8
Bass Metals Ltd. (ASX: BSM) Email: [email protected] Phone: (07) 3203 5894 ASX ANNOUNCEMENT 9 OCTOBER 2017 GRAPHMADA GRAPHITE MINE OPERATIONAL UPDATE HIGHLIGHTS Bass Metals Ltd nearing completion of Stage 1 of the optimisation program: the establishment of 6000 tonnes per annum (tpa) production of premium graphite concentrates at its 100% owned Graphmada Large Flake Graphite Mine. Major processing equipment items have now arrived in Madagascar. Process Plant civil works are nearing completion, to time with the release from customs of the major equipment items. Modular Dryer System (MDS) construction has commenced and is on time and budget, with expected commissioning in November 2017. Prices for graphite concentrates in Bass’ intended end markets have improved materially over the last 2 quarters. Figure 1: The commencement of MDS installation; laying out of frames, completion of structural footing, and control room construction nearing completion. For personal use only

171009 Graphmada Graphite Mine Operational Update bcp · Bass plans to invest capital to expand production to greater than 20,000 tonnes per annum (Stage 2) of graphite concentrate

Embed Size (px)

Citation preview

Page 1: 171009 Graphmada Graphite Mine Operational Update bcp · Bass plans to invest capital to expand production to greater than 20,000 tonnes per annum (Stage 2) of graphite concentrate

BassMetalsLtd.(ASX:BSM)

Email:[email protected]:(07)32035894

Post:POBox1048,SubiacoWA6904Web:www.bassmetals.com.au 1

ASXANNOUNCEMENT9OCTOBER2017

GRAPHMADAGRAPHITEMINEOPERATIONALUPDATE

HIGHLIGHTS

• BassMetalsLtdnearingcompletionofStage1oftheoptimisation

program:theestablishmentof6000tonnesperannum(tpa)

productionofpremiumgraphiteconcentratesatits100%owned

GraphmadaLargeFlakeGraphiteMine.

• MajorprocessingequipmentitemshavenowarrivedinMadagascar.

• ProcessPlantcivilworksarenearingcompletion,totimewiththe

releasefromcustomsofthemajorequipmentitems.

• ModularDryerSystem(MDS)constructionhascommencedandison

timeandbudget,withexpectedcommissioninginNovember2017.

• PricesforgraphiteconcentratesinBass’intendedendmarketshave

improvedmateriallyoverthelast2quarters.

Figure1:ThecommencementofMDSinstallation;layingoutofframes,completionofstructuralfooting,

andcontrolroomconstructionnearingcompletion.

For

per

sona

l use

onl

y

Page 2: 171009 Graphmada Graphite Mine Operational Update bcp · Bass plans to invest capital to expand production to greater than 20,000 tonnes per annum (Stage 2) of graphite concentrate

BassMetalsLtd.(ASX:BSM)

Email:[email protected]:(07)32035894

Post:POBox1048,SubiacoWA6904Web:www.bassmetals.com.au 2

ASXANNOUNCEMENT9OCTOBER2017

BassMetalsLimited(ASX:“BSM”)(the“Company”)ispleasedtoprovideanupdateonits

optimization and refurbishment of the Graphmada Graphite Mine, located in

Madagascar.

MINEHEALTHANDSAFETYUPDATE

TheCompanyispleasedtoreportthatwhilsttheoptimizationandrefurbishmentofthe

minehasbeeninprogressnoLostTimeInjurieshavebeenreported.TheCompany

continuesitsfocusofapplyingsoundsafetymanagementpracticestoitsactivitiesand

maintainsitsstrategyofengineeringasafeoperatingenvironmentintothe

refurbishmentofthemine.

OPTIMISATION&REFURBISHMENTPROGRAMUPDATE

Refurbishmentworkscontinueasplannedwiththeprogramonbudgetandonschedule.

SignificantactionsundertakensincethelastOperationalUpdateinclude:

ü ProcessingplantequipmentshippedandinMadagascarawaitingcustoms

clearance;

ü ManufactureofnewpumpscompleteandshippedtoMadagascar;

ü Allproceduresforheavyloadtransportofequipmenttositearranged;

ü Onsiteoff-loadingsafetyproceduresfinalised;

ü Plansforrefurbishingelectricalcontrolroomandplantofficesfinalised;

ü Manufacturingofallelectricalcontrolboardsandcablesinprogress;

ü Finalplanforelectricalcablingroutingconfirmed;

ü Extensionoftheexistinggeneratorshedtoaccommodateelectricaldistribution

boardsinprogress;

ü ProcessPlantcivilworksnearingcompletionintimeforthearrivalonsiteof

majorprocessingequipmentitems;

ü Integrationbetweenoldandnewfloatationcellscompleteandwaterfilltest

successful;

ü Floatationcellspipingandmaterialflowconnectionworkunderway;

ü Refurbishingofpreviouslyusedplantpumpsunderway;

For

per

sona

l use

onl

y

Page 3: 171009 Graphmada Graphite Mine Operational Update bcp · Bass plans to invest capital to expand production to greater than 20,000 tonnes per annum (Stage 2) of graphite concentrate

BassMetalsLtd.(ASX:BSM)

Email:[email protected]:(07)32035894

Post:POBox1048,SubiacoWA6904Web:www.bassmetals.com.au 3

ASXANNOUNCEMENT9OCTOBER2017

ü Surgebins,pumpsandpipinginstallationunderway.

ü AllcivilworktoaccommodateModularDryerSystem(MDS)complete;

ü AssemblyanderectionofMDScomponentsinprogress;

ü MDSelectricalcontrolroomnearingcompletion;

ü Manufacturingofdrysortingandscreeningequipmentcomplete;

ü Graphitesizefractionstoragebinscomplete;

ü Mahefadokmineplanningunderway;

ü Planningforextendedstockpilearearevisedandconfirmed.

Figure2:Completedflotationrecyclebinsinstalled.

For

per

sona

l use

onl

y

Page 4: 171009 Graphmada Graphite Mine Operational Update bcp · Bass plans to invest capital to expand production to greater than 20,000 tonnes per annum (Stage 2) of graphite concentrate

BassMetalsLtd.(ASX:BSM)

Email:[email protected]:(07)32035894

Post:POBox1048,SubiacoWA6904Web:www.bassmetals.com.au 4

ASXANNOUNCEMENT9OCTOBER2017

Figure3:MDSinstallationunderway.

SALES&MARKETUPDATE

Theminecurrentlyhas298 tonnesofgraphiteconcentrates in stock.TheCompany is

negotiatingthesaleofthisstockaspartofmaintainingregularsuppliestoGraphmada’s

maincustomers.

Smallsampleshavealsobeendispatchedfromexistingstocktopotentialnewcustomers

whoareenquiringastoGraphmada’splanstosupplynaturalflakegraphitein2018.Most

interest is centred on the large to very large flake size concentrates as the market

continuestoseeasignificantdecreaseinsupplyintheseflakesizes.

Table1:CurrentStock

GRADEFC% MeshSize

+50 -50+80 -80 -100

<85 1

85-90 45 78 10

90-94 13 43 69 36

>94 1

TOTAL 14 88 150 46

Atotalof298tonnesproduct.

For

per

sona

l use

onl

y

Page 5: 171009 Graphmada Graphite Mine Operational Update bcp · Bass plans to invest capital to expand production to greater than 20,000 tonnes per annum (Stage 2) of graphite concentrate

BassMetalsLtd.(ASX:BSM)

Email:[email protected]:(07)32035894

Post:POBox1048,SubiacoWA6904Web:www.bassmetals.com.au 5

ASXANNOUNCEMENT9OCTOBER2017

PricesforgraphiteconcentratesinBass’intendedendmarketshaveimprovedmaterially

over the last 2 quarters due to weakening supply out of China from the continued

environmentalcrackdowns,particularlyintheuseofcoalindryingclosingmanyfactories

in Shandong. Reports also indicate that Expandable Graphite usage is increasing

significantlyinChinaduetorecentlegislativechangesintheuseoffireretardants.

Pricesareexpectedtocontinuetoriseinthecomingmonthsparticularlyforlargeflake

sizeswithFC>94%,thetargetofoptimizedproductionactivitiesatGraphmada.

Figure4:6monthflakegraphiteprices.

BASSMETALSCEO,MRTIMMCMANUS:

“WearenearingcompletionofStage1ofouroptimizationandrefurbishmentofthe

GraphmadaMineandaimtorampupproductionfromlate2017throughtoearly2018

toreach500tonnesamonthofhigh-valuegraphiteconcentrates(Stage1:6000tpa

run-rate).

AstheonlyindustrialmineralscompanyontheASXcapableofenteringallgraphite

marketsegmentsatpremiumpricinglevels,andwithpricingcontinuingtogrowby

doublefiguresmonthonmonth,theCompanyisexperiencingsignificantenquiresforits

futureproduction,particularlyinthelargerflakesizes.

For

per

sona

l use

onl

y

Page 6: 171009 Graphmada Graphite Mine Operational Update bcp · Bass plans to invest capital to expand production to greater than 20,000 tonnes per annum (Stage 2) of graphite concentrate

BassMetalsLtd.(ASX:BSM)

Email:[email protected]:(07)32035894

Post:POBox1048,SubiacoWA6904Web:www.bassmetals.com.au 6

ASXANNOUNCEMENT9OCTOBER2017

AssuchtheteamatBassremainsencouragedthatourstrategictimingtore-commission

theGraphmadaMinewillprovetoaddsignificantvaluetoallshareholdersandprovide

anexcellentbasetoimplementaStage2expansionto20,000tpa.”

Formoreinformation,pleasecontact:

TimMcManus

ChiefExecutiveOfficer

Phone:(07)32035894

Email:[email protected]

PeterWright

Director

Phone:(07)32035894

Email:[email protected]

Pleasevisitusat:www.bassmetals.com.au

For

per

sona

l use

onl

y

Page 7: 171009 Graphmada Graphite Mine Operational Update bcp · Bass plans to invest capital to expand production to greater than 20,000 tonnes per annum (Stage 2) of graphite concentrate

BassMetalsLtd.(ASX:BSM)

Email:[email protected]:(07)32035894

Post:POBox1048,SubiacoWA6904Web:www.bassmetals.com.au 7

ASXANNOUNCEMENT19JUNE2017

ABOUTTHEGRAPHMADAJUMBOFLAKEGRAPHITEMINE

Bass Metals Ltd. is one of only three

publicly listed graphite producers in the

world. The Company 100% owns and

operates the Graphmada large flake

graphite mine, Bass’ flagship project,

located in eastern Madagascar.

Madagascar has been a recognized

producer and exporter of premium

graphite forover100yearsandsets the

world standard for product quality and

flakesize.

TheGraphmadaminehas40-yearmining

permitsinplace,containingfourpremium

quality,largeflake,graphitedepositshostedinweatheredgraphiticgneiss,asoft,easilyminablerock

thatincurslowminingcosts.Withallassociatedmininginfrastructureandlogisticsinplace,themine

currently produces and sells a range of graphite concentrates into multiple market segments, to

customersinIndia,theUnitedStatesandEurope.

Withtheaimofgeneratingrevenuethroughlowestquartilecostproduction,themineiscurrentlybeing

optimizedbyanexperiencedmanagementteamto6000tonnesperannum(Stage1)with improved

finalgraphiteconcentrategrades,inordertogrowcashmargins.

Graphmadaalsohassignificantpotentialforlowcapitalintensityexpansion.Bassplanstoinvestcapital

toexpandproductiontogreaterthan20,000tonnesperannum(Stage2)ofgraphiteconcentratesales

by2019.

InadditiontoexploringthegreatermineralizationpotentialofMadagascar,theCompanyhasalsomade

thestrategicdecision,inparallelwiththeoptimizationofGraphmada,toactivelyexploreanddevelop

depositsintheimmediateproximitytothemine,tomateriallyexpanditsresourceinventories.

TheLoharanodeposithasprovidedthebulkofthefeedtotheGraphmadaprocessingplantandhastotal

JORC compliant Indicated and Inferred resources of 5.7Mt@ 4.1% Grade with a 2% cut-off1. This

mineralizationisknowntogotodepthwithincreasinggrade,andisopeninalldirections.

WiththeCompanyhavingastrongcommunityengagementprogramandbeingwelldownthepathin

achievingitsoptimisationplansandgrowingitsresourceinventory,theteamatBassisconfidentofits

plansforexpansionanditsfuturevaluecreationforshareholders.

1TheseestimateswerepreparedandfirstdisclosedbyStratminGlobalResourcePLCundertheJORCCode2004.Theestimates

havenotbeenupdatedtoJORCCode2012onthebasisthattheinformationhasnotmateriallychangedsinceitwaslastreported.

ReferenceismadetotheCompany'sannouncementof2September2015,whichprovidesfurtherdetailregardingthisinformation.

For

per

sona

l use

onl

y

Page 8: 171009 Graphmada Graphite Mine Operational Update bcp · Bass plans to invest capital to expand production to greater than 20,000 tonnes per annum (Stage 2) of graphite concentrate

BassMetalsLtd.(ASX:BSM)

Email:[email protected]:(07)32035894

Post:POBox1048,SubiacoWA6904Web:www.bassmetals.com.au 8

ASXANNOUNCEMENT19JUNE2017

DISCLAIMER&CAUTIONARYSTATEMENTS

DISCLAIMER

ThisdocumenthasbeenpreparedbyBassMetalsLimited(the“Company”).Itshouldnotbeconsidered

asaninvitationoroffertosubscribefororpurchaseanysecuritiesintheCompanyorasaninducement

tomakeaninvitationorofferwithrespecttothosesecurities.Noagreementtosubscribeforsecurities

intheCompanywillbeenteredintoonthebasisofthisdocument.Thisdocumentisprovidedonthe

basis that neither the Company nor its officers, shareholders, related bodies corporate, partners,

affiliates, employees, representatives and advisersmake any representation orwarranty (express or

implied) as to the accuracy, reliability, relevance or completeness of the material contained in the

documentandnothingcontainedinthedocumentis,ormayberelieduponasapromise,representation

orwarranty,whetherastothepastorthefuture.TheCompanyherebyexcludesallwarrantiesthatcan

beexcludedbylaw.

FORWARDLOOKINGSTATEMENTS

Thisdocumentmaycontaincertainforward-lookingstatements.Suchstatementsareonlypredictions,

basedoncertainassumptionsandinvolveknownandunknownrisks,uncertaintiesandotherfactors,

manyofwhicharebeyondtheCompany’scontrol.Actualeventsorresultsmaydiffermateriallyfrom

the events or results expected or implied in any forward-looking statement. The inclusion of such

statements should not be regarded as a representation,warranty or predictionwith respect to the

accuracyoftheunderlyingassumptionsorthatanyforwardlookingstatementswillbeorarelikelytobe

fulfilled. TheCompany undertakes no obligation to update any forward-looking statement to reflect

events or circumstances after the date of this document (subject to securities exchange disclosure

requirements).The information inthisdocumentdoesnottake intoaccounttheobjectives, financial

situationorparticularneedsofanyperson.Nothingcontainedinthisdocumentconstitutesinvestment,

legal,taxorotheradvice.

COMPETENTPERSONSTATEMENT

TheinformationinthisdocumentthatrelatestoExplorationResultsisbasedoninformationcompiled

byTimMcManus,aCompetentPersonwho isamemberof theAustralasian InstituteofMiningand

Metallurgyandafull-timeemployeeoftheCompany.

TimMcManushassufficientexperiencethatisrelevanttothestyleofmineralisationandtypeofdeposit

underconsiderationandtotheactivitybeingundertakentoqualifyasaCompetentPersonasdefinedin

the2012EditionoftheAustralasianCodeforReportingofExplorationResults,MineralResourcesand

OreReserves.

TimMcManusconsentstotheinclusionoftheinformationinthisdocumentintheformandcontextin

whichitappears.

For

per

sona

l use

onl

y