1415 H24MPP Lecture 11 - Conditions of Contract

Embed Size (px)

Citation preview

  • 7/25/2019 1415 H24MPP Lecture 11 - Conditions of Contract

    1/26

    Ioannes Tang

    Senior University Teaching Fellow

    Department of Civil Engineering

    Faculty of Engineering

    Room: B1C16, Telephone: 03-8924 8346

    Email: [email protected]

    Based on original notes by

    W H Askew

    H24MPP Lecture 11

    Conditions of Contract

  • 7/25/2019 1415 H24MPP Lecture 11 - Conditions of Contract

    2/26

    Introduction

    Construction projects involve a number of companies

    (parties) doing work they are responsible for

    Links between parties identify the roles and

    responsibilities and have a legal context

    Explicit links are contracts or agreements

    Some legal rights exist when no contract exists

    Contracts often use standard clauses and terms

    expressed in standard forms of contract

    The contract must fit into the prevailing legal system

    We will look at two standard contracts

    2

  • 7/25/2019 1415 H24MPP Lecture 11 - Conditions of Contract

    3/26

    Parties to Contract

    The key parties to a main construction

    contract are:

    client (or Employer)

    contractor

    Other parties may be named, or exist in

    other contracts:

    Consultants (or Engineer)

    sub-contractors

    suppliers

    3

  • 7/25/2019 1415 H24MPP Lecture 11 - Conditions of Contract

    4/26

    Key Topics in Clauses

    Roles and responsibilities (relationships)

    Procedures for execution of project

    Dealing with money and time

    Dealing with changes

    Dealing with disputes and their avoidance

    RISK ALLOCATION

    Contracts evolve and create/follow trends. Consider

    the following clause from 80-100 years ago:

    4

  • 7/25/2019 1415 H24MPP Lecture 11 - Conditions of Contract

    5/26

    Example of Early Contract Clause

    In the event of anything reasonably necessary or proper to the

    due and complete performance of the work (of which the

    Engineer shall be the sole judge) being omitted to be shown or

    describedin the said drawings or schedules the contractor shall

    notwithstanding execute and provide all such omitted worksand things as if they had been severally shown and described

    without any extra charge and according to the directions of the

    Engineer and to his satisfaction.

    What are the concerns?

    Who carries the risks?

    Would it be a good clause now?

    5

  • 7/25/2019 1415 H24MPP Lecture 11 - Conditions of Contract

    6/26

    Conditions of Contract I

    Particular clauses will be examined in:

    New Engineering ContractEngineering and

    Construction Contract Edition 3 (NEC ECC)

    ICE Conditions of Contract (7th ed) (ICE 7)

    6

  • 7/25/2019 1415 H24MPP Lecture 11 - Conditions of Contract

    7/26

    Conditions of Contract II

    Others include:

    JCT,

    FIDIC,

    Design and Construct,

    Small Works,

    Subcontracts,

    Framework contracts,

    Terms of engagement

    7

  • 7/25/2019 1415 H24MPP Lecture 11 - Conditions of Contract

    8/26

    ICE7 Clauses

    71 specific clauses

    5-7 Contract documents

    8-35 General obligations

    12 Adverse physical conditions and artificial obstructions

    14 Programme to be furnished 17 Setting out

    32 Fossils etc

    41-46 Commencement time and delays

    51-53 Alterations additions and omissions

    55-57 Measurement system

    60-61 Certification and payment

    66 Avoidance and settlement of disputes

    8

  • 7/25/2019 1415 H24MPP Lecture 11 - Conditions of Contract

    9/26

    13 - Work to be to satisfaction of

    Engineer

    13(1)

    Save insofar as it is legally or physically impossible

    Contractor shall construct and complete in strict

    accordance with the Contract to the satisfaction of the

    Engineer (whether mentioned in the Contract or not).

    13(3) covers Delay and extra cost and in addition to the

    above refers to clauses 5, 44, 51, 53, 60

    9

  • 7/25/2019 1415 H24MPP Lecture 11 - Conditions of Contract

    10/26

    44 - Extensions of time

    Deals with possible extensions of time for:

    any variation ordered under clause 51(1)

    any increased quantities under clause 51(4)

    any cause of delay in any of the clauses

    exceptional adverse weather conditions

    any delay impediment prevention or default by

    the Employer other special circumstances of any kind

    whatsoever which may occur

    10

  • 7/25/2019 1415 H24MPP Lecture 11 - Conditions of Contract

    11/26

    51-53Variations

    51 - allows for any variation necessary with a

    variation defined as additions, omissions,

    substitutions, alterations to quality, form,

    character, kind, position, dimension, level orline

    52 - covers the valuation of ordered variations

    53 - covers procedure for additional payments

    11

  • 7/25/2019 1415 H24MPP Lecture 11 - Conditions of Contract

    12/26

    12 - Adverse physical conditions and

    artificial obstructions

    excludes weather conditions and conditions

    due to weather conditions

    acknowledges risks with could not in his

    opinion reasonably have been foreseen by anexperienced contractor

    and shall as early as practicable give written

    notice

    allows consideration with if the Contractor

    intends to make any claim for additional

    payment or extension of time arising from such

    condition 12

  • 7/25/2019 1415 H24MPP Lecture 11 - Conditions of Contract

    13/26

    66Disputes

    66(2) - If the Contractor or Employer are dissatisfied

    with anything the matter shall be referred to the

    Engineer who shall notify his decision to the

    Employer and Contractor within one month

    66(3)&(4) - mentions decision of Engineer and/or

    adjudicator

    66(5) - covers conciliation procedure

    66(6)-(8) - cover adjudication procedure66(7)-(11) - covers arbitration procedure

    THIS IS A KEY RISK SHARING CLAUSE13

  • 7/25/2019 1415 H24MPP Lecture 11 - Conditions of Contract

    14/26

    ICE7 and NEC3 I

    Note the fragmented structure of ICE 7

    Many clauses refer to clauses 44, 51-53 which

    allow consideration of extra time and money

    Clauses refer to claims and disputes

    Users attitude can be adversarial with disputes

    arising too easily and taking too long to resolve

    14

  • 7/25/2019 1415 H24MPP Lecture 11 - Conditions of Contract

    15/26

    ICE7 and NEC3 II

    Nevertheless it has been the contract of choice

    for many years and forms the basis of the

    international FIDIC conditions

    It has been extended to include a partneringaddendum

    It is promoted by ICE and other

    professional/industry groups

    So too is its main rival and now arguably

    preferred NEC3

    15

  • 7/25/2019 1415 H24MPP Lecture 11 - Conditions of Contract

    16/26

    New Engineering Contract

    Engineering and Construction Contract

    Has a general spirit of co-operation

    expressed in its aim to stimulate good

    management and cover a wide variety of

    work

    It has many parts which can be selected

    and bolted together as appropriate, whilst

    being clear and simple to understand

    16

  • 7/25/2019 1415 H24MPP Lecture 11 - Conditions of Contract

    17/26

    NEC3 Structure

    Contains core clauses 1-9

    And 6 option clauses A-F

    And 18 secondary option clauses X-Z (X1-7, X12-18, X20,

    Y(UK)2, Y(UK)3, Z

    And dispute resolution clauses W1, W2 It includes a partnering option (X12)

    17

  • 7/25/2019 1415 H24MPP Lecture 11 - Conditions of Contract

    18/26

    Choosing NEC3

    Firstly choose either:

    A priced contract (with activity schedule or bill of

    quantities) (A or B)

    A target contract (with activity schedule or bill ofquantities) (C or D)

    A cost reimbursable contract (E)

    A management contract (F)

    Also choose either: Dispute Resolution Option (W1 or W2)

    Then choose secondary options X (more

    complicated but none needed)18

  • 7/25/2019 1415 H24MPP Lecture 11 - Conditions of Contract

    19/26

    NEC3 Core Clauses

    1. General

    2. Contractors main responsibilities

    3. Time

    4. Testing and defects

    5. Payment

    6. Compensation events

    7. Title

    8. Risks and insurance

    9. Termination

    19

  • 7/25/2019 1415 H24MPP Lecture 11 - Conditions of Contract

    20/26

    NEC3

    Clause 1

    10.1 shall act in a spirit of mutual trust and cooperation

    States responsibilities for:

    Employer

    Contractor

    Project Manager

    SupervisorAdjudicator

    [ICE 7 mentions only Employer, Contractor, Engineer,

    Engineers Representative, Nominated Subcontractor]

    20

  • 7/25/2019 1415 H24MPP Lecture 11 - Conditions of Contract

    21/26

    NEC3

    Clause 3

    31 Programme to be submitted [cf. ICE 7 clause 14]

    Clause 550 Assessment of amount due [cf. ICE 7 clause 52, 55-57]

    51 Payment of amount due [cf. ICE 7 clause 53, 60]

    21

  • 7/25/2019 1415 H24MPP Lecture 11 - Conditions of Contract

    22/26

    NEC3

    Clause 6

    60 Compensation events [cf. several ICE 7 clauses]

    61 Notification [cf. ICE 7 clauses 51-53]

    62 Price quotations [ditto]63 Assessing [ditto]

    64 Project managers assessments[ditto]

    65 Implementing [ditto]

    22

  • 7/25/2019 1415 H24MPP Lecture 11 - Conditions of Contract

    23/26

    Clause 60.1 Compensation events

    1. Changes to the Works information

    2. Revised site accessibility

    3. Late provision of information

    4. Timing changes5. Employer not working to times

    6. Delay responding

    7. Found valuable/historical objects

    8. Changed decision

    9. Withholding acceptance

    23

  • 7/25/2019 1415 H24MPP Lecture 11 - Conditions of Contract

    24/26

    Clause 60.1 Compensation events

    10. Defects not found

    11. Delay caused by test/inspection

    12. Adverse physical conditions

    13. Unusual weather14. Employers risk event

    15. Early take-over of works

    16. Materials facilities not provided

    17. Correction to assumption

    18. Breach of contract

    19. Unpreventable/unforeseeable event24

  • 7/25/2019 1415 H24MPP Lecture 11 - Conditions of Contract

    25/26

    Clause 60.1(12) Adverse physical

    conditions

    The Contractor encounters physical conditions which

    Are within the Site

    Are not weather conditions

    An experienced contractor would have judged at theContract Date to have such a small chance of occurring

    that it would have been unreasonable for him to have

    allowed for them.

    Only the difference between the physical conditions

    encountered and those for which it would have been

    reasonable to have allowed is taken into account in

    assessing a compensation event.

    25

  • 7/25/2019 1415 H24MPP Lecture 11 - Conditions of Contract

    26/26

    Clause 60.1(13) Unusual Weather

    A weather measurement is recorded

    within a calendar month

    before the Completion Date for the whole of the works

    and at the place stated in the Contract Data

    the value of which, by comparison with the weather

    data, is shown to occur on average less frequently than

    once in ten years. Only the difference between the weather measurement

    and the weather which the weather data show to occur

    on average less frequently than once in ten years is

    taken into account in assessing a compensation event.26