Upload
trinhmien
View
228
Download
0
Embed Size (px)
Citation preview
120/25-kV Gracefield Substation and 120-kV LinesINFORMATION ON THE SOLUTION SELECTED • November 2015
To meet growing demand for electricity, Hydro-Québec conducted draft-design studies in winter 2013-2014 to build a 120/25-kV* transformer substation in Gracefield and rebuild the 120-kV transmission line between Paugan substation, in Low, and Maniwaki substation, in Egan-Sud.
The 65-km line will be rebuilt in the middle of the corridor occupied by the current line. Since the plan calls for adding a circuit, a new 5-km line must be built that follows the existing line from Déléage to the entry to Maniwaki substation.
In addition, a 120-kV line about 5.3 km long must be built to supply the new Gracefield substation.
This bulletin describes the lowest-impact solution selected by Hydro-Québec.
Note: kV is the abbreviation for kilovolt, which is equal to 1,000 volts.
2
#
#
#
#
#
#
Gracefield, V
Low, CT
Déléage, M
Aumond, CT
Denholm, MKazabazua, M
Lac-Sainte-Marie, M
Bouchette, M
Messines, MBlue Sea, M
Egan-Sud, M
Sainte-Thérèse-de-la-
Gatineau, M
!
Maniwaki, V
!
Maniwaki, V
Kitigan Zibi, R
!
Maniwaki, V
La Vallée-de-la-Gatineau (MRC)
LacSainte-Marie
LacBlue Sea
LacHeney
Grand lacRond
Grand lacdes Cèdres
Gat
inea
u
LacPitòbìg
Petit lacdes Cèdres
LacCameron
Rivièr
e
LacKichi-gàngwenindam
Riv
ière
LacBois Franc
Ruisseau
Venosta
301
107
105
105
Paugansubstation
Maniwakisubstation
Messinessubstation
Kazabazuasubstation
Gracefieldsubstation
(to be rebuilt)
Mont-Lauriertap
76°0'
76°0'
46°2
0'
46°2
0'
46°1
0'
46°1
0'
46°0
'
46°0
'
45°5
0'
45°5
0'
0 3 6 km
UTM, zone 18, NAD837339_bu_tet_041_traceretenu_151015.mxd
120-KV LINES AND GRACEFIELD SUBSTATION
Composantes du projet
Tracé retenu pour l’alimentationdu poste de Gracefield
Tracé retenu
Ligne à reconstruire
Postes et lignes de transport existants
69 kV
120 kV
230 kV
#
#
Infrastructures
Route nationale
Route régionale
Route locale301
105
Limite
Municipalité
#
Boundary
Municipality
Infrastructure
Provincial highway
Secondary road
Tertiary road
301
105
Existing substations and transmission lines
69 kV
120 kV
230 kV
#
#
#
Project components
Selected route
Line to be rebuilt
Selected route for Gracefieldsubstation supply line
PROJECT TO DATE
In the previous steps of this project, Hydro-Québec carried out an inventory of the natural and human environments to better understand the host environment for the planned equipment.
Based on its studies and technical, economic and environmental criteria, Hydro-Québec proposed two routes for the Gracefield substation supply line and two variants for the transmission line’s entry at Maniwaki substation.
Hydro-Québec then held information and consultation sessions with various stakeholders. The company gathered the comments of representatives of local organizations, government departments, affected landowners and the general population.
The outcomes of these discussions, combined with the technical, economic and environmental studies, contributed to determining the lowest-impact solution.
3
LINE SEGMENT FROM PAUGAN SUBSTATION TO THE MONT-LAURIER SUBSTATION TAP
Paugan substation
�����������������
�����
���� ������������� �������������� ������������������������������
����
���������
������
� ���
�����
�������
�����
������
� ���
������
�����
�����
�������������������������� �����������
������
�����������������
�����
�������
�����
������
� ���
����
���������
������
� ���
������ �����������������
#
#
#
#
#
#
#
366
301
105
105
Paugansubstation
Maniwakisubstation
Messinessubstation
Kazabazuasubstation
Gracefieldsubstation
(to be rebuilt)
Mont-Lauriertap
7339
_bu_
tet_
043_
pylo
neP
aug_
1510
15.m
xd
Paugan–Maniwaki transmission line
Line segment between Paugan substation and the Mont-Laurier tap This segment will be rebuilt over 65 km in the middle of the existing corridor. The current line on wooden H-frames will be dismantled before construction begins.
The line will be supported by guyed steel lattice towers in forested areas and reduced-footprint towers in farmland.
To accommodate an additional circuit, the right-of-way must be widened by 4.3 m on either side of the line, for a total width of 39 m.
4
#
190
190
180
200
190
180
210200
220
210
200
190
180
180
180
190
180
220
200
190
190
190
180
180190
200
Riv
ière
Gat
inea
u
des
Quatre
Fourches
LacGodin
Lac Scott
Crique
Criq
uede
sH
all
LacGrier
Lac de laBarbotte
Rue Lafrance
Rue Montreuil
Chemin des
Amoureux
Rue McDougall
Rue
Poul
in
Rue
King
Chem
inde
laMon
tagne
Rue Éthier
Rue
Laur
ier
107
105
700
!Mont-Laurier tap
Maniwakisubstation
A
75°56'
75°56'
75°58'
75°58'
46°2
3'15
"
46°2
3'15
"
46°2
2'30
"
46°2
2'30
"
0 290 580 m
MTM, zone 9, NAD837339_bu_tet_021_Maniwaki_151015.mxd
Maniwakisubstation
A
Composantes du projet
Tracé retenu
Ligne à reconstruire
Ligne à démanteler
69 kV120 kV
Postes et lignes de transport existants
##
69 kV120 kV
Existing substations and transmission lines
##
Project components
Selected route
Line to be rebuilt
Line to be dismantled
EXPANSION OF THE ENTRY TO MANIWAKI SUBSTATION
Maniwaki substation
Paugan–Maniwaki transmission line
Line segment between Mont-Laurier tap and Maniwaki substation At Déléage, after the Mont-Laurier substation tap, the new line will run side-by-side with the existing line to the Route 105 crossing.
For the entry to Maniwaki substation, Hydro-Québec has selected Variant A, which routes the new line south of the current line, passing between existing buildings. The company optimized this variant based on concerns expressed by local representatives and affected landowners.
The line segment will be supported by four-legged lattice towers as well as reduced-footprint lattice towers.
This 4.5-km segment will be built to the west of the existing line and require widening the right-of-way by 26.3 m.
5
LINE SEGMENT FROM THE MONT-LAURIER SUBSTATION TAP TO MANIWAKI SUBSTATION
�����
�����
����������������
�����
�����������������������������
����
��������
������
�����
�����
�������
����
������
�����
�����
�������
����
������
�����
��������������������������������������������
��������������
�����
�����
����������������������������� � � ����
������ ������
������������
#
#
#
#
#
#
#
366
301
105
105
Paugansubstation
Maniwakisubstation
Messinessubstation
Kazabazuasubstation
Gracefieldsubstation
(to be rebuilt)
Mont-Lauriertap
73
39_b
u_te
t_04
4_py
lone
Man
i_15
1015
.mxd
6
105
Gracefieldsubstation
Planned Gracefieldsubstation
0 50 100 m
UTM, zone 18, NAD837339_bu_tet_045_poste_151015.mxd
Gracefield substation and supply line
Selected substation site The new 120/25-kV Gracefield substation will be adjacent to the existing substation, near Route 105. This site is close to the load centre and 25-kV distribution system and uses the existing access road and ditches. It minimizes environmental and social impacts by limiting modifications to the landscape.
The fenced area of the planned substation will be about 100 m by 75 m, not including drainage ditches on its periphery. While the planned substation will be built primarily on a lot belonging to Hydro-Québec, the company must acquire part of the adjacent property to accommodate all equipment.
The substation will be supplied by two 120-kV circuits from the main line. A prefabricated building will house the control, protection and telecommunications equipment.
Related work will be required at Paugan and Maniwaki substations to add or modify 120-kV outgoing line structures. This work will take place entirely on Hydro-Québec property.
Gracefield substation supply line Based on the draft-design studies and the public consultation process, Hydro-Québec selected Route A.
This 5.3-km route runs along property boundaries for about 1.8 km, then crosses Chemin Henri and 800 m further turns to follow the relief for better landscape integration and reduced visibility from Route 105. This route also limits the impact on farmland and some wetlands.
The substation supply line will be supported by guyed steel lattice towers in forested areas and reduced-footprint towers in farmland. The planned right-of-way is 39 m wide.
7
#
#
#
#
#
#
#
366
301
105
105
Paugansubstation
Maniwakisubstation
Messinessubstation
Kazabazuasubstation
Gracefieldsubstation
(to be rebuilt)
Mont-Lauriertap
7339
_bu_
tet_
042_
pylo
neG
race
_151
015.
mxd
GRACEFIELD SUBSTATION SUPPLY LINE
�����������������
�����
��������� ���������������������
����
�����
�����
�����
����
�����
�����
�����
������
��
�����
����������������������������� � � ����
������
������
�����
�����������������
##
230
210
200
170
160
200
210
200
190190
200
180
170
150
170
200
200
180
200
160
180
220
200
160
200
190
220230
210
190
180
150
220
200
180
32B32A3130
33A
30B
26
15A
29 28 2730A
44A 43A 4142
17
18
19
20
21
3031
32 33 34 35
40 39 38 37 36 35 34 33 32 31
151515
16
33B 34 35
26
25
Rivière
Gatin
eau
LacPaquin
Rue
Saint-Jo
seph
Chem
inH
enriChemin
Lachapelle
Chem
i ndu
Dom
a ine
Chemin Bertrand
Chemin
105
Chem
inde
Riviè
re-G
atine
au
la
route
Selec
ted
Current Gracefield substation
Planned Gracefield substation
76°0'
76°0'
76°2'
76°2'
46°7
'30"
46°7
'30"
46°6
'45"
46°6
'45"
46°6
'
46°6
'
0 330 660 m
MTM, zone 9, NAD837339_bu_tet_020_derivation_151015.mxd
Project components
Planned Gracefield substationSelected routeTransmission line to be rebuilt
The property boundaries shown on this map areapproximate and provided for reference only.
## Existing 69-kV substation andtransmission line
100 %
2015E1395-ACe document est également publié en français. This is a translation of the original French text.
Tangible support for community development Hydro-Québec sees its projects as an opportunity to participate in the development of host communities through the Integrated Enhancement Program (IEP). Once the work has begun, the company grants eligible organizations funding equivalent to 1% of the initially authorized value of the new facilities covered by the IEP.
Schedule Permitting 2016
Land clearing, dismantling of line and construction of substation and new lines Fall 2016–Fall 2018
Dismantling of existing substation 2018-2020
About the construction work Hydro-Québec has planned two phases of construction work. The first phase involves building Gracefield substation and its supply line and rebuilding the transmission line between Paugan substation and the Gracefield substation tap.
The second phase consists of rebuilding the transmission line to the Mont-Laurier tap and building the new line segment from the tap to Maniwaki substation.
To minimize the project’s impacts, Hydro-Québec will implement a range of mitigation measures, ensure environmental compliance monitoring of the worksite and rehabilitate the sites after construction.
Public participationStarting in 2014, Hydro-Québec informed and consulted with the various groups affected by the project: official representatives of the communities, local organizations, members of the business community, ministries, affected landowners and citizens.
This process made it possible to develop mitigation measures to adapt the project to local realities, taking into account the results of the technical, economic and environmental studies carried out for the project.
Once the necessary government permits have been obtained, Hydro-Québec will contact the groups affected to present the planned construction schedule.
For more information Julie Léonard Advisor – Community Relations – Laurentides Direction – Affaires régionales et collectivités E-mail: [email protected]
Info-project Line – Laurentides1 8 0 0 4 6 5-1 5 2 1, ext. 6 0 2 2
www.hydroquebec.com/projects/gracefield.html