Upload
benoit-latapie
View
145
Download
1
Embed Size (px)
Citation preview
Foundation design for tall buildingsFrom Pile Groups to Piled Rafts
Benoît LatapieTechnical Manager – Ground Engineering
16 November 2016 1
Underground Infrastructure and Deep Foundations UAE
1. Introduction to Combined Pile Raft Foundations (CPRF)2. Foundation design procedure / Case study3. Existing buildings on CPRF in Dubai4. Why carry out a preliminary test pile early and to failure?5. Benefits of using BS8004:20156. Common ME practice VS Atkins geotechnical approach7. Conclusions8. References
Foundation design for tall buildings
16 November 2016 2
From Pile Groups to Piled Rafts – Contents
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
0 1 2 3 4 5 6 7 8 9 10Pile spacing in multiples of its diameter Ø
Negligible pile interaction
Intro. to Combined Pile Raft Foundation
16 November 2016 3
Pile group interactionS
hear
stre
ss n
orm
alis
ed b
y sh
ear s
tress
at p
ile /
rock
inte
rface
( -)
Most CPRF have average pile spacing larger than 5Ø
Typical range of fully piled foundations
High pile interaction
Piles close to each other are not efficient.
Larger pile spacing have the following benefits:
• Decreases pile-to-pile interactions
• Increases pile utilisation
• Increases foundation efficiency
After the studies of Cooke (1974), Frank (1974) and Baguelin et al. (1975).
• Composite foundation that combines the bearing resistance of both raft and piles• Building loads shared between the piles and the raft• Piles are settlement reducers• The raft provides additional load capacity to the piles• Stiffness governs the design over bearing capacity
Intro. to Combined Pile Raft Foundation
16 November 2016 4
Design philosophy
Piled foundation design = Capacity Limiting + Settlement Check
CPRF design = Settlement Limiting + Capacity Check
Intro. to Combined Pile Raft Foundation
16 November 2016 5
The different types of foundations using rafts and piles
Sou
rce:
Bur
land
, J.,
Cha
pman
, T.,
Ski
nner
, H.D
. and
Bro
wn,
M
., 20
12.I
CE
Man
ual o
f Geo
tech
nica
l Eng
inee
ring.
Piles located to reduce shear and bending in raft.
Pile capacity fully mobilised.
B - Pile-enhanced raft
Piles at larger spacing than conventional pile group.
Piles located to minimise differential settlement.
Intro. to Combined Pile Raft Foundation
16 November 2016 6
The different types of foundations using rafts and piles
Source: Burland, J., Chapman, T., Skinner, H.D. and Brown, M., 2012. ICE Manual of Geotechnical Engineering.
C - raft-enhanced pile group
Intro. to Combined Pile Raft Foundation
16 November 2016 7
Complex soil-structure interaction mechanisms
1. Raft–soil interaction: The contact stresses between the raft and the soil are transmitted into the soil and settlement of the raft takes place.
2. Raft–soil–raft interaction: Interaction takes place through the soil with other parts of the raft.
3. Raft–soil–pile interaction: The raft contact stresses are also transmitted through the soil and interact with the piles.
4. Raft–pile interaction: Loads are transmitted into the piles directly by the raft.
5. Pile–soil interaction: The pile loads disperse into the ground surrounding the piles.
6. Pile–soil–pile interaction: Interaction takes place between each pile through the soil to other piles.
7. Pile–soil–raft interaction: Interaction also takes place between each pile through the soil to the underside of the raft.
Source: Burland, J., Chapman, T., Skinner, H.D. and Brown, M., 2012. ICE Manual of Geotechnical Engineering.
1. Introduction to Combined Pile Raft Foundations (CPRF)2. Foundation design procedure / Case study3. Existing buildings on CPRF in Dubai4. Why carry out a preliminary test pile early and to failure?5. Benefits of using BS8004:20156. Common ME practice VS Atkins geotechnical approach7. Conclusions8. References
Foundation design for tall buildings
16 November 2016 8
From Pile Groups to Piled Rafts – Contents
9
Foundation Design Procedure
16 November 2016
Outputs from the geotechnical analysis
For all structural elements, deflections, axial forces, shear forces and bending moment diagrams are available in the output.
Confidential project – case study
16 November 2016 10
Confidential project – case study
11
Plaxis 3D settlements
Maximum settlement: 42mm16 November 2016
Confidential project – case study
16 November 2016 12
SAFE settlements with Springs from Plaxis 3D
Maximum settlement: 47mm
Confidential project – case study
16 November 2016 13
SAFE settlements with Springs from SI Report
Maximum settlement: 13mm
1. Introduction to Combined Pile Raft Foundations (CPRF)2. Foundation design procedure / Case study3. Existing buildings on CPRF in Dubai4. Why carry out a preliminary test pile early and to failure?5. Benefits of using BS8004:20156. Common ME practice VS Atkins geotechnical approach7. Conclusions8. References
Foundation design for tall buildings
16 November 2016 14
From Pile Groups to Piled Rafts – Contents
Existing tall buildings with CPRF in Dubai
16 November 2016 15
A few numbers from published literature
Building HeightFoundation System
(dimensions)
Predicted Settlement
Bui
lt
Emirates Twin Towers 355mCombined Piled Raft Foundation(1.2mØ, 45m piles & 1.5m thick raft)
140mm
(1/378)
Burj Khalifa 828mCombined Piled Raft Foundation(1.5mØ, 50m piles & 3.7m thick raft)
80mm
(1/250)
On
Hol
d Pentominium Tower 516mCombined Piled Raft Foundation
(1.2-1.5mØ, 32-42m piles & 5m thick raft)92mm
Nakheel Tall Tower 1,000mCombined Piled Raft Foundation
(2.8mx1.2m, up to 58m barrettes & up to 8m thick raft)
Up to 100mm
Existing CPRF arrangements in Dubai 1/2
16 November 2016 16
Emirates Twin Towers Burj Khalifa
Contours of maximum axial load [kN]Typ. layout of one tower
Existing CPRF arrangements in Dubai 2/2
16 November 2016 17
Pentominium Tower (on hold) Nakheel Tall Tower (on hold)
1. Introduction to Combined Pile Raft Foundations (CPRF)2. Foundation design procedure / Case study3. Existing buildings on CPRF in Dubai4. Why carry out a preliminary test pile early and to failure?5. Benefits of using BS8004:20156. Common ME practice VS Atkins geotechnical approach7. Conclusions8. References
Foundation design for tall buildings
16 November 2016 18
From Pile Groups to Piled Rafts – Contents
Recommendations – PTP to failure
16 November 2016 19
Recommendations – PTP to failure
16 November 2016 20
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
0 10 20 30 40 50 60 70 80 90 100
Tota
l Axi
al L
oad
[MN
] –E
xam
ple,
typi
cal
Deflection at Pile's Head [mm] – Example, typical
Pile Load Test To Failure
Conservative Pile Load Test
Recommendations – PTP to failure
16 November 2016 21
Optimised working load
We propose to test the pile to geotechnical failure
FoS=2
FoS=2
Conservative test stops at empirical capacity
Under estimated working load
1. Introduction to Combined Pile Raft Foundations (CPRF)2. Foundation design procedure / Case study3. Existing buildings on CPRF in Dubai4. Why carry out a preliminary test pile early and to failure?5. Benefits of using BS8004:20156. Common ME practice VS Atkins geotechnical approach7. Conclusions8. References
Foundation design for tall buildings
16 November 2016 22
From Pile Groups to Piled Rafts – Contents
Benefits of using BS 8004:2015
16 November 2016 23
Time for an update?
https://login.dm.gov.ae/wps/wcm/connect/29d53e7c-7f22-4c42-aded-066727d87c0f/Structural+Codes+%26+guidelines+4.pdf?MOD=AJPERES
• BS 8004:2015 was updated in line with the Eurocodes• Partial factors may be reduced if pile load tests are carried out• Clear and detailed guidance on foundation design• Piled rafts are addressed with reference toICE Manual of Geotechnical Engineering (2012), Volume II, Chapter 56 is provided.
Benefits of using BS 8004:2015
16 November 2016 24
Time for an update?
Benefits of using BS 8004:2015
16 November 2016 25
Partial factors reduction based on in situ pile testing• Two partial factors are used in pile design to BS 8004:2015 (or/and BS EN 1997-1)
γRd model factor, used to obtain the characteristic ultimate pile compressive resistance Rc,k
γs and γb partial resistance factors for shaft and end bearing respectively.
Partial factor
DefaultValue
Testing to BS 8004:2015(i.e. UK NA to BS EN 1997-1)
Revised Value Saving
γRd 1.4 Maintained load test taken to the required unfactored ultimate resistance 1.2 14%
γs 1.6 Explicit verification of SLS:
Working test on 1% of constructed piles to loads not less than 1.5 times the representative load.
1.4 12%
γb 2.0 1.7 15%
Total SAVINGMinimum 25%
1. Introduction to Combined Pile Raft Foundations (CPRF)2. Foundation design procedure / Case study3. Existing buildings on CPRF in Dubai4. Why carry out a preliminary test pile early and to failure?5. Benefits of using BS8004:20156. Common ME practice VS Atkins geotechnical approach7. Conclusions8. References
Foundation design for tall buildings
16 November 2016 26
From Pile Groups to Piled Rafts – Contents
Common geotechnical approach in ME• Early stage project involvement
• Desk study
• Design/scoping and specification of high quality GI
• Carry out GI
• Full time GI supervision
• Factual reporting by contractor
• Review of factual reporting
• Interpretation
• Ground model + parameters + design
27
STANDALONEGROUND
INVESTIGATION CONTRACTOR
CONSERVATIVE / UN-ECONOMIC / RISKY SOLUTION
ECONOMIC RISK CONTROLLED FOUNDATION SOLUTION
• Early stage project involvement
• Desk study
• Design/scoping and specification of high quality GI
• Carry out GI
• Full time GI supervision
• Factual reporting by contractor
• Review of factual reporting
• Interpretation
• Ground model + parameters + design
Atkins proposal to reduce geotechnical risk
28
SPEC
IALI
ST G
EOTE
CH
NIC
AL
CO
NSU
LTAN
T
By GI Contractor
1. Foundation design for tall buildings is complex and requires sophisticated analyses2. 3D FE analyses encompass soil-structure interactions3. CPRF are economical and proven in Dubai4. Preliminary test piles with O-cells help reduce cost and risk5. BS8004:2015 is recommended for the design of foundations6. Ignoring project specific data raises the foundation risk7. Employing a specialist geotechnical consultant is recommended to maximise
opportunities
Conclusions
16 November 2016 29
• BS 8004:2015 Code of practice for foundations• Haberfield, C.M. and Paul, D.R. 2011. Footing Design of the Nakheel Tower, Dubai,
UAE in Workshop on soil-structure interaction and retaining walls. Proceedings of the Technical Meeting TC207 ISSMGE, Dubrovnik, pp 35 to 52.
• Poulos, H.G. and Bunce, G., 2008. Foundation design for the Burj Dubai–the world’s tallest building. 6th International Conference on Case Histories in Geotechnical Engineering, Arlington, VA.
• Poulos, H.G. and Davids, A.J., 2005. Foundation design for the Emirates twin towers, Dubai. Canadian Geotechnical Journal, 42(3), pp.716-730.
• Ibrahim, K., Bunce, G. and Murrells, C., 2009, December. Foundation design for the Pentominium tower in Dubai, UAE. In Proceedings of the Institution of Civil Engineers-Civil Engineering (Vol. 162, No. 6, pp. 25-33). Thomas Telford Ltd.
References
16 November 2016 30
Foundation design for tall buildingsFrom Pile Groups to Piled Rafts
Benoît LatapieTechnical Manager – Ground [email protected] November 2016 31
Underground Infrastructure and Deep Foundations UAE
QUESTIONS?