Upload
buinga
View
217
Download
0
Embed Size (px)
Citation preview
Gas Natural Fenosa’s BESS
Project
John Chamberlain
Technology Project Manager
Madrid
February 16th 2016
Index
1. Who we are
2. The Project and it’s Objectives
3. Motivation in Grid Connected Storage
4. Initial Results
5. Main lessons Learnt
6. Next Steps
7. Initial Conclusions
2
Who we are
1
Gas Natural Fenosa
Who we are
• Gas Natural Fenosa is the largest gas and electricity company
in Spain and in Latin America, leading the natural gas sales
market in the Iberian Peninsula, and is the biggest distributor
of natural gas in Latin America. Currently the company is
present in over 30 countries and has around 23 million
customers worldwide.
• Benchmark operator in the Atlantic and Mediterranean
basins of LNG and natural gas supplies
1 – Figures 31/12 /2014
4
The Project and it’s Objectives
2
The Project and It’s Objectives
Principal Project Facts
• An ambitious 5 year testing programme to evaluate a storage
solution in up to 5 different locations across Spain
• Compact Storage solution based upon Toshiba’s SCiBTM
Lithium-Titanate Technology
• Two independent battery systems with a combined storage
capacity of 776 kWh and 500kW power capacity.
• Start-Up achieved in Autumn 2015
• Project Partners6
The Project and It’s Objectives
BESS System Definition
• The BESS system is integrated into two 6 meters long standard
width containers for easy transportation.
The main characteristics of each
unit are:
• The combined system has a capacity of 500 kVAs / 776 kWh.
Importantly each container can work independently or together
Auxiliary systems
(control, communications) Power ElectronicsBatteries
Max. Power 250 KVAs
Stored energy 388 kWh
Power voltage 290V
Auxiliary voltage 240V
7
The Project and It’s Objectives
First Demonstration site: Alcalá substation
• Representative site that hosted the PRICE smart-grid
demonstration project.
MV/LV Grid
AutomationEnergy Management
Distributed
GenerationDemand
Management
8
Site access pathStorage System
The Project and It’s Objectives
First Demonstration site: Alcalá substation
• Medium voltage line 720 starting at the
Alcala substation has been selected:
• The chosen line 720 has shown power
demand variations adequate for the limits
of the BESS system .
Alcala substation
132 kV / 45 kV / 15 kV9
Battery (BESS)
ContainersStep up
TransformersIntelligent secondary
substation
The Project and It’s Objectives
First Demonstration site: Alcalá substation
10
Motivation in Grid Connected Storage
3
Motivation in Grid Connected Storage
Evolution of Spain’s renewable generation
• Gas Natural Fenosa are interested in testing and validating this
technology for different applications/cases in distribution grid, at
different locations (need for portability) to validate the technology and
identify the business case storage. GNF provides the connection with
the grid and will operate the BESS.
• Renewable generation (hydro, wind, solar, thermal solar, biomass)
accounts for 50% of the total installed power and 40% of the energy
consumed.
0
10 000
20 000
30 000
40 000
50 000
60 000
Other
Thermosolar
PV
Wind
Small Hydro
Hydro
0
20 000
40 000
60 000
80 000
100 000
120 000
Installed power (MW). Source REE Energy produced (GWh). Source REE12
Motivation in Grid Connected Storage
Evolution of Spain’s renewable generation
• Storage is identified as one of the important technology solutions to
integrate and optimize Renewable Energy generation.
• Amongst the current storage technologies, batteries have the
advantage of the good efficiency and scalability. Li-ion batteries are
benefitting from a technology push in other sectors such as the car
industry.
• For distribution networks, a mobile solution is considered the most
ideal solution.
• Toshiba are interested in testing and verifying their SCiB (lithium)
storage technology at different locations and for different user-cases.
In this project they provide the BESS (Battery Energy Storage
System).
13
Initial Results
4
Initial Results
Smoothening/Flattening the Demand Load of the Al1–720 line
• The recent average demand from of the clients A, is used by the
battery’s local control system to determine the algorithm that
determines the periods of storage (current withdrawal) and current
injection B with the aim to levelize the load delivered to the grid by the
substation C.
A
B
C
15
Initial Results
Smoothening/Flattening the Demand Load of the Al1–720 line
• The line chosen shows relatively large variations over relatively short
periods of time with oscillations in the range of 500 kW being
observed, similar to the stored energy capacity.
• The real client demand (green curve) is subsequently adjusted to the
averaged the medium demand of the previous hours (blue line) by the
operation of the storage system (black curve) resulting in a real
“levelized” demand being delivered to the grid (red curve).
16
Main lessons Learnt
5
Main Lessons Learnt
There are areas for improvement
• The technology is new and there are areas of improvement that
we hope to address throughout this project as we all gain
experience:
• Simplify the installation for the targeted market.
• Increase energy density to obtain more power in a given
container and optimize the cell management within the
batteries.
• Reduce the cell calibration periods to maximise availability
• Control logic needs to be fully integrated into the power
electronics, not layered over it for faster and finer response
and control of the battery’s performance. Also we need to
develop and optimize control algorithms for real case studies.
• Communication systems can be optimized.
18
Next Steps
6
Next Steps
Extensive testing
• Additional user cases to be tested will hopefully include:
• Intermittent RES support
• Scheduled charge and discharge times and performance over
the five years
• Voltage drop avoidance (long MV lines)
• Voltage regulation (reactive)
• New Sites
• End of long MV line or MV line with a high intermittent sources
connected along it
• LV grid with temporary surges in power demand
• Our goal is simply to identify and analyze case studies where the
use of a storage system could potentially resolve future
issues/problems in the most economic way.20
Initial Conclusions
7
Initial Conclusions
• Storage integrated into the electrical system may well provide
a technical solution to the challenges presented by a more
variable generation scenario (Renewable Generation).
• This technology is in development. All the parties need to
understand the requirements and potential of the solution.
• Project allows both companies to be at the forefront of these
developments and to advance them towards commercial
applications if and when the Regulation permits.
22
Muchas gracias
Esta presentación es propiedad de Gas Natural
Fenosa. Tanto su contenido temático como diseño
gráfico es para uso exclusivo de su personal.
©Copyright Gas Natural SDG, S.A.