventional hauling machine is used,
gravity on the cable accelerates the speed of the machine
caterpillars during running mode, and this acceleration causes
the cable to fall. So these problems necessitated the
development of a new hauling machine equipped with a
regenerating brake. This regenerative braking is achieved by an
induction generator/motor that is used as a motor during the
sending operation and is switched to a generator function when
braking force is required. The generated energy fed back to a
power source through an inverter produces a maximum braking
force of 7.4-kN in running mode. Also, a new governing
system in the hauling machine was developed. This system
provides speed control supplemented by torque control
which enables every hauling machine to be synchronized
without slack in the cable.
4CONSTRUCTION WORK
Construction of the 500-kV XLPE cable circuits
commenced in November, 1997. Prior to cable laying work,
Hitachi Cable, Ltd. conferred with Shanghai Cable
Transmission and Distribution Co., an owner-appointed
installation contractor, on the cable laying procedure including
familiarization with the new hauling machine. During trial
operations, the hauling machines and associated main/localcontrol panels were carefully adjusted to eliminate any possible
problems. After these thorough trials, the laying operation
commenced.
The cable drum was set up outdoors in front of the
aboveground switching room. The cable was transferred from
the drum to the upper horizontal cable gallery, then lowered
into the 96-m vertical shaft. Fifteen sets of hauling machines
were utilized in the laying operation. Among them, seven sets
were installed on platforms in the vertical shaft which
supported the weight of the cable (Figs. 7 and 8). The distance
between the adjacent hauling machines in the shaft was
determined to provide continuous laying even if one of thehauling machines experienced operating difficulties.
Furthermore, four sets of the hauling machines set in tandem
near the upper entry of the shaft could hold the full weight of
the cable even if some of the hauling machines in the shaft
became disabled.
After laying the cable, it was fixed from bottom to top. The
cable was removed from the hauling machine, lowered slightly
into the shaft and given initial transverse offsets by cable
benders, then fixed to the wall of the shaft with cleats. This
procedure was repeated until the whole length of the cable was
fixed in the snaked formation. The cable laying and fixing
operation in the vertical shaft was completed in two days. Dust
and other contaminants were excluded from the sealing end due
to stringent quality control assembly procedures. A working
tent formed a contaminant-free room and an air-conditionerwas installed to maintain temperature and humidity within
acceptable ranges.
After assembling the sealing ends, an electrical test was
performed on the cable jacket. A test voltage of DC 20-kV was
applied for 15 minutes to confirm the jackets integrity. Then, a
dielectric security test was performed by an independent testing
specialist appointed by the owner. An AC test voltage of 365-
kV (85% of the factory test voltage and 1.26 Uo) generated by
a frequency-variable resonance device was applied to the cable
for 10 minutes via a test bushing equipped to the switchgear.
The voltage tests and other commissioning tests on the first
circuit were successfully completed in April 1998. The first
circuit was put into commercial operation in July, 1998. The
H15
TRF. Hall
96m
Verticalshaft
Direction of laying
Cable Gallery
E.V Floor
14m
14m
Scaffolding
HaulingMachine
to : Hauling machines
Cable Drum
GIS Room
H14
H13
H12
H11
H9
H8
H7
H6 H3
H2 H1
H1 H15
H10
14m
14m
14m
14m
25m 30m
E.V Floor
E.V Floor
E.V Floor
Cable GalleryE.V Floor
Fig. 7 Arrangement of hauling
machines
15 sets of hauling machines were
effectively dispersed to lower the
cable into the vertical shaft.
Fig. 8 Lay ing of 500-
kV XLPE cable
in vertical shaft
Newly developed hauling
machines were set on
platforms in the vertical
shaft.
7/30/2019 1_review01
6/6
8 HITACHI CABLE REVIEW No.18 (October 1999)
Fig. 9 Ext ernal appearance of control build ing in the power
station
The first 500-kV XLPE cable circuit in the most advanced pumped
storage power plant, THP, commenced its operation in July, 1998.
second circuit was completed and put into service in July, 1999
(Fig. 9). As for the third circuit, the cable laying work and
assembly of the sealing end on the switchgear side are
completed. It is expected that all construction work will be
completed by the end of 1999, and the THP will then become
fully operational and reinforce the stability of the power supply
in the East China Network.
He Yongquan
Deputy Chief Engineer, Tianhuangping PumpedStorage Power Station Construction Co.Received BE Degree in Electric Engineering fromZhejiang University in 1969.Chief Supervisor Engineer for EL-Mech., Equipmentinstallation of THP Project.Member of Association of China Hydropower andAssociation of Electric Engineer
Tatsuji Ishibashi
Assistant Manager, Power Cable Engineering Dept.,Hitaka Works, Hitachi Cable, Ltd.Received BE Degree in Electric Engineering fromKyoto University in 1983.Currently engaged in design of EHV cables andsystems.Member of IEE of Japan.
Katsuhiko Yamamoto
Assistant Manager, Power Cable Accessories &Distribution System Dept., Hitaka Works, HitachiCable, Ltd.Graduated in Electrical Engineering from MatsumotoTechnical High School in 1963.Currently engaged in design of EHV cableaccessories.
Kazutoshi Abe
Manager, Engineering & Development Sec., PowerCable Construction Engineering Dept., Hitaka Works,Hitachi Cable, Ltd.Received the BE Degree in Electric Engineering fromYamagata University in 1985.Currently engaged in engineering EHV cablesystems.Member of IEE of Japan.
Tetsuyo Yoneda
Assistant Manager, Power Cable Construction Dept.,Hitaka Works, Hitachi Cable, Ltd.Received BE Degree in Electric Engineering fromOsaka University in 1978.Currently engaged in construction of power cablesystems.
5CONCLUSION
A 500-kV XLPE cable designed for vertical installation
was developed and applied in a 96-m vertical shaft in theTianhungping Pumped Storage Power Plant. A hauling
machine with a regenerating brake was also developed for the
laying of the cable in deep vertical shaft. The first 500-kV
XLPE cable circuit was successfully put into service in July,
1998.
This successful vertical cable installation will accelerate the
adoption of EHV XLPE cables in hydropower stations and
deep underground transmission lines.
6ACKNOWLEDGMENT
The authors wish to express their deepest appreciation toShanghai Cable Transmission and Distribution Co. for their
generous cooperation during every stage of the construction of
the cable circuits.
REFERENCES
(1) K. Ogawa et al., The Worlds First Use of 500-kV XLPE
Insulated Aluminum Sheathed Power Cables at The
Shimogo and Imaichi Power Stations, IEEE 89 SM 643-8
PWRD (1989)
(2) N. Palmieri and G.M. Lanfranconi, Extra High-Voltage
Oil-Filled cables (From 300 to 400-kV) Laid in Vertical
Shafts, CIGRE 21-06, (1973)
(3) S. Mori et al., Investigation of Thermal Behavior of 275-
kV XLPE Cable in Vertical Installation, Proceeding of
Annual Convention 1981 of IEE of Japan, Paper No. 1191
(in Japanese)
(4) K. Kaminaga et al., Research and Development of 500-kV
XLPE Cables - Study on Thermo-mechanical Behavior andInstallation Method, Proceeding of Annual Convention
1986 of IEE of Japan, Paper No. 1350 (in Japanese)
(5) C. A. Arkell and W. E. Blake, Installation of E.H.V. Oil
Filled Cables in Deep Shaft, IEE Conference Publication
No. 44, pp. 213-217 (1968)
(6) G. Bazzi et al., 400-kV Cable Installations in Mexico,
IEEE Trans. PES F77 636-4 (1977)
(7) M. Nakanishi et al., An Installation of an EHV OF Cable
Laid in a Vertical Shaft, Sumitomo Electric Technical
Review No. 121, pp. 31-44. (1982)