Rajiv Misra 1
Project Management
Introduction to Microsoft Project 1
Rajiv Misra 2
Defining A Project in MS Project
• Steps 1. Create a new project file.2. Setup the Project – Views, Table and Calendar3. Define WBS code structure.4. Entering activity information.
Rajiv Misra 3
Create a new project file.
Rajiv Misra 4
Create an MS Project File
1.Click on White Document Icon
2. Fill in the Project Information and click OK.You can access Project Information later from the Project menu.
Rajiv Misra 5
Create an MS Project File
Backward vs Forward Scheduling
Rajiv Misra 6
Getting Specific Help
1.Click on question mark icon
2. Move the cursor onto the Option and click.
Rajiv Misra 7
Setup the Project – Views, Table and Calendar
Rajiv Misra 8
Understanding View / Table
VIEWTABLE
Rajiv Misra 9
Understanding View / Table
VIEWTABLEVIEW
TABLE
Note different style of Table/ View
Rajiv Misra 10
Setting the View
Select this
Rajiv Misra 11
Setting the View
Select thisDetail Gantt
Rajiv Misra 12
Setting the Table
Select thisSchedule
Rajiv Misra 13
Navigating the Table
Use the SliderTo see Columns
Rajiv Misra 14
Navigating the Table
Use the SliderTo see ColumnsThis table showsSlack values too
Rajiv Misra 15
Understanding the Calendar
CalendarsProject
AndResource
Gray Portion
IndicatesHoliday
Rajiv Misra 16
Understanding the Calendar
Project Calendar
Resource Calendar
Rajiv Misra 17
Changing the Calendar
Project Calendar
Resource Calendar
Rajiv Misra 18
Changing the Calendar
Project Calendar
Resource Calendar
Select datesAnd this
Radio buttonFor Working
day
Rajiv Misra 19
Entering activity information
Rajiv Misra 20
A Simple Project
project
1 2 3 4 5 6
2.32.22.1
Rajiv Misra 21
Entering Activity Information
To add activity double click on the any field (e.g. Task Name).
… or you can right-click on any field and select Task Information.
… or if you right-click on the row header you get access to a wider set of actions..
Rajiv Misra 22
1.Task Name 2.Duration
3.WBS Code
Entering Activity Information
Rajiv Misra 23
2. Enter Predecessors 1.Click Predecessors
Entering Activity Information
Now enter work packages (not the summary tasks) which aregiven to you in the Assignment
Rajiv Misra 24
1. Enter Predecessors2. Enter Relation type: FS, SS, SF, OR FF
Entering Activity Information
Now enter work packages (not the summary tasks) which aregiven to you in the Assignment
Rajiv Misra 25
1. Enter Predecessors2. Enter Relation type: FS, SS, SF, OR FF
Entering Activity Information
Now enter work packages (not the summary tasks) which aregiven to you in the Assignment
3. Lead or Lag
Rajiv Misra 26
Sub Projects and Recurring Tasks
Rajiv Misra 27
Sub Project
Link the project to other tasks like any other activity
Rajiv Misra 28
Sub Project
Link the project to other tasks like any other activity
Changes here affect Main Project
Rajiv Misra 29
Sub Project
Link the project to other tasks like any other activity
Rajiv Misra 30
Recurring Tasks (Insert – Recurring Tasks)
Rajiv Misra 31
Summary Tasks (Heading)
Rajiv Misra 32
Defining Summary Tasks
First insert a task right above the tasks that will make up the summary task, by right-clicking on the row header.
Rajiv Misra 33
Defining Summary Tasks
Select the tasks that will make up the summary task, right-click and select Indent.
Note how initially a WBS code of 9 is automatically assigned. This will change when Indent operation is complete.
Rajiv Misra 34
Defining Summary Tasks
After the Indent operation is complete, and WBC codes are renumbered as described in slide 13, we obtain the structure displayed below.
You can hide a summary task by clicking on the minus sign.
Summary task duration is calculated automatically.
Rajiv Misra 35
Do NOT forget
to save your file as
<username>-PART1.
Rajiv Misra 36
Define WBS code structure.
Rajiv Misra 37
1.Click on Project
2.Select WBS, then Define Code...
Defining WBS Code Structure
Rajiv Misra 38
Level of WBSdepends on
complexity of the project. In this project there are 2 levels.
Code Structure, changes made below settingscan be followedby this preview.
• Generally, for complex projects with many levels, letters are used for upper levels of the WBS hierarchy. • It is very important that you set the WBS structure correctly in the beginning :
• Once you set the it, it it would be difficult to change it. • Clearly defined WBS means that the project is already solved in the mind.
Defining WBS Code Structure
Rajiv Misra 39
Length of the codes can be set here.Click on Length, the box below will be opened.Select 1, since there are not too manyactivities in this WBS.
Click on Separator. Select “.”
Defining WBS Code Structure
Rajiv Misra 40
Displaying WBS
Rajiv Misra 41
Displaying WBS Code
Select the column header where you want the new WBS column.Right-click and select Insert Column.
Choose WBS as the Field name of the new column.
Rajiv Misra 42
Displaying WBS CodesThese codes can be automatically (re)generated using the WBS code structure you have defined earlier.
Rajiv Misra 43
Developing a Network Plan
• Steps1. Network Diagram view (AoN network).2. Customizing Network Diagram view.3. Identifying critical path(s).4. Overview Report.5. Current Activities Report.6. Printing a Gantt chart.7. Creating a Milestone.
Rajiv Misra 44
Select “Detail GanttView”
Checking the Gantt ChartProject Network
Red Bars indicate CRITICAL
SLACK is shown as GREEN lines
Rajiv Misra 45
Viewing Only the Critical Path
Select Critical
Rajiv Misra 46
Viewing Only the Critical Path
Select Critical
Rajiv Misra 47
Select “NetworkDiagram”
Developing an Activity-On-Node (AoN) Project Network
These make upthe summary task. You can hide them by clicking on the minus sign.
Rajiv Misra 48
Customizing Network Diagram
Right-click on the background,then select “Box Styles”
You may want to see different information on the nodes.
Rajiv Misra 49
Click“More Templates...”
Customizing Network Diagram
Rajiv Misra 50
Select “New...””
Customizing Network Diagram
Rajiv Misra 51
Customizing Network Diagram
1.Give a name to your template
Info: You may folllow the changes in your template
2.You maychange the cell layout (# rows &# columns) by clickingthis icon.
Rajiv Misra 52
Customizing Network Diagram
2.CheckShowlabel in cell.
1.Select the activity
Propertysuch as
“Late finish”
Rajiv Misra 53
Identifying the Critical Path
Critical path indicated by RED boxes To see the details, move
the pointer on to boxes
Rajiv Misra 54
Viewing Only the Critical Path
Select Critical
Rajiv Misra 55
Reports
Rajiv Misra 56
Getting an Overview Report
2.Select “Reports”1.Select “View”
Rajiv Misra 57
Getting an Overview Report
2.Enter “Select”1.Select
“Overview”
Rajiv Misra 58
Getting an Overview Report
2.Enter “Select”
1.Select “Project
Summary”
Rajiv Misra 59
Getting an Overview Report
Project Summary Report
Rajiv Misra 60
1.From “View” menuSelect “Reports”
2.SelectCurrent Activities 3. Select
Print out ES-LS-EF-LF-Slack Times
Rajiv Misra 61
1.Select “Unstarted Tasks” 2.Edit...
Print out ES-LS-EF-LF-Slack Times
Rajiv Misra 62
1.From Table option, select “Schedule” 2. “OK”
Print out ES-LS-EF-LF-Slack Times
Rajiv Misra 63
1. Choose “Unstarted Tasks”
2. “Select”
Print out ES-LS-EF-LF-Slack Times
Rajiv Misra 64
Report with ES,LS,EF,LF and Slack
Print out ES-LS-EF-LF-Slack Times
Rajiv Misra 65
Print out a Gantt ChartOr alternatively,
1.Go to View , then 2. Select Gantt Chart
1.Click on “Gantt Chart”
Rajiv Misra 66
Print Out a Gantt Chart:Obtaining A Printable Timescale
1.Right click mouse,when your pointer is on the timescale
2.Select “Timescale”
Rajiv Misra 67
Print Out a Gantt Chart:Obtaining A Printable Timescale
2.Select “Months”
1.Click on“Major Scale”
Rajiv Misra 68
Print Out a Gantt Chart:Obtaining A Printable Timescale
1.Click on “Minor Scale”
2.Select “Days”
Rajiv Misra 69
Print Out a Gantt Chart:Obtaining A Printable Timescale
1.Arrange the Size of timescale by increasing or decreasing this number.
You can follow the changes in the timescaleby observing this area. 2.Click OK.
Rajiv Misra 70
Print Out a Gantt Chart
1.Select “Print Preview”
Rajiv Misra 71
Print out a Gantt Chart Click on “Page Setup...” to set the printoutput styles
Rajiv Misra 72
Milestones
Rajiv Misra 73
Creating a Milestone
1.Right-click on the activity where you want to put a milestone.
2.Click on the “New Task”
Rajiv Misra 74
Creating a Milestone
1.Double-click on this new activity
2.Select Advanced.
Rajiv Misra 75
Creating a Milestone
3. Check Mark task as milestone.
2. Give zeroduration.
1.Give a name to your milestone
Rajiv Misra 76
Creating a Milestone
1.Click on Predecessors.
2.Choose necessaryactivities to link your milestone to the network
Rajiv Misra 77
Creating a Milestone
NOTE: Pay attention to Predecessors column. When you add any new task these numbers are changed automatically; therefore you do not need to change predecessors of each activity.
Rajiv Misra 78
Creating a Milestone
1.Select “Network View”.Milestone 1 is in the network.Note that its shape is different from regular activities.
Rajiv Misra 79
Do NOT forget
to save your file as
<username>-PART2.
Rajiv Misra 80
ResourcesResources
Rajiv Misra 81
Entering Resources-1
1.Click on “View”
2.Select “Resource Sheet”
Rajiv Misra 82
Entering Resources-2
1.Click on the Resource Name cell to enter the
resource name.
2.There are two types of resources. One is labor, the other one is material. In this example project we just have
workers as a resource.
Rajiv Misra 83
Entering Resources-3
1.Write the label of material here.In this project there is no material.
2.Write the initials of workers.
3. Enter the number of units in this cell. 100% means that resource or department is used fully.50% means that half capacity of that resource is used.
Rajiv Misra 84
Entering Resources-4
1.Standard Rate:Write the standard hourly wage rate of resources.
2.Overtime Rate:Write the hourly overtime rate. If a resource is used overtime, this rate is used to calculate the cost of overtime work.
3.Cost per use:A set fee for the use of a resource.(e.g. Travel cost, insurance) It is not related with the working hours.
Rajiv Misra 85
Entering Resources-5
This cell is used for accounting purposes. There are 3 types of entering the cost of resources.In this example we will use “Prorated”
Start: Cost at the beginning of the work.
Prorated: Cost accrues while activity progress. If 30% of the work is finished, 30% of the cost related with that work accrued.
End:Cost is accrued at the end of the work.
Rajiv Misra 86
Entering Resources-6
Through “Base Calender”cell, you can assign different calendars to different resources. In this example, Standard calendar is used:5 working-days in a week, 8 hours a day.
There are 2 more default base calendars which are 24 Hours and Night Shift. Other than these, you can create resources’ own calendars from “Tools”, “Change Working Time...”. In the appeared dialog box choose “New...” icon.
Rajiv Misra 87
Resource Information Dialog Box
1.Double-click on the resource name cell.
Resource Information box will appear
You can also enter resourse details using this dialog box instead of “Resource Sheet”. There are lots of details in this dialog box, Do Not Be Lost in these details.
Rajiv Misra 88
Resource Information Dialog Box
1.Double-click on the resource name cell.
Manage Costs Information
Rajiv Misra 89
Resource Information Dialog Box
Rates for different periods can be given here
Different Cost tables A-F
Rajiv Misra 90
Work Contours (View – Task Usage. Click on Task Assignment – Resource)
Work Load varies over time
Front vs back …
Rajiv Misra 91
Assigning Resources to Tasks
1.Double click on an activity
2.From “Task Information”dialog box, click on “Resources”
100% means that this resource, “A” in this case, is used at full capacity.
3.Enter the resources which are needed for this activity.
Rajiv Misra 92
A Simple Project
project
1 2 3 4 5 6
2.32.22.1
Rajiv Misra 93
Resource Leveling
Rajiv Misra 94
Identify which resources are overloaded-1
2.Click on “Resources Usage”
1.Go to “View”menü
Rajiv Misra 95
Identify which resources are overloaded-2
The resources in red are overloaded on at least one day.
Rajiv Misra 96
Identify which resources are overloaded-3
By scrolling to the right, you can see when each resource is used, how much it is used and whether it is overloaded
(indicated with red colour)
Rajiv Misra 97
Graphical Display of the Load Distribution of Each Resource Over Time-1
2.Select “Resource Graph”
1.Go to “View” menu.
Rajiv Misra 98
Graphical Display of the Load Distribution of Each Resource Over Time-2
By scrolling this cursor to the right, you can see
other resources.
By scrolling this cursor to the right, you can see resource load over time.
Rajiv Misra 99
Graphical Display of the Load Distribution of Each Resource Over Time-3
Red area indicates that this resource is overallocated at these times
Rajiv Misra 100
Resolve over-allocation problems-1
1.Go to “Tools” 2.Select “Resource Leveling”
Rajiv Misra 101
Ways of Leveling Resources
AutomaticAutomatic: : Automatic leveling levels resources instantaneously when you change a task or resource. If your project is large, automatic leveling might slow down your work in the schedule.
ManualManual::Manual leveling allows you to control when Microsoft Project levels resources.
Rajiv Misra 102
Resolve over-allocation problems-2
1.Check “Manual”
2.Select “Week by Week”
Rajiv Misra 103
Time-Unit Used in Leveling
• Example:– Resource A has a weekly capacity of 40 hours, and
daily capacity of 8 hours.– His workload on Monday of his 1st week is 10 hours.– His workload for the entire 1st week is 38 hours.– Then, “week-by-week” leveling will not perform any
leveling for resource A in week 1.• “Day-by-day” leveling would change the schedule.
Rajiv Misra 104
Resolving Methods Available in MS Project
Level only within available slack: Select this check box if you want to prevent the finish date of your project from being delayed. In many projects, however, unless there is a lot of built-in slack, with this setting you might not see a significant change after leveling.
Leveling can adjust individual assignments on a task:Select this check box to allow leveling to adjust when a resource works on a task independent of the other resources working on the same task.
Leveling can create splits in remaining work: Select this check box if you want leveling to interrupt tasks by creating splits in the remaining work on tasks or assignments.
Rajiv Misra 105
Resolve over-allocation problems-3
1.Select “Standart” option
2.Check “Level only within
available lack”
Rajiv Misra 106
Resolve over-allocation problems-4
2.Click on “Level now”
2.Do not check others.
Rajiv Misra 107
Save Your Results
SAVE AS YOUR RESULTSSAVE AS YOUR RESULTSASAS
<username><username>--partpart33--2 2
Rajiv Misra 108
Seeing the Effects of Leveling in the Leveling Gantt Chart
1.Go to “View”
2.Select “More Views”
Rajiv Misra 109
Seeing the Effects of Leveling in the Leveling Gantt Chart
1.Select “Leveling Gantt”
2.Click on “Apply”
Rajiv Misra 110
Seeing the Effects of Leveling in the Leveling Gantt Chart
1. Effects of leveling seen as green lines
Rajiv Misra 111
Seeing the Effects of Leveling in Summary Report -1
1.Go to “Toolbar” 2.Select “Resource Leveling”
Rajiv Misra 112
Seeing the Effects of Leveling in Summary Report -2
2.Select “Reports”1.Select “View”
Rajiv Misra 113
Seeing the Effects of Leveling in Summary Report -3
2.Enter “Select”
1.Select “Overview”
Rajiv Misra 114
Seeing the Effects of Leveling in Summary Report -4
2.Enter “Select”
1.Select “Project
Summary”
Rajiv Misra 115
Seeing the Effects of Leveling in Summary Report –5
Duration of the project project did not change.This is because we selected
“Level only within available slack” in the leveling dialog box.
There is still an overallocated resource
Rajiv Misra 116
Seeing the Effects of Leveling on The Critical Path-1
1.Click on “More Views...”
2.Select “Leveling Gantt”
3.Click on “Apply”
Rajiv Misra 117
Seeing the Effects of Leveling on The Critical Path-2
1.Firstly, Choose “Critical”
from the menuThere is delay at one of the critical activities.
This has not caused any delay in the project’s completion, becausethis critical activity was not a critical activity before leveling,
it became critical due to delaying.
Rajiv Misra 118
Compare After-leveling and Pre-leveling Reports
Leveling only within available slack means that we are keeping the duration of the project constant. If we look at the both reports we can easily see that duration of the project in each case is the same.
What difference did leveling make? Leveling reduces the amount of overallocation. At the pre-leveling stage resourse B was overallocated for 13 days, after leveling resource B is overallacated for 8 days.
At the end with Leveling only within available slack did not solve overallocation problem due to limited slack time.
Rajiv Misra 119
Leveling Not Limited to Available Slack-1
1.Do not check “Level only
within available slack”
2.Select “Level Now”
Rajiv Misra 120
Leveling Not Limited to Available Slack-2
Get the project overview report...
Duration of the project is increased
All overallacotion problem is solved.
Rajiv Misra 121
Comparison of These Two Leveling Methods
Leveling only within available slack time reduces the overallocation problem but not solve the whole overallocation problem. But on the other hand the project time is kept constant.
The other method solved the overallocation problem completely, but the project duration is prolonged.
Rajiv Misra 122
Different types of Tasks can affectTimes and Resource Usage
Rajiv Misra 123
Keeping the amount of work constant in effort-driven scheduling can have varying effects on duration and units depending on the task type
Rajiv Misra 124
Change these and find out Impact
ie Change duration and Resources to see the impact.
Can cause confusion
Task – Right Click-Task Information -Advanced tab
Check on Task Sheet for Differences
Rajiv Misra 125
Fixed Duration Set the task to Fixed Duration if you want the task duration to remain constant, regardless of any change in assignment
units or work for the task. For fixed-duration tasks:
If you revise units, Microsoft Project recalculates work.
If you revise duration in a fixed-duration task, Microsoft Project recalculates work.
If you revise the amount of work, Microsoft Project recalculates the units
Fixed Duration
Rajiv Misra 126
Fixed Units Set the task to Fixed Units if you want the number of assignment units to remain constant, regardless of any change in duration or work for the task. This is the
default. For fixed-unit tasks:
If you revise units in a fixed-unit task, Microsoft Project recalculates duration.
If you revise duration, Microsoft Project recalculates work.
If you revise the amount of work, Microsoft Project recalculates the duration.
Fixed Units
Rajiv Misra 127
Fixed Work Set the task to Fixed Work if you want the amount of work to remain constant, regardless of any change in duration or
resource assignment units for the task. Because, by definition, fixed-work tasks are effort-driven, the Effort driven check box is
automatically selected for fixed-work tasks.
For fixed-work tasks: If you revise units, Microsoft Project recalculates duration. If you revise duration, Microsoft Project recalculates units.
If you revise the amount of work in a fixed-work task, Microsoft Project recalculates the duration.
Fixed Work
Rajiv Misra 128
Resource Management
Rajiv Misra 129
Resource Management-1
1.Click on an empty area in the tool bar
2.Select “Resource Management”
Rajiv Misra 130
Resource Management-2
Rajiv Misra 131
Ways of reducing over-allocations:Delaying a task-1
• Delaying an assigned task until the resource has time to work on it is a simple way to resolve a resource overallocation.
• You can add delay to a task or assignment, check the effect on the resource's allocation, and then adjust the delay further if necessary.
• If you want to add delay without changing the finish date of other tasks or the project finish date, review available slack and add delay only within that slack time.
Rajiv Misra 132
Ways of reducing over-allocations:Delaying a task-2
1.Double-click on the relationship between activities which you want a delay.
2.Set how many days will you delay.
Rajiv Misra 133
Ways of reducing over-allocations:Splitting a task-1
• In addition to reducing over-allocations, splitting a task is useful when you need to interrupt work on a task.
• For example, your project may include a task that requires materials that are ordered but that won't be received for two weeks.
Rajiv Misra 134
Ways of reducing over-allocations Spliting a task-2
1.First Click on “Split Task” icon
2. Move pointer on the Gantt Chart view, and
split the task which is needed to be interrupted
Rajiv Misra 135
Sharing Resources across projects
Rajiv Misra 136
Create a project and only model allResources in that project which arecommon. (say Common_Resource)
(For other projects that shall use thecommon resources
Tools – Resources – Share Resources-Select the name as Common_Resource
Rajiv Misra 137
Rajiv Misra 138
Common ResourcesFile Name
Rajiv Misra 139
PERT Calculations
Rajiv Misra 140
For PERT CalculationsView – Tool Bars – PERT Analysis
Rajiv Misra 141
PERT Tool Bar
Enter PERT Durations (Opt/Pess/Likely) and Calculate PERTYou can view all 3 Gantt – Opt/Pess/ Likely
PERT Calculate
Button
Important- Press to see results
Rajiv Misra 142
Base Lines
Rajiv Misra 143
If “Save with a baseline option” does not appear,Base Line means the details of the Previous Version
of the Plan
1.Choose “Tools”
2.Select “Tracking”
3.Click on “SaveBaseline...”
Rajiv Misra 144
Tracking and Costing
Rajiv Misra 145
Display the Tool Bar for TrackingView – Tool Bars - Tracking
3 Activities A, B and C Duration 6,4,4.A & B FS relation.
All use resource AR. Cost per hour of AR = 10/hr (Resource Sheet)
Rajiv Misra 146
Set the OptionsTools – Options - Calculations
Rajiv Misra 147
Create a Network as below
3 Activities A, B and C Duration 6,4,4.A & B FS relation.
All use resource AR. Cost per hour of AR = 10/hr (Resource Sheet)
Rajiv Misra 148
Update the Task Status using the buttonson the Tool Bar (0-100% buttons)
or Task Update Button (or Tools – Tracking)
3 Activities A, B and C Duration 6,4,4.A & B FS relation.
All use resource AR. Cost per hour of AR = 10/hr (Resource Sheet)
Buttons forTask Status
Rajiv Misra 149
Update Tasks and Add Progress Lines (Button onTool Bar or Tools – Tracking – Progress Lines)
Rajiv Misra 150
Task Updated and Progress Lines Added
Black bars Indicate Progress
Progress Line (Line to left indicates Slow Progress, to Right Ahead of Schedule)
Rajiv Misra 151
Update Project based on Actual Status
Menu Tools – Tracking – Update Project
Rajiv Misra 152
Update Project based on Actual Status
Menu Tools – Tracking – Update Project
Select this button.
Put date based on Date till Status got
Rajiv Misra 153
Updated Project based on Actual Status
Menu Tools – Tracking – Update Project
Dotted line indicates Delay
Rajiv Misra 154
Update the Progress of the Project-1
1.Select the activity that you will update
2. From “Tools” select “Tracking” 4.Update Tasks...
Rajiv Misra 155
Update the Progress of the Project-2
Change the durations using the data provided in the Excel file.
Note: Although we changed the actual and remaining durations, baseline dates are not affected by changes you made.
Rajiv Misra 156
Update the Progress of the Project-3
If a number of tasks started and finished on time, you can set the actual finish information for all those tasks at once. Procedure as follows;
Select the tasks that you want to update (press CTRL key and click on Task Name).
Rajiv Misra 157
Update the Progress of the Project-4
1.Go to “Tool” bar
2.Choose “Update Project...”
2.Select “Tracking”
Rajiv Misra 158
Update the Progress of the Project-5
Choose “selected tasks” then click “OK”
Rajiv Misra 159
Seeing the Effects of Update-1
1.Go to “View”
2.Click “More Views”
3.Select
“Tracking Gantt”
Rajiv Misra 160
Seeing the Effects of Update-2
Dark Blue Bar shows the completion percentage of the tasks.
Light Blue Bar shows the remaining percentage of the tasks.
Gray Bar shows the base line of the tasks.
Rajiv Misra 161
Seeing the Effects of Update on Critical Path
Select “Critical”
As you can see Tracking Gantt Chart does not show the completed tasks on the critical path. Therefore we have only
remaining critical activities as indicated by the Red Bar.
Rajiv Misra 162
Costing – Earned Value Management
Rajiv Misra 163
Step 1
Create a Network with one Task A Duration 10Resource ARSet Std Rate for Resource as 10/hr (View-Resource Sheet)
Step 2Set the Status Date appropriately (Project – Project Information)
Step 3Save the Base Line (Tools – Tracking – Save Base Line)
Rajiv Misra 164
Set the Tables to Earned ValueView – Tables – More Tables – Earned
Value
EVM terms
Rajiv Misra 165
Update Actual Costs Set Table to Cost (View – Table – Cost)
Enter Actual Costs
Rajiv Misra 166
To see the BCWP/ACWPSet the Tables to Earned Value
View – Tables – More Tables – Earned ValueUpdate the Progress of the job also (for BCWP)
EVM terms Now
BCWS and ACWP also appear Black bar showing Progress
Rajiv Misra 167
Earned Value Analysis Report-1
What is earned value analysis?Earned value analysis is a method for measuring project performance. It indicates how much of the budget should have been spent, in view of the amount of work done so far, and the baseline cost for the task, assignment, or resource. Earned value is also referred to as budgeted cost of work performed (BCWP).
In our example we use the beginning of each month as a control date for the earned value analysis.
Rajiv Misra 168
Earned Value Analysis Report-2
1. From “Project” select “Project Information” 2.Set “Status date” to 5/1/2002
Rajiv Misra 169
Earned Value Analysis Report-3
1.Select
“View”
2.Choose
“Report”3.Click on “Costs...”
4.Click “Select”
Rajiv Misra 170
Earned Value Analysis Report-4
1.Select “Earned Value” 2.Click on “Select”
Rajiv Misra 171
Fields in the Earned Value Table
Field Description
BCWS Budgeted cost of work scheduled, through the project status date
BCWP Budgeted cost of work performed, through the project status date
ACWP Actual cost of work performed, through the project status date
SV Earned value schedule variance, through the project status date
CV Earned value cost variance, through the project status date
BAC Budgeted at completion (the baseline cost of the task/project)
EAC Estimate at completion, (estimated cost of the task/project)
VAC Variance at completion, (=BAC – EAC)
Rajiv Misra 172
Earned Value Analysis Report-5-1
Cost calculations for activity 5:Uses 100% of resource B whose fixed cost is $450 & variable cost is $12/hr.BCWS = 450 + 13 (12*8) = $1698 BCWP = 450 + 13 (12*8)*(13/14) = $1608.86
Rajiv Misra 173
Earned Value Analysis Report-5-2
•If BCWS is larger than BCWP, then that task is behind schedule. Hence there is a negative schedule variance.
•Total ACWP is larger than BCWP; that is money spent on tasks performed has been larger than the budgeted amount.
Rajiv Misra 174
Earned Value Analysis Report-5-3
• EAC for activities that are not yet started (7, 8, 9, and 11) is set equal to BAC.
• It is presumed that the fact that there has been deviations in the started activities does not necessarily mean that there will be deviations in the future activities.
•EAC for activity 5 is calculated as follows: 450 + 14(12*8) = $1794
Rajiv Misra 175
Monthly Cost Schedule Report-1
1.Select “View”
2.Choose “Report”
Rajiv Misra 176
Monthly Cost Schedule Report-2
1.Choose “Cost”
2.Click on “Select”
3.Select “CashFlow”
4. Click on “Edit” icon.
Rajiv Misra 177
Monthly Cost Schedule Report-3
You can change the format and details of cost schedule report by changing the items within “Crosstab Report” view. For the monthly cost report change the time unit to months.
1.Select “Definition”
2.Select “Month”
3.Click “OK”
Rajiv Misra 178
Monthly Cost Schedule Report-4
Click on “Select” icon.
Rajiv Misra 179
Monthly Cost Schedule Report-5
Monthly Cost Schedule Report
Rajiv Misra 180
Save as your project as <username>-Part4-1