Upload
richard-nguyen
View
45
Download
5
Tags:
Embed Size (px)
Citation preview
PROJECT
TAN TAO DEVELOPMENT
SPECIFICATION ELECTRICAL
JULY 2014
SPECIFICATION ELECTRICAL
M&E CONSULTANT
MARS CORPORATION
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 1/12
GENERAL REQUIREMENTS
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 2/12
1. SITE INSPECTION
Tenders must inspect the site to familiarize themselves with the conditions thereupon
prior to Submission of tender. Confirmation of site inspection shall be Submitted with
tender.
2. SPECIFICATION AND DRAWINGS
The drawings provided with this Specification shall be read in conjunction with this
Specification.
The Specification and drawings are mutually explanatory, and all work called for by one,
even if not by the other, shall be fully executed and completed.
The drawings shall be considered approximate and diagrammatic only. Actual
dimensions shall be obtained by The Contractor.
Accept the responsibility to ascertain that all particular equipment offered fits into the
provided spaces taking into consideration the requirements for maintenance and other
factors affecting the installation.
3. DISCREPANCIES & OMISSIONS
If any discrepancy, contradiction or omission appears in the specification or drawings,
the Tenderer shall refer same to the Project Manager and Consultant for resolution before
Submitting a Tender. The Consultant will issue directives on such matters in writing.
Oral amendments to the specification shall not be recognised by the Tenderer.
4. SETTING OUT OPENINGS AND MAKING GOOD
The precise location of all openings, fixings and similar items of work required for these
works to be provided by the Contractor shall be determined at such times as not to cause
delay to the work. All items shall be checked to ensure correct positioning. If openings,
fixings and similar items of work are wrongly located or are omitted due to incorrect or
lack of information, the cost of any remedial works shall be paid for by The Contractor.
The specification drawings are diagrammatic only and unless otherwise stated shall not
be used for determining the precise positions of equipment outlets and like features. The
exact location of these shall be determined on site or from shop drawings.
All chases, recesses and penetrations in structural elements not shown on the building
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 3/12
and structural drawings shall be Subject to approval.
5. POSITIONING OF OUTLETS AND EQUIPMENT
The layout of equipment shown on the drawings is diagrammatic only, and exact
positions shall be determined on site. Final position shall be to the approval of the
Project Manager. Ensure that all plant offered in suitable for installation in the location
and spaces shown on the drawings and will be accessible for maintenance in accordance
with the manufacturer’s recommendations when installed.
6. POSITIONING OF OUTLETS AND EQUIPMENT
The layout of equipment shown on the drawings is diagrammatic only, and exact
positions shall be determined on site. Final position shall be to the approval of the
project director.Ensure that all plant offered in suitable for installation in the location and
spaces shown on the drawings and will be accessible for maintenance in accordance with
the manufacturer’s recommendations when installed.
Outlets shall be spaced accurately and symmetrically within rooms.
Positions of all outlets, switches and fittings shall be chalked up in areas where the
outlets are adjacent to tiles or other architectural dados. Approval of the Consultant shall
be obtained before placing any final conduits or wiring for these outlets.
The position of outlets and switches shown on the drawings is assumed to be correct,
however, variations of up to 2m may be effected without cost variation if the change is
advised before the outlet or switch is fitted off.
Where outlets are in close proximity they shall be aligned horizontally and/or vertically
as the case may be.
Equipment shall be symmetrically located in relation to other equipment and devices, the
building module and general aesthetic treatment.
7. CO-ORDINATIONOF INSTALLATION
Co-ordination shall be carried out to ensure that all items for installation in false ceilings
are provided in sufficient time to comply with the Contractor’s program. All other
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 4/12
services within false ceilings shall be completely installed so that it will not be necessary
to remove any ceiling tiles to finish other work, apart from commissioning.
Responsibility and provision shall be allowed for any cost where due to delays or
deficiencies attributable to this Contract, ceiling tiles must be removed and replaced, or
additional penetrations provided in the ceiling.
8. PERFORMANCE AND GUARANTEE
The Tenderer will, by the fact of his tendering, be regarded as guaranteeing that:
a) The equipment offered by him is of the most modern and correct design and
construction and of the necessary capacity to efficiently perform the work specified.
b) The equipment offered is capable of being installed in the plant space shown on the
exhibited drawing with adequate clearance for its proper operation and maintenance.
c) The equipment offered will provide the minimum capacities as scheduled elsewhere in
this Specification or on the drawings.
d) All the settings and limits of all control instruments and equipment shall be the
responsibility of The Contractor and he shall ensure that the specified requirements and
conditions are met.
9. CONSTRUCTION DRAWINGS
The Contractor shall prepare working drawings (shop drawings) of the proposed
installation. All working drawings shall be submitted to the Consultant for approval
before commencing any work. All checking and approval of such drawings by the
Consultant shall be construed as gratuitously assisting The Contractor and does not
relieve The Contractor from responsibility for errors or omissions.
Where such errors or omissions are discovered later they shall be corrected by The
Contractor irrespective of any approval given by the Consultant. Approval of drawings
shall not be construed as authorising additional work or increased cost to the principal In
the event that the drawings indicate additional work involving increased cost, The
Contractor shall notify the Consultant at the time of submission of the drawings.
10. AS-BUILT DRAWINGS
As from the commencement of work The Contractor shall employ a competent
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 5/12
draughtsman to keep a record of all deviations and changes from the contract and
workshop drawings and shall mark on a set of prints an accurate record of all work as
actually installed.
During the progress of the work The Contractor shall have recorded on AutoCAD files,
as specified, the installations as actually built, and shall submit these to the Consultant for
checking. Upon approval by the Consultant of these drawings The Contractor shall
provide at his own expense sets of prints as specified elsewhere. In addition The
Contractor shall provide sets of correctly recorded diagrams, schedules of equipment,
piping, fittings and all information regarding the installations as actually built.
The Contractor shall in addition retain one copy of each of the "as installed" drawings
and schedules for use by him during the Defects Liability Period.
11. EQUIPMENT DEVIATIONS
The dimensions and ratings of equipment specified herein or indicated on the drawings
are intended to establish the outlines and characteristics of equipment Supplied by the
particular manufacturers specified. Where The Contractor intends to use an item of
equipment other than that specified or shown on the drawings or in the Schedule of
Technical Data in the Contract, he must apply in writing to the Consultant and await
written approval before proceeding.
12. PACKAGED EQUIPMENT
Where packaged or unitary equipment is specified or offered against this Specification,
such equipment shall be modified to conform with the requirements of this Specification,
whether or not this requires modification of the Manufacturer's standard construction.
The fact that the Tenderer may have offered a particular packaged item by name shall not
absolve him from modifying it to meet the Specification.
13. SAMPLES AND PROTOTYPES
Samples of materials and items described as "to be approved" shall be delivered to site at
least 15 days before approval is required. Two samples shall be supplied of each item
required, each one to be properly identified and marked with the suppliers name and
model number. One of the samples shall be held on site, the second shall be returned to
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 6/12
The Contractor/Manufacturer once it has been viewed and comments have been received
from the Project Manager. On acceptance the samples will be marked with date
approved and by whom
Submit the following sample fittings and accessories to obtain approval of the C Project
Manager before installation:
- Light Fittings;
- Power Outlets, Switches.
- Conduits, Cables, Cable Tray, Trunking ….
Arrange for the Project Manager to inspect the samples to obtain approval and acceptance
in writing of the offered samples.
The approved samples shall be retained on site for reference purposes until completion of
the work. All such materials used in the work covered by this specification shall conform
with the approved samples.
The Project Manager will be at liberty at any time to test or analyse samples of any
materials brought onto the site and intended for these Works.
In addition to the above requirements for the production, submission and approval of
samples and prototypes, the Contractor may prepare an area in advance of the general
construction cycle. The purpose of this area shall be to ensure co-ordination of all
services and finishes and as a display area. Provide and install all samples and prototypes
required for such an area as directed by the Contractor.
14. RADIO INTERFERENCE
All equipment and/or appliances provided under this specification shall be designed so
that no interference will be caused with any radio or other electronic transmitting or
receiving equipment in the same locality. In the event of the inherent characteristics of
the electrical installation being such that interference is possible, efficient devices or
screening techniques capable of eliminating such interference shall be provided at The
Contractor's expense.
Define the areas susceptible to interference prior to the purchase of equipment and
appliances and advise the Consultant of the methods to be adopted to reduce the
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 7/12
interference.
15. WORKMANSHIP AND MATERIALS
The Contractor shall provide skilled and expert labour as necessary to carry out the work
in the best possible manner. The quality of workmanship shall be of first grade and in
accordance with the highest standards of the respective trades. Workmanship of poor
quality or of an unacceptable standard will be rejected by the Consultant and must be
replaced by The Contractor at no extra cost to the Principal with workmanship of the
required standard.
All materials, fittings, accessories and apparatus are to be of first grade design and
manufacture and are to comply with the British standard or relevant specification. All
materials, fittings, accessories and apparatus shall be new and shall be of current model
and design unless specified otherwise. The Contractor must Submit for the approval of
the Project Manager prior to commencing installation, a list of all accessories, fittings and
apparatus which it is proposed to employ in the work, and only such items as have been
approved may be installed. Failure to comply with this provision will result in the
unconditional rejection of such items when inspected on site.
Where directed by the Project Manager "approved" samples shall be kept on site. Each
item of equipment shall be a standard catalogue product of an established, reputable,
approved manufacturer. All similar equipment shall be of the same manufacture, type,
class and finish, unless otherwise specified.
Where manufacturer catalogue numbers or types are specified or shown on the Drawings,
they are generally intended to be used as a guide, and are not intended to take precedence
over the basic duty and performance specified or shown. In all cases, verify the duty with
the particular characteristics of the equipment offered for approval.
Where no alternative materials are noted in the specification or on the drawings and
where the words "equal", "approved equal", "as approved" etc do not appear, the exact
make specified must be Supplied and installed. No alterations will be permitted in the
lists of manufacturers and suppliers Submitted by The Contractor with his Tender or
Subsequently without the written approval of the Project Manager.
Should The Contractor install materials and/or equipment other than by the approved
manufacturer or supplier, such items may be rejected on site. All such rejected items
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 8/12
shall be removed from the site as soon as possible and be replaced by approved items at
no cost to the Principal.
The replacement of any such items shall not constitute grounds for any variation or any
extension of time.
The Contractor shall take every care to avoid damage to fittings, surfaces and equipment
in the premises and any damage caused by his staff and/or the works of his Contract shall
be his responsibility and shall be made good at his expense.
16. PRECAUTIONS IN CARRYING OUT WORKS
Where any current Standard published by the Standards Association of Australia is
appropriate to storage, transport and use of materials, plant and equipment, to work
processes or to safety precautions the provision of such Standard shall be observed except
if they conflict with any statutory or special requirements of proper authority in which
case the latter shall apply.
In the absence of any such statutory or special requirements or relevant Standard, The
Contractor shall ensure that suitable procedures are observed and all proper care is taken.
During construction, cleaning all equipment unfinished in a safe place and protect
equipment from damage or loss.
17. SCAFFOLDINGANDLIFTING QUIPMENT
Unless specifically instructed otherwise, provide all necessary temporary lifting
equipment, scaffolding, framing or other supports to enable installation and access to the
work.
18. SEALING OF PENETRATIONS
a) Waterproofing of Penetrations
Floor penetrations for cable risers shall be made weatherproof progressively during the
construction of the works to minimise weather damage or effects of internal flooding
within the building.
b) Acoustic Sealing
Wherever services penetrate walls, floors or ceilings, acoustic sealant shall be supplied
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 9/12
and installed to maintain a degree of acoustic separation at least equal to the materials
penetrated.
c) Fire Barrier Penetrations
Where services penetrate fire walls, ceilings, floors or other fire rated barrier, sealant for
those penetrations shall be sealed to the approval of the Authorities.
19. FIXINGS AND PLUGS
Holes shall be drilled by electric or compressed air drill wherever possible. Explosive
charge fixing devices shall not be used.
Where devices are required for attaching materials or equipment to the building approved
metal expansion devices shall be used when and where approved by the Consultant.
Wooden plugs will not be permitted. Approval of the Consultant shall also be obtained
prior to drilling to ensure that any post tensioning cables in the slab are not damaged.
The Contractor will mark the location of all such cables.
Cadmium plated expanding metallic type masonry anchors shall be used for fixings in
concrete, clay or concrete brickwork. Except in fire isolated stairways and tunnels
conduits may be saddled to walls and ceilings using "Tappits" or similar fixing devices.
Fixed or suspended light fittings shall be supported from the concrete slab using
"Dynabolts" or "Ramset" fixings.
Bolts or machine screws with nuts, washers and anti-vibration devices shall be used
where necessary for fixings into metal.
Plugs may be used for screw fixing to masonry construction including plastered
expanded metal. Such plugs shall be used only for minor shear loadings. Holes and
inserts and PVC screw anchor plugs, "Expandet" brand or equivalent shall be correctly
sized.
Cadmium plated bolts, screws and washers shall be used in all instances.
20. STORAGE AND PROTECTION
The Contractor shall be responsible for proper storage and protection of apparatus,
materials and equipment on any site adjacent to, associated with or the Subject of the
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 10/12
works.
Upon delivery to site all materials and equipment shall immediately be secured properly
stacked and protected from the weather dampness and dust with particular attention to
preventing ingress to working parts and pipes. The Contractor shall be responsible for
storing all equipment which cannot be accommodated on site.
The Contractor shall be instructed with regard to storage of materials, particularly heavy
loads. All equipment and materials shall be stored clear of floor slabs on timber packers.
Special care shall be exercised to prevent the ingress of dirt, moisture and foreign
Substances into conduit pipes, duct and equipment. Should such ingress occur carefully
remove the offending matter and thoroughly clean the conduit pipes, ducts and equipment
to approval.
When any room in the building is used as a shop or storeroom in connection with these
works all resulting making good and repairs, patching or cleaning of the room arising
from such use shall be carried out prior to completion of the works.
Mixing of any materials on the floors other than where such material is finally to be
located shall not be permitted.
Fittings or other equipment shall not be used as a place for depositing tools and materials,
as a means of supporting scaffolding or for use as a work bench.
21. DIMENSIONS
Dimensions must be checked before work is put in hand or prefabricated. All invert
levels on the drawings are recommended only and must be checked on site before
excavation or installation of pipework to ensure connection to supply services and correct
cover and fall.
22. LABELLING
All switches, fuses, relays, terminal strips, circuit breakers and compartments shall be
comprehensively labelled to clearly indicate their function.
Labels shall be of Sandwich Ivorine or Traffolyte material, white with black lettering for
normal power and white with red lettering for standby power.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 11/12
Circuit breaker labels shall include base rating and protection setting.
Submit all label schedules for approval prior to manufacture.
The labels on switchgear protecting outgoing circuits and sub-mains greater than 6
sq.mm per phase shall include the cable size, number of cores and cable type.
Labels for fuse combination units shall include both fuse rating and frame rating.
Each power outlet shall be engraved or fitted with a means of identification, indicating
the circuit protective device and the distribution board to which the switch or outlet is
connected. In the case of metal-clad power outlets, or equipment isolators, this means of
identification shall be 5mm uppercase engraving red filled or an ivorine label, screwed to
the metal casing of the switch or outlet, the label to be 10mm wide with 5mm lettering
(white) on a black background.
For outlets and equipment other than metal-clad, engraving shall be 3mm uppercase red
filled or circular tag labels equal to those referred to as "IPA studs".
Where consumer main and sub main cables enter and leave trays, racks, troughs or ducts
along their route length and at each end they shall be labelled according to the cable
schedule, or as directed with stamped aluminium or brass tags attached with nylon straps
or other approved means. Such straps shall be used to tie together single core cables of
the one circuit.
Where extra low voltage dichroic lamp luminaires are used within the installation a label
shall be attached to each switchboard stating the following, "Warning: Ceiling mounted
recessed extra low voltage lighting fittings are installed in these premises. In order to
avoid the risk of overheating they MUST NOT be covered by thermal insulation".
23. POWER FACTOR, BALANCING & VOLTAGE DROP
Ensure and be responsible for the final installation having:
- An overall power factor min. 0.85;
- The balance of over phases follow current standard;
- A voltage drop ensure that voltage drop does not exceed 5% from the point of
connection to the furthest outlet during normal conditions of operation.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 12/12
- All of the above to the satisfaction of the Local Power Company.
24. EARTHING
Earthing of the complete electrical installation shall be strictly in accordance with the
requirements of the SAA Wiring Rules, and the special requirements of the specification
and the Local Power Company.
Earth conductors, excepting earth conductors in insulated and sheathed cables, shall be of
annealed stranded copper of a size not less than 2.5m2 and shall be insulated and enclosed
in conduit with the respective circuit wiring. Earth conductors in insulated and sheathed
cables shall be a minimum of 2.5m2.
The whole of the system shall be mechanically and electrically continuous throughout.
All general purpose power outlets and light fittings shall be earthed.
25. COLOUR CODING
The correct phase colour for each active conductor shall be extended throughout all
circuits.
26. SITE CLEANLINESS AND REMOVAL OF RUBBISH
The Contractor shall remove from site all rubbish, debris, material cuttings and other
redundant materials which result from the works of this Trade-contract, progressively and
whenever directed by the Contractor
On completion of the work, promptly remove all materials and equipment from site,
except such materials and equipment which the Principal has agreed to store for use
during the Maintenance Period or as are required for testing.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 1/7
ELECTRICAL COMMISSIONING
AND MAINTENANCE
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 2/7
1. ELECTRICAL COMMISSIONING
1.1. GENERAL
1.1.1. FUNCTIONAL DESCRIPTION
A specialist team is to be engaged tocarry out the commissioning of theelectrical
services. This team may consist of the contractors employees, if their experience and
aptitude isapproved.
The commissioning of the electricalsystems is a critical stage and the specialist team need
to be involved withthe project from an early stage. This should be approximately 1
month prior to the availability of permament electrical power to the site.
A fully commissioned and documentedsystem is required at the end of theproject, and
this section of thespecification describes the minimumactivities required.
1.1.2. CROSS REFERENCES
General
Refer to the General requirementsworksection.
Related Worksections
Electrical General Requirements, MV Switchgear, Transformers, Switchboards,
Switchboard Components, Motor Starters, Generating Sets, Lighting, Lightning
Protection, Fire detection & Alarms
1.2. COMMISSIONING
1.2.1. GENERAL
All testing shall be in compliance with relevant Standards.
All testing shall be scheduled and approved.
Complete test and inspection records shall be made and incorporated into a report for
each piece of equipment tested. All readings taken shall be recorded.
Following established procedure, equipment will be, energised after certification that the
installation is satisfactory. Final operational tests shall determine that the wiring
connections are correct.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 3/7
1.2.2. INSPECTION AND TESTING
System testing schedule
Test Demonstrate Hold point
Dielectric Tests on all electric
cables, components and accessories
to IEC/BS.
Functional and operational
testsafter protective and control
devices have been installed and
connected.
Functional testing
Operate mechanical devices, relays,
programmable logic controllers and
logic control, protection,
interlocking and alarm equipment.
Verify time/current
characteristics and settings on
adjustable trip circuit breakers
after installation and before
energisation.
Interconnected systems
Functional and operational
performance
All systems in accordance with the
performance required for this
project
Performance and
interoperability between
systems
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 4/7
Material inspection and testing schedule
Inspection/test
Requirement or
acceptance
criteria
Method
Frequency
Hold/witness
status
Accessories Straight and
level
Site
inspection
Once on
completion
Completion
Conduit and cable
tray
Straight and
level
Site
inspection
Site
inspection
Progress status
Insulation resistance IEC/BS IEC/BS Once on
completion
Completion
Touch potential IEC/BS IEC/BS Once on
completion
Completion
Lightingperformance Lux/colour
Meter Once on
completion
Completion
Emergency and
evacuation lighting
IEC/BS Meter
6 months Completion
1.2.3. TEST INSTRUMENTS
All instruments and appliances required far testing shall be furnished for theduration of
the tests.
Gauges, thermometers or other instruments specified as a permanent part of the
installation may be used for testing purposes.
Test instruments shall be tested for accuracy by an approved laboratory and recent test
certificates shall be made available prior to testing.
1.2.4. TEST REPORT TERMS
The results of all testing shall hesubmitted in a neat and legible manner.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 5/7
1.2.5. INFRA RED THERMOGRAPHIC TESTS
Infra red thermographic tests shall beconducted after Practical Completion asfollows:
(a) When the electrical system is loadedto 50% of its maximum demand or, 10 to 12
weeks after practical completion, whichever occurs first.
(b) One month before the expiry of theWarranty period.
(c) Subsequently, after the expiry of the Warranty period, at six monthly periods, at rates
to be negotiated.
(d) If "Hotspots" or overheating issuspected from the results of the tests carried out under
(a) to (c) above, the defective components shall be rectified and another thermographic
test shall be conducted after rectification of the fault. In this case; the test can be limited
only to the faulted equipment.
Thermographic scanning shall beconducted only after the electrical installation has
been under load for a minimum period of one hour.
Tests shall be conducted on the main switchboard, busducts, distribution boards and all
electrical connections and components rated at, or greater than, 60A per 3 phase; or 50A
per single phase.
The test instrument used shall provide computerised processing of images andbe able to
record actual temperatureprofiles of the component under test toproduce a COLOUR
image.
Submit a detailed report, complete withhard copy printouts & photographs of the
installation, taken as normal images and as COLOUR infra red images.
1.2.6. LIGHTING LEVELS
Record lighting levels in all areas on a 5m x 5m grid. Tabulate results against specified
design levels.
1.2.7. COMPLETION
General
General: When the installation is complete, commission the installation byputting it into
working order and operating it for at least the designated running period. Make the
adjustments necessary to achieve the designatedperformance under continuous operating
service conditions, including balancing,setting the controls, checking the operation of
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 6/7
overload and safety devices, and correcting malfunctions.
1.2.8. CLEANING
General
At practical completion, clean the following:
-Switchgear and contactors, and otherelectrical contacts. Adjust as necessary.
-Ensure all equipment requiring dust orwater protection is suitably protected. Prepare a
schedule of all suchequipment and certify the installationis satisfactory.
1.2.9. TRAINING
Operation
Provide instruction and operating procedures to be adopted for this project.
1.2.10. SPARES
Required spares schedule
Tools - all systems
Supply one set of special installation, operation and
servicing tools.
Indicator lights Provide 3 spare lamps and one lampextractor per 10
indicating lights. Locate in spares cabinet.
Alarm annunciators
Provide 3 spare lamps, lamp remover, screen remover (if
applicable), mountedon clips in the assembly enclosure
or inspares cabinet.
Fuse links Provide 3 spare fuse links for each ratingof fuselink on
each assembly. Mount spares on clips within the spares
cabinet.
2. MAINTENANCE
Regular maintenance
Make service visits and carry out the following procedures, as applicable:
- Service items of equipment.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 7/7
- Check equipment items for operation, calibration, performance compliance,
temperature and energy consumption and record values.
- Check motors and machinery for excessive operating temperature, bearing noise and
excessive vibration. Record current draw of motors.
- Check condition of insulation, and repair.
- Check electrical and control systems, including safety limits for temperature,
pressure and humidity.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 1/43
ELECTRICAL SERVICES
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 2/43
1. INTENT OF SPECIFICATION
This specification covers the Electrical Installation Works.
This specification is intended to cover the supply of all materials, all labour,
transport, tools, plant and everything else necessary for the construction,
installation, testing, commissioning, and 12 months Maintenance and Defects
Liability of the equipment and systems described in this technical specification,
together with all minor and incidental work not specifically mentioned herein, to the
true intent and meaning of this technical specification and the drawings.
All works noted and/or described in this specification and associated drawings, shall
be carried out by this Contractor, unless otherwise noted as being done by others.
This Contractor shall be responsible for the installation and method thereof of all
specified works and all shall be to the Engineer’s approval.
All workshop drawings prepared by the Contractor shall be submitted to and
approved by the Engineer prior to any work being commenced.
2. CONTRACTORS RESPONSIBILITY
As detailed further herein, this technical Specification is concerned with the
distribution and reticulation of electricity throughout the Building. The Contractor
shall hold current Government work permits and Authority to allow him to carry out
the herein specified works.
The Contractor shall be responsible for obtaining all necessary permits from all
governing Authorities before work commences, during the process of the works and
at Completion of the works.
The Contractor shall assist in the commissioning and assist the Client in obtaining
all Authority Certificates of Completion and ready to occupy.
The Contractor shall be fully responsible for ensuring that all equipment as
determined by him and supplied by him, fully complies with the specified
requirements and true intent of this specification.
3. SCOPE OF WORK
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 3/43
This specification covers the supply, installation, testing, commissioning, guarantee,
preparation of necessary drawings, operating instructions and manuals, all associated
with the electrical services, to the extent specified herein and as shown on the drawings.
The specification and drawings are intended to include everything for the proper
completion and setting into effective operation of the complete Electrical Installation.
The works shall include but not be limited to the provision of the following:
The supply and installation of L.V. Main Switchboard.
The supply and installation of various L.V. Distribution Switchboards.
The supply and installation of all submains including cable trays, ducts, conduits etc…
The supply and installation of a combined L.V earthing system in the L.V. equipment.
The supply and installation of a separate telephone earthing system.
The supply and installation of a lightning discharge earthing system of building.
The supply and installation of complete lightning surge arrestor system throughout whole
building.
The supply and installation of all light and power connections, specified power sockets,
power connections to Mechanical, Fire, and Hydraulic plant etc.
The supply and installation of all lighting fittings
The supply and installation of all emergency lighting fittings and exit signs.
The supply and installation of telephone system.
The supply and installation of data network.
The supply and installation of a CCTV and access control system.
The supply and installation of a roof mounted lightning protection system.
Supply of spare parts
Miscellaneous work as specified.
12 months warranty.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 4/43
“As-installed” drawings and Operating and Maintenance Instruction Manuals.
3.1. WORK BY OTHERS
Other Contractors will provide the following works:
Arranged by Owner
Supply and installation of telephone handsets
Supply and installation of all office computer systems (IT).
Principal Contractor
The building structures and finishes generally.
Provision of concrete plinths as detailed by this Contractor. (The Electrical Installation
Contractor).
Provision of all coreholes and penetrations as detailed by this Contractor.
The provision of access panels in ceilings to details provided by this Contractor.
All sign writing required.
Temporary 380/220 Volt power and lighting for the construction period.
All standard electrically operated sanitary fixtures and fittings.
All sanitary conveniences during construction.
Mechanical Services Contractor (Subcontractor to the Principal Contractor)
Plunbing Contractor (Subcontractor to the Principal Contractor).
Supply and installation of all Hydraulic Services.
Supply and physical installation of electrical operated valves for sanitary fixtures and
fittings.
Fire Services Contractor (Subcontractor to the Principal Contractor).
Supply and installation of all Fire Services.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 5/43
It shall be clearly understood that apart from the work provided by the Owner as above,
the Principal Contractor has overall responsibility for all Engineering Services
irrespective of the division of responsibility referred to above.
The Electrical Installation Tenderer shall ensure that he and the Tenderer for the Principal
Contract works fully understand this clause and the Introduction.
3.2. APPLICABLE STANDARDS
The standards which shall apply throughout this contract are the appropriate Australian
Codes. BS, IEC, Tiêu chuẩn Việt Nam, so some normalization associated Other as in
materials/equipment (Technical Schedule). All of which are applicable in Vietnam under
the Vietnamese Building Code.
3.3. STANDARD OF MATERIALS AND WORKMANSHIP
All electrical equipment shall be new and of first-grade quality as regards design,
manufacture and installation, and shall be complete for satisfactory operation, control
maintenance and safety under all conditions of service.
To a minimum standard, all electrical equipment shall comply with the most recent
appropriate specification of the Standards Association of Australia.
The installation shall be carried out in accordance with this Specification, and any special
requirements of the Supply Authority.
Workmanship shall be of the highest class throughout and all manufacture shall be to
such tolerances as to ensure that similar parts of equipment are interchangeable.
Uniformity of type and manufacture of each individual fitting and accessory shall be
preserved throughout the whole installation.
The Contractor shall supply samples of all electrical equipment he intends to supply and
to use to the Engineer for his approval before the Contractor places bulk orders for such
equipment. Unapproved equipment and materials found on site (installed or otherwise)
may be rejected by the Engineer and as such must be removed from site immediately.
It should be understood that where trade names are mentioned within this Specification or
shown on the associated drawings, it is not intended that the particular brand or type be
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 6/43
considered exclusively. Brand names of fittings have been included solely for the purpose
of conveying the general type and standard of fitting or component desired. Where
Tenderers desire to propose an alternative to the type or brand mentioned within the
Specification, they must clearly set out the alternative offered in their tender form.
It must be clearly understood that all equipment shall be adequately protected against
corrosion. In particular all made up brackets, suspension rods etc etc must be hot dip
galvanized
3.4. POWER SUPPLY
Power supply for the project is feed from Tan Tao Development projects via two L.V.
underground cable ways.
4. EARTHING SYSTEM
The Contractor shall supply and install a complete system of earthing to effectively earth
the main switchboard, distribution boards and all other equipment in the installation.
Earth conductors shall be extended with the submains so that all light and power
distribution switchboards, mechanical services switchboards, conduits, cable trays
trunking plant, equipment, general purpose outlets, metal plates, fluorescent light fittings,
etc., are effectively earthed using a multiple-earthed neutral system.
The main electrical earthing system shall be extended from a series of earthing electrodes
which shall consist of a solid steel core bonded to an outer casing of electrolytic copper.
The rods shall be of minimum length 2.4m and minimum diameter 16mm and be screw
fixed into each other.
The earthing conductors shall be extended via busbar from the earthing electrodes
generally as shown on the drawings.
Earth continuity shall be maintained throughout the installation.
The Main Earthing System as described above shall be one (01) of four (04) separate
earthing systems and it shall have no connections with the separate Lightning Charge
Dissipation Earthing System, nor with the separate telephone earthing System nor with
the separate computer earthing system.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 7/43
The Contractor shall be responsible for obtaining Test Certificates from a recognised
Authority confirming that the earth resistance of the Electrical and the Lightning earthing
systems are satisfactory.
4.1. LOAD BALANCE
It shall be the Contractor's responsibility to ensure that the whole of the electrical
installation is balanced over the three phases of supply.
4.2. VOLTAGE DROP
Notwithstanding anything stated to the contrary or shown on the drawings or included in
the Contractor's quotation, it shall be the Contractor's responsibility to ensure that all
conductors installed are sized in strict accordance with the respective voltage drop rules,
as stated in the relevant Wiring Rules.
Twenty percent (20%) spare capacity shall be allowed on all final sub-circuit cables to
cater for future additions.
5. SWITCHBOARDS
The Contractor shall install all switchboards throughout the project.
In particular the following switchboards shall be provided:
The Main Low Voltage Switchboard.
The various L.V. Distribution Switchboards
The Contractor shall protect these switchboards when they are delivered to site from the
weather and from damage and from theft.
The switchboards shall be installed generally as shown on the drawings and the
Contractor shall ensure that all switchboards will fit through available openings and into
their allocated positions with no need for delays or alternations to building works.
Maintain all specified clearances and protection from weather.
Maintain all specified clearances and protection from weather
5.1. THE MAIN LOW VOLTAGE SWITCHBOARD
5.1.1. General
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 8/43
The switchboard shall be of the indoor, metal enclosure cabinet, Fully Type Tested IEC
439-1 (TTA) or ASTA, air break type suitable for operation in the location as indicated
on the drawings.
The switchboard shall be dead front, totally enclosed, unitised, dustproof, top or back
connected as specified and constructed generally as described below.
Unless the main switchboard is located in a separate switch room arranged for entry by
authorised operators, the switchboard shall be provided with full height lockable door
panels over each module of equipment to prevent unauthorised operation.
5.1.2. SHOP DRAWINGS
Shop drawings shall be provided and shall include plans, elevations, sections, details and
schematic wiring diagram to show makeup of switchboard and distribution boards to full
compliance with Contract Drawings and Specification.
Shop drawings shall be issued to all relevant Consultant/Authorities for approval prior to
manufacture.
5.1.3. MECHANICAL CONSTRUCTION
The Switchboard shall be Top or back connected and shall be constructed to conform to
the requirements as nominated in the Design Requirement section of this Specification.
The switchboard shall be capable of withstanding the thermal and magnetic stresses set
up by a designed fault level. This fault level shall apply to all busbar and busbar
connections up to the line side of all circuit breakers switch fuse units and isolator
switches.
The switchgear shall be of the self supporting type designed to allow maintenance,
inspection and testing to be carried out safely and easily.
The equipment shall be dust, drip and vermin proof, and damp protecting in accordance
with BS2817 or IEC 947-2, and these requirements shall be met whether the equipment is
in the ‘service', ‘test' or ‘isolated' position.
The switchgear shall be provided complete with all Air Circuit Breakers, CFS Units,
Isolators, and other electrical components necessary for the correct operation and
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 9/43
protection of the installation as described in this specification and shown on the
drawings.
The overall height of the switchboard shall not exceed 2200mm above floor level.
Operating handles shall be so located that the highest and lowest points reached by an
operator's hand shall be within the limits of 2000mm and 300mm above floor level. If the
switchboard is installed in a basement switch room adjacent to car parking spaces then all
electrical equipment shall be arranged such that live parts are positioned a minimum of
500mm above floor level.
The switchboard shall be constructed from non-hygroscopic and non-inflammable
materials, and shall be such that eddy current and hysteresis heating in the enclosure is
eliminated.
Doors or lift-off panels as applicable, shall be fitted to the front of cubicles, and unless
otherwise noted.
Switchboards containing contactors, relays or motor control centre type equipment shall
have access doors locked with budget Tee handle operators to prevent unauthorised
access.
Doors shall be constructed of material of the same type and thickness as that used in the
manufacture of the switchboard cabinet, pressed or rolled to give a neat rounded finish.
A stiffening channel of a broad "U" section with returned edges shall be spot welded
down the centre of the door for its entire length. The rims of the door shall have a 12mm
x 6mm thick natural foam rubber seal glued and retained within a metal channel around
the entire perimeter so as to form a dustproof seal when the doors are in a closed position.
Hinges shall be large chromed pintal types so arranged as to permit the door to be lifted
off, and open through a minimum of 120 degrees.
Door handles shall be chrome plated or of non-rusting material, fitted with a barrel lock
and a latch operated rod fastening both top and bottom of the door. All locks shall have a
common key.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 10/43
Where removable access panels are required, they shall be of similar construction to the
doors. Access panels shall be fitted with lifting handles where greater than 0.6m2 and
retaining clips or locating pins at the bottom and chrome plated dome nuts or captive
chrome plated knurled or ‘Phillips’ head set screws with locating cores at the top.
Natural rubber foam gaskets shall be fitted to all access panels.
Insulating panels, mounting brackets and all necessary connections shall be provided to
all spaces for the connection of future equipment.
All exposed welds shall be full filled welds ground and machined smooth and wall weld-
spatter shall be removed. Internal welds may be tag welds provided satisfactory structural
strength is achieved.
The dimensions of the weld shall be such as to provide adequate penetration and strength
to the component concerned to enable it to fulfil its normal service function.
All joints, particularly lap joints and joints to the framework shall be completely and
continuously welded throughout the entire periphery of the section to avoid differential
oxygen concentration between the outside and inside of the joint.
5.1.4. BUSBARS
The busbar configurations shall match incoming conductors and phase rotation shall be
uniform.
Busbars shall be of high conductivity hard drawn copper with continuous current ratings
as detailed. Ratings shall be considered to be nett values after any applicable de-ratings
have been applied relative to the mounting or assembly.
Busbars shall be rated to match the frame rating of the switchgear connected thereto.
Drilled busbars and supports shall be fitted for incoming and outgoing supplies, future
switchgear and CT's where detailed.
Busbar sections for CT mounting shall be readily removable.
All main interconnections and tee-offs in excess of 100 amp rating shall be busbar.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 11/43
All busbars shall be machine bent and formed. Matching faces shall be smoothed by draw
filing or belt sanding before jointing. High tensile steel bolts with washers, torque
tensioned to the manufacturers recommendations, shall be used for all busbar joints.
Other approved proprietary busbar connection systems may be offered for switchboards
up to 15KA fault rating.
Pencils, crayons or dye shall be used when marking out busbars. Scribing of busbars will
not be permitted. Where scribing marks are found on busbars these will be condemned
and shall be replaced.
Busbars shall be bent and formed at radii appropriate to the busbar dimensions so as not
to mark or stress the busbar. All such marked or stressed busbar will be condemned and
shall be replaced.
Busbars assemblies shall be coloured by means of two coats of enamel on etched and
primed surface. The colouring shall be applied in 50mm bands on each busbar section in
each compartment.
Busbars for distribution boards shall be rectangular sections stamped in one piece.
Busbars shall be insulated with phase coloured thermoplastic insulation.
Busbar connections for Moulded Case Circuit Breakers (MCCB) and Miniature Circuit
Breakers (MCB) shall be installed so that either a triple pole or 3 single pole circuit
breakers can be mounted side by side.
Busbar supports shall be rigid and made of an approved insulating material, with
secondary insulation through each support for uninsulated busbars to prevent direct
tracking paths between phases and earth.
Neutral bars for each supply shall extend for the full length of each supply section of the
switchboard and be rated at 100% of the active conductor capacity.
Switchboards in excess of 900mm in length shall have neutral and earth bars extending
for their full length.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 12/43
Each supply section of switchboards shall be fitted with readily accessible and removable
neutral and earth bar links permanently and legibly labelled.
Earth and Neutral bars shall be adjacent to each other in the cabling zones.
General light and power distribution switchboards shall be fitted with screw terminal type
neutral and earth bars. Connecting devices shall consist of tunnel connectors of 4.8mm
diameter with provision for lug or stud connectors for all cables greater than 10mm2.
5.1.5. CABLE ENTRIES
The switchboard shall be designed to accommodate cable entries for incoming and
outgoing services of the type and size shown on the drawings. Adequate space shall be
allowed for the termination and bending of cables within the switchboard compartments
in accordance with the cable manufacturer's recommendations.
The arrangement of cable terminations shall be such as to minimise the bending of cores
and make for easy termination. Cables shall be supplied within the switchboard so that
no stress is imposed on the termination.
All incoming and outgoing cables whether power or control, shall be terminated in the
fixed portions of units. All necessary cable boxes, gland plates, cable glands, cable trays,
cable lugs, conduit entries and accessories necessary for the termination of cables shall be
supplied by the switchboard manufacturer.
Internal connections shall be provided between terminations and equipment. If more than
one power circuit termination exists in a module or cable chamber section, such power
circuits shall be shrouded to prevent accidental contact by maintenance personnel.
5.1.6. PAINTING
Before dispatch from the manufacturer's works, the whole of the exposed metal work of
the equipment specified under these Clauses shall be painted with materials of approved
manufacture, composition and colour.
All steelwork shall be new and free from rust and scale. After degreasing, one coat of
etch primer shall be applied, followed by one coat of compatible undercoat and two coats
of synthetic enamel. All coats shall be stove baked to paint manufacturer's specification.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 13/43
The finished colour of internal and external surfaces shall be the same and is to be as
scheduled in this specification. Equipment panels are to be gloss white.
Any defects which may occur during the maintenance period shall be made good. In
addition, any damage occurring during transit or erection is to be made good to a
standard equal to that of the equipment as originally manufactured.
The paint finish is to be repaired to its original condition using primer, undercoat and top
coats. Overall, the finish is to have a uniform appearance. Spot repainting which allows
colour differences to show will not be permitted.
Protective covers shall be provided for the switchgear during the construction phase and
up to Practical Completion.
Protective covers shall be to the approval of the Consultant and shall be removed after
Practical Completion.
5.1.7. COMBINED FUSE SWITCH UNITS
The fuse switches shall be triple pole with neutral link and the quick make/quick break
design complying fully with AS1775 or IEC 947-3 and IEC 269-1 and arranged to ensure
that operation is independent of the operator's control.
Fuse switch contacts shall be fully shrouded and each unit shall accommodate English
Electric HRC fuse links complying with the requirements of IEC 269 Class "Q1"
category. The fuse links shall be completely disconnected from the line and load contacts
in the "OFF" position.
An interlock shall be provided for each fuse switch to prevent the switch being switched
to the "ON" position with the cover open or the cover opened with the switch in the "ON"
position. The interlock shall be of a form which can be cancelled for maintenance
purposes.
Fuse switch(es) shall be tested and proved to be capable of closing onto and carrying a
through fault. It shall be capable of making and breaking three times full load current at
0.3 power factor.
Each fuse switch shall be capable of being locked in the "OFF" position and padlocking
facilities shall be provided on each CFS unit capable of incorporating a Supply Authority
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 14/43
padlock. The position of the switch indicator shall be operated by the moving contacts
themselves and not be dependent only on the operating handle position.
The switch operating handle shall not project beyond the flush front of the switchboard
when the switch is not being operated. Switch handle(s) shall not be detachable. Fuse
links shall be of the English Electric cartridge type, complying with IEC 269 Class Q1
and ASTA certified for category of duty 550 AC 80 and shall be supplied to the rating
specified on the Single Line Diagram.
5.1.8. PROTECTION RELAYS
Protection Relays shall be provided as shown on the drawings. The relays shall be
designed to disconnect faulty circuits with speed and certainty, and without interference
to healthy circuits. In addition they shall be designed to prevent incorrect operation of
switchgear as a result of transient or spurious conditions which may arise during faults
occurring in the Local Power Company's system.
Protection relays associated with a single circuit may be mounted on the switchboard
panels provided that the relays are mounted in such a manner so that mal-operation due to
vibration or other causes is impossible. Each relay shall be individually labelled as
described in latter clauses.
Protection relays shall comply with AS 1023 Part 2, BS 142 or IEC 947-2 and shall
operate from 5 amp secondary current transformers.
Protection relays shall be of the draw-out type contained in dust proof flush mounted
metal cases arranged so that on opening the cases it shall be impossible for any dust
which may have collected in or on the cases to fall on the relayed mechanism. All cases
shall be earthed.
All relays which are connected into trip circuits shall be provided with approved flag
indicators which, wherever possible, shall be of the mechanically operated type.
Indicators shall also be provided on additional relay elements in order to identify the
phase. Indicators shall be mechanically reset from outside the case.
All relays shall be provided with at least two separate pairs of independent contacts.
Relays required to operate with a time delay device shall not be of the dash-pot type.
Relay contacts shall be of silver, platinum or other approved material and shall be
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 15/43
capable of repeated operation without deterioration.
All relays shall be capable of making and breaking the maximum current which can
occur in the circuit they control. Relays shall not be affected by vibration or stray
magnetic fields.
Optimum plug settings shall be established on site during first commissioning in
consultation with the Local Power Company.
5.1.9. INDICATING INSTRUMENTS
Indicating instrument(s) and current transformer(s) shall be supplied and installed when
required, and shall be incorporated on the main switchboard.
Ammeter(s) shall be "M" and "W" type EQ144R or equivalent moving iron type
instrument(s). Over scaling 2 x rated current.
Maximum demand ammeter(s) shall be "M" and "W" type MEQ144, or equivalent and
shall have combined in the one instrument, 2 separate movements. One shall provide a
reading on a separate scale in amperes (rms) maximum demand (15 minute setting time)
with an external resetting knob and shall have a bi-metallic movement. The other
movement shall be a moving iron ammeter with a separate scale in amperes (rms).
Voltmeter shall be calibrated 0-500 Volts with scale background coloured RED between
0-400 Volts, GREEN between 400-440 Volts, RED above 440 Volts.
All instantaneous value indicating instruments shall be of the flush square pattern type
with quadrant scales (Length 140mm). Rated current calibration shall be shown.
Instrument transfer switches (ammeter and voltmeter) shall be installed as required.
Kilowatt hour meters shall comply fully with AS1284 or IEC Standards. Meters shall be
flush mounted, with black bezels and digital type readouts.
5.1.10. CURRENT TRANSFORMERS
Current transformers shall comply fully with the requirements of AS1675 or IEC 60044,
and unless otherwise indicated, shall have Class 2.0 accuracy and be of the through or bar
type pattern. They shall, with a 5 amp secondary winding, deliver a rated output of
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 16/43
15VA with a rated burden of 0.6 ohm. Ratios shall be as shown on the Single Line
Diagram.
All current transformers shall be held in place with busbar clamps, adequately separated
so that terminals are readily accessible. Busbars shall be so arranged that current
transformers may be easily removed and replaced. Current transformer test links and
potential fuses shall be provided and located for switchboard front access.
The secondary windings of each set of current trans- formers shall be earthed through a
link at one point only. The polarity of windings shall be marked with approved labels.
5.1.11. FUSES
All fuse fittings shall complying with IEC 269, Class Q1 and ASTA certified for category
of duty 550 AC 80. Note that Classes R and Q2 are not acceptable. Each fuse shall be
fitted internally with a marker indicating ampere rating of the fuse cartridge.
5.1.12. MINIATURE AND MOULDED CASE CIRCUIT BREAKERS
Miniature and Moulded Case Circuit Breakers shall be of approved manufacture and
shall be constructed and rates in accordance with AS 3111 or IEC 60898 or IEC 947-2
They shall be provided with combined inverse thermal and instantaneous magnetic
overload trip features, shall have quick make/break trip free operating mechanisms and
shall be fitted with operating toggles which provide "centre trip", "on" and "off" position.
Circuit breakers rated above 150 amps shall incorporate interchangeable trip units and
shall be connected so that their fixed contacts are connected to the line side and the
moving contacts to the load side of the breaker.
Where fault levels exceed that of the relevant circuit breaker, HRC current limiting fuses
shall be used to provide back up protection in accordance with the manufacturer's
recommendation.
5.1.13. LABELLING
All switchgear, apparatus, and controls shall be labelled in accordance with the Local
Power Company's requirements and in accordance with this Specification.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 17/43
Unless otherwise specified, all labels shall be traffolyte engraved black lettering on
white. The size of lettering and the wording of labels will be subject to approval. Label
schedules shall be submitted prior to manufacture.
The switchboard shall be fitted with a main label mount in a prominent position.
Labels shall be secured with brass screws or steel screws which have been rust proofed in
an approved manner. Labels shall be secured in such a manner that they can be easily
replaced.
Labels shall designate circuit number and equipment function.
With the exception of labels conforming to those below, labels shall only be fastened to
removable panels or doors which are mechanically non-interchangeable. Labels shall be
fitted to the front and rear of all units and panels.
Labels engraved white on red in 12mm high letters and with the following wording shall
be fastened to all covers or panels giving access to bus chambers
`Danger - Live Bars Behind'
Terminal strips shall be labelled to identify the circuit number, phase connection,
terminal number and function - e.g. control, indication, protection, etc.
Control relays, timers, fuses and other items of switchgear located on common panels
shall be clearly labelled to identify circuit number, function and rating. Additional
information including terminated cable size/type, fault level, fuse rating, circuit breaker
rating shall be provided on each switch/isolator label.
5.1.14. ZONING
The main switchboard shall be physically divided and clearly zoned "Essential" and "Non
Essential" as shown on the drawings.
5.1.15. AUXILIARY RELAYS
Auxiliary relays shall comply fully with the requirements of AS1431 and where
practicable, shall be of the plug in type and have silver to silver contacts with an inherent
self cleaning action.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 18/43
Auxiliary relays shall close satisfactorily at 80% nominal Volts and hold in satisfactorily
at 65% nominal Volts.
Auxiliary relays shall have a minimum of 6 contacts rated at 5 amps minimum for an
inductive load. However, contacts shall be capable of carrying and breaking without
damage, the inrush and operating currents of circuits they are switching. The contact
arrangement must be easily alterable.
5.1.16. TIMING RELAYS AND TIMERS
Where possible, timing relays are to be plug-in type and of the same manufacture as
auxiliary relays. Timing relays shall operate under the same conditions as auxiliary
relays and shall have contacts rated at a minimum of 5 amps inductive load. The timing
device shall not deteriorate with age.
5.1.17. TIME CLOCKS
Time clocks shall be 365 day 24 hour electronic programmable type with a minimum of
four independently controllable output contacts.
5.1.18. CONTROL SWITCHES
Control switches shall be of the rotary pattern suitable for panel mounting and shall be
lockable in positions detailed on the drawings.
Control switches shall be double break type and rated at a minimum of 10 amps
inductive. The contact arrangement shall suit the application of the switch.
5.1.19. PUSHBUTTONS
Pushbuttons shall be of the oil tight pattern, heavy duty unless otherwise specified, and
rated at a minimum of 5 amps inductive. Pushbuttons shall consist of an actuating button
assembly coupled to an interchangeable contact assembly of sufficient poles to suit the
application.
Colour codes shall be :
"Close" or "On" –Green
"Open" of "Off" – Red
"Reset" and Pushbutton bezels shall be Black
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 19/43
5.1.20. INDICATING LIGHTS
Indicating lights shall be of the domed glass or plastic lens type employing MES, SES or
SBC connected lamps at 6 watts. The indication must be clearly visible from the sides or
front at a distance of 15 metres in a normally illuminated room. Indicating lights shall
have black bezels.
The bodies of indicating lights shall be ventilated to ensure efficient heat dissipation.
Connection to lights shall be by screw or clamp terminals; soldered terminations are
unacceptable.
Colour codes shall be:
- De-energised – Green
- Energised – Red
- Abnormal condition – Amber
- Other functions - Blue or White
5.2. DISTRIBUTION BOARDS
5.2.1. GENERAL
Supply and install all floor distribution boards indicated on the Single Line Diagram in
accordance with this part of the Specification.
All distribution boards shall be surface or recessed mounted, as indicated on the
drawings, and of the totally enclosed "dead front" type for indoor use, of dust protected
construction, being provided with doors to cover all circuit breakers, fuses, flush isolating
switches, push buttons and control switches. The distribution boards shall be fitted with
amply proportioned sections extending to the floor and to the ceiling to act as cable ducts
for incoming and outgoing cables.
Distribution boards shall be fabricated from a minimum 1.6mm sheet steel using folded
sections and/or angle iron bracing where necessary for stiffeners and all joints shall have
continuous seam welds.
Doors shall be provided on all distribution boards. They shall be mounted on concealed
type non-ferrous hinges and fitted with snap catch mechanism and lock. The doors shall
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 20/43
be fitted with neoprene sheathed sponge rubber dust proofing gaskets. The gaskets shall
be retained within a metal channel section spot welded to the door to prevent lateral
movement of the gasket.
The distribution boards shall be capable of with standing the thermal and magnetic
stresses set up by a fault consistent with the fault rating on the main switchboard.
DIN Rail type distribution boards are not acceptable unless specifically approved by the
Consultant.
Main busbars for both fuse distribution boards and Moulded Case Circuit Breakers
distribution boards shall be copper busbar with milled rounded edges of the appropriate
size for the maximum demand current for the switchboard but in no case shall such
busbars be less than 12mm x 3mm or equivalent cross sectional area. Where the cross
sectional area is reduced by drilling to take brass or copper tongues or fixings for take off
lugs, the tongues or lugs shall be brazed or satisfactorily fastened in position so as to
maintain the conductivity of the busbar. Neutral bars shall be rated at 100% of the active
conductor capacity.
Fuses shall be connected to the supply by copper busbar, which has been fitted with brass
or copper tongues, minimum size 3mm diameter, brazed to the busbar.
Moulded Case Circuit Breakers shall be connected to the supply by copper busbar with
cross connected take off lugs of minimum size 12mm x 1.6mm. Take off lugs shall be
brazed or suitably pressure riveted to the main busbar.
The whole busbar, including tongues and take off lugs shall be insulated with 660 Volts
Nylex sleeving or similar thermo plastic materials which shall be of the appropriate phase
colour.
Supply and fit in all distribution boards, neutral and earth bars containing as many ways
as the maximum possible number of circuits that can be accommodated within the
enclosure both initially and in the future. Construct from copper or brass of rectangular
or square section. Provide approved cable lugs, connected to the bars by hexagon headed,
brass bolts and lock-washers for all incoming or outgoing cables of size 6mm2
or larger.
Provide tunnel type holes for the connection of smaller cables and provide two brass grub
screws per tunnel to retain conductors.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 21/43
The main switch or main isolator on a distribution board shall be fitted in the top or
bottom centre of the cabinet. Provision shall be made for the future fitting of a time
switch and/or contactor to both fuse type and miniature circuit breaker boards.
5.2.2. CIRCUIT BREAKER TYPE DISTRIBUTION BOARDS
Circuit breakers shall be fitted to the take off lugs by stripping the PVC or plastic only as
far as is necessary to make connection to the circuit breaker. Spare take off lugs shall be
left coated.
The distribution board enclosure shall be fitted with approved type escutcheons hinged to
the main cabinet. Escutcheons shall be constructed so as to be rigid with angle
reinforcing if necessary. Edges shall be lipped, returned or welded to an angle frame.
Alternatively factory produced escutcheons may have edges which are machine cut to
give a neat edge, chamfered so as to be free from burrs or sharp corners.
Neatly fitting cut-outs for the breaker toggles must be provided and the escutcheons shall
be securely fixed to the enclosures free side by either chrome plated capture screws or
suitable spring clips.
Circuit breakers shall be mounted on a purpose made chassis, such that removal of
breakers does not disturb connections to remaining circuit breakers.
Spare space shall be provided for the future accommodation of circuit breakers as
indicated on the drawings in each section and the panels shall be fitted with the necessary
studs and busbar connections to facilitate fitting the additional circuit breakers at a later
date without disturbance to the existing installation. Cut-outs in the escutcheons for
future circuit breaker toggles shall be fitted with neat cover plates which are easily
removed when the additional breakers are fitted.
The whole switchboard shall be arranged so that all conductors immediately accessible
when the escutcheon is opened are insulated. All connection to busbars or switchgear
shall be either approved sheathed or shall be made behind removable cover plates.
Busbars, circuit breakers, earth bar and neutral link shall be mounted behind the
escutcheon plate.
Circuit breakers shall be moulded case constructed in accordance with AS 3111 or IEC
60947, of uniform type and manufacture, connected correctly at line and load terminals.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 22/43
Dimensions shall be such that single pole breakers may be readily interchanged with
multi-pole types.
Circuit breakers shall be provided with combined inverse thermal and instantaneous
magnetic overload trip features, shall have quick make/break trip free operating
mechanisms and shall be fitted with operating toggles which provide "centre trip", "on"
and "off" positions.
Circuit breakers rated above 150 amps. shall incorporate interchangeable trip units and
shall be connected so that their fixed contacts are connected to the line side and the
moving contacts to the load side of the breaker.
Where fault levels exceed that of the relevant circuit breaker, HRC current limiting fuses
shall be used to provide back up protection in accordance with the manufacturer's
recommendation.
Circuit breakers shall be of the rating as shown on the Single Line Diagram.
5.2.3. DISTRIBUTIONBOARD LABELLING
All switchgear, apparatus, and controls shall be labelled in accordance with the Local
Power Company requirements and in accordance with this Specification.
Provide and affix to the door or escutcheon plate, of each distribution board, a white
Traffolyte label engraved with black lettering to denote details of supply, service, etc.
Submit proposed details of engraving for approval.
Labels shall be secured with brass screws or steel screws which have been rust proofed in
an approved manner. Labels shall be secured in such a manner that they can be easily
replaced.
Provide a typewritten circuit schedule and mount behind Perspex or glass. Indicate the
description of load, and circuit breaker rating, conduit and cable sizes. Each circuit
breaker shall be identified with its circuit designation by an adjacent approved label.
5.2.4. PAINTING AND FINISHING
Before dispatch from the manufacturer's works, the whole of the exposed metal work of
the equipment specified under these Clauses shall be painted with materials of approved
manufacture, composition and colour.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 23/43
All steelwork shall be new and free from rust and scale. After degreasing, one coat of
etch primer shall be applied, followed by one coat of compatible undercoat and two coats
of synthetic enamel. All coats shall be stove baked to paint manufacturer's specification.
The finished colour of internal and external surfaces shall be the same and is to be as
scheduled in this specification. Equipment panels are to be gloss white.
All defects which may occur during the maintenance period shall be made good. In
addition, any damage occurring during transit or erection is to be made good to a
standard equal to that of the equipment as originally manufactured.
The paint finish is to be repaired to its original condition using primer, undercoat and top
coats. Overall, the finish is to have a uniform appearance. Spot repainting which allows
colour differences to show will not be permitted.
Protective covers shall be provided for the switchgear during the construction phase and
up to Practical completion.
Protective covers shall be to the approval of the Consultant and shall be removed after
Practical Completion.
5.2.5. ZONING
All distribution boards shall be physically divided and clearly zoned "Essential" and
"Non Essential" as shown on the drawings.
5.2.6. AUXILIARY RELAYS
Auxiliary relays shall comply fully with the requirements of AS1431 or IEC 947-5-2 and
where practicable, shall be of the plug in type and have silver to silver contacts with an
inherent self cleaning action.
Auxiliary relays shall close satisfactorily at 80% nominal Volts and hold in satisfactorily
at 65% nominal Volts.
Auxiliary relays shall have a minimum of 6 contacts rated at 5 amps minimum for an
inductive load. However, contacts shall be capable of carrying and breaking without
damage, the inrush and operating currents of circuits they are switching. The contact
arrangement must be easily alterable.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 24/43
5.2.7. TIMING RELAYS AND TIMERS
Where possible, timing relays are to be plug-in type and of the same manufacture as
auxiliary relays. Timing relays shall operate under the same conditions as auxiliary relays
and shall have contacts rated at a minimum of 5 amps inductive load. The timing device
shall not deteriorate with age.
5.2.8. TIME CLOCKS
Time clocks shall be 365 day 24 hour electronic programmable type with a minimum of
four independently controllable output contacts.
5.3. MAINS AND SUBMAINS
5.3.1. General
This Contractor shall supply, install and connect all mains and submains cables of the
type and size indicated on the single line diagram, and other drawings, complete with all
accessories, ducts, conduits, trays, brackets, etc., necessary for their proper installation,
mechanical protection, support terminations, etc...
Each submain shall be provided with a stamped copper tag at the origin, indicating the
number and size of the cables. The cables indicated on the single line diagram have been
sized, assuming spacing of circuit will be in accordance with AS 3008. Therefore, no de-
rating has been allowed.
Should tenderers prefer to provide alternative spacing, any increase in cable sizes
necessary due to de-rating shall be deemed to be included in their tender price.
All submains shall be complete with an earth conductor as required.
All mains and submain cables shall be V75 grade PVC-insulated PVC-sheathed, copper
conductors or fire rated cables, as shown on the single line diagrams. No aluminium
conductors shall be installed
Pipe sizes shall be such that cables occupy less than 60% of the pipe internal cross-
sectional area.
The Contractor shall size the pipes and radius of bends to ensure that all cables may be
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 25/43
pulled through easily.
All mains and submains which are to terminate onto switchboards from above shall be
supported on overhead cable tray. All submain terminations (both ends) are included in
this contract.
Submains shall generally be installed on cable ladders, cable tray within switchrooms and
plant rooms, and within vertical risers and internal ceiling spaces, etc.
All groups of single core cables comprising three-phase circuits shall be run in trefoil
formation throughout the entirely of their route lengths.
Where submains are carried on a cable ladder or tray, this Contractor shall supply and
install all necessary hangers, etc., for cable tray, and these will need to be of sufficient
length to enable the cable tray to clear beams, etc., without any unnecessary changes of
direction.
Mechanical protection shall be provided when and as required, however, this protection
must be of a form which does not de-rate the cable.
Where cables rise vertically, the Contractor shall support these by cable tray with cable
cleats or clamps, the cable tray being securely fixed to holding brackets as specified.
Generally, all cable runs shall be completed in the one length of cable. If shall be the sole
responsibility of the Contractor to establish correctly the lengths of cable required to
successfully complete this work.
Any joints or additional cable required to complete the work, due to the Contractor’s
failure to establish these lengths at the time of tendering, will be the Contractor’s
financial responsibility, and the work shall be completed at the Contractor’s expense.
Unavoidable joints in PVC-insulated cable shall be “Scotchcast” cast-resin type to the
manufacturer’s recommendation.
Termination of cables shall be in strict accordance with the cable manufacturer’s
recommendations and procedures. The supply and fitting of all termination lugs and cable
glands and materials are in this contract.
Sub circuit cables which leave distribution boards either from the top or from the bottom
shall:
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 26/43
Be circular PVC, PVC cables each fitted with cable glands into a gland plate at the
switchboard.
Be single core PVC insulated cores enclosed in screwed galvanize conduit.
Bundles of single insulated cables enclosed in vertical ducts with clip on or screwed on
covers will not be acceptable.
All screw terminals shall be of an approved type having positive clamping arrangements.
5.3.2. Special Submains
The Contractor shall note the special 2HR fire rated submains which leave the Main
L.V.Switchboard and he must ensure that particular care is exercised during their
installation.
As shown on the single line diagram certain submains which leave the Main
L.V.Switchboard are not controlled by Main Switches.
The method of installing fire rated cables is important and must be to code requirements
and to the Engineers’ satisfaction.
5.3.3. Discrimination Study
This Contractor, the Electrical installation Contractor shall particularly note that a full
discrimination study on the overall distribution system has been undertaken by the L.V.
Switchboard Manufacturer.
As the installation progresses certain changes and additions to the distribution system
may be made.
This Contractor shall ensure that the designed discrimination system does not become
compromised.
This Contractor shall record each and every change to the switchboards and check that
the designed system is still functional.
Before Practical Completion this Contractor shall advise the Switchboard Manufacturer
of all changes to the switchboards and the switchboard manufacture shall adjust his “As
Delivered” drawings to reflect the “As Installed” conditions and insert the new drawings
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 27/43
into the switchboard O&M Manuals.
5.4. CONDUITS
Conduits shall be minimum 20 mm diameter first-grade galvanised steel where liable to
damage, or heavy duty PVC type complying with AS 2053, elsewhere.
Supply and install all conduits necessary to enclose TPI wiring using all sizes to permit
the easy drawing-in or removing of any one conductor while all others are in place.
Allow for withdrawing and replacing any conductors that may be selected on site to
ensure that the provisions of this foregoing clause have been complied with. Use no
conduit smaller than 25 mm in all slabs.
Rigid or corrugated PVC conduit and fittings or ductwork shall not be used in the
following locations:
Where subject to vibration or the need to be flexible.
Where exposed to mechanical damage, sunlight, or daylight.
Where subject to ambient or contact temperatures exceeding 60 C.
Where exposed to weather, in damp situations.
Where subject to normal industrial abuse which would, in the Engineers opinion, be
likely to cause damage to the installation (Mechanical plant rooms, generator room,
pump rooms etc.)
Within all ceiling spaces which are used as return air plenums.
In those locations as above, galvanized steel screwed conduit shall be used (Exposed
threads shall be aluminium lacquer painted) or PVC covered, plated steel flexible
conduits as in appropriate.
All conduits shall be concealed by running in slabs, ceiling spaces and wall cavities, by
chasing into rendered walls, etc., except in plant rooms, switch rooms and similar
locations. When exposed to view, install conduits parallel to building members and pack
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 28/43
out from walls or ceiling with spacers placed under each saddle. Single-leg saddles will
not be permitted.
Where conduits cannot be concealed they shall be steel and they shall be painted in with
the wall colour.
Conduits and wiring runs exposed in view shall be neatly set and be vertical, horizontal
and parallel to walls as applicable.
Saddle conduits at a maximum of 1200 mm centres to provide a rigid installation
throughout.
Install conduit and accessories complete with draw wires, and pull through a swab before
wiring any section.
All chasing for the concealing of conduits shall be carried out by this Contractor. Chasing
of walls shall be carried out using a power-operated abrasive disc. Patching and rendering
of chases will be undertaken by this Contractor.
Cut all conduit ends square and remove all burrs, rough edges, etc., so that conduits are
completely clean inside. Treat all threads in conduits with aluminium paint or similar, to
prevent corrosion at the joints and to preserve electrical continuity.
Burrs found inside any steel conduits will be reason for the Engineer to condemn the
complete conduit installation in the area concerned.
Inspection elbows are NOT acceptable as draw-in-boxes. Outlet boxes shall be of the
deep type placed so that the outlet face is flush with the finished surface of the concrete,
render or face of dry work. Conduits shall be arranged so that they drain naturally to each
box.
Pressed metal boxes shall be used for flush wall-mounting light switches, general purpose
outlets, telephone outlets, etc,. Boxes shall have adjustable threaded fixing devices to
permit flush-mounting of the cover plate. Flush wall boxes shall be provided for all
switches and outlets, and are to be mounted horizontally unless stated otherwise.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 29/43
All wall boxes located in masonry walls shall be grouted securely in position by this
Contractor. All wall boxes located in steel frame cavity walls shall be secured to the
frames by this Contractor.
All bolts, washers, nuts, self-tapping screws, etc., shall be galvanized.
Use flexible conduit only where it is impracticable to carry fixed conduit into equipment,
or as may be directed on site.
Flexible conduit, either metallic or PVC, shall be used to connect all permanently-
connected appliances and motors. Screwed conduit glands shall be used both ends.
Where exposed to the weather flexible conduit shall be steel with an integral PVC
covering - use only approved screwed fitting glands to terminate flexible conduit.
Flexible conduit glands which use a grub screw to tighten against the links of the flexible
conduit shall not be approved.
Provide draw-in boxes at intervals of 30 m maximum to facilitate the drawing-in of
conductors on long runs, and use sets in lieu of bends or elbows.
Conduits installed for future wiring and services shall be provided with 1.2 mm
galvanized steel draw wire and a stamped metal tag indicating the service and area
supplied. Conduits shall be swabbed out to remove all moisture before floor or wall
finishes are applied. Conduits shall be fitted with a cap and sealed to prevent moisture or
obstructions entering; most particularly during concrete placement.
Fixing of equipment to in-situ poured concrete walls and slabs and in brick walls shall be
by means of stainless steel screws or bolts screwed into masonry anchors of the
expanding type.
Fixing to driven timber plugs is not acceptable.
Fixings to timber framing shall be means of brass or stainless steel wood screws. Details
of the type and method of fixing shall be approved before commencing any installation.
Where PVC conduit is embedded in concrete which is screeded or vibrated after pouring,
or where conduits may be subjected to heavy traffic prior to pour, the Contractor shall, in
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 30/43
both cases, provide constant supervision by a responsible person to ensure that conduit
runs are not damaged.
The Contractor shall be responsible for such damage and shall make good at his own cost.
All conduits entering junction boxes, etc., shall be tied 300 mm away from the box.
Ensure at least 300 mm straight run of conduit into each box.
Conduits shall be positioned so that they have a definite sweep or curve between boxes.
Where conduit is damaged or bumped during installation, the affected section shall be cut
out and a new piece installed.
All conduits in slab shall be installed above the bottom layer of reinforcement and
securely tied in place, boxes firmly fixed to form ply, and be separated from other
conduits in slab by a distance equal to the diameter of the conduit.
Where conduits within the slab pass a construction joint, proprietary brand flexible
conduit couplings shall be provided to the satisfaction of the Engineer.
Conduits shall be run at all times in a manner which will not necessitate penetration of the
damp courses or permit the entry of moisture to any portion of the building.
Where conduits are installed in topping above precast structural concrete beams they shall
be positioned so as to ensure a minimum of 10mm topping concrete cover is provided
over the top of the conduits. In some cases this may necessitate the provision of a number
of smaller conduits rather than one large conduit.
Conduits which are installed within hard plaster or rendered wall finishes shall be
securely fixed to prevent movement or vibration, and shall have a minimum cover of 10
mm of plaster and render.
Conduits shall be chased into walls to ensure that this minimum cover is obtained. In no
case, however, will chasing of single brick walls be permitted. The Contractor shall
arrange for the bricklayer to provide suitable chases during erection of brickwork. Oval
conduit may be used for switch drops. No conduit fittings other than wall boxes for
switches and general purpose power outlets, couplings and junction boxes, shall be
concealed in plaster or cement render.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 31/43
Materials embedded in plaster shall be non-rusting. Conduits run in external brick cavity
walls shall be vertical only, and shall be secured to the inner skin. Horizontal conduits
will not be permitted. Underground conduits shall be non-metallic, complying with AS
2053 unless noted otherwise.
This Contractor shall supply and install spare conduits for possible future use in all
internal columns on every floor.
These conduits shall all be 25 and turn out of the columns above ceiling level. They shall
be positioned on all four sides of every column and finish in a wall box 300 AFFL. After
the principal contractor has rendered and painted each column this Contractor shall fit a
blank white escutcheon plate to each box. (4 per column).
Upon completion of the installation, this Contractor shall supply three (03) sets of conduit
layout drawings of all areas where conduits, junction boxes, etc., are concealed
underground, in floor slabs, walls and ceilings.
This Contractor shall particularly note how all conduits shall pass through external walls
which are underground.
No incoming or outgoing underground conduit which passes through the building
perimeter wall (in the basement) shall start or finish within the building or terminate
below a level of 200 above finished ground floor level. Refer details of conduit
penetrations through perimeter walls on drawings.
5.5. CABLE TRAY AND CABLE LADDER
Cable tray and cable ladder shall be installed in concealed spaces such as plant rooms,
electrical cupboards and above ceilings.
All cable trays shall be made of hot-dip galvanised finish, and shall be machine press-
formed with both edges returned for stiffening. Trays shall be formed in 2.5m lengths and
shall be of not less than 1.5mm with electric cable tray and 1,8mm cable ledder.
All cable trays shall be complete with galvanised perforated fish plates, bends and fixings,
all to the manufacturer’s recommendations. Tray shall be free from burrs and sharp edges
which can damage cable sheathing and insulation. Bolts (gutter bolts) used to join
sections of tray together shall have their (shallow) heads inside the tray.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 32/43
Each section of cable tray or cable ladder shall be effectively earth bonded to each other
via a short section of earth cable.
Each tray shall be secured to the structure to approval, and shall be installed with
sufficient clearance from the structure, pipes, ducts, etc. Cable tray support shall be
evenly spaced to ensure that the tray is true and straight.
Spacing of supports shall be within the manufacturer’s recommendations for the loading
concerned, and not less than two (02) supports shall be provided per length of tray.
5.6. WIRING AND CABLES
The whole of the installation shall be wired from the main L.V. Switchboard and the
distribution boards as shown on the single line diagram.
Except where otherwise specified, all wiring shall be stranded copper conductor
insulation type V-75 PVC-enclosed in rigid PVC or steel conduits. Circular section TPS
cable shall be installed on cable tray and cable ladder where the cable is free from
possible mechanical damage.
Conductors run within light fittings shall be type V-105 PVC-insulated.
All wiring shall be concealed wherever possible by locating in ceiling spaces, wall
cavities, chased in rendered walls, cast in floor slabs, etc., Wiring in plant room and
similar locations may be surface-mounted in accordance with this Specification.
Cables shall not be directly embedded, but shall be capable of withdraw at any time, by
the provision of conduits, sleeves or clear wiring ways.
Cables with heat-resisting insulation shall be used as final wiring in connections, to all
incandescent lights in recessed and enclosed fittings, and to any other situation required
by the Wiring Rules.
All conduit and wiring shall be installed using the loop-in system, and the use of conduit
fittings other than junction boxes for light outlets, wall boxes, bends and couplings, will
not be permitted. Conductors shall only be drawn into conduit at light outlets, power
outlets positions, approved draw-in box positions and switchboards.
Install all wiring without damage to insulation and replace, without cost, any in which
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 33/43
damage occurs.
The minimum size of sub-circuit conductors shall be 2.5 mm2 for lighting, and 2.5 mm
2
for general purpose power. Cables shall be sized to carry the current rating of the circuit
breaker, and to ensure that voltage drop does not exceed 5% from the point of connection
to the furthest outlet during normal conditions of operation.
Prepare all ends of insulation for termination without cutting strands, and fix in lugs or
approved clips when such are necessary to prevent spread of strands when terminals are
tightened.
Where TPI cabling is used, the following colour code shall be used.
Phase Cables - RED, WHITE and BLUE
Neutral Cables - BLACK
Covered Earth - YELLOW/GREEN exclusively
TPS cables, type V-75, PVC-insulated and sheathed 650/1000 V grade shall generally be
used for mains and submains.
Except in plant rooms TPS cables shall not be used in any area where they would
normally be visible. Their use shall be confined to wall cavities, ceiling spaces and ducts.
In false ceiling areas, wiring may be TPS, suitably installed, supported on cable tray or
cable ladder concealed behind removable ceiling tiles, clipped to timber batterns or
catenary wires fixed directly to underside of roof purlins or ceiling slab as applicable.
Under no circumstances shall cables be laid directly on ceiling tiles or fixed ceiling
panels.
It is preferred that wiring to within-ceiling equipment be enclosed in conduit embedded in
the concrete slab above.
All runs shall be neat and orderly.
The Contractor shall ensure that where thermoplastic sheathed cables (including fire rated
cables) are run within false ceilings, the routes chosen do not interfere with any other
service or roof members or ceiling suspensions, ceiling penetrations, etc..
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 34/43
The above clause refers to signal cables, P.A Cables, security cables, access control cables
etc etc as well as Light & Power cables. As mentioned above it is preferred that all cables
be enclosed in conduits embedded in the concrete slab above.
It shall be particularly noted that cables associated with life safety equipment shall be fire
rated cables and they shall be installed in a manner which guarantees their integrity during
a fire.
Where TPS cables pass through penetrations in steel structural members, the holes shall
be bushed.
Sheathing shall be continuous and shall extend into junction boxes and fittings. Sheathing
which has been cut or broken in any way will be rejected and shall be replaced by the
Contractor.
Where TPS cables are run in conduit, stripping of sheathing shall not be permitted.
Earth wires when run with single core TPS cables shall be stranded copper conductors,
size in accordance with SAA Wirings Rules.
All TPS cables shall be run on trays or clipped to battens in accordance with the
requirements of the SAA Wiring Rules. All TPS cables installed on cable tray shall be
clipped to the tray in an approved manner.
Multicore and single core TPS cables shall be of circular section and fitted with approved
screwed glands where they enter or leave switchboards or equipment terminal boxes.
Single insulated cables shall not exit switchboards in ducts.
Poorly installed above ceiling wiring inspected by the Engineer will be cause for complete
condemnation of all above ceiling work and the Contractor shall remove and replace all
wiring to the specified requirements and to the Engineers’ satisfaction.
The Contractor shall note that single core, single insulated cables shall not exit the
Distribution Boards if they are not enclosed in conduit and the conduit connections are
bolted into the top and bottom gland plates of the respective distribution boards.
Circular multi core cables (PVC.PVC insulated) may exit the distribution boards without
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 35/43
further protection provided they exit the boards via approved screwed glands.
5.7. LIGHTING SWITCHES
Light switches shall generally be of a minimum 15 A capacity, single pole toggle action
mechanism, and flush-mounted into a pressed steel wall box under a flush plate to
selected finish, or of the architrave style.
The switches shall be of an approved miniature type and suitable for multi-gang
mounting, and shall incorporate separate operating mechanism.
Flush switches shall be mounted with switch mechanism operating in the vertical plane.
Flush plates shall be of an impact-resistant type.
The lighting toggles shall be DOWN when in the “ON” position.
All lighting switch toggles shall have a red dot on their operator visible when the circuit is
“ON”.
Unless specified otherwise, switches shall generally be mounted at 1400 mm above
finished floor level or follow interior consultant rules, due consideration being given to
the height of dadoes, tiling, painting, etc. Switches shall not be fitted across the junction
of different wall finishes. The precise position of all switches shall be subject to approval
on site.
Where switches are shown as located on, or adjacent to, door-ways, the Contractor shall
ascertain the correct swing of doors, and place switches on the lock side of door frames,
irrespective of the position shown on the drawings.
All lighting switches and their flush plates shall be white or follow interior consultant
rules.
Where mounted in plant rooms, switches shall be of the weather-proof, pressure diecast
aluminium metal clad type.
Where shown on the plans or specified herein, provide two-way and intermediate
switches. Switches external to the buildings shall be weather proof. Switches for
fluorescent and discharge lights shall be rated at twice the connected load.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 36/43
5.8. FLUSH PLATES
All flush plates for switches, general purpose power or special outlets shall generally be
of the impact-resistant type, unless otherwise specified herein.
Flush plates shall be white or follow interior consultant rules.
Where two or more switches connected to the same phase are grouped together, they shall
be fitted into a common flush plate. Switches connected to different phases shall not be
grouped together.
Where switches, plug socket and switch and the like are mounted together, they shall be
fitted behind a common flush cover plate.
Certain flush plates shall be machine engraved and filled with black or red paint.
Details will be as directed on site.
5.9. GENERAL PURPOSE POWER OUTLETS (GPOS) AND SPECIAL
PURPOSE POWER OUTLETS
Generally, power outlets shall all be switched and be flush-mounted and fitted with flush
plates as specified above. Wall boxes shall be used, and these shall be set into rendered
brickwork or blockwork without damage to the wall finish.
The Contractor shall supply and install power outlets generally as shown on the drawings.
In some instances, the exact positioning of outlets shall be dependent upon the final
location of furniture and fittings, and hence, the Contractor shall be required to closely
liaise with the principal Contractor before final installation.
The drawings show the circuiting of power outlets, and this shall not be varied without
written approval or as amended on revised issu es of the drawings.
General purpose outlets shall be PVC high-impact flush type with 10 A min. switch
mechanism. Special purpose outlets shall have mechanisms rated as indicated on the
drawings, and where applicable, shall also be flush-mounted high-impact type.
Generally, GPOs shall be mounted at 300 mm above floor level in offices and corridors,
and 150 mm above benches, etc., or as shown in the drawings.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 37/43
GPOs installed near wets areas shall be protected by an earth leakage circuit breaker in
the distribution board or by an integral ELCB outlet.
GPOs and their flush plates shall be coloured red where they provide a UPS supply.
Provision shall be made for GPOs to be extended to island work partitions under a future
“fit-out” contract.
5.10. PERMANENTLYCONNECTED EQUIPMENT AND APPLIANCES
This Contractor, the Electrical Services Contractor, shall supply and install three phase
circuits to a number of items of plant which are provided by others.
In these cases the local surface mounted control panel (starter panel) shall be provided
and mounted near to the particular drive by the other contractor and he shall also supply
and install the necessary control and indication circuit cables (BMS or remote switch).
This Contractor, the Electrical Services Contractor, shall supply and install all power
cables and make all connections from the nominated distribution board into the local
starter and from the local starter into the local isolator adjacent to the plant item and from
the isolator into the plant item.
This Contractor shall supply and install a whole current isolating switch adjacent to each
item of plant, whether the plant item was provided and installed by this Contractor or
otherwise. The isolating switch shall be lockable. Where applicable, flexible conduit shall
be provided between the isolating switch and the plant. Provide weather-proof isolating
switches in all cases where items are external. PVC equipment (switches and conduit)
shall not be exposed to sunlight, or daylight.
The Contractor shall supply and install all accessories, fixing devices and material for the
full and satisfactory working of the equipment, and shall complete the whole installation
to approval.
The nominated plant items which will be provided and physically installed by others but
will require wiring by this Contractor are shown on the drawings.
5.11. LIGHTING FITTINGS
5.11.1. General
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 38/43
This Contractor shall supply and install all lighting fittings as generally shown on
scheduled and on the drawings
Tenderers shall clearly nominate, in schedule form, exactly what type of lighting fittings,
brand and type No. they have allowed for in their bids
Should Tenderers include the number of particular lighting fittings in their schedule this
will have no contractual significance – This is not a priced Bill of Quantities type of
Contract
Where fluorescent lighting fittings are shown on the drawings they shall all be
instantaneous start-electronic ballast type
Power factor min. 0.85, max THD 10%
The Contractor shall note that when his lighting fittings, tubes, bulbs) etc., are delivered
to him on site they remain his responsibility until the project is complete
It should be noted that all lighting fittings, lamps etc are easily damaged or broken and
consequently the Contractor shall take special care – also care against theft.
Lighting fittings which become broken or damaged on site shall be replaced by this
Contractor at his expense.
All fluorescents tubes in the open office areas and lift lobbies etc shall have a discharge
colour 4,000oK.
All fluorescents tubes in toilet areas shall have a discharge colour of 3,000oK.
All flood lighting fittings shall be provided with high pressure sodium lamps with a
discharge colour of 2,000oK.
Please note the requirements for protection of all steel work from rust and corrosion.
5.11.2. Interior Lighting
The Contractor shall note the different types of lighting shown on the drawings:
Toilet lighting – Toilet lighting – compact recessed fluorescent downlight
Plant rooms, and basement – surface mounted fluorescent weatherproof enclosures.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 39/43
These fittings shall have open 10mm mirror finish egg crate diffusers located level with
the ceilings and the fluorescent tubes shall be a warmer colour (3000oK) than the tubes in
the open office area.
Lobby areas – surface mounted ceiling light fittings warm white colour.
Lobby areas – surface mounted ceiling light fittings warm white colour.
Grand lobby areas – recessed down lights and decorative lights.
Security Room, IT room, Hub room and Communication room – surface mounted 2x36
watt fluorescent fitting each with an emergency back up battery and invertor. Each fitting
shall be provided with an open egg crate diffuser.
5.11.3. Exterior Lighting.
The Contractor shall supply and install exterior flood lighting to the building generally as
shown on the drawings. The principal lighting to the front, back and two sides of the
building.
The fittings shall be weatherproof and preferably not have separate control gear i.e
integral lamp and gear. The fittings shall be finished in a heat and light stable, matt
special “bone” colour finish. Colour sample will be provided to the Contractor after
contract award.
The special colour to the outside of the flood lights shall match the colour of the building.
5.11.4. Landscape lighting
The provision for exterior lighting throughout the landscaped areas in front of the
building shall be provided by this Contractor.
The supply and installation of these coloured uplighters or tree sparkle lights is included
in this Contractor.
5.11.5. Installation of lighting fittings
This Contractor shall provide the Principal Contractor with details and location of all
recessed fittings to be installed in or on the suspended ceilings to enable the Principal
Contractor to arrange for the provision and trimming of all openings and/or above ceiling
supports.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 40/43
Recessed fittings generally shall be supported in the suspended ceilings by the use of
adjustable brackets or mountings to suit the suspension system.
The Contractor shall note that to effectively coordinate his work in the large open areas
with the other trades he shall cable and terminate the lighting circuits well before the
other trades move into these areas. ie 03 core flexible cords 1500 long should be left
trailing out of the embedded junction boxes so that each cord can be connected into its
lighting fitting after all other services have been installed, the tee bar ceiling suspension
system erected and then and only then the lighting fittings positioned
Fittings mounted on the surface of suspended ceilings shall be fixed through the ceiling
panel with a minimum of 04 wood screws into timber battens
Battens shall be a minimum 50 x 25mm dressed pine finished with white primer. Battens
shall span across the ceiling suspension channels (not Tee Bars). Light fittings shall not
be supported directly onto ceiling material
Where large surface-mounted light fittings are to be installed on fixed ceilings, support
rods securely attached to the slab above shall be used
Suspended lighting fittings shall be supported on minimum 2.6mm cadmium-plated steel
chain; single and double tube fluorescent fittings shall have a minimum of two support
chains
The exterior lighting fittings shall be spaced as generally shown on the drawing, and shall
be installed exactly as explained in the installation instruction sheets supplied with each
fitting
The Contractor shall fit lamps to all luminaries before the installation will be considered
complete
The Contractor shall ensure that his workers wear clean white gloves when installing
polished reflector fittings and when installing lamps and tubes.
Recessed down lights shall be fixed to approval and must not transfer their weight to the
ceiling tiles
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 41/43
All installation work must be carried out in a workmanlike manner and shall be to the
Engineer’s satisfaction
Particular care must be paid to the safe suspension mounting of lighting fittings and to the
approved method of cable entry into the light fitting housings as specified above
5.12. EMERGENCY LIGHTING SYSTEM
This Contractor shall be responsible for installing an emergency lighting system on every
level of the building, including the Basement and the Roof. All areas requiring emergency
lighting for escape purposes shall be provided with sufficient emergency lighting fittings
to achieve a min of 2 Lux at floor level for 30 mins.
5.12.1. Emergency Lighting Fittings
All emergency lighting fittings and illuminated exit signs shall be supplied and installed
by this Contractor
The Contractor shall be fully responsible for these fittings after he has had them delivered
to him on site.
Each fitting shall have an inbuilt battery charger, battery and inventor and the internal
components shall be suitable for connection to the regular 220 VAC supply.
The Contractor shall protect all fittings from theft and weather damage
The Contractor shall note that not all exit signs and not all emergency lighting fittings
may be shown on the drawings. The Contractor shall comply with code requirements
irrespective of what is shown on the drawings and satisfy the Engineer.
5.12.2. Installation of Emergency Lighting Fittings
Where emergency lighting fittings form part of the general office lighting system they
shall be illuminated when the rest of the office lights are illuminated but should the
regular power fail (not be switched off) then the inbuilt battery inverter will give up it’s
power to illuminate the selected tube (one of the two tubes in the fitting).
As shown on the drawings there are a number of different types of emergency lighting
fittings. Some emergency lighting fittings are separate, surface mounted, some are
recessed and some are built into regular fittings.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 42/43
In some areas they shall be mounted directly on the ceiling panels or on the walls.
Exit signs shall be carefully positioned so as to be effective with regard to line of site
etc., and the correct signage shall be used to suit the location (arrows and running man).
All exit signs shall be continuously illuminated and have a green background with white
lettering and characters.
All emergency lighting fittings shall only be illuminated when the normal supply fails.
Both exit signs and emergency lighting fitting shall each be fitted with a small LED and
interrupt push switch which shows that the battery charger is working and by operating
the switch allows testing of the fitting and battery supply.
5.12.3. Security Lighting System
This Contractor shall be responsible for installing a Security Lighting System on every
level of the building.
Security lighting in this case means certain selected lighting fittings which do not have
individual switching but are protected by a circuit breaker in the distribution board only ie
these lighting fittings are continually illuminated, 24 hours/day.
5.13. LIGHTNING PROTECTION
5.13.1. General Requirements
This Contractor shall supply and install a complete lightning discharge protection system
to the building
The installation shall generally be as shown on the drawings and as specified herein and
shall comply in all respects with the intention of Vietnam Standard TCVN 9385 : 2012
and Australia Standard AS – 1768
5.13.2. Lightning
Copperplate lightning terminal, D16, L=500mm
The air terminals shall be connected to the down conductors and linked to earthing
system as specified in drawings
5.13.3. Down Conductors
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 43/43
Lightning down conductors are bare copper conductors with a cross section of 70mm2
PVC pipes to D32
This Contractor shall be coordinated and defined on site the penetration through building
for each downconductor.
5.13.4. Underground Conductors
The 70mm2 down conductor shall enter the ground and continue to the first path box
where connection shall be made to the first driven electrode and the continuing conductor
which shall be a bare copper cable min size 70mm2
5.13.5. Path Boxes
The Contractor shall supply and install cast iron hinged lid, path boxes above each driven
electrode so that access is always available to the connection point. The boxes shall be
large enough so that hand and spanner access to the top of the electrode is available
The path boxes shall be secured in a concrete surround 400x400 to allow trimming to the
local ground surface and finish
5.13.6. Earth Electrodes
The down conductor shall be connected to at least three (3) earth electrodes and each
shall consist of sections of copper jacketed 16mm dia solid steel rods screwed together
and driven into the earth.
Earth electrodes shall be as generally shown on the drawings
Connection between the down conductor, the test link and the earth electrodes shall be to
approval
The Contractor shall particularly note that the earth arrangement for the lightning charge
dissipation is completely separate from the electrical earth system and the telephone earth
system. Underground conductors for each system shall be kept as far apart as possible
from each other
A minimum earth resistance of 4 Ohms shall be achieved and maintained throughout the
defects liability period
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 44/43
5.13.7. Tests
This Contractor shall be responsible for obtaining test certificates from a recognised
Authority confirming that the earth resistance of the electrode/down conductor assembly is
4 or less as defined in TCVN 9385: 2012 and is satisfactory. Should more than three (3)
electrodes be necessary to achieve a satisfactory earth resistance then the Contractor shall
so provide.
A cable tray system shall be provided by this Contractor within all ceiling spaces as
shown
Such Telephone/data cables will then be able to traverse lengthwise through the office
floor to serve free standing interconnected office furniture which traverse the in floor ducts
6. FIRE ALARM SYSTEM
6.1. DESCRIPTION OF WORK
6.1.1. Project description
This section of the specification covers the requirements for the supply, deliver,
installation, testing, commissioning and 12 months warranty and comprehensive
maintenance for the entire microprocessor based Interactive Fire Alarm System
The fire alarm system shall be designed and installed in accordance with the latest edition
of Vietnamese Standard TCVN 2622 –1995, TCVN 5738 1993, TCVN5760-1994 or
other applicable recognised standard and in full compliances with the rules and
regulation of the Vietnam Fire Department (PCCC), and other relevant authorities.
All main equipment and devices shall be produced by the same manufacturer. This
applies particular to detectors, control units and central data processing equipment.
System formed by equipment from different manufacturers will not be accepted.
The Engineer shall be entitled when require to conduct quality audit of the Contractor
and/or Manufacturer's premises to assess the quality standard.
The installation shall include all necessary hardware and software for a complete
operable system in accordance with the requirements of this specification.
The entire project will consist of a life safety system.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 45/43
6.1.2. Central Equipment
Fire Alarm Control Panel (FACP)
One FACP together with the operating panel will be located at the Control Room Level.
Two additional FACP shall be located within the building to minimize the installation
work. Each FACP will include:
A high resolution bright LCDdisplay with English characters is to clearly indicate the
type of event that is being displayed. It will display all input alarms, input pre-alarms and
trouble indications. The terminal will display the device that initiated the alarm, the floor,
the zone and the address of the device. It is imperative that a minimum 1,000 events
stored in memory for recall as needed.
Central Fire Command Center (FMS)
The FMS is located at the control center of the complex. The FMS will include:
A color high resolution LCD displaying both text and graphics. It will display all input
alarms, input supervisory alarms and trouble indications from the total project. The LCD
terminal will display the address of the device that initiated the alarm, the building or
occupancy, the floor and the zone to which the address was assigned.
There will be an event log printer which will be located adjacent to the LCD and an alarm
printer which will clearly print which device is in alarm as well as its location.
Peripheral Devices
Detection Devices
Provide detection and signaling devices as shown on drawings.
Utilizeopticalconventionalsmoke photo detector.
Utilize heat detectors with signal processing in the detector for areas totally unsuitable for
smoke detection. These must be base compatible with all smoke detectors. It shall react
with both fixed temperature and rate of rise.
The detector base wiring shall be connected to the polarity and topology free detection
bus.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 46/43
Input / output elements
6.1.3. Equipment access
Utilize input element to allow connection of sprinkler flow switches, tamper valve
switches or other contacts to the polarity and topology free detection bus.
Utilize control element for interfacing control functions on the polarity and topology free
detection bus.
6.1.4. Manual Call points
Utilize red manual call points to be located at each exit stair vestibule entry as shown on
plans.
6.2. SCOPE
6.2.1. General
The FACP must be able to monitor, control and communicate with a number of FACP
distributed through the complex.
All equipment must be located and integrated with the CPU's (at the FACP) to provide
true stand-alone performance.
All automatic and manual functions, such as detection, switch on/off of zones, manual
activation, can be performed at the FACP as well as duplicated at the FMS.
The FACP must utilize a system based on a physical and logical structure. The physical
address of each detection element must be converted to a logical address. This logical
address must be fully user definable.
The physical address of a detection device must be set automatically by the FACP.
Systems which require the manual setting of an address in either the detector or the base
are not considered equal. The logical address must be user definable and it will consist of
the link between an element, being the lowest level 1, and the complex being the highest
level 4 in the structure.
Expansion of devices on any detection bus must be possible any time without any wiring
changes and a spare capacity of 25% shall be provided. Addition of a device must only
require tying the device into the closest detection bus.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 47/43
Provide monitoring of critical fire pump and emergency generator functions. Interface
modules to be supplied by this contractor.
Provide a relay contact output to feed an automatic dialing device that will notify the fire
authorities of an emergency. All dialing equipment required to be by this contractor.
6.2.2. Sequence of Operation
Actuation of an alarm initiating device, (manual station, area smoke detector, electronic
heat detector, water flow switch etc.) is to result in the following:
At the FACP:
Light a large red alarm led to indicate the alarm
Display in English the location of alarm on the LCD with additional red LED’s. A
standard text plus a user text of will describe the device.
Provide output to building management system to initiate building smoke control
functions.
If the device initiating the alarm was a smoke detector in a lift lobby or a sprinkler water
flow switch provide signal to elevator supplier to initiate necessary alarm procedures. All
lift cars in the lift bank serving the floor where the alarm device was activated will
immediate be sent to the ground level landing where they will be decommissioned until
the alarm condition has been cleared or reset or until, manually taken over by the fire
department or fire service procedures.
If the device initiating the alarm was a lift machine room smoke detector provide signal
to elevator supplier to initiate necessary alarm procedures. All lift call buttons, door
buttons and signals will become inoperative in the lift bank serving that machine room.
Lifts will immediately be sent to the ground level landing where they will be
decommissioned until the alarm condition has been cleared or reset or until manually
taken over by the fire department or fire service procedures.
6.2.3. At the FMS
Light a large red alarm led to indicate the alarm.
Display the alarm in English characters on the LCD with a flashing red on the dynamic
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 48/43
symbol represents the alarm point. A standard text plus a user text will describe the
device. An additional message containing intervention information must be available.
This additional information may be called up from memory as required.
Display the map of the floor area where the alarm originated on the color graphics LCD.
Print the alarm with time and date, and user text (English) describing the device in alarm,
on the alarm printer.
Print this alarm and all relating events, such as acknowledge, reset etc. on the event log
printer. This printer to print one line per event.
At the initiating devices
Flash the alarm indicator on the detector or manual pull station as applicable.
Light the led on the input or output element.
6.2.4. Supervisory functions
Activation of supervisory devices, i.e. tamper switches on shut-off valves, fire pump
status, etc. must provide the following operation:
At the FACP Command Station:
Display the device that changed state on the LCD (English) with a yellow led. A standard
text plus a user text will describe the device.
At the FMS Command Station
Light a large magenta lamp to indicate the event.
Display the map of the floor area where the event originated on the color graphics LCD.
Print the event (English) with time and date, and user text describing the device on the
alarm printer.
Print this event and all relating events, such as acknowledge, reset etc. on the event log
printer.
6.2.5. Trouble functions
The FACP must supervise the entire system. Assigned messages are to be displayed on
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 49/43
the LCD display for all fault conditions. Every monitored point must display its fault
condition individually, and all faults within the entire system must be displayed on a per
point basis. In the event of a malfunction, the following must occur:
Sound the audible trouble signal and light the system trouble lamp at the operator panel.
Operation of a momentary silence switch to silence the audible trouble signal. The
trouble lamp will stay lit until all troubles have cleared.
6.3. PRODUCTS
6.3.1. Concept / requirements of the FMS
The entire automatic fire detection system as a centralized data communication and
processing system. This is achieved by connecting each FACP via serial data lines to the
FMS.
The overall system (network) architecture will be based on the principle of distributed
processing. The FACP will remain autonomous (independent) in evaluation,
annunciating, alarming and control in case of interrupted communication between the
systems and the FMS. The FACP will operate totally in a standalone mode. Full
operation will take place in the building associated with the systems regardless of the
condition of the FMS or the wiring network.
The peripheral devices such as system main terminal(s), printer(s), etc. are built into a
control desk of adequate size.
The equipment is designed for mounting into 19 inch (48 cm) standard racks or with
standard wall mount cabinet.
6.3.2. Data transmission
A state-of-the-art data transmission network will connect the FACP with the FMS
equipment.
The communication network is a "free network". This means that messages are
transmitted in a spontaneous manner, leaving the system's response time independent of
its size and number of FACP's connected.
Systems in which the FMS equipment "scan" the FACP’s are not acceptable.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 50/43
Only systems using standard half or full duplex, digital, serial data transmission will be
accepted.
The communication network must be designed for standard telephone wire however local
codes in wiring will have to be adhered to.
The individual system components are interfaced to the transmission network via
transformer-coupled modems, using either RS 232C or fibre optics technology.
Every path of the data transmission network must be monitored for open circuit.
Proper operation of the FMS should be checked periodic by itself.
In all point-to-point networks, communication faults are announced on both sides.
Transmission errors will be indicated at the FMS and the FACP's. Such a fault must not
lead to deterioration of the autonomous operation of the FACP's concerned.
6.3.3. Central data processing unit (FMS)
By definition, the central data processing unit monitors and controls the entire system and
allows control of all FACP's connected to the network.
The central data processing unit will be of modular design, allowing easy stage-by-stage
extension of capacity (in hard- and software) to meet specific project requirements.
The data processing unit must be capable of monitoring and processing a minimum of
30'000 data points with at least 20,000 points spare capacity for future system expansion.
The individual microprocessors contained in the central data processing unit must be
supervised by means of a built-in watch dog circuit.
The following program and data carriers are used for the central data processing unit:
RAM
EPROM
HARD DISK
A history file of all system events, such as alarm, status, fault, operator activities, etc. is
stored on disk.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 51/43
A record of the last 1000 events must be maintained on disk to be printed out upon
request from the system main terminal(s).
The exchange and copying of a back-up or history file disk must not affect the normal
system operation.
Systems requiring non-standard configuration to meet project requirements should be
clearly indicated in the tender document.
6.3.4. System printer units
It must be possible to connect an alarm printer and an event logger, both must print
English characters.
All events will be logged automatically on the printer(s).
It must be possible to initiate separate printouts via menu command on the system main
terminal.
It must be possible to assign dedicated functions (selected messages, system sectors, etc.)
to each printer via configuration perimeters.
6.3.5. System printer
This printer will only print alarm messages and must print English characters.
Each alarm message is only composed of plain text related to the protected area, building,
and floor.
Each alarm printout contains the following information per device:
Time of day
Date
Type of alarm
Origin of alarm
Description of affected alarm location
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 52/43
6.3.6. Color graphic display terminal
The color graphic display terminal(s) will display the location of the alarm initiating
device in a graphic format.
It must be possible to display all events in plain text on the system LCD and the color
graphic maps selectively on the color graphics LCD. Text or graphic selection is made in
the menu field by using the mouse.
Block diagrams the entire system must be stored in the graphics system. Each FACP will
have its block diagram stored with its ports, modems, interfaces and major panel blocks
represented by active icons. Any failure of these system segments will be represented by
a yellow flashing icon.
The system will allow the generation of schematics and pictures in an easy and fast
manner so that no extensive operator training is required.
The color graphic terminal allows the interactive (real time) display of all alarms, fault
conditions and specific status events (e.g. zone off) in the entire fire alarm system.
The events to be displayed on the graphic unit will allow identification of their origin by:
Location of all sub systems such as FACP
Device location
Originating source
Automatic detector
Manual call point
Extinguishing system (if applicable)
Sprinkler flow switch
Building services (plant monitoring)
Priority of alarm/fault condition
Selection and activation of a certain graphics display is either automatic (event driven) or
on manual request by menu selection using an electronic mouse.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 53/43
No specific training must be required for the picture generation.
The picture editing program will allow the addition of alphanumeric text and pre-defined
graphic symbols to each picture.
6.3.7. Concept / requirements of the FACP
A. General
Maximum system availability will be realized by decentralizing the system intelligence
whereby the detection and evaluation task is performed by the detector. The FACP will
verify and process the detectors' output signals in conjunction with the pre-defined user
data, e.g. display the event, perform pre-defined control, signal tasks and respond to
manual commands entered by the system operator.
The FACP will be capable of operating conventional/collective, and analogue
addressable detector bus. A combination of these circuits in the same FACP, for the
initial installation or for any future system expansions, will be possible.
The FACP will allow easy system expandability up to 10'000 addressable detecting
points.
The FACP will be capable of communicating with up to 15 remote operating terminals.
Each terminal will be pre-programmable to operate on the whole of the detection system
or only a certain section of it.
In addition to fire detection devices, it will be possible for the FACP to evaluate and
operate signals from:
Sprinkler flow switches
Stand-alone automatic extinguishing systems
Stand-alone gas detection systems
Information from technical plant equipment
To optimize the response characteristics of automatic detectors, it will be possible to
monitor these and to download different sensitivity settings.
An audible and visual application warning signal will automatically be activated per
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 54/43
detector, if the response characteristic of the detector does not correspond with the
environmental conditions it is operating in.
B. Detector bus communication
By using the principle of detection bus, the FACP will be able to process signals from
and send data to detection devices via a twisted two wire line.
The detector bus will be capable to interfacing with detection devices such as automatic
detectors (e.g. smoke, heat, etc.), manual call points, input and output devices.
Free topology and polarity are allowed. It is possible to wire the detection bus without
consider the polarity and T-tapping can also be possible throughout the detection bus.
The line capacity will handle up to 127 automatic detectors (e.g. smoke, heat, etc.) and
the operating power for these devices will be supplied through the same two-wire
detection bus.
Each detector bus will interface with its own dedicated detector bus module complete
with an on board microprocessor.
The FACP will have the capacity to handle up to such 20 modules.
It will be possible to assign to each automatic detector (e.g. smoke, heat, etc.) an
individual sensitivity setting that can, whenever desired, be manually or automatically
exchanged for that of another type.
The operation of a short circuit isolator / separator, an integral part of a line detection
device, will guarantee full bus functionality.
An address will be freely assigned to all the detection devices that have been connected
to a detector bus. Any future extensions, i.e. the connection of additional detection
devices between existing devices, or at the end of the detection bus, will not interfere
with any of the initially assigned addresses or user data for the existing detection devices.
Address allocations will be displayed on the operating terminal as a geographical
description of the physical location of the detecting device.
The system will be able to identify the type of detector installed in each base and
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 55/43
consequently, verify this information during normal operation and service.
C. Hardware configuration / Mechanical design
The FACP will consist entirely of standard modular, printed circuit board assemblies to
facilitate removal, easy maintenance and modular system expansion.
A central CPU module controlling an operating terminal wit a 10” LCD display and an
internal bus onto which detection bus, various input/output modules, bell and remote
alarm circuits can be connected.
A remote microprocessor based operating terminal.
Indication of real time analogue values of smoke and heat detectors can be shown in a
graphical point in the operation terminal
An ac/dc converter module, with charging unit
Battery capacity for 24 hours emergency supply in standby ode and 30 minutes in an
alarm condition.
It will be possible to optionally expand the basic assembly of an FACP by modules for:
Detection bus
Programmable outputs, driver type (24VDC/40mA)
Outputs, relay contact type (250VAC/10A)
Additional rated power supply and battery charging module
It will be possible to locate the fire brigade intervention plans at the location of the FACP
or at the operating terminal itself, if this is remotely installed.
D. Power supply unit
The power supply will comply with EN 54 part 4 or UL864.
The power supply unit will contain suitable over-voltage protection to prevent any
malfunction or damage which might occur from line power surges.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 56/43
The FACP will be equipped with a built-in standby battery, rated to maintain operation
for twenty four (24) hr's after mains failure. An alarm condition must be maintained for at
least 30 minutes after the above lapse of time expired.
The battery type shall be recommended by the manufacturer.
It will be possible for a pre-defined period to suppress an audible- and visible mains
failure alarm indication at the operators terminal for any mains supply interruptions, that
do not exceed this time period.
6.3.8. Software functions
A. General
The operating terminal will either process and display events spontaneously or at the
request of the operator
The operating terminal will distinguish between alarm, fault, information and isolation
conditions.
The operating terminal will provide, apart from acknowledge, reset and event scrolling
functions, at least the following controls:
A back lighted 10 inches LCD display
A key pad to enter user passwords
Means of overriding alarm delays for extinguishing function
Possible to program all the necessary user parameters from the key pad without the need
of a commissioning computer.
B. Data
The FACP will be able to handle the following capacities
10.000 data points (detection devices)
20 detection module or 80 detection bus, or
40 programmable control outputs via FACP, or 1000 programmable control outputs via
detector circuits, or 30 integrated extinguishing sections, or any combination of the above
mentioned function units within the limits of the FACP.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 57/43
C. Remote operating Connection. Important functions
1) Pre-alarm
The FACP will be capable of monitoring the frequent occurrence of pre-alarm signals
released by an automatic detector. A pre-alarm signal will then be displayed by means of
an audible and visual indication at the operating terminal.
2) Multi detector logic.
It will be possible to operate an output if two or more automatic detectors, monitoring the
same area, activate a warning signal.
3) Device not ready yet.
It will not be possible to switch any device (automatic detector, manual call point,
control- and monitoring device etc.) back into operation, if the device, at the moment of
switching, is not in the normal state yet. For these devices will the FACP indicate a not
ready message on the operating terminal.
4) Programmable control functions
Upon receipt of an event (alarm, warning, fault), or the release of a manual operating
command, the control functions will activate the assigned physical control device.
A control device will be either a bell circuit function or an output relay device connected
to either a detection bus or directly the FACP.
To perform flexible pre-programmed automatic control functions, it will be possible to
assign time dependent AND and OR function gates, or a combination of those, to
different detection devices within a group.
5) Access levels and passwords.
Operator access will be granted via three different access levels.
The password will consist of an identification code and a mental code. The identification
code will at least consist of two digits and the mental code will at least contain a three
digit code defined and entered into the system by the operator.
The FACP will automatically log out the signed-on operator, if he did not operate any
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 58/43
system functions for a pre-defined period.
6) History file
The FACP will save and display the data of at least 1.000 system operating event.
The historical data will be displayed at the operating terminal as follows :
All messages listed in a chronological order
All pre-alarms
All alarms
All faults
All information
All active control functions
For processing additional parameters of the historical data, the FACP will provide an
interface to a PC, normally used as a maintenance tool:
Transfer of all system events
Store information about all different type of signals
Transfer and save the detector fault codes
It will not be possible to delete the data in the history file from the operating terminal of
the FACP.
7) Real time clock
The actual real time will be displayed on the operating terminal.
8) “Turning on” and “switching off” system devices.
It will be possible to “switch on” and to “switch off” the following “devices” from the
operating terminal:
Any automatic detector (e.g., smoke, heat, etc.)
The remote alarm and fault indications transmitted to the fire brigade
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 59/43
Any alarm devices
A printer unit
Any control outputs
Any monitoring inputs
9) Printer interface.
The FACP will interface, either directly or from the remotely installed operating
terminal, via a RS232 type data link, with a standard off-the-shelf printer unit.
The character-set which the FACP supports, will be English characters.
10) Alarm counter
By making use of an alarm counter will, upon manual request, all active alarms be
indicated on the operating terminal.
D. Person-Machine Interface
1) The FACP will be designed such, that the operating terminal serving
as a person-machine interface, be either an integrated part of the
FACP, or a separate unit suited to be installed at a remote location.
2) The FACP will communicate with the operating terminal via a
communication bus that operates in a bus configuration.
3) It will be possible to operate the entire system from one operating
terminal. Additionally up to 15 operating terminal can be used to
perform dedicated display and control operations for pre-defined
sections of the system.
4) To guide the operator through the operating process, the operating
procedure at the operating terminal will be fully menu driven.
5) The layout of the front plate for the operating terminal will guarantee
that the incoming event messages are clearly distinguished by the
operator. For this purpose, these will be categorized as follows:
Alarm conditions
Fault conditions
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 60/43
Isolated / disabled conditions
Status information
E. Commissioning features
1) To provide maximum ease and flexibility for the commissioning
process, the following pre-defined commissioning modes will be
possible:
Upon insertion of a detection device into its base, the FACP will
automatically read in the address.
Setting of the address shall be performed in programming the dip
switches on all the automatic detectors and input / output elements.
2) It will be possible to program all user application data for the FACP,
off-line with a maintenance PC. For up-loading purposes the
maintenance PC will be interfaced to the FACP.
3) It will be possible to reprogram the detection devices from the
operating terminal or maintenance PC.
4) In order to save all the system data, it will be possible to generate a
back-up file.
5) It will be possible to locally monitor the system behavior.
F. System printer units
1) 1. It must be possible to connect an event logger to the FACP.
2) 2. All events will be logged automatically on the printer.
3) 3. It must be possible to initiate separate printouts via menu command
on the system main terminal.
4) System event printer
This printer will log all change-of-status, alarm and fault messages,
along with time of day and date.
Each message will be printed in one line (or maximum two) and will
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 61/43
contain a reduced plain text related to the zone and/or device location.
G. Power supply units
1) Power supply
Each self-contained unit, such as:
Central data processing unit
System main terminal(s)
Color graphics terminal(s)
Remote graphic annunciator
The power supply must be able to operate on a primary power of
110/120/220/240 VAC, -15% to +10%, 48 to 62 Hz.
The power supply unit must contain suitable over-voltage protection
to prevent any malfunction or damage which might occur from line
power surges.
When battery voltage drops below defined value. a fault indication is
to be provided to indicate a battery fault condition.
A visible and audible signal is to be generated to indicate that the
FACP is operating under emergency power.
The master fault indicator on the FACP is to be illuminated until
mains power has been restored.
When the AC power is restored, the FACP must automatically revert
to normal operation without requiring any manual restarting
procedures.
2) Standby battery
Equip the FACP with a built-in 24 V rechargeable sealed maintenance
free battery, complete with all necessary interconnections and filled
with electrolyte, charged and ready for service and with sufficient
capability to maintain the system for 24 hours and still provide
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 62/43
afterwards signal power for 30 minutes.
Upon loss of mains power, the power supply unit must automatically
revert to battery power, and the system remain full operational.
Battery must consist of rechargeable sealed maintenance free cells.
Charger designed to suit the characteristics of the battery providing
automatic boost charge facility when the battery bank potential falls
below acceptable voltage for maintaining a working system and return
to float charge when the battery bank reaches maximum acceptable
voltage.
3) Uninterrupted power supply
Provide a UPS (uninterruptable power supply) with the capacity to
operate all life safety and security equipment located in the FMS room
for a period of 30 minutes.
H. Mechanical Design
1) Design the FACP to 19 inch panel standards or wall mount cabinet.
2) House it in a heavy-gauge metal cabinet with the display and
operating terminal suitable for flush mounting.
3) The FACP is to consist entirely of modular, unit-type assemblies to
facilitate removal, maintenance and system expansion.
4) Display and operating terminal(s) to be integrated to the FACP
enclosure or separate.
5) All lettering on the display and operating terminals must be in
English.
I. Field Devices and Equipment
1) Manual call point (fire alarm red)
The manual call point must be electrically compatible with the
standard range of automatic detectors, so that it can be connected
directly into the supervised two-wire zone of the manufacturer
standard range of FACP for class B wiring.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 63/43
The manual call point will be pleasant, streamlined and flat in
appearance permitting its use as a surface mounted unit.
The breaking of the glass must not release an alarm. The glass plate
must be designed in a way to prevent injuries when struck by the
operator. The pushing of the call button will initiate the alarm.
It must be possible to test the manual call point without breaking the
glass by the use of a special tool.
The call point must comply with standard EN54-11 or UL.
All designations and markings must be available.
The call point will be ASIC based and have a dip switch to program
it’s an address.
The manual call point will have a built-in LED, automatically
confirming its operation.
The electronic intelligence is potted to prevent outside interference
and make it immune to ambient influence.
2) Input module (1 Input)
The input module allows the connection of 1 potential free contact
devices into a detector bus.
The input module connects to the FACP via a fully supervised two-
wire circuit. No separate power line will be required. No special need
to consider the polarity on wiring.
The lines to the acknowledgment contacts will be supervised with a
class B circuit with end-of-line resistor.
The input module will be ASIC based and has dip switch to program
it’s an address.
The input module is equipped with a built-in alarm lamp as a response
indicator for parallel detectors and/or contacts connected.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 64/43
It will be possible to change the electronic parts without removing the
housing or the wiring.
3) Output module (1 output)
The output module is designed to convert specific signals on a
detection bus from the FACP into control functions.
The output contact of the output module must be rated for at least 1.0
Amp at 24 DC.
The output module has an input for a connection of an external contact
to provide a confirmation signal to be sent back to the FACP via the
detection line after the control function has been carried out.
The output module will be microprocessor based and have its own
factory set identification number.
It will be possible to change the electronic parts without removing the
housing or the wiring.
4) Optical Smoke Detector
The design of the smoke sensitive system must guarantee a uniform
response behavior to all combustion products of smoke-forming
flaming and smoldering fires.
The detector must be ASIC based
The detector will transmit analogue value to the FACP for evaluation
according to the customer specific programming of the FACP.
The detector must be able to execute a self-test.
The detector will require the setting of a dip switch or other similar
device to define the address of the detector.
A built-in barrier must prevent the entry of insects into the detector.
The detector must be insertable into the base without the need of any
tools.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 65/43
The base must be completely hidden by the detector.
5) Electronic Thermal Detector
It must require only one version of the electronic thermal detector
which can react on either fixed temperature or rate of rise.
The detector must be ASIC based.
All electronics must be solid state using SMD technology.
The detector will require the setting of a switch or other similar device
to define the address of the detector.
The detector must be insertable into the base without the need of any
tools.
The base must be completely hidden by the detector.
Reversed polarity or faulty wiring must not damage the detector.
6) Plug-in Bases
Provide twist lock plug-in bases for the electronic thermal detectors,
smoke detectors and multi-criteria detectors as required.
All bases for collective, smoke and thermal detectors must have the
same appearance and general design. The detectors must be
interchangeable into these bases for all addressable detectors.
The base will be manufactured of impact and scratch proof material.
The detector shall require the setting of a dip switch or other similar
device to define the address of the detector.
A built-in barrier must prevent the entry of insects into the detector.
The detector must be insertable into the base without the need of any
tools.
The base must be completely hidden by the detector.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 66/43
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 1/19
ELV SERVICES
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 2/19
1. INTRODUCTION:
Profile basic design overview of technical solutions for ELV systems: Fire Alarm System
(FA); Public Address System (PA); Closed Circuit Television System (CCTV); Voive-
Data System
Profile notes engineering construction after the foundation approved for deployment
detailed drawings.
2. GENERAL REQUIREMENTS
The ELV system is installed to meet the technical criteria of Vietnam and International,
benefit, convenience to homeowners, raising class stature house.
3. SCOPE OF WORKS:
Supply and installation for ELV System
4. APPLICABLE STANDARD:
America Standards
BS Standards.
IEC Standards
Vietnam Standards
5. CONFIGURING THE SYSTEM:
5.1. CCTV SYSTEM
5.1.1. General
This Contractor (the Electrical Installation Contractor) shall provide a complete and
operating color CCTV System as indicated in the drawings and as specified herein.
Supply and install a complete and operable CCTV system consisting of color cameras,
lenses, housings, mounting hardware, color monitors, digital video recorders, alarm
interface facility, keyboards, interface hardware, power and signal/data cabling, conduit,
cable trays, equipment racks, power supplies, necessary software, programming and
commissioning.
5.1.2. Standard Components
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 3/19
All equipment and materials used shall be standard components, regularly manufactured,
regularly utilized in the manufacturer’s system. All systems and components shall have
been thoroughly tested and proven in actual use.
5.1.3. Color PTZ Dome Camera
The CCTV camera dome drive system shall consist of a discreet, miniature camera dome;
variable speed/high speed pan and tilt drive unit with continuous 3600 degree rotation;
high resolution, 1/4”, color, CCD camera; 22X optical with additional 8X digital, auto
focusing, motorized zoom lens; integral receiver/driver; and quick–install pendant mount.
As part of the Outdoor CCTV camera dome system, the lower dome shall be a maximum
of 5.9” in diameter and extend to a maximum of 2.75” below the pendant back box, shall
be made of acrylic material, be optically clear, and have no distortion in any portion of
the dome up to +20 above the horizontal, and shall weigh a maximum of 1 lb. – 5 oz. The
variable speed/high speed pan and tilt drive unit shall be capable of 3600 continuous pan
rotation and a vertical unobstructed tilt of +20 to –92
0 and shall pan from a creep speed of
0.10
to 800
per second, and pan at 1500 per second in turbo mode. Tilt operation shall
range from 0.10 to 40
0 per second. The pan and tilt drive unit shall operate under variable
speed automatic preset control at a pan speed of 2500 and a tilt speed of 200
0 per second.
The pan and tilt drive unit shall be capable of 64 preset positions with a 20–character
label available for each position. The high resolution, color CCD camera shall be a 1/4”
interline transfer imager meeting NTSC signal format specifications and shall be 2:1
interlace, with AC line lock that is phase adjustable by remote control. The image sensor
shall have a total pixel array of 811 (H) x 508 (V) and an effective pixel array of 768 (H)
x 494 (V). The camera shall provide a horizontal resolution of 470 TV lines. The camera
shall have a signal–to–noise ratio of > 46 dB. All programmable camera functions shall
be stored within the dome drive unit using non–volatile memory, without the need for
battery backup. The motorized zoom lens shall be 22X optical zoom with an additional
8X digital zoom (176X total zoom), 4 mm to 88 mm, F1.6 and shall have a horizontal
angle of view of 470 at 4 mm and 2
0 at 88 mm telephoto zoom. The lens shall feature an
automatic focus with manual and programmable override.
5.1.4. Interior PTZ Color Cameras
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 4/19
The indoor CCTV camera dome drive system shall consist of a discreet, miniature
camera dome; variable speed/high speed pan and tilt drive unit with continuous 3600
rotation; high resolution, 1/4”, color, CCD camera; 18X optical with additional 4X
digital, auto focusing, motorized zoom lens; integral receiver/driver; and plenum–rated,
quick–install back box assembly. The lower dome shall be a maximum of 5.9” in
diameter and extend to a maximum of 3.25” below the ceiling when installed in the back
box. The lower dome shall be made of acrylic material, be optically clear, and have no
distortion in any portion of the dome up to +20
above the horizontal. The lower dome
shall weigh a maximum of 3.1 oz. The variable speed/high speed pan and tilt drive unit
shall be capable of 3600 continuous pan rotation and a vertical unobstructed tilt of +2
0 to
–920. The pan and tilt drive unit shall pan under manual control from a creep speed of
0.10 to 80
0 per second, and pan at 150
0 per second in turbo mode. Tilt operation shall
range from 0.10 to 40
0 per second. The pan and tilt drive unit shall operate under variable
speed automatic preset control at a pan speed of 2500 and a tilt speed of 200
0 per second.
The pan and tilt drive unit shall be capable of 64 preset positions with a 20–character
label available for each position. The pan and tilt, dome drive, receiver/driver, and
camera/lens assembly shall weigh a maximum of 2 lb. – 11 oz. The high resolution, color
CCD camera shall be a 1/4” interline transfer imager meeting NTSC signal format
specifications and shall be 2:1 interlace, with AC line lock that is phase adjustable by
remote control. The image sensor shall have a total pixel array of 811 (H) x 508 (V) and
an effective pixel array of 768 (H) x 494 (V). The camera shall provide a horizontal
resolution of 470 TV lines. The camera shall have a signal–to–noise ratio of >46 dB. All
programmable camera functions shall be stored within the dome drive unit using non–
volatile memory, without the need for battery backup. The motorized zoom lens shall be
18X optical zoom with an additional 4X digital zoom (72X total zoom), 4.1 mm to 73.8
mm, F1.4 with a horizontal angle of view of 480 at 4.1 mm and 2.7
0 at 73.8 mm telephoto
zoom. The lens shall feature automatic focus with manual and programmable override.
5.1.5. High Resolution Color CCD Cameras
The High Resolution Color CCD Cameras shall be comprised of an enhanced CCD
sensor, solid state circuitry, and state of the art electronics incorporating the latest in
digital technology, housed in a compact, rugged ABS plastic case. The High Resolution
Color CCD Color Cameras shall be a 1/3” interline transfer imager meeting PAL/CCIR
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 5/19
signal format specifications. The camera shall be 2:1 interlace, internal or external sync.,
230VAC input power, 50/60 hertz, with AC line lock, V–phase ±900 adjustable. The
camera shall provide a resolution of 470 TV lines horizontal. The camera shall feature
digital signal processing, DSP. The camera shall feature CCD Iris technology and
standard auto iris lens compatibility. The camera shall accept either Video type or DC
servo type auto iris lenses, switch selectable. The camera shall have automatic iris control
and gain control which shall be switchable ON/OFF/Turbo. The camera/lens package
shall provide for a sensitivity of 1.9 lux at F1.2
5.1.6. Low Profile, Ceiling Enclosures
The low profile camera enclosure shall consist of an camera housing designed specifically
for use with 1/2” or smaller format cameras and fixed focal length lenses in indoor
applications along with any accessories which may be required for a complete camera
enclosure. The camera enclosure shall be designed for use in fixed or suspended ceiling
applications or be wall mounted. The enclosure shall accommodate camera / lens
packages up to 3.00”H x 4.00”W x 10.00”L including the BNC connector. The enclosure
shall be NEMA 1 rated and UL listed to 2044. The enclosure shall measure a maximum of
13.50”L x 7.50”W x 7.00”H, with a maximum of 3.50” extending below the ceiling level.
The enclosure shall weigh a maximum of 1 lbs. – 12 oz
5.1.7. Camera / Enclosure Mount
The camera / enclosure mount shall consist of a mount designed specifically for
mounting a camera/enclosure on a wall, along with any accessories which may be
required for a complete camera mount. The camera/enclosure mount shall measure
16.50”L with a manually adjustable tilt table extending up 2.62” from the horizontal arm.
The mount shall be capable of supporting up to 40 lbs. The mount shall be supplied with
a manually adjustable tilt table capable of unlimited 3600 pan adjustment and ±75
0 tilt
adjustment. The mount shall constructed of cast aluminum arm with aluminum adjustable
head and finished in a gray polyester powder coat. The mount shall be UL listed to
Standard 2044
5.1.8. High Security, Indoor Corner Mounts
The High Security Indoor, Corner Mounts shall provide a tamper–resistant corner mount
for fixed camera locations. The High Security Indoor, Corner Mounts may be installed
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 6/19
flush against a ceiling or mid–wall in high ceiling applications without compromising
enclosure integrity. The unit shall be constructed of heavy gauge steel and feature a half–
inch thick impact–resistant lexan window. The smaller frontal area and reduced overall
size create an unobtrusive enclosure shall support the specified camera. Three conduit
knockouts shall be provided to allow wires to be delivered from the wall on either side or
the ceiling
5.1.9. Indoor Camera Enclosure
The indoor camera enclosure shall consist of a camera housing designed specifically for
use with 1/2” or smaller format cameras and fixed focal length lenses in indoor
applications along with any accessories which may be required for a complete
environmental camera enclosure. The enclosure shall accommodate camera/lens
packages up to 2.75”H x 3.75”W x 8.00”L including the BNC connector. The enclosure
shall be provided with a viewing window constructed of 1/8” thick, optically clear, Lucite
SAR super abrasion resistant acrylic). The viewing window shall measure 2.50”H x
3.50”W, minimum. The enclosure shall be NEMA 1 rated and UL listed to 2044. The
enclosure shall measure a maximum of 11.50”L x 4.65”W x 3.40”H.
5.1.10. Digital Video Recorder
The Digital Video Recorder (DVR) shall provide digital video storage capability with
enhanced built–in video motion detection, alarm–based recording and relay outputs to
control. The Digital Video Recorder shall provide 16 camera inputs for fixed and/or
moveable cameras, as well as Camera Pan/Tilt/Zoom control via RS–232 connections.
The DVR shall provide expandable hard drive configurations, provide multiple camera
displays for live viewing or playback while recording, continuous, motion detection,
alarm, pre–alarm, and scheduled recording modes and record up to 60 images per second.
The DVR supports up to 8 hard drives, factory installed, with capacity (at maximum
configuration) for over 90 days of recording.
5.1.11. CCTV Software Interface
The CCTV software interface shall support a multiple video switcher. The integrated
security system shall control the CCTV system
The CCTV software interface shall provide for the capability of displaying any camera on
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 7/19
any monitor within the system via a video switcher. The system shall support camera
positioning and Pan, Tilt, Zoom (PTZ)-equipped cameras. The system shall support the
setting of the video switcher to automatically move the PTZ camera to a specified pre-set.
The system shall provide for automatic camera and monitor selection whenever an input,
output or group icon is selected in the Integrated Security System.
When an alarm occurs, the system shall automatically select the highest priority alarm,
resulting in the display of the pre-defined camera scenes on the pre-defined monitors.
The software interface shall, as a minimum, support the operation of either American
Dynamics 168, 1600, 1650, 1995C, 2050 and 2150 and Burle TC8500, TC8600, TC8800
and TC8900 and Pelco CM 6700, 6800, 8500, 9740 and 9760 Panasonic 550 and 850,
and Ultrak MAX 1000 series Video Switchers
The CCTV control switching and sequencing programs shall be configured using the
system configuration program. By designating specific CCTV programs (camera shot-
monitor definitions) to certain alarm points, the system shall be able to automatically link
point selection to video control and monitoring, plus define all in-video camera titles
The CCTV interface shall be provided over an RS-232 link between the Security
Application Server and the video switcher. The CCTV software interface shall support an
unlimited number of CCTV monitors, cameras and CCTV switching programs (i.e.;
camera/monitor selections). The system shall provide for the initiation of video recording
on an event-driven basis
Effective CCTV tours shall be implemented by linking input, output and grouped points
to CCTV programs. As the alarm monitoring and control program sequences through
points within the Alarm Review program, the pre-defined CCTV pictures shall be
displayed on the pre-defined monitors
Video Switcher configuration shall be such that automatic addition and deletion of
cameras from their respective menus shall occur upon the configuration of the switcher
parameters. The system shall support more than one view (shot, pre-set) for each camera
5.2. PUBLIC ADDRESS SYSTEM (PA SYSTEM)
5.2.1. General
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 8/19
This Contractor, the Electrical Installation Contractor, shall supply and install complete
public address systems.
This part of the specification covers the manufacture, factory testing (components and
assemblies), delivery to site, assembly on site, installation, test and commissioning of a
Public Address System, generally as shown on the drawings and as specified herein.
The works will include all incidental items necessary for proper functioning of the whole
system whether or not specifically mentioned.
The equipment shall be entirely suitable for the purpose intended.
This equipment is part of the Life Safety installation in this building
5.2.2. Amplifier Rack
The amplifier and certain other equipment shall be assemblied into a ventilated, dust free,
common, free standing rack or cabinet.
The rack shall be provided with a glass, dust excluding door and be designed to dissipate
all internally generated heat either by natural radiation - convection or mechanical
ventilation via a small and silent dust excluding electric fan.
The rack shall be constructed so as to allow circulating air to pass under the lowest unit.
Stacked loose equipment will not be acceptable.
The 220 VAC power for the amplifier rack shall emanate from a UPS source which forms
part of the PA equipment.
The single phase UPS system shall have a rating such that the P.A. System can operate
without compromise for 60 minutes.
5.2.3. Amplifier and Inputs
The amplifier equipment shall be designed to accept the output from two (2)
microphones. Operation shall be simple and easy to use.
This PA system is part of the life safety installation within this building and as such all
equipment including the Amplifier itself must be as reliable as possible. All components
must be adequately rated and none shall operate near their limit.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 9/19
The output to all speakers must be clear and distinct and be absolutely free of any
interference or mains frequency hum.
Sound penetration into all areas shall saturate the space via multiple speakers all at low
out put level.
High intensity sound levels, even supplied distortion free, will not be acceptable.
Not all individual zones which may be selected have equal numbers of speakers.
5.2.4. Microphones
Two microphones (one table stand and one “push-to-talk” types) shall be provided for
each PA system and will input into the amplifier.
The Contractor shall provide all necessary cabling and preamplifier equipment if
necessary
The stable stand microphone shall be provided with a stand which shall be suitable for
screw fixing to a desk or table and the microphone shall have an adjustable, flexible,
gooseneck stem.
The table stand shall be have a built-in “push to talk” button.
Provision immediately to the right of each button shall allow (slip in behind stiff plastic)
descriptions of the zones which will receive the broadcast if the adjacent “push to select”
button is depressed.
The base of the Microphone stand shall incorporate two small LEDs:
Green: PA System is in standby mode
Red: Microphone is “alive”.
5.2.5. Chime
When either of the microphones is selected to become active a soft chime shall sound in
those areas about to receive the broadcast. This chime shall be capable of being muted
5.2.6. Speakers
All speakers shall be provided by this Contractor.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 10/19
Ceiling type speakers shall each be approx 200 in diameter and be screw fixed to a baffle
board.
The baffle board shall be independently suspended and be provided with an off white
circular metal grille - spring loaded clip into the suspended ceiling material or receiving
bracket fixed to the baffle board.
Provide a dust excluding light weight linen bag to each speaker above the ceiling.
Horn speakers (installed in the basement) shall each be type of horn loud output speaker
complete with mounting bracket.
Note: All speaker mounting brackets and all wall mounting brackets shall be hot dip
galvanized, if made of steel.
5.2.7. Speaker Circuits
The amplifier output shall, through selective push button control on the microphone
stands, be capable of directing sound to specific areas, groups of areas or “all in”.
The individual areas or zones shall be as in drawings.
The output from the amplifier to each speaker in any one (1) zone shall be carefully
adjusted in gain so that there is an even sound level throughout the whole area (no loud
spots or weak spots).
The output from the amplifier to each speaker zone shall be carefully adjusted in gain so
that there are no excessively loud areas and the sound level in any one (1) zone is
consistent irrespective of how many zones are selected.
5.2.8. Fire Alarm Panel interface
The Contractor shall ensure that the P.A equipment supplied is designed to provide a
separate output signal corresponding to the activation of a PA zone selection prior to and
during an announcement.
These signals shall be connected into the Fire Alarm Panel.
5.3. VOICE DATA
5.3.1. General requirement
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 11/19
Tenderers shall propose and submit a comprehensive Structured Cabling Solution to
define the telecommunications infrastructure (patch panels, frames, patch cords, cables,
faceplates and outlets) necessary to build a uniform premises distribution system, which
will function for a multi-media communications solution to support up to 100Mbps.
Tenderers shall make full allowance in their bid for all necessary equipment and it’s
installation – See also the proposed data network schematic in the drawings.
A Structured Cabling Solution that uses Category 5e components and/or Optical Fiber
backbone shall be capable of providing 100 Megabit Ethernet operation using full duplex
transmission.
The solution should define the method(s) of flexible patching for the
telecommunications services to enable simple Moves, Adds & Changes, (MAC’s)
without frequent rewiring of locations
Please particularly note that the complete data system shall be protected from
transmission borne lightning strikes at the point of connection of the incoming IT cable
from the provider.
5.3.2. Structured cabling system
All Vendor products supplied under this tender shall be genuine Vendor products. There
shall be no unapproved or falsely claimed “Vendor Compatible” or “Vendor Alternative”
products.
The communications channel shall be capable of supporting 100Mbps (100BASE-T)
Ethernet.
All copper products in the communications channel shall be capable of supporting the
provision of power to the Data Terminal Equipment via the electrically conductive Media
Dependant Interfaces as specified in the latest IEEE 802.3af “Power over Ethernet”
standard.
All IDC connectors shall be Vendor IDC technology for all systems and subsystems.
5.3.3. Work Area System
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 12/19
Tenderers shall supply and install the wiring or interconnections that connect active
terminal devices to the telecommunication outlets. This includes patch cords, connectors,
faceplates, as well as the work area patch cords (terminal fly leads) needed to make
connections.
5.3.4. Faceplate
The faceplates offered shall have a clear label for application of circuit identification and
the following;
For Cat 5e
A choice of 1, 2, 3, 4, or 12 outlets.
Options for vertical style or horizontal style.
4 port angled faceplates on perimeter trunking or surface skirting ducts.
5.3.5. Telecommunication Outlets (TO)
All copper telecommunication outlets supplied by the tenderer shall be Vendor modular
8-position / 8-contact outlets, accepting standard modular RJ45 plugs
The TO shall be;
Capable of receiving 0.4 to 0.64mm diameter solid wires into insulation
displacement contacts.
Surface or flush mounted, single or dual sockets are required as specified in the
drawings.
Should have the ability to accept a dust cap to prevent dust and dirt getting into the
socket.
Underwriter Laboratories (UL) listed, and comply with CFR47 Part 68.500.
Made from high-impact, flame-retardant, UL94 -V0 rated thermoplastic material.
The TO shall provide Near End Crosstalk (NEXT) performance of >54dB @ 100MHz,
and >46dB @ 100MHz for Cat 5e.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 13/19
The Insulation Displacement Connector (IDC) wiring termination shall have a minimum
of 2 mechanical forces applied to the wire to provide a reliable and stress-free resistant
connection.
The IDC termination must be have a 45 degree angled configuration when connecting
with the cable conductor to reduce the effect of metal fatigue.
The IDC contact element shall be special spring brass with silver plating to increase
conductivity, angularly arranged across the axis of conducting wire to maximize the gas
tight connection. The contact range shall be minimum 5µm silver-plated to ensure
minimum oxidization impact.
The socket offered shall be marked to conform to the T568A wiring scheme in AS/NZS
3080, as a minimum.
The telecommunication outlet shall meet the following electrical performances;
RJ Interface resistance: 20 mΩ
Insulation resistance ≥100 MΩ at 500 Vdc
Contact resistance of 20 mΩ maximum. (1mΩ typical)
Current rating of ≤2A at 20ºC
The telecommunication outlet shall meet the following mechanical performance:
Plug/Jack contact force: >100g minimum per contact using a FCC-approved plug.
Plug retention force: 133 N minimum.
Temperature range: –20ºC to +75ºC
5.3.6. Horizontal Cable System
Category 5e Cabling for 100 Megabit Ethernet
Tenderer shall supply Vendor Category 5e horizontal 4 pair solid cable to connect each
telecommunication outlet (TO) or consolidation point (CP) to the floor distributor (FD).
The type of horizontal cables used shall be 4-pair 100Ω+/- 3% high performance
unshielded twisted pair (UTP) cable for Cat 5e applications.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 14/19
The UTP cable shall be of nominal 0.5 mm diameter bare solid copper conductors
insulated with high density insulation and a PVC sheath. The insulated conductors shall
be twisted into pairs, with pairs balanced for maximum performance and noise reduction.
The 4-pair UTP cable shall be run using a star topology format from the cross-connect at
the floor distributor (FD) on each floor to every individual telecommunication outlet.
The 4-pair UTP cable must exceed AS/NZS 3080:2003 Category 5e requirements. It
must be tested to Class D to ensure performance for any application up to and including
100 Mbps from the floor distributor (FD) to the telecommunications outlet (TO) at the
work area.
All horizontal UTP cable must meet requirement specified for current such as IEEE
802.3, 10/100/1000 BASE T; IEEE 802.5, 4/16/100Mbps; ATM Forum 52/155/622/1200
Mbps, 1 Gigabit Networking.
Each run of cable from the cross-connect at the floor distributor (FD) to the
telecommunication outlet (TO) shall be continuous without any joints or splices.
Consolidation points (CP) are permitted provided Class D channel performance is
maintained.
The length of each individual run of fixed horizontal cable from the floor distributor (FD)
to the telecommunication outlet (TO) shall be based on the distance set out in the tables
and formulas in AS/NZS 3080:2003 plus the appropriate length de-rating for maximum
ambient temperatures above 20ºC. Installed lengths may differ from the designed lengths
as long as they pass testing.
The 4-pair UTP cable should be Underwriter Laboratories (UL) listed as type CM or
CMR.
The 4-pair UTP cable shall meet or exceed the following AS/NZS 3080:2003
requirements specifications for cable;
Impedance at 100MHz: 100 +/- 3%@ 100 MHz
Conductor DC Resistance (Max): 9.38 /100m @ 20oC
DC Resistance Unbalance (Max) 5%
Insulation Resistance (Min): 5000 MΩ /1km @ 20oC
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 15/19
Mutual Capacitance (Typical): 5.6 nF/100m
Characteristics impedance : 100Ω
Worst Case Cable Skew : 45 nsec/100 Meters
5.3.7. Telecommunications Room Cable Terminations
The size, location and provisioning of services and facilities in Telecommunications
Rooms (TR) should be in accordance with AS/NZS 3084.
The TR on the ground floor (unless nominated elsewhere on the drawings) shall contain
the Building Distributor (BD) to terminate the incoming cables from the Service
Provider.
The Telecommunications Room (TR) shall contain rack mounted patch panels, or wall
mounted profil rods or back mount frames to suit either 8 or 25-pair Vendor modules for
termination of the internal horizontal and/or backbone copper cables onto modules and
outlets. The TR must also house the rack mounted or wall mounted
Patch cords shall be provided when patching of voice and/or data circuits is required at
the cross-connections to facilitate Moves, Adds and Changes (MAC’s).
The patch cords supplied shall be able to support the designed application, like 1GBE
applications.
5.3.8. Cross-Connect System
Tenderer shall utilize Patch By Exception for copper cross-connection of termination
modules at the backbone and/or horizontal cross-connect.
The cross-connect system inside Telecommunications Rooms (TR) shall consist of 2
modules per horizontal cable run.
On Module 1, 4-pair positions shall be connected from the top of the module to the
network equipment by a System Tail with the RJ45 plug at the equipment end.
On Module 2, 4-pair positions shall be connected at the top of the module to the
horizontal cabling from the TO.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 16/19
The hard-wired jumper cable shall consist of 4-pair solid cable with sheath (the same
cable as the horizontal 4-pair cable), and this will connect from the 4-pair positions on
the bottom of Module 1 to the 4-pair positions on the bottom of Module 2.
The cross-connect terminations on Category 5e components shall be either;
Vendor modules, fire-retardant, molded plastic UL94 V0 rated, mounted
horizontally for ease of termination, with 8-pair or 25-pair disconnection contacts
for incoming voice and/or data services up to 100Mbps, or
Vendor RJ45 Cat 5e patch-panels for incoming voice and/or data services up to
100Mbps.
Tenderer shall supply appropriate patch cords with factory assembled plug-ends
for mating with the termination modules.
These patch cords are to be used as the “Exception” patching facility during
temporary Moves, Adds and Changes.
Restoration of the original hard wired jumper arrangement shall be by the removal
of the “Exception” patch cords.
When the temporary “Exception” patching arrangements are to be made
permanent, the appropriate modules shall be hard-wired using solid 4-pair fully
sheathed cable, and the “Exception” patch cords shall be removed and stored for
future use.
The type of patch cords shall match the termination modules used.
5.3.9. Termination Module
The termination module shall be able to accommodate over 200 repeated wire insertions
without incurring permanent deformation.
For up to Cat 5e performance, the termination module shall be a Vendor Cat 5e
disconnection module to allow test cords to isolate the cabling system for testing
purposes.
For all modules, the termination shall be able to accommodate 0.4 – 0.64 mm diameter
solid copper conductors and 7/0.2 – 7/0.32 multi-wire stranded conductors.
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 17/19
The IDC contact element shall be set at 45o and made from special spring brass with
silver plating. The wire contact area shall have 5 µm of silver-plating to ensure maximum
reliability.
All components that are to be connected to a carrier’s network must comply with the A-
Tick requirements in accordance with the Telecommunications Labelling Notice.
5.3.10. Copper Patch Panels, Rack And Cabinet-Mounted
The modular outlet patch panel shall be a Vendor panel with 8 pin modular sockets
having a worst pair NEXT loss values for the outlet of >54dB at 100MHz and >46dB at
100MHz.
The patch panel shall be available in 16 or 24 port configurations in one rack unit height
or 48 port in two rack unit height and shall fit into a 19" rack. Rear cable management
shall be a Vendor cable manager either steel or plastic (MasterMinder) to occupy the
same height as the 1 RU patch panel.
The contact plating of the modular jacks shall have a minimum thickness of 1.3µm of
hard gold in accordance with FCC CFR47 Part 68.5, over a minimum thickness of 2.0µm
of nickel. The modular patch panel will have a plug insertion life of Level B reliability to
IEC 60603-7.
Vendor Patch Cord Minders shall be fitted so that there is one patch cord minder for
every 2 x flat patch panels. The front and/or rear vertical rails of the cabinet shall be set
back sufficiently to accommodate the patch cord minders.
When angled patch panels are used, the installation of patch cord minders is not
mandated. However, the rack and/or cabinet must have sufficient space on the sides at the
front to provide adequate room and support to contain the patch cords and their minimum
bending radius.
5.3.11. Rack And Cabinet-Mount
The 19” rack-mounting unit should be either 12 or 24 ports for one rack unit (1RU) and
can be either a fixed position unit or have a slide or swing tray to improve access.
5.3.12. Patch Cords and System Leads
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 18/19
Tenderer shall supply Vendor Cat 5e patch cords and copper System Leads for cross-
connection and/or inteconnection of termination modules, patch panels and network
equipment.
The type of patch cords and system leads shall match the termination module used, ie 8-
pair modules, 25-pair Cat 5e modules or Cat 5e RJ45 patch panel.
Cat 5e RJ45 patch cords shall be factory terminated 4-pair UTP cable with lengths of 1.2,
2.1, 3.0, 4.5, 7.5, and 15 meters.
System Leads shall be supplied and installed to connect the network equipment to the
cross-connect or interconnect modules. The system leads shall have 4-pair conductors
with length and construction (stranded or solid) suited to the installation.
System Leads shall have an RJ45 plug on each end and shall be “cut in half” on site to
achieve the desired lengths from network equipment to cross-connect module. Each
System Lead will produce two (2) system tails (RJ45 plug one end to IDC termination
other end).
5.3.13. Backbone System
The backbone system shall include UTP multi-pair copper cable for voice and 4-pair
copper UTP and/or Fiber optic cable for high-speed data networking in the intra-building
wiring.
The backbone cables shall be run in a star topology, terminated in the Equipment Room
(ER) or Building Distributor (BD) at one end, and in a Floor Distributor (FD) at the other
end.
5.3.14. The UTP copper cables
Shall be marked CM or CMR.
Shall consist of 0.5 mm diameter, twisted pair copper conductor.
The UTP multi-pair cable shall meet the requirements of AS/NZS 3080:2003 and
AS/ACIF S008
5.4. ELEVATOR SERVICES
PROJECT: TAN TAO DEVELOPMENT
SPECIFICATION_ELECTRICAL Page 19/19
The supply, installation and commissioning of the elevators shall be undertaken by
others.
This Contractor, the Electrical Services Contractor, shall separate supplies from the Main
L.V. Switchboard, one to the control panel of each elevator.
PROJECT: TAN TAO DEVELOPMENT
SPECICATION_ELECTRICAL Page 1/7
TECHNICAL DATA
PROJECT: TAN TAO DEVELOPMENT
SPECICATION_ELECTRICAL Page 2/7
ELECTRICAL SERVICES
STT
No.
MÔ TẢ
DESCRIPTION
QUI ĐỊNH
REGULATIONS
ĐỀXUẤT
OFFERED
A LOW VOLTAGE – MAIN SWITCH BOARD
HẠ ÁP - TỦ PHÂN PHỐI ĐIỆN CHÍNH
1 Manufacturer:
Hãng sản xuất Sunlight, Hải Nam, Viet Star, Sáng Tạo
2 Country of Origin:
Nước xuất xứ Việt Nam
3 Standard:
Tiêu chuẩn IEC, EN, AS, BS
4 Type Test:
Lọai kiểm tra TTA, IEC 439-1
5 Quantity
Số lượng
Refer to detail design document
Tham khảo trên bản vẽ thiết kế chi tiết
6 Form of Internal Segregation
Mẫu phân chia bên trong 3B
7 Spare Space:
Khỏang trống dự phòng 30%
B CIRCUIT BREAKER (ACB, MCCB, MCB, CB):
THIẾT BỊ ĐÓNG NGẮT MẠCH
1 Manufacturer:
Hãng sản xuất ABB, Schneider, GE
2 Country of Origin:
Nước xuất xứ
Ý, Pháp , Mỹ
ITALIA,FRANCE, USA
3 Standard:
Tiêu chuẩn IEC, EN, AS, BS
3 Rated Currend
Dòng điện định mức
Refer to detail design document
Tham khảo trên bản vẽ thiết kế chi tiết
4
Rated Short-Circuit Breaking
Current
Định mức dòng điện cắt ngắn
mạch
Refer to detail design document
Tham khảo trên bản vẽ thiết kế chi tiết
C DISTRBUTION BOARDS
TỦ PHÂN PHỐI
PROJECT: TAN TAO DEVELOPMENT
SPECICATION_ELECTRICAL Page 3/7
1 Manufacturer:
Hãng sản xuất Sunlight, Hải Nam, Viet Star, Sáng Tạo
2 Country of Origin:
Nước xuất xứ Việt Nam
3 Standard:
Tiêu chuẩn IEC, EN, AS, BS
4 Type Test:Lọai kiểm tra TTA, IEC 439-1
5 Form of Internal Segregation
Mẫu phân chia bên trong 2B
6 Spare Space:
Khỏang trống dự phòng 30%
D Ổ CẮM, CÔNG TẮC
SOCKET OUTLET, LIGHT SWITCHES
1 Manufacturer:
Hãng sản xuất PANASONIC, AC, CLIPSAL, LEGRAND
2 Country of Origin:
Nước xuất xứ Thái Lan, Malaysia , Pháp
3 Standard:
Tiêu chuẩn IEC 60898,61009,60669; BS 5733
4 Technical data
Thông số kỹ thuật
Refer to detail design document
Tham khảo trên bản vẽ thiết kế chi tiết
E LIGHTING
ĐÈN CHIẾU SÁNG
1 Manufacturer:
Hãng sản xuất Philips, Cooper, Sjlite
2 Hãng sản xuất bóng đèn
Lamp Manufacturer: Philips, Cooper, Mestar, Sjlite
3 Country of Origin:
Nước xuất xứ Thái Lan,Trung Quốc, Malaysia
4 Standard:
Tiêu chuẩn IEC,IEC 60598,61167; EN 12665
5 Technical data
Thông số kỹ thuật
Refer tender drawings, I.D & Landscape
drawings
Tham khảo trên bản vẽ dự thầu & bản vẽ
Nội thất, Landscape
PROJECT: TAN TAO DEVELOPMENT
SPECICATION_ELECTRICAL Page 4/7
F CHỐNG SÉT & NỐI ĐẤT
LIGHTNING PROTECTION & EARTHING SYSTEM
1 Manufacturer:
Hãng sản xuất LPI, SYCOM, Technology
2 Country of Origin:
Nước xuất xứ Úc , Mỹ
3 Standard:
Tiêu chuẩn
IEC, NZS/AS 1768, NF C17-102, IEC
61643
4 Type:
Loại
Refer to detail design document
Tham khảo trên bản vẽ thiết kế chi tiết
G WIRING & ACCESSORIES
DÂY DẪN & PHỤ KIỆN
I CABLE - PVC INSULATED
CÁP - CÁCH ĐIỆN PVC
1 Manufacturer:Hãng sản xuất Taya, Taisin, Taihan-Sacom
2 Country of Origin:
Nước xuất xứ Singapore, Hàn quốc
3 Standard:
Tiêu chuẩn
IEC 60502, IEC 60322-1, TCVN 5935, BS
6346, BS 6004
4 Voltage rate
Định mức điện áp 1KV
5
Max. rate conducttor temperature
in normal use
Nhiệt độ ruột dẫn lớn nhất sử dụng
bình thường
70oC
II CABLE - PVC/PVC INSULATED
CÁP - CÁCH ĐIỆN PVC/PVC
1 Manufacturer:
Hãng sản xuất Taya, Taisin, Taihan-Sacom
2 Country of Origin:
Nước xuất xứ Singapore, Hàn quốc
3 Standard:
Tiêu chuẩn
IEC 60502, IEC 60322-1, TCVN 5935, BS
6346, BS 6004
4 Voltage rate
Định mức điện áp 1KV
PROJECT: TAN TAO DEVELOPMENT
SPECICATION_ELECTRICAL Page 5/7
5
Max. rate conducttor temperature
in normal use
Nhiệt độ ruột dẫn lớn nhất sử dụng
bình thường
70oC
III CÁP - CÁCH ĐIỆN XLPE/PVC
CABLING - XLPE/PVC INSULATED
1 Manufacturer:
Hãng sản xuất Taya, Taisin, Taihan-Sacom
2 Country of Origin:
Nước xuất xứ Singapore, Hàn quốc
3 Standard:
Tiêu chuẩn
IEC 60502, IEC 60322-1, TCVN 5935, BS
6346, BS 6004
4 Voltage rate
Định mức điện áp 1KV
5
Max. rate conducttor temperature
in normal use
Nhiệt độ ruột dẫn lớn nhất sử dụng
bình thường
90oC
IV CABLE - CU/FR INSULATED
CÁP - CÁCH ĐIỆN Cu/FR
1 Manufacturer:
Hãng sản xuất Taya, Taisin, Taihan-Sacom
2 Country of Origin:
Nước xuất xứ Singapore, Hàn quốc
3 Standard:Tiêu chuẩn IEC 60502, IEC 60322-1, TCVN 5935, BS
6346, BS 6004
4 Voltage rate
Định mức điện áp 1KV
5
Max. rate conducttor temperature
in normal use
Nhiệt độ ruột dẫn lớn nhất sử dụng
bình thường
70oC
V CONDUIT
ỐNG LUỒN DÂY ĐIỆN
1 Manufacturer:
Hãng sản xuất AC, WEGA, GS, CLIPSAL
2 Country of Origin:
Nước xuất xứ
Ấn độ, Malaysia
India, Malaysia
PROJECT: TAN TAO DEVELOPMENT
SPECICATION_ELECTRICAL Page 6/7
3 Standard:
Tiêu chuẩn BS EN 50086, IEC 614
4 Thichness (mm)
Độ dày (mm) 1.4 mm-1.6mm
5 OUTSIDE DIAMETER
Đường kính ngoài ∅20, ∅25, ∅32
6 TYPE
Chuẩn loại HEAVY PVC CONDUIT
7 LENGHT ( m/Piece )
Chiều dài ( m/ống ) 2.92 m/ PIECE
VI MÁNG CÁP
CABLE TRAY
1 Manufacturer:
Hãng sản xuất Sáng Tạo, Việt Star, Reetech
2 Country of Origin:
Nước xuất xứ Viet Nam
3 Standard:
Tiêu chuẩn IEC 61537, NEMA VE 1-2002
4 Thichness (mm)
Độ dày (mm) 1.5 -->1,8 mm
5 Standard Length
Chiều dài tiêu chuẩn 2400 mm
VII THANG CÁP
CABLE LADDER
1 Manufacturer:
Hãng sản xuất Sáng Tạo, Việt Star, Reetech
2 Country of Origin:
Nước xuất xứ Viet Nam
3 Standard:
Tiêu chuẩn IEC 61537, NEMA VE 1-2002
4 Thichness (mm)
Độ dày (mm) 1.8 -->2,0 mm
5 Standard LengthChiều dài tiêu
chuẩn 2400 mm
VIII CABLE TRUNKING
HỘP CÁP
PROJECT: TAN TAO DEVELOPMENT
SPECICATION_ELECTRICAL Page 7/7
1 Manufacturer:
Hãng sản xuất Sáng Tạo, Việt Star, Reetech
2 Country of Origin:
Nước xuất xứ Viet Nam
3 Standard:
Tiêu chuẩn IEC 61537, NEMA VE 1-2002
4 Thichness (mm)
Độ dày (mm) 1.2mm -->1,5mm
5 Standard Length
Chiều dài tiêu chuẩn 2400 mm