1 PRODUCCION DE MATERIALCORTE 653,468.89 Meses Cant. EQ.
D8 150.00 M3/HM 9.00 1.86
ZARANDEO 653,468.89 Meses Cant. EQ.EXC. 336 150.00 M3/HM 9.00 1.86
ZARANDA EST. 150.00 M3/HM 9.00 1.86
CARGUIO 653,468.89 Meses Cant. EQ.CF 962 70.00 M3/HM 9.00 3.99
2 CONFORMACION DE MATERIALCONFORMACION 534,763.21 Meses Cant. EQ.
MOTONIVELADORA 140H 329.67 M3/HM 9.00 0.69 RODILLO LISO 329.67 M3/HM 9.00 0.69
CISTERNA AGUA 5000 GLN 329.67 M3/HM 9.00 0.69
3 TRANSPORTE DE MATERIALCORTE 15,321,971.93 Meses Cant. EQ.
CAMION VOLQUETE 15 M3 1,143.48 M3/HM 9.00 57.26
Cant. EQ: Real HM x Mes Costo HM Parcial 2.00 260.00 140.00 655,200.00
Cant. EQ: Real HM x Mes Costo HM Parcial 2.00 260.00 125.45 587,127.27 2.00 260.00 25.00 117,000.00
Cant. EQ: Real HM x Mes Costo HM Parcial 4.00 260.00 84.55 791,345.45
2,150,672.73
Cant. EQ: Real HM x Mes Costo HM Parcial 1.00 260.00 79.55 186,136.36 1.00 260.00 48.18 112,745.45 1.00 260.00 48.41 113,277.27
412,159.09
Cant. EQ: Real HM x Mes Costo HM Parcial 58.00 260.00 59.55 8,081,509.09
8,081,509.09
71.00 10,644,340.91
CD 15,887,075.98
CI 4,766,122.80
T 20,653,198.78
ALCANCE DE PROYECTO
NOMBRE DEL PROYECTO
CONSTRUCCION DE BASE Y SUB BASE DE VÍAS - AGROLMOS S. A.
CLIENTE
AGROLMOS S. A.
UBICACIÓN
OLMOS - LAMBAYEQUE - LAMBAYEQUE
ALCANCE
METAS
* Extracción y producción de materialen cantera pañalá: 653,000.00 m3.
* Transporte de material seleccionado; 534,000.00 m3.
* Conformación y compactación de sub base y base; 534,000.00 m3.
RESTRICCIONES
* El cliente entregará liberada las canteras y el costo por el material es responsabilidad del cliente.
* El cliente garantiza la potencia de la cantera.
* Las pruebas de calidad (densidad de campo), se realizarán cada 2 km.
* El cliente entrega el agua en un punto específico del proyecto.
* La conformación y compactación de la sub base será en capas de 0.30 m y la base en capas de 0.15 m.
HITOS
PRESUPUESTO
Extracción y producción de material en canteras, para construcción de sub base y base de vías con un ancho efectivo de 9.00 m. Considerar sub base un espesor de 0.30 m y la base un espesor de 0.15 m.
* El cliente entregará el terreno a nivel de subrasante con el perfilado y compactado que la norma de calidad requiere. San Martín verificará previo al proceso constructivo de sub base.
CONSTRUCCION DE BASE Y SUB BASE DE VÍAS - AGROLMOS S. A.
GERENCIA DE PROYECTO TRABAJOS PRELIMINARES CALIDAD VIAS OESTE VIAS ESTE MANTENIMIENTO DE VIAS
0.00 270 DIAS 1.00 270 DIAS 2.00 270 DIAS 3.00 270 DIAS 4.00 270 DIAS 5.00 270 DIAS 6.00 270 DIAS
ENTREAGBLES SM MOVILIZACION Y DESMOVILIZACION ESTUDIO DE CANTERAS MATERIAL SUB BASE SUB BASE SUB BASE
0.01 270 DIAS 1.01 270 DIAS 2.01 270 DIAS 3.01 270 DIAS 4.01 270 DIAS 5.01 270 DIAS 6.01 270 DIAS
ENTREGABLES CLIENTE MATERIAL BASE BASE BASE RIEGO DE VÍAS
0.02 270 DIAS 1.02 270 DIAS 2.02 270 DIAS 3.02 270 DIAS 4.02 270 DIAS 5.02 270 DIAS 6.02 270 DIAS
ACCESOS A CANTERAS
1.03 270 DIAS
W B SCONSTRUCCION DE BASE Y SUB BASE DE VÍAS - AGROLMOS S. A.
EXTRACCION Y PRODUCCION DE MATERIAL
MANTENIMIENTO DE VIAS PROCESO CONSTRUCTIVO
CAMPAMENTO, OFICINAS, PATIO DE MAQUINAS, LABORATORIOS
CONTROL DE CALIDAD (DENSIDAD DE CAMPO)
MTO
PROYECTO: CONSTRUCCION DE BASE Y SUB BASE DE VÍAS - AGROLMOS S. A.
CLIENTE: AGROLMOS S. A.
UBICACIÓN: OLMOS - LAMBAYEQUE - LAMBAYEQUE
ITEM DESCRIPCION UNIDAD CANTIDAD
1.00 TRABAJOS PRELIMINARES
1.01 MOVILIZACION Y DESMOVILIZACION GLB 1.00
1.02 CAMPAMENTO, OFICINAS, PATIO DE MAQUINAS, LABORATORIOS GLB 1.00
1.03 ACCESOS A CANTERAS KM 5.00
2.00 CALIDAD
2.01 ESTUDIO DE CANTERAS UND 2.00
2.02 CONTROL DE CALIDAD (DENSIDAD DE CAMPO) UND 54.00
3.00 EXTRACCION Y PRODUCCION DE MATERIAL
3.01 MATERIAL SUB BASE
3.01.01 EXPLOTACION DE MATERIAL EN CANTERA PARA SUB BASE M3 434,568.57
3.01.02 PRODUCCION DE MATERIAL EN CANTERA PARA SUB BASE M3 359,642.95
3.02 MATERIAL BASE
3.02.01 EXPLOTACION DE MATERIAL EN CANTERA PARA BASE M3 218,900.33
3.02.02 PRODUCCION DE MATERIAL EN CANTERA PARA BASE M3 175,120.26
4.00 VIAS OESTE
4.01 SUB BASE
4.01.01 TRANSPORTE DE MATERIAL < 1.00 KM, INCLUYE CARGUIO M3 142,050.11
4.01.02 TRANSPORTE DE MATERIAL > 1.00 KM M3/KM 4,164,482.87
4.01.03 CONFORMACION Y COMPACTACION DE SUBBASE E=0.30 M. M2 371,372.83
4.02 BASE
4.02.01 TRANSPORTE DE MATERIAL < 1.00 KM, INCLUYE CARGUIO M3 69,168.19
4.02.02 TRANSPORTE DE MATERIAL > 1.00 KM M3/KM 2,027,803.75
4.02.03 CONFORMACION Y COMPACTACION DE BASE E=0.15 M. M2 348,162.03
5.00 VIAS ESTE
5.01 SUB BASE
5.01.01 TRANSPORTE DE MATERIAL < 1.00 KM, INCLUYE CARGUIO M3 217,592.84
5.01.02 TRANSPORTE DE MATERIAL > 1.00 KM M3/KM 6,139,964.19
5.01.03 CONFORMACION Y COMPACTACION DE SUBBASE E=0.30 M. M2 568,870.18
5.02 BASE
5.02.01 TRANSPORTE DE MATERIAL < 1.00 KM, INCLUYE CARGUIO M3 105,952.07
5.02.02 TRANSPORTE DE MATERIAL > 1.00 KM M3/KM 2,989,721.12
5.02.03 CONFORMACION Y COMPACTACION DE BASE E=0.15 M. M2 533,315.79
6.00 MANTENIMIENTO DE VIAS
6.01 MANTENIMIENTO DE VIAS PROCESO CONSTRUCTIVO KM 100.54
6.02 RIEGO DE VÍAS MES 9.00
METRADOS DE OBRA
PROYECTO: CONSTRUCCION DE BASE Y SUB BASE DE VÍAS - AGROLMOS S. A.
CLIENTE: AGROLMOS S. A.
UBICACIÓN: OLMOS - LAMBAYEQUE - LAMBAYEQUE
1.00 TRABAJOS PRELIMINARES
1.01 MOVILIZACION Y DESMOVILIZACION
Item Descripción Total
1 Movilización y desmovilización de equipo 1.00
TOTAL GLB 1.00
1.02 CAMPAMENTO, OFICINAS, PATIO DE MAQUINAS, LABORATORIOS
Item Descripción Total
1 Campamento, oficinas, laboratorio de suelos 1.00
TOTAL GLB 1.00
1.03 ACCESOS A CANTERAS
Item Descripción Total
1 Habilitación de accesos a canteras 5.00
TOTAL KM 5.00
2.00 CALIDAD
2.01 ESTUDIO DE CANTERAS
Item Descripción Total
1 Estudio de Canteras Pivot 34 1.00
2 Estudio de Cantera Pañalá 1.00
TOTAL UND 2.00
2.02 CONTROL DE CALIDAD (DENSIDAD DE CAMPO)
Item Longitud (Km) Total
1 105.00 1.00 2.00 53.50
TOTAL UND 54.00
3.00 EXTRACCION Y PRODUCCION DE MATERIAL
3.01 MATERIAL SUB BASE
3.01.01 EXPLOTACION DE MATERIAL EN CANTERA PARA SUB BASE
Item VíaProgresivas
Longitud Area VolumenInicio Final
FRENTE OESTE
Control de Calidad
1 ensayo cada 2 Km
% Comp. y % Desp. Prod.
METRADOS DE OBRA
PROYECTO: CONSTRUCCION DE BASE Y SUB BASE DE VÍAS - AGROLMOS S. A.
CLIENTE: AGROLMOS S. A.
UBICACIÓN: OLMOS - LAMBAYEQUE - LAMBAYEQUE
1 K1 00+000 08+813.78 8,813.78 3.06 45% 39,106.74
2 K2 00+000 08+655.64 8,655.64 3.06 45% 38,405.07
3 K3 00+000 08+655.64 8,655.64 3.06 45% 38,405.07
4 K4 00+000 03+917.73 3,917.73 3.06 45% 17,382.97
5 R1 00+000 02+153.72 2,153.72 3.06 45% 9,556.06
6 R2 00+000 06+488.16 6,488.16 3.06 45% 28,787.97
SUB TOTAL M3 171,643.88
FRENTE ESTE
1 K5 00+000 10+984.62 10,984.62 3.06 45% 48,738.76
2 K6 00+000 10+838.02 10,838.02 3.06 45% 48,088.29
3 K7 00+000 09+984.80 9,984.80 3.06 45% 44,302.56
4 K8 00+000 09+984.80 9,984.80 3.06 45% 44,302.56
5 K9 00+000 07+364.74 7,364.74 3.06 45% 32,677.35
6 R3 00+000 06+359.00 6,359.00 3.06 45% 28,214.88
7 R4 00+000 03+388.16 3,388.16 3.06 45% 15,033.27
8 R5 00+000 00+353.17 353.17 3.06 45% 1,567.02
SUB TOTAL M3 262,924.68
TOTAL M3 434,568.57
NOTA: Se cionsidera un % de compactación de 20% y % de desperdicio en el proceso de producción de cantera de 25%.
3.01.02 PRODUCCION DE MATERIAL EN CANTERA PARA SUB BASE
Item VíaProgresivas
Longitud Area VolumenInicio Final
FRENTE OESTE
1 K1 00+000 08+813.78 8,813.78 3.06 20% 32,364.20
2 K2 00+000 08+655.64 8,655.64 3.06 20% 31,783.51
3 K3 00+000 08+655.64 8,655.64 3.06 20% 31,783.51
4 K4 00+000 03+917.73 3,917.73 3.06 20% 14,385.90
5 R1 00+000 02+153.72 2,153.72 3.06 20% 7,908.46
6 R2 00+000 06+488.16 6,488.16 3.06 20% 23,824.52
SUB TOTAL M3 142,050.11
FRENTE ESTE
1 K5 00+000 10+984.62 10,984.62 3.06 20% 40,335.52
2 K6 00+000 10+838.02 10,838.02 3.06 20% 39,797.21
3 K7 00+000 09+984.80 9,984.80 3.06 20% 36,664.19
4 K8 00+000 09+984.80 9,984.80 3.06 20% 36,664.19
5 K9 00+000 07+364.74 7,364.74 3.06 20% 27,043.33
6 R3 00+000 06+359.00 6,359.00 3.06 20% 23,350.25
7 R4 00+000 03+388.16 3,388.16 3.06 20% 12,441.32
8 R5 00+000 00+353.17 353.17 3.06 20% 1,296.84
SUB TOTAL M3 217,592.84
TOTAL M3 359,642.95
NOTA: Se cionsidera un % de compactación de 20%
% Comp. y % Desp. Prod.
METRADOS DE OBRA
PROYECTO: CONSTRUCCION DE BASE Y SUB BASE DE VÍAS - AGROLMOS S. A.
CLIENTE: AGROLMOS S. A.
UBICACIÓN: OLMOS - LAMBAYEQUE - LAMBAYEQUE
3.02 MATERIAL BASE
3.02.01 EXPLOTACION DE MATERIAL EN CANTERA PARA BASE
Item VíaProgresivas
Longitud Area VolumenInicio Final
FRENTE OESTE
1 K1 00+000 08+813.78 8,813.78 1.49 50% 19,698.80
2 K2 00+000 08+655.64 8,655.64 1.49 50% 19,345.36
3 K3 00+000 08+655.64 8,655.64 1.49 50% 19,345.36
4 K4 00+000 03+917.73 3,917.73 1.49 50% 8,756.13
5 R1 00+000 02+153.72 2,153.72 1.49 50% 4,813.56
6 R2 00+000 06+488.16 6,488.16 1.49 50% 14,501.04
SUB TOTAL M3 86,460.24
FRENTE ESTE
1 K5 00+000 10+984.62 10,984.62 1.49 50% 24,550.63
2 K6 00+000 10+838.02 10,838.02 1.49 50% 24,222.97
3 K7 00+000 09+984.80 9,984.80 1.49 50% 22,316.03
4 K8 00+000 09+984.80 9,984.80 1.49 50% 22,316.03
5 K9 00+000 07+364.74 7,364.74 1.49 50% 16,460.19
6 R3 00+000 06+359.00 6,359.00 1.49 50% 14,212.37
7 R4 00+000 03+388.16 3,388.16 1.49 50% 7,572.54
8 R5 00+000 00+353.17 353.17 1.49 50% 789.33
SUB TOTAL M3 132,440.09
TOTAL M3 218,900.33
NOTA: Se cionsidera un % de compactación de 20% y % de desperdicio en el proceso de producción de cantera de 30%.
3.02.02 PRODUCCION DE MATERIAL EN CANTERA PARA BASE
Item VíaProgresivas
Longitud Area VolumenInicio Final
FRENTE OESTE
1 K1 00+000 08+813.78 8,813.78 1.49 20% 15,759.04
2 K2 00+000 08+655.64 8,655.64 1.49 20% 15,476.28
3 K3 00+000 08+655.64 8,655.64 1.49 20% 15,476.28
4 K4 00+000 03+917.73 3,917.73 1.49 20% 7,004.90
5 R1 00+000 02+153.72 2,153.72 1.49 20% 3,850.85
6 R2 00+000 06+488.16 6,488.16 1.49 20% 11,600.83
SUB TOTAL M3 69,168.19
FRENTE ESTE
1 K5 00+000 10+984.62 10,984.62 1.49 20% 19,640.50
2 K6 00+000 10+838.02 10,838.02 1.49 20% 19,378.38
3 K7 00+000 09+984.80 9,984.80 1.49 20% 17,852.82
4 K8 00+000 09+984.80 9,984.80 1.49 20% 17,852.82
5 K9 00+000 07+364.74 7,364.74 1.49 20% 13,168.16
6 R3 00+000 06+359.00 6,359.00 1.49 20% 11,369.89
% Comp. y % Desp. Prod.
% Comp. y % Desp. Prod.
METRADOS DE OBRA
PROYECTO: CONSTRUCCION DE BASE Y SUB BASE DE VÍAS - AGROLMOS S. A.
CLIENTE: AGROLMOS S. A.
UBICACIÓN: OLMOS - LAMBAYEQUE - LAMBAYEQUE
7 R4 00+000 03+388.16 3,388.16 1.49 20% 6,058.03
8 R5 00+000 00+353.17 353.17 1.49 20% 631.47
SUB TOTAL M3 105,952.07
TOTAL M3 175,120.26
NOTA: Se cionsidera un % de compactación de 20%.
4.00 VIAS OESTE
4.01 SUB BASE
4.01.01 TRANSPORTE DE MATERIAL < 1.00 KM, INCLUYE CARGUIO
Item Vía Volumen
FRENTE OESTE
1 K1 32,364.20
2 K2 31,783.51
3 K3 31,783.51
4 K4 14,385.90
5 R1 7,908.46
6 R2 23,824.52
TOTAL M3 142,050.11
4.01.02 TRANSPORTE DE MATERIAL > 1.00 KM
Item Vía Longitud Vías Distancia Media
FRENTE OESTE
1 K1 8.81 23.00 27.41 32,364.20 887,002.07
2 K2 8.66 25.20 29.53 31,783.51 938,497.76
3 K3 8.66 27.40 31.73 31,783.51 1,008,421.49
4 K4 3.92 29.60 31.56 14,385.90 454,002.82
5 R1 2.15 30.70 31.78 7,908.46 251,306.02
6 R2 6.49 23.00 26.24 23,824.52 625,252.70
TOTAL M3/KM 4,164,482.87
4.01.03 CONFORMACION Y COMPACTACION DE SUBBASE E=0.30 M.
Item Vía Ancho Capa 1 Ancho Capa 2 Area
FRENTE OESTE
1 K1 8,813.78 9.60 0.00 84,612.29
2 K2 8,655.64 9.60 0.00 83,094.14
3 K3 8,655.64 9.60 0.00 83,094.14
4 K4 3,917.73 9.60 0.00 37,610.21
5 R1 2,153.72 9.60 0.00 20,675.71
6 R2 6,488.16 9.60 0.00 62,286.34
Longitud Tramo (Km)
Volumen / Tramo
Volumen / Distancia
Longitud Tramo (m)
METRADOS DE OBRA
PROYECTO: CONSTRUCCION DE BASE Y SUB BASE DE VÍAS - AGROLMOS S. A.
CLIENTE: AGROLMOS S. A.
UBICACIÓN: OLMOS - LAMBAYEQUE - LAMBAYEQUE
TOTAL M2 371,372.83
4.02 BASE
4.02.01 TRANSPORTE DE MATERIAL < 1.00 KM, INCLUYE CARGUIO
Item Vía Volumen
FRENTE OESTE
1 K1 15,759.04
2 K2 15,476.28
3 K3 15,476.28
4 K4 7,004.90
5 R1 3,850.85
6 R2 11,600.83
TOTAL M3 69,168.19
4.02.02 TRANSPORTE DE MATERIAL > 1.00 KM
Item Vía Longitud Vías Distancia Media
FRENTE OESTE
1 K1 8.81 23.00 27.41 15,759.04 431,906.24
2 K2 8.66 25.20 29.53 15,476.28 456,980.94
3 K3 8.66 27.40 31.73 15,476.28 491,028.76
4 K4 3.92 29.60 31.56 7,004.90 221,066.73
5 R1 2.15 30.70 31.78 3,850.85 122,367.96
6 R2 6.49 23.00 26.24 11,600.83 304,453.11
TOTAL M3/KM 2,027,803.75
4.02.03 CONFORMACION Y COMPACTACION DE BASE E=0.15 M.
Item Vía Ancho Capa Area
FRENTE OESTE
1 K1 8,813.78 9.00 79,324.02
2 K2 8,655.64 9.00 77,900.76
3 K3 8,655.64 9.00 77,900.76
4 K4 3,917.73 9.00 35,259.57
5 R1 2,153.72 9.00 19,383.48
6 R2 6,488.16 9.00 58,393.44
TOTAL M2 348,162.03
5.00 VIAS ESTE
5.01 SUB BASE
5.01.01 TRANSPORTE DE MATERIAL < 1.00 KM, INCLUYE CARGUIO
Longitud Tramo (Km)
Volumen / Tramo
Volumen / Distancia
Longitud Tramo (m)
METRADOS DE OBRA
PROYECTO: CONSTRUCCION DE BASE Y SUB BASE DE VÍAS - AGROLMOS S. A.
CLIENTE: AGROLMOS S. A.
UBICACIÓN: OLMOS - LAMBAYEQUE - LAMBAYEQUE
Item Vía Volumen
FRENTE ESTE
1 K5 40,335.52
2 K6 39,797.21
3 K7 36,664.19
4 K8 36,664.19
5 K9 27,043.33
6 R3 23,350.25
7 R4 12,441.32
8 R5 1,296.84
TOTAL M3 217,592.84
5.01.02 TRANSPORTE DE MATERIAL > 1.00 KM
Item Vía Longitud Vías Distancia Media
FRENTE ESTE
1 K5 10.98 29.60 35.09 40,335.52 1,415,466.73
2 K6 10.84 27.40 32.82 39,797.21 1,306,105.01
3 K7 9.98 25.20 30.19 36,664.19 1,106,979.76
4 K8 9.98 23.00 27.99 36,664.19 1,026,318.55
5 K9 7.36 7.00 10.68 27,043.33 288,886.81
6 R3 6.36 24.10 27.28 23,350.25 636,983.09
7 R4 3.39 23.20 24.89 12,441.32 309,715.30
8 R5 0.35 38.00 38.18 1,296.84 49,508.93
TOTAL M3/KM 6,139,964.19
5.01.03 CONFORMACION Y COMPACTACION DE SUBBASE E=0.30 M.
Item Vía Ancho Capa 1 Ancho Capa 2 Area
FRENTE ESTE
1 K5 10,984.62 9.60 0.00 105,452.35
2 K6 10,838.02 9.60 0.00 104,044.99
3 K7 9,984.80 9.60 0.00 95,854.08
4 K8 9,984.80 9.60 0.00 95,854.08
5 K9 7,364.74 9.60 0.00 70,701.50
6 R3 6,359.00 9.60 0.00 61,046.40
7 R4 3,388.16 9.60 0.00 32,526.34
8 R5 353.17 9.60 0.00 3,390.43
TOTAL M2 568,870.18
5.02 BASE
Longitud Tramo (Km)
Volumen / Tramo
Volumen / Distancia
Longitud Tramo (m)
METRADOS DE OBRA
PROYECTO: CONSTRUCCION DE BASE Y SUB BASE DE VÍAS - AGROLMOS S. A.
CLIENTE: AGROLMOS S. A.
UBICACIÓN: OLMOS - LAMBAYEQUE - LAMBAYEQUE
5.02.01 TRANSPORTE DE MATERIAL < 1.00 KM, INCLUYE CARGUIO
Item Vía Volumen
FRENTE ESTE
1 K5 19,640.50
2 K6 19,378.38
3 K7 17,852.82
4 K8 17,852.82
5 K9 13,168.16
6 R3 11,369.89
7 R4 6,058.03
8 R5 631.47
TOTAL M3 105,952.07
5.02.02 TRANSPORTE DE MATERIAL > 1.00 KM
Item Vía Longitud Vías Distancia Media
FRENTE ESTE
1 K5 10.98 29.60 35.09 19,640.50 689,230.53
2 K6 10.84 27.40 32.82 19,378.38 635,979.24
3 K7 9.98 25.20 30.19 17,852.82 539,019.56
4 K8 9.98 23.00 27.99 17,852.82 499,743.35
5 K9 7.36 7.00 10.68 13,168.16 140,667.11
6 R3 6.36 24.10 27.28 11,369.89 310,164.97
7 R4 3.39 23.20 24.89 6,058.03 150,809.09
8 R5 0.35 38.00 38.18 631.47 24,107.29
TOTAL M3/KM 2,989,721.12
5.02.03 CONFORMACION Y COMPACTACION DE BASE E=0.15 M.
Item Vía Ancho Capa Area
FRENTE ESTE
1 K5 10,984.62 9.00 98,861.58
2 K6 10,838.02 9.00 97,542.18
3 K7 9,984.80 9.00 89,863.20
4 K8 9,984.80 9.00 89,863.20
5 K9 7,364.74 9.00 66,282.66
6 R3 6,359.00 9.00 57,231.00
7 R4 3,388.16 9.00 30,493.44
8 R5 353.17 9.00 3,178.53
TOTAL M2 533,315.79
Longitud Tramo (Km)
Volumen / Tramo
Volumen / Distancia
Longitud Tramo (m)
METRADOS DE OBRA
PROYECTO: CONSTRUCCION DE BASE Y SUB BASE DE VÍAS - AGROLMOS S. A.
CLIENTE: AGROLMOS S. A.
UBICACIÓN: OLMOS - LAMBAYEQUE - LAMBAYEQUE
6.00 MANTENIMIENTO DE VIAS
6.01 MANTENIMIENTO DE VIAS PROCESO CONSTRUCTIVO
Item Vía Longitud Total
FRENTE OESTE
1 K1 8.81 8.81
2 K2 8.66 8.66
3 K3 8.66 8.66
4 K4 3.92 3.92
5 R1 2.15 2.15
6 R2 6.49 6.49
FRENTE ESTE
1 K5 10.98 10.98
2 K6 10.84 10.84
3 K7 9.98 9.98
4 K8 9.98 9.98
5 K9 7.36 7.36
6 R3 6.36 6.36
7 R4 3.39 3.39
8 R5 0.35 0.35
OTROS
1 C. Pañalá 2.60 2.60
TOTAL KM 100.54
6.02 RIEGO DE VÍAS
Item Descripción Total
1 Movilización y desmovilización de equipo 9.00
TOTAL MES 9.00
ANALISIS DE PRECIOS UNITARIOS
PROYECTO: CONSTRUCCION DE BASE Y SUB BASE DE VÍAS - AGROLMOS S. A. CLIENTE: AGROLMOS S. A. UBICACIÓN: OLMOS - LAMBAYEQUE - LAMBAYEQUE
Partida 1.01 MOVILIZACION Y DESMOVILIZACION
Rendimiento GLB 0.20 Costo Unitario $ 298,000.00 Descripcion de recurso Unidad Cuadrilla Cantidad Precio Parcial
Subcontratos 298,000.00
MOVILIZACION DE EQUIPOS L AMARILLA GLB 40.0000 3,200.00 128,000.00
MOVILIZACION DE VOLQUETES GLB 30.0000 700.00 21,000.00
DESMOVILIZACION DE EQUIPOS L AMARILLA GLB 40.0000 3,200.00 128,000.00
DESMOVILIZACION DE VOLQUETES GLB 30.0000 700.00 21,000.00
Materiales -
-
Equipos -
-
-
-
-
Partida 1.02 CAMPAMENTO, OFICINAS, PATIO DE MAQUINAS, LABORATORIOS
Rendimiento GLB 0.20 Costo Unitario $ 591,666.67 Descripcion de recurso Unidad Cuadrilla Cantidad Precio Parcial
Subcontratos 591,666.67
CAMPAMENTO GLB 1.0000 277,777.78 277,777.78
OFICINAS GLB 1.0000 111,111.11 111,111.11
LABORATORIOS GLB 1.0000 21,111.11 21,111.11
PATIO DE MAQUINAS - MANTENIMIENTO GLB 1.0000 15,000.00 15,000.00
TRATAMIENTPO DE AGUAS RESIDUALES GLB 1.0000 166,666.67 166,666.67
Materiales -
-
Equipos -
-
-
-
Partida 1.03 ACCESOS A CANTERAS
Rendimiento KM 0.40 Costo Unitario $ 14,438.10 Descripcion de recurso Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra 3,519.40
CAPATAZ HH 1.00 20.0000 11.53 230.60
OPERARIO HH - 0.0000 - -
OFICIAL HH 2.00 40.0000 8.98 359.20
AYUDANTE (PISO) HH 4.00 80.0000 6.78 542.40
AYUDANTE (CUADRADOR VIGIA) HH 4.00 80.0000 6.78 542.40
OPERADOR DE EQUIPO PESADO HH 8.00 160.0000 11.53 1,844.80
Materiales -
-
Equipos 10,918.70
HERRAMIENTAS MANUALES %MO 5% 3,519.40 175.97
TRACTOR D8 HM 1.00 20.0000 140.00 2,800.00
MOTONIVELADORA 140 H HM 1.00 20.0000 77.50 1,550.00
RODILLO LISO HM 1.00 20.0000 47.18 943.64
CARGADOR FRONTAL HM 1.00 20.0000 91.73 1,834.55
ANALISIS DE PRECIOS UNITARIOS
PROYECTO: CONSTRUCCION DE BASE Y SUB BASE DE VÍAS - AGROLMOS S. A. CLIENTE: AGROLMOS S. A. UBICACIÓN: OLMOS - LAMBAYEQUE - LAMBAYEQUECAMION VOLQUETE HM 4.00 80.0000 45.18 3,614.55
Partida 2.01 ESTUDIO DE CANTERAS
Rendimiento UND 0.20 Costo Unitario $ 5,500.00 Descripcion de recurso Unidad Cuadrilla Cantidad Precio Parcial
Subcontratos
ESTUDIO DE CANTERAS GLB 1.0000 5,500.00 5,500.00
-
-
-
Materiales -
-
Equipos -
-
-
-
-
-
-
Partida 2.02 CONTROL DE CALIDAD (DENSIDAD DE CAMPO)
Rendimiento UND 4.00 Costo Unitario $ 610.00 Descripcion de recurso Unidad Cuadrilla Cantidad Precio Parcial
Subcontratos
DENSIDAD DE CAMPO GLB 1.0000 610.00 610.00
-
-
-
Materiales -
-
Equipos -
HERRAMIENTAS MANUALES %MO 5% - -
-
-
-
-
-
Partida 3.01.01 EXPLOTACION DE MATERIAL EN CANTERA PARA SUB BASE
Rendimiento M3 2,160.00 Costo Unitario $ 1.93 Descripcion de recurso Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra 0.35
CAPATAZ HH 1.00 0.0037 11.53 0.04
OPERARIO HH - 0.0000 10.10 -
OFICIAL (CONTROLADOR) HH 1.00 0.0037 8.98 0.03
AYUDANTE (PISO) HH 3.00 0.0111 6.78 0.08
AYUDANTE (CUADRADOR VIGIA) HH 3.00 0.0111 6.78 0.08
OPERADOR DE EQUIPO PESADO HH 3.00 0.0111 11.53 0.13
ANALISIS DE PRECIOS UNITARIOS
PROYECTO: CONSTRUCCION DE BASE Y SUB BASE DE VÍAS - AGROLMOS S. A. CLIENTE: AGROLMOS S. A. UBICACIÓN: OLMOS - LAMBAYEQUE - LAMBAYEQUE
Materiales -
-
Equipos 1.57
HERRAMIENTAS MANUALES %MO 5% 0.35 0.02
TRACTOR D8 HM 3.00 0.0111 140.00 1.56
-
-
-
-
Partida 3.01.02 PRODUCCION DE MATERIAL EN CANTERA PARA SUB BASE
Rendimiento M3 2,880.00 Costo Unitario $ 3.72 Descripcion de recurso Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra 0.27
CAPATAZ HH 1.00 0.0028 11.53 0.03
OPERARIO HH - 0.0000 - -
OFICIAL (CONTROLADOR) HH 1.00 0.0028 8.98 0.02
AYUDANTE (PISO) HH 4.00 0.0111 6.78 0.08
AYUDANTE (CUADRADOR VIGIA) HH 4.00 0.0111 6.78 0.08
OPERADOR DE EQUIPO PESADO HH 2.00 0.0056 11.53 0.06
Materiales -
-
Equipos 3.45
HERRAMIENTAS MANUALES %MO 5% 0.27 0.01
EXCAVADORA 336 HM 4.00 0.0111 113.45 1.26
ZARANDA ESTATICA HM 4.00 0.0111 12.00 0.13
CARGADOR FRONTAL 966 HM 8.00 0.0222 91.73 2.04
-
-
Partida 3.02.01 EXPLOTACION DE MATERIAL EN CANTERA PARA BASE
Rendimiento M3 1,440.00 Costo Unitario $ 1.97 Descripcion de recurso Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra 0.39
CAPATAZ HH 1.00 0.0056 11.53 0.06
OPERARIO HH - 0.0000 - -
OFICIAL (CONTROLADOR) HH 1.00 0.0056 8.98 0.05
AYUDANTE (PISO) HH 2.00 0.0111 6.78 0.08
AYUDANTE (CUADRADOR VIGIA) HH 2.00 0.0111 6.78 0.08
OPERADOR DE EQUIPO PESADO HH 2.00 0.0111 11.53 0.13
Materiales -
-
Equipos 1.58
HERRAMIENTAS MANUALES %MO 5% 0.39 0.02
TRACTOR D8 HM 2.00 0.0111 140.00 1.56
-
-
-
-
Partida 3.02.02 PRODUCCION DE MATERIAL EN CANTERA PARA BASE
ANALISIS DE PRECIOS UNITARIOS
PROYECTO: CONSTRUCCION DE BASE Y SUB BASE DE VÍAS - AGROLMOS S. A. CLIENTE: AGROLMOS S. A. UBICACIÓN: OLMOS - LAMBAYEQUE - LAMBAYEQUE
Rendimiento M3 1,120.00 Costo Unitario $ 5.29 Descripcion de recurso Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra 0.83
CAPATAZ HH 1.00 0.0071 11.53 0.08
OPERARIO HH - 0.0000 - -
OFICIAL (CONTROLADOR) HH 1.00 0.0071 8.98 0.06
AYUDANTE (PISO) HH 2.00 0.0143 6.78 0.10
AYUDANTE (CUADRADOR VIGIA) HH 2.00 0.0143 6.78 0.10
OPERADOR DE EQUIPO PESADO HH 6.00 0.0429 11.53 0.49
Materiales -
-
Equipos 4.45
HERRAMIENTAS MANUALES %MO 5% 0.83 0.04
EXCAVADORA 336 HM 2.00 0.0143 113.45 1.62
ZARANDA ESTATICA HM 2.00 0.0143 12.00 0.17
CARGADOR FRONTAL 966 HM 4.00 0.0286 91.73 2.62
-
-
Partida 4.01.01 TRANSPORTE DE MATERIAL < 1.00 KM, INCLUYE CARGUIO
Rendimiento M3 801.37 Costo Unitario $ 2.81 Descripcion de recurso Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra 0.73
CAPATAZ HH 1.00 0.0100 11.53 0.12
OPERARIO HH - 0.0000 - -
OFICIAL (CONTROLADOR) HH 1.00 0.0100 8.98 0.09
AYUDANTE (PISO) HH - 0.0000 6.78 -
AYUDANTE (CUADRADOR VIGIA) HH 1.00 0.0100 6.78 0.07
OPERADOR DE EQUIPO PESADO HH 4.00 0.0399 11.53 0.46
Materiales -
-
Equipos 2.08
HERRAMIENTAS MANUALES %MO 5% 0.73 0.04
CARGADOR FRONTAL 966 HM 1.00 0.0100 91.73 0.92
CAMION VOLQUETE DE 15 M3 HM 2.50 0.0250 45.18 1.13
-
-
-
Partida 4.01.02 TRANSPORTE DE MATERIAL > 1.00 KM
Rendimiento M3/KM 20,661.15 Costo Unitario $ 0.47 Descripcion de recurso Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra 0.11
CAPATAZ HH 1.00 0.0004 11.53 0.00
OPERARIO HH - 0.0000 - -
OFICIAL (CONTROLADOR) HH 2.00 0.0008 8.98 0.01
AYUDANTE (PISO) HH - 0.0000 6.78 -
AYUDANTE (CUADRADOR VIGIA) HH 5.00 0.0019 6.78 0.01
OPERADOR DE EQUIPO PESADO HH 20.00 0.0077 11.53 0.09
Materiales -
-
Equipos 0.36
ANALISIS DE PRECIOS UNITARIOS
PROYECTO: CONSTRUCCION DE BASE Y SUB BASE DE VÍAS - AGROLMOS S. A. CLIENTE: AGROLMOS S. A. UBICACIÓN: OLMOS - LAMBAYEQUE - LAMBAYEQUEHERRAMIENTAS MANUALES %MO 5% 0.11 0.01
CAMION VOLQUETE DE 15 M3 HM 20.00 0.0077 45.18 0.35
-
-
-
-
Partida 4.01.03 CONFORMACION Y COMPACTACION DE SUBBASE E=0.30 M.
Rendimiento M2 1,714.29 Costo Unitario $ 2.83 Descripcion de recurso Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra 1.18
CAPATAZ HH 2.00 0.0093 11.53 0.11
OPERARIO HH 2.00 0.0093 10.10 0.09
OFICIAL (CONTROLADOR) HH 2.00 0.0093 8.98 0.08
AYUDANTE (PISO) HH 12.00 0.0560 6.78 0.38
AYUDANTE (CUADRADOR VIGIA) HH 6.00 0.0280 6.78 0.19
OPERADOR DE EQUIPO PESADO HH 6.00 0.0280 11.53 0.32
Materiales -
AGUA M3 0.02 - -
-
Equipos 1.65
HERRAMIENTAS MANUALES %MO 5% 1.18 0.06
MOTONIVELADORA 140 H HM 2.00 0.0093 77.50 0.72
RODILLO LISO HM 2.00 0.0093 47.18 0.44
CISTERNA DE AGUA HM 2.00 0.0093 45.91 0.43
-
Partida 4.02.01 TRANSPORTE DE MATERIAL < 1.00 KM, INCLUYE CARGUIO
Rendimiento M3 801.37 Costo Unitario $ 2.81 Descripcion de recurso Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra 0.73
CAPATAZ HH 1.00 0.0100 11.53 0.12
OPERARIO HH - 0.0000 10.10 -
OFICIAL (CONTROLADOR) HH 1.00 0.0100 8.98 0.09
AYUDANTE (PISO) HH - 0.0000 6.78 -
AYUDANTE (CUADRADOR VIGIA) HH 1.00 0.0100 6.78 0.07
OPERADOR DE EQUIPO PESADO HH 4.00 0.0399 11.53 0.46
Materiales -
-
Equipos 2.08
HERRAMIENTAS MANUALES %MO 5% 0.73 0.04
CARGADOR FRONTAL 966 HM 1.00 0.0100 91.73 0.92
CAMION VOLQUETE DE 15 M3 HM 2.50 0.0250 45.18 1.13
-
-
-
Partida 4.02.02 TRANSPORTE DE MATERIAL > 1.00 KM
Rendimiento M3/KM 14,462.80 Costo Unitario $ 0.47 Descripcion de recurso Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra 0.12
CAPATAZ HH 1.00 0.0006 11.53 0.01
ANALISIS DE PRECIOS UNITARIOS
PROYECTO: CONSTRUCCION DE BASE Y SUB BASE DE VÍAS - AGROLMOS S. A. CLIENTE: AGROLMOS S. A. UBICACIÓN: OLMOS - LAMBAYEQUE - LAMBAYEQUEOPERARIO HH - 0.0000 10.10 -
OFICIAL (CONTROLADOR) HH 1.00 0.0006 8.98 0.00
AYUDANTE (PISO) HH - 0.0000 6.78 -
AYUDANTE (CUADRADOR VIGIA) HH 4.00 0.0022 6.78 0.02
OPERADOR DE EQUIPO PESADO HH 14.00 0.0077 11.53 0.09
Materiales -
-
Equipos 0.36
HERRAMIENTAS MANUALES %MO 5% 0.12 0.01
CAMION VOLQUETE DE 15 M3 HM 14.00 0.0077 45.18 0.35
-
-
-
-
Partida 4.02.03 CONFORMACION Y COMPACTACION DE BASE E=0.15 M.
Rendimiento M2 2,400.00 Costo Unitario $ 2.02 Descripcion de recurso Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra 0.84
CAPATAZ HH 2.00 0.0067 11.53 0.08
OPERARIO HH 2.00 0.0067 10.10 0.07
OFICIAL (CONTROLADOR) HH 2.00 0.0067 8.98 0.06
AYUDANTE (PISO) HH 12.00 0.0400 6.78 0.27
AYUDANTE (CUADRADOR VIGIA) HH 6.00 0.0200 6.78 0.14
OPERADOR DE EQUIPO PESADO HH 6.00 0.0200 11.53 0.23
Materiales -
AGUA M3 0.01 - -
-
Equipos 1.18
HERRAMIENTAS MANUALES %MO 5% 0.84 0.04
MOTONIVELADORA 140 H HM 2.00 0.0067 77.50 0.52
RODILLO LISO HM 2.00 0.0067 47.18 0.31
CISTERNA DE AGUA HM 2.00 0.0067 45.91 0.31
-
Partida 5.01.01 TRANSPORTE DE MATERIAL < 1.00 KM, INCLUYE CARGUIO
Rendimiento M3 801.37 Costo Unitario $ 2.81 Descripcion de recurso Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra 0.73
CAPATAZ HH 1.00 0.0100 11.53 0.12
OPERARIO HH - 0.0000 10.10 -
OFICIAL (CONTROLADOR) HH 1.00 0.0100 8.98 0.09
AYUDANTE (PISO) HH - 0.0000 6.78 -
AYUDANTE (CUADRADOR VIGIA) HH 1.00 0.0100 6.78 0.07
OPERADOR DE EQUIPO PESADO HH 4.00 0.0399 11.53 0.46
Materiales -
-
Equipos 2.08
HERRAMIENTAS MANUALES %MO 5% 0.73 0.04
CARGADOR FRONTAL 966 HM 1.00 0.0100 91.73 0.92
CAMION VOLQUETE DE 15 M3 HM 2.50 0.0250 45.18 1.13
-
-
ANALISIS DE PRECIOS UNITARIOS
PROYECTO: CONSTRUCCION DE BASE Y SUB BASE DE VÍAS - AGROLMOS S. A. CLIENTE: AGROLMOS S. A. UBICACIÓN: OLMOS - LAMBAYEQUE - LAMBAYEQUE
-
Partida 5.01.02 TRANSPORTE DE MATERIAL > 1.00 KM
Rendimiento M3/KM 27,837.43 Costo Unitario $ 0.47 Descripcion de recurso Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra 0.11
CAPATAZ HH 1.00 0.0003 11.53 0.00
OPERARIO HH - 0.0000 10.10 -
OFICIAL (CONTROLADOR) HH 2.00 0.0006 8.98 0.01
AYUDANTE (PISO) HH - 0.0000 6.78 -
AYUDANTE (CUADRADOR VIGIA) HH 7.00 0.0020 6.78 0.01
OPERADOR DE EQUIPO PESADO HH 27.00 0.0078 11.53 0.09
Materiales -
-
Equipos 0.36
HERRAMIENTAS MANUALES %MO 5% 0.11 0.01
CAMION VOLQUETE DE 15 M3 HM 27.00 0.0078 45.18 0.35
- -
- -
- -
- -
Partida 5.01.03 CONFORMACION Y COMPACTACION DE SUBBASE E=0.30 M.
Rendimiento M2 2,571.43 Costo Unitario $ 2.83 Descripcion de recurso Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra 1.18
CAPATAZ HH 3.00 0.0093 11.53 0.11
OPERARIO HH 3.00 0.0093 10.10 0.09
OFICIAL (CONTROLADOR) HH 3.00 0.0093 8.98 0.08
AYUDANTE (PISO) HH 18.00 0.0560 6.78 0.38
AYUDANTE (CUADRADOR VIGIA) HH 9.00 0.0280 6.78 0.19
OPERADOR DE EQUIPO PESADO HH 9.00 0.0280 11.53 0.32
Materiales -
AGUA M3 0.02 - -
-
Equipos 1.65
HERRAMIENTAS MANUALES %MO 5% 1.18 0.06
MOTONIVELADORA 140 H HM 3.00 0.0093 77.50 0.72
RODILLO LISO HM 3.00 0.0093 47.18 0.44
CISTERNA DE AGUA HM 3.00 0.0093 45.91 0.43
Partida 5.02.01 TRANSPORTE DE MATERIAL < 1.00 KM, INCLUYE CARGUIO
Rendimiento M3 801.37 Costo Unitario $ 2.81 Descripcion de recurso Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra 0.73
CAPATAZ HH 1.00 0.0100 11.53 0.12
OPERARIO HH - 0.0000 - -
OFICIAL (CONTROLADOR) HH 1.00 0.0100 8.98 0.09
AYUDANTE (PISO) HH - 0.0000 6.78 -
AYUDANTE (CUADRADOR VIGIA) HH 1.00 0.0100 6.78 0.07
ANALISIS DE PRECIOS UNITARIOS
PROYECTO: CONSTRUCCION DE BASE Y SUB BASE DE VÍAS - AGROLMOS S. A. CLIENTE: AGROLMOS S. A. UBICACIÓN: OLMOS - LAMBAYEQUE - LAMBAYEQUEOPERADOR DE EQUIPO PESADO HH 4.00 0.0399 11.53 0.46
Materiales -
-
Equipos 2.08
HERRAMIENTAS MANUALES %MO 5% 0.73 0.04
CARGADOR FRONTAL 966 HM 1.00 0.0100 91.73 0.92
CAMION VOLQUETE DE 15 M3 HM 2.50 0.0250 45.18 1.13
-
-
-
Partida 5.02.02 TRANSPORTE DE MATERIAL > 1.00 KM
Rendimiento M3/KM 13,403.21 Costo Unitario $ 0.47 Descripcion de recurso Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra 0.11
CAPATAZ HH 1.00 0.0006 11.53 0.01
OPERARIO HH - 0.0000 - -
OFICIAL (CONTROLADOR) HH 1.00 0.0006 8.98 0.01
AYUDANTE (PISO) HH - 0.0000 6.78 -
AYUDANTE (CUADRADOR VIGIA) HH 3.00 0.0018 6.78 0.01
OPERADOR DE EQUIPO PESADO HH 13.00 0.0078 11.53 0.09
Materiales -
-
Equipos 0.36
HERRAMIENTAS MANUALES %MO 5% 0.11 0.01
CAMION VOLQUETE DE 15 M3 HM 13.00 0.0078 45.18 0.35
-
-
-
-
Partida 5.02.03 CONFORMACION Y COMPACTACION DE BASE E=0.15 M.
Rendimiento M2 2,400.00 Costo Unitario $ 1.97 Descripcion de recurso Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra 0.80
CAPATAZ HH 2.00 0.0067 11.53 0.08
OPERARIO HH 2.00 0.0067 10.10 0.07
OFICIAL (CONTROLADOR) HH 2.00 0.0067 8.98 0.06
AYUDANTE (PISO) HH 12.00 0.0400 6.78 0.27
AYUDANTE (CUADRADOR VIGIA) HH 4.00 0.0133 6.78 0.09
OPERADOR DE EQUIPO PESADO HH 6.00 0.0200 11.53 0.23
Materiales -
AGUA M3 0.01 - -
-
Equipos 1.18
HERRAMIENTAS MANUALES %MO 5% 0.80 0.04
MOTONIVELADORA 140 H HM 2.00 0.0067 77.50 0.52
RODILLO LISO HM 2.00 0.0067 47.18 0.31
CISTERNA DE AGUA HM 2.00 0.0067 45.91 0.31
-
-
ANALISIS DE PRECIOS UNITARIOS
PROYECTO: CONSTRUCCION DE BASE Y SUB BASE DE VÍAS - AGROLMOS S. A. CLIENTE: AGROLMOS S. A. UBICACIÓN: OLMOS - LAMBAYEQUE - LAMBAYEQUE
Partida 6.01 MANTENIMIENTO DE VIAS PROCESO CONSTRUCTIVO
Rendimiento KM 0.37 Costo Unitario $ 12,146.79 Descripcion de recurso Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra 3,654.49
CAPATAZ HH 1.00 21.6216 11.53 249.30
OPERARIO HH - 0.0000 - -
OFICIAL HH 1.00 21.6216 8.98 194.16
AYUDANTE (PISO) HH 6.00 129.7297 6.78 879.57
AYUDANTE (CUADRADOR VIGIA) HH 4.00 86.4865 6.78 586.38
OPERADOR DE EQUIPO PESADO HH 7.00 151.3514 11.53 1,745.08
Materiales -
-
Equipos 8,492.31
HERRAMIENTAS MANUALES %MO 5% 3,654.49 182.72
MOTONIVELADORA 140 H HM 1.00 21.6216 75.00 1,621.62
RODILLO LISO HM 1.00 21.6216 48.18 1,041.77
CISTERNA DE AGUA HM 1.00 21.6216 48.41 1,046.68
CAMION VOLQUETE DE 15 M3 HM 4.00 86.4865 53.18 4,599.51
-
Partida 6.02 RIEGO DE VÍAS
Rendimiento MES 1.00 Costo Unitario $ 28,650.00 Descripcion de recurso Unidad Cuadrilla Cantidad Precio Parcial
Subcontratos 28,650.00
MOVILIZACION Y DESMOVILIZACION DE ERQUIPOS GLB 3.0000 9,550.00 28,650.00
-
-
-
-
-
Materiales -
-
Equipos -
-
-
-
-
-
-
Presupuesto de Obra
PROYECTO: CONSTRUCCION DE BASE Y SUB BASE DE VÍAS - AGROLMOS S. A.
CLIENTE: AGROLMOS S. A.
UBICACIÓN: OLMOS - LAMBAYEQUE - LAMBAYEQUE
ITEM DESCRIPCION UNIDAD CANTIDAD P. UNITARIO PARCIAL
1.00 TRABAJOS PRELIMINARES 961,857.15
1.01 MOVILIZACION Y DESMOVILIZACION GLB 1.00 298,000.00 298,000.00
1.02 CAMPAMENTO, OFICINAS, PATIO DE MAQUINAS, LABORATORIOS GLB 1.00 591,666.67 591,666.67
1.03 ACCESOS A CANTERAS KM 5.00 14,438.10 72,190.49
2.00 CALIDAD 43,940.00
2.01 ESTUDIO DE CANTERAS UND 2.00 5,500.00 11,000.00
2.02 CONTROL DE CALIDAD (DENSIDAD DE CAMPO) UND 54.00 610.00 32,940.00
3.00 EXTRACCION Y PRODUCCION DE MATERIAL 3,531,871.08
3.01 MATERIAL SUB BASE 2,174,872.18
3.01.01 EXPLOTACION DE MATERIAL EN CANTERA PARA SUB BASE M3 434,568.57 1.93 837,862.68
3.01.02 PRODUCCION DE MATERIAL EN CANTERA PARA SUB BASE M3 359,642.95 3.72 1,337,009.50
3.02 MATERIAL BASE 1,356,998.91
3.02.01 EXPLOTACION DE MATERIAL EN CANTERA PARA BASE M3 218,900.33 1.97 430,776.99
3.02.02 PRODUCCION DE MATERIAL EN CANTERA PARA BASE M3 175,120.26 5.29 926,221.92
4.00 VIAS OESTE 5,258,925.75
4.01 SUB BASE 3,405,085.85
4.01.01 TRANSPORTE DE MATERIAL < 1.00 KM, INCLUYE CARGUIO M3 142,050.11 2.81 399,559.50
4.01.02 TRANSPORTE DE MATERIAL > 1.00 KM M3/KM 4,164,482.87 0.47 1,954,861.42
4.01.03 CONFORMACION Y COMPACTACION DE SUBBASE E=0.30 M. M2 371,372.83 2.83 1,050,664.92
4.02 BASE 1,853,839.91
4.02.01 TRANSPORTE DE MATERIAL < 1.00 KM, INCLUYE CARGUIO M3 69,168.19 2.81 194,556.75
4.02.02 TRANSPORTE DE MATERIAL > 1.00 KM M3/KM 2,027,803.75 0.47 955,712.89
4.02.03 CONFORMACION Y COMPACTACION DE BASE E=0.15 M. M2 348,162.03 2.02 703,570.26
5.00 VIAS ESTE 7,849,332.88
5.01 SUB BASE 5,093,360.33
5.01.01 TRANSPORTE DE MATERIAL < 1.00 KM, INCLUYE CARGUIO M3 217,592.84 2.81 612,046.61
5.01.02 TRANSPORTE DE MATERIAL > 1.00 KM M3/KM 6,139,964.19 0.47 2,871,901.59
5.01.03 CONFORMACION Y COMPACTACION DE SUBBASE E=0.30 M. M2 568,870.18 2.83 1,609,412.13
5.02 BASE 2,755,972.54
5.02.01 TRANSPORTE DE MATERIAL < 1.00 KM, INCLUYE CARGUIO M3 105,952.07 2.81 298,022.70
5.02.02 TRANSPORTE DE MATERIAL > 1.00 KM M3/KM 2,989,721.12 0.47 1,405,529.68
5.02.03 CONFORMACION Y COMPACTACION DE BASE E=0.15 M. M2 533,315.79 1.97 1,052,420.17
6.00 MANTENIMIENTO DE VIAS 1,479,112.63
6.01 MANTENIMIENTO DE VIAS PROCESO CONSTRUCTIVO KM 100.54 12,146.79 1,221,262.63
6.02 RIEGO DE VÍAS MES 9.00 28,650.00 257,850.00
COSTO DIRECTO $19,125,039.49
GASTOS GENERALES 29.20% $5,584,031.61
RIESGOS 1.20% $229,500.47
SAN JUAN 3.50% $669,376.38
COSTO INDIRECTO 33.90% $6,482,908.46
UTILIDAD 12.00% $2,295,004.74
PRESUPUESTO TOTAL $27,902,952.70
DESCUENTO COMERCIAL -4.00% $1,116,118.11
PRESUPUESTO FINAL DE OBRA $26,786,834.59
Presupuesto
PROYECTO: CONSTRUCCION DE BASE Y SUB BASE DE VÍAS - AGROLMOS S. A.
CLIENTE: AGROLMOS S. A.
UBICACIÓN: OLMOS - LAMBAYEQUE - LAMBAYEQUE
ITEM DESCRIPCION UNIDAD CANTIDAD P. UNITARIO PARCIAL
1.00 TRABAJOS PRELIMINARES GLB 1.00 1,005,797.15
2.00 EXTRACCION Y PRODUCCION DE MATERIAL M3 534,763.21 4,123,516.13
3.00 CARGUIO Y ACARREO M3 534,763.21 8,988,013.68
4.00 CONFORMACION Y COMPACTACION M2 1,821,720.83 5,007,712.53
COSTO DIRECTO 19,125,039.49
COSTOS INDIRECTOS 8,777,913.20
TOTAL 27,902,952.69
PRESUPUESTO POR KILOMETRO
ITEM DESCRIPCION UNIDAD CANTIDAD P. UNITARIO PARCIAL
1.00 CONSTRUCCION DE BASE Y SUB BASE DE VIAS KM 1.00 284,892.68 284,892.68
PRESUPUESTO POR METRO LINEAL
ITEM DESCRIPCION UNIDAD CANTIDAD P. UNITARIO PARCIAL
1.00 CONSTRUCCION DE BASE Y SUB BASE DE VIAS ML 1.00 284.89 284.89
PRESUPUESTO POR METRO LINEAL
ITEM DESCRIPCION UNIDAD CANTIDAD P. UNITARIO PARCIAL
1.00 CONSTRUCCION DE BASE Y SUB BASE DE VIAS M2 1.00 31.65 31.65
CONSIDERACIONES
1. Inicio inemdiato de otorgarse carta de intensión.
2. No solicitaremos adelanto.
3. De otorgarse la buena pro SM ofrece la ingeniería de detalle de las vías a construir.
4. El costo del material en cantera y la potencia son responsabilidad del cliente.
5. SM realizará la verificación de la calidad de subrasante antes del proceso constructivo.
EVALUAR
1. Posibilidad de ejecutar a tiempo y material.
2. Disponibilidad inmediata de recursos.
Item Vía
FRENTE OESTE
1 K1 8.81 8.81
2 K2 8.66 8.66
3 K3 8.66 8.66
4 K4 3.92 3.92
5 R1 2.15 2.15
6 R2 6.49 6.49
FRENTE ESTE
1 K5 10.98 10.98
2 K6 10.84 10.84
3 K7 9.98 9.98
4 K8 9.98 9.98
5 K9 7.36 7.36
6 R3 6.36 6.36
7 R4 3.39 3.39
8 R5 0.35 0.35
TOTAL (km) 97.94
Longitud(km)
Total(km)
ITEM DESCRIPCION
1.00 TRABAJOS PRELIMINARES
1.01 MOVILIZACION Y DESMOVILIZACION
1.02 CAMPAMENTO, OFICINAS, PATIO DE MAQUINAS, LABORATORIOS
1.03 ACCESOS A CANTERAS
2.00 CALIDAD
2.01 ESTUDIO DE CANTERAS
2.02 CONTROL DE CALIDAD (DENSIDAD DE CAMPO)
3.00 MOVIMIENTO DE TIERRAS
3.01 MATERIAL SUB BASE
3.01.01 EXPLOTACION DE MATERIAL EN CANTERA PARA SUB BASE
3.01.02 PRODUCCION DE MATERIAL EN CANTERA PARA SUB BASE
3.02 MATERIAL BASE
3.02.01 EXPLOTACION DE MATERIAL EN CANTERA PARA BASE
3.02.02 PRODUCCION DE MATERIAL EN CANTERA PARA BASE
4.00 VIAS OESTE
4.01 SUB BASE
4.01.01 TRANSPORTE DE MATERIAL < 1.00 KM, INCLUYE CARGUIO
4.01.02 TRANSPORTE DE MATERIAL > 1.00 KM
4.01.03 CONFORMACION Y COMPACTACION DE SUBBASE E=0.30 M.
4.02 BASE
4.02.01 TRANSPORTE DE MATERIAL < 1.00 KM, INCLUYE CARGUIO
4.02.02 TRANSPORTE DE MATERIAL > 1.00 KM
4.02.03 CONFORMACION Y COMPACTACION DE BASE E=0.15 M.
5.00 VIAS ESTE
5.01 SUB BASE
5.01.01 TRANSPORTE DE MATERIAL < 1.00 KM, INCLUYE CARGUIO
5.01.02 TRANSPORTE DE MATERIAL > 1.00 KM
5.01.03 CONFORMACION Y COMPACTACION DE SUBBASE E=0.30 M.
5.02 BASE
5.02.01 TRANSPORTE DE MATERIAL < 1.00 KM, INCLUYE CARGUIO
5.02.02 TRANSPORTE DE MATERIAL > 1.00 KM
5.02.03 CONFORMACION Y COMPACTACION DE BASE E=0.15 M.
6.00 MANTENIMIENTO DE VIAS
6.01 MANTENIMIENTO DE VIAS PROCESO CONSTRUCTIVO
6.02 RIEGO DE VÍAS
UNIDAD CANTIDAD DURACION
GLB 1.00 1.00
GLB 1.00 1.00
KM 5.00 12.50
UND 2.00 1.00
UND 54.00 1.00
M3 434,568.57 201.19
M3 359,642.95 124.88
M3 218,900.33 152.01
M3 175,120.26 156.36
M3 142,050.11 177.26
M3/KM 4,164,482.87 201.56
M2 371,372.83 216.63
M3 69,168.19 86.31
M3/KM 2,027,803.75 140.21
M2 348,162.03 145.07
M3 217,592.84 271.53
M3/KM 6,139,964.19 220.57
M2 568,870.18 221.23
M3 105,952.07 132.21
M3/KM 2,989,721.12 223.06
M2 533,315.79 222.21
KM 100.54 1.00
MES 9.00 270.00
MO
(H
H)
CA
PA
TA
Z
OP
ER
AR
IO
OF
ICIA
L
AY
UD
AN
TE
(P
ISO
)
AY
UD
AN
TE
(C
UA
DR
AD
OR
VIG
IA)
OP
ER
AD
OR
DE
EQ
UIP
O P
ES
AD
O
MA
TE
RIA
LE
S
AG
UA
EQ
UIP
OS
(H
M)
TR
AC
TO
R D
8
MO
TO
NIV
EL
AD
OR
A 1
40
H
RO
DIL
LO
LIS
O
EX
CA
VA
DO
RA
33
6
ZA
RA
ND
A E
ST
AT
ICA
CA
RG
AD
OR
FR
ON
TA
L 9
66
CA
MIO
N V
OL
QU
ET
E D
E 1
5 M
3
CIS
TE
RN
A D
E A
GU
A
ITEM PARTIDA UNIDAD METRADO
1.00 TRABAJOS PRELIMINARES - -
HH HM
1.02 MOVILIZACION Y DESMOVILIZACION GLB 1.00
HH HM
1.02 CAMPAMENTO, OFICINAS, PATIO DE MAQUINAS, LABORATORIOS GLB 1.00
HH 20.000 0.000 40.000 80.000 80.000 160.000 0.000 HM 20.000 20.000 20.000 20.000 80.000
1.03 ACCESOS A CANTERAS KM 5.00 100.000 0.000 200.000 400.000 400.000 800.000 0.000 100.000 100.000 100.000 100.000 400.000
CANTIDAD 0.481 0.000 0.962 1.923 1.923 3.846 0.000 0.481 0.481 0.481 0.481 1.923
2.00 CALIDAD - -
HH HM
2.01 ESTUDIO DE CANTERAS UND 2.00
HH HM
2.02 CONTROL DE CALIDAD (DENSIDAD DE CAMPO) UND 54.00
3.00 EXTRACCION Y PRODUCCION DE MATERIAL - -
3.01 MATERIAL SUB BASE - -
HH 0.004 0.004 0.011 0.011 0.011 0.000 HM 0.011
3.01.01 EXPLOTACION DE MATERIAL EN CANTERA PARA SUB BASE M3 434,568.57 1,609.513 0.000 1,609.513 4,828.540 4,828.540 4,828.540 0.000 4,828.540
CANTIDAD 7.738 0.000 7.738 23.214 23.214 23.214 0.000 23.214 0.000 0.000 0.000 0.000
HH 0.003 0.003 0.011 0.011 0.006 0.000 HM 0.011 0.011 0.022
3.01.02 PRODUCCION DE MATERIAL EN CANTERA PARA SUB BASE M3 359,642.95 999.008 0.000 999.008 3,996.033 3,996.033 1,998.016 0.000 3,996.033 3,996.033 7,992.066
3.02 MATERIAL BASE - -
HH 0.006 0.006 0.011 0.011 0.011 0.000 HM 0.011
EXPLOTACION DE MATERIAL EN CANTERA PARA BASE M3 218,900.33 1,216.113 0.000 1,216.113 2,432.226 2,432.226 2,432.226 0.000 2,432.226
CANTIDAD 5.847 0.000 5.847 11.693 11.693 11.693 0.000 11.693 0.000 0.000 0.000 0.000
HH 0.007 0.007 0.014 0.014 0.043 0.000 HM 0.014 0.014 0.029
3.02.02 PRODUCCION DE MATERIAL EN CANTERA PARA BASE M3 175,120.26 1,250.859 0.000 1,250.859 2,501.718 2,501.718 7,505.154 0.000 2,501.718 2,501.718 5,003.436
CANTIDAD 6.014 0.000 6.014 12.027 12.027 36.082 0.000 0.000 0.000 0.000 24.055 0.000
4.00 VIAS OESTE - -
4.01 SUB BASE - -
HH 0.010 0.000 0.010 0.000 0.010 0.040 0.000 HM 0.010 0.025
4.01.01 TRANSPORTE DE MATERIAL < 1.00 KM, INCLUYE CARGUIO M3 142,050.11 1,418.073 0.000 1,418.073 0.000 1,418.073 5,672.292 0.000 1,418.073 3,545.182
CANTIDAD 6.818 0.000 6.818 0.000 6.818 27.271 0.000 0.000 0.000 0.000 6.818 17.044
HH 0.000 0.000 0.001 0.000 0.002 0.008 0.000 HM 0.008
4.01.02 TRANSPORTE DE MATERIAL > 1.00 KM M3/KM 4,164,482.87 1,612.488 0.000 3,224.977 0.000 8,062.442 32,249.768 0.000 32,249.768
CANTIDAD 7.752 0.000 15.505 0.000 38.762 155.047 0.000 0.000 0.000 0.000 0.000 155.047
HH 0.009 0.009 0.009 0.056 0.028 0.028 M3 0.015 HM 0.009 0.009 0.009
4.01.03 CONFORMACION Y COMPACTACION DE SUBBASE E=0.30 M. M2 371,372.83 3,466.146 3,466.146 3,466.146 20,796.879 10,398.439 10,398.439 5,570.592 3,466.146 3,466.146 3,466.146
CANTIDAD 16.664 16.664 16.664 99.985 49.992 49.992 26.782 0.000 16.664 16.664 0.000 0.000
4.02 BASE - -
HH 0.010 0.000 0.010 0.000 0.010 0.040 0.000 HM 0.010 0.025
4.02.01 TRANSPORTE DE MATERIAL < 1.00 KM, INCLUYE CARGUIO M3 69,168.19 690.500 0.000 690.500 0.000 690.500 2,761.998 0.000 690.500 1,726.249
CANTIDAD 3.320 0.000 3.320 0.000 3.320 13.279 0.000 0.000 0.000 0.000 3.320 8.299
HH 0.001 0.000 0.001 0.000 0.002 0.008 0.000 HM 0.008
4.02.02 TRANSPORTE DE MATERIAL > 1.00 KM M3/KM 2,027,803.75 1,121.666 0.000 1,121.666 0.000 4,486.662 15,703.319 0.000 15,703.319
CANTIDAD 5.393 0.000 5.393 0.000 21.570 75.497 0.000 0.000 0.000 0.000 0.000 75.497
HH 0.007 0.007 0.007 0.040 0.020 0.020 M3 0.008 HM 0.007 0.007 0.007
4.02.03 CONFORMACION Y COMPACTACION DE BASE E=0.15 M. M2 348,162.03 2,321.080 2,321.080 2,321.080 13,926.481 6,963.241 6,963.241 2,611.215 2,321.080 2,321.080 2,321.080
CANTIDAD 11.159 11.159 11.159 66.954 33.477 33.477 12.554 0.000 11.159 11.159 0.000 0.000
5.00 VIAS ESTE - -
5.01 SUB BASE - -
HH 0.010 0.000 0.010 0.000 0.010 0.040 0.000 HM 0.010 0.025
5.01.01 TRANSPORTE DE MATERIAL < 1.00 KM, INCLUYE CARGUIO M3 217,592.84 2,172.209 0.000 2,172.209 0.000 2,172.209 8,688.836 0.000 2,172.209 5,430.522
CANTIDAD 10.443 0.000 10.443 0.000 10.443 41.773 0.000 0.000 0.000 0.000 10.443 26.108
HH 0.000 0.000 0.001 0.000 0.002 0.008 0.000 HM 0.008
5.01.02 TRANSPORTE DE MATERIAL > 1.00 KM M3/KM 6,139,964.19 1,764.520 0.000 3,529.041 0.000 12,351.642 47,642.047 0.000 47,642.047
CANTIDAD 8.483 0.000 16.967 0.000 59.383 229.048 0.000 0.000 0.000 0.000 0.000 229.048
HH 0.009 0.009 0.009 0.056 0.028 0.028 M3 0.015 HM 0.009 0.009 0.009
5.01.03 CONFORMACION Y COMPACTACION DE SUBBASE E=0.30 M. M2 568,870.18 5,309.455 5,309.455 5,309.455 31,856.730 15,928.365 15,928.365 8,533.053 5,309.455 5,309.455 5,309.455
CANTIDAD 25.526 25.526 25.526 153.157 76.579 76.579 41.024 0.000 25.526 25.526 0.000 0.000
5.02 BASE - -
HH 0.010 0.000 0.010 0.000 0.010 0.040 0.000 HM 0.010 0.025
5.02.01 TRANSPORTE DE MATERIAL < 1.00 KM, INCLUYE CARGUIO M3 105,952.07 1,057.710 0.000 1,057.710 0.000 1,057.710 4,230.838 0.000 1,057.710 2,644.274
CANTIDAD 5.085 0.000 5.085 0.000 5.085 20.341 0.000 0.000 0.000 0.000 5.085 12.713
HH 0.001 0.000 0.001 0.000 0.002 0.008 0.000 HM 0.008
5.02.02 TRANSPORTE DE MATERIAL > 1.00 KM M3/KM 2,989,721.12 1,784.481 0.000 1,784.481 0.000 5,353.443 23,198.252 0.000 23,198.252
CANTIDAD 8.579 0.000 8.579 0.000 25.738 111.530 0.000 0.000 0.000 0.000 0.000 111.530
HH 0.007 0.007 0.007 0.040 0.013 0.020 M3 0.008 HM 0.007 0.007 0.007
5.02.03 CONFORMACION Y COMPACTACION DE BASE E=0.15 M. M2 533,315.79 3,555.439 3,555.439 3,555.439 21,332.632 7,110.877 10,666.316 3,999.868 3,555.439 3,555.439 3,555.439
CANTIDAD 17.093 17.093 17.093 102.561 34.187 51.280 19.230 0.000 17.093 17.093 0.000 0.000
6.00 MANTENIMIENTO DE VIAS - -
HH 21.622 0.000 21.622 129.730 86.486 151.351 0.000 HM 21.622 21.622 86.486 21.622
6.01 MANTENIMIENTO DE VIAS PROCESO CONSTRUCTIVO KM 100.54 2,173.881 0.000 2,173.881 13,043.284 8,695.523 15,217.165 0.000 2,173.881 2,173.881 8,695.523 2,173.881
CANTIDAD 10.451 0.000 10.451 62.708 41.805 73.159 0.000 0.000 10.451 10.451 0.000 41.805
HH HM
6.02 RIEGO DE VÍAS MES 9.00
SUB TOTAL HH 32,565.431 14,652.120 36,042.439 115,114.521 97,789.931 212,653.972 M3 20,714.729 HM 7,360.765 16,926.001 16,926.001 6,497.751 6,497.751 18,433.992 141,235.136 16,826.001TOTAL HH 508,818.416 M3 20,714.729 HM 230,703.398
CANTIDAD DE MANO DE OBRA, MATERIAL Y EQUIPOS - REFERENCIAL UND 156.565 70.443 173.281 553.435 470.144 1,022.375 UND 99.590 UND 35.388 81.375 81.375 31.239 31.239 88.625 679.015 80.894