1723295

  • Upload
    qzm74l

  • View
    217

  • Download
    0

Embed Size (px)

Citation preview

  • 8/13/2019 1723295

    1/13

    Overview

    Project Number

    Project Purpose

    Project SponsorProject Manager

    Tracking Project Progress

    Contract Administration

    Planning Activities

    Estimating Activities

    Human Resources

    Quality Management

    Inspections

    Procurement Procurement Planning

    The EPO project management checklists are intended to assist the project manager in planning, executing

    and controlling projects. The checklists consist of Yes/No questions based on the knowledge areas in the

    PMBOK 2004 edition. If the answer to a question is No, review the explanation provided and consider

    what needs to be done in your organization or on your project to move to a Yes answer. Suggested EPO e-

    Books and Templates are identified to facilitate the change from No to Yes answers.

    Managing Issues & Changes

    Closing the Project

    Planning the Scope

    The content list below can be used to jump to a selected topic.

    PMBOK Knowledge Area Project Management Topic

    Obtaining Project ApprovalIntegrationInitiating the Project

    Sponsoring DepartmentPerforming Department

    Project Management Checklist

    Project Informat ion

    Project Name

    Scope

    Time

    Communications

    Monitoring Project Costs

    Cost Estimating Project CostsEstablishing the Budget

    Stakeholder Identification

    Quality

    Risk Risk Identification

    Evaluating Bids & Proposals

    Risk Assessment

    Risk Response Planning

    Planning the Work

    Reporting Project Status

    Communications Planning

    Testing

    Developing the Schedule

    Monitoring the Schedule

    Human Resource Planning

    Managing the Team

    EPO Template 2006 Gord Gibben, PMP Version 7.0

  • 8/13/2019 1723295

    2/13

    Integration

    Question Y/N Explanation EPO Template EPO e-book

    Is there a well-defined process to

    identify potential projects?

    The first step in the project approval process is the

    identification of potential projects. This can be part of a

    strategic or annual planning process or triggered by some

    external business event.

    Potential Project

    Identification

    Project Prioritization

    & Approval

    Has a project sponsor been identified

    for each potential project?

    The project sponsor is a key interface between the project

    team and senior management. Project sponsors are often

    responsible for providing resources and setting direction for

    the project.

    Potential Project

    Identification

    Project Prioritization

    & Approval

    Does a screening & prioritization

    process exist for potential projects?

    The needs of potential projects will often surpass the

    available resources and finances. Prioritization will establish

    the relative importance of competing projects and screen out

    projects will low importance or poor benefits.

    Potential Project

    Identification, Project

    Priority & Approval

    Project Prioritization

    & Approval

    Are potential projects prioritized by

    business management prior to

    approval?

    Prioritization is not an approval process; rather it is a

    screening and ranking process. The output from

    prioritization is a list of projects that have been ranked

    according to their relative importance.

    Project Priority &

    Approval

    Project Prioritization

    & Approval

    Does a Project Approval Committee

    exist to review and approve projects?Project prioritization should be done by department

    managers and division Vice Presidents. Project approvals

    are obtained from executives who belong to a Project

    Approval Committee.

    Project Business

    Case, Project

    Priority & Approval

    Project Prioritization

    & Approval

    Is a business case prepared for each

    project approval?The Project Business Case describes the project costs and

    benefits to enable a business decision whether or not to

    proceed with the project.

    Project Business

    Case

    Project Prioritization

    & Approval

    Is a business need assessment

    conducted for each potential project?The Business Need Assessment provides an analysis of the

    high level business requirement being addressed by the

    project and an opportunity to comment on the relative

    importance of the project.

    Project Business

    Case

    Project Prioritization

    & Approval

    Is a cost/benefit analysis completed

    for each project?

    The cost benefit analysis is performed to determine if the

    benefits of completing the project outweigh the costs of

    performing the work

    Cost Benefit

    Analysis

    Project Prioritization

    & Approval

    Are objective criteria such as Return

    on Investment (ROI) or payback

    period used to prioritize and approve

    projects?

    Return on Investment (ROI) is a percentage based on the

    net income from a project divided by the costs of the project.

    The payback period for a project is the time it takes for the

    benefits of a project to repay its costs.

    Cost Benefit

    Analysis

    Project Prioritization

    & Approval

    Are project approvals based on

    business, financial and technical

    criteria?The Project Approval Committee (or a similar group of

    senior management) needs to balance the business,

    financial and technical criteria from a corporate perspective

    when granting approvals to proposed projects

    Project Business

    Case

    Project Prioritization

    & Approval

    Has a Project Charter been prepared? The Project Charter is the document that formally

    acknowledges the existence of the project. It may beprepared by the Project Sponsor, the Project Manager, or as

    a collaborative effort.

    Project Charter Project Initiation &

    Scope Planning

    Are project assumptions

    documented?

    Assumptions are conditions upon which the project is based.

    They often involve a degree of risk and express situations

    that the project may encounter. These assumptions must be

    communicated to project stakeholders and confirmed where

    required.

    Constraints &

    Assumptions

    Checklist

    Project Initiation &

    Scope Planning

    Have project constraints been

    documented?

    Constraints are restrictions that will impact project

    management options. Because these constraints will limit

    the project management approaches or alternatives

    available, it is imperative that both Project Sponsor and

    Project Manager share an understanding of these limitations

    Constraints &

    Assumptions

    Checklist

    Project Initiation &

    Scope Planning

    Has the Project Manager beenassigned and his/her authority

    defined?

    The Project Manager should be assigned prior to projectinitiation and his/her authority should be defined and agreed

    to by the project sponsor.

    Project Charter Project Initiation &Scope Planning

    Project Management Checklist

    Obtain ing Project Approval

    Init iat ing the Project

    Tracking Project Progress

    EPO Template 2006 Gord Gibben, PMP Version 7.0

  • 8/13/2019 1723295

    3/13

    Integration

    Are project team tracking meetings

    held to monitor progress and discuss

    issues?

    Project team tracking meetings should be held on a regular

    basis to discuss progress on activities and status of high

    priority risks and open issues, changes and decisions.

    Team Tracking

    Meeting

    Project Tracking

    Do project team members report time

    spent on project activities?

    Time reports should be completed on a regular basis (daily

    or weekly) by team members and reviewed by team leads or

    the project manager.

    Time Report,

    Tracking View

    Project Tracking

    Is there a process in place to manage

    project issues?

    An issue is a situation that occurs outside the control of the

    project team that must be resolved in order for progress to

    continue. In most cases, the issue must be resolved by a

    certain date or there will be an adverse affect on the project

    deliverables, target dates or costs. The resolution to the

    issue needs to be documented and understood by all parties

    affected.

    Project Issue,

    Change

    Management Log

    Issue & Change

    Management

    Is a formal change management

    process used on the project?

    Change is a constant on projects; it is a reality of project

    management. Changes require deviations from project plan

    and can impact project scope, cost or schedule. The

    changes must be handled through five Change Management

    processes: identification, evaluation, recommendation,

    approval, and incorporation.

    Change Request,

    Change

    Management Log

    Issue & Change

    Management

    Does a Project Steering Committee

    exist to help manage issues and

    changes?

    The Project Steering Committee consists of various project

    stakeholders. The specific make up of the Project Steering

    Committee will vary from project to project and will depend

    on a number of factors

    Project Steering

    Committee

    Stakeholder

    Management

    Is there a process in place to escalate

    important project decisions?

    The Project Manager, in conjunction with the project team

    and/or Project Steering Committee will have to make

    important decisions during the project that will affect its

    outcome. In some cases the decision will be made by the

    project team and communicated to those affected. In other

    cases, the decision will be escalated to the Project Steering

    Committee for approval.

    Decision Request,

    Change

    Management Log

    Issue & Change

    Management

    Is there a process in place to escalate

    project action items?

    In response to decisions or issue resolutions, actions may

    be required. Actions are not to be confused with plannedtasks or activities in the project schedule. Actions are

    unforeseen tasks undertaken to bring the project back into

    alignment with baseline project plan.

    Action Item,

    Change

    Management Log

    Issue & Change

    Management

    Have lessons learned from the project

    been documented for future projects

    Project lessons describe what worked well on the project.

    This will provide an opportunity to carry these successes

    over to future projects. Challenges and opportunities

    encountered on the project provide recommendations for

    improvement on future projects.

    Project Closure

    Report

    Project Review &

    Closure

    Has an assessment of the overall

    project been conducted?

    The purpose of the project review is to:

    Assess the project management techniques used on the

    project and recommend changes where applicable,

    Review the application of the organizations project

    management framework and identify improvements to theframework based on lessons learned on projects,

    Assess the feasibility of continuing with the project (or

    program) and provide validation to terminate the project if

    necessary.

    Project Review

    Report, Project

    Closure Report

    Project Review &

    Closure

    Has a review of the project business

    case been conducted?

    The purpose of the business case review is to compare the

    achievement of business objectives and project benefits with

    what was originally forecast

    Project Closure

    Report

    Project Review &

    Closure

    Has the project team provided an

    assessment of challenges and

    successes from their perspective?

    The Project Team Review section should be completed by

    the team and submitted to the project reviewers for inclusion

    in the Project Closure Report

    Project Closure

    Report

    Project Review &

    Closure

    Has a review of the technology and

    lifecycle processes been conducted?

    The technical review focuses on the technology and lifecycle

    processes used on the project.Project Closure

    Report

    Project Review &

    Closure

    Managing Issues & Changes

    Closing the Project

    EPO Template 2006 Gord Gibben, PMP Version 7.0

  • 8/13/2019 1723295

    4/13

    Scope

    Question Y/N Explanation EPO Template EPO e-book

    Have project objectives and critical

    success factors been identified?

    Project objectives are the goals of the project. Critical

    success factors (CSF) are the project objectives that mustbe met for the project to be considered successful.

    Project Scope

    Statement

    Project Initiation &

    Scope Planning

    Have scope inclusion and exclusion

    criteria been identified?

    Inclusion and exclusion criteria identify the specific

    deliverables, products, and services to be provided by the

    project and explicitly define the items to be excluded from

    the project. This will define the scope boundary from both

    Project Scope

    Statement

    Project Initiation &

    Scope Planning

    Has the project strategy been defined

    and agreed to by the project sponsor?

    The project strategy defines the approach to be followed on

    the project. It should clarify the methods, techniques and

    tools to be used.

    Project Scope

    Statement

    Project Initiation &

    Scope Planning

    Has a scope management matrix

    been prepared and agreed to by the

    project sponsor?

    The scope management matrix identifies the relative

    priorities of the three dimensions of the triple constraint

    (time, cost, and product).

    Scope Management

    Plan

    Project Initiation &

    Scope Planning

    Has a scope stability assessment

    been prepared?

    An assessment of the project scope stability will indicate the

    likelihood that the project scope may change and thepotential magnitude of such a change.

    Scope Management

    Plan

    Project Initiation &

    Scope Planning

    Has a scope change management

    approach been prepared?Successful change management on a project starts with an

    agreement on the methods to be followed to identify and

    evaluate changes.

    Scope Management

    Plan

    Project Initiation &

    Scope Planning

    Has a project Work Breakdown

    Structure (WBS) been prepared?

    The Work Breakdown Structure (WBS) provides an initial

    decomposition of project deliverables into smaller packages

    of work to support planning and estimating activities

    Work Package,

    WBS Planning

    View

    Work Breakdown

    Structure

    Planning

    Have project Work Packages been

    prepared and assigned?

    Work packages are discreet units of work that are assigned

    to individuals, teams, or external contractors. They can be

    used to subdivide the work according to discipline or to

    prescribe a deliverable to be completed by a contractor

    Work Package,

    WBS Assignment

    View

    Work Breakdown

    Structure

    Planning

    Project Management Checklist

    Planning the Scope

    Planning the Work

    EPO Template 2006 Gord Gibben, PMP Version 7.0

  • 8/13/2019 1723295

    5/13

    Time

    Question Y/N Explanation EPO Template EPO e-book

    Has a project activity list been

    prepared?

    The activity list is an extension of the WBS and identifies all

    the activities required to produce WBS deliverables.

    Activity Plan, Activity

    Planning View

    Activity Planning &

    Estimating

    Does each project activity have a

    tangible deliverable?

    The activity name should consist of an action verb (produce,

    prepare, develop, install, etc) and an object of that verb that

    names the activity deliverable

    Activity Plan, Activity

    Planning View

    Activity Planning &

    Estimating

    Has a project network diagram been

    created?

    The activity sequencing is shown using a Project Network

    Diagram which illustrates how the project activities will flow

    from beginning to end. It is created by establishing the

    dependencies among project deliverables

    Activity Plan, Activity

    Sequencing View

    Activity Scheduling

    Have activity dependencies been

    established?Dependencies can be mandatory (based on required

    completion of deliverables) or discretionary (based on

    preferred sequence of activities).

    Activity Plan, Activity

    Sequencing View

    Activity Scheduling

    Have activity duration and effort

    estimates been prepared?

    Activity estimates have two components:

    Duration estimates (in days) provide an indication of how

    long a task will take and are used for critical path

    scheduling.

    Effort estimates (in hours) are used to determine the

    amount of work (by each resource) required to produce a

    deliverable. Effort estimates are variable by resource and

    will be used when resource leveling the project schedule.

    Both duration and effort estimates need to be done for each

    activity.

    Activity Plan, Activity

    Estimating View

    Activity Planning &

    Estimating

    Have PERT duration estimating

    techniques been used?

    Using PERT estimating, three duration estimates are

    prepared for each activity: optimistic (O), pessimistic (P) andmost likely (M).

    Activity Plan, Activity

    Estimating View

    Activity Planning &

    Estimating

    Have resource effort estimates been

    prepared for each activity?

    The effort required to perform an activity is dependent on the

    resources assigned. Because effort is variable by resource,

    it should be estimated for each resource assigned to an

    activity.

    Activity Plan, Activity

    Estimating View

    Activity Planning &

    Estimating

    Has the project critical path been

    identified?

    The critical path is defined as the sequence of activities with

    the longest duration. The critical path activities should be

    associated with production of important project deliverables

    and not support tasks.

    Activity Scheduling

    View

    Activity Scheduling

    Have resource leveling techniques

    been applied to the project schedule?

    Resource leveling is necessary when:

    One resource is assigned to multiple activities and their

    over allocation must be leveled out by extending the duration

    of some activities. Too many activities are assigned to one resource and

    some activities must be transferred to other resources.

    Multiple resources (with varying availability) are assigned to

    one activity.

    There are times in the schedule when resources are not

    fully occupied and will need work. Activity dependencies

    can be shifted to level off peaks and fill in valleys of resource

    usage

    Activity Plan,

    Resource Leveling

    View

    Activity Scheduling

    Have duration compression

    techniques been applied to the project

    schedule?

    To meet fixed end dates, the duration of the project critical

    path may need to be shortened. This duration compression

    can be accomplished through fast tracking or crashing the

    schedule.

    Activity Scheduling

    View

    Activity Scheduling

    Have schedule milestones been

    established?

    Schedule milestones (evenly distributed throughout the

    schedule) are established for status tracking and reporting Activity SchedulingView Activity Scheduling

    Has a baseline project schedule been

    established?

    A project baseline provides a foundation for tracking &

    reporting and managing the effects of change.

    Activity Scheduling

    View

    Activity Scheduling

    Project Management Checklist

    Planning Activi t ies

    Estimating Activi t ies

    Developing the Schedule

    EPO Template 2006 Gord Gibben, PMP Version 7.0

  • 8/13/2019 1723295

    6/13

    Time

    Has a schedule management plan

    been prepared?

    The Schedule Management Plan describes how the PMBOK

    time management processes will be carried out on the

    project

    Schedule

    Management Plan

    Project Schedule

    Management

    Is progress tracked and the schedule

    updated on a regular basis?

    Updating the schedule on a regular basis enables

    forecasting:

    Finish dates of activities started or already in progress, Estimated start dates of activities not yet started

    Schedule Update

    View

    Project Schedule

    Management

    Have schedule variance thresholds

    been established?

    Schedule variance reporting procedures should include:

    Frequency of reporting schedule variances

    Responsibility for explaining schedule variances,

    Variance thresholds that will trigger explanation.

    Schedule

    Management Plan

    Project Schedule

    Management

    Are procedures in place to re-

    establish the schedule baseline?

    Approved change requests can be incorporated into the

    project baselines. A new baseline schedule and/or project

    budget (depending on the nature of the change) is

    established

    Schedule

    Management Plan

    Project Schedule

    Management

    Moni tor ing the Schedule

    EPO Template 2006 Gord Gibben, PMP Version 7.0

  • 8/13/2019 1723295

    7/13

    Cost

    Question Y/N Explanation EPO Template EPO e-book

    Has a project cost estimate been

    prepared?

    Project cost estimates provide senior management

    stakeholders with the financial information to:

    Compare costs of potential projects competing for

    approval,

    Compare the costs of an initiative to the tangible benefits

    associated with delivery,

    Determine the financial commitment required to complete

    the project,

    Reliable project cost estimates are essential when managing

    the expectations of funding authority stakeholders.

    Project Cost

    Estimate

    Project Estimating &

    Budgeting

    Have estimates been prepared for

    labor, equipment, supplies, expenses

    and financing costs to be incurred by

    the project?

    Project estimates and budgets are both based on the project

    accounts which, in turn, must be tied to the corporate

    financial Chart of Accounts. The structure of the financial

    chart of accounts will vary from one organization to another

    Project Cost

    Estimate, Project

    Budget

    Project Estimating &

    Budgeting

    Have estimating assumptions been

    recorded?

    Estimating assumptions should be documented for

    reference during cost control and to help support the

    management of risks, issues and changes.

    Project Cost

    Estimate

    Project Estimating &

    Budgeting

    Has a budget been established for

    cost tracking and control?The project budget, which forms the baseline for cost

    control, is a time phased distribution of project costs. An

    estimate becomes a budget when costs are allocated to time

    phases (usually months or years).

    Project Budget Project Estimating &

    Budgeting

    Has a project cost management plan

    been prepared?

    The Cost Management Plan establishes how the project

    estimating, budgeting and cost control processes will occur

    Cost Management

    Plan

    Project Cost

    Management

    Have funding release amounts been

    defined for the project?

    Typically, funding is based on budget amounts and is

    released in increments before money is spent on the project.Cost Management

    Plan

    Project Cost

    Management

    Are earned value performance

    indicators used to report schedule and

    cost variance?

    Using earned value performance measurements, the cost

    and schedule variances are calculated as follows:

    Cost Variance (CV) = Earned Value Actual Costs

    Schedule Variance (SV) = Earned Value Planned Value

    Earned Value

    Performance

    Calculator,

    Performance Report

    View, Project

    Earned Value

    Performance

    Reporting

    Are earned value performance indices

    used to forecast project completion

    costs and variances?

    Earned value calculations provide a means of estimating

    project completion costs based on actual cost and schedule

    performance.

    Earned Value

    Performance

    Calculator,

    Performance Report

    View, Project

    Performance Report

    Earned Value

    Performance

    Reporting

    Are actual costs being recorded on

    the project?

    Actual cost expenditures incurred by the project can be

    captured using timesheets or the organizations cost

    accounting process

    Project Cost

    Tracking

    Project Cost

    Management

    Are procedures in place to re-

    establish the cost baseline?

    Approved change requests can be incorporated into the

    project baselines. A new baseline schedule and/or project

    budget (depending on the nature of the change) is

    established

    Cost Management

    Plan

    Project Cost

    Management

    Project Management Checklist

    Est imat ing Project Costs

    Establ ish ing the Budget

    Monitor ing Project Costs

    EPO Template 2006 Gord Gibben, PMP Version 7.0

  • 8/13/2019 1723295

    8/13

    Quality

    Question Y/N Explanation EPO Template EPO e-book

    Has a Quality Management Plan been

    prepared for the project?

    The Quality Management Plan describes how the project

    management team will manage the quality of deliverables

    produced on the project.

    Quality Management

    Plan

    Quality Management

    Are formal quality control techniques

    being applied to the project?

    Quality control is the process of:

    1. Measuring deliverables to determine if quality standards

    are being met,

    2. Monitoring results to determine compliance with quality

    standards.

    Control Chart,

    Pareto Diagram

    Quality Management

    Are project deliverables subjected to

    formal inspections? Inspections provide a mechanism to detect defects early and

    improve the overall quality of project products. This will, in

    turn, improve productivity and motivate team members to

    produce better quality deliverables

    Inspection Report Software Inspections

    & Deliverable

    Reviews

    Does a formal review and acceptance

    process exist for project deliverables?

    The primary objective of a deliverable review is to gain

    acceptance of a product so that work can proceed on to thenext phase or step. This acceptance should be based on

    predefined acceptance criteria.

    Deliverable

    Acceptance

    Software Inspections

    & Deliverable

    Reviews

    Are acceptance criteria defined for

    review and testing of project

    deliverables?

    Acceptance criteria describe the conditions required for the

    project deliverables to be accepted by the project sponsor.

    The acceptance criteria should be prepared early in the

    project; initial acceptance criteria should be included in the

    Project Charter to ensure that the project sponsor and the

    project team are in agreement throughout the project.

    Acceptance Criteria,

    Acceptance Test

    Tracking

    Software Test

    Planning &

    Execution

    On software development projects,

    are test scripts and test cases defined

    for software testing?

    Test scripts identify the business functions to be tested.

    Test cases should be defined for each business function

    identified in the test script. They are designed to exercise

    the applications response to both good and bad test data

    Test Case Software Test

    Planning &

    Execution

    During software testing, are defects

    recorded and prioritized for

    resolution?

    Tests can be executed either manually or through the use of

    an automated testing tool that pumps test cases through the

    application. In both cases it is important to record test

    results, track defects and assign priorities to deal with

    defects

    Defect report, Defect

    Tracking Log

    Software Test

    Planning &

    Execution

    Project Management Checklist

    Qual i ty Management

    Inspections

    Testing

    EPO Template 2006 Gord Gibben, PMP Version 7.0

  • 8/13/2019 1723295

    9/13

    Human Resources

    Question Y/N Explanation EPO Template EPO e-book

    Have project roles been defined? Assigning the right resources to project activities is critical to

    meeting project objectives. To ensure that everyone

    understands their contribution, resources can be classified

    into a number of roles.

    Project Human

    Resource Plan

    Human Resource

    Planning

    Have the project resource

    requirements been identified?

    Defining resource requirements for a project is one of the

    most important planning processes. Each project will have

    unique resource requirements and may require a different

    emphasis on project roles.

    Project Human

    Resource Plan

    Human Resource

    Planning

    Have the project resource constraints

    been identified?Resource availability constraints such as commitment levels

    or dependencies on another project to release the resource

    should be identified and agreed to with the resources

    functional manager

    Project Human

    Resource Plan

    Human Resource

    Planning

    Have project resources been

    assigned to project deliverables?

    Once the project resources have been identified, they can

    be assigned to Work Packages in the Work Breakdown

    Structure (WBS) using a Responsibility Assignment Matrix

    Responsibility

    Assignment Matrix

    Human Resource

    Planning

    Has a project resource training plan

    been prepared?

    Some of the resources assigned to the project will require

    training to perform their roles and produce their deliverables.

    This may occur when:

    New technology is being adopted on a project,

    A software package has been purchased,

    Employees are provided with career development

    opportunities on projects.

    Resource Skills

    Assessment,

    Resource Training

    Plan

    Human Resource

    Planning

    Is a project kick-off event planned? The project team kick-off meeting is the first team meeting

    to be held on a project. The primary purpose of the team

    kick-off meeting is to obtain commitment from team

    members and key stakeholders.

    Team Kick-off

    Meeting

    Team Management

    Do project team members understand

    their roles on the project and how they

    will work together?

    To encourage constructive behaviors, curtail subversive

    behaviors and guide the team through the development

    stages, a Team Charter should be prepared. The Team

    Charter is an agreement that states:

    What the team wants to accomplish,

    Why the team is important,

    How the team will work together to accomplish its goals

    Team Charter Team Development

    Have open communication channels

    been established within the project

    team?

    The groundwork for open communications within the project

    team is laid with the Team Communications PlanTeam

    Communications

    Plan

    Team Management

    Project Management Checklist

    Human Resource Planning

    Managing th e Team

    EPO Template 2006 Gord Gibben, PMP Version 7.0

  • 8/13/2019 1723295

    10/13

    Communications

    Question Y/N Explanation EPO Template EPO e-book

    Have project stakeholders been

    identified?

    According to the PMI PMBOK 2000 (section 2.2), project

    stakeholders are:

    Individuals and organizations that are actively involved in

    the project, or whose interests may be positively or

    negatively affected as a result of project execution or project

    completion; they may also exert influence over the project

    and its results.

    Stakeholder

    Identification

    Stakeholder

    Identification &

    Analysis

    Has the stake in the project and the

    required commitment from each

    stakeholder been identified?

    Each stakeholders stake in the project will take one of three

    forms:

    1. Providing a product or service which contributes to the

    project objectives.

    2. Receiving or using a product or service delivered by the

    project.

    3. Interested in the project outcome

    The required commitment of each stakeholder is critical to

    the level of planned communication.

    Stakeholder

    Identification,

    Stakeholder Analysis

    Stakeholder

    Identification &

    Analysis

    Have the communication needs of

    each stakeholder been identified?

    The stakeholder communication needs should consider:

    Preferred communication medium,

    Constraints on technology access that may affect

    communications,

    Recommended reporting frequency,

    Special information needs of each stakeholder.

    Stakeholder

    Identification,

    Stakeholder Analysis

    Stakeholder

    Identification &

    Analysis

    Have the priorities, support and

    influence of key stakeholders been

    identified?

    It is important to determine the schedule, cost and product

    quality priorities and support of key stakeholders.

    Stakeholder influence is their ability to make or influence

    decisions related to project objectives.

    Stakeholder Analysis Stakeholder

    Identification &

    Analysis

    Has a project stakeholdercommunications plan been prepared?

    The Project Stakeholder Communications Plan describes

    how communication will be accomplished with each

    stakeholder.

    StakeholderCommunications

    Plan

    CommunicationsPlanning

    Has a project meeting plan been

    prepared?

    The Project Meeting Plan identifies (for each type of project

    meeting) the:

    Meeting attendees,

    Objectives of the meeting,

    Agenda items,

    Logistics such as timeframe, frequency and location,

    Technology medium

    Meeting &

    Presentation Plan

    Communications

    Planning

    Have required project presentations

    been planned?

    The Project Presentation Plan identifies (for each type of

    project presentation) the:

    Presentation audience (individuals or groups),

    Objectives of the presentation (what will be accomplished),

    Logistics such as timeframe, frequency, and location, Equipment required for the presentation (projectors,

    screens, flipcharts, laptops, etc),

    The presentation type (speech, presentation, video)

    Meeting &

    Presentation Plan

    Communications

    Planning

    Has a project document distribution

    plan been prepared?

    The Project Document Distribution Plan describes:

    Original source of the information (previous project or

    deliverable of current project),

    Project repository location of the deliverable (hyperlink to

    Web URL or directory folder name),

    Distribution schedule (completion date or distribution

    frequency)

    Distribution list (based on stakeholder communication plan)

    Document

    Distribution Plan

    Communications

    Planning

    Project Management Checklist

    Stakeholder Identi f ication

    Commun icat ions Planning

    EPO Template 2006 Gord Gibben, PMP Version 7.0

  • 8/13/2019 1723295

    11/13

    Communications

    Is access to project documentation

    provided for key stakeholders?

    The Project Stakeholders Communications plan should

    describe procedures for:

    Accessing information between scheduled

    communications,

    Updating and refining the communications plan as the

    project progresses.

    Stakeholder

    Communications

    Plan

    Communications

    Planning

    Are project accomplishments reported

    to stakeholders on a regular basis?

    The project progress report is used to report on deliverables

    completed and accomplishments during the reporting period.

    It is also used to predict deliverables that will be completed

    during the next reporting period.

    Project Progress

    Report

    Progress & Status

    Reporting

    Is project schedule and cost status

    reported to stakeholders on a regular

    basis?

    Based on project milestones, status reports provide a

    comparison of actual/forecasted completion dates with

    schedule and cost baselines.

    Project Status

    Report, Status View,

    Status Presentation

    Progress & Status

    Reporting

    Is the status of project issues and

    changes reported to stakeholders on

    a regular basis?

    The status of outstanding (or recently resolved) changes and

    issues should be reported to stakeholders regularly. The

    description of the issue should include the impact on

    schedule, cost and deliverable (where known) and a

    resolution required by date. The description of the change

    should include a business justification for the change andthe impact on cost and schedule.

    Project Progress

    Report, Project

    Status Report

    Progress & Status

    Reporting

    Is the status of high priority project

    risks reported to stakeholders on a

    regular basis?

    A description of the specific risk and triggering event should

    be provided along with the risk priority (high, medium, or

    low). The consequences that arise from the risk occurrence

    should be described and the approved risk decision

    (prevent, mitigate, monitor, or accept) should be indicated

    Project Progress

    Report, Project

    Status Report

    Progress & Status

    Reporting

    Reporting Project Status

    EPO Template 2006 Gord Gibben, PMP Version 7.0

  • 8/13/2019 1723295

    12/13

    Risk

    Question Y/N Explanation EPO Template EPO e-book

    Has a risk management plan been

    prepared for the project?

    The risk management plan (prepared early in the planning

    phase of the project) describes how the four risk

    management steps (identification, assessment, response

    planning and monitoring/control) will be performed on the

    project.

    Risk Management

    Plan

    Risk Management

    Have project risk factors been

    identified?

    Risk factors are categories of risk sources that may have an

    impact on the project cost, schedule, scope or quality

    objectives. Each project risk factor should be considered

    when identifying potential project risk events.

    Risk Identification

    Checklist

    Risk Identification

    Have potential risk events been

    identified?

    The first step in risk assessment is the identification of risk

    events (discreet occurrences of potential problems). The

    risk description must be complete enough to support risk

    response decisions and preparation of risk response plans.

    Risk Identification

    Checklist, SWOT

    Analysis

    Risk Identification

    Has an assessment of each potential

    risk event been prepared? For each identified risk, an assessment of its urgency,

    growth, probability, and impact should be conducted. Each

    risk should be described in sufficient detail to be understood

    by project team members, sponsors and management.

    Risk Assessment,

    Risk Event

    Scenarios

    Risk Assessment &

    Response Planning

    Have high priority project risks been

    identified?The priority of the risk is assigned based on the probability

    and impact assessment. Attention should be focused on

    high probability and high impact risks.

    Risk Assessment,

    Risk Register

    Risk Assessment &

    Response Planning

    Are decision tree techniques used to

    quantify project risks and

    opportunities?

    Decision trees provide a graphical representation of

    decisions and quantify the risks and rewards of these

    decisions.

    Decision Tree Decision Analysis

    Has a readiness assessment been

    done to evaluate risks associated with

    one or more alternatives?

    Readiness Assessment footprints are a means to evaluate

    risks associated with one or more alternatives. These risks

    are assessed using eight categories of organizationalreadiness and the corresponding attributes of alternatives

    under consideration.

    Readiness Footprint Readiness

    Assessment

    Has a risk response plan been

    prepared for high priority risks?

    The risk response plan contains preventative actions,

    corrective actions, risk monitoring and communications

    plans.

    Risk Response Plan Risk Assessment &

    Response Planning

    Have risk response plans evaluated to

    determine their effectiveness?

    Risk response plans often affect more that one risk event.

    Risk responses should be evaluated to determine the affect

    of risk responses on the high priority risk events. The risk

    response evaluation will also help uncover secondary and

    residual risks.

    Risk Response Plan,

    Risk Register

    Risk Assessment &

    Response Planning

    Has a risk monitoring plan been

    implemented for high priority risks?

    The Risk Monitoring plan describes:

    The tracking and control of risks (a continuous processinvolving both the project team and management).

    The preventative action plans to be implemented

    How the status of existing risks and the potential for new

    risks are to be assessed.

    Triggers that alert the project team of a risk occurrence and

    the corrective action to be taken.

    Risk Response Plan,

    Risk Register

    Risk Assessment &

    Response Planning,Risk Management

    Project Management Checklist

    Risk Identi f ication

    Risk Assessment

    Risk Response Planning

    EPO Template 2006 Gord Gibben, PMP Version 7.0

  • 8/13/2019 1723295

    13/13

    Procurement

    Question Y/N Explanation EPO Template EPO e-book

    Has a procurement management plan

    been prepared for the project?

    The Procurement Management plan is completed if products

    or services will be purchased for the project from an outside

    supplier. The Procurement Management Plan identifies:

    How services will be procured for the project,

    Procedures for evaluating bids and proposals (including

    approvals required),

    The types of contracts to be used to procure products or

    services,

    Contract administration and reporting procedures.

    Procurement

    Management Plan

    Procurement

    Planning

    Has a Statement of Work been

    prepared for the procurement items?

    The Statement of Work (SOW) describes the procurement

    item so that prospective sellers can decide if they are

    capable of providing the item and how the work can be

    undertaken.

    Statement of Work Procurement

    Planning

    Has the project team performed a buy

    vs. build analysis on projectdeliverables?

    Analysis of buy vs. build options is undertaken to determine

    whether the project team can produce the product/service orif it should be purchased.

    Procurement

    Management Plan

    Procurement

    Planning

    Have objective evaluation criteria

    been defined for alternative

    evaluation?

    Proposals should be evaluated against a set of criteria

    ranked as follows:

    Mandatory these are must criteria based on critical

    success factors or project objectives.

    Optional these are the want criteria based on

    requirements.

    Alternative Selection Bid & Proposal

    Evaluation

    Is a rational process used to select

    from alternatives and minimize risks

    from selection decisions?

    Project teams frequently must evaluate alternatives and

    make selection decisions that involve a degree of risk.

    These decisions can be complex; a quantifiable approach is

    required.

    Alternative Selection Bid & Proposal

    Evaluation

    Has a Contract Management Planbeen prepared for each contract on

    the project?

    Contract administration is the process of managing thecontract and the relationship between the buyer and the

    seller. The Contract Management Plan describes how a

    specific contract will be administrated during the project

    ContractManagement Plan

    ContractAdministration

    Upon completion of the contract, has

    a contract closure report been

    prepared?

    Contract closure is the process of completing and settling

    the contract, resolving open items and completing contract

    closure documentation.

    Contract Closure

    Report

    Contract

    Administration

    Contract Adminis t ration

    Project Management Checklist

    Procurement Planning

    Evaluat ing Bids & Proposals

    EPO Template 2006 Gord Gibben, PMP Version 7.0