Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
Autostack HFC-JU Project No.: 245142
- 1 -
Agenda 18 April 2011
Topic Venue
Joint Workshop on Generic Stack Design, Cost Model Lucerne
and Resources Requirements Date 28.06.2011
Start 14:00
End 18:00
Convener Telefon-Nr. Minutes taken by Telefon-Nr. Agenda from
L. Jörissen +49-731-9530-605 18.04.2011
Participants CC
A. Martin L. Jörissen F. Finsterwalder P. Ekdunge T. Priem B. Andreas-Schott T. Giunti S. Sibona R. Ströbel
V. Banhardt F. Büchi G. Tsotridis R. Zuber M. Holzmann N. Zandona C. Loevenbruck J. Sfeir U. Hannessen
C. Navas A. Müller
Discussion / Result Remark / Action
Agenda
TOP 1. Welcome and Introduction to the Autostack Project TOP 2. OEM-Requirements for Automotive Fuel Cell Stacks TOP 3. European Supply Chain Analysis TOP 4. Stack Cost Analysis (Methodology) TOP 5. Coffee break TOP 6. Stack Cost Analysis (Preliminary Results) TOP 7. Draft Business Concept for a European Stack Integrator TOP 8. Discussion TOP 9. End of Meeting
Daimler AG
AutostackFinal Conclusions on
WP 1: OEM Stack Platform
General Assembly / Workshop on generic Stack Designs
Jun 28th 2011, Luzern
F. Finsterwalder
1
Automotive System Architecture
M
anode
cathode
coolant
MM
humidifier
radiator
MM
H2-blower
M
anode
cathode
coolant
MM
humidifier
radiator
MM
Simplified schematic
Features:• Air compressor without
expander• Gas-to-gas humidifier
(cathode out cathode in)
• High power density stack• An active / passive
H2 recirculation pumpp = 1 .. 2 bar abs
T = 55 .. 95°C max (outlet)
Rh cathode @ max power = 50%
2
High Level Stack Requirements
Stack nominal power (gross, continuous) 95 kW (requirement)(System power 80 kW)
Stack Open Circuit Voltage <430 V (requirement)(limit set by power electronics – consider OCV > 1V @ freeze T)
Minimum stack voltage >200 V (guidance)(limit depending on E-motor and DC/DC converter characteristics)
Weight <75 kg
Volume <60 l
Operating Temperature min -25°C (start capability)max +95°C (outlet temp.)
Interface parameters at nominal powerPressure 2 baraAir Stoichiometry 1,6 Cathode Humidification 50% (nominal OP)
3
Stack and Plate Design
Area Power density 95 kW, 1 W/cm2
Cell voltage at nominal power 0,67 VCurrent density at nominal power 1,5 A/cm2
Active area of stack 9.5 m2
Number of cells (1-row stack is a requirement) 300 .. 380 (staple height!)
Active are area per cell (projected) 317 cm2
Plate Area (a.a. = 60% of plate area) 528 cm2
Cell pitch 1,5 mm
Ci
Ao
Ai
Co
Wi Wo
Active Area (aspect ratio 1:3)Port
Region Transition
Region
Preliminary Plate Design (1 Path parallel Flow Field)
30,8 cm
10,3 cm
Plate Dimensions:
11,3 x 46,8 cm2
4
Packaging ComparisonAvailable Stack Box volume in OEM vehicles
Daimler(E-class)
Fiat(Panda)
VW(Jetta)
688
mm
610
mm
786
mm
688
mm
610
mm
786
mm
785 mm
Driving
direction
Driv
ing
dire
ctio
n
Top view
Sideview
618
mm
driving direction
865 mm
618
mm
driving direction
865 mm
770 mm610 mm
driving direction subfloor limit
5
critical due to crash
stack might be tilted
Driv
ing
dire
ctio
nPrinciple Stack Mounting Orientations
6
Packaging Conclusion
Stack can be fitted in common box
785 m
m60
5 m
m
510 mm
470
mm
600
mm
140 mm
450
mm
„common box“ volume
V = 40 l
7
Conflicting Targets / Major Gaps
• Essential target is to bring down costs of stack
• The latter are primarily determined by the PGM content
• Lowering PGM content entails technical challenges / conflicting targets
• Improving power density w/o compromising other targets is a long-term effort
• Short term mitigation: Trading off power density vs. Pt-loading
8
Gap Power Density / Pt LoadingFuel efficiency targets might even be more challenging
relevant for fuel efficiency relevant for top speed
15
Projected MEA (2015) "automotive ready"
Specific Stack Costs
17
Specific Stack Costs
Projected MEA “CEA cost study"
19
Conclusion
• The cost optimized Pt loading is influenced by:- the costs of membrane, GDL, BIP vs. Pt- the power density characteristics of the MEA
• Given today’s price structure, the cost optimized Pt loading goes along with meetings the power density target.
• Lower costs of area components / higher Pt costs shift the cost minimum towards lower Pt-loadings.
• Power density is the paramount target. High power density allows standardization, thus economies of scale and cost reduction.
20
Standardization & Economies of Scale
higher power density higher degree of freedom (packaging)
standardizationeconomies of scale (1)
Pt reduction economies of scale (2)
Addressing ultimate cost targets
Addressing product design targets
market volume
Cost optimized Pt loading is high
Cost optimized Pt loading movestowards lower values
Ultimate cost targets met
21
Open Issues
• Efficiency targets at reduced Pt-loading
• Limited turn-down ratio of thefuel cell stack
Fuel Cell Range Extenderas a short-term mitigation ?
…. to be discussed
Pre
ssur
e dr
op
in s
tack
Current density / volumetric flow / load
pmax
pmin
turn down ratio)
Daimler AG
Thank you very much for your kind attention
Seite 1
European Supply Chain Analysis
Paul Scherrer Institut
Stefan Kreitmeier, Philipp Dietrich, Felix Büchi
28th June 2011, Lucerne
6. Oktober 2011PSI,
Workshop on Cost Model and Resources Requirements
Seite 2
Objective
Inventory of the European stack component supply industry
Developing a technical roadmap for afuture generic PEFC stack platform
Autostack
Workpackage 2.1
Seite 3
Goals
1. Compiling a database of European companiesdealing with PEFC technology
2. Assessment of commercial availabilityand level of product maturity
3. Prepare basic technical data of PEFC materials and components suited for the stack platform
• Component properties
• Component cost
Seite 4
Boundaries
• Only stack repeating components
Membrane
Catalyst
GDL
Subgasket
Metallic BPP
Composite BPP
Sealing
BPP
MEA
Seite 5
Boundaries
• Only European suppliers of PEFC stack components
• Only stack repeating components
only representative for Europe
Seite 6
Boundaries
• Only European suppliers of PEFC stack components
• Only stack repeating components
• Component specifications were restricted to the requirements of Auto-Stack (WP 1)
Seite 7
Boundaries
• Only European suppliers of PEFC stack components
• Only stack repeating components
• Component specifications were restricted to the requirements of Auto-Stack (WP 1)
• For current and future preliminary mass production (250-25.000 stacks/year) in the time frame 2015 to 2020
• Non disclosure agreement
A minimum of 3 replies required fordata anonymisation based on averaging
Seite 8
Methodology
1. Compile an inventory of the European companies
Short questionnaire
Long questionnaire
with NDA
Interviewwith NDA+ +
2. Data acquisition
internetresearch
stakeholderdatabase
Fuel CellExhibition
+ +
Seite 9
Summary of results
1. Compiling a database of European companiesdealing with PEFC technology
Seite 10
Summary of component properties
1. Metallic bpp mostly fulfill the requirements
2. GDLs are supplied with adequate properties based on the Autostack requirements.
3. No evaluation for catalyst and sealing materials
Seite 11
Summary of component properties
4. Gap beetween demand and supply
• High power density at required low Pt loading
• Cell pitch for carbon composite BPP usage
• Coating technology for metallic BPP
6. Limited availability of high matured PEFC components in EU
Market competitiveness?
5. Inadequate disclosure of stack component durability
Seite 12
Summary of component cost
• 1 W/cm2 specific power density of the MEA at
• 95 kW stack power* (80 kW stack net power)
with
• 315 cells per stack with
• 300 cm2 active area
Cost specified for generic stack from Autostack
* DTI: 87 kW stack power for 80 kW net power
Seite 13
Summary of component cost
MEA: Agreement to DTI study for lowest cost target.
B. D. James, J. A. Kalinoski, K. N. Baum, DTI, Contract Nr. DE-AC36-08GO28308, Virginia, USA, 2010.
0.9 mio units23 €2015
2.4 mio units
300.000 units
@ annualproduction rate
14 €2020
74 €2010
Production cost[per kWstack]
4 mio units
1 mio units
100.000 units
@ annualproduction rate
n.a.14 €44 €2020
0.1 – 1 mio/a14 €62 €2015
10 – 300 k/a71 €124 €2010
Production capacity[units]
Lowestvalue
Meanvalue
Production cost[per kWstack]
DTI study
Seite 14
Summary of component cost
Membrane: Moderate cost dependency on production rate
B. D. James, J. A. Kalinoski, K. N. Baum, DTI, Contract Nr. DE-AC36-08GO28308, Virginia, USA, 2010.
30.0006 €2015
1000
@ annual stackproduction rate
40 €2010
Production cost[per kWstack]
100.000
10.000
1000
@ annual stackproduction rate
n.a.n.a.2020
10 €1 €2015
15 €n.a.2010
Per-fluorinated
Hydro-carbon
Production cost[per kWstack]
DTI study
Seite 15
Summary of component cost
B. D. James, J. A. Kalinoski, K. N. Baum, DTI, Contract Nr. DE-AC36-08GO28308, Virginia, USA, 2010. 30.0007 €2015
1000
@ annual stackproduction rate
16 €2010
Production cost[per kWstack]
100.000
10.000
1000
@ annual stackproduction rate
n.a.n.a.2020
1.5 €3.5 €2015
6 €13 €2010
Lowestvalue
Meanvalue
Production cost[per kWstack]
DTI study
GDL: 50% lower cost compared to DTI study in 2015
Seite 16
11 €
18 €
44 €
Metallic BPP Mean
value
8 €
15 €
37 €
Metallic BPP Lowest
value
30.00012 €20 €2020
300027 €42 €2015
30032 €87 €2010
@ annual stackproduction rate
CarbonBPP Lowest
value
CarbonBPP Mean
value
Productioncost
[per kWstack]
Summary of component cost
B. D. James, J. A. Kalinoski, K. N. Baum, DTI, Contract Nr. DE-AC36-08GO28308, Virginia, USA, 2010.
2.3 €
2.8 €
CarbonBPP
2015
2010
Production cost[per kWstack]
3 €
13 €
Metallic BPP
30.000
1000
@ annual stackproduction rateDTI
study
• Composite plates more expensive than metallic • Both metallic and composite plates are severalfactors more expensive compared to DTI study
BPP:
Seite 17
Summary of component cost
Only a limited number of suppliers with high maturity level of their product
Cost and technology assessment difficult
Seite 186. Oktober 2011PSI,PSI, Seite 18
Thank you very much for your kind attention
Status Work Package 4 Luzern 27.6.2011Preliminary results
André Martin Consulting
1. Deliverable 4.1 – Expertise and Resources
1/17/2012 1AMC
2
Combination and integration of expertise and resources of research, supply industry and OEMs.
Development of a joint technology roadmap and transparent collaboration scheme based on strategic partnerships.
Improvement of economies of scale by combining volumes of several OEMs andapplications based on joint platform concept.
Establishment of a dedicated development structure with focus on stack integration, validation and production.
Recruitment of experienced staff with solid track record in stack development to accelerate learning curves.
General assumptions of the business model
3
Core competences:•Stack development and design (concept, interfaces, specification, IP…)•Component specification and validation (MEA, BPP, BoP..)•Stack prototype build, testing and validation•Supply chain management Manufacturing/assembly
Support to core: •Sales & Marketing•Project- and program management •Quality system•Infrastructure and IT•Finance & Admin
Core competences of stack integrator
Overall staff demand:25 … 40 depending ofprogress
André Martin Consulting
2. Deliverable 4.2 – Market Study
1/17/2012 4AMC
Common OEM specification
Operating point 1,5 A/cm²@ 0,675 mV Pt-loading 0,15 mg/cm² Stack-power 95 kW, scalable Operating temperature < 95° C Operating pressure < 2bara Voltage 220 - 430 V Power density < 60l / 75kg Cost 40 €/kW @ 100000
5
State-of-the-art in stationary offers room for maneuver
1/17/2012André Martin Consulting 6
Stationary PEFC StacksModerate power density (~0.4 W/cm2)Medium cell pitch (~ 5 mm)High endurance ~ 20 000 h under
stationary conditions)Turn down ratio 1:3
Automotive PEFC StacksHigh power density (~ 1 W/cm2)Low cell pitch (<1,5 mm)Reasonable endurance < 10 000 h
under stationary conditions)Turn down ratio ~ 1:20
Several stationary applications have complementing requirements.Transfer of automotive design concepts can deliver substantial benefits.Stack design needs to be robust to allow sufficient flexibility.
Assessment identified technical compliance level
1/17/2012André Martin Consulting 7
Large potential based on technical synergy
1/17/2012André Martin Consulting 8
~ € 0,8 – 1,0 billion market potential even @ low penetration rates
1/17/2012 9AMC
According to Stack Voltage:Standard Voltage levels: 12 V, 24 V, 48 V, 96 V
According to design single cell voltage:High efficiency: 0.75 VAutomotive: 0.67 VHigh power: 0.62 V
According to BoP-Effort:
Low effort: ambient pressureAutomotive: 2 barabsHigh effort: 3 barabs
Possible Stack Classification
1/17/2012 André Martin Consulting 9
1/17/2012 10AMC
High efficiency stack for 24 V applications:Number of cells: 32 Average single cell voltage: 0.75 VPressure level: ambient Area specific power density: 0.5 W/cm2
Stack nominal power: 5 kW
Automotive:Number of cells: 314 Average single cell voltage: 0.67 VPressure level: 2 barabs Area specific power density: 1.0 W/cm2
Stack nominal power: 95 kW
High power density stack for 96 V applications:
Number of cells: 155 Average single cell voltage: 0.62 VPressure level: 3 barabs Area specific power density: 1.3 W/cm2
Stack nominal power: 61 kW
Stack design examples using the same cell hardware (active Area 300 cm2)
1/17/2012 10
1. Outline and objectives of the project
Standardized cell and battery design have reduced cost dramatically.
Success story consumer markets…
Anticipated overall market launch for FCEVsand other applications is now more certain
Assumed roll-out scenario of FCEVs in Europe *:
2015 – 100.000 FCEVs2020 – 1.000.000 FCEVS
Other applications have the potential to add 10 000s of units from 2015
Hence production volume potential of at least 50.000 units is assumed as baseline after ramp-up
* A portfolio of powertrains for Europe (McKinsey Study)
12
Use of platform concepts to help economies of scale early on
Standardized platform concepts are allowing superior scale effects in early phases of commercialization for both, OEMs and suppliers.
In the long-term, novel processes and materials will be required to achieve ultra-low Pt-loading targets and thus achieve the required scale effects at growing market volumes.
13
High power density
Improved flexibility (Packaging)
StandardizationEconomies of scale (1)
Pt - reduction Economies of scale (2)
Marktvolumen
André Martin Consulting
Deliverable 4.3 - Draft business plan
1/17/2012 14AMC
Massive savings are possible when accumulating volumes through a common platform concept
15
Total stack cost
Production rate
Savings by no of vehicles when arriving next level of scale effect:A B = 6,5 m €/1000 B C = 28,3 m €/10000C D = 46,5 m €/50000D E = 166,6 m €/100000
16
P & L - sensitivity analysis over three scenarios
Total Cash FlowScenario 1 58 M€Scenario 2 64 M€Scenario 3 72 M€
Breakeven 10 2004000
50000
André Martin Consulting
5. Summary and conclusions
1/17/2012 17AMC
Summary and conclusions
18
Economies of scale are much more important for early cost reduction than Pt-loading.
Pt-loading is a long-term issue for higher production volumes in combination with advanced technology while observing efficiency limitations.
High power density of the stack is key for platform concept and for achieving cost targets in mid term.
Market introduction of fc vehicles will require massive investment before and until reaching market penetration (optimum production rates).
Therefore, common platform concepts can help mitigate and substantially reduce market introduction cost.