[12]Multi-Target Optimized Decision in the IT Surveillance (English)

Embed Size (px)

Citation preview

  • 8/4/2019 [12]Multi-Target Optimized Decision in the IT Surveillance (English)

    1/11

    Multi-Target Optimized Decision in the IT Surveillance

    Bi Th Khang

    H Ni, Ngy 23/06/2011

  • 8/4/2019 [12]Multi-Target Optimized Decision in the IT Surveillance (English)

    2/11

    INTRODUCTION

    Along with the development of information engineering surveillance,

    the manager must select reasonable optimized technology of network

    plan "I .To make construction duration shorter, investment lower andthe scientific disposition of manpower and material resources, it must

    carry out optimization of network plan.

    Usually, it is often conflict between each target of information

    engineering project. For instance, the engineering construction is rapid

    to build but the cost is up, sometimes the engineering cost is saved, but

    the project time is longer.

    It is impossible that an engineering project planning is finished with

    minimum construction duration, minimum resource and lowest

    investment at the same time.

  • 8/4/2019 [12]Multi-Target Optimized Decision in the IT Surveillance (English)

    3/11

    INTRODUCTION(continue)

    This is a multi-target optimized problem. Network planned optimization

    is a complex problem and the traditional methods are still not enough

    to satisfied.

    The traditional methods of optimization network plan are single-

    target methods. Under the certain condition, we can get a satisfied

    single-target of project through the continuously adjusting and seeking.

    When we think about the multi-target such as the optimization ofresource, cost and engineering time, we must use the new method that is

    multi-target method. It is very important to determine a relatively

    satisfactory scheme in existing feasible scheme by trading off various

    targets synthesize.

  • 8/4/2019 [12]Multi-Target Optimized Decision in the IT Surveillance (English)

    4/11

    THE MATHEMATICS OPTIMIZATION MODEL

    OF MULTI-TARGET NETWORK PLANNED

    We can use T to show the set up all selecting network picture (T1,..,Tn)

    in the network project. There are m target in network project, and each

    target has a different meaning (such as construction engineering timelimit, engineering cost and resource etc.). There, the goal of multi-target

    decision problem can be described : k : The importance weight of sub-target k.

    Z kp : The goal value of the p in selected network.

    Z k0 : The best value of sub-target k.

    n : The selected number of network picture.

    We consider three sub-target (m = 3) such minimum engineering time,

    minimum cost and the minimum resource, each sub-target can be calculated

    by following :

    : Minimum project time for only considering first sub-target.

    : Minimum cost for only considering second sub-target.

    : Minimum used resource for only considering third goal.

  • 8/4/2019 [12]Multi-Target Optimized Decision in the IT Surveillance (English)

    5/11

    A. Engineering time :

    There two method that can reduce the critical path :

    o Break down the critical work to many small work.o Organize parallel activity or parallel overlapping activity.

    Example : There are two work, A work needs to be completed for 15 says, B work

    need to be completed for 30 days , if the condition allows, work A and work B will

    be doing at the same time, This is illustrated in figure, the engineering time has

    changed from 45 to 35 days :

    The engineering time is independent work.

    The engineering time has changed from 45 to 35 days.

    THE CALCULATION OF EACH TARGET(1)

  • 8/4/2019 [12]Multi-Target Optimized Decision in the IT Surveillance (English)

    6/11

    B. Cost :

    The total costs of network plan include two parts, one is direct cost and the other is

    indirect cost. The relationship between the project cost as below :The directly cost rate of working i-j is expressed with Si-j

    DNi-j - the normal duration of working i-j

    DCi-j - the minimum duration of working i-j

    CCi-j -the direct cost needed for working i-j of minimum

    CNi-j - the direct cost needed for working i-j of normal

    Here is a procedure for scheduling a project. In this case, we identify the activities

    as follows :

    THE CALCULATION OF EACH TARGET(2)

  • 8/4/2019 [12]Multi-Target Optimized Decision in the IT Surveillance (English)

    7/11

    C. Resource of project :

    A various resources (such as labor force, mechanical and material etc.) that one

    company can offer in certain time havecertain limit, this has one problem howto use these resources economy and efficiently It is known that planned

    engineering duration is T, so the average requirement (Rm) of resource for T is:

    (The average requirement of resource)

    (The resource distribution of

    enure plan unbalanced level E)

    (The unbalanced level of resource)

    Obviously, the resource requirement for day by day is the more changing with

    the higher of E. So, we want to make resource allocation be balanced as far as

    possible when the E value reach to minimum.

    THE CALCULATION OF EACH TARGET(3)

  • 8/4/2019 [12]Multi-Target Optimized Decision in the IT Surveillance (English)

    8/11

    C. Resource of project:

    Example the optimized process :

    THE CALCULATION OF EACH TARGET(3)

  • 8/4/2019 [12]Multi-Target Optimized Decision in the IT Surveillance (English)

    9/11

    Because of the optimization network plan is a multi-target, problem, so we

    need to select a satisfactory network plan in many targets in synthesize

    consideration according to determine each target weight coefficient. Themeaning of weight coefficient has reflected the important level between

    each target essentially. It valde range is [0,1]

    The target can be compared each other to get every target weight, and than we get

    the judgment matrix B as following

    Each target weight coefficient ak

    DETERMINE EACH TARGET WEIGHT

    COEFFICIENT k

  • 8/4/2019 [12]Multi-Target Optimized Decision in the IT Surveillance (English)

    10/11

    It must point out that the multi-target optimization of network

    planned is a very complex problem.

    This slide has made some preliminary theories research for this

    problem, and given an optimization model of multi-target network

    plan.

    This model is a model with general comparison, and does not get the

    restriction of target number, can select proper target number

    according to actual condition.

    CONCLUSION

  • 8/4/2019 [12]Multi-Target Optimized Decision in the IT Surveillance (English)

    11/1114/04/2012MBA Trn Vit Dng 11