Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
SAFETY AND ENVIRONMENTAL PROTECTION IN A SYSTEM OF
PRODUCTION, STORING AND DISTRIBUTION OF AMMQNIA
BY
Dr. Theo Huberich
of
BASF AKTIENGESELLSCHAFT
AMMQNIA.DEPARTMENT
D-6700 LUDWIGSHAFEN/GERMANY
Paper for the
Symposium on Safety in Ammonia Plantsand Related Fecilities
American Institute of Chemical Engineers
Montreal / Canada
October 1981
1. Outline of BASF's posi tlon
In its Ludwigshafen works BASF produces in three plants daily upto 2500 metric tons of ammonta, which has to be deliveredpartly in gaseous and partly in liquid form to numerousindividual users within the works area. Some of theconsumers require liquid airanonia not as a raw material forsynthesis but for cooling purposes and therefore return gaseousairanonia to the network. Delivery to subsidiaries andpurchase of supplementary airanonia is handled by tank barges,while smaller outside customers are supplied by railtank cars. Some customers also take aqueous airanonia sol utionby way of railway tank cars or tank trucks. Storage capacityhas been installed to compensate for production outages andfluctuations in demand.
2. Statement of the problem
For the distribution of ammonia an interlocking grid hasbeen instalied which has to fuifi 11 the following re-quirements:
- Reliable supply of liquid,gaseous and aqueousammonia to various consumers even in case ofproduction outages or breakdown of one plant.
- Adaptation of the supply ratio of liquid andgaseous ammonia to the demand, which fluctuatesparticularly according to the season..
- Guarantee of maximum safety
- Compliance with. environmental regulations
^' Description of the Supply Grid
For the distribution of liquid, gaseous and aqueous ammoniaa pi pel ine grid of a total length of 70 km (40 miles),
Page 2
including branches, has been insta "lied in the ludwigshafen works.
The liquid aranonia grid is direct! y connected to the production
plants. Spherical tanks for the storage of about 2000 metric
tons ammonia at ambient temperature (pressure approximately
10 bar [145 psij ) are available to equalize short-term
fluctuations in supply and demand. In order to keep the grid
pressure of 25 bar (363 psi) independent of the pressure in the
intermediate expansion vessels of the synthesis plants, a buffer
vessel with a volume of 100 m (3500 ft ) is incorporated in the
grid, into which gaseous ammonia is constantly fed at a temperature
of 60 °C (140 °F). The flow into and out of the pressure storage is
controlled according to the liquid leve! in this buffer vessel.
The actual storage to cover the demand for ammonia during shut-
down of the synthesis plants consists of two large pressure-
less tanks, each of which holds 25 000 metric (27560 shtn)
tons of ammonia. The pressure in these cold storage
tanks is maintained by means of screw compressors, which
draw off the gas that normaUy evaporates in the tanks and
transfer it into the gaseous ammonia grid. For feeding
pressurized ammonia into the cold storage tanks a refrigeration
unit with reciprocating compressors is available. Cold
ammonia is heated to at least 5 °C (40 °F) by heat exchange
with hot water before i t is introduced into the 25 bar (363 psi)
liquid ammonia grid. The cold and pressurized ammonia storage
are connected by pi pel ine to a loading doek in the harbor,
where refrigerated and pressurized tank barges can be loaded
and unloaded. Railway tank cars can receive or discharge
pressurized ammonia at a railway loading station.
Page 3
The grid for gaseous ammonia operates at a pressure of 2 bar abs
(28 psig). It receives gaseous ammonia from the refrigeration
units of the synthesis plants and from the users of liquid
ammonta for-eooling purposes.
The volume of ammonia gas made available by the synthesis plants
can be controlled by operating their refrigeration units with
or without their ammonia compressors. If a further matching
between supply and demand is necessary, a unit for pressurizing
and liquefying is available in case of an excess of gaseous ammonia,
while an evaporator comes on line when more gaseous ammonia
is needed. The pressure in the gaseous ammonia grid is maintained
exclusively by means of an evaporator operating on hot water.
The by-product aqueous ammonia from the synthesis plant is brought
up to the required concentration of 25 %, resp. 3.0 % in an
absorption unit where gaseous ammonia is added. Captive users
are supplied with 25 % ammonia solution via a pipe grid.
For delivery to outside customers a loading station for rail-
way tank cars and tank trucks has- been installed.
The system described above assures an optima! supply to all users.
4. Installations for Safety and Environmental Protection
Plant safety and environmental protection are closely interreiated
with questions of safe supply.
Page 4
The measures taken in this regard in the Ludwigshafen works
wil! be illustrated by the foTIowing examples.
4.1 Liquid Ammonia Grid
For the construction of the pi pel ine grid for liquid ammonia •
seamless pipe with a nomina! diameter up to 200 mm (7.9 in) and a«=-*sr ' " a
nomina! pressure rating of at least 40 bar (580 psi) has been
used, preferably welded together. Where flanged joints are
necessary, for instance adjacent to valves, metal rings with
inserted asbestos gaskets have been used. The grid is sub-
divided into sections by numerous remotely controlled quick-v
action shutoff valves, with the volume contained in each
section beeing not larger than 5 m (175 ft. .). In case
of a leak the segment in question can be separated immediately
from the remainder of the network. Only a smal! number of
users wil! be affected by each shutoff since the pipeline
network is almost completely looped. The siubdivision into
segments also facilitates the installation of branchlines
for new users. Expansion valves have^ejn__insta_lled before
and after each quick-action shutoff valve. When necessary,
the contents of the isolated pipeline segment can be emptied
through a metal hose into a neighboring, stil! operating
part of the pipeline, which is done by means of a mobile
pump belonging to the works fi re department. Hoses and the
pump are afterwards purged with bottled nitrogen.
Page 5
4.2 Pi pel ine Network for Gaseous Ammonia
The pi pel ines of this network with a nomina! diameter up to 600 mm
(23.6 in) and a nomina! pre'-sure of 10 bar (145 psi) are long-
itudinaüy welded and'provided with f!at flanges and flat rjjbber
gaskets,,JUJ- necessary expansion beüows are made of stainless
steel. Temperature measuring points at the connections to* '•
refrigeration plants trigger alarms in case of breakthrough of
liquid ammonia into the gaseous ammonia network. I f there is*.
a sudden surplus of ammonia, e. g. in case of a plant fai!ure
on the part of a user, the pressure in the network is aüowed
to rise temporarüy from 2 to 3.5 bar abs (28 to 50 psi). This
pressure increase reduces the evaporation of üquid ammonia
in the refrigeration units connected to the network and
simultaneously increases the rate of absorption in the pro-
duction facility for aqueous ammonia which is automatically
switched to fuil load. At the same time the repressurizing
compressors are started. Only when a pressure of 4 bar abs (57 psi)
should be reached, ammonia and injected steam wou!d be released
into the air through. safety valves.
4.3 Barge Loading Facüities and Pi pel i nes
At the loading doek in the harbor the remotely controüed
articulated loading arms are equipped with remotely controüed
quick-action valves and quick-disconnecting flanges. In critica!
situations, e. g. a fi re in the harbor, these permit the barges
to cast off immediately, The loading and unloading is watched
via monitors. Remotely controüed water guns are available to
Page 6
fight ammonia spil!s and flres in the harbor area. The long
distance between the harbor and the ammonia storage requires
special safety measures for the pumping stations and un-
branched l i nes connecting them. Thus the 4.2 km (2.6 miles) l;ong
pressurized ammonia pipeline of 150 mm (6 in) diameter is
subdivided by qutck-action valves into five sections, each
of which is protected by safety valves arranged in cascade.
Volume flow and pressure of the ammonia are adjusted
exact!y at the pumping station. Rapid changes in flow vel oeity,
such as may be caused by a sudden closure of the loading device,
can cause pressure surges (so-called "water hammer") that can
seriously endanger the system, mainly the loading arm and
the fittings on the barges. The occurrence of a "water hammer"
was simulated on a digital computer using generally valid
pressure transient equations as a basis (cf. V. L. Streeter,
E. B. Willie,."Hydraulic Transients", McGraw Hill, New york).
At the same time pressure surges occurring at the pumping station
and the loading arm after pump fai l ure or rapid closure of
a valve were measured for various flow rates with the ai d of a
fast respondingrecorder when the pipeline was put into service.
3 ?When the volume flow rate was 100 m /h (3500 ft./h) and the
quick-action valve at the doek was closed within 1.5 secs.,
which is certainly less than the 2.9 seconds required for the
pressure surge to traverse the pipeline, the observed pressure
peaked at 13 bar (185 psi) instead of the calculated 20 bar
Page 7
(284 psi). When this measurement was repeated after liquid
anmonia had been passed through the pi pel i ne for a "longer
period and the pressure at the loading arm had been
inv.reased by partly closing the valve on the barge, the
pressure surge was much more pronounced. This leads to
the conclusion that inert gases dissolved in the liquid
anmonia (hL» j CH,, A) have a certain cushioning effect.
4.4 Col d Annnonia Storage
Special care was taken in designing safeguards for the cold
ammonia storage.
Both doublé wal! tanks have been errected at a safe distance
from neighboring plants and storage vessels in a depression2
measuring 10 000 m (2.5 acres). Liquid ammonia leaking into
the space between the inner and outer tank wal!s can be
pumped into the other storage tank or into the pipeline
network. Liquid ammonia escaping into the open will collect
in a concrete pit, where i t can be pumped out. '
In case of disaster foamed polystyrene panels stored.nearby
can be used to cover large quantities of escaped cold ammonia.
For fighting ammonia clouds eight water guns with spray nozzles
have been permanently instalied. In addition the fire department
stationed nearby has available mobile foam and water guns and
water guards for raising water curtains.
'This pit is also very useful when during tank revisions the oilcollected in the tank bottom has to be separated from the washwater.
Page 8
In case of a power fai l ure the pressure in the col d storage
tank can be kept constant by means of a diesel-driven
reciprocating compressor. Besides both tanks are secured
against an excess pressure of up to 80 mbar (8QQ mm'- 31. in water
column) by means of a dipleg seal filled with oil. Gas
that escapes through this dipleg seal is drawn off with
steam-driven injectors and after dilution with air ten times
in excess and preheating is ejected at a height of 20 m (65 ft.)
above the roof. Because of the problems in connection with
pi lot fTame and NO -formation a fl are was not used.A
In one of the tanks the temperatures near the wal! and in
the center were measured at various leve!s over a period
of twelve years. These measurements showed only minor
- temperature differences (up to 2 °c[5,6 °F]). between the
layer and the surface, even at a high liquid level. The
danger of a "rol! over" thus seems very improbable.
Equipment for circulating the contents of the tanks was
therefore not considered necessary.
4.5 Tank Car Loading Station
Over and above the safeguards which are required by law for
atank car loading facility, such as scales, derailers, "car
connected" warning light, quick-action valves in the
connecting lines and tripwires to keep the bottom valves of
the tank cars open during filling, the following safety
Page 9
equipment was installed:
The entire filling process is steered and monitored by a
computer. A step-wise program and the storage of important
data concerning the tank car prevent operating errors during
filling and an overfilling of the tank cars. The rip cord
mentioned above unhooks if the car is moved accidentally and
automatically allows the bottom valve of the tank car, which
is being bottom-loaded through an articulated l dading arm, to
close. This tripwire can also be unhooked by remote control
in case of leakage. When this happens the quick-acting valves
in the connecting l i nes are closed, an alarm is actuated,
breathing air is routed into the weighing shed and a water
curtain is raised around the entire loading area.
4.6 General Safety and Environmental Protection Measures
The entire ammonia distribution is monitored and regulated from
a control room. The plants that surround the central plant are
interconnected by an emergency speaker system. On a wind speed
and direction indicator in the control room personnel can
immediately recognize in case of an emergency which plants are
endangered. Through a hook-up to the central alarm teletyper
of BASF all interna! ammonia consumers can be forewarned with
preprogrammed announcements in case of emergency. Our safety
program is complemented by regular drills with the fire
Page 10
department, where for instance the pumping of amnonia out of
a damaged tank car is practiced.
Speaker system, emergency shower, eye douche, respirator and
protective clothing are available in all parts of the plant.
AU control rooms and rest rooms are provided with emergency
breathing air.
Extensive measures have also been taken to keep air and water
clean. In various parts of the plant the air and the spent .
cooling and waste water are monitored by analyzers.
In order to minimi ze pollution during noraial operation, inert
gas mixtures which contain ammonia and which originate in the
ammonia storage vessels, in the repressurizing units and in the
loading stations are collected and fed into a cold storage tank.
Subsequently the gas is drawn off through a refrigeration unit,
scrubbed with water under pressure and,burned as boiler fuelThe air drawn off during filling cars with aqueous ammonia or
from the aqueous ammonia tanks is also scrubbed.
At this time we are engaged in improving noise prevention in the
plant.
For the future we consider i t important to deepen experience
Page 11
exchanges with and the flow of experience to our customers.
In concluding these remarks i t should not be omitted to
express thanks to all companies whlch have partlcipated actively
In the exchange of experience in the important area of safety in
the storage and distribution of ammonia and which have thus
contributed to obtain the best solutions.
Page 12
Typteal daiiy production and consumptionintonsNH3
internaqueous consumere
40
nitricaad A 750
ionia syrrthesis plants
other inorg. products
60
15
fertfizer ) 740
> 190
60
* 30
BASF distribution of ammonia
Page 13
ammonia synthesis plants
/
aqueous-'• 7* ,' ,' ','. /ammoriia
gaseousammonia(2 bar)
/ ' X / S / S ./ / x ' ^ X /
'truck station / .S X f / S *
•'S/-/-'' ''jroanay'HVGt 11 X~T^
/ //.spheres'
^aqueoüs'ammonia plantJ t t t i ~
'/./ Areüquefiactlon
evaponzer' //A
2=2=3=5 cooling/ / /
V'/ s /s
processes
BASF distribution of ammonia
4,2 km (2,6miles)
fast recorder
•oEU(dn>
BASF measuring device for pressure wavesOSMttnlMTM tg -N» «011776 l
P bar
40-
30-
20-
10 -
O
F m3/h100
O -
H
open
closed l
P theoret.\\
O 10 20 30 40 50 60i
70 time s«an>
BASF strongly dampened waterhammer
P bar
40-
30 -
20 -
10 -
O
F m3/h100
O -
H
open
closed
P theoret.\l
safty valve open
Oi
10i
20l
30l
40i
50l
60
•o(UtafD
70 time s
BASF weakly dampened water ham mer
air
s team
Lr
r, rf-ti** dryNorT
< "~* 1
•
««
1
*
interna! tank
tank root
bottorrw
oil Styropor'0'-concrete
outside tank bottom
armoured concrete
inlet
to compression
rwith quick stop valve
outlet
electric heating in ring foun'dationriver gravel with bitumen
steamTJP>
(Om
doublé wall tanks A and B
Page 18
roof layers
inside tank roof
tank A : glass fiber matsandStyropor® concrete
inside tank wall
tank B 2 Neopolen^plates withsteel bandages
flat steel bondageLucobit® foil(polyolefine - bitumen)bitumen - Al - foilStyropor® concretetar - boardStyropor® plates (tank A )Neopolen® plates (tank 8 )steel roof
inside tank bottom
outside tank wall
bottom layers :inside tank bottomasphalt3 Styropor concrete layersbitumen with graveland wire meshoutside tank bottomelectric heatingin river gravelwith bitumen
o -oo <=> oarmoured concrete'l
> o o o o co o o o oo o o o o '
l |o o o o oo *o^o o o
o o ao S
ringofoundationo0^ e
BASF tank isolation A and B
water curtain/ fa fa fa fa fa
N /
weighingstation o£_al:
gas/liquid
v5
raillscale*j
rip cord
centralcontrolroom
.^ 1
LJLV v " "
rail 2
rail 1
connected " sign
derailer
o"o push button
key switch
rail car station - safety system
ammonia gassystem O bar
Ibar
screwcompressors
tanks
drain - vessels in theammonia synthesisplant and ammoniadistribution plant
[A . A , T"!—y v v /
condensers anddrain - vessels inthe NH3 recom =pression
O O
rail-cars
to boiler house
water
coolingequipment
ships
aqueousammonia
spheres
-ao»10roINio
BASF ammonia- inertgas-systemOM335nlU7IM Lfl-N( 903» 775 i
neighboringplants
distribution plant
winddirection
windvelocity
plan and windgauge of the plant