27
Addendum No. 4 page 1 of 3 ADDENDUM NO. 4 11/2/16 PROJECT: ISSUED: CARTS Wednesday, November 2, 2016 Tucker Hill Lane Complex Jackson & McElhaney Architects 5300 Tucker Hill Lane 1135 West 6 th Street, Suite 125 Cedar Creek, Texas 78612 Austin, Texas 78703 NOTE: This addendum amends and thereby supersedes the Drawings, Project Manual and RFP on the referenced project. (IV) Item #1 - Refer to Addendum No. 2 Item #7, the Buy America Certification page was inadvertently left out at the end of Section 32 3113, CHAIN LINK FENCES AND GATES. Incorporate the Buy America Certification page at the end of this section. (IV) Item #2 - Bidder Question with Answer by Architect: Q: Addendum No. 2, Item 8 – shows concrete design. Just clarify, are we to use the Geotech for the subgrade? A: Yes, use the Heavy Duty Traffic recommendations for Lime Stabilized Subgrade and Crushed Limestone Base Material. (IV) Item #3 - Bidder Question with Answer by Architect: Q: We are unable to locate the spec on the Window Blinds, will they be provided by the owner or will a spec be released in a future amendment? A: Rolling Window Shades are covered by Allowance No. 13. (IV) Item #4 - Bidder Question with Answer by CARTS: Q: Are data, access controls, fire alarm and telecommunications required? If so, please provide specifications. A: Data and telecommunications wiring and systems will be provided by the owner. (Back boxes and conduits shall be provided as indicated on drawings.) No fire alarm is included in the project since it is not required for occupant notification. However, the fire sprinkler does have the requirement for off-site monitoring as indicated on the fire protection drawings. Access Controls: Proximity reader/keypads shall be added to the project and be located at each door noted in the Door Hardware Schedule to have a Card Reader (Provide a total of 9 readers). Please see the attached product information for the HID EntryProx Reader. (Owner will provide main controller unit for these readers in the IT Room.)

11/2/16 - RideCARTSridecarts.weebly.com/uploads/1/1/1/1/11111920/... · 11/2/2016  · 20110319-enrtyprox-revc-ds-en North America: +1 949 732 2000 Toll Free: 1 800 237 7769 Europe,

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 11/2/16 - RideCARTSridecarts.weebly.com/uploads/1/1/1/1/11111920/... · 11/2/2016  · 20110319-enrtyprox-revc-ds-en North America: +1 949 732 2000 Toll Free: 1 800 237 7769 Europe,

Addendum No. 4 page 1 of 3

ADDENDUM NO. 4

1111//22//1166 PROJECT: ISSUED: CARTS Wednesday, November 2, 2016 Tucker Hill Lane Complex Jackson & McElhaney Architects 5300 Tucker Hill Lane 1135 West 6th Street, Suite 125 Cedar Creek, Texas 78612 Austin, Texas 78703 NOTE: This addendum amends and thereby supersedes the Drawings, Project Manual and RFP on

the referenced project.

(IV) Item #1 - Refer to Addendum No. 2 Item #7, the Buy America Certification page was

inadvertently left out at the end of Section 32 3113, CHAIN LINK FENCES AND GATES. Incorporate the Buy America Certification page at the end of this section.

(IV) Item #2 - Bidder Question with Answer by Architect:

Q: Addendum No. 2, Item 8 – shows concrete design. Just clarify, are we to use the Geotech for the subgrade? A: Yes, use the Heavy Duty Traffic recommendations for Lime Stabilized Subgrade and Crushed Limestone Base Material.

(IV) Item #3 - Bidder Question with Answer by Architect: Q: We are unable to locate the spec on the Window Blinds, will they be provided by the owner or will a spec be released in a future amendment? A: Rolling Window Shades are covered by Allowance No. 13.

(IV) Item #4 - Bidder Question with Answer by CARTS:

Q: Are data, access controls, fire alarm and telecommunications required? If so, please provide specifications. A:

• Data and telecommunications wiring and systems will be provided by the owner. (Back boxes and conduits shall be provided as indicated on drawings.)

• No fire alarm is included in the project since it is not required for occupant notification. However, the fire sprinkler does have the requirement for off-site monitoring as indicated on the fire protection drawings.

• Access Controls: Proximity reader/keypads shall be added to the project and be located at each door noted in the Door Hardware Schedule to have a Card Reader (Provide a total of 9 readers). Please see the attached product information for the HID EntryProx Reader. (Owner will provide main controller unit for these readers in the IT Room.)

Page 2: 11/2/16 - RideCARTSridecarts.weebly.com/uploads/1/1/1/1/11111920/... · 11/2/2016  · 20110319-enrtyprox-revc-ds-en North America: +1 949 732 2000 Toll Free: 1 800 237 7769 Europe,

Addendum No. 4 page 2 of 3

(IV) Item #5 - Bidder Question with Answer by CARTS: Q: Will the security be taken care of in house for the project? A: Yes, security will be provided by Owner. (See Item #4 above for Access Control components to be provided by Contractor.)

(IV) Item #6 - Bidder Question with Answer by CARTS: Q: We didn’t see any of the following systems in the specification; low voltage cabling, access control, video surveillance, and A/V. A: Low voltage cabling, video surveillance, and A/V systems will be provided by owner. For information on access control, see Item #4.

(IV) Item #7 - Bidder Question with Answer by CARTS: Q: In Reviewing the Building and Heavy Highway rates, some categories are not reflected. While these can be added at a later date, how should the rates not shown be addressed during the bidding process? A: We believe the information in the RFP is the information available.

(IV) Item #8 - Bidder Question with Answer by CARTS:

Q: In the Request for Proposals it is stated " FTA funding will be utilized...all state and federal construction guidelines and requirements must be adhered to, including but not limited to....." With this in mind, have all required components been included in the project specifications? If not, are we to include those items referenced in the FTA in this bid? A: Proposals must comply with the FTA construction guidelines and requirements.

(IV) Item #9 - Bidder Question with Answer by Architect & Civil Engineer: Q: Addendum No. 1 added piles underneath the radio antenna tower; this appears to be in direct conflict with an existing utility line per sheet V1-13R. A: The conflict between foundation and utilities is acknowledged. The design team is working on a resolution, however it will not be resolved by bid date. Please bid the project as if there is no conflict.

(IV) Item #10 - Refer to attached updated Project Manual Table of Contents which includes all changes up to and including this addendum.

(IV) Item #11 - Refer to Project Manual, Section 01 2100, ALLOWANCES. Clarification: The cost of

each allowance listed shall contain the General Conditions associated with that allowance.

(IV) Item #12 - Refer to the attached NEW specification Section 07 9200, JOINT SEALANTS to be

incorporated into the project. (IV) Item #13 - Refer to attached Section 09 1001, INTERIOR FINISH SCHEDULE. Replace existing

section with this new section. Revisions included are noted in bold & italicized text. (IV) Item #14 - Refer to attached revised specification Section 10 2800, TOILET, BATH AND

LAUNDRY ACCESSORIES. Changes in this section include quantities of toilet accessories added to description for clarity. Replace Section 10 2800 previously issued in Addendum No. 1 with this attached section.

(IV) Item #15 - Refer to attached revised Civil Sheet 12.1R, Enlarged Grading Plan. Underground

Rainwater Collection System has been revised. Install underground PVC system as shown on this sheet, instead of the underground trunk line shown on sheets A1.0 and

Page 3: 11/2/16 - RideCARTSridecarts.weebly.com/uploads/1/1/1/1/11111920/... · 11/2/2016  · 20110319-enrtyprox-revc-ds-en North America: +1 949 732 2000 Toll Free: 1 800 237 7769 Europe,

Addendum No. 4 page 3 of 3

A2.0. The Underground branch piping routed from downspouts to trunk shall be 4” schedule 40 PVC; align branch with every downspout shown on A2.0 (except branch M1, where it shall tie into the 18” storm sewer). Connect each branch to trunk line with 4”x8” wye fitting. Refer to Cistern Piping on A1.1 for 8” goose neck filler pipe above ground.

(IV) Item #16 - Refer to attached, revised Sheet L1.4, Details. Replace existing sheet with this new

sheet. Revisions include: • Revised 10L1.4 Note about Reinforced Concrete Footing

(IV) Item #17 - Bidder Question with Answer by Architect:

Q: FOUNDATION PADS FOR OUTSIDE EQUIPMENT: Only Generator, Radio Tower, and Cistern have foundation pad details (S3.02); HOWEVER, sheet A1.1 shows a propane tank pad as well. Is this propane tank pad to be included in the base bid? Need details, if so.

A: The foundation for the propane tank is not yet designed, however for bidding purposes include cost for a propane tank foundation that matches the size and configuration of the electric generator foundation.

(IV) Item #18 - Bidder Question with Answer by Structural Engineer:

Q: Will there be specifications provided for Division 3 – Concrete Planks? A: We do not intend to issue any additional specifications for concrete planks. The planks are specified in the current documents.

(IV) Item #19 - Bidder Question with Answer by Structural Engineer:

Q: Spec 3.03: Static Pile Test: Please confirm that static load testing is not necessary if 5 piles are dynamically tested per ASTM D 4945. A: Static load test is not required if dynamic testing is performed.

(IV) Item #20 - Bidder Question with Answer by Structural Engineer: Q: Spec 3.07.C.2: Low-Strain Integrity Measurement: Please confirm that this is not necessary with the ability to visually inspect the interior of the closed-end pipe piles. A: All testing is required per specifications.

END OF ADDENDUM NO. 4 SUMMARY

Attachments: • (Four 8-1/2”x11” pages) Key Pad and EntryProx. Reader Information • (Four 8-1/2”x11” pages) Project Manual Table of Contents dated 11/2/16 • (Six 8-1/2”x11” pages) Section 07 9200, JOINT SEALANTS dated 11/2/16 • (Five 8-1/2”x11” pages) Section 09 1001, INTERIOR FINISH SCHEDULE dated 11/2/16 • (Three 8-1/2”x11” pages) Section 10 2800, TOILET, BATH AND LAUNDRY ACCESSORIES dated 11/2/16 • (One 24”x36” sheet) Civil Sheet 12.1R, Enlarged Grading Plan dated 11/2/16 • (One 24”x36” sheet) L1.4, Details dated 11/2/16

Page 4: 11/2/16 - RideCARTSridecarts.weebly.com/uploads/1/1/1/1/11111920/... · 11/2/2016  · 20110319-enrtyprox-revc-ds-en North America: +1 949 732 2000 Toll Free: 1 800 237 7769 Europe,

HID Global North America 15370 Barranca Parkway Irvine, CA 92618 Tel: 1 800 237 7769 Tel: +1 949 732 2000 Fax: +1 949 732 2360 Specific Model Number: EntryProx 4045CGNU0 12Volt DC on all components (Keypads, door locks, maglocks, Request to Exit devices, etc). Most devices for access control systems have options that are available to use 12V DC, 12V AC, and 24V AC. Our systems are configured to use 12V DC. It would be best to keep everything using the 12V DC if possible.

Page 5: 11/2/16 - RideCARTSridecarts.weebly.com/uploads/1/1/1/1/11111920/... · 11/2/2016  · 20110319-enrtyprox-revc-ds-en North America: +1 949 732 2000 Toll Free: 1 800 237 7769 Europe,

hidglobal.com

LOGICAL ACCESS SOLUTIONS

EntryProx™ ReaderSTAND-ALONE, SINGLE-DOOR PROXIMITY READER

� Trouble-Free Keypad Input – Extra secure keypad enables PIN entry or programming.

� Remote Monitoring - Configurable to be used in conjunction with an on-line system.

� Faster Programming – Batch load up to 2,000 HID cards or keytags with a single keypad command sequence.

� Efficient Badge Administration – Block Delete allows deletion of cards/keytags by user location.

HID’s EntryProx™ stand-alone reader truly

stands alone in what it delivers.

Compatible with all HID proximity cards and

keytags, EntryProx™ provides single-door

proximity access control and is ideal for unique

applications. The reader, designed to be

weather- and vandal-resistant, can be mounted

indoors or outdoors up to 10 feet away from

the control unit using the detachable antenna

module. The versatile, attractive unit is easily

modified to become an on-line reader by

switching to Wiegand output mode, allowing it

to connect to any OEM controller and provide

card and PIN output.

The ADA-compliant 12-position keypad features

large white-on-black numbers, enabling

PIN entry or programming, with optional audio

feedback and a raised dot on the 5 key.

For extra security, EntryProx’s keypad

incorporates the “invalid PIN” lockout feature,

preventing unauthorized trial-and-error PIN

code entry.

The reader also features faster programming,

enabling end-users to batch load up to

2,000 HID cards or keytags, in any format up to

37 bits, by entering a single keypad

command sequence. A Block Delete feature

allows for efficient badge administration by

deleting a sequential range of cards/keytags

from the EntryProx by user location.

Customers can select the HID EntryProx Reader

with confidence because HID offers a

lifetime product warranty and global technical

support.

Page 6: 11/2/16 - RideCARTSridecarts.weebly.com/uploads/1/1/1/1/11111920/... · 11/2/2016  · 20110319-enrtyprox-revc-ds-en North America: +1 949 732 2000 Toll Free: 1 800 237 7769 Europe,

© 2012 HID Global Corporation. All rights reserved. HID, the HID logo, Crescendo, naviGO, HID on the Desktop, and iCLASS are trademarks or registered trademarks of HID Global in the U.S. and/or other countries. All other trademarks, service marks, and product or service names are trademarks or registered trademarks of their respective owners. 20110319-enrtyprox-revc-ds-en

North America: +1 949 732 2000Toll Free: 1 800 237 7769 Europe, Middle East, Africa: +44 1440 714 850Asia Pacific: +852 3160 9800Latin America: +52 (55) 5081 1650

hidglobal.com

SPECIFICATIONS

� Card Programming – 26-bit format - batch enrollment; Other formats - present card to enroll

� Facility Code Processing Options (26-bit only) – Check Facility Code and Card ID; Check Facility Code only (accept any ID#)

� Options – Various options are user programmable – not ordered by model. Accessories: Security Tool 04-0001-03

FEATURES: � **Monitor Inputs – Door Position - N.O. dry contact. Request to

Exit - N.O. dry contact

� Sounder - 4000Hz, defeatable

� Relay Outputs – Strike Relay - Form C, switches up to 1A @ 30 VDC. Aux Relay - Form C, switches up to 1A @ 30 VDC

� LEDs – Bi-Color (Red/Green), Amber, Infrared (use with Data Transfer Device (DTD) accessory)

� Operation Strike Time: 1 - 99 seconds (Adjustable); Strike Mode: Access Timer or Toggle/Latch; Door Ajar Time: 10 - 990 Seconds (Adjustable)

*Model Name EntryProx™

Model NumberEntryProx 4045CGNU0

EntryProx plus 10 Keytags 4045CGKU0EntryProx plus 20 ProxCard II 4045CGCU0

**Read Range

ISOProx® II card - Up to 2.5” (6.35 cm)Smart ISOProx® II - Up to 2.5” (6.35 cm)

HID Proximity & MIFARE® Card - Up to 2.5” (6.35 cm)HID Proximity & iCLASS® Card - Up to 2.5” (6.35 cm)

ProxKey™ II key fob - Up to 1.5” (3.8 cm)ProxCard® II card - Up to 3.0” (7.6 cm)DuoProx® II card - Up to 2.5” (6.35 cm)

Smart DuoProx® II - Up to 2.5” (6.35 cm)ProxCard® Plus card - Up to 1.0” (2.5 cm)

Microprox® Tag - Up to 2.0 “ (5.1 cm)

Mounting Mounts on US or EU single gang box, wall surface, or on glass with included adhesive pads

Color Gray

Keypad No

Dimensions 5.25” x 2.75” x 1.625” (13.33 cm x 6.98 cm x 4.1 cm)

Power Supply 10 - 15 VDC, reverse voltage protectedLinear supply recommended

Power Requirements

(Standard Power)

150 mA @ 12 VDC

Operating Temperature -31° to 150°F (-35° to 66°C)

Operating Humidity 5% to 95% relative humidity non-condensing

Transmit Frequency 125 kHz

Environmental IP55

Cable Distance

Remote Reader Module - 10 feet (3 m)Wiegand Interface - 500 feet (152 m)

Recommended cable is ALPHA 1295C (22AWG) 5-conductor stranded with overall shield or equivalent

CertificationsUL294/cUL (US), FCC Certification (US), IC (Canada), CE (EU), C-tick (Australia,

New Zealand),SRRC (China), MIC (Korea), NCC (Taiwan), MIC (Japan), iDA (Singapore), RoHS

Housing Material UL94 Polycarbonate

Warranty Lifetime

*Consult How to Order Guide for specific ordering instructions.**Dependent upon installation conditions

Page 7: 11/2/16 - RideCARTSridecarts.weebly.com/uploads/1/1/1/1/11111920/... · 11/2/2016  · 20110319-enrtyprox-revc-ds-en North America: +1 949 732 2000 Toll Free: 1 800 237 7769 Europe,

Signature of Authorized Person: May 31, 2016

Robert Cresswell: Manager – Global Product Compliance Date of Signature:

Phone/303-404-6700

Fax/ 303.404.6840

Web/ www.hidcorp.com

CER-00194, Rev.001

DoC-R-TTE-Prox-Reader-4045C

Technical/Compliance File Held by:HID Global Corporation (Compliance Engineering Department)

10385 Westmoor Drive, Suite 300, Westminster, CO 80021 USA

Place and Date of Issuance: Westminster, CO USA on January 28, 2009

R&TTE Radio Class: Class 1 (Commission Decision 2006/771/EC)

Testing Organization Involved:

CKC Laboratories, Inc.

5473A Clouds Rest, Mariposa, CA 95338 USA

The following harmonized standards and/or other normative documents were applied in full to show conformity to the

Directives:

Product Specifications Standard(s) Applied in Full

Safety EN60950-1: 2006/ A11:2009 +A1:2010 +A12:2011

EMC EN 301 489-1 V1.9.2, EN 301 489-3 V1.6.1, EN 50130-4:2011

Spectrum ETSI EN 300 330-2 V1.5.1, ETSI EN 302 291-2 V1.1.1

RoHS2 EN 50581:2012

Supplementary Information:

Trade Name(s): Prox Reader

Further Description:

(only where required)EntryProx

Model Number(s): 4045C

and applicable parts of

Electromagnetic Compatibility (EMC) Directive: 2004/108/EC

Product / Device Information:

Product Type: 125 kHz Proximity Reader

Declaration of Conformity (DoC)

We, HID Global Corporation located at 611 Center Ride Drive, Austin TX, 78753 USA, declare under our sole

responsibility that the product(s) described in the tables are in conformity with the essential requirements and

other relevant reqirements of the following Directives:

Radio and Telecommunications Terminal Equipment (R&TTE) Directive: 1999/5/EC

Low voltage (LVD) Directive: 2006/95/EC

RoHS Recast (RoHS2) Directive: 2011/65/EU

An ASSA ABLOY Group brand ASSA ABLOY

Page 8: 11/2/16 - RideCARTSridecarts.weebly.com/uploads/1/1/1/1/11111920/... · 11/2/2016  · 20110319-enrtyprox-revc-ds-en North America: +1 949 732 2000 Toll Free: 1 800 237 7769 Europe,

CARTS Tucker Hill Lane Complex Addendum No. 4 Cedar Creek, Texas 5300 Tucker Hill Lane November 2, 2016

TABLE OF CONTENTS 1 of 4

Tucker Hill Lane Complex

5300 Tucker Hill Lane Cedar Creek, Texas

Table of Contents PREFACE All Preface documents are part of the Project Contract whether inserted or included by reference:

1111--22--1166 Request for Proposal (RFP provided under separate cover) Performance Bond & Payment Bond,

AIA Document A312 (included by reference) Standard Form of Agreement Between Owner and Contractor,

AIA Document A101 (included by reference) General Conditions of the Contract for Construction, AIA Document A201 (included by reference) Supplementary General Conditions for Construction Contracts

DIVISION 01 - GENERAL REQUIREMENTS 01 1000 SUMMARY 01 2100 ALLOWANCES 01 2200 UNIT PRICES 01 2300 ALTERNATES 01 3000 ADMINISTRATIVE REQUIREMENTS 01 4000 QUALITY REQUIREMENTS 01 4216 DEFINITIONS 01 6000 PRODUCT REQUIREMENTS 01 7000 EXECUTION AND CLOSEOUT REQUIREMENTS 01 7800 CLOSEOUT SUBMITTALS

Page 9: 11/2/16 - RideCARTSridecarts.weebly.com/uploads/1/1/1/1/11111920/... · 11/2/2016  · 20110319-enrtyprox-revc-ds-en North America: +1 949 732 2000 Toll Free: 1 800 237 7769 Europe,

CARTS Tucker Hill Lane Complex Addendum No. 4 Cedar Creek, Texas 5300 Tucker Hill Lane November 2, 2016

TABLE OF CONTENTS 2 of 4

DIVISION 02 - EXISTING CONDITIONS 02 0000 GEOTECHNICAL INVESTIGATION & MEMO DIVISION 03 - CONCRETE 03 3000 CAST-IN-PLACE CONCRETE

1111--22--1166 DIVISION 05 - METALS

05 1200 STRUCTURAL STEEL FRAMING 05 3100 STEEL DECKING

05 4000 COLD-FORMED METAL FRAMING DIVISION 06 - WOOD, PLASTICS AND COMPOSITES 06 1000 ROUGH CARPENTRY 06 4100 ARCHITECTURAL WOOD CASEWORK

DIVISION 07 - THERMAL AND MOISTURE PROTECTION 07 2100 THERMAL INSULATION 07 2500 WEATHER BARRIERS 07 4113 METAL ROOF PANELS 07 4213 METAL WALL PANELS 07 4264 METAL COMPOSITE MATERIAL WALL PANELS 07 5423 THERMOPLASTIC-POLYOLEFIN ROOFING (TPO) 07 9200 JOINT SEALANTS

DIVISION 08 - OPENINGS 08 1113 HOLLOW METAL DOORS AND FRAMES 08 1216 08 1416

INTERIOR ALUMINUM FRAMES FLUSH WOOD DOORS

08 3100 08 3200 08 4313

ACCESS DOORS AND PANELS SLIDING GLASS DOORS ALUMINUM-FRAMED STOREFRONTS

08 5113 ALUMINUM WINDOWS 08 7100 DOOR HARDWARE 08 8000 08 9100 08 9200

GLAZING LOUVERS LOUVERED EQUIPMENT ENCLOSURES

DIVISION 09 - FINISHES 09 1000 INTERIOR CODE KEY 09 1001 INTERIOR FINISH SCHEDULE

09 2116 GYPSUM BOARD ASSEMBLIES 09 3000 TILING

Page 10: 11/2/16 - RideCARTSridecarts.weebly.com/uploads/1/1/1/1/11111920/... · 11/2/2016  · 20110319-enrtyprox-revc-ds-en North America: +1 949 732 2000 Toll Free: 1 800 237 7769 Europe,

CARTS Tucker Hill Lane Complex Addendum No. 4 Cedar Creek, Texas 5300 Tucker Hill Lane November 2, 2016

TABLE OF CONTENTS 3 of 4

09 5100 09 6500 09 6813 09 9000 09 9724

SUSPENDED ACOUSTICAL CEILINGS RESILIENT FLOORING TILE CARPETING PAINTING AND COATING EXTERIOR CONCRETE COATING SYSTEM

DIVISION 10 - SPECIALTIES 10 2113.16 10 2800

PLASTIC-LAMINATE-CLAD TOILET COMPARTMENTS TOILET, BATH AND LAUNDRY ACCESSORIES

10 4400 FIRE PROTECTION SPECIALTIES 10 5100 LOCKERS

1111--22--1166

DIVISION 14 - CONVEYING EQUIPMENT 14 2400 MACHINE ROOM-LESS HYDRAULIC ELEVATORS (Sections noted as “JIG” were prepared by Jose I. Guerra, Inc.)

DIVISION 21 FIRE SUPPRESSION 210517 Sleeves & Sleeve Seals for Fire Suppression Piping ...................................................JIG 210518 Escutcheons for Fire Suppression Piping .....................................................................JIG 210533 Heat Tracing for Fire Suppression Piping .....................................................................JIG 210553 Identification for Fire Suppression ................................................................................JIG 210700 Fire Suppression Systems Insulation ...........................................................................JIG 211313 Wet Pipe Sprinkler System ...........................................................................................JIG

DIVISION 22 PLUMBING 220513 Common Motor Requirements for Plumbing Equipment ..............................................JIG 220517 Sleeves and Sleeve Seals for Plumbing Piping............................................................JIG 220518 Escutcheons for Plumbing Piping .................................................................................JIG 220519 Meters and Gages for Plumbing Piping ........................................................................JIG 220523 General Duty Valves for Plumbing Piping ....................................................................JIG 220529 Hangers and Supports for Plumbing Piping & Equipment ............................................JIG 220553 Identification for Plumbing Piping & Equipment ............................................................JIG 220719 Plumbing Piping Insulation ...........................................................................................JIG 221116 Domestic Water Piping .................................................................................................JIG 221119 Domestic Water Piping Specialties ...............................................................................JIG 221316 Sanitary Waste & Vent Piping.......................................................................................JIG 221319 Sanitary Waste Piping Specialties ................................................................................JIG 221413 Facility Storm Drainage Piping .....................................................................................JIG 221429 Sump Pumps ................................................................................................................JIG 223300 Electric Domestic Water Heaters ..................................................................................JIG 224213.13 Commercial Water Closets ...........................................................................................JIG 224213.16 Commercial Urinals ......................................................................................................JIG 224216.13 Commercial Lavatories .................................................................................................JIG 224216.16 Commercial Sinks .........................................................................................................JIG 224716 Pressure Water Coolers ...............................................................................................JIG

Page 11: 11/2/16 - RideCARTSridecarts.weebly.com/uploads/1/1/1/1/11111920/... · 11/2/2016  · 20110319-enrtyprox-revc-ds-en North America: +1 949 732 2000 Toll Free: 1 800 237 7769 Europe,

CARTS Tucker Hill Lane Complex Addendum No. 4 Cedar Creek, Texas 5300 Tucker Hill Lane November 2, 2016

TABLE OF CONTENTS 4 of 4

DIVISION 23 HEATING VENTILATING AND AIR CONDITIONING 230500 Common Work Results for HVAC ..................................................................................JIG 230513 Common Motor Requirements for HVAC Equipment… .................................................JIG 230529 Hangers and Supports for HVAC Piping and Equipment... ............................................JIG 230923 Testing, Adjusting, and Balancing for HVAC… ..............................................................JIG 230700 HVAC Insulation .............................................................................................................JIG 232300 Refrigerant Piping ...........................................................................................................JIG 233113 Metal Ducts…….. ...........................................................................................................JIG 233300 Air Duct Accessories ......................................................................................................JIG 233423 HVAC Power Ventilators…….. .......................................................................................JIG 233600 Air Terminals…….. .........................................................................................................JIG 233713 Diffusers, Registers, and Grilles .....................................................................................JIG 237433 Packaged Outdoor Air Rooftop Units .............................................................................JIG 238123.13 Computer Room Air Conditioners ..................................................................................JIG 238127 Split System Air Conditioners……………………………………………………………… ..JIG 238239 Unit Heaters ....................................................................................................................JIG

DIVISION 26 ELECTRICAL 260500 Common Work Results for Electrical ...............................................................................JIG 260519 Low Voltage Electrical Power Conductors and Cables ....................................................JIG 260526 Grounding and Bonding for Electrical Systems ...............................................................JIG 260529 Hangers and Supports for Electrical Systems .................................................................JIG 260533 Raceways and Boxes for Electrical Systems ...................................................................JIG 260543 Underground Ducts and Raceways for Electrical Systems .............................................JIG 260544 Sleeves and Sleeve Seals for Electrical Raceways and Cabling ....................................JIG 260553 Identification for Electrical Systems .................................................................................JIG 260573 Overcurrent Protective Device Coordination Study .........................................................JIG 260575 Arc Flash Hazard Analysis Study .....................................................................................JIG 260923 Lighting Control Devices ..................................................................................................JIG 262200 Low Voltage Transformers ...............................................................................................JIG 262413 Switchboards ....................................................................................................................JIG 262416 Panelboards .....................................................................................................................JIG 262726 Wiring Devices .................................................................................................................JIG 262816 Enclosed Switches and Circuit Breakers .........................................................................JIG 263213 Gaseous Emergency Engine Generators ........................................................................JIG 263600 Transfer Switches ............................................................................................................JIG 265119 LED Interior Lighting ........................................................................................................JIG 265600 Exterior Lighting ...............................................................................................................JIG DIVISION 31 - EARTHWORK 31 3116 TERMITE CONTROL 31 6223 COMPOSITE PILES DIVISION 32 - EXTERIOR IMPROVEMENTS 32 3113 CHAIN LINK FENCES AND GATES

END OF TABLE OF CONTENTS 1111--22--1166

Page 12: 11/2/16 - RideCARTSridecarts.weebly.com/uploads/1/1/1/1/11111920/... · 11/2/2016  · 20110319-enrtyprox-revc-ds-en North America: +1 949 732 2000 Toll Free: 1 800 237 7769 Europe,

CARTS Tucker Hill Lane Complex Addendum No. 4 Cedar Creek, Texas5300 Tucker Hill Lane November 2, 2016

JOINT SEALANTS 1 - 07 9200

SECTION 07 9200JOINT SEALANTS

PART 1 GENERAL1.01 SECTION INCLUDES

A. Nonsag gunnable joint sealants.B. Joint backings and accessories.

1.02 RELATED REQUIREMENTSA. Steel, iron and/or manufactured products specified in this Section shall comply with the Buy

America provision and shall be produced in the United States in accordance with 49 USC5323(j) and 49 CFR 661.

B. Section 07 2500 - Weather Barriers: Sealants required in conjunction with air barriers andvapor retarders.

C. Section 09 2116 - Gypsum Board Assemblies: Sealing acoustical and sound-rated walls andceilings.

1.03 REFERENCE STANDARDSA. ASTM C834 - Standard Specification for Latex Sealants; 2014.B. ASTM C919 - Standard Practice for Use of Sealants in Acoustical Applications; 2012.C. ASTM C920 - Standard Specification for Elastomeric Joint Sealants; 2014.D. ASTM C1193 - Standard Guide for Use of Joint Sealants; 2013.E. ASTM C1248 - Standard Test Method for Staining of Porous Substrate by Joint Sealants; 2008

(Reapproved 2012).F. ASTM C1330 - Standard Specification for Cylindrical Sealant Backing for Use with Cold

Liquid-Applied Sealants; 2002 (Reapproved 2013).G. ASTM C1521 - Standard Practice for Evaluating Adhesion of Installed Weatherproofing Sealant

Joints; 2013.1.04 SUBMITTALS

A. Buy America Compliance Certification: Provide the signed Buy America Provision Complianceform attached to the end of this Section. Only products complying with Buy America will beallowed to be used in this project.

B. See Section 01 3000 - Administrative Requirements, for submittal procedures.C. Product Data for Sealants: Submit manufacturer's technical data sheets for each product to be

used, that includes the following.1. Physical characteristics, including movement capability, VOC content, hardness, cure time,

and color availability.2. List of backing materials approved for use with the specific product.3. Substrates that product is known to satisfactorily adhere to and with which it is compatible.4. Substrates the product should not be used on.5. Substrates for which use of primer is required.6. Sample product warranty.

D. Product Data for Accessory Products: Submit manufacturer's technical data sheet for eachproduct to be used, including physical characteristics, installation instructions, andrecommended tools.

E. Color Cards for Selection: Where sealant color is not specified, submit manufacturer's colorcards showing standard colors available for selection.

F. Samples for Verification: Where custom sealant color is specified, obtain directions fromArchitect and submit at least two physical samples for verification of color of each requiredsealant.

Page 13: 11/2/16 - RideCARTSridecarts.weebly.com/uploads/1/1/1/1/11111920/... · 11/2/2016  · 20110319-enrtyprox-revc-ds-en North America: +1 949 732 2000 Toll Free: 1 800 237 7769 Europe,

CARTS Tucker Hill Lane Complex Addendum No. 4 Cedar Creek, Texas5300 Tucker Hill Lane November 2, 2016

JOINT SEALANTS 2 - 07 9200

G. Preinstallation Field Adhesion Test Plan: Submit at least two weeks prior to start of installation.H. Preinstallation Field Adhesion Test Reports: Submit filled out Preinstallation Field Adhesion

Test Reports log within 10 days after completion of tests; include bagged test samples andphotographic records.

1.05 QUALITY ASSURANCEA. Manufacturer Qualifications: Company specializing in manufacturing the products specified in

this section with minimum five years experience.B. Installer Qualifications: Company specializing in performing the work of this section and with at

least five years of experience.C. Preinstallation Field Adhesion Test Plan: Include destructive field adhesion testing of one

sample of each combination of sealant type and substrate, except interior acrylic latex sealants,and include the following for each tested sample.1. Identification of testing agency.2. Name(s) of sealant manufacturers' field representatives who will be observing3. Preinstallation Field Adhesion Test Log Form: Include the following data fields, with known

information filled out.a. Test date.b. Copy of test method documents.c. Age of sealant upon date of testing.d. Test results, modeled after the sample form in the test method document.e. Indicate use of photographic record of test.

D. Field Adhesion Test Procedures:1. Allow sealants to fully cure as recommended by manufacturer before testing.2. Have a copy of the test method document available during tests.3. Record the type of failure that occurred, other information required by test method, and the

information required on the Field Quality Control Log.4. When performing destructive tests, also inspect the opened joint for proper installation

characteristics recommended by manufacturer, and report any deficiencies.5. Deliver the samples removed during destructive tests in separate sealed plastic bags,

identified with project, location, test date, and test results, to Owner.6. If any combination of sealant type and substrate does not show evidence of minimum

adhesion or shows cohesion failure before minimum adhesion, report results to Architect.E. Destructive Field Adhesion Test: Test for adhesion in accordance with ASTM C1521, using

Destructive Tail Procedure.1. Sample: At least 18 inch long.2. Minimum Elongation Without Adhesive Failure: Consider the tail at rest, not under any

elongation stress; multiply the stated movement capability of the sealant in percent by two;then multiply 1 inch by that percentage; if adhesion failure occurs before the "1 inch mark"is that distance from the substrate, the test has failed.

3. If either adhesive or cohesive failure occurs prior to minimum elongation, take necessarymeasures to correct conditions and re-test; record each modification to products orinstallation procedures.

4. Record results on Field Quality Control Log.5. Repair failed portions of joints.

1.06 WARRANTYA. See Section 01 7800 - Closeout Submittals, for additional warranty requirements.B. Correct defective work within a five year period after Date of Substantial Completion.C. Warranty: Include coverage for installed sealants and accessories that fail to achieve

watertight seal , exhibit loss of adhesion or cohesion, or do not cure.

Page 14: 11/2/16 - RideCARTSridecarts.weebly.com/uploads/1/1/1/1/11111920/... · 11/2/2016  · 20110319-enrtyprox-revc-ds-en North America: +1 949 732 2000 Toll Free: 1 800 237 7769 Europe,

CARTS Tucker Hill Lane Complex Addendum No. 4 Cedar Creek, Texas5300 Tucker Hill Lane November 2, 2016

JOINT SEALANTS 3 - 07 9200

PART 2 PRODUCTS2.01 MANUFACTURERS

A. Subject to compliance with requirements indicated, provide products only from manufacturersthat can provide compliance with Buy America so that the steel, iron and/or manufacturedproducts used in the project are produced in the United States in compliance with 49 USC5323(j) and 49 CFR 661. Manufacturers listed below may or may not be compliant. It is thecontractor’s responsibility to confirm the manufacturer’s compliance with Buy America duringthe bidding phase of the project.

B. Non-Sag Sealants: Permits application in joints on vertical surfaces without sagging orslumping.1. Dow Corning Corporation: www.dowcorning.com/construction/sle.2. Tremco Global Sealants: www.tremcosealants.com.3. Substitutions: See Section 01 6000 - Product Requirements.

2.02 JOINT SEALANT APPLICATIONSA. Scope:

1. Exterior Joints: Seal open joints, whether or not the joint is indicated on the drawings,unless specifically indicated not to be sealed. Exterior joints to be sealed include, but arenot limited to, the following items.a. Wall expansion and control joints.b. Joints between door, window, and other frames and adjacent construction.c. Joints between different exposed materials.d. Openings below ledge angles in masonry.e. Other joints indicated below.

2. Interior Joints: Do not seal interior joints unless specifically indicated to be sealed. Interiorjoints to be sealed include, but are not limited to, the following items.a. Joints between door, window, and other frames and adjacent construction.b. Other joints indicated below.

3. Do not seal the following types of joints.a. Intentional weepholes in masonry.b. Joints indicated to be treated with manufactured expansion joint cover or some other

type of sealing device.c. Joints where sealant is specified to be provided by manufacturer of product to be

sealed.d. Joints where installation of sealant is specified in another section.e. Joints between suspended panel ceilings/grid and walls.

B. Exterior Joints: Use non-sag non-staining silicone sealant, Type A, unless otherwise indicated.C. Interior Joints: Use non-sag polyurethane sealant, unless otherwise indicated.

1. Wall and Ceiling Joints in Non-Wet Areas: Acrylic emulsion latex sealant.2. Wall and Ceiling Joints in Wet Areas: Non-sag polyurethane sealant for continuous liquid

immersion.D. Interior Wet Areas: restrooms and food service areas; fixtures in wet areas include plumbing

fixtures, countertops, cabinets, and other similar items. Sealants used in food service areasmust be food grade type.

2.03 JOINT SEALANTS - GENERAL2.04 NONSAG JOINT SEALANTS

A. Type A - Non-Staining Silicone Sealant: ASTM C920, Grade NS, Uses M and A; not expectedto withstand continuous water immersion or traffic.1. Movement Capability: Plus 100 percent, minus 50 percent, minimum.2. Non-Staining To Porous Stone: Non-staining to light-colored marble when tested in

accordance with ASTM C1248.3. Dirt Pick-Up: Reduced dirt pick-up compared to other silicone sealants.

Page 15: 11/2/16 - RideCARTSridecarts.weebly.com/uploads/1/1/1/1/11111920/... · 11/2/2016  · 20110319-enrtyprox-revc-ds-en North America: +1 949 732 2000 Toll Free: 1 800 237 7769 Europe,

CARTS Tucker Hill Lane Complex Addendum No. 4 Cedar Creek, Texas5300 Tucker Hill Lane November 2, 2016

JOINT SEALANTS 4 - 07 9200

4. Color: To be selected by Architect from manufacturer's full range.5. Manufacturers:

a. Dow Corning Corporation; 790 Silicone Building Sealant: www.dowcorning.com/construction/sle.

b. Tremco Commercial Sealants & Waterproofing; Spectrem 1 Single-Component,Moisture-Cure Silicone Sealant: www.tremcosealants.com.

c. Substitutions: See Section 01 6000 - Product Requirements.B. Polyurethane Sealant for Continuous Water Immersion: ASTM C920, Grade NS, Uses M and

A; single component; explicitly approved by manufacturer for continuous water immersion;suitable for traffic exposure when recessed below traffic surface .1. Movement Capability: Plus and minus 35 percent, minimum.

C. Acrylic Emulsion Latex: Water-based; ASTM C834, single component, non-staining,non-bleeding, non-sagging; not intended for exterior use.

2.05 ACCESSORIESA. Backer Rod: Cylindrical cellular foam rod with surface that sealant will not adhere to,

compatible with specific sealant used, and recommended by backing and sealantmanufacturers for specific application.1. Type for Joints Not Subject to Pedestrian or Vehicular Traffic: ASTM C1330; Type O -

Open Cell Polyurethane.2. Type for Joints Subject to Pedestrian or Vehicular Traffic: ASTM C1330; Type B -

Bi-Cellular Polyethylene.3. Open Cell: 40 to 50 percent larger in diameter than joint width.4. Closed Cell and Bi-Cellular: 25 to 33 percent larger in diameter than joint width.

B. Backing Tape: Self-adhesive polyethylene tape with surface that sealant will not adhere to andrecommended by tape and sealant manufacturers for specific application.

C. Masking Tape: Self-adhesive, nonabsorbent, non-staining, removable without adhesiveresidue, and compatible with surfaces adjacent to joints and sealants.

D. Joint Cleaner: Non-corrosive and non-staining type, type recommended by sealantmanufacturer; compatible with joint forming materials.

E. Primers: Type recommended by sealant manufacturer to suit application; non-staining.PART 3 EXECUTION3.01 EXAMINATION

A. Verify that joints are ready to receive work.B. Verify that backing materials are compatible with sealants.C. Verify that backer rods are of the correct size.D. Preinstallation Adhesion Testing: Install a sample for each test location shown in the test plan.

1. Test each sample as specified in PART 1 under QUALITY ASSURANCE article.2. Notify Architect of date and time that tests will be performed, at least 7 days in advance.3. Arrange for sealant manufacturer's technical representative to be present during tests.4. Record each test on Preinstallation Adhesion Test Log as indicated.5. If any sample fails, review products and installation procedures, consult manufacturer, or

take whatever other measures are necessary to ensure adhesion; re-test in a differentlocation; if unable to obtain satisfactory adhesion, report to Architect.

6. After completion of tests, remove remaining sample material and prepare joint for newsealant installation.

3.02 PREPARATIONA. Remove loose materials and foreign matter that could impair adhesion of sealant.B. Clean joints, and prime as necessary, in accordance with manufacturer's instructions.C. Perform preparation in accordance with manufacturer's instructions and ASTM C1193.

Page 16: 11/2/16 - RideCARTSridecarts.weebly.com/uploads/1/1/1/1/11111920/... · 11/2/2016  · 20110319-enrtyprox-revc-ds-en North America: +1 949 732 2000 Toll Free: 1 800 237 7769 Europe,

CARTS Tucker Hill Lane Complex Addendum No. 4 Cedar Creek, Texas5300 Tucker Hill Lane November 2, 2016

JOINT SEALANTS 5 - 07 9200

D. Mask elements and surfaces adjacent to joints from damage and disfigurement due to sealantwork; be aware that sealant drips and smears may not be completely removable.

E. Concrete Floor Joints That Will Be Exposed in Completed Work: Test joint filler ininconspicuous area to verify that it does not stain or discolor slab.

3.03 INSTALLATIONA. Perform work in accordance with sealant manufacturer's requirements for preparation of

surfaces and material installation instructions.B. Perform installation in accordance with ASTM C1193.C. Perform acoustical sealant application work in accordance with ASTM C919.D. Measure joint dimensions and size joint backers to achieve width-to-depth ratio, neck

dimension, and surface bond area as recommended by manufacturer, except where specificdimensions are indicated.

E. Install bond breaker backing tape where backer rod cannot be used.F. Install sealant free of air pockets, foreign embedded matter, ridges, and sags, and without

getting sealant on adjacent surfaces.G. Do not install sealant when ambient temperature is outside manufacturer's recommended

temperature range, or will be outside that range during the entire curing period, unlessmanufacturer's approval is obtained and instructions are followed.

H. Nonsag Sealants: Tool surface concave, unless otherwise indicated; remove masking tapeimmediately after tooling sealant surface.

I. Concrete Floor Joint Filler: After full cure, shave joint filler flush with top of concrete slab.3.04 FIELD QUALITY CONTROL

A. Perform field quality control inspection/testing as specified in PART 1 under QUALITYASSURANCE article.

B. Destructive Adhesion Testing: If there are any failures in first 500 linear feet, notify Architectimmediately.

C. Remove and replace failed portions of sealants using same materials and procedures asindicated for original installation.

D. Repair destructive test location damage immediately after evaluation and recording of results.3.05 POST-OCCUPANCY

A. Post-Occupancy Inspection: Perform visual inspection of entire length of project sealant jointsat a time that joints have opened to their greatest width; i.e. at the low temperature in thethermal cycle. Report failures immediately and repair.

END OF SECTION 07 9200

Page 17: 11/2/16 - RideCARTSridecarts.weebly.com/uploads/1/1/1/1/11111920/... · 11/2/2016  · 20110319-enrtyprox-revc-ds-en North America: +1 949 732 2000 Toll Free: 1 800 237 7769 Europe,

CARTS Tucker Hill Lane Complex Addendum No. 4 Cedar Creek, Texas 5300 Tucker Hill Lane November 2, 2016

BUY AMERICA PROVISION - COMPLETE AND SUBMIT WITH BID TO GENERAL CONTRACTOR

Buy America Provision Compliance: This project is funded by the Federal Transit Administration (FTA) and is therefore required to meet the Buy America requirements, as described in 49 USC 5323(j) and 49 CFR 661. These sections of the United States Code and the Code of Federal Regulations are incorporated as requirements of this project by their inclusion in the Consolidated Certification Form in the Request for Proposal (RFP). The General Contractor shall certify that all steel, iron and manufactured products used in the project are produced in the United States as described in detail in the above referenced USC and CFR sections. In order for the General Contractor to provide this certification to the Owner, each Subcontractor shall certify that his/her specific products which will be furnished or installed in the project are Buy America compliant. Subcontractor shall complete and submit the certification statement below with his/her bid to the General Contractor in accordance with the requirement contained in 49 CFR 661.13(b). Bids will not be accepted without certification of compliance with Buy America. Buy America (check applicable box): □ The vendor or offeror hereby certifies it will comply with the requirements of 49 USC 5323(j) and

the applicable regulations in 49 CFR 661, providing Buy America compliant manufactured goods. □ The vendor or offeror cannot comply with the requirements 49 USC 5323(j), buy may qualify for an

exception to the requirement pursuant to the regulations in 49 CFR 661.

Buy America Certification Name of Company Printed Name of Person Completing Form

Date Signature

Notes:

• All Subcontractors that provide steel, iron and/or manufactured products for this project shall provide the above certification whether or not this Project Manual contains a specification section pertaining to their products.

• Steel, iron and/or manufactured products that are included in work self-performed by the General Contractor shall also comply with Buy America and certification shall be provided for each product.

• The Buy America provision is not the same as the Buy American provision. These are two different federal requirements and this project must meet the Buy America requirements.

Page 18: 11/2/16 - RideCARTSridecarts.weebly.com/uploads/1/1/1/1/11111920/... · 11/2/2016  · 20110319-enrtyprox-revc-ds-en North America: +1 949 732 2000 Toll Free: 1 800 237 7769 Europe,

CARTS- Operations and Administration Facility SECTION 09 1001

INTERIOR FINISH SCHEDULE Issued: September 26, 2016

Revised: November 2, 2016 (See bold italicized text)

Rm # Room Name Floor Walls Ceiling Base Trim Doors Built-in Remarks

N E S W Casework

Page 1 of 5

FIRST FLOOR 100 Reception RF-01,

RB-02

PT-01, PT-04

PT-01, PT-04

PT-01, PT-04

PT-01

PT-02 RB-01 N/A N/A

SS-01, SS-02, PL-01, PL-02, PL-04

PT-04 wraps around the recessed wall at the dropped ceiling above the reception desk, see interior elevations. RB-02 to be used as stair nosing.

101 File/Copy RF-01

PT-01

PT-01

PT-01

PT-01

PT-02 RB-01 N/A

PL-07 PL-03, SS-01

102 Janitor / Storage CONC-01 PT-01 FRP-01

PT-01 FRP-01

PT-01 FRP-01

PT-01 FRP-01

PT-02 N/A N/A PL-01 PL-06 on adj. wood shelves

FRP TO 8’-0” A.F.F.

103 Stor. CONC-01 PT-01 PT-01 PT-01 PT-01 No Ceiling RB-01 N/A N/A

N/A

104 Restroom TI-05 PT-01, TI-04

PT-01, TI-04

PT-01, TI-04, TI-03

PT-01, TI-04

PT-02 MT-01 MT-02 PL-07 PL-03 SS-01

TI-04 TO 4’ A.F.F, West Wall TI-04 TO 5’ A.F.F.

105 Electrical Room CONC-01 PT-01

PT-01

PT-01

PT-01

No Ceiling RB-01 N/A N/A Install 4’x8’ sheet of 3/4” AC plywood on one wall (coord. location w/ Owner); paint surface

106 Breakroom RF-01

PT-01

PT-01

PT-01

PT-01

PT-02 RB-01 N/A PL-07 PL-03 SS-01

107 Boardroom CPT-01 PT-01

PT-01

PT-01

PT-01 PT-02 RB-01 N/A PL-07

PL-03 SS-01

108 Hall RF-01 PT-01, PT-03

PT-01, PT-03

PT-01, PT-03

PT-01, PT-03

PT-02 RB-01 N/A N/A PL-03 PL-03 located on Hallway Bench, PT-03 only on walls around exterior of elevator shaft

109 Training Room CPT-01 PT-01

PT-01

PT-01

PT-01

SC-01 RB-01 N/A PL-07 N/A

Page 19: 11/2/16 - RideCARTSridecarts.weebly.com/uploads/1/1/1/1/11111920/... · 11/2/2016  · 20110319-enrtyprox-revc-ds-en North America: +1 949 732 2000 Toll Free: 1 800 237 7769 Europe,

CARTS- Operations and Administration Facility SECTION 09 1001

INTERIOR FINISH SCHEDULE Issued: September 26, 2016

Revised: November 2, 2016 (See bold italicized text)

Rm # Room Name Floor Walls Ceiling Base Trim Doors Built-in Remarks

N E S W Casework

Page 2 of 5

110 Driver Ready Room

RF-01 PT-01

PT-01

PT-01

PT-01

PT-02, SC-01

RB-01 N/A N/A PL-03, PL-06

See interior elevations for PL-03 and PL-06 locations

111 Breakroom RF-01 PT-01

PT-01

PT-01

PT-04

PT-02, SC-01

RB-01 N/A N/A PL-03 SS-01

112 Route Supervisors CPT-01 PT-01

PT-01

PT-01

PT-01

SC-01 RB-01 N/A PL-07 PL-06 PL-07

113 Storage CPT-01 PT-01

PT-01

PT-01

PT-01

PT-02 RB-01 N/A PL-07 PL-06

114 Fare CPT-01 PT-01

PT-01

PT-01

PT-01

SC-01 RB-01 N/A PL-07 PL-06

115 Ride Sim. CPT-01 PT-01

PT-01

PT-01

PT-01

SC-01 RB-01 N/A PL-07 N/A

116 Reservations CPT-01 PT-01

PT-01

PT-01

PT-01

SC-01 RB-01 N/A PL-07 PL-03 PL-03 on Cubbies

117 Call Center Director

CPT-01 PT-01

PT-01

PT-01

PT-01

SC-01 RB-01 N/A PL-07 N/A

118 Operations Director

CPT-01 PT-01

PT-01

PT-01

PT-01

SC-01 RB-01 N/A PL-07 N/A

119 Sprinkler Room CONC-01 PT-01

PT-01

PT-01

PT-01

No Ceiling RB-01 N/A N/A N/A

120 NOT USED --- --- --- --- --- --- --- --- --- ---

121 Dispatch CPT-01 PT-01

PT-01

PT-01

PT-01

SC-01 RB-01 N/A PL-07 PL-06

122 Electrical Room CONC-01 PT-01

PT-01

PT-01

PT-01

N/A RB-01 N/A PL-07 Install 4’x8’ sheet of 3/4” AC plywood on one wall (coord. location w/ Owner); paint surface

Page 20: 11/2/16 - RideCARTSridecarts.weebly.com/uploads/1/1/1/1/11111920/... · 11/2/2016  · 20110319-enrtyprox-revc-ds-en North America: +1 949 732 2000 Toll Free: 1 800 237 7769 Europe,

CARTS- Operations and Administration Facility SECTION 09 1001

INTERIOR FINISH SCHEDULE Issued: September 26, 2016

Revised: November 2, 2016 (See bold italicized text)

Rm # Room Name Floor Walls Ceiling Base Trim Doors Built-in Remarks

N E S W Casework

Page 3 of 5

123 Women’s Restroom

TI-05 PT-01, TI-01, TI-06

PT-01, TI-01, TI-04,

PT-01, TI-04, TI-06

PT-01, TI-01, TI-04, TI-06

PT-02 MT-01 MT-02 PL-07 PL-03, PL-05, SS-01

See Interior Elevations for TI locations and PL locations, TI-04 TO BE 4’-0” A.F.F

124 Men’s Restroom TI-05 PT-01, TI-04, TI-06

PT-01, TI-01, TI-04, TI-06

PT-01, TI-01, TI-06

PT-01, TI-01, TI-04, TI-06

PT-02 MT-01 MT-02 PL-07 PL-03, Pl-05, SS-01

See Interior Elevations for TI locations and PL locations, TI-04 TO BE 4’-0” A.F.F

125 Janitor Room CONC-01 PT-01 FRP-01

PT-01 FRP-01

PT-01 FRP-01

PT-01 FRP-01

PT-02 N/A N/A PL-07 N/A

126 HR Office CPT-01 PT-01

PT-01

PT-01

PT-01

SC-01 RB-01 N/A PL-07 N/A

127 HR CPT-01 PT-01

PT-01

PT-01

PT-01

SC-01 RB-01 N/A PL-07 N/A

128 Storage CPT-01 PT-01

PT-01

PT-01

PT-01

PT-02 RB-01 N/A PL-07 N/A

129 Hall RF-01 PT-01

PT-01, TI-07

PT-01, TI-07

PT-01, TI-07

PT-02 RB-01, MT-01

MT-02 N/A N/A TI-07 located in water fountain recess, see interior elevation, MT-01 & MT-02 located at TI-07

200 Office CPT-01 PT-01

PT-01

PT-01

PT-01

PT-02, PT-05

RB-01 N/A PL-07 N/A

201 Office CPT-01 PT-01

PT-01

PT-01

PT-01

PT-02, PT-05

RB-01 N/A PL-07 N/A

Page 21: 11/2/16 - RideCARTSridecarts.weebly.com/uploads/1/1/1/1/11111920/... · 11/2/2016  · 20110319-enrtyprox-revc-ds-en North America: +1 949 732 2000 Toll Free: 1 800 237 7769 Europe,

CARTS- Operations and Administration Facility SECTION 09 1001

INTERIOR FINISH SCHEDULE Issued: September 26, 2016

Revised: November 2, 2016 (See bold italicized text)

Rm # Room Name Floor Walls Ceiling Base Trim Doors Built-in Remarks

N E S W Casework

Page 4 of 5

202 Meeting & Work Area

CPT-01 PT-01

PT-01

PT-01

PT-01

PT-02, PT-05

RB-01 N/A N/A PL-03 SS-01

203 Office CPT-01 PT-01

PT-01

PT-01

PT-01

PT-02, PT-05

RB-01 N/A N/A N/A

204 Office CPT-01 PT-01

PT-01

PT-01

PT-01

PT-02, PT-05

RB-01 N/A N/A N/A

205 Electrical Room CONC-01 PT-01

PT-01

PT-01

PT-01

No Ceiling, PT-05

RB-01 N/A PL-01 Install 4’x8’ sheet of 3/4” AC plywood on one wall (coord. location w/ Owner); paint surface

207 Breakroom/ Cafe RF-01, CPT-01

PT-01, PT-03

PT-01, PT-03

PT-01

PT-01

SC-02, PT-02, PT-05

RB-01 N/A N/A PL-03, PL-02 SS-01

See interior elevations for PL locations. PT-03 only on walls around exterior of conference room and exterior of breakroom counter walls.

208 Accounting CPT-01 PT-01

PT-01

PT-01

PT-01

PT-02 RB-01 N/A PL-07 N/A

209 Acct. Manager CPT-01 PT-01

PT-01

PT-01

PT-01

PT-02 RB-01 N/A PL-07 N/A

210 I.T. Room CONC-01 PT-01

PT-01

PT-01

PT-01

PT-02 RB-01 N/A PL-07 3/4” AC plywood (floor to ceiling) on face of 1-hour firewall; all 4 walls; caulk joints; paint surface

211 Open Office CPT-01 PT-01 PT-01, PT-03

PT-01, PT-03

PT-01, PT-03

PT-02, PT-05

RB-01 N/A N/A PL-01, SS-01

PT-03 only on walls around exterior of conference room and exterior of breakroom counter walls.

Page 22: 11/2/16 - RideCARTSridecarts.weebly.com/uploads/1/1/1/1/11111920/... · 11/2/2016  · 20110319-enrtyprox-revc-ds-en North America: +1 949 732 2000 Toll Free: 1 800 237 7769 Europe,

CARTS- Operations and Administration Facility SECTION 09 1001

INTERIOR FINISH SCHEDULE Issued: September 26, 2016

Revised: November 2, 2016 (See bold italicized text)

Rm # Room Name Floor Walls Ceiling Base Trim Doors Built-in Remarks

N E S W Casework

Page 5 of 5

212 Storage CONC-01 PT-01 PT-01 PT-01 PT-01 PT-02 RB-01 N/A PL-07 N/A

213 Stair CPT-01, RF-01, RB-02

PT-01 PT-01 PT-01 PT-01 PT-02 RB-01 --- --- N/A RE-01 to be used on Stair Treads, RB-02 to be used as stair nosing.

214 Restroom TI-05 PT-01 TI-04

PT-01 TI-04

PT-01 TI-04

PT-01 TI-04, TI-02

PT-02 MT-01 MT-02 PL-07 PL-03, SS-01

TI-04 TO BE 4’-0” A.F.F

215 Restroom TI-05 PT-01, TI-04

PT-01, TI-04, TI-02

PT-01, TI-04,

PT-01, TI-04

PT-02 MT-01 MT-02 PL-07 PL-03, SS-01

TI-04 TO BE 4’-0” A.F.F

216 Storage CONC-01 PT-01 PT-01 PT-01 PT-01 PT-02 RB-01 N/A PL-07 N/A

217 Water heater CONC-01 PT-01 PT-01 PT-01 PT-01 N/A RB-01 N/A PL-07 N/A

218 Conference CPT-01 PT-03 PT-03 PT-03 PT-03 PT-02 RB-01 N/A PL-(black color laminate to be determined)

N/A

219 Electrical Room CONC-01 PT-01 PT-01 PT-01 PT-01 No Ceiling, PT-05

RB-01 N/A PL-07 Install 4’x8’ sheet of 3/4” AC plywood on one wall (coord. location w/ Owner); paint surface

220 Health Room CPT-01 PT-01 PT-01 PT-01 PT-01 PT-02 RB-01 N/A PL-07 PL-03 SS-01

221 Meeting Area CPT-01 PT-01 PT-01 PT-01 PT-01, PT-03

PT-02, PT-05

RB-01 N/A N/A N/A PT-03 only on walls around exterior of breakroom counter walls.

Page 23: 11/2/16 - RideCARTSridecarts.weebly.com/uploads/1/1/1/1/11111920/... · 11/2/2016  · 20110319-enrtyprox-revc-ds-en North America: +1 949 732 2000 Toll Free: 1 800 237 7769 Europe,

CARTS Tucker Hill Lane Complex Addendum No. 4 Cedar Creek, Texas 5300 Tucker Hill Lane November 2, 2016

TOILET, BATH, AND LAUNDRY ACCESSORIES

1 - 10 2800

SECTION 10 2800 TOILET, BATH, AND LAUNDRY ACCESSORIES

PART 1 GENERAL 1.01 SECTION INCLUDES 1.02 RELATED REQUIREMENTS

A. Steel, iron and/or manufactured products specified in this Section shall comply with the Buy America provision and shall be produced in the United States in accordance with 49 USC 5323(j) and 49 CFR 661.

1.03 ADMINISTRATIVE REQUIREMENTS A. Coordinate the work with the placement of internal wall reinforcement, concealed ceiling

supports, and reinforcement of toilet partitions to receive anchor attachments. 1.04 SUBMITTALS

A. Buy America Compliance Certification: Provide the signed Buy America Provision Compliance form attached to the end of this Section. Only products complying with Buy America will be allowed to be used in this project.

B. See Section 01 3000 - Administrative Requirements, for submittal procedures. PART 2 PRODUCTS 2.01 MANUFACTURERS

A. Subject to compliance with requirements indicated, provide products only from manufacturers that can provide compliance with Buy America so that the steel, iron and/or manufactured products used in the project are produced in the United States in compliance with 49 USC 5323(j) and 49 CFR 661. Manufacturers listed below may or may not be compliant. It is the contractor’s responsibility to confirm the manufacturer’s compliance with Buy America during the bidding phase of the project.

B. Basis of Design: 1. Provide the following accessory types/styles/mounting from compliant manufacturers:

a. Recessed Toilet Paper Dispenser: Bobrick B-4388; Qty. 5; Install where unit is located in stud wall.

b. Surface Mounted Toilet Paper Dispenser: Bobrick B-4288; Qty. 2; Install where unit is located on toilet partition.

c. Counter Mounted Automatic Sensored Top-Fill Liquid Soap Dispenser: Bobrick B-824; Qty. 7; Install in countertop.

d. Recessed Sanitary Napkin Disposal: Bobrick B-4353; Qty. 4; Install where unit is located in stud wall.

e. Partition Mounted Sanitary Napkin Disposal: Bobrick B-4354; Qty. 1; Install where unit is located in toilet partition (one unit serves two stalls).

f. Grab Bars; 1 1/4" Dia. Stn. Steel with Snap Flange: B-5806 Series; Verify quantity & sizes with drawings and TAS compliance.

g. Recessed Waste Receptacle (with Linermate): Bobrick B-43644; Qty. 5; Install where unit is located in stud wall.

h. Automatic Sensored Hand Dryer: Xlerator Model XL-SB, with Xlerator ADA Compliant Recess Kit; Qty. 5; Install where unit is located in stud wall.

2. Other Acceptable Manufacturers: a. Substitutions: Section 01 6000 - Product Requirements.

PART 3 EXECUTION 3.01 EXAMINATION

A. Verify existing conditions before starting work. B. Verify exact location of accessories for installation.

Page 24: 11/2/16 - RideCARTSridecarts.weebly.com/uploads/1/1/1/1/11111920/... · 11/2/2016  · 20110319-enrtyprox-revc-ds-en North America: +1 949 732 2000 Toll Free: 1 800 237 7769 Europe,

CARTS Tucker Hill Lane Complex Addendum No. 4 Cedar Creek, Texas 5300 Tucker Hill Lane November 2, 2016

TOILET, BATH, AND LAUNDRY ACCESSORIES

2 - 10 2800

C. For electrically-operated accessories, verify that electrical power connections are ready and in the correct locations.

D. Verify that field measurements are as indicated on drawings and comply with TAS. 3.02 PREPARATION

A. Deliver inserts and rough-in frames to site for timely installation. B. Provide templates and rough-in measurements as required.

3.03 INSTALLATION A. Install accessories in accordance with manufacturers' instructions in locations indicated on the

drawings. B. Install plumb and level, securely and rigidly anchored to substrate. C. Mounting Heights: As required by TAS accessibility regulations, unless otherwise indicated.

3.04 PROTECTION A. Protect installed accessories from damage due to subsequent construction operations.

END OF SECTION 10 2800

Page 25: 11/2/16 - RideCARTSridecarts.weebly.com/uploads/1/1/1/1/11111920/... · 11/2/2016  · 20110319-enrtyprox-revc-ds-en North America: +1 949 732 2000 Toll Free: 1 800 237 7769 Europe,

CARTS Tucker Hill Lane Complex Addendum No. 4 Cedar Creek, Texas 5300 Tucker Hill Lane November 2, 2016

BUY AMERICA PROVISION - COMPLETE AND SUBMIT WITH BID TO GENERAL CONTRACTOR

Buy America Provision Compliance: This project is funded by the Federal Transit Administration (FTA) and is therefore required to meet the Buy America requirements, as described in 49 USC 5323(j) and 49 CFR 661. These sections of the United States Code and the Code of Federal Regulations are incorporated as requirements of this project by their inclusion in the Consolidated Certification Form in the Request for Proposal (RFP). The General Contractor shall certify that all steel, iron and manufactured products used in the project are produced in the United States as described in detail in the above referenced USC and CFR sections. In order for the General Contractor to provide this certification to the Owner, each Subcontractor shall certify that his/her specific products which will be furnished or installed in the project are Buy America compliant. Subcontractor shall complete and submit the certification statement below with his/her bid to the General Contractor in accordance with the requirement contained in 49 CFR 661.13(b). Bids will not be accepted without certification of compliance with Buy America. Buy America (check applicable box): □ The vendor or offeror hereby certifies it will comply with the requirements of 49 USC 5323(j) and

the applicable regulations in 49 CFR 661, providing Buy America compliant manufactured goods. □ The vendor or offeror cannot comply with the requirements 49 USC 5323(j), buy may qualify for an

exception to the requirement pursuant to the regulations in 49 CFR 661.

Buy America Certification Name of Company Printed Name of Person Completing Form

Date Signature

Notes:

• All Subcontractors that provide steel, iron and/or manufactured products for this project shall provide the above certification whether or not this Project Manual contains a specification section pertaining to their products.

• Steel, iron and/or manufactured products that are included in work self-performed by the General Contractor shall also comply with Buy America and certification shall be provided for each product.

• The Buy America provision is not the same as the Buy American provision. These are two different federal requirements and this project must meet the Buy America requirements.

Page 26: 11/2/16 - RideCARTSridecarts.weebly.com/uploads/1/1/1/1/11111920/... · 11/2/2016  · 20110319-enrtyprox-revc-ds-en North America: +1 949 732 2000 Toll Free: 1 800 237 7769 Europe,

N

5

9

°

1

2

'

1

3

"

W

7

7

9

.

3

6

'

416.7

5

423

HP

OPERATIONS/ADMIN

BUILDING FF

E = 419.00 <<

M

A

T

C

H

L

IN

E

M

A

T

C

H

L

IN

E

BUILDING FF

E = 419.00

AutoCAD SHX Text
416
AutoCAD SHX Text
417
AutoCAD SHX Text
418
AutoCAD SHX Text
419
AutoCAD SHX Text
421
AutoCAD SHX Text
422
AutoCAD SHX Text
423
AutoCAD SHX Text
424
AutoCAD SHX Text
420
AutoCAD SHX Text
416
AutoCAD SHX Text
2%
AutoCAD SHX Text
2%
AutoCAD SHX Text
422
AutoCAD SHX Text
2%
AutoCAD SHX Text
X
AutoCAD SHX Text
X
AutoCAD SHX Text
417.63
AutoCAD SHX Text
417.65
AutoCAD SHX Text
WHEELSTOP, TYP.
AutoCAD SHX Text
416.5
AutoCAD SHX Text
417
AutoCAD SHX Text
417.5
AutoCAD SHX Text
418
AutoCAD SHX Text
419
AutoCAD SHX Text
420
AutoCAD SHX Text
421
AutoCAD SHX Text
X
AutoCAD SHX Text
417.5
AutoCAD SHX Text
X
AutoCAD SHX Text
417.25
AutoCAD SHX Text
X
AutoCAD SHX Text
X
AutoCAD SHX Text
418
AutoCAD SHX Text
418
AutoCAD SHX Text
X
AutoCAD SHX Text
417.63
AutoCAD SHX Text
X
AutoCAD SHX Text
418.92
AutoCAD SHX Text
X
AutoCAD SHX Text
418.92
AutoCAD SHX Text
X
AutoCAD SHX Text
418.92
AutoCAD SHX Text
420
AutoCAD SHX Text
421
AutoCAD SHX Text
422
AutoCAD SHX Text
419
AutoCAD SHX Text
417
AutoCAD SHX Text
X
AutoCAD SHX Text
416
AutoCAD SHX Text
418
AutoCAD SHX Text
417
AutoCAD SHX Text
417
AutoCAD SHX Text
418
AutoCAD SHX Text
418
AutoCAD SHX Text
424
AutoCAD SHX Text
423
AutoCAD SHX Text
422
AutoCAD SHX Text
421
AutoCAD SHX Text
X
AutoCAD SHX Text
416
AutoCAD SHX Text
X
AutoCAD SHX Text
416
AutoCAD SHX Text
420
AutoCAD SHX Text
418
AutoCAD SHX Text
416
AutoCAD SHX Text
417
AutoCAD SHX Text
418
AutoCAD SHX Text
419
AutoCAD SHX Text
421
AutoCAD SHX Text
422
AutoCAD SHX Text
423
AutoCAD SHX Text
424
AutoCAD SHX Text
420
AutoCAD SHX Text
416
AutoCAD SHX Text
X
AutoCAD SHX Text
418.69
AutoCAD SHX Text
X
AutoCAD SHX Text
417.15
AutoCAD SHX Text
COVERED PORCH
AutoCAD SHX Text
EXISTING CONCRETE PAVEMENT
AutoCAD SHX Text
RAINWATER COLLECTION
AutoCAD SHX Text
A1
AutoCAD SHX Text
A2
AutoCAD SHX Text
A3
AutoCAD SHX Text
A4
AutoCAD SHX Text
A5
AutoCAD SHX Text
A6
AutoCAD SHX Text
A7
AutoCAD SHX Text
A8
AutoCAD SHX Text
A9
AutoCAD SHX Text
A10
AutoCAD SHX Text
A11
AutoCAD SHX Text
B1
AutoCAD SHX Text
C1
AutoCAD SHX Text
D1
AutoCAD SHX Text
E1
AutoCAD SHX Text
F1
AutoCAD SHX Text
G1
AutoCAD SHX Text
H1
AutoCAD SHX Text
I1
AutoCAD SHX Text
J1
AutoCAD SHX Text
K1
AutoCAD SHX Text
L1
AutoCAD SHX Text
M1
AutoCAD SHX Text
N1
AutoCAD SHX Text
A12
AutoCAD SHX Text
1
AutoCAD SHX Text
2
AutoCAD SHX Text
3
AutoCAD SHX Text
4
AutoCAD SHX Text
5
AutoCAD SHX Text
6
AutoCAD SHX Text
7
AutoCAD SHX Text
8
AutoCAD SHX Text
9
AutoCAD SHX Text
10
AutoCAD SHX Text
11
AutoCAD SHX Text
A13
AutoCAD SHX Text
12
AutoCAD SHX Text
13
AutoCAD SHX Text
2%
AutoCAD SHX Text
2%
AutoCAD SHX Text
X
AutoCAD SHX Text
417.63
AutoCAD SHX Text
X
AutoCAD SHX Text
X
AutoCAD SHX Text
418
AutoCAD SHX Text
418
AutoCAD SHX Text
Bleyl & Associates
AutoCAD SHX Text
Bleyl & Associates
AutoCAD SHX Text
PROJECT NUMBER
AutoCAD SHX Text
FILE NAME:
AutoCAD SHX Text
SHEET:
AutoCAD SHX Text
OF:
AutoCAD SHX Text
&
AutoCAD SHX Text
B
AutoCAD SHX Text
A
AutoCAD SHX Text
Bleyl & Associates
AutoCAD SHX Text
Project Engineering & Management
AutoCAD SHX Text
1715 CAPITAL OF TEXAS HWY S, SUITE 109
AutoCAD SHX Text
AUSTIN, TEXAS 78746
AutoCAD SHX Text
512-328-7878 PHONE
AutoCAD SHX Text
512-328-7884 FAX
AutoCAD SHX Text
PREPARED FOR:
AutoCAD SHX Text
DRAWN BY:
AutoCAD SHX Text
PROJECT MANAGER:
AutoCAD SHX Text
SCALE:
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
REV
AutoCAD SHX Text
DATE
AutoCAD SHX Text
COMMENT
AutoCAD SHX Text
APP
AutoCAD SHX Text
BY
AutoCAD SHX Text
FIRM REGISTRATION No. F-678
AutoCAD SHX Text
CARTS
AutoCAD SHX Text
TUCKER HILL LANE COMPLEX
AutoCAD SHX Text
HWY 71 AT TUCKER HILL LANE
AutoCAD SHX Text
CEDAR CREEK, TEXAS 78712
AutoCAD SHX Text
TRAVIS/BASTROP COUNTY
AutoCAD SHX Text
11825
AutoCAD SHX Text
11825
AutoCAD SHX Text
AS NOTED
AutoCAD SHX Text
JC
AutoCAD SHX Text
KENNY WATKINS, P.E.
AutoCAD SHX Text
CARTS
AutoCAD SHX Text
27
AutoCAD SHX Text
1 inch = ft.
AutoCAD SHX Text
( IN FEET )
AutoCAD SHX Text
GRAPHIC SCALE
AutoCAD SHX Text
0
AutoCAD SHX Text
20
AutoCAD SHX Text
20
AutoCAD SHX Text
40
AutoCAD SHX Text
20
AutoCAD SHX Text
80
AutoCAD SHX Text
10
AutoCAD SHX Text
1 inch = ft.
AutoCAD SHX Text
( IN FEET )
AutoCAD SHX Text
GRAPHIC SCALE
AutoCAD SHX Text
0
AutoCAD SHX Text
5
AutoCAD SHX Text
5
AutoCAD SHX Text
10
AutoCAD SHX Text
5
AutoCAD SHX Text
20
AutoCAD SHX Text
2.5
AutoCAD SHX Text
BEGIN SWALE FL = 418.25
AutoCAD SHX Text
SWALE AT 1%, TYP.
AutoCAD SHX Text
5' X 5' LANDING, TYP.
AutoCAD SHX Text
1:12' RAMP SLOPE, TYP.
AutoCAD SHX Text
8.3 LF 12" HDPE PIPE CULVERT FL = MATCH EXISTING GRADE
AutoCAD SHX Text
PROP 4-SIDED AREA INLET THROAT = 417.00 FL (24") = 414.10
AutoCAD SHX Text
PROP 21 LF 24" HDPE @ 0.50% FL @ HDWL = 413.00
AutoCAD SHX Text
PROP 24 LF 18" HDPE @ 0.50%
AutoCAD SHX Text
PROP 4' x 4' INLET FL = 413.23 T/G = 415.50
AutoCAD SHX Text
SLOPE LANDSCAPE AREA AWAY FROM BUILDING @ 2%, TYP.
AutoCAD SHX Text
PROP DRY STACK WALL. TOP OF WALL MATCHES HIGHEST ADJACENT GRADE. SET INSIDE FACE OF WALL 5' OUTSIDE TANK FOOTING
AutoCAD SHX Text
PROP 19 LF DRY STACK ROCK WALL. TOP OF WALL MATCHES ADJACENT GRADE
AutoCAD SHX Text
HIGHEST FINISHED GRADE ADJACENT TO BUILDING IS 418.67, ALL SIDES
AutoCAD SHX Text
PROP 76 LF 24" HDPE @ 0.50%
AutoCAD SHX Text
SEE LANDSCAPE PLAN FOR LAYOUT AND ELEVATION OF WALLS, TURF AREA, AND BASALT WALKWAY
AutoCAD SHX Text
PROP 128 LF 24" HDPE @ 0.50% - CONSTRUCT 2' BEHIND CURB
AutoCAD SHX Text
FL @ 29 DEG BEND = 413.74
AutoCAD SHX Text
ADA RAMP ENLARGEMENT
AutoCAD SHX Text
ENLARGED GRADING PLAN
AutoCAD SHX Text
8.3 LF 12" HDPE PIPE CULVERT FL = MATCH EXISTING GRADE
AutoCAD SHX Text
1' EARTHEN BERM, TYP.
AutoCAD SHX Text
FL @ JUNCTION = 413.10
AutoCAD SHX Text
12.1R
AutoCAD SHX Text
4
AutoCAD SHX Text
11/2/16
AutoCAD SHX Text
ADDENDUM NO. 4
AutoCAD SHX Text
3
AutoCAD SHX Text
3
AutoCAD SHX Text
10/31/16
AutoCAD SHX Text
ADDENDUM NO. 3
AutoCAD SHX Text
4
AutoCAD SHX Text
4
AutoCAD SHX Text
4
AutoCAD SHX Text
PROP 2-WAY CLEANOUT @ GRADE BREAK
AutoCAD SHX Text
PROP 8" PVC SCH 40 RAINWATER COLLECTION SYSTEM
AutoCAD SHX Text
PROP 4" GATE VALVE & BOX INSTALL 8"x4" REDUCE EACH SIDE OF VALVE
AutoCAD SHX Text
PROP 6" 2-WAY CLEANOUT, TYP. INSTALL AT BENDS AS SHOWN AND 50' INTERVALS
AutoCAD SHX Text
4
AutoCAD SHX Text
4
AutoCAD SHX Text
4
AutoCAD SHX Text
4
Page 27: 11/2/16 - RideCARTSridecarts.weebly.com/uploads/1/1/1/1/11111920/... · 11/2/2016  · 20110319-enrtyprox-revc-ds-en North America: +1 949 732 2000 Toll Free: 1 800 237 7769 Europe,