Monthly Progress Report No. 39Covering Project Activities During
March 2016
PT. PERENTJANADJAJAin subconsultancy with ~ Yongma Engineering Co. Ltd and .iilPT. Epadascon Pennata Engineering ConsultantCTCOffice: JI. Ciniru VII No. 25, Kebayoran Baru, Jakarta 5elatan, 12180
Phone /Fax: (02i) 7229823
Team LeaderCc:
1. Direktur Jenderal Bina Marga2. Inspektorat Jenderal, Kementerian PU-PERA3. Direktur Transportasi - Bappenas4. Direktur Pengelolaan Kas Negara (PKN), Kementerian Keuangan5. Direktur Pengembangan Jaringan Jalan, Dit.Jen Bina Marga6. Direktur Jalan Bebas Hambatan, Perkotaan dan Fasilitasi Jalan Daerah, Dit.Jen Bina Marga7. Direktur Pembangunan Jalan, DitJen Bina Marga.8. Direktur Preservasi Jalan, Dit.Jen Blna Marga9. Biro Perencanaan & KLN, Kementrian PU-PERA10. Kepala Balai Besar Pelaksanaan JalanNaslonal t Medan11. Kepala Balai Besar Pelaksanaan Jalan Nasional llPadanq12. Kepala Balai Besar Pelaksanaan Jalan Nasionalill Palembang13. Kasubdit Keterpaduan Perencanaan & Sistem Jaringan, DPJJ - DJBM14. Kasubdit Manajemen Konstruksi, DPJ - DJBM15. Kepala Satker Pembinaan Administrasi dan Pelaksanaan Pengendallan PHLN16, PT. Perentjana Djaja17. Yongma Engineering Co, Ltd18. PT. Epadascon Pennata Engineering Consultant19. File "
This Report is reproduced in twenty (20) copies for distribution to all concerned authorities.
In compliance with the Terms of Reference of our Consultancy Contract, we submit herewith the MonthlyProgress Report NO.39 covering the month of March 2016.
Dear Sir,
Subject : Submission of March 2016 Monthly Progress Report No.39; WINRIP Loan IBRDNO.8043·ID
Attention: Ir. Agusta Ersada Sinulingga, MTOfficer In Charge PMU W1NRIP
Directorate General of Highways, MPWHJI. Patimura 20 Kebayoran Baru\Jakarta SelatanIndonesia
Jakarta,Apnl7,2016: 03_02/CTAlO/M-03.2016Our Ref.No.
Perentjana Ojaja
MINISTRY OF PUBLIC WORKS &. HOUSINGDIitECTORATE GENERAL OF HIGHWAYSDIRECTORATE OF ROAD NETWORK DEVELOPMENT
Core Team Consultant forWestern Indonesia National Roads Improvement Project (WINRIP)
IBROloan No.8043-10
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
ANNEXES
Annex P-1 : Package No. 1
Annex P-2 : Package No. 2
Annex P-3 : Package No. 3
Annex P-4 : Package No. 4
Annex P-5 : Package No. 5
Annex P-6 : Package No. 6
Annex P-7 : Package No. 7
Annex P-11: Package No.11
Annex P-13: Package No.13
Annex P-15: Package No.15
Annex P-17: Package No.17
Annex P-19 : Package No.19
05-Jul-15 Status tanggal : 25-Mar-16
Amount Time ellaps Remaining (incl VAT) days days Target Highest Avg The lastIDR million % % % % % %
BIHA - KRUI 25-Nov-13 640 10-Jan-16 154.073 100 100 -PT Jaya Konstruksi MP, Tbk
8-Jan-14 93 154.073 154.073
PADANG SAWAH-SIMPANG EMPAT 6-Dec-13 730 19-Apr-16 226.713 98,21 96,83 (1,37) 810 25 3,17 9,26 4,03 1,11PT Jaya Konstruksi MP, Tbk 6-Jan-14 105 222.646 219.535 97,00% 3,00%
MANGGOPOH - PADANG SAWAH 6-Dec-13 730 20-Mar-16 165.157 100 100 -PT Jaya Konstruksi MP, Tbk 6-Jan-14 75
165.157 165.157IPUH - BANTAL 14-Nov-13 730 11-Apr-16 196.438 96,29 91,62 (4,67) 803 17 8,38 9,09 3,82 6,98PT WASKITA KARYA - PT DMT, JO 13-Jan-14 90 189.142 179.976 97,92% 2,08% SIMPANG RAMPA - PORIAHA 17-Mar-15 540 8-Dec-16 107.321 52,88 10,11 (42,77) 282 258 9,99 2,74 1,26 2,74PT. NUSA KONSTRUKSI ENJ Tbk. 18-Jun-15 - 56.748 10.847 52,13% 47,87%KERKAP - PASAR PEDATI 27-Feb-15 450 31-Aug-16 86.517 85,36 27,55 (57,81) 291 159 36,22 7,76 2,50 1,67PT. WASKITA KARYA Tbk 11-Mar-15 90 73.852 23.840 70,50% 29,50%INDRAPURA-TAPAN 26-Nov-15 630 30-Aug-17 129.700 0,58 0,73 0,14 107 523 5,84 0,31 0,36 0,14PT. ADHI KARYA 10-Dec-15 - 757 944 16,85% 83,15%BANTAL - MUKOMUKO 18-Dec-14 720 11-Feb-17 262.611 43,85 38,87 (4,98) 397 323 5,56 6,20 3,89 5,83PT. HUTAMA KARYA - PT. DMT, JO 23-Feb-15 - 115.155 102.082 55,08% 44,92%SIMPANG RUKIS-TANJUNG KEMUNING 18-Dec-14 720 10-Jul-17 292.700 26,94 14,62 (12,32) 248 472 5,34 10,31 2,44 0,24PT. WASKITA KARYA 22-Jul-15 - 78.858 42.784 34,35% 65,65%SIBOLGA - Batas TAPSEL 13-Jul-15 810 6-Feb-18 260.100 5,57 1,69 (3,88) 127 683 4,27 0,50 0,84 0,27 PT. PEMBANGUNAN PERUMAHAN 20-Nov-15 - 14.488 4.391 15,57% 84,43%Sp.Gn KEMALA-PUGUNG TAMPAK 17-Nov-14 720 23-Aug-17 199.551 6,10 6,16 0,06 204 516 5,21 2,05 1,54 2,05PT Jaya Konstruksi MP, Tbk 4-Sep-15 - 12.169 12.288 - 28,23% 71,77% BINTUNAN-LAIS 27-Feb-15 300 8-May-16 44.418 79,68 80,78 1,10 381 44 9,61 24,57 7,34 3,44PT RODATEKNINDO PURAJAYA 11-Mar-15 125 35.392 35.882 89,62% 10,38%KAMBANG-INDERAPURA 28-Jan-16 720 358.650PT LANCARJAYA MA-CAHAYA TA,JO ? -BATAS KOTA PARIAMAN-MANGGOPOH 28-Jan-16 720 12-Mar-18 355.500 3 717PT PP - STATIKA JO 23-Mar-16 - 0,28% 99,72%
2.125.300 52,62 44,78 (7,84)####### 951.799 -
Review for Taking-Over Certificate. The95.39% progress is equivalent to 100%because the amount of provisional sumsGeneral Item was never utilized in theimplementetion of the works
01
02
03
Contractor SchTimeextension
Review for Taking-Over Certificate. The95.58% progress is equivalent to 100%because the amount of provisional sumsGeneral Item was never utilized in theimplementetion of the works
04
06
19
T O T A L :
05
13
15
17
11
07
12
08
Time for Complation
Actual Dev
Physical Progress (%)CONTRACTSIGN DATE
COW
CIVIL WORKS PROGRESSWESTERN INDONESIA ROAD IMPROVEMENT PROJECT (WINRIP)
Package No. & Name TakingOver
Certificate(PHO)
ContractPROGRESS ACHIEVEMENT
Time forCompletion
ESR March 2016_BDF25D
ANNEX P-1
MONTH :
Package No. Time Elapsed (Days) 807
Name Time Elapsed (%) 110,1%
Project Manager Scheduled Progress (%) 96,08 Contractor Actual Overall Progress (%) 91,02 Supervision Consultant Balance (%) -5,06Contract Sign Progress This Month (%) 14,46 Commencement Date Time for Complation (Days) 733 Take Over Date Status date Contract Amount Rp. Accumulative Rp. 71,80% Contract Amount Add-1 (+ VAT) Rp. *) Include advance payment
Comp Add.2 Accum Actual Accum AccumTotal Total Last this to this Sch to
% % Month Month Month thisMonth
I G e n e r a l 8,25 7,22 7,22 0,32 7,54 8,36II D r a i n a g e 34,19 23,78 24,29 1,06 25,35 20,11III Earthworks 3,95 6,56 4,14 0,51 4,65 7,41
IV Pavement Widening &Shoulders
1,47 0,94 0,54 0,48 1,02 0,80
V Granular Pavement 9,22 7,04 7,07 0,42 7,49 6,94VI Asphalt Pavement 40,14 46,76 38,74 2,32 41,07 44,78VII S t r u c t u r e s 1,09 5,36 5,23 1,18 6,41 5,96
VIII Reinstatement &Minor Works
1,20 1,91 3,47 2,58 6,05 5,16
IX Day Work 0,14 0,12 - 0,09 0,09 0,11
X Routine MaintenanceWorks
0,36 0,32 0,31 0,01 0,33 0,37
TOTAL 100,00 100,00 91,02 8,98 100,0 100,0Note :
2016Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 250,22 0,87 1,69 5,62 11,11 18,06 24,50 31,58 38,99 46,36 52,53 60,68 67,46
31,90 35,31 40,53 47,72 56,69 65,59 75,18 84,21 94,42 100,0088,43 91,76 96,08 100,00
0,10 0,58 0,79 1,59 2,93 3,71 4,79 5,98 8,60 11,28 12,62 16,08 18,71 21,04 25,88 32,67 37,50 42,27 45,05 55,51 65,00 70,08 76,56 91,02 100,00(0,12) (0,29) (0,90) (4,03) (8,18) (14,35) (19,71) (25,60) (30,39) (35,08) (39,91) (44,60) (48,75) (14,27) (14,65) (15,06) (19,18) (23,31) (30,13) (28,70) (29,43) (18,34) (15,19) (5,06) -
0,48 0,21 0,80 1,34 0,78 1,08 1,19 2,62 2,68 1,34 3,46 2,63 2,33
MAJOR PROBLEMS ACTION TO BE TAKEN
01
TIM
E March 25, 2016
BIHA - KRUI
RENARDET S.A JV
Joko Wisargo, ST, MT
AMO
UN
T
08-Jan-1425-Nov-13
DISBURSEMENT *)
110.630.337.746
EXECUTIVE SUMMARY REPORTMar-16
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS
31-Mar-16
PHYSICAL PROGRESS MONITORING TABLE2014 Year
10-Jan-16
PHYSICAL WORK PROGRESS BY CATEGORY
134.909.211.000154.073.015.000
2015
PT JAYA KONSTRUKSI MP, Tbk
Actual Progress (%) Balance (%)
Div Description
The month of time for complation
Rivised Progress Schedul Add.1 (%) Original Progress Schedul (%)
Month
Actual progress should not 100 % because there are still hasremaining items provisional sums IDR 7.10 billion even though civilworks has complete 100%.The actual condition shall be comparedwith final quantity.Civil Works progress maximum 95.39%
Rivised Progress Schedul Add.2 (%)
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
PHYS
ICAL
PRO
GRES
(%)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE #01
Original
1st Revised Shc
2nd Revised Sch
ACTUAL
ESR March 2016_BDF25D P-1
ANNEX P-2
MONTH :
Package No. Time Elapsed (Days) 809 Name Time Elapsed (%) 96,89% Project Manager Scheduled Progress (%) 98,21 Contractor PT JAYA KONSTRUKSI MP, Tbk Actual Overall Progress (%) 96,83 Supervision Consultant Balance (%) -1,37Contract Sign Progress This Month (%) 1,11 Commencement Date Time for Complation (Days) 730 Time for Complation (Days) 835 Status date Take Over Date Accumulative Rp. 80,98% Contract Amount Rp. *) Include advance payment Contract Amount Add-1 (+ VAT) Rp.
Comp Accum Actual Accum AccumTotal Last this to this Sch to
% % Month Month Month thisMonth
I G e n e r a l 10,46 3,378 3,00 - 3,00 3,14
II D r a i n a g e 3,53 3,244 3,24 (0,05) 3,19 3,24
III Earthworks 4,44 4,691 4,69 (0,54) 4,15 4,69
IV Pavement Widening &Shoulders
2,26 1,948 1,88 - 1,88 1,95
V Granular Pavement 10,49 10,944 10,94 (0,40) 10,55 10,94
VI Asphalt Pavement 52,09 57,028 56,06 1,34 57,40 56,36
VII S t r u c t u r e s 14,35 16,115 14,64 - 14,64 15,60
VIII Reinstatement & MinorWorks
1,65 2,002 0,74 0,70 1,44 1,43
IX Day Work 0,12 0,108 0,04 - 0,04 0,11
X Routine MaintenanceWorks
0,62 0,541 0,49 0,05 0,54 0,54
TOTAL 100,00 100,00 95,73 1,11 96,83 98,00
Note :
Year Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 Original Progress Schedul (%) 0,45 0,90 2,20 3,45 7,17 13,58 17,48 20,63 27,88 33,56 38,81 44,72 50,52 56,13 62,58 67,95 73,65 79,35 1st Revised Progress Schedul (%) 66,92 71,10 81,03 87,07 91,35 95,62 100,00 2nd Revised Progress Schedul (%) 92,53 95,62 96,75 97,25 98,21 100,00Actual - 0,13 1,02 2,19 4,11 5,96 9,69 13,85 22,55 25,61 31,45 33,73 40,41 44,25 49,98 55,715 58,61 58,35 63,76 71,36 77,80 83,27 92,53 93,20 92,85 95,73 96,83Balance (0,45) (0,77) (1,17) (1,26) (3,07) (7,62) (7,80) (6,78) (5,33) (7,95) (7,36) (10,99) (10,11) (11,88) (12,59) (12,23) (15,04) (8,57) (7,35) (9,67) (9,27) (8,08) (3,09) (2,41) (3,90) (1,52) (1,37)
0,89 1,17 1,91 1,86 3,72 4,17 8,69 3,07 5,84 2,28 6,68 3,84 38,29
The month of time for complation
DISBURSEMENT *)31-Mar-16
183.591.477.365
PHYSICAL WORK PROGRESS BY CATEGORY
Div Description
PHYSICAL PROGRESS MONITORING TABLE2014 2015 2016
226.713.217.000
19-Apr-16
EXECUTIVE SUMMARY REPORT
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS
Mar-16
197.936.699.000
Amandm04
March 25, 2016PADANG SAWAH-SIMPANG EMPAT02
TIM
E
MAJOR PROBLEMS ACTION TO BE TAKEN
AMO
UN
T
RENARDET S.A JV06-Dec-1306-Jan-14
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
PHYS
ICAL
PRO
GRES
(%)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE #02
ORIGINAL
1st Revised Sch
2nd Revised Sch
ACTUAL
ESR March 2016_BDF25D P-2
ANNEX-P3
MONTH :
Package No. Time Elapsed (Days) 809
Name Time Elapsed (%) 100% Project Manager Scheduled Progress (%) 99,31 Contractor Actual Overall Progress (%) 99,13 Supervision Consultant Balance (%) -0,18Contract Sign Progress This Month (%) 0,75 Commencement Date Time for Complation (Days) 730 Time for Complation (Days) 805 Status date Take Over Date Accumulative Rp. 81,59% Contract Amount Rp. *) Include advance payment Contract Amount Add-1 (+ VAT) Rp.
Comp Revised Accum Actual Accum AccumTotal Total Last this to this Sch to
% % Month Month Month thisMonth
I G e n e r a l 10,21 10,21 2,07 0,32 2,39 2,39II D r a i n a g e 13,17 13,17 10,09 - 10,09 10,09III Earthworks 3,04 3,04 6,99 - 6,99 6,99
IV Pavement Widening &Shoulders
2,45 2,45 1,38 0,54 1,92 1,92
V Granular Pavement 11,27 11,27 11,25 - 11,25 11,25VI Asphalt Pavement 55,81 55,81 60,20 (0,48) 59,72 59,72VII S t r u c t u r e s 0,80 0,80 5,35 (0,07) 5,28 5,28
VIII Reinstatement &Minor Works
2,27 2,27 0,46 1 1,02 1,02
IX Day Work 0,22 0,22 0,69 - 0,69 0,69
X Routine MaintenanceWorks
0,76 0,76 0,65 - 0,65 0,65
TOTAL 100 100 99,13 0,87 100 100Note :
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 270,26 1,00 1,67 2,45 4,78 7,45 10,70 14,27 21,53 30,10 36,95 44,01 51,62 58,67 65,63 73,03 79,97 87,04
70,14 74,54 82,69 89,96 95,17 97,89 100,0093,78 98,11 99,31 100,00
0,24 0,48 2,07 2,43 2,87 5,45 5,70 7,01 12,43 14,45 19,30 24,38 29,11 30,11 32,97 39,72 43,28 43,98 48,56 54,37 65,63 85,01 91,15 96,30 98,38 99,13 100,00(0,02) (0,52) 0,40 (0,02) (1,91) (2,00) (5,00) (7,26) (9,10) (15,65) (17,65) (19,63) (22,51) (28,56) (32,66) (33,31) (36,69) (26,16) (25,98) (28,32) (24,33) (10,16) (6,74) 2,52 0,27 (0,18) -
0,24 1,59 0,36 0,44 2,58 0,25 1,31 5,42 2,02 4,85 5,08 4,73 1,00
03
TIM
E March 25, 2016MANGGOPOH - PADANG SAWAH MAJOR PROBLEMS ACTION TO BE TAKEN
EXECUTIVE SUMMARY REPORT
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS
Mar-16
AMO
UN
T
RENARDET S.A JV06-Dec-13
PT JAYA KONSTRUKSI MP, Tbk
06-Jan-14
Actual progress should not 100 % because there are still hasremaining items provisional sums IDR 7.30 billion even though civilworks has complete 100%. The actual condition shall be comparedwith final quantity.Civil Works progress maximum 95.58%
DISBURSEMENT *)
20-Mar-1631-Mar-16
Div Description
134.753.354.692143.688.963.000
Balance (%)
2016
Rivised Progress Schedul (%)
165.157.772.000
Rivised Progress Schedul (%)
Actual Progress (%)
PHYSICAL PROGRESS MONITORING TABLE Year 2014 Month The month of time for complation
2015
PHYSICAL WORK PROGRESS BY CATEGORY
Original Progress Schedul (%)
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
PHYS
ICAL
PRO
GRE
S (%
)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE #03
ORIGINAL
1st Revised Sch
2nd Revised Sch
ACTUAL
ESR March 2016_BDF25D P-3
ANNEX P-4
MONTH :
Package No. Time Elapsed (Days) 802
Name Time Elapsed (%) 97,80%
Project Manager Scheduled Progress (%) 96,29 Contractor PT WASKITA KARYA - PT DAYA JO Actual Overall Progress (%) 91,62 Supervision Consultant Balance (%) -4,67Contract Sign Progress This Month (%) 6,98 Commencement Date Time for Complation (Days) 730 Time for Complation (Days) 820 Status date Take Over Date Accumulative Rp. 58,0% Contract Amount Rp. *) Include advance payment
Contract Amount Add-1 (+ VAT) Rp.
Comp Accum Actual Accum AccumTotal Last this to this Sch to
% Month Month Month thisMonth
I G e n e r a l 7,59 0,52 (0,00) 0,52 5,89II D r a i n a g e 12,26 7,92 (0,00) 7,92 6,92III Earthworks 3,58 3,02 0,04 3,05 3,06
IV Pavement Widening &Shoulders
3,39 3,04 (0,00) 3,04 3,04
V Granular Pavement 18,07 16,79 0,03 16,82 16,82VI Asphalt Pavement 49,27 45,08 1,79 46,87 46,88VII S t r u c t u r e s 2,55 4,68 (0,00) 4,68 4,68
VIII Reinstatement & MinorWorks
2,95 3,42 5,12 8,54 8,82
IX Day Work 0,14 0,00 0,00 0,00
X Routine MaintenanceWorks
0,20 0,17 0,00 0,17 0,18
TOTAL 100 84,64 6,98 91,62 96,29
Note :
Year Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr The month of time for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 Schedl Progress Original (%) 0,11 0,32 0,75 1,14 6,57 10,29 12,85 15,81 20,08 24,22 32,76 40,88 47,93 55,61 63,451st Revised Schedule (%) 28,57 37,28 48,18 56,89 64,18 73,78 84,47 91,89 98,53 2nd Revised Schedule (%) 61,23 62,14 76,26 86,77 96,29 100,0 Actual Progress (%) - 0,18 0,40 0,53 0,56 0,78 0,87 1,45 3,73 5,35 8,10 9,35 13,79 21,76 27,67 35,43 39,36 42,14 44,24 46,28 50,09 53,17 61,23 70,32 78,69 84,64 91,62 Balance (%) (0,11) (0,14) (0,35) (0,61) (6,01) (9,51) (11,98) (14,36) (16,35) (18,88) (24,66) (31,53) (34,14) (33,85) (0,91) (1,86) (8,81) (14,75) (19,95) (27,51) (34,38) (38,72) (37,30) 8,18 2,43 (2,13) (4,67)
0,22 0,13 0,03 0,22 0,09 0,58 2,27 1,62 2,76 1,25 4,44 7,97
RENARDET S.A JV
MAJOR PROBLEMS ACTION TO BE TAKEN
2015 20162014PHYSICAL PROGRESS MONITORING TABLE
PHYSICAL WORK PROGRESS BY CATEGORY
Div Description
196.438.084.000
EXECUTIVE SUMMARY REPORTMar-16
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS
13-Jan-1414-Nov-13
04
TIM
E March 25, 2016
IPUH - BANTALENDRO KUSUMOJOYO, ST.MT
AMO
UN
T
DISBURSEMENT *)
186.936.750.000113.856.052.141,0011-Apr-16
31-Mar-16
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
PHYS
ICAL
PRO
GRE
S (%
)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE #04
ORIGINAL
1st Revised Sch
2nd Revised Sch
ACTUAL
ESR March 2016_BDF25D P-4
ANNEX P-5
MONTH :
Package No. Time Elapsed (Days) 281
Name SIMPANG RAMPA - PORIAHA Time Elapsed (%) 52,04% Project Manager Ir.Juara M.Siahaan Scheduled Progress (%) 52,88 Field engineering and technical justification Speed up the process of field engineering Contractor PT. NUSA KONSTRUKSI ENJ Tbk. Actual Overall Progress (%) 10,11 unfinished Supervision Consultant Balance (%) -42,77Contract Sign Progress This Month (%) 2,74 Commencement Date Time for Complation (Days) 540 Take Over Date Status date Contract Amount Rp. Accumulative Rp. 13,58%
*) Include advance payment
Comp Accum Actual Accum AccumTotal Last this to this Sch to this
% Month Month Month Month
I G e n e r a l 8,09 0,93 0,02 0,95 5,29II D r a i n a g e 2,77 0,17 0,01 0,18 1,61III Earthworks 21,28 2,85 0,59 3,44 12,47
IV Pavement Widening &Shoulders
1,28 - - - -
V Granular Pavement 8,04 0,85 0,75 1,60 3,79VI Asphalt Pavement 38,75 - - - 12,21VII S t r u c t u r e s 16,22 2,58 1,36 3,94 15,24
VIII Reinstatement & MinorWorks
3,48 - - - 0,02
IX Day Work 0,10 0,00 0,00 0,00 0,06
X Routine MaintenanceWorks
- - - - -
TOTAL 100,0 7,37 2,74 10,11 50,69Note :
Year Month Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec The month of time for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 Schedl Progress Original (%) 0,22 0,99 3,89 8,90 16,87 23,69 36,44 40,23 46,08 52,88 57,21 61,53 66,93 71,12 79,57 90,71 96,82 100,0 100,0 Actual Progress (%) - 0,57 1,09 1,69 2,72 3,08 3,53 5,77 7,37 10,11 Balance (%) (0,22) (0,42) (2,80) (7,20) (14,16) (20,61) (32,91) (34,45) (38,70) (42,77)
0,57 0,52 0,60 1,03 0,37 0,44 2,25 1,60 2,74 (10,11) - - -
2015PHYSICAL PROGRESS MONITORING TABLE
107.321.260.310
2016
RENARDET S.A JV
05
TIM
E March 25, 2016
MAJOR PROBLEMS ACTION TO BE TAKEN
AMO
UN
T
EXECUTIVE SUMMARY REPORTMar-16
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS
DISBURSEMENT *)18-Jun-1517-Mar-15
Div Description
PHYSICAL WORK PROGRESS BY CATEGORY
31-Mar-1614.576.527.316
08-Des-16
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
PHYS
ICAL
PRO
GRE
S (%
)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE #05
Schedule
Actual
ESR March 2016_BDF25D P-05
ANNEX P-06
MONTH :
Package No. Time Elapsed (Days) 380 Name Time Elapsed (%) 84,44% Project Manager DINAR PANGAYOMAN, ST Scheduled Progress (%) 85,36 Field engineering and technical justification Speed up the process of contract amendment Contractor PT. WASKITA KARYA Tbk Actual Overall Progress (%) 27,55 have finished Supervision Consultant RENARDET S.A JV PT. CIPTA STRADA Balance (%) -57,81 Contract Sign Progress This Month (%) 1,67 Commencement Date Time for Complation (Days) 450 Calendar Days Take Over Date Status date Contract Amount Rp. Accumulative Rp. 27,90%
*) Include advance payment
Comp Accum Actual Accum AccumTotal Last this to this Sch to this
% Month Month Month Month
I G e n e r a l 0,83 0,68 (0,0) 0,68 0,58II D r a i n a g e 2,09 0,19 0,00 0,20 2,09III Earthworks 7,20 6,45 (0,00) 6,45 7,20
IV Pavement Widening &Shoulders
4,02 - - 1,88
V Granular Pavement 11,07 9,57 0,00 9,57 11,06VI Asphalt Pavement 70,65 7,46 1,65 9,10 59,12VII S t r u c t u r e s 0,92 0,88 (0,00) 0,88 0,92
VIII Reinstatement & MinorWorks
2,38 0,12 (0,00) 0,12 0,19
IX Day Work - - - -
X Routine MaintenanceWorks
0,85 0,53 0,02 0,55 0,75
TOTAL 100 25,89 1,67 27,6 83,78Note :
Year Month March Apr May June July August Sep Oct Nop Dec Jan Feb March Apr May The month of time for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Schedl Progress Original (%) 0,17 0,59 1,28 3,09 4,38 8,17 14,27 25,82 38,49 49,93 62,08 75,00 85,36 95,41 100,00 Actual Progress (%) 0,07 0,33 0,76 1,04 1,18 2,27 10,03 15,13 18,75 20,54 23,04 25,89 27,55 Balance (%) -0,15 -0,26 -0,53 -2,04 -3,20 -5,90 -4,24 -10,69 -19,74 -29,38 -39,04 -49,11 -57,81
0,42 0,29 0,13 1,10 7,76 5,09 3,62 1,79 2,49 2,85 1,67 (27,55)
6
TIM
E March 25, 2016KERKAP - PASAR PEDATI MAJOR PROBLEMS
EXECUTIVE SUMMARY REPORTMar-16
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS
02-Jun-16DISBURSEMENT *)
ACTION TO BE TAKEN
AMO
UN
T
27-Feb-1511-Mar-15
24.138.322.99631-Mar-16
2016PHYSICAL PROGRESS MONITORING TABLE
2015
86.517.470.000
PHYSICAL WORK PROGRESS BY CATEGORY
Div Description
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
PHYS
ICAL
PRO
GRE
S (%
)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE #06
Schedule
Actual
ESR March 2016_BDF25D P-06
ANNEX P-07
MONTH :
Package No. Time Elapsed (Days) 106 Name Time Elapsed (%) 16,83% Sub Project Manager / PPK Scheduled Progress (%) 0,58 Field engineering and technical justification Speed up the process of field engineering Contractor PT ADHI KARYA Actual Overall Progress (%) 0,73 unfinished Supervision Consultant Balance (%) 0,14Contract Sign Progress This Month (%) 0,14 Commencement Date Time for Complation (Days) 630
Take Over Date Status date Contract Amount (+ PPN) Rp. Accumulative Rp. 14,0%
*) Include advance payment
Comp Accum Actual AccumTotal Last this to this
% % Month Month Month
I G e n e r a l 2,45 0,54 0,06 0,60 0,43II D r a i n a g e 21,84 - - - -III Earthworks 5,38 - 0,00 0,00 0,00IV
Pavement Widening &Shoulders
1,09 - - - -V Granular Pavement 9,22 - - - -VI Asphalt Pavement 51,16 - - - -VII S t r u c t u r e s 6,08 - 0,04 0,04 -VIII
Reinstatement & MinorWorks
2,48 - - - -IX Day Work 0,09 - 0,01 0,01 0,01X
Routine MaintenanceWorks
0,20 0,05 0,03 0,08 0,14 TOTAL 100,0 - 0,59 0,14 0,73 0,58
Note :
Year 2015 Month Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug The month for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 Original Progress Schedul (%) 0,05 0,11 0,36 0,58 1,21 2,00 4,18 6,17 9,25 15,74 24,13 33,56 43,41 53,60 63,16 72,06 80,85 88,26 93,30 98,00 100,0 Actual Progress (%) - 0,31 0,59 0,73 Balance (%) (0,05) 0,21 0,23 0,14
0,38 0,14 (0,73) - - - - - - - - - -
March 25, 2016MAJOR PROBLEMS ACTION TO BE TAKEN
DISBURSEMENT *)30-Agust-17 31-Mar-16
10-Des-15
AMO
UN
T
7
TIM
E
INDRAPURA - TAPAN
RENARDET S.A JV PT. SEECONS03-Dec-15
18.093.136.050129.699.900.000
PHYSICAL PROGRESS MONITORING TABLE2016 2017
PHYSICAL WORK PROGRESS BY CATEGORY
Div DescriptionAmandment
Accum Schto thisMonth
EXECUTIVE SUMMARY REPORTMar-16
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
PHYS
ICAL
PRO
GRE
S (%
)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE # 07
Schecule Actual
ESR March 2016_BDF25D P-07
ANNEX P-11
MONTH :
Package No. Time Elapsed (Days) 396 Name Time Elapsed (%) 55,00% Project Manager Satker Wilayah I Scheduled Progress (%) 43,85 Contractor PT. HUTAMA KARYA, Tbk JO PT. DMT Actual Overall Progress (%) 38,87 Supervision Consultant RENARDET S.A JV PT. CIPTA STRADA Balance (%) (4,98) Contract Sign Progress This Month (%) 5,83 Commencement Date
Take Over Date
Time for Complation (Days) 720 Calendar Days Status date Contract Amount Rp. Accumulative Rp. 29,56% Contract Amount Add-1 (+ VAT) Rp. *) Include advance payment
Comp Accum Actual Accum AccumTotal Last this to this Sch to this
% % Month Month Month Month
I G e n e r a l 0,89 0,854 0,874 - 0,874 0,854II D r a i n a g e 1,97 2,493 1,238 0,04 1,277 1,917III Earthworks 26,30 11,273 6,258 1,16 7,414 7,503
IV Pavement Widening &Shoulders
5,13 3,597 - - 0,556 0,827
V Granular Pavement 7,31 14,409 6,847 1,36 8,204 8,525VI Asphalt Pavement 48,54 52,347 11,401 2,67 14,070 17,634VII S t r u c t u r e s 5,54 9,879 6,210 0,02 6,229 6,193
VIII Reinstatement & MinorWorks
4,00 4,873 0,036 0,03 0,062 0,249
IX Day Work - - - - - -
X Routine MaintenanceWorks
0,32 0,278 0,179 0,01 0,187 0,150
TOTAL 100,00 100,00 33,04 5,27 38,87 43,85Note :
Year Month March Apr May June July August Sep Oct Nop Dec Jan Feb March Apr May June July August Sep Oct Nop Dec Jan Feb The month of time for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Schedl Progress Original (%) 0,39 2,18 4,68 7,70 9,91 14,17 18,72 22,96
20,01 22,98 25,39 29,15 36,74 43,85 51,45 58,80 66,39 70,16 77,18 84,00 89,39 93,63 96,19 99,45 100,00 Actual Progress (%) 1,477 5,59 6,59 9,13 10,00 11,28 15,09 17,23 23,22 24,82 26,84 33,04 38,87 Balance (%) 1,08 3,42 1,92 1,43 0,09 (2,89) (3,64) (2,78) 0,23 (0,56) (2,31) (3,70) (4,98)
1,00 2,54 0,87 1,28 3,80 2,15 5,99 1,61 2,02 6,20 5,83 (38,87)
Rivised Progress Schedul (%)
PHYSICAL PROGRESS MONITORING TABLE2015 2016 2017
228.899.717.000,00262.611.303.000,00
PHYSICAL WORK PROGRESS BY CATEGORY
Div DescriptionAmend-
02
70.559.260.36231-Des-15
23-Feb-15
DISBURSEMENT *)11-Feb-17
18-Dec-14 AMO
UN
T
EXECUTIVE SUMMARY REPORTMar-16
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS11
TIM
E March 25, 2016BANTAL - MUKOMUKO MAJOR PROBLEMS ACTION TO BE TAKEN
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
PHYS
ICAL
PRO
GRE
S (%
)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE #11
Original Sch
Revised Sch
Actual
ESR March 2016_BDF25D P-11
ANNEX P-13
MONTH :
Package No. Time Elapsed (Days) 247
Name SIMPANG RUKIS-TANJUNG KEMUNING Time Elapsed (%) 34,31% Project Manager Scheduled Progress (%) 26,94 Field engineering and technical justification Speed up the process of field engineering Contractor PT. WASKITA KARYA Actual Overall Progress (%) 14,62 unfinished Supervision Consultant Balance (%) -12,32Contract Sign Progress This Month (%) 0,24 Commencement Date Time for Complation (Days) 720 Take Over Date Status date Contract Amount Rp. Accumulative Rp. 21,32%
*) Include advance payment
Comp Accum Actual Accum AccumTotal Last this to this Sch to this
% Month Month Month Month
I G e n e r a l 0,38 0,35 0,00 0,35 0,35II D r a i n a g e 1,87 0,51 - 0,51 1,16III Earthworks 16,52 2,86 - 2,86 8,90
IV Pavement Widening &Shoulders
4,11 - - -
V Granular Pavement 8,43 3,99 0,14 4,13 4,93VI Asphalt Pavement 64,33 6,13 0,10 6,23 10,41VII S t r u c t u r e s 2,05 0,01 - 0,01 1,08
VIII Reinstatement & MinorWorks
2,14 0,53 - 0,53 0,04
IX Day Work - - - -
X Routine MaintenanceWorks
0,18 - - - 0,07
TOTAL 100,0 14,37 0,24 14,62 26,94
Note :
Year Month Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul The month of time for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Schedl Progress Original (%) 0,02 0,21 1,65 4,18 6,69 9,61 14,62 20,36 26,94 33,58 41,24 47,87 50,63 58,32 63,60 68,28 72,97 77,66 82,62 86,79 91,19 95,75 99,36 99,74 100,00 Actual Progress (%) - 0,36 0,88 2,19 3,39 13,71 13,84 14,37 14,62 Balance (%) (0,02) 0,14 (0,77) (1,98) (3,30) 4,10 (0,78) (5,99) (12,32)
0,36 0,52 1,32 1,20 10,31 0,14 0,53 0,24 (14,62) - - - -
PHYSICAL PROGRESS MONITORING TABLE2015 2016 2017
PHYSICAL WORK PROGRESS BY CATEGORY
Div Description
DISBURSEMENT *)10-Jul-17 31-Mar-16
292.700.000.000,00 62.390.761.200
AMO
UN
T
RENARDET S.A JV18-Dec-1422-Jul-15
EXECUTIVE SUMMARY REPORTMar-16
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS
13
TIM
E March 25, 2016
MAJOR PROBLEMS ACTION TO BE TAKEN
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
PHYS
ICAL
PRO
GRE
S (%
)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE #13
SCHEDULE
ACTUAL
ESR March 2016_BDF25D P-13
ANNEX P-15
MONTH :
Package No. Time Elapsed (Days) 126 Name Time Elapsed (%) 15,6% Project Manager Ir. ASNER SILALAHI, MT Scheduled Progress (%) 5,57 Field engineering and technical justification Speed up the process of field engineering Contractor PT. PEMBANGUNAN PERUMAHAN Actual Overall Progress (%) 1,69 unfinished Supervision Consultant Balance (%) -3,88Contract Sign Progress This Month (%) 0,27 Commencement Date Time for Complation (Days) 810 Take Over Date Status date Contract Amount Accumulative Rp. 9,30%
*) Include advance payment
Comp Accum Actual Accum AccumTotal Last this to this Sch to this
% Month Month Month Month
I G e n e r a l 2,30 1,05 0,01 1,05 1,13II D r a i n a g e 19,42 0,03 0,03 0,06 2,34III Earthworks 13,18 - 0,07 0,07 1,26
IV Pavement Widening &Shoulders
1,95 - - - -
V Granular Pavement 11,46 - - - 0,21VI Asphalt Pavement 45,06 - - - -VII S t r u c t u r e s 3,81 0,20 0,15 0,35 0,19
VIII Reinstatement & MinorWorks
2,78 0,14 0,03 0,16 0,44
IX Day Work 0,04 0,00 - 0,00 0,01
X Routine MaintenanceWorks
- - - - -
TOTAL 100,0 1,42 0,27 1,69 5,57Note :
Year
Month Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec The month of time for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 Schedl Progress Original (%) 0,11 0,45 1,04 3,18 5,57 8,98 13,46 19,96 23,3 29,8 36,3 42,3 48,17 53,91 58,4 64,3 69,6 75,51 81,15 87,1 90,01 93,9 97,3 98,7 99,7 100,0 Actual Progress (%) 0,15 0,46 0,92 1,42 1,69 Balance (%) 0,03 0,02 (0,12) (1,76) (3,88)
0,32 0,46 0,50 0,27 (1,69) - - - - - - - -
SIBOLGA - BTS. TAPSEL
20-Nop-15
260.100.100.000
PHYSICAL PROGRESS MONITORING TABLE
2015 2016 2017
PHYSICAL WORK PROGRESS BY CATEGORY
Div Description
06-Feb-18 31-Mar-1624.189.300.000
A Joint Venture of Renardet, S.A.13-Jul-15
DISBURSEMENT *)
AMO
UN
T
15
TIM
E March 25, 2016MAJOR PROBLEMS ACTION TO BE TAKEN
Mar-16
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS
EXECUTIVE SUMMARY REPORT
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
PHYS
ICAL
PRO
GRE
S (%
)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE #15
Schedule
Actual
ESR March 2016_BDF25D P-15
ANNEX P-17
MONTH :
Package No. Time Elapsed (Days) 203
Name PUGUNG TAMPAK-Sp.Gn KEMALA Time Elapsed (%) 28,19% Project Manager Scheduled Progress (%) 6,10 Field engineering and technical justification Speed up the process of field engineering Contractor PT. JAYA KONSTRUKSI MP, Tbk Actual Overall Progress (%) 6,16 unfinished Supervision Consultant Balance (%) 0,06Contract Sign Progress This Month (%) 2,05 Commencement Date Time for Complation (Days) 720 Take Over Date Status date Contract Amount Rp. Accumulative Rp. 10,66%
*) Include advance payment
Comp Accum Actual Accum AccumTotal Last this to this Sch to this
% Month Month Month Month
I G e n e r a l 8,05 1,482 0,024 1,506 1,250II D r a i n a g e 12,92 0,40 0,247 0,65 1,43III Earthworks 16,93 2,05 1,515 3,57 2,11
IV Pavement Widening &Shoulders
7,36 - - - 0,16
V Granular Pavement 4,09 - - - 0,36VI Asphalt Pavement 42,82 - - - -VII S t r u c t u r e s 1,98 - 0,245 0,25 0,63
VIII Reinstatement & MinorWorks
5,30 0,001 - 0,001 0,03
IX Day Work 0,23 0,01 - 0,01 0,04
X Routine MaintenanceWorks
0,34 0,16 0,019 0,18 0,08
TOTAL 100,0 4,11 2,05 6,16 6,09
Note :
Year Month Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Jul Agt The month of time for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Schedl Progress Original (%) 0,18 0,70 1,18 1,51 2,39 3,80 6,10 10,09 14,15 18,21 21,04 26,32 33,01 39,79 46,73 54,12 61,80 69,15 75,00 80,05 85,25 90,26 95,19 100,0 100,0 Actual Progress (%) 0,921 1,13 1,42 3,05 3,45 4,11 6,16 Balance (%) 0,74 0,43 0,23 1,54 1,06 0,30 0,06
0,21 0,29 1,63 0,40 0,66 2,05 (6,16) - - - - - -
PHYSICAL PROGRESS MONITORING TABLE2015 2016 2017
PHYSICAL WORK PROGRESS BY CATEGORY
Div Description
23-Agust-17 31-Mar-16199.551.000.000 21.262.953.242,00
RENARDET S.A JV17-Nov-1404-Sep-15
DISBURSEMENT *)
AMO
UN
T
17
TIM
E March 25, 2016
MAJOR PROBLEMS ACTION TO BE TAKEN
EXECUTIVE SUMMARY REPORTMar-16
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
PHYS
ICAL
PRO
GRE
S (%
)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE #17
Schedule
Actual
ESR March 2016_BDF25D P-17
ANNEX P-19
MONTH :
Package No. Time Elapsed (Days) 380 Name Time Elapsed (%) 89,41 Project Manager Scheduled Progress (%) 79,68 Contractor Actual Overall Progress (%) 80,78 Supervision Consultant Balance (%) 1,10 Contract Sign Progress This Month (%) 3,44 Commencement Date Time for Complation (Days) 300 Calendar Days Time for Complation (Days) 425 Calendar Days Status date Take Over Date Accumulative Rp. 40,31% Contract Amount Rp. *) Include advance payment Contract Amount Add-1 (+ VAT) Rp.
Comp Accum Actual Accum AccumTotal Last this to this Sch to this
% Month Month Month Month
I G e n e r a l 0,43 0,23 - 0,23 0,23II D r a i n a g e 3,15 2,64 - 2,64 2,48III Earthworks 11,96 11,31 - 11,31 11,31
IV Pavement Widening &Shoulders
5,30 1,46 - 1,46 2,01
V Granular Pavement 10,69 8,82 - 8,82 8,82VI Asphalt Pavement 59,66 48,63 3,45 52,1 50,62VII S t r u c t u r e s 2,00 4,02 - 4,02 3,98
VIII Reinstatement & MinorWorks
6,79 0,20 - 0,20 0,20
IX Day Work 0,02
X Routine MaintenanceWorks
0,03 0,02 - 0,02 0,02
TOTAL 100,00 77,34 3,45 80,8 79,69Note :
Year Month March April May June July Aug Sept Oct Nov Des Jan Feb March April May The month of time for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Schedl Progress Original (%) 0,12 1,40 8,96 18,40 21,37 23,62 37,37 58,19 87,25 100,00
43,60 52,20 67,79 79,68 98,93 100,00 Actual Progress (%) 0,15 1,30 6,28 14,54 16,21 22,41 28,90 49,74 57,15 57,48 52,77 77,34 80,78 Balance (%) 0,03 -0,10 -2,68 -3,86 -5,16 -1,21 -8,47 -8,45 -30,10 13,88 0,57 9,55 1,10
4,98 8,26 1,67 6,20 6,49 20,84 7,42 0,32 (4,71) 24,57 3,44 (80,78)
2016PHYSICAL PROGRESS MONITORING TABLE
Div
PT RODATEKNINDO PURAJAYA
2015
PHYSICAL WORK PROGRESS BY CATEGORY
31-Mar-1617.907.342.643
27-Feb-1511-Mar-15
RENARDET S.A JV
33.689.452.00044.419.760.000
Description
Rivised Progress Schedul Add.1 (%)
DISBURSEMENT *)
AMO
UN
T
EXECUTIVE SUMMARY REPORTMar-16
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS 19
TIM
E March 25, 2016 BINTUNAN-LAIS MAJOR PROBLEMS ACTION TO BE TAKEN
08-Mei-16
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
PHYS
ICAL
PRO
GRE
S (%
)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE #19
ORIGINAL
REVISED SCH
ACTUAL
ESR March 2016_BDF25D P-19
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
ATTACHMENT No. 1
Summary of Submitted Environmental Reports
Attachment No.1 As of March 2016
1 2 3 5 6 7 8 9
1 Krui - Bha Lampung 1 SPPL November 2010 1X 24 Sep 2013 30 Sep 2013 20 Nov 2013 /NOL
2 AMDAL Environmental Feasibility : 12 Oct 2012
Environmental permits: 21 Nov 2012 1X 24 Sep 2013 30 Sep 2013 20 Nov 2013/NOL
3 Monitoring of Integration
AMDAL into Design - 1X 15 August 2014 NN NN
4 AMDAL Implementation Report
(PIU to BLH) - each 6month
17 April 2015 ; 6 Oct2015
29 April 2015 ; 19 Oct2015
11 Mei 2015 ; 14 Des2015
5 RKPPL - 1X 28 Jan 2015 06 Feb 2015 23 Feb 2015/NOL
6 RKPPL Implementation Report - Quarter 3 July 2015 ; 13 Nov
2015 31 July 2015 ; 24 Nov
2015 13 August 2015:
14 Dec 15
7 HIV - AIDS Campaign Report - 1X 8 January 2016 NY NY
2 Padang Sawah - Sp Empat Sumatera Barat 1 SPPL Nov. 2013 1X - 20 Jan 2014 14 April 2014/NOL
Jembatan Air Gadang Sumatera Barat 2 UKL & UPL Recommendation: Nov 2013 1X - 09 June 2014 08 Auguts 2014/NOL
3 UKL&UPL Implementation
Report (PIU to BLH) - each 6month
17 April 2015 ; 6 Oct2015
29 April 2015 ; 19 Oct2015
11 Mei 2015 ; 14 Des2015
4 RKPPL - 1X 11 Dec 2014 19 Dec 2014 30 Jan 2015/NOL
5 RKPPL Implementation Report - Quarter 3 July 2015 ; 13 Nov
2015 31 July 2015 ; 24 Nov
2015 13 August 2015:
14 Dec 15
6 HIV - AIDS Campaign Report - 1X 8 January 2016 Ny NY
3 Manggopoh - Padang Sawah Sumatera Barat 1 SPPL 30 Dec 2013 1X - 20 Jan 2014 14 April 2014
2 SPPL Implementation Report
(PIU to BLH) - each 6month
17 April 2015 29 April 2015 11 Mei 2015
3 RKPPL - 1X 11 Dec 2014 19 Dec 2014 30 Jan 2015/NOL
4 RKPPL Implementation Report - Quarter 3 July 2015 ; 13 Nov
2015 31 July 2015 ; 24 Nov
2015 13 August 2015:
14 Dec 15
5 HIV - AIDS Campaign Report - 1X 8 January 2016 UP NY
4 Ipuh - Bantal Bengkulu 1 SPPL (Initial study) 20 Dec 2013 1X April 2013 - -
2 UKL & UPL Environmental permits : 6 Des 2014 1X - 06 Feb 2015
(Environment permits) 23 Feb 2015
3 UKL&UPL Implementation
Report (PIU to BLH) - each 6month
17 April 2015 ; 6 Oct2015
29 April 2015 ; 19 Oct2015
11 Mei 2015 ; 14 Des2015
4 RKPPL - 1X 28 Jan 2015 06 Feb 2015 23 Feb 2015/NOL
5 RKPPL Implementation Report - Quarter 3 July 2015 ; 13 Nov
2015 31 July 2015 ; 24 Nov
2015 13 August 2015:
14 Dec 15
6 HIV - AIDS Campaign Report - 1X 8 January 2016 UP NY
Sent to WBCTC Letters to PMU4
DuarationsEnvironmental Safeguard
Correspondence of Environmental Safeguard and Reporting on CTC WINRIP
Date of Recomendation/Environmental Permits
No ofPackage
Name of Link Province
Environmental Activity, CTC WINRIP
WB NOL/Letters
Page 1 of 5
1 2 3 5 6 7 8 9
Sent to WBCTC Letters to PMU4
DuarationsEnvironmental SafeguardDate of Recomendation/Environmental Permits
No ofPackage
Name of Link Province WB NOL/Letters
5 Sp. Rampa - Poriaha Sumut 1 UKL & UPL Recommendation : 8 Dec 2011 1X 24 Sep 2013 30 Sep 2013 20 Nov 2013
2 Monitoring of Integration
UKL&UPL into Design - 1X 11 Nov 2014 NN NN
3 UKL&UPL Implementation
Report (PIU to BLH) - each 6month
NY NY NY
4 RKPPL - 1X UP UP NY
6 RKPPL Implementation Report Quarter NY NY NY
6 HIV - AIDS Campaign Report - 1X 29 February 2016 NY NY
6 Ps. Pedati - Kerkap Bengkulu 1 UKL & UPL Recommendation : 9 Nov 2011 1X 24 Sep 2013 30 Sep 2013 20 Nov 2013
2 Monitoring of Integration
UKL&UPL into Design - 1X 29 Oct 2015 NN NN
3 UKL&UPL Implementation
Report (PIU to BLH) - Quarter NY NY NY
4 RKPPL - one time 4 Nov 2015 24-Nop-15 12/14/2015/NOL
5 RKPPL Implementation Report Quarter 13 Nov 2015 24 Nov 2015 12/14/2015/NOL
6 HIV - AIDS Campaign Report - 1X 12 February 2016 NY NY
7 Indrapura - Tapan Sumatera Barat 1 AMDAL Environmental feasibility : 05 Feb 2014 ;
environmental permits : 5 Feb 2014 1X - 09 June 2014 08 August 2014
2 Monitoring of Integration
AMDAL into Design - 1X 2 Dec 2015 NN NN
3 AMDAL Implementation Report
(PIU to BLH) - each 6month
NYS NYS NYS
4 RKPPL - 1X NYS NYS NYS
5 RKPPL Implementation Report Quarter NYS NYS NYS
6 HIV - AIDS Campaign Report - 1X NYS NYS NYS
8 Bts. Kota Pariaman - Manggopoh Sumatera Barat 1 AMDAL Environmental permits : 23 July 2013 1X - 20 Jan 2014 14 April 2014
2 Monitoring of Integration
AMDAL into Design - 1X 6 Oct 2015 NN NN
3 AMDAL Implementation Report
(PIU to BLH) - each 6month
NYS NYS NYS
4 RKPPL - 1X NYS NYS NYS
5 RKPPL Implementation Report Quarter NYS NYS NYS
6 HIV - AIDS Campaign Report - 1X NYS NYS NYS
Page 2 of 5
1 2 3 5 6 7 8 9
Sent to WBCTC Letters to PMU4
DuarationsEnvironmental SafeguardDate of Recomendation/Environmental Permits
No ofPackage
Name of Link Province WB NOL/Letters
9 Bentungan- Tais (N.013.018 ; 43,42km)
Bengkulu
10 Sp. Empat - Air Balam Sumatera Barat 1 AMDAL Environmental permits : 23 July 2013 1X - 20 Jan 2014 14 April 2014
2 Monitoring of Integration
AMDAL into Design - 1X 6 Oct 2015 NN NN
3 AMDAL Implementation Report
(PIU to BLH) - each 6month
NYS NYS NYS
4 RKPPL - 1X NYS NYS NYS
5 RKPPL Implementation Report Quarter NYS NYS NYS
6 HIV - AIDS Campaign Report - 1X NYS NYS NYS
11 Bantal - Mukomuko Bengkulu 1 AMDAL Environmental permits : 3 April 2014 1X - 09 June 2014 08 August 2014
2 Monitoring of Integration
AMDAL into Design - 1X 10 Dec 2014 NN NN
3 AMDAL Implementation Report
(PIU to BLH) - each 6month
NY NY NY
4 RKPPL - 1X 10 Des 2015 23-Des-15 8 Jan 2016/NOL
5 RKPPL Implementation Report Quarter 13 Nov 2015 24 Nov 2015 14 Des 2015
6 HIV - AIDS Campaign Report - 1X 8 January 2016 UP NY
12 Kambang - Indrapura Sumatera Barat 1 AMDAL Environmental Feasibility : 05 Feb 2014 ;
Environmental permits : 5 Feb 2014 1X - 09 June 2014 08 August 2014
2 Monitoring of Integration
AMDAL into Design - 1X 2 Dec 2015 NN NN
3 AMDAL Implementation Report
(PIU to BLH) - each 6month
NYS NYS NYS
4 RKPPL - 1X NYS NYS NYS
5 RKPPL Implementation Report Quarter NYS NYS NYS
6 HIV - AIDS Campaign Report - 1X NYS NYS NYS
13 Sp. Rukis - Tj. Kemuning Bengkulu 1 UKL & UPL Recommendation : 31 Jan 2012 (Link of Sp Rukis
Mana-Bts Kab Kaur & 4 Feb 2012 (Bts Kaur - TjKemuning)
1X - 09 June 2014 08 August 2014
2 Monitoring of Integration
UKL&UPL into Design - 1X 6 Oct 2015 NN NN
3 UKL&UPL Implementation
Report (PIU to BLH) - each 6month
NY NY NY
4 RKPPL - 1X 4 Nov 2015 24-Nop-15 14 Dec 2015/NOL
5 RKPPL Implementation Report Quarter NY NY NY
6 HIV - AIDS Campaign Report - 1X 12 February 2016 NY NN
Page 3 of 5
1 2 3 5 6 7 8 9
Sent to WBCTC Letters to PMU4
DuarationsEnvironmental SafeguardDate of Recomendation/Environmental Permits
No ofPackage
Name of Link Province WB NOL/Letters
14 Painan - Kambang Sumatera Barat 1 AMDAL Environmental Feasibility : 05 Feb 2014 ;
Environmental permits : 5 Feb 2014 1X - 09 June 2014 08 August 2014
2 Monitoring of Integration
AMDAL into Design - 1X 2 Dec 2015 NN NN
3 AMDAL Implementation Report
(PIU to BLH) - each 6month
NYS NYS NYS
4 RKPPL - 1X NYS NYS NYS
5 RKPPL Implementation Report Quarter NYS NYS NYS
6 HIV - AIDS Campaign Report - 1X NYS NYS NYS
15 Sibolga - Bts. Tapsel Sumut 1 UKL & UPL Recommendation : 8 Dec 2011 1X 24 Sep 2013 30 Sep 2013 20 Nov 2013
2 Monitoring of Integration
UKL&UPL into Design - 1X 11 Nov 2014 NN NN
3 UKL&UPL Implementation
Report (PIU to BLH) - each 6month
NY NY NY
4 RKPPL - 1X UP UP NY
5 RKPPL Implementation Report Quarter NY NY NY
6 HIV - AIDS Campaign Report - 1X 29 February 2016 NY NN
16 Sebelat-Ipuh Inc.Air Lalang & AirGunung Bridges
Bengkulu 1 AMDAL Environmental permits : 3 April 2014 1X - 09 June 2014 08 August 2014
2 Monitoring of Integration
AMDAL into Design - 1X 10 Dec 2014 NN NN
3 AMDAL Implementation Report
(PIU to BLH) - each 6month
NYS NYS NYS
4 RKPPL - 1X NYS NYS NYS
5 RKPPL Implementation Report Quarter NYS NYS NYS
6 HIV - AIDS Campaign Report - 1X NYS NYS NYS
17 Sp. Gunung Kemala-Pg. Tampak, IncWay Tauu Bridge
Lampung 1 AMDAL Environmental Feasibility : 12 Oct 2012
Environmental permits: 21 Nov 2012 1X 24 Sep 2013 30 Sep 2013 20 Nov 2013
2 Monitoring of Integration
AMDAL into Design - 1X 11 Nov 2014 NN NN
3 AMDAL Implementation Report
(PIU to BLH) - each 6month
NY NY NY
4 RKPPL - 1X UP UP NY
5 RKPPL Implementation Report Quarter NY NY NY
6 HIV - AIDS Campaign Report - 1X 8 January 2016 UP NN
Page 4 of 5
1 2 3 5 6 7 8 9
Sent to WBCTC Letters to PMU4
DuarationsEnvironmental SafeguardDate of Recomendation/Environmental Permits
No ofPackage
Name of Link Province WB NOL/Letters
18 Seblat - Ketahun (N.013.005 :Panjang 42,07km)
Bengkulu
19 Lais- Bintunan Bengkulu 1 UKL & UPL Recommendation : 9 Nov 2011 1X 24 Sep 2013 30 Sep 2013 20 Nov 2013
2 Monitoring of Integration
UKL&UPL into Design - 1X 6 Oct 2015 NN NN
3 UKL&UPL Implementation
Report (PIU to BLH) - each 3month
NY NY NY
4 RKPPL - 1X 4 Nov 2015 24-Nop-15 14 Dec 2015/NOL
5 RKPPL Implementation Report Quarter 13 Nov 2015 24-Nop-15 14 Dec 2015/NOL
6 HIV - AIDS Campaign Report - 1X 12 February 2016 NY NN
20 Lubuk Alung - Sincin Sumatera Barat 1 UKL & UPL Recommendation : 27 Dec 2011 1X 24 Sep 2013 30 Sep 2013 20 Nov 2013
2 Monitoring of Integration
UKL&UPL into Design - 1X 29 Oct 2015 NN NN
3 UKL&UPL Implementation
Report (PIU to BLH) - each 6month
NYS NYS NYS
4 RKPPL - 1X NYS NYS NYS
RKPPL Implementation Report Quarter NYS NYS NYS
5 HIV - AIDS Campaign Report - 1X NYS NYS NYS
21 Lubuk Alung - Kuraitaji Sumatera Barat 1 UKL & UPL Recommendation : 27 Dec 2011 1X 24 Sep 2013 30 Sep 2013 20 Nov 2013
2 Monitoring of Integration
UKL&UPL into Design - 1X 29 Oct 2015 NN NN
3 UKL&UPL Implementation
Report (PIU to BLH) - each 6month
NYS NYS NYS
4 RKPPL - 1X NYS NYS NYS
5 RKPPL Implementation Report Quarter NYS NYS NYS
6 HIV - AIDS Campaign Report - 1X NYS NYS NYS
Keterangan :
NN : Not Need
UP : Under Process
incl. 1 Document Studi Amdal
incl. 1 Document Studi Amdal
NY : Not Yet incl. 1 Document Studi Amdal
NYS: Not Yet Started
Page 5 of 5
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
Appendix A
Overall Loan Progress
Estimated Contractor(s) or Total Est. BudgetStarting Completion Consultant(s) Man-Month WB + GOI Remarks
Date Date Name (Excl. the (PIP) Original Physical Man-Month Physical Man-Month Physical Man-Month
Supp. Staff) (USD, Excl.VAT) In IDR In USD Amendment No. 1 InIDR
Amendment No. 2 InIDR
Amendment No. 3 InIDR
Amendment No. 4 InIDR
Amendment No. 5 InIDR
Amendment No. 6 InIDR ( % ) ( MM ) ( % ) ( MM ) ( % ) ( MM )
1 Betterment and Capacity 308.730.000,00 $206.391.627,27Expansion of NationalRoads
1.A AWP-1 ICB DGH 81.630.000,00 $57.821.551,951.A1 08-Jan-14 10-Jan-16 1. Krui-Biha (PT. Jaya Konstruksi) 134.909.211.000,00Rp $11.757.337,74 154.073.015.000Rp 100% 100% 0,00% Completed
1.A2 06-Jan-14 19-Apr-16 2. Pd. Sawah-Sp. Empat(PT.Jaya Konstruksi) 197.936.699.896,00Rp $17.250.183,32 226.713.217.000Rp 249.348.931.000Rp 98,21% 96,83% -1,38% On - Going Construction
1.A3 06-Jan-14 20-Mar-16 3. Manggopoh-Pd. Sawah(PT. Jaya Konstruksi) 143.688.963.435,00Rp $12.522.493,13 156.157.772.000Rp 183.940.872.000Rp 100% 100% 0,00% Completed
1.A4 10-Jan-14 11-Apr-16 4. Ipuh-Bantal (PT. Waskita Karya) 186.936.750.000,00Rp $16.291.537,76 196.438.084.000Rp 96,29% 91,62% -4,67% On - Going Construction
1.B AWP-2 and AWP-3 ICB & NCB DGH 227.100.000,00 $148.570.075,32
18-Jun-15 08-Des-16 5. Sp. Rampa - Poriaha (PT. NusaKonstruksi Enjiniring Tbk.) 107.321.260.000,00Rp $8.084.464,03 52,88% 10,11% -42,77% On - Going Construction
11-Mar-15 02-Jun-16 6. Ps Pedati - Kerkap (PT. Waskita KaryaTbk) 86.517.470.000,00Rp $6.641.396,33 85,36% 27,55% -57,81% On - Going Construction
10-Des-15 30-Agust-17 7. Indrapura - Tapan (PT. Adhi Karya) 129.699.900.000,00Rp $9.350.065,79 0,58% 0,73% 0,15% On-Going Construction8. Bts. Kt Pariaman - Manggopoh (PT.PP/PT. Statika) 355.500.000.000,00Rp $25.627.995,00 NTP issued on March 23, 2016
9. R. Tikang - Kt. Agung Cancelled
10. Sp Empat - Sp Air Balam NOL on BER already issued by WB
23-Feb-15 11-Feb-17 11. Bantal - Mukomuko(PT. Hutama Karya - PT. DMT, JO) 228.899.717.000,00Rp $18.765.198,80 262.611.303.000Rp 43,85% 38,87% -4,98% On - Going Construstion
12. Kambang - Indrapura (PT.Lancarjaya/PT. Cahaya T.A) 358.650.400.000,00Rp $25.855.107,34 Contract signed on January 28,
2016
22-Jul-15 10-Jul-17 13. Sp. Rukis - Tj. Kemuning(PT. Waskita Karya) 292.700.000.000,00Rp $23.454.051,00 26,94% 14,62% -12,32% On-going construction
14. Painan -Kambang Bids opened on Jan 5, 201620-Nop-15 06-Feb-18 15. Sibolga - Bts Tap Sel (PT. PP) 260.100.000.000,00Rp $19.954.872,00 5,57% 1,69% -3,88% On-Going Construction
16. Seblat - Ipuh NOL on BER issued by WB
04-Sep-15 23-Aug-17 17. Sp. Gunung Kemala - Pg. Tampak(PT. Jaya Konstruksi) 199.551.233.000,00Rp $16.335.263,93 6,10% 6,16% 0,06% On-going construction
18. Mukomuko - Bts. Sumbar Cancelled
11-Mar-15 08-Mar-16 19. Lais- Bintunan (PT. RodatekindoPurajaya) Rp 33.689.452.000,00 $2.586.125,12 Rp 44.419.760.000 79,68% 80,78% 1,10% On - Going Construction
20. Lubuk Alung - Sicincin NOL issued by WB on March 23,2016
21. Lubuk Alung -Kuraitaji NOL issued by WB on March 23,2016
1.C Contingency - DGH 6.170.000,00
2 Implementation Support 16.000.000,00
2.A Core Team Consultants (CTC) QCBS DGH 06-Nop-12 06-Mar-16 PT. Perentjana Djaja 556 5.000.000,00 $1.276.700,00 $1.315.925,00 $1.371.925,00 $1.339.925,00 $1.743.780,00 $1.743.780,00 212.95 187.95 25.00 Supporting PMU. Joint Venture with Rp21.415.400.000,00 Rp22.426.175.000 Rp22.458.676.500 Rp23.934.595.000 Rp37.161.972.299 Rp37.161.972.299 Yongma Engineering Co.Ltd. Or US$ equivalent total : 25-Okt-13 03-Sep-14 30-Nop-15 04-Mar-16 04-Mar-16 PT. Epadascon Permata $3.512.681,91 $3.641.077,48
2.B Design & Superv. Consultants QCBS DGH 19-Jun-13 18-Nop-16 Renardet S.A. 1.068 10.000.000,00 $820.600,00 42.33 36.33 -6.00 Design preparation andconstruction supervision.
Joint Venture with Rp51.818.705.000,00 PT Cipta Strada Or US$ equivalent total : PT. Daya Creasi Mitrayasa $6.465.729,72 PT. Seecons PT. Yodya Karya
2.C Incremental Operating Cost Varies PMU 1.000.000,00Including Technical Audits
3 Road Sector Institutional 1.000.000,00Development
3.A Capacity Building for NCB DGH 1.000.000,00 TOR has been finalizedDisaster Risks Reduction
4 Contingency for Disaster DGH -Risk Response
5 Unallocated DGH 18.100.000,00
Total 343.830.000,00 216.370.038,90
31 March 2016
Contract ValueTotal ( WB + GOI )
PROGRESS
Respon-sibility Revised (in 000)
Appendix - AOVERALL PROGRESS STATUS
Description
WESTERN INDONESIA NATIONAL ROADS IMPROVEMENT PROJECT (WINRIP)IBRD LOAN No. 8043-ID
Proc.MethodCategory
Planned Actual Balance
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
Appendix B
Road Safety Audit Progress
Appendix B. Road Safety Audit Progresss (March 2016)
Old (2004) New (2009) Site VisitingSubmission of
ReportSite Visiting
Submission ofReport
Site VisitingSubmission of
Report1. No Road Safety Audit at Design Stage.2. Road Safety Engineering Review by CTC, Dec, 20143. RSA at Construction Stage/Monitoring of Traffic Mgmt & Safety by CTC, Dec, 2014
Date 13-Nop-14 29-Des-14 13-Nop-14 29-Des-14 11-Feb-16 22-Feb-16 4. RSA at PHO stage by CTC, Feb, 20161. No Road Safety Audit at Design Stage.2. Road Safety Engineering Review by CTC, Nov, 20143. RSA at Construction Stage/Monitoring of Traffic Mgmt & Safety by CTC, Nov, 2014
Date 09-Okt-14 05-Nop-14 09-Okt-14 05-Nop-141. No Road Safety Audit at Design Stage.2. Road Safety Engineering Review by CTC3. RSA at Construction Stage/Monitoring of Traffic Mgmt & Safety by CTC, Nov, 2014
Date 09-Okt-14 05-Nop-14 09-Okt-14 05-Nop-14 17-Mar-16 23-Mar-16 4. RSA at PHO stage by CTC, Mar, 20161. No Road Safety Audit at Design Stage.2. Road Safety Engineering Review by CTC3. RSA at Construction Stage/Monitoring of Traffic Mgmt & Safety by CTC, Dec, 2014
Date 13-Nop-14 29-Des-14 13-Nop-14 29-Des-141. Technical Advisory Report by International RSA CTC, Sept 2013
Date 08-May-13 17-Sep-131. Technical Review & RSA at Design Stage done by International RSA CTC3. RSA at Construction Stage/Monitoring of Traffic Mgmt & Safety by CTC, Sep, 2015
Date 18-Jul-13 17-Sep-13 25-Agust-15 08-Sep-151. Technical Advisory Report by International RSA CTC, Sept 2013
27-Sep-13 2. Road Safety Audit by Dit. EA & RS, May 20143. Result of Highway and RSA Final DED Review by CTC, Nov 2014
Date Apr-14 Mei-141. Technical Advisory Report by CTC, Sept 2013
27-Sep-13 2. Road Safety Audit by Dit. EA & RS, May 20143. Result of Highway and RSA Final DED Review by CTC, Nov 2014
Date Apr-14 Mei-141. Technical Advisory Report by CTC, Sept 2013
27-Sep-13 2. Road Safety Audit by Dit. EA & RS, May 20143. Result of Highway and RSA Final DED Review by CTC, Nov 2014
Date Apr-14 Mei-141. Technical Review & RSA at Design Stage by International RSA CTC , Jul, 20132. RSA at Construction Stage/Monitoring of Traffic Mgmt & Safety by CTC, Dec, 2015
Date 18-Jul-13 18-Jul-13 17-Des-15 29-Des-151. Technical Advisory Report by International RSA CTC, Sept 2013
27-Sep-13 2. Road Safety Audit by Dit. EA & RS, May 20143. Result of Highway and RSA Final DED Review by CTC, Nov 2014
Date Apr-14 Mei-141. Technical Advisory Report by International RSA CTC, Sept 2013
Date 18-Jul-13 18-Jul-131. RSA DED Report by CTC, June, 2015
Date 15-Apr-15 15-Jun-151. Technical Advisory Report by International RSA CTC, Sept 2013
Date 08-May-13 23-Sep-131. RSA DED Report by CTC, Sept, 2014
Date 14-Agust-14 01-Sep-14
Date1. Technical Advisory Report by International RSA CTC, Sept 20132. RSA at Construction Stage/Monitoring of Traffic Mgmt & Safety by CTC, Sep, 2015
Date 18-Jul-13 17-Sep-13 25-Agust-15 08-Sep-151. RSA DED Report by CTC, June, 2015
Date 15-Apr-15 15-Jun-151. RSA DED Report by CTC, June, 2015
Date 15-Apr-15 15-Jun-15
Notes :Road Safety Engineering Review by CTC
Road Safety Audit by International RSA CTC
Road Safety Audit by Dit. EA & RS DGH
Road Safety Audit by CTC
7 54.557Process
16.80 7 65.788Process
33%
Lais - Bintuan 13.009.1 13.007.0 10.80
14.60
No Road Safety Audit at Design Stage
6 110.237Process
33%
33%
19 #21 Lubuk Alung - Kuraitaji 06.027.0 06.025.0
7 35.886Process
66%
18 #20 Lubuk Alung – Sicincin 06.009.1 06.041.0
17 #19
Process33%
31.50 7 118.993Process
33%
16 #17 Sp.Gng Kemala–Pg.Tampak 17.061.1 17.025.0 36.80
15 #16 Seblat – Ipuh 13.010.0 13.004.0 34.50
6 255.269Process
0%
14 #15 Sibolga – Bts TapSel 03.016.1 03.044.0
7 316.304,8Process
33%
13 #14 Painan – Kambang 06.017.1 06.032.0
12 #13 SP.Rukis - TJ.Kemuning 13.006.0 13.021.0 56.30
35.86 7 376.479
45.20 7 438.675Process
33%
6 262.611Process
66%50.10
11 #12 Kambang – Indrapura 06.17.2 06.033.0
10 #11 Bantal - Mukomuko 13.015.2 13.002.0
7 511.375Process
33%9 #10 Sp.Empat – Sp. Air Balam 06.034.1 06.020.0 61.70
7 374.647Process
33%8 #8 Bts.Pariaman – Manggopoh 06.24.0 06.23.0 46.80
7 175.812Process
33%7 #7 Indrapura – Tapan 06.019.0 06.34.0 19.50
20.88 7 92.127Process
66%
6 152.870Process
33%9.7
6 #6 PS.Pedati - Kerkap 13.010.0 13.009.0
5 #5 Sp.Rampa – Poriaha xx.xxx.x 03.075.0
42.40 7 247.105Process
66%
7 167.678Process
100%32.00
4 #4 Ipuh - Bantal 13.051.1 13.003
3 #3 Manggopoh -Padangsawah 06.047.1 06.022.0
40.90 7 228.772Process
66%
7 163.535Process
100%25.00
2 #2 Padangsawah - Simpangempat 06.047.2 06.021.0
1 #1 Biha - Krui 17.053.0 17.027.0
EstimatedCost /
Excl.VAT(mil. RP)
Road Safety AuditTotal Process
(%)Remarks
StatusDesign Stage Construction Stage PHO StageNo
PkgNo.
Name of Sub-projectLink No Length
(km)Width
(m)
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
Appendix C
Financial Progress
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
Appendix C Financial Progress
The table below shows total expenditure to date measured in the terms of World BankCommitment.
DatePercentage
Completion oftime
WBExpenditureCommitment
Percentage ofAvailable
ExpenditureSource
31/03/2012 1.45% - - -30/04/2012 2.90% - - -31/05/2012 4.35% - - -30/06/2012 5.80% - - -31/07/2012 7.25% - - -30/08/2012 8.70% - - -30/09/2012 10.15% - - -31/10/2012 11.60% - - -30/11/2012 13.05% - - -31/12/2012 14.50% 800,000 0.32% Actual31/01/2013 15.95% 800,000 0.32% Actual28/02/2013 17.40% 800,000 0.32% Actual31/03/2013 18.85% 2,207,915 0.88% Actual30/04/2013 20.30% 2,207,915 0.88% Actual31/05/2013 21.75% 2,207,915 0.88% Actual30/06/2013 23.20% 2,207,915 0.88% Actual31/07/2013 24.65% 2,207,915 0.88% Actual31/08/2013 26.10% 2,207,915 0.88% Actual30/09/2013 27.55% 2,207,915 0.88% Actual31/10/2013 29.00% 2,207,915 0.88% Actual30/11/2013 30.45% 2,207,915 0.88% Actual31/12/2013 31.90% 2,207,915 0.88% Actual31/01/2014 33.35% 4,940,115 1.98% Actual28/02/2014 34.80% 4,940,115 1.98% Actual31/03/2014 36.25% 4,966,535 1.99% Actual30/04/2014 37.70% 4,966,535 1.99% Actual31/05/2013 39.15% 6,109,480 2.44% Actual30/06/2014 40.60% 6,263,610 2.51% Actual31/07/2014 42.05% 6,470,288 2.59% Actual31/08/2014 43.50% 6,470,288 2.59% Actual30/09/2014 44.95% 6,681,304 2.67% Actual31/10/2012 46.40% 6,991,757 2.80% Actual30/11/2014 47.85% 7,323,303 2.93% Actual31/12/2014 49.30% 11,533,045 4.61% Actual31/01/2015 50.75% 11,533,045 4.61% Actual28/02/2015 52.20% 12,794,201
4.61%Actual4.61%Actual
5.12% Actual31/03/2015 53.65% 14,918,776 5.97% Actual30/04/2015 55.10% 18,424,843 7.37% Actual
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
DatePercentage
Completion oftime
WBExpenditureCommitment
Percentage ofAvailable
ExpenditureSource
31/05/2015 56.55% 21,646,890 8.66% Actual30/06/2015 58.00% 23,691,573 9.48% Actual31/07/2015 59.45% 27,426,670
9.48%10.97% Actual
31/08/2015 60.90% 27,861,670 11.14% Actual30/09/2015 62.35% 31,214,254 12.49% Actual31/10/2015 63.80% 33,538,544 13.42% Actual30/11/2015 65.25% 37,740,899 15.10% Actual31/12/2015 66.70% 48,269,952 19.31% Actual31/01/2016 68.15% 48,845,535 19.54% Actual28/02/2016 69.60% 50,144,535 20.06% Actual31/03/2016 71.05% 52,938,748 21.18% Actual30/04/2016 72.50%31/05/2016 73.95%30/06/2016 75.40%31/07/2016 76.85%31/08/2016 78.30%30/09/2016 79.75%31/10/2016 81.20%30/11/2016 82.65%31/12/2016 84.10%31/01/2017 85.55%28/02/2017 87.00%31/03/2017 88.45%30/04/2017 89.90%31/05/2017 91.35%30/06/2017 92.80%31/07/2017 94.25%31/08/2017 95.70%30/09/2017 97.15%31/10/2017 98.60%30/11/2017 99.05%31/12/2017 100.00%
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
Appendix D
Quality Assurance Progress
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
Appendix D: Quality Assurance Progress
No Activities has been doneStatus/conditionDate of Finish/
completed1. Site Visit to Bengkulu/TFAC Mission package 11 and package 19 March 01 to 04, 2016
2. Leave March 07 to 08, 2016
3. Public Holiday March 09 , 2016.4. Preparation data for site visit package 02 and package 03 about
socialization flow of TOC/PHO.March 10 to 11,
2016.
5. Attended meeting CTC regular in CTC office. March 14, 2016.6. Duty trip to Padang (package 02 and package 03) March 15 to 18 ,
2016.7. Prepared an accountably report s budget of Padang site visit March 21 , 2016.
8. Prepared site visit report internal for TFAC and socializationTOC/PHO
March 22, 2016.
9. Revised (edited ) PMM 2015. March 23 , 2016.
10. Make site visit report package 02 and package 03. March 24 , 2016.
11. Public Holiday March 25, 2016.
12. Finalization make site visit report package 02 and package 03. March 28, 2016.13. Attendants monthly meeting with WB and TFAC meeting. March 29 , 2016.14. Prepared make monthly report CTC of QA March 30, 2016.15. To be continued Prepared make monthly report CTC of QA March 31 , 2016.
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
Appendix E
Environmental Progress and Social Progress
Length Width
(Km) (m) Result CommentsBudget
Alocated,YearStatus BLH Approval Result Comments
BudgetAlocated,Year
Status
THE WB Approval(A=Studi LARAP ;
B=ImplementationLARAP
A. NOL LARAP 04 Jan2013 ;
ICB/Prior B. NOL Mon Report (MR)18 April 2013, Rev 26 June2013.
2 Padang Sawah - Sp Empat Sumatera Barat 40,9 7 Total PAP 430 . No Land affected . Aset affected:building 149 unit = 2.110 M2 ; Fence 2 unit = 341.8 M; Kiosks BBM: 25 unit; Trees: 873 rod ; Mosque: 2 unit
A. NOL LARAP 13 Jan 2013;
2a Including Air Gadang Bridge Sumatera Barat 100 m 7 Total PAP 15. Land affected 2,110 M2 ; Aset affected:building 6 unit = 410 M2 ; Trees 72 rod.
B. NOL MR-1: 19 July2013, MR-2:12 Feb 2015
ICB/Prior A. NOL LARAP 04 Jan 2013
B. NOL MR-1: 26 June2013, MR-2: 5 Mar 2014,MR-3: 23 Jun 2014, MR-4:12 Feb 2015, MR-5: 17Mar 2015.
A. NOL LARAP 10 Dec 2012
ICB/Prior B.NOL MR-1: 6 Jan 2014,MR-2: 5 Mar 2014, MR-3:12 Feb 2015
NCB/Post A. NOL LARAP 16 Sept2013, and approvalrevision the report 12 Nov2013; Waiting NOL WB forAdditional LARAP B= Not Yet
A. NOL LARAP 20November 2013;
NCB/Post B: NOL MR-1: 23 Mar2015. NOL MR-2: 26 Nov2015
ICB/Prior NOL Larap: Oct 14, 2014
B: NOL WB MonitoringReport-1 (276 PAP) onMarch 8, 2016
A. NOL LARAP 12 Sep2014;B: NOL WB for theMonitoring Report-1 onMarch 8, 2016
ICB/Pr
ENVIRONMENTAL : a) The RKPPL :Complete NOL WB issued on 23 Feb 2015, b) theexternal monitoring of implementation UKL&UPL (period 1) to BLH wassubmit to the WB on 29 April 2015 & (period 2) submit to WB on 14Dec 2015. CTC propose schedule to carried out AMDAL monitoring forBLH (refer to environmental permit) at 11 April 2016 then period 3 willsubmit to WB end of April 2016c) The implementation of RKPPL (periode January to April 2015) hasbeen submit to PMU & WB on 3 July 2015 &(April to June 2015)submit to PMU on 14 Dec 2015,then period 3 (jan to April 2016 willsubmit at April 2016. d) The HIV-AIDS campaign complete on 4 Dec2015. e) the quarry, AMP & Stone Crusher permits from Bupati, (thequarry owner & contractor not yet make changes the permission(Bupati to Governor refer Law No.23 year 2014) . SOC: Complete
Ipuh- Bantal4 Bengkulu 42,4 7
ENVIROMENTAL: a) The project PHO on 20 Jan 2016. b) The RKPPL :Complete, NOL issued from the WB on 23 Feb 2015, & RKPPLimplementation (Environmental Quarterly) was Complete until period3 (Oct - Dec 2015). c) the external monitoring of implementationAMDAL (period 3) was submit to the WB on 14 Dec 2015. CTC proposeschedule to carried out AMDAL monitoring for BLH (refer toenvironmental permit) at 9 May 2016. d) The Integration ofrecommendation AMDAL in to the design Complete.e) The HIV-AIDS campaign complete on 10 Nov 2015. e) the quarry,AMP & Stone Crusher permits from Bupati, (the quarry owner &contractor not yet make changes the permission (Bupati to Governorrefer Law No.23 year 2014) . SOCIAL: Certification of land affected isbeing resolved by PPK/Satker PJN II Lampung
Manggopoh - Padang Sawah3 Sumatera Barat 32 7 SPPL Air pollution, traffic congestion,market on street, soft soil andrivers
APBN (P2JN 2010) 100% YES Recommended2010. SPPL no needNOL from the WB.
LARAP Total PAP 1.338 . No affected land . Aset affected:building 115 unit = 668,33 M2; Culvert 661,05 m;concrete & foundations 1.421,60M3 ; Soilembankment 5.564,21 M3; Trees 5.324 rod
Rp. 1.147.700.000APBD Prov Sumbar,Dinas PU, 2012/2013;4.9 M from APBD2014
Complete ENV IRONMENTAL: a) TOC 20 Mar 2016, b) The RKPPL :Complete NOLWB issued on 30 January 2015. b) the external monitoring ofimplementation SPPL was submit to the WB on 29 April2015/Complete. c) RKPPL implementation (periode October toDecember 2015)has been submit to PMU& WB on Dec 2015,d) TheHIV-AIDS campaign complete on 17 Nov 2015. e) the quarry, AMP &Stone Crusher permits still from Bupati (the quarry owner & contractornot yet make changes the permission (Bupati to Governor refer LawNo.23 year 2014) . SOC : Complete
LARAP Total PAP 2.805 in 21 Pekon. Land affected 28.763,12M2 ; Aset affected : building 882,13 M2; Fence2.445,41 M ; Trees 653 rod ; paddy field 25 plots ;Social & Pablic Facilities
Air pollution, traffic congestion,steep slopes, soft soil and riversand beach abrasion
APBN (P2JN 2010 &2011)
100% YES RecommendedSPPL 2010 and AMDAL2012 & NOL WB issuedon 20 Nov 2013. Note:environmentalmitigation was makedetail on RKPPL
1 Krui - Bha Lampung 25 7
Pending issues : (1) compensation for the remaining 1PAP on the Air Gadang Bridge, and 24 new PAP asAdditional LARAP not yet paid by LG. (2) Certificationof the land affected for 13 plots not yet availableresolved.
LARAP Total PAP are change from 227 PAP becomes 257 PAP.257 PAP has received compensation from The LocalGovernment as : Affected Assets: house building =307,05 M2; terace = 672,84M2; fence = 503,85M ;foundation = 8,9 m; pavement = 2,632,01M2; Trees =82 rod, tomb = 7 unit
Rp.286.743.000.APBN, Satker PJN I,Bengkulu, 2013
Complete
(1). Relocation for one kiosk already be done. (2).Additional LARAP approval WB on January 8, 2016.(3) Compensation payment for 71 PAPs is underresolved by Satker PJN II Sumatera Utara
PMU/CTC waiting data of payment progress for 389PAPs from Satker PJN II West Sumatera
SPPL 100%andUKL&UPL
Geometric, traffic congestion,steep slopes, soft soil and riversand beach abrasion
APBN (P2JN 2010) SPPL 100%,UKL&UPLcontract(100%)
YES Recommended2010 for SPPL andUKL&UPLrecommendation byBLH was issued on 30Oct 2014 &environmental permitswas publish by BupatiMuko Muko on 8 Dec2014.
100% YES Recommended2011. UKL&UPL no needNOL from the WB.
SimpleLARAP
(1). 1 PAP with aset affected : 1 kiosk BBM. Agree torelocate the kios. Relocate to the beside her house.Relocating costs be the responsibility of the project;(2). Require permit the state land use (14 ha) of theMinister of Forestry and environmental life, andcompensation payment for 4 buildings and the 7.724trees affected (Additional LARAP)
SOCIAL ENVIRONMENTAL STATUS & PROGRESS FOR WINRIP, IBRD LOAN NO.8043-ID
Remedial Action
AWP - 1
No Loan Package Name Provinces
Procur
Approval Status by Environmental Agency (BLH)Environmental Screening Social Screening Approval Status by The World Bank
YES Recommended2010. UKL&UPL no needNOL from the WB.
ICB/PriorSPPL&UKL/UPL
Bridge
LARAP Rp.2.340.600.000APBD Prov Sumbar,Dinas PU, 2012
APBN (P2JN 2010) 100%
Rp. 5.172.349.955APBN, Satker PJN IILampung, 2011 - 2012
Pending issue: Certification of the land affected isunder process
SPPL &AMDAL
Appendix E : Progress of Social Environmental Safeguard Studies on WINRIPas per 31 March, 2016
one link,sensitive areas/resident,public,facilities, squater (no landacquisition), market,sopt soil andrivers
ENV IRONMENTAL: a) The RKPPL :Complete. NOL WB issued on 30 Jan2015. b) the external monitoring of implementation UKL&UPL to BLH(period 1) was submit to the WB on 29 April 2015. & (period 2) submitto WB on 14 Dec 2015. CTC propose schedule to carried out AMDALmonitoring for BLH (refer to environmental permit) at 5 April 2016then period 3 will submit to WB end of April 2016,c) RKPPLimplementation, period (October to December 2015) has been submitto PMU & WB on 14 Dec 2015, period Jan to March 2016 will submit toPMU/WB at April 2016. d) The HIV-AIDS campaign complete on 17 Nov2015. e) the quarry, AMP & Stone Crusher permits still from Bupati,(the quarry owner & contractor not yet make changes the permission(Bupati to Governor refer Law No.23 year 2014)
AWP - 25 Sp. Rampa - Poriaha Sumatera Utara 11,1 6 UKL&UPL slope stability, water quality, Run
off, bridges acces, continuedtraffic access & quarry problem
APBN (BBPJN I 2011)
APBN (TLKJ 2012) 100%
ENVIRONMENTAL :a) The contractor under reviewing the RKPPL based on CTC comments.the final RKPPL will submit to PMU/WB end of April 2016. b). Theexternal monitoring of implementation UKL&UPL to BLH not yetprepare, CTC propose schedule to carried out AMDAL monitoring forBLH (refer to environmental permit) at 26 April 2016 then period 3 willsubmit to WB end of April 2016. b) The HIV-AIDS campaign completeon 28 Jan 2016.e) the quarry, AMP & Stone Crusher permits from Bupati, (the quarryowner & contractor not yet make changes the permission (Bupati toGovernor refer Law No.23 year 2014) . SOCIAL: The payment for 716 Ps Pedati - Kerkap Bengkulu 25 7 UKL&UPL Comersial areas, traffic
congestion, market on the street,air pollution & noise,
APBN (TLKJ 2011) 100% YES Recommended2010. UKL&UPL no needNOL from the WB.
LARAP Total PAP = 637. Affected land = 3,625 M2. Terrace =2,925 M2 ; Fence = 4,169 M, pavement = 4399 m2
RP. 8.049.290.000APBN, Satker PJN I,
Bengkulu, 2014
Complete ENVIRONMENTAL :a) The RKPPL complete, WB NOL issues on 14 Dec 2015, b) UKL&UPLimplementation for BLH not yet prepare, CTC propose schedule tocarried out AMDAL monitoring for BLH (refer to environmental permit)at 11 April 2016 then period 3 will submit to WB end of April 2016.c)the RKPPL implemetation (period 1) has been submit to PMU/WB,period 2 Jan to March 2016 will submit to PMU/WB at April 2016. b)The HIV-AIDS campaign complete on 12 Jan 2016. c) the quarry, AMP &Stone Crusher permits from Bupati, (the quarry owner & contractornot yet make changes the permission (Bupati to Governor refer LawNo.23 year 2014).SOCIAL: LARAP implementation is completed
Rp.2.900.000.000APBN, Satker PJN II,
Sumut, 2016
Completed/YESEnvironmental permitson Feb 2014. & NOL WBissued on 8 Aug 2014
LARAP Total PAP 861 change original 1,193. Partilly affectedbuilding ( houses an kiosks) = 4,013 M2 : Affectedfence = 19,206 m : Partially affected other building(terrace, decker and floors) = 9,401 M2, and trees =3,290.
Rp 3,5 Billion. APBN2015,
ENVIRONMENTAL; a) COW 10 Dec’15, b) CTC propose schedule tocarried out AMDAL monitoring for BLH (refer to environmental permit)at May 2016 then period 3 will submit to WB first of June 2016.SOCIAL: Now, PMU/CTC waiting a data progress compensationpayment Satker PJN II - West Sumatera Province
8 Bts. Kota Pariaman - Manggopoh Sumatera Barat 4680% 700% AMDAL Comersil areas, market, publicfacilities, Air pollution, trafficcongestion, market on street, softsoil and rivers
APBN (TLKJ 2011) 100% Completed/YESEnvironmental permitson July 2013. & NOL WBissued on 14 April 2014
LARAP Total PAP 1.575 change from original 1,282. Partillyaffected building ( houses an kiosks) = 8,352 M2 :Affected fence = 3,673 m : Partially affected otherbuilding (terrace, decker and floors) = 8,771 M2 andtrees = 7,863.
Rp 12.76 Billion. APBDProv Sumbar, DinasPU,
MR-2 (613 PAPs) is under preparation by Satker/CTC.PPK/Satker PJN I West Sumatera and LocalGovernment is under appraisal process for theremaining PAP.
ENVIRONMENTAL; a) The project not yet started, b) CTC need check tofield for preparing the external monitoring report of implementationAMDAL (Pre - Construction phase) and should submit to PMU/PPK/WB.SOCIAL: PPK/Satker PJN I West Sumatera and Local Governmant arebeing paid the remaining PAP
7 Indrapura - Tapan (1 Doc Amdal) Sumatera Barat 19,5 7 AMDAL Sensitive forest areas, socialissues, slope stability, waterquality, waste management, airpollution, squater on ROW etc
Length Width
(Km) (m) Result CommentsBudget
Alocated,YearStatus BLH Approval Result Comments
BudgetAlocated,Year
Status
THE WB Approval(A=Studi LARAP ;
B=ImplementationLARAP
Remedial ActionNo Loan Package Name Provinces
Procur
Approval Status by Environmental Agency (BLH)Environmental Screening Social Screening Approval Status by The World Bank
A. -
A. NOL LARAP 12 Sep2014;
B: NOL WB for theMonitoring Report-1 onMarch 8, 2016
ICB/Prior A. NOL LARAP 20November 2013;
B: NOL WB-1: 2 Dec 2014,NOL WB-2: 12 Feb 2015
ICB/Prior NOL Larap: Oct 14, 2014
B: Monitoring Report onSep 2015 (target)
ICB/Prior A. NOL LARAP 20November 2013;B: NOL WB-1: 18 Aug2015, NOL WB-2: 13 Oct2015
ICB/Prior A. NOL LARAP 19December 2014;
B: Monitoring Report onOct 2015 (target)
ICB/Prior A. NOL LARAP 28 October2013 and NOL revise 05Feb 2014;
B: NOL WB-1: 16 Nov 2015
Seblat - Ipuh including (1 Amdal) 34,5 6 A. NOL LARAP 20November 2013;
Air Lalang & Air Guntung Bridge 64 m 6 B: NOL MR-1: 12 Feb 2015
A. NOL LARAP 16 Sept2013
B: Monitoring Report - 1on Jul 2015 and MR-2 onNov 2015
A. -
NCB/Post A. NOL LARAP 20November 2013;B: NOL MR-1: 23 Mar2015. NOL MR-2: 26 Nov2015
NCB/Post Target LARAP approvalfrom WB is Dec 2014
B: Monitoring Report onOct 2015 (target)
Target LARAP approvalfrom WB is Dec 2014
NCB/Post B: Monitoring Report onOct 2015 (target)
NCB/Po
ICB/Pr
ICB/P
YES Recommended2012.UKL&UPL no needNOL from the WB.
LARAP
Total PAP 259 changed from original 316. No affectedland, Affected assets: building= 658 M2 ; Terrace= 98;Fence= 232 M ; Trees 33 rod
Complete
LARAP is under preparation by Balai III Palembang.This package was changed to Bengkunat - Biha
RP. 8.237.443.000APBN Satker PJN I,Bengkulu, 2014
Complete
RP. 11.295.833.000APBN, Satker PJN IBengkulu, 2014
Starting the compensation payment to the remainingPAPs (3.106) still waiting revision the DIPA 2016
YES Recommended2011. UKL&UPL no needNOL from the WB.
LARAP
17 Lampung ICB/Prior YES Recommended2012. & NOL WB issuedon 20 Nov 2013
APBN (TLKJ 2011)
100%
16 Bengkulu ICB/Prior
AMDAL
100%AMDAL sensitive areas/steep slopes, softsoil and rivers and beach abrasion
AWP - 3
ENVIRONMENTAL: a) The RKPPL under review by the contractor basedon CTC comments. b) CTC propose schedule to carried out AMDALmonitoring for BLH (refer to environmental permit) at 9 May 2016 thenperiod 3 will submit to WB firs of June 2016. , c) The HIV-AIDScampaign, complete on 27 Jan 2015 . d) CTC not yet receive of licensefor quarry,AMP & Stone Crusher. SOC: PMU waiting data of paymentprogress from PPK/Satker PJN II Lampung as to be submitted to WB.
100% ENVIRONMENTAL: Link of Bengkunat-Biha already completed byAMDAL study with environmental permit from the Governor at 2012.WILL DELETED
10 Sp Empat - Sp Air Balam Sumatera Barat 6170% 700% AMDAL Sensitive forest areas, socialissues, slope stability, waterquality, waste managemnt, bridgeaccess road & quarry problem
APBN (TLKJ 2011) 100% Completed/YESEnvironmental permitsonJuly 2013. & NOL WBissued on 14 April 2014
LARAP Total PAP 2059 change from original 1,514. Partillyaffected building ( houses an kiosks) = 11,523 M2 :Affected fence = 2,613 m : Partially affected otherbuilding (terrace, decker and floors) = 11,538 M2 andtrees = 4,369
Rp 14.02 Billion. APBDProv Sumbar, DinasPU,
MR-2 (138 PAPs) is under preparation by Satker/CTC.PPK/Satker PJN I West Sumatera and LocalGovernment is under appraisal process for theremaining PAP.
ENVIRONMENTAL; a) The project not yet started, b) CTC need check tofield for preparing the external monitoring report of implementationAMDAL (Pre - Construction phase) and should submit to PMU/PPK/WB.SOCIAL: PPK/Satker PJN I West Sumatera and Local Government arecontinuing the process of payments to the remaining of the PAPs
9 Rantau Tijang - Kota Agung / Replace toBengkunat - Biha (already completed byAMDAL)
Lampung 4200% 700% UKL&UPL Sensitive areas, resident, airpollution, traffic congestion,steep slopes,soft soil and riversand beach abrasion
APBN (TLKJ 2011)
ENVIRONMENTAL :.a) The RKPPL complete, NOL WB issues on 23 Dec2015. b) CTC propose schedule to carried out AMDAL monitoring forBLH (refer to environmental permit) at 11 April 2016 then period 1 willsubmit to WB end of April 2016. . c) RKPPL implemetation period (Octto Dec 2015) was submit to PMU/WB on firs of Feb 2016 & period Janto March 2016 at April 2016. d) The HIV-AIDS campaign complete on 5Dec 2015. c) the quarry, AMP & Stone Crusher permits from Bupati,(the quarry owner not yet make changes the permission (Bupati toGovernor refer Law No.23 year 2014). SOCIAL: PMU waiting data ofthe payment progress (108 PAPs) from PPK/Sater PJN I BKL as to bereported to WB
12 Kambang - Indrapura (1 Doc Amdal) Sumatera Barat 55,2 6 AMDAL Resident, productive land,Catcment areas,rivers, slopestability, squater on the street,land acquisition.
APBN (TLKJ 2011) 100% Completed/YESEnvironmental permitson Feb 2014. & NOL WBissued on 8 Aug 2014
LARAP Total PAP 2.337. Partilly affected building ( houses ankiosks) = 2,057 M2 : Affected fence = 32,741m :Partially affected other building (terrace, decker andfloors) = 17,144 M2 and trees = 3,225
Rp 9.08 Billion. APBDProv Sumbar, DinasPU,
Compensation payment stage is under process ENVIRONMENTAL; a) The project not yet started, b) CTC need check tofield for preparing the external monitoring report of implementationAMDAL (Pre - Construction phase) and should submit to PMU/PPK/WB.SOCIAL: PMU waiting data of the payment progress report fromPPK/Sater PJN II West Sumatera as to be reported to WB
11 Bantal - Mukomuko (1 Paket doc AMDAL) Bengkulu 50,1 6 AMDAL
100%
Completed/YESEnvironmental permitson April 2014. & NOLWB issued on 8 Aug2014
LARAP Total PAP 262 . No affected land. House building =261.7 M2; kiosks = 147.7 m2, terrace = 412.9 m2,Fence = 249 M ; Trees= 36 rod, foundation = 17.2m2, retaining wall = 35.1 m, pavement = 2,937 m2
Sensitive areas, social issues,market on the street, geometric,waste managemnt, continuedtraffic access, etc
APBN (TLKJ 2011) 100%
YES Recommended2011. UKL&UPL no needNOL from the WB.
LARAP Total PAP: 3.412 change from original 2,564 . Affectedland = 88,852 M2. Aset affected : building 111 unit =2.196 M2 ; Fence 127 unit = 1.575 M ; Trees 363 rod ;electricity pole 25 unit
ENVIRONMENTAL : a)The RKPPL complete, WB NOL issues on 14 Dec2015). b) CTC propose schedule to carried out AMDAL monitoring forBLH (refer to environmental permit) at May 2016 then period 3 willsubmit to WB first of June 2016. , c) the RKPPL implemetation period 1(oct to Dec 2015) was submit to PMU on firs of Feb 2016, period Jan -March 2016 will submit to PMU/WB at April 2016 c) The HIV-AIDScampaign, complete on 14 Jan 2016. c) the quarry, AMP & StoneCrusher permits from Bupati, (the quarry owner not yet make changesthe permission (Bupati to Governor refer Law No.23 year 2014).SOCIAL: PPK/Satker PJN II BKL will completed DIPA 2016 as soon forpayment
14 Painan -Kambang (1 doc Amdal) Sumatera Barat 31,5 7 AMDAL Sensitive forest areas, socialissues, slope stability, waterquality, waste managemnt,continued traffic access & quarryproblem
APBN (TLKJ 2011) 100% Completed/YESEnvironmental permitson Feb 2014. & NOL WBissued on 8 Aug 2014
SimpleLARAP
Total PAP 1.092. Partilly affected building ( houses ankiosks) = 10,474 M2 : Affected fence 21,735m :Partially affected other building (terrace, decker andfloors) = 20,988 M2 and trees = 1044
Rp 22.62 Billion. APBDProv Sumbar, Dinas
PU,
Preparation the compensation payment is underprocess
ENVIRONMENTAL; a) The project not yet started, b) CTC need checkto field for preparing the external monitoring report of implementationAMDAL (Pre - Construction phase) and should submit to PMU/PPK/WB.SOCIAL: PMU/CTC will always monitor the land acquisition progress astheir schedule.
13 Sp Rukis - Tj Kemuning Bengkulu 56,3 7 UKL/UPL one link,sensitive/ steepslopes,soft soil and rivers,squater on the street, resident,productive land.
APBN (P2JN 2011)
15 Sibolga - Bts Tap Sel Sumatera Utara 36 7 UKL/UPL resident, commersil areas,geometric etc.
APBN (BBPJN I 2011) 100% Total PAP 1.448 . Land affected 1.531 plot = 45,831M2.Aset affected : building 340 unit = 3.399 M2 ; Fence 12unit = 1.563 M ; Trees 385 rod, Terrace = 991,607 M2
Rp 19.34 Billion.APBN, Satker PJN II,Sumut, 2015
MR-4 (55 PAPs) is under preparation by Satker/CTC.Compensation payments for the remaining 1.111 PAPis under process
Environmental: a) The RKPPL under review by the contractor based onCTC comments, target will submit to PMU/WB enf of April 2016. b) CTCpropose schedule to carried out AMDAL monitoring for BLH (refer toenvironmental permit) at 26 April 2016 then period 3 will submit to WBend of April 2016. c) The HIV-AIDS campaign, complete on 27 Jan 2015 .d) CTC not yet receive of license for quarry,AMP & Stone Crusher.SOCIAL: Payments to the 1.111 PAP (Balance from 1.554 PAPs) areunder process
Sp.Gunung Kemala - Pg. Tampak 36,8 6
ENVIRONMENTAL : a) The project not yet started, b) CTC need checkto field for preparing the external monitoring report of implementationAMDAL (Pre - Construction phase) and should submit to PMU/PPK/WB. SOCIAL: PMU waiting data of payments to the 18 PAP (Balance from259 PAPs) from PPK/Satker PJN I BKL as to be reported to WB
Completed/YESEnvironmental permitson April 2014. & NOLWB issued on 8 Aug2014
sensitive areas/resident, landacquisition, steep slopes,soft soiland rivers and beach abrasion
APBN (TLKJ 2011) LARAP Total PAP 2269 . Land affected 1.926 plot = 194.278M2. Aset affected : building 440 unit = 4.557 M2 ; ;Trees 4.267 rod ;paddy field 48.602 clumps.
Rp 64.0 BillionAPBN, Satker PJN IILampung, 2015
For MR-3, PMU/CTC waiting data of paymentprogress for the remaining of 1.384 PAPs from SatkerPJN II Lampung
SimpleLARAP
APBN, 2015 LARAP is under preparation by Balai III Palembang.This package was changed to Sibolga - Sorkam
ENVIRONMENTAL: Based on CTC survey for environmental screening isconclusion that this packages need completed by UKL&UPL. WILLDELETED
19 Lais- Bintunan Bengkulu 11,6 7 UKL&UPL one link,sensitive/air pollution,traffic congestion, squater on thestreet, etc
APBN (TLKJ 2011) 100% YES Recommended2010. UKL&UPL no needNOL from the WB.
LARAP Total PAP 556. Affected land = 9,504 M2. Asetaffected : floor = 1,381 M2; Terrace: 652 M2; Fence =3,276 M; Tomb = 18 units; Trees 379 rod; utilities 14unit
Rp.3.349.829.000APBN, Satker PJN IIBengkulu
Complete ENVIRONMENTAL: :a) The RKPPL complete (WB NOL issues on 14 Dec2015). b) CTC propose schedule to carried out AMDAL monitoring forBLH (refer to environmental permit) at 11 April 2016 then period 3 willsubmit to WB end of April 2016, c) the RKPPL implemetation period 1(Oct to Dec 2015) was submit to PMU/WB firs of Feb 2016,period Jan -March 2016 will submit to PMU/WB at April 2016. b) The HIV-AIDScampaign, complete on 13 Jan 2016. c) the quarry, AMP & StoneCrusher permits from Bupati, (the quarry owner not yet make changesthe permission (Bupati to Governor refer Law No.23 year 2014)SOCIAL: For MR-3, PMU/CTC waiting data of payment progress for theremaining of 82 PAPs from Satker PJN I Bengkulu
1800% Mukomuko - Bts. Sumbar / Replace toSorkam - Sibolga
Bengkulu 2580% 600% UKL&UPL
sensitive areas/resident, landacquisition, steep slopes,soft soiland rivers
APBN (TLKJ 2011) 100%
YES Recommended2010. UKL&UPL no needNOL from the WB.
LARAPone link,sensitive/steepslopes,soft soil and rivers
APBN (TLKJ 2011) 100%
YES Recommended2011. UKL&UPL no needNOL from the WB.
SimpleLARAP
Total PAP: 940, Affected land: 46,579 m2, PT KAIAffected land: 682 m2, Partilly affected building(houses and kiosks) = 528m2, Affected fence = 294m,Irrigation channal: 2.600m.
Rp 46.86 Billion. APBDProv Sumbar/ APBN2016
Local Government /Satker PJN I Sumatera Barat isunder the inventory of affected assets stage
ENVIRONMENTAL; a) The project not yet started, b) CTC need check tofield for preparing the external monitoring report of implementationAMDAL (Pre - Construction phase) and should submit to PMU/PPK/WB.Social: Now, PMU waiting Larap implementation progress report fromSatker I West Sumatera Province in 2 weekly
21 Lubuk Alung -Kurataji Sumatera Barat 16,8 7 UKL&UPL one link,sensitive/steepslopes,soft soil and rivers
APBN (Balai II 2011) 100% YES Recommended2011. UKL&UPL no needNOL from the WB.
SimpleLARAP
Total PAP: 1,301, Affected land: 40,612 m2, Partillyaffected building (houses and kiosks) = 360.9m2Affected fence = 284m Irrigation channal: 433m
Rp 39.64 Billion. APBDProv Sumbar/ APBN2016
Local Government /Satker PJN I Sumatera Barat isunder the inventory of affected assets stage
ENVIRONMENTAL; a) The project not yet started, b) CTC need checkto field for preparing the external monitoring report of implementationAMDAL (Pre - Construction phase) and should submit to PMU/PPK/WB.SOCIAL: Now, PMU waiting Larap implementation progress report fromSatker I West Sumatera Province in 2 weekly
20 Lubuk Alung - Sicincin Sumatera Barat 14,6 7 UKL&UPL
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
Appendix F
Procurement Plan & Progress
APPENDIX F
Submission Notification
Sub - Project of ofIDR (x10
⁶
) Application Qualification Original Addendum
AWP - 1
1 10-17/01-WINRIP-WP1/CE/A/8043-ID/11-13 Krui - BihaLampung Province.
CapacityExpansion 163.534,85 25-Jan-11 21-Feb-11 02-Nov-11 28-Dec-11 30-Dec-11 28-Feb-12 25-Jan-13 28-Mar-13 17-May-13 27-Jun-12 31-Oct-12 27-May-13 18-Jul-13 10-Sep-13 18-Sep-13 PT. Jaya Konstruksi
Manggala Pratama, Tbk. 25-Nov-13 Civil Work ICB 134.909,21 154.073,02 70,00
2 39-06/02-WINRIP-WP1/CE/A/8043-ID/12-13Padang Sawah - Sp.Empat (incl.Air Gadang Bridge), WestSumatera Province.
CapacityExpansion 228.772,24 25-Jan-11 21-Feb-11 02-Nov-11 28-Dec-11 30-Dec-11 28-Feb-12 25-Jan-13 28-Mar-13 17-May-13 27-Jun-12 31-Oct-12 27-May-13 18-Jul-13 10-Sep-13 18-Sep-13 PT. Jaya Konstruksi
Manggala Pratama, Tbk. 06-Dec-13 Civil Work ICB 197.936,70 226.713,22 70,00
3 40-06/03-WINRIP-WP1/CE/A/8043-ID/12-13 Manggopoh - Padang Sawah, WestSumatera Province
CapacityExpansion 167.678,40 25-Jan-11 21-Feb-11 02-Nov-11 28-Dec-11 30-Dec-11 28-Feb-12 25-Jan-13 28-Mar-13 17-May-13 27-Jun-12 31-Oct-12 27-May-13 18-Jul-13 10-Sep-13 18-Sep-13 PT. Jaya Konstruksi
Manggala Pratama, Tbk. 06-Dec-13 Civil Work ICB 143.688,96 165.157,77 70,00
4 01-26/04-WINRIP-WP1/CE/A/8043-ID/11-13 Ipuh - Bantal, Bengkulu Province CapacityExpansion 247.105,24 25-Jan-11 21-Feb-11 02-Nov-11 28-Dec-11 30-Dec-11 28-Feb-12 25-Jan-13 28-Mar-13 17-May-13 27-Jun-12 31-Oct-12 27-May-13 18-Jul-13 10-Sep-13 18-Sep-13 PT. Waskita Karya - PT.
Daya Mulia Turangga, J.O. 14-Nov-13 Civil Work ICB 186.936,75 196.438,08 70,00
AWP - 2
5 01-03/05-WINRIP-WP2/CE/A/8043/03-15 Simpang Rampa - Poriaha, NorthSumatera Province.
CapacityExpansion 152.870,49 07-Nov-13 22-Jul-14 07-Nov-13 18-Nov-13 23-Dec-13 10-Feb-14 9-Jun-14 15-Jul-14 22-Jul-14 18-Jul-14 22-Jul-14 11-Aug-14 22-Sep-14 18-Nov-14 27-Jan-15 PT. Nusa Konstruksi
Enjiniring, TBK 4-May-15 Civil Work ICB 107,321,260 70,00
6 04-26/06-WINRIP-WP2/CE/A/8043/02-15 Ps. Pedati - Kerkap, BengkuluProvince
CapacityExpansion 92.127,40 21-Nov-13 N/A (Bank
Post Review) 19-Nov-14 24-Nov-14 29 Des 2014 NA PT. Waskita Karya 3-Mar-15 Civil Work NCB 86,517,470 70,00
7 01-06/07-WINRIP-AWP II/CE/A/8043/12-15 Indrapura - Tapan, West SumateraProvince
CapacityExpansion 178.600,23 18-Dec-14 22-Dec-14 12-May-15 26-May-15 28-May-15 13-Aug-15 9-Oct-15 12-Oct-15 PT. Adhi Karya (Persero)
Tbk. 3-Dec-15 Civil Work NCB 129.699,90 70,00
8 06-06/08-WINRIP-WP2/CE/A/8043-ID/01-16 Bts.Kota Pariaman - Manggopoh,West Sumatera Province
CapacityExpansion 379.034,45 18-Dec-14 22-Dec-14 12-May-15 26-May-15 28-May-15 13-Aug-15 9-Oct-15 9-Dec-15
PT. PP (Persero), Tbk. -PT. Statika Mitra Sarana,
J.O.28-Jan-16 Civil Work ICB 355.500,00 70,00
9
Rantau Tijang - Kota Agung,Lampung Province(proposed change to Biha -Bengkunat, Lampung Province)
CapacityExpansion 149.831,00 Civil Work NCB 70,00
10 Simpang Empat - Sp.Air Balam,West Sumatera Province
CapacityExpansion 515.842,21 18-Dec-14 22-Dec-14 12-May-15 26-May-15 28-May-15 13-Aug-15 9-Oct-15 22-Feb-16 Civil Work ICB 70,00
11 02-26/11-WINRIP-AWP2/CE/A/8043.ID/12-14 Bantal - Mukomuko, BengkuluProvince
CapacityExpansion 246.499,55 07-Nov-13 06-Aug-14 07-Nov-13 18-Nov-13 23-Dec-13 10-Feb-14 16-Jun-14 25-Jun-14 11-Jul-14 21-Jul-14 6-Aug-14 22-Aug-14 3-Oct-14 4-Nov-14 13-Nov-14 PT. Hutama Karya (Persero)
- PT. Daya Mulia Turangga 18-Dec-14 Civil Work ICB 228.899,72 262.611,30 70,00
12 02-06/07-WINRIP-AWP II/CE/A/8043/01-16 Kambang - Indrapura, WestSumatera Province
CapacityExpansion 451.810,58 18-Dec-14 22-Dec-14 12-May-15 26-May-15 28-May-15 13-Aug-15 9-Oct-15 26-Nov-15
PT. Lancarjaya MandiriAbadi - PT. Cahaya Tunggal
Abadi, J.O.28-Jan-16 Civil Work ICB 358.950,42 70,00
13 01-26/13-WINRIP-AWP2/CE/A/8043.ID/12-14 Sp Rukis - Tj Kemuning, BengkuluProvince.
CapacityExpansion 316.304,67 07-Nov-13 06-Aug-14 07-Nov-13 18-Nov-13 23-Dec-13 10-Feb-14 16-Jun-14 25-Jun-14 11-Jul-14 21-Jul-14 6-Aug-14 22-Aug-14 3-Oct-14 4-Nov-14 18-Nov-14 PT. Waskita Karya (Persero)
Tbk 18-Dec-14 Civil Work ICB 292,700.00 70,00
AWP - 3
14 Painan - Kambang, West SumateraProvince
CapacityExpansion 267.588,30 22-Oct-15 22-Oct-15 2-Nov-15 5-Jan-16 22-Mar-16 Civil Work NCB 70,00
15 02-03/15-WINRIP-WP2/CE/A/8043/07-15 Sibolga - Batas Tapsel, NorthSumatera Province
CapacityExpansion 376.479,38 30-Dec-13 28-Feb-14 18-Dec-14 23-Dec-14 12-Jan-15 23-Feb-15 29-Apr-15 7-May-15 PT. PP (Persero), Tbk. 13-Jul-15 Civil Work ICB 260.100,00 70,00
16Seblat - Ipuh, (incl. Air Lalang & AirGuntung Bridge), BengkuluProvince
CapacityExpansion 269.559,20 22-Oct-15 22-Oct-15 22-Oct-15 19-Nov-15 11-Jan-16 Civil Work NCB 70,00
17 07-17/17-WINRIP-AWP2/CE/A/8043.ID/11-14 Sp.Gng Kemala - Pugung Tampak,Lampung Province
CapacityExpansion 255.269,25 30-Sep-13 10-Oct-13 30-Sep-13 10-Oct-13 11-Nov-13 30-Dec-13 28-Feb-14 13-Jun-14 25-Jun-14 19-Dec-14 7-Jan-14 4-Jul-14 15-Aug-14 10-Oct-14 14-Oct-14 PT. Jaya Kostruksi
Manggala Pratama, Tbk 17-Nov-14 Civil Work ICB 199.551,23 70,00
18 Mukomuko - Batas Sumbar,Bengkulu Province
CapacityExpansion 69.233,00 Civil Work NCB 70,00
19 05-26/19-WINRIP-WP2/CE/A/8043/02-15 Lais - Bintunan, Bengkulu Province CapacityExpansion 35.886,28 21-Nov-13 N/A (Bank
Post Review) 19-Nov-14 24-Nov-14 19-Dec-14 NA PT. Rodateknindo Purajaya 03 Maret 2015 Civil Work NCB 33.689,45 44.419,76 70,00
20 Lubuk Alung - Sicincin, WestSumatera Province Betterment 131.302,20 22-Oct-15 22-Oct-15 2-Nov-15 5-Jan-16 22-Mar-16 23-Mar-16 Civil Work NCB 70,00
21 Lubuk Alung - Kuraitaji, WestSumatera Province
CapacityExpansion 164.629,30 22-Oct-15 22-Oct-15 2-Nov-15 5-Jan-16 22-Mar-16 23-Mar-16 Civil Work NCB 70,00
WESTERN INDONESIA NATIONAL ROAD IMPROVEMENT PROJECTPROCUREMENT MANAGEMENT FOR CIVIL WORK
PackageNo. Type of Work
Estimated CostEE (Incl. VAT)
Design PQ Document Invitation forPre-
qualification
Evalt.QualificationReport Category
ContractProcurement Method
Contract Price (IDR 106)including Tax
Invitation forBidsDate
Bid Opening DateBid Evaluation Report
As of March 31. 2016
World BankFinancingRatio (%)
ContractorContractSignature
DateContract No.
WB NOLDate
Bidding Document
SubmissionDate NOL Date Submission
DateWB NOL
DateSubmissio
n Date Submission Date WB NOLDate
SubmissionDate WB NOL
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
Appendix G
WINRIP Website & Application Progress
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
APPENDIX GManagement Information System (MIS) Status on March, 2016
NO. TASK DESCRIPTION STATUS WORK PLAN1 File Storage
storage.winrip-ibrd.comThe storage server to stored all ofsoft files of reports and documents.
The new version of application has beencompleted on February 2015.
2 DMS (DocumentManagement System)dms.winrip-ibrd.com
The application to record allinformation of letter and documentfiles.
The DMS applications is already finals developedwith the addition of features such as parent-childmechanism, letter comments, and directnotification. The data that has been inputted inthe DMS database until the end of January 2016are 735 records of letters and 298 records ofdocuments.
3 Websitewww.winrip-ibrd.com
The WINRIP official website. The website has been developed on August 2013.
4 WebGISwebgis.winrip-ibrd.com
The spatial data and roadsinformation that overlay intoGoogle Maps.
The application has been developed on October2013.
5 FMIS (FinancialManagement InformationSystem)fmis.winrip-ibrd.com
The application to monitoring afinancial and physical progressreport.
The programming modules that have beenfinished are as follows: Project Data Financial and Physical Progress Progress Summary History of Financial and Physical Progress User
The programming modules that notyet finished are as follows: Consultant Services Reports
6 CHS (Complaint HandlingSystem)chs.winrip-ibrd.com
The application to accommodatecomplaints from the public.
The application has been developed on January2014.
7 Photo Progressphoto.winrip-ibrd.com
The application to upload thephotographs of civil works progress.
This application is start developed on October2015.
Just finished developed.
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
CHECKLIST OF DOCUMENTS IN THE DMS DATABASELast Updated at The End of March 2016
NO PACKAGE
ACAP ENVIRONMENT FINANCIAL HIGHWAY PROCUREMENT QA RSA SOCIAL TRAINING
PROJECT
PMU CTC
CRO CHU TPM AMDAL HIV/AIDS RKPPL SPPL UKL/
UPL IFR AUDIT DED EE RTA PP BD BER CONTRACT PRAR COW PCM PMER PHO RSTMMR RSA LARAP STUDY
LARAP TIR WIR PMM IR MPR QPR DPCR PCR
1 Krui - Biha #01#02#03#04#05#06#07#08#09#10#11#12
#2013#2014
#2016
Loan Agr.PIPPADMTR
#01#02#03#04#05#06#07#08#09#10#11#12#13#14#15#16#17#18#19#20#21#22#23#24#25#26#27#28#29#30#31#32#33#34#35#36#37
#01#02#03#04#05#06#07#08
2 Pd Sawah - SpEmpat
3 Manggopoh - PdSawah
4 Ipuh - Bantal
5 Sp Rampa -Poriaha
6 Ps Pedati -Kerkap
7 Indrapura -Tapan
8Bts KotaPariaman -Manggopoh
9 Rantau Tijang -Kota Agung
10 Sp Empat - Sp AirBalam
11 Bantal -Mukomuko
12 Kambang -Indrapura
13 Sp Rukis - TjKemuning
14 Painan -Kambang
15 Sibolga - BtsTapsel
16 Seblat - Ipuh
17 Sp Gn Kemala -Pugung Tampak
18 Mukomuko - BtsSumbar
19 Lais - Bintunan
20 Lubuk Alung -Sicincin
21 Lubuk Alung -Kuraitaji
*(Read the list of glossary on the next page).
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
Glossary of the Document Types in the DMS database.
NO DOCUMENT TYPE ABBREVIATION
1 Addendum ADD2 Aide Memoire AM3 Amendment AMD4 Analisis Mengenai Dampak Lingkungan AMDAL5 Audit AUDIT6 Bid Document BD7 Bid Evaluation Report BER8 Commencement of Work COW9 Complaint Report CR
10 Contract CONTRACT11 Detail Engineering Design DED12 Draft Project Completion Report DPCR13 Engineer Estimate EE14 HIV AIDS Report HIV_AIDS15 Inception Report IR16 Interim Financial Report IFR17 Invoice INV18 Land Acquisition Resettlement Action Plan LARAP19 Loan Agreement LA20 Mid Term Review MTR21 Minute of Meeting MOM22 Monthly Progress Report MPR23 Photo PHOTO24 Pre-Construction Meeting PCM25 Procurement Readines Assessment Report PRAR26 Project Appraisal Document PAD27 Project Completion Report PCR28 Project Implementation Plan PIP29 Project Management Manual PMM30 Project Monitoring and Evaluation Report PMER31 Provisional Hand Over PHO32 Quarterly Progress Report QPR33 Rencana Kerja Pengelolaan dan Pemantauan Lingkungan RKPPL34 Report RPT35 Road Safety and Traffic Management Monitoring Report RSTMMR36 Road Safety Audit RSA37 Road Technical Analysis RTA38 Surat Pernyataan Pengelolaan Lingkungan SPPL39 Term of Reference TOR40 Third Party Monitoring TPM41 Training Implementation Report TIR
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
NO DOCUMENT TYPE ABBREVIATION
42 Upaya Kelola/Pemantauan Lingkungan UKL-UPL43 Video VIDEO44 Wakil Pengamat Masyarakat WPM45 Workshop Implementation Report WIR
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
Appendix H
ACAP Training /Dissemination Progress
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
Appendix H ACAP Activity ProgressAppendix H1
Activities Progress of Community Representative Observers (CROs) and the Works PlanJanuary 2013 – March 2016
No Subject of Activities Date of Finish/completed
1. Orientation and studied of WINRIP documents and Development of Works Plan January 2013
2 Prepared of Workshop of Procurement Document Evaluation. February 2013
3. Conducted Workshop of Procurement Document Evaluation for POKJA, Satker/PPK, BalaiBBPJN and PMU.
Febr. 28, 2013 –March 01, 2013
4. Provided of Term of Reference (TOR) of the CRO's Selection and Guidelines for CRO’sSelection
March 1, 2013
5. Provided the Materials (Slide Presentation/Power-point) of General Explanations aboutWINRIP and the CRO’s selection and
March 8, 2013
6. Provided Training Materials for CROs. March 8, 2013
7. Sending an official letter No. Hm.0603/Bp-11/0175/2013, from the Director of Planning asChairman of PMU to Head of BBPJN II & III, about the Selection of CROs/WPM, + TOR andGuidelines Document
March 11, 2013
8 Preparation of Socialization on CROs selection in BBPJN II Padang for package 02 PadangSawah – Simpang Empat and package 03 Manggopoh - Padang Sawah, and Socialization onCROs selection in BBPJN III Palembang for package 01 Krui – Biha and package 04 Ipuh –Bantal.
March 31, 2013
9. Socialization on CROs selection in BBPJN II Padang for package 02 Padang Sawah – SimpangEmpat and package 03 Manggopoh - Padang Sawah
April 9, 2013
10 Socialization on CROs selection in BBPJN III Palembang for package 01 Krui – Biha andpackage 04 Ipuh – Bantal.
April 11, 2013
11. Sent the Invitation letter from Head of BBPJN III to Rector of Universities /Head of Colleges inPalembang, about selection of the CROs for package 01. Krui – Biha (Prov. Lampung) andpackage 04. Ipuh – Bantal (Prov. Bengkulu).
May 17, 2013
12. Sent the Invitation letter from Head of BBPJN II to Rector of Universities /Head of Colleges inPadang, about selection of the CROs for package 02. Padang Sawah – Simpang Empat andpackage 03. Manggopoh - Padang Sawah (Prov. Sumatera Barat).
May 20, 2013
13. Selection of CROs for Packages Krui – Biha Province Lampung and Ipuh – Bantal ProvinceBengkulu, and training for selected CROs in BBPJN III Palembang
May 23, 2013
14. Selection of WPM/CROs for Packages Manggopoh – Padang Sawah and Padang Sawah –Simpang Empat, and training for selected CROs in BBPJN II Padang
May 27, 2013
15. Sending an official letter No. Hm.0603/Bp-11/0175/2013, from the Director of Planning asChairman of PMU to Head of BBPJN II & III, about the Selection of CROs/WPM, + TOR andGuidelines Document
May 28, 2013
16. Guiding the Balai Besar Pelaksanaan Jalan Nasional (Balai) II Padang to compose theApplication Letter for Approval of selected CROs for Package 03. Manggopoh – PadangSawah, package 02. Padang Sawah – Simpang Empat, and Balai III Palembang for Package 01.Krui – Biha Province Lampung and Package 04. Ipuh – Bantal Province Bengkulu.
May 29, 2013
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
No Subject of Activities Date of Finish/completed
17. Compiling summary of the results of Selection the Community Representative Observers(CROs)/ Wakil Pengamat dari Masyarakat (WPM) and the Training activities for selectedCROs for four Packages AWP-1
June 1 - 9, 2013
18. Assist PMU to prepare the Approval letter of selected CROs for four AWP-1 Packages, andprepare of the Decree on Establishment the CROs of AWP-1 WINRIP from Director ofPlanning DGH, as the Chairman of PMU.
June 1 - 9, 2013
19. Monitor and observation the Pre-Bid Meeting and Site Visit activities of Procurement Processthat held by the Procurement Committee, in BBPJN II and III, on 10 June 2013 by CROs inimplementing their tasks on the
June 10 - 16,2013
20. Evaluate of the CROs observation on Pre-Bid Meeting and Site Visit activities Jun.17 - 23, 2013
21. Examine the report of CROs on the monitoring and observation of Pre-Bid Meeting and SiteVisit at the packages of Annual Works Program - 1 (AWP-1) WINRIP.
Modify the template of monitoring the report of the CROs, to be more focused and moresystematically
June 24 - 30,2013
22. Monitor /Observe of Bids Submission and Bids Opening for four packages AWP-1 byCommunity Representative Observers (CROs) for Package 01, 02, 03, and 04
July 18, 2013
23. Monitoring and examined of the CRO’s Report on the monitoring and observation of BidSubmission and Bid Opening activities for four packages of Annual Works Program - 1 (AWP-1) WINRIP, which have been carried out on July 18, 2013
August, 2013
24 Preparation on the Socialization of CROs selection to the Procurement Committee (POKJA) ofSumatera Utara province, for package Simpang Rampa – Poriaha and package Sibolga – BatasTapanuli Selatan
October 2013
25 Monitored /Observed of Procurement progress on Commencement of Bid Winners for fourpackages AWP-1 (Package 01, 02, 03, and 04) and informed to related CommunityRepresentative Observers (CROs).
November 2013
26 Carried out the dissemination of CROs selection to the Procurement Committee (POKJA) ofSumatera Utara province, for package Simpang Rampa – Poriaha. in Balai (BBPJN) I Medanand in Project Management (Satker) Office.
November 19 –20, 2013
27 Carried out the CROs selection for package 17: Simpang Gunung Kemala – Pugung Tampak inLampung..
July 17, 2014
28 Carried out the CROs selection for package 05: Simpang Rampa – Poriaha in North Sumateraprovince.
August 20, 2014
29 Carried out the CROs selection for package 11: Bantal – Mukomuko, and package 13:Simpang Rukis – Tanjung Kemuning in Bengkulu province.
Sept. 1, 2014
30 Ms. Hesti Aulia Sari, ST, CRO for Package 11: Bantal - Mukomuko, meet the invitation of theProcurement Committee (Pokja of Procurement Unit/Unit Layanan Pengadaan BBPJN III,PIU/Satker PJN Region I Bengkulu Province).
Oct. 03, 2014
31 Ms. Hot Maria Angelina, ST, CRO for Package 13: Simpang Rukis - Tanjung Kemuning wasattended Bid-Opening meeting meet the invitation by the Procurement Committee (Pokja ofProcurement Unit/Unit Layanan Pengadaan BBPJN III, PIU/Satker PJN Region II BengkuluProvince).
Oct. 03, 2014
32 Carried out the CROs selection for package 06: pasar Pedati –Kerkap and package 19: Lais -Bintunan in Bengkulu province.
Nov. 27, 2014
33 The elected CROs (Ms. Hot Maria Angelina, ST and Ms. Hesti Aulia Sari, ST) attanded Pre-BidMeeting and site visit for package 06 (Pasar Pedati – Kerkap) and package 19 (Lais –Bintunan), Bengkulu Province
Dec. 05, 2014
34 The Community Development team CTC WINRIP has carried out the selection of CROs forPackage 15: Sibolga – Batas Tapanuli Selatan. The Elected CRO is Ernie Shinta Y. Sitanggang,ST, MT, and Ir. M. Koster Silaen, MT as the substitute CRO (both from Politeknik NegeriMedan / State Polytechnic of Medan)
Dec. 16, 2014,
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
No Subject of Activities Date of Finish/completed
35 The elected CROs for package 06 (Pasar Pedati – Kerkap) and package 19 (Lais – Bintunan)Bengkulu Province was attanded the Bid-Opening Meeting.
Dec. 29, 2014
36 Ir. M. Koster Silaen, MT as the substitute CRO of Package 15: Sibolga – Batas Tapanuli Selatanwas attended the Pre-Bid Meeting.
Jan. 26, 2015
37 Ir. M. Koster Silaen, MT as the substitute CRO of Package 15: Sibolga – Batas Tapanuli Selatanwas attended the Bid Opening Meeting
Feb. 23, 2015
38 The Community Development team CTC WINRIP has carried out the selection of CROs forfour packages WINRIP in West Sumatera province, as follow; The appointed CRO for Package 07: Indrapura – Tapan, is Ir. Riswandi, M.Si, and
Apwiddhal, ST, MT as the substitute CRO, both from State Polytechnic of Padang(Politeknik Negeri Padang).
The appointed CRO for Package 08: Batas Pariaman – Manggopoh, is M. Nursyaifi Yulius,MT (Mgt), and Ir. Alzahri, MT as the substitute CRO, both from Bung Hatta University ofPadang (Universitas Bung Hatta Padang).
The appointed CRO for Package 10: Simpang Empat – Simpang Air Balam, is Ir. Drs. Heldi,M.Si, and Ir. Afrizal Naumar, MT as the substitute CRO, both from Bung Hatta University ofPadang (Universitas Bung Hatta Padang).
The appointed CRO for Package 12: Kambang – Indrapura, is Syaiful Amri, SST, MT, and B.Army, ST, MT as the substitute CRO, both from State Polytechnic of Padang (PoliteknikNegeri Padang)
June 12, 2015
39 The appointed CRO Ir. Riswandi, M.Si for Package 07: Indrapura – Tapan, and the appointedCRO Syaiful Amri, SST, MT for Package 12: Kambang – Indrapura were attended the Pre-BidMeeting and Site Visit as invited by the Procurement Committee (Pokja) of PIU/Satker PJNRegion II of West Sumatera ProvinceThe appointed CRO M. Nursyaifi Yulius, MT (Mgt) for Package for Package 08: Batas Pariaman– Manggopoh, , and the appointed CRO Ir. Drs. Heldi, M.Si for Package 10: Simpang Empat –Simpang Air Balam were attended the Pre-Bid Meeting and Site Visit as invited by theProcurement Committee (Pokja) of PIU/Satker PJN Region I of West Sumatera Province.
June. 15-16, 2015
40 The appointed CRO Ir. Riswandi, M.Si for Package 07: Indrapura – Tapan, and the appointedCRO Syaiful Amri, SST, MT for Package 12: Kambang – Indrapura were sent the ObservationReport on Pre-Bid Meeting and Site Visit.
July. 02, 2015
41 The appointed CRO M. Nursyaifi Yulius, MT (Mgt) for Package for Package 08: Batas Pariaman– Manggopoh, , and the appointed CRO Ir. Drs. Heldi, M.Si for Package 10: Simpang Empat –Simpang Air Balam were sent the Observation Report on Pre-Bid Meeting and Site Visit.
July. 10, 2015
42 The CRO for Package 07: Indrapura – Tapan (Ir. Riswandi, M.Si), and the CRO for Package 12:Kambang – Indrapura (Syaiful Amri, SST, MT) were attended the Bid Opening Meeting.
August 13, 2015
43 The CRO for Package for Package 08: Batas Pariaman – Manggopoh (M. Nursyaifi Yulius, MT(Mgt), and the CRO for Package 10: Simpang Empat – Simpang Air Balam (Ir. Drs. Heldi, M.Si)were attended the Bid Opening Meeting.
August 13, 2015
44 Selection of CROs for packages 16 (Sebelat – Ipuh) in Bengkulu province, as follow; The appointed CRO for Package 16 is Mr. Besperi, ST, MT, and and Ms. Anggi Nidya Sari,
ST., MT as the substitute CRO. Both of them were from Bengkulu University.
Nov,.4-5, 2015
45 Selection of CROs for packages 14, 20, and 21 in West Sumatera province, as follow; The Elected CRO for Package 14 (Painan - Kambang) were Mr. M. Nursyaifi Yulius, MT
(Mgt), and Mr. Ir. Alzahri, MT, as the substitute CRO, both of them were from Bung HattaUniversity.
The Elected CRO for Package 20 (Lubuk Alung - Sicincin), were Mr. Ir. Riswandi, M.Si andMr. Syaiful Amri, SST., MT, as the substitute CRO, both of them were from StatePolitechnic of Padang (Politeknik Negeri Padang).
The Elected CRO for Package 21 (Lubuk Alung - Kuraitaji) were Mr. Jafril Tanjung, DR. Engand Mr. Ophiyandri, Ph.D as the substitute CRO, both of them were from AndalasUniversity
Nov,.16-17, 2015
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
No Subject of Activities Date of Finish/completed
46 The substitute CRO for Package 16: Sebelat – Ipuh, Ms. Anggi Nidya Sari, ST., MT wasattended the Pre-Bid Meeting and Site Visit as invited by the Procurement Committee (Pokja)of PIU/Satker PJN Region I of Bengkulu Province.
Nov. 05, 2015
47 The substitute CRO for Package 14: Painan - Kambang, Mr. Ir. Alzahri, MT was attended thePre-Bid Meeting and Site Visit as invited by the Procurement Committee (Pokja) ofPIU/Satker PJN Region II of West Province.
Nov. 18, 2015
48 The Elected CRO for Package 20 (Lubuk Alung - Sicincin), Mr. Ir. Riswandi, M.Si, was attendedthe Pre-Bid Meeting and Site Visit as invited by the Procurement Committee (Pokja) ofPIU/Satker PJN Region I of West Sumatera Province.
Nov. 18, 2015
49 The Elected CRO for Package 21 (Lubuk Alung - Kuraitaji), Mr. Jafril Tanjung, DR. Eng, wasattended the Pre-Bid Meeting and Site Visit as invited by the Procurement Committee (Pokja)of PIU/Satker PJN Region I of West Sumatera Province.
Nov. 18, 2015
50 The substitute CRO for Package 16: Sebelat – Ipuh, Ms. Anggi Nidya Sari, ST., MT wasattended the Bid Opening Meeting, invited by the Procurement Committee (Pokja) ofPIU/Satker PJN Region I of Bengkulu Province.
Nov. 19, 2015
51 The CRO for Package 14: Painan - Kambang, Mr. Ir. Alzahri, MT was attended the Bid OpeningMeeting as invited by the Procurement Committee (Pokja) of PIU/Satker PJN Region II ofWest Province.
Jan. 05, 2016
52 The Elected CRO for Package 20 (Lubuk Alung - Sicincin), Mr. Ir. Riswandi, M.Si, was attendedthe Bid Opening Meeting as invited by the Procurement Committee (Pokja) of PIU/Satker PJNRegion I of West Sumatera Province.
Jan. 05, 2016
53 The Elected CRO for Package 21 (Lubuk Alung - Kuraitaji), Mr. Jafril Tanjung, DR. Eng, wasattended the Bid Opening Meeting as invited by the Procurement Committee (Pokja) ofPIU/Satker PJN Region I of West Sumatera Province.
Jan. 05, 2016
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
Appendix H.2The Progress of Third Party Monitoring (TPM) Activities and Works Plan for Next Steps
January 2013 – March 2016
No Subject of Activities Target Completed
1. Preparation the initial draft of ToR of selection the TPM Dec, 2013 Dec, 2013
2. Providing the TPM selection guidelines. Dec, 2013 Dec, 2013
3. Providing the Training Materials for the TPM Dec, 2013 Dec, 2013
4. Preparing the official letter from the Director of Planning as Chairman ofPMU to Head of BBPJN II & III, about the Selection of TPM. Jan, 2014 Jan. 24, 2014
5. Preparing the official letter from the Director of Planning as Chairman ofPMU to Universities, about the Selection of TPM. Jan., 2014 Jan 29, 2014
Preparing the official letter from the Official in Charge/Ketua PelaksanaHarian PMU to Satker/PPK, about the Selection of TPM Jan, 2014 Jan 13, 2014
5.Preparing the official letter from the Official in Charge/Ketua PelaksanaHarian PMU to Universities and Satker/PPK, about the Socialization ofTPM Selection for Package 01, 02, & 03
Feb. 2014 Feb. 07, 2014Feb. 13, 2014
6. Socialization of the TPM selection for package 01: Krui - Biha. Feb. 2014 Febr. 14, 2014
7. Socialization of the TPM selection for package 02: Padang Sawah –Simpang Empat and package 03: Manggopoh – Simpang Empat Feb. 2014 Febr. 18, 2014
8.Preparing the official letter from the Director of Planning as Chairman ofPMU to University of Bengkulu, about the Selection of TPM for package04: Ipuh - Bantal.
Jan, 2014 Febr. 19, 2014
9. Help the PMU on formulating the TPM Evaluation Team March 2014 Febr. 25, 2014
10. Implementation of selection of the TPM for four AWP-1 packages by TPMEvaluation Team March 2014 March 10, 2014
11. Delivery of the Preparatory Training for elected TPM for package 01: Krui– Biha in Lampung June 2014 June 5 - 6, 2014
12.Delivery of the Preparatory Training for elected TPM for package 02:Padang Sawah – Simpang Empat, and package 03: Mangopoh – PadangSawah in West Sumatera
June 2014 June 17-18, 2014
13. Delivery of the Preparatory Training for elected TPM for package 04: Ipuh– Bantal in Bengkulu July 2014 July 7 – 8, 2014
14 Approval process of elected TPM July 2014 July 7 – 8, 2014
15 Assist PMU to prepare the Decree on Establishment the TPM of AWP-1WINRIP from Director of Planning DGH, as the Chairman of PMU.
August 2014 Sept. 1, 2014
16
Sending the Coordination Letter from Director of Planning, DirectorateGeneral of Highways to the Head of BBPJN Region I Medan, aboutSelection of the Third Party Monitoring (TPM) for package 05 (SimpangRampa – Poriaha, and package 15 (Sibolga – Tapanuli Selatan border) inNorth Sumatera.
October 2014 Oct, 07, 2014
17
Sent the Information Letter about participation of Third Party Monitoring(TPM) on WINRIP, from Director of Planning, Directorate General ofHighways to the University of Lampung (UNILA) for package 17 (SimpangGunung Kemala – Pugung Tampak) in Lampung Province.
October 2014 Oct, 03, 2014
18
Sent the Information Letter about participation of Third Party Monitoring(TPM) on WINRIP, from Director of Planning, Directorate General ofHighways to the University of Sumatera Utara (USU) for package 05(Simpang Rampa – Poriaha) in North Sumatera Province
October 2014 Oct, 03, 2014
19Sent the Information Letter about participation of Third Party Monitoring(TPM) on WINRIP, from Director of Planning, Directorate General ofHighways to the University of Bengkulu (UNIB) for package 11 (Bantal –
October 2014 Oct, 20, 2014
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
No Subject of Activities Target Completed
Mukomuko) and package 13 (Simpang Rukis - Tanjung Kemuning) inBengkulu Province.
20Selection of the Third Party Monitoring (TPM) for packages 17 (SimpangGunung Kemala – Pugung Tampak) Lampung Province November 2014 Dec. 4, 2014
21 Selection of the Third Party Monitoring (TPM) for packages 11, and 13,Bengkulu Province
December 2014 Dec. 22, 2014
22 Socialization and Explaination of the Third Party Monitoring (TPM) forpackages 05, and 15 in Universitas Graha Nusantara Padang-sidempuan
January 2015 Jan, 28, 2015
23 Socialization and Explaination of the Third Party Monitoring (TPM) forpackages 05, and 15 in Universitas Sumatera Utara Medan
January 2015 Jan, 30, 2015
24The Employment Agreement or Memorandum of Understanding betweenTPM (packages 01, 02, 03, and 04) with the CTC WINRIP (PT. PlannersDjaja) has been signed.
November 2014 Feb. 26, 2015
25Delivery of the Preparatory Training for elected TPM for package 11:Bantal – Mukomuko and package 13: Simp. Rukis – Tj. Kemuning, inBengkulu
January 2015 March 11-12,2015
26 Selection of the Third Party Monitoring (TPM) for packages 05, and 15,Northern Sumatera Province March 2015 April 9, 2015
27 Selection of the Third Party Monitoring (TPM) for packages 06, and 19, inBengkulu Province May 2015 May 5, 2015
28Delivery of the Preparatory Training for elected TPM for package 06:Pasar Pedati – Kerkap and package 19: Lais – Bintunan, in BengkuluProvince
June 2015 June 4-5, 2015
29 The TPM of package 01 (Krui - Biha) has been doing site observations (fieldvisit) for the first phase July 2015
30 TPM package 02 (Padang Sawah - Simpang Empat) and package 03(Mangopoh - Padang Sawah), had conducted a field visit for first phase July 2015
31 The TPM of package 01 (Krui - Biha) has been done site observations (fieldvisit) for the second phase
3rd week ofAugust 2015
32 The TPM of package 04 (Ipuh - Bantal) has been done site observations(field visit) for the first phase
4th of August2015
33 The Community Development Team of CTC WINRIP has monitored theTPM’s Activity on TPM Package 01 Krui - Biha
Agt. 19 -21,2015
34 The Community Development Team of CTC WINRIP has monitored theTPM’s Activity on TPM Package 04 Ipuh - Bantal
Agt. 27 -28,2015
35The Community Development Team of CTC WINRIP has monitored theTPM’s Activity on TPM Package 02 (Padang Sawah – Simpang Empat)package 03 (Manggopoh Padang Sawah)
Sept. 10 - 11,2015
36The TPM of Package 02 (Padang Sawah – Simpang Empat) an package 03(Manggopoh Padang Sawah) had been done site observations (field visit)for the first phase
Sept, 2015
37Delivery of the Preparatory Training for appointed TPM for package 05:Sp. Rampa – Poriaha and package 15: Sibolga – Batas Tapsel in NorthSumatera Province
October 9, 2015
38Delivery of the Preparatory Training for appointed TPM for package 17:Sp. Gunung Kemala – Pugung Tampak in Lampung Province Oct. 22, 2015
39 TPM package 04 Ipuh – Bantal has submitted their Field Visit MonitoringReport to PMU WINRIP Oct. 27, 2015
40 TPM package 03 Maggopoh – Padang Sawah has submitted their FieldVisit Monitoring Report to PMU WINRIP Nov. 11, 2015
41 TPM package 01 Krui – Biha has submitted their Field Visit MonitoringReport to PMU WINRIP Nov. 26, 2015
42 The Community Development Team of CTC WINRIP has monitored the Dec. 03-04, 2015
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
No Subject of Activities Target Completed
TPM’s Activity on TPM Package 11 (Bantal – Mukomuko) package 13(Simpang Rukis – Tanjung Kemuning) in Bengkulu Province
43 Selection of the Third Party Monitoring (TPM) for packages 07 and 12 inWest Sumatera Province Dec. 22, 2015
44 Selection of the Third Party Monitoring (TPM) for package 16 in BengkuluProvince Dec. 29, 2015
45 Selection of the Third Party Monitoring (TPM) for packages 08 and 10 inWest Sumatera Province Jan. 14, 2016
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
Appendix H.3
Works Activities on Complaints Handling Mechanism System (CHS)March 2013 – March 2016
No Subject of Activities / Item of Tasks Completion Plan/Progress Condition
1 Review of Minister Decree of Public Works No. 323/2005 concerning the procedures ofHandling input from communities on the environment of the Ministry of Public Works April 18, 2013
2 Preparation of Complaints Register and the complaints address (developing of web site ofWINRIP) and provided ACAP to inputting data in the web site.
Completed on themiddle of Feb. 2014.
3 Preparation of Complaint Handling Procedure (already available on the websiteapplication http://www.winrip-ibrd.com) April 2014
4The completion of the Initial investigation of a complaint Procedure, and the procedurefor the investigation of Complaints, as well as the conclusion of investigation (alreadyavailable on the website application http://www.winrip-ibrd.com)
April 2014
5 Monitored and noted the public complaints via SiPP website and WINRIP website, butuntil December 2014 have no complaint about the WINRIP programs December 2014
6
Clarification of Community complaint for package 02 & 03 by Jejak Media Group (JMG) byMr. Buyung on gravel aggregate materials, routine maintenance, and watering work site(dust pollution). It has been followed up by PPK 09 and PPK 10 to hold a clarificationmeeting, followed by the elements PPK, Supervision Consultant (DSC), and Jejak MediaGroup (JMG).
March 23, 2015
7
Clarification of information of work implementation on package 04: Ipuh - Bantal wasunfavorable, by TPM member (Mr. Hardiansyah, ST, MT). The information obtained fromthe local mass media. The problem is that the people around the location of the packageIpuh - Bantal especially road users complained about the excavation of road widening isleft open for an extended period of time without equipped with signs and safety fence,felt very dangerous, especially when driving at night, and according to the informationsome of the riders had been an accident which the vehicle plunged into the hole dug.This information has been followed up by PPK 01 Bengkulu together with the SupervisionConsultant (DSC Field Team) to instruct the Contractor to install traffic signs and safetyfences in places that endanger of road user
March 26, 2015
8
On May 11, 2015, Mr. Dr. M. Fauzi, ST, MT,, the main observer of the Third PartyMonitoring for Package 11 (Bantal - Mukomuko) Bengkulu Province, conveyinginformation from local newspaper clippings (Koran Rakyat Bengkulu) containing news thata 1.5-year-old toddler fell and nearly drowned in the excavation of the road wideningPackage 11 (Bantal - Mukomuko) which flooded about 80 cm deep. That is because theexcavation is situated in the location residential and not immediately undertaken, andwere not given the signs and safety fence.The complaint was submitted to the PMU and forwarded to the related PIU / PPK to beclarified.Until the end of May there has been no follow-up report to the complaint from the PIU /PPK 01 linked.
May 11, 2015
9
The CHS team has been received the copy of complaints letter from Tender Participantson package 08 to the Procurement Committee. Disclaimer of submitted by the tenderparticipants of package 08 (Batas Kot Pariaman – Manggopoh) PT. Adhi Karya (Persero)Tbk – PT. Yasa Patria Perkasa, JO by letter No: ADHI-YASA/12/I/2016 dated January 12,2016, to the Procurement Committee concerning to the results of Bid Evaluation Report(BER) section III, clause 4, point 4.2 (b): Specific Construction Experience in Key Activitiesspecifically on the experience of aggregate base production.
Jan. 15, 2016
10
CHS team has been received the other similar complaint to the Procurement Committeewas submitted by the same tender participant of package 12: Painan – Kambang (PT. AdhiKarya (Persero) Tbk – PT. Yasa Patria Perkasa, JO) by letter No: ADHI-YASA/11/I/2016dated January 4, 2016. The content of complaint was the similar subject i.e. the results ofBid Evaluation Report (BER) section III, clause 4, point 4.2 (b): Specific Construction
Jan. 15, 2016
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
Experience in Key Activities specifically on the experience of aggregate base production
11
CHS team has been received the complaints from Riki Susanato (Konsorsium Nasional LSMProvinsi Bengkulu) dated February 02, 2016. Riki Susanato and Edy Novriansyah had sent aletter No: 06/Khusus/XII/2015 dated December 11, 2015 on a request for publicinformation related to the documents of WINRIP project in Bengkulu province. But thisrequest was unable to fulfill by Satker PJN Wil. I of Bengkulu Province, especially inrelation to Contract Document / Letter of Agreement between the ProjectImplementation Unit of WINRIP for Bengkulu Province with the Contractors.By not granting of the request of the documents, then Riki Susanto delivered thecomplaint through the Complaint Handling System (CHS) of WINRIP website (www.winrip-ibrd.com). The complaint was submitted to the PMU WINRIP and the relevantstakeholders to immediately follow-up.
Feb. 02, 2016
12
On January 20, 2016, there was a World Bank letter No. 281 on reviewing Bid EvaluationReport (BER) for Package 16: Seblat – Ipuh in Bengkulu Province. World Bank has and havecomments on the Bina Marga proposed rejection of the five lower priced bidders.As a follow up of these comments, on February 10, 2016 has been held DiscussionMeeting to respond to the letter. Meeting followed by elements from the WB, PMU, PokjaPJN Reg. 1 of Bengkulu Province. Clarification should be explained in the revision of BERand sent to World Bank.
January 20, 2016February 10, 2016
13 The establishment of the settlement Commission Handling the Complaint under theInspectorate General of the Ministry of Public Works (Executing Agency) if it necessary
Will establish if there is acase that needs specialhandling
14Preparation of the device for Executing Agency such as: Procedures announcement ofpenalties, procedures for the annual Survey, Procedure Annual Independent Review, theprocess of Auctions
Done by ProcurementSpecialist and theContract ExaminerCommittee
15 The development of a code of conduct and actions for Implementing Institutions/Implementing Agency (Bidders, Suppliers, contractors and Consultants)
Done by PMU of DGH
16 Support the PMU in the Management and Monitoring of the implementation policy inhandling public complaints
Have been carried outthroughout projectimplementation period
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
Appendix H.4Works Activities on Publication / Disclosure Activities
January 2013 – March 2016
No Subject of Activities / Item of Tasks Completion Plan/Progress Condition
1 Conducted Workshop of Procurement Document Evaluation for POKJA,Satker/PPK, Balai BBPJN and PMU
February 28, 2013– March 01, 2013
2 Conducted Workshop of World Bank Guidelines of Procurement for WINRIP tothe POKJA, Satker/PPK, Balai BBPJN and PMU
April 24 – 25, 2013
3 Review training materials on Project Management Manual (PMM), especiallyCHAPTER XI of the anti-Corruption Action Plan (ACAP)
First updating April 29, 2013
4 The second Review of training materials on Project Management Manual(PMM), Chapter I - XII
Second updating onDecember 18, 2013
5 The third Review of training materials on Project Management Manual (PMM),Chapter I - XII
third updating onApril, 2014
6. Preparing Method Transparency to the Public, and Improvement the proceduresto the Public Disclosure through information media (website).
Establishment of InformationSystem (MIS) was finish on
March 2014
7. The updating of Project Management Manual (PMM), Chapter 3, 9, 11, and 13,has been held in Bogor June 2014
8 Delivery of the Preparatory Training for elected TPM for AWP-a packages: 01,02, and 03 June 2014
9 Delivery of the Preparatory Training for elected TPM for AWP-a packages: 04 July 2014
10 The implementation of Dissemination/training of the PMM to Stakeholders forPackages 01, 02, 03, and 04
September 10 - 11 2014
11Inputting / upload / update of data/documents/reports of the CommunityRepresentative Observers (CROs) activities for packages 01, 02, 03, 04, 17, 11,13, 05, 06, 19, and 15 into the WINRIP’s website.
From Augt 2013 – April, 2015
12Inputting / upload / update of data/documents/reports of the Third PartyMonitoring (TPM) activities for packages 01, 02, 03, 04, 17, 11, and 13 into theWINRIP’s website.
From Augt 2013 – April, 2015
13Inputting / upload / update of data/documents/reports of Procurement ofContractors for packages 01, 02, 03, 04, 17, 11, 13, 05, 06, and 19 into theWINRIP’s website.
From Augt 2013 – April, 2015
14Inputting / upload / update of data/documents/reports of Environmentalactivities for packages 01, 02, 03, 04, 17, 11, 13, 05, 06, and 19 into the WINRIP’swebsite.
From Augt 2013 – April, 2015
15Inputting / upload / update of data/documents/reports of Social Safeguard /LARAP for packages 01, 02, 03, 04, 17, 11, 13, 05, 06, and 19 into the WINRIP’swebsite.
From Augt 2013 – April, 2015
16Inputting / upload / update of Progress Report/ Actual Status (fisichal worksand financial) of each package that has been contracted (packages 01, 02, 03,and 04) into the WINRIP’s website.
From Augt 2013 – April, 2015
17 Inputting / upload of Monthly Progress Report (MPR December 2012 – December2014) into the WINRIP’s website.
Every Month
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
No Subject of Activities / Item of Tasks Completion Plan/Progress Condition
18 Inputting / upload of Quarterly Progress Report (QPR December 2012 –December 2014) into the WINRIP’s website.
Every Three Months
19 Delivery the IFM Training for Stakeholders (Official and staff of Satker, Officialand staff of PPK) packages 01, 02, 03, and 04.
26 – 27 November 2014
20 Publish the Quarterly Newsletter on official website of MPW and WINRIP’swebsite
Every three months forQuarterly Newsletter October –
December 2015
21 Delivery the IFM Training for Stakeholders (Official and staff of Satker, Officialand staff of PPK) packages 05, 11, 13, and 17.
Feb. 11 - 12, 2015
22 Report of Technical and Financial Audit Consultants (TFAC) for Packages 02 and03 has been received from TFAC Team
Feb. 27, 2015
23
Delivery of the Preparatory Training for elected TPM for package 11: Bantal –Mukomuko and package 13: Simp. Rukis – Tj. Kemuning, in Bengkulu. Thistraining followed the elements of TPM, Satker/PPK, Contractors, SupervisionConsultants, and Balai BBPJN III Palembang.This training is intended to provide an explanation of the scope of duties of TPMand provide information to all elements involved in the implementation of theproject that the community be involved in monitoring the implementation ofthe project which is represented by the TPM, in accordance with the LoanAgreement.
March 11 – 12, 2015
24 Publish the Quarterly Newsletter on official website of MPW and WINRIP’swebsite
Every three months forQuarterly Newsletter January –
March 2015
25Delivery of PMM Socialization to Stakeholders (Balai BBPJN III, PIU/PPK,contractors and Supervision Consultants ‘DSC’) for four Packages (06, 11, 13,and 19) in Bengkulu Province
May 6 – 7, 2015
26
Delivery of the Preparatory Training for elected TPM and Work Plan for manageand monitor the Environment / Rencana Kerja Pengelolaan dan PemantauanLingkungan (RKPPL) for package 06: Ps. Pedati – Kerkap and package 19: Lais –Bintunan, in Bengkulu. This training followed the elements of TPM, Satker/PPK,Contractors, Supervision Consultants, and Balai BBPJN III Palembang.
June 4 – 5, 2015
27 Publish the Quarterly Newsletter on official website of MPW and WINRIP’swebsite
Every three months forQuarterly Newsletter April –
June 2015
28 The Mid-Term Report of the first semester 2015 has been written by the early ofJuly 2015
July, 2015
29 Delivery of PMM Training for Stakeholders (PPK, contractors and SupervisionConsultants ‘DSC’) for Packages 17, 05, and 15
November 23 – 24, 2015
30Inputting / upload / update of data/documents/reports of the CommunityRepresentative Observers (CROs) activities for packages 07, 08, 10, 12, 14, 16,20 and 21 into the WINRIP’s website.
From May – Dec, 2015
31Inputting / upload / update of data/documents/reports of the Third PartyMonitoring (TPM) activities for packages 05, 06, 07, 12, 15, 19 and 16 into theWINRIP’s website.
December, 2015
32Inputting / upload / update of data/documents/reports of Procurement ofContractors for packages 07, 08, 10, 12, 14, 16, 20 and 21 into the WINRIP’swebsite.
From June – Dec, 2015
33 Inputting / upload / update of data/documents/reports of Environmentalactivities for 07, 08, 10, 12, 14, 16, 20 and 21 into the WINRIP’s website.
From May – Dec, 2015
34Inputting / upload / update of data/documents/reports of Social Safeguard /LARAP for packages for 07, 08, 10, 12, 14, 16, 20 and 21 into the WINRIP’swebsite.
From May – Dec, 2015
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
No Subject of Activities / Item of Tasks Completion Plan/Progress Condition
35Inputting / upload / update of Progress Report/ Actual Status (physically works,financial and audits) of each package that has been contracted (packages 05, 06,07, 11, 13, 15, 17 and 19) into the WINRIP’s website.
From May – Dec, 2015
36Inputting / upload / update of data/documents/reports of the CommunityRepresentative Observers (CROs) activities for packages 14, 20 and 21 into theWINRIP’s website.
January, 2016
37Inputting / upload / update of data/documents/reports of the Third PartyMonitoring (TPM) activities for packages 14, 20, and 21 into the WINRIP’swebsite.
December, 2015
38 Updated the Project Management Manual (PMM) Chapter III : Planning andProgramming
January, 2016
39Review and Updated of the Project Management Manual (PMM) Chapter IX :Performance Monitoring and Evaluation, Chapter XI: Anti-Corruption Action Plan(ACAP)
March, 2016
Activities Plan for Next Step
1 Delivering the other training programs of WINRIP shall inline of projectimplementation progress.
Depend on projectimplementation progress
2 Public Expose on ACAP to the civil society forum in each project location (eachpackage)
Before the construction worksstarted
3 Monitoring of the implementation of disclosure and transparency of informationto each package during contraction period.
Plan for three time monitoringto field for each package during
contraction period
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
Appendix I
Performance Indicator
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
Appendix I: WINRIP Performance Indicators
Project Development Objective Indicators
Indicator Name CoreUnit ofMeasure
Baseline(2010)
FY1(2013)target
FY1 (2013)actual
FY2(2014)target
FY2(2014)actual
FY3(2015)target
FY3(2015)actual
FY4(2016)target
FY4(2016)actual
FY5 (2017)end target
FY5 (2017)end actual
Increase of AADT onproject roadsections (all vehicletypes)
Number Value 8,241 10,880 11,936 4,140 13,094 12,696 13,990 14,947
Date 31-Dec-2010 31-Dec-14
March2015
31-Dec-2017
Comments 2010 baseline isthe simpleaverage of theAADT of the 19WINRIP sections(page 41 of PAD).
Resultsfrom IRMS
Resultsfrom statictrafficcounts on6 links in 4provinces
2017 target calculated using the growth forecastsfor four vehicle types on page 39 of the PAD,weighing them by the typical traffic compositionfrom the 2010 Master Plan for Arterial RoadNetwork in Sumatra Island (motorcycles 54.9%,cars 24.6%, buses 2.7% and trucks 17.8%)
Indicator Name CoreUnit ofMeasure
Baseline(2010)
FY1(2013)target
FY1 (2013)actual
FY2(2014)target
FY2(2014)actual
FY3(2015)target
FY3(2015)actual
FY4(2016)target
FY4(2016)actual
FY5 (2017)end target
FY5 (2017)end actual
Average vehicleoperating cost for atypical car reducedby at least 5% onproject roads (baseyear operating cost:US$0.19/veh-km)
Percentage Value 0.00 n.a. 3.00 n.a. 5.00
Date 31-Dec-2010 31-Dec-14
10-Nov-15
31-Dec-2017
Comments Target notassessedbecause noworkscompleted
Target notassessedbecauseno workscompleted
Indicator Name CoreUnit ofMeasure
Baseline(2010)
FY1(2013)target
FY1 (2013)actual
FY2(2014)target
FY2(2014)actual
FY3(2015)target
FY3(2015)actual
FY4(2016)target
FY4(2016)actual
FY5 (2017)end target
FY5 (2017)end actual
Average vehicleoperating cost for atypical bus reduced
Percentage Value 0.00 n.a. 5.00 n.a. 8.00
Date 31-Dec-2010 31-Dec-14
10-Nov-15
31-Dec-2017
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
by at least 8% onproject roads (baseyear operating cost:US$0.35/veh-km)
Comments Target notassessedbecause noworkscompleted
Target notassessedbecauseno workscompleted
Indicator Name CoreUnit ofMeasure
Baseline(2010)
FY1(2013)target
FY1 (2013)actual
FY2(2014)target
FY2(2014)actual
FY3(2015)target
FY3(2015)actual
FY4(2016)target
FY4(2016)actual
FY5 (2017)end target
FY5 (2017)end actual
Average vehicleoperating cost for atypical heavy truckreduced by 10% onproject roads (baseyear operating cost:US$0.65 veh-km)
Percentage Value 0.00 n.a. 7.00 n.a. 10.00
Date 31-Dec-2010 31-Dec-14
10-Nov-15
31-Dec-2017
Comments Target notassessedbecause noworkscompleted
Target notassessedbecauseno workscompleted
Indicator Name CoreUnit ofMeasure
Baseline(2010)
FY1(2013)target
FY1 (2013)actual
FY2(2014)target
FY2(2014)actual
FY3(2015)target
FY3(2015)actual
FY4(2016)target
FY4(2016)actual
FY5 (2017)end target
FY5 (2017)end actual
Average passengertravel time for lightvehicles reduced byat least 20% onproject roads (baseyear speed: 51km/h)
Percentage Value 0.00 0.00 -15.29 5.00 3.7 20.00
Date 31-Dec-201031-Dec-13
31-Dec-14
10-Nov-15
31-Dec-2017
Comments For 4ongoingworks only
For 9ongoingworks only
Indicator Name CoreUnit ofMeasure
Baseline(2010)
FY1(2013)target
FY1 (2013)actual
FY2(2014)target
FY2(2014)actual
FY3(2015)target
FY3(2015)actual
FY4(2016)target
FY4(2016)actual
FY5 (2017)end target
FY5 (2017)end actual
Average passengertravel time for largebuses reduced by atleast 20% on projectroads (base year
Percentage Value 0.00 0.00 -19.57 5.00 -2.17 20.00
Date 31-Dec-201031-Dec-13
31-Dec-14
10-Nov-15
31-Dec-2017
Comments No For 4 For 9
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
speed: 46 km/h) available ongoingworks only
ongoingworks only
Indicator Name CoreUnit ofMeasure
Baseline(2010)
FY1(2013)target
FY1 (2013)actual
FY2(2014)target
FY2(2014)actual
FY3(2015)target
FY3(2015)actual
FY4(2016)target
FY4(2016)actual
FY5 (2017)end target
FY5 (2017)end actual
Average passengertravel time forheavy trucksreduced by at least20% on projectroads (base yearspeed: 40 km/h)
Percentage Value 0.00 0.00 -17.50 5.00 -6.53 20.00
Date 31-Dec-201031-Dec-13
31-Dec-14
10-Nov-15
31-Dec-2017
Comments For 4ongoingworks only
For 9ongoingworks only
.
Intermediate Results Indicators
Indicator Name CoreUnit ofMeasure
Baseline(2010)
FY1(2013)target
FY1 (2013)actual
FY2(2014)target
FY2(2014)actual
FY3(2015)target
FY3(2015)actual
FY4(2016)target
FY4(2016)actual
FY5 (2017)end target
FY5 (2017)end actual
Number of km ofimproved nationalroads in the projectregion as planned
Kilometers
Value 0.00 0.00 0 5 5.38 80 134.54 380 640
Date 31-Dec-201031-Dec-13 Dec-14
10-Nov-15
31-Dec-2017
Comments Rev.Target
Rev.Target
Rev.Target
Rev. Target
Indicator Name CoreUnit ofMeasure
Baseline(2010)
FY1(2013)target
FY1 (2013)actual
FY2(2014)target
FY2(2014)actual
FY3(2015)target
FY3(2015)actual
FY4(2016)target
FY4(2016)actual
FY5 (2017)end target
FY5 (2017)end actual
Number of metersof improved bridges
Meters
Value 0.00 0.00 0.00 0.00 0.00 48.00 0.00 96.00 160.00
Date 31-Dec-201031-Dec-13 0
10-Nov-15
31-Dec-2017
Comments rehabilitated,Rural"
Rev.Target
Rev.Target
Rev.Target
Rev. Target
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
Indicator Name CoreUnit ofMeasure
Baseline(2010)
FY1(2013)target
FY1 (2013)actual
FY2(2014)target
FY2(2014)actual
FY3(2015)target
FY3(2015)actual
FY4(2016)target
FY4(2016)actual
FY5 (2017)end target
FY5 (2017)end actual
Satisfactorycompletion oftechnical audits forall road projects ofcomponent 1
Percentage
Value 0.00 0.00 0.00 0.00 0.00 20.00 16.00 60.00 100.00
Date 31-Dec-2010 31-Dec-13 0 31-Dec-2017
Comments Rev.Target
0 out of19
Rev.Target
3 out of19
Rev.Target
Rev. Target
Indicator Name CoreUnit ofMeasure
Baseline(2010)
FY1(2013)target
FY1 (2013)actual
FY2(2014)target
FY2(2014)actual
FY3(2015)target
FY3(2015)actual
FY4(2016)target
FY4(2016)actual
FY5 (2017)end target
FY5 (2017)end actual
Satisfactorycompletion of roadsafety audits carriedout by CTC or TLKJfor all road projectsof component 1
Percentage
Value 0.00 0.00 0 40 80 90 100 100 100.00
Date 31-Dec-2010 31-Dec-13 Dec-14 31-Dec-2017
Comments16 out of19
Rev.Target
19 outof 19
Rev.Target
Rev. Target
Indicator Name CoreUnit ofMeasure
Baseline(2010)
FY1(2013)target
FY1 (2013)actual
FY2(2014)target
FY2(2014)actual
FY3(2015)target
FY3(2015)actual
FY4(2016)target
FY4(2016)actual
FY5 (2017)end target
FY5 (2017)end actual
% of Environmentunit staff trainedand capacitated tomitigate disasterrisk related to roadnetwork (230 staff)
Percentage
Value 0.00 0.00 0.00 0.00 0 0.00 60.00 100.00 Indicator will be
Date 31-Dec-2010 31-Dec-13 31-Dec-2017 deleted
Comments
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
Appendix J
Correspondence
Monthly Progress Report March 2016 November 2014
Western Indonesia National Roads Improvement Project
Table of Contents
1 EXECUTIVE SUMMARY............................................................................................................ 1-1
1.1 Current Implementation Situation.......................................................................................................1-1
1.2 Disbursement..........................................................................................................................................1-4
1.3 World Bank Implementation Review Mission and Site Visit...............................................................1-5
1.4 Procurement of Civil Works Contract Under Category 1 of the Loan Agreement...........................1-5
2 PROJECT DESCRIPTION ........................................................................................................... 2-1
2.1 Background.............................................................................................................................................2-1
2.2 Project Development.............................................................................................................................2-1
2.3 Project Objective ......................................................................................................................................2-6
3 CONSULTANCY SERVICES ........................................................................................................... 3-1
3.1 CTC Consultants ......................................................................................................................................3-1
3.1.1 Scope of Services ........................................................................................................... 3-1
3.1.2 CTC Manning ................................................................................................................. 3-2
3.1.3 CTC Contract.................................................................................................................. 3-43.2 DSC Consultants.....................................................................................................................................3-6
3.3 Technical Assistance for Capacity Building for Disaster Risks Reduction........................................3-6
4 CIVIL WORKS............................................................................................................................ 4-1
4.1 Detailed Design Preparation...................................................................................................................4-1
4.2 Procurements ............................................................................................................................................4-1
4.3 Civil Works Implementation ...................................................................................................................4-1
4.4 Civil Works Progress.................................................................................................................................4-3
4.5 Quality Assurance.....................................................................................................................................4-8
4.6 Environmental and Social Considerations.............................................................................................4-9
4.6.1 Current Overall Situation.............................................................................................. 4-9
4.6.2 Environmental and Social Issues................................................................................ 4-104.7 Anti Corruption Issues..........................................................................................................................4-21
4.7.1 Anti‐Corruption Action Plan (ACAP) ........................................................................... 4-21
4.7.2 Community Representative Observers (CRO)........................................................... 4-21
4.7.3 Publication / Disclosure ............................................................................................... 4-22
4.7.4 Complaints Handling Mechanism (CHS) .................................................................... 4-23
4.7.5 Third Party Monitoring (TPM)..................................................................................... 4-244.8 Road Safety Audit ...............................................................................................................................4-25
5 FINANCIAL & MANAGEMENT INFORMATION SYSTEMS.......................................................... 5-1
5.1 Draw‐Downs and Future Costs..............................................................................................................5-1
5.2 Disbursement..........................................................................................................................................5-1
Monthly Progress Report March 2016 November 2014
Western Indonesia National Roads Improvement Project
5.3. Management Information System ......................................................................................................5-1
6 PROJECT PERFORMANCE ........................................................................................................ 6-1
6.1 World Bank and GOI Compliance........................................................................................................6-1
6.1.1 World Bank Missions .................................................................................................... 6-1
6.1.2 Agreed Key Actions and Mission Plans during Recent World Bank Mission ........... 6-1
6.1.3 Performance Indicators ................................................................................................ 6-36.2 Implementation Support Components...............................................................................................6-4
6.2.1 Core Team Consultant (CTC)........................................................................................ 6-4
6.2.2 Design and Supervision Consultant (DSC)................................................................... 6-4
6.2.3 Study on Slope Stabilization Design and Management............................................. 6-56.3 TRAINING TO SUPPORT PROJECT IMPLEMENTATION ........................................................................6-5
6.3.1 Continuing to prepare the implementation of three training programs thatactually should had been delivered in November-December last year; i.e: ...................... 6-5
6.3.2 Progress.......................................................................................................................... 6-6
6.3.3 Activities Plan for next month (March 2016).............................................................. 6-76.4 Anti‐Corruption Issues ...........................................................................................................................6-10
6.4.1 Anti-Corruption Action Plan (ACAP) .......................................................................... 6-10
6.4.2 Community Representative Observers (CRO).......................................................... 6-11
6.4.3 Third Party Monitoring (TPM).................................................................................... 6-11
6.4.4 Complaint Handling System (CHS)............................................................................. 6-12
6.4.5. Public Disclosures / Publication.................................................................................. 6-136.5 Road Safety Audit ................................................................................................................................6-14
6.5.1 Activities during This Month (March 2016) .............................................................. 6-146.6 Management Information System ....................................................................................................6-14
6.7 Quality Assurance...................................................................................................................................6-23
6.8 Project Risks and Mitigation Measures ...............................................................................................6-23
6.8.1 Risks Related to Delays ............................................................................................... 6-23
6.8.2 Financial Risks.............................................................................................................. 6-23
6.8.3 Risks Related to Quality .............................................................................................. 6-237 ISSUES and RECOMMENDATIONS .......................................................................................... 7-1
7.1 Current Situation ...................................................................................................................................7-1
7.2 Actions Required....................................................................................................................................7-1
8 CORRESPONDENCES ............................................................................................................... 8-1
Monthly Progress Report March 2016 November 2014
Western Indonesia National Roads Improvement Project
ABBREVIATIONS AND ACRONYMS
ACAP : Anti Corruption Action PlanAER : Application Evaluation ReportAIP : Australian Indonesia PartnershipAMDAL : Environmental Management (Analisis Mengenai Dampak
Lingkungan)ANDAS : Analisis Dampak SosialAWPs : Annual Work ProgramsBalai : Regional Office for National Roads ImplementationBAPPENAS : Badan Perencanaan Pembangunan Nasional (National
Development Planning Agency of GOI)Bappedalda : Regional Environmental Impact AgenciesBBPJN : Balai Besar Pelaksanaan Jalan Nasional (Regional Office for
National Roads Implementation)BER : Bid Evaluation Report
BLH : Badan Lingkungan Hidup
BPK : Badan Pemeriksaan Keuangan (Audit Board of the Government
of Indonesia)
CAD : Computer Aided Design
CHS : Complaint Handling System
CTC : Core Team Consultant
CHU : Complaint Handling Unit
CRO : Community Representative Observer ( = WPM)
DIA : Directorate of Implementing Affairs
DOP : Directorate of Planning
DGH : Directorate General of Highways
DMS : Document Management System
DTA : Directorate of Technical Affairs
DMS : Document Management System
DSC : Design and Supervision Consultants
EA : Executing Agency
EINRIP : Eastern Indonesian National Roads Improvement Project
EIRTP-1 : Eastern Indonesia Regional Transport Project First Project
ESAMP : Environmental and Social Assessment Plan
ESS : Environmental and Social Safeguards
FMIS : Financial Management Information System
FIDIC : Federation Internationale des Ingenieur Conseils
Monthly Progress Report March 2016 November 2014
Western Indonesia National Roads Improvement Project
FMIS : Financial Management Information System
GIS : Geographic Information System
GOI : Government of Indonesia
IA : Implementation Agency
IBRD : International Bank for Reconstruction and Development
IFR : Internal Financial Report
IRMS : Integrated Road Management System
Kabupaten : Regency
KPIs : Key Performance Indicators
KPPN : Kantor Pelayanan Perbendaharaan Negara (Indonesian: State
Treasury Service Office)
LAN : Local Area Network
LARAP : Land Acquisition and Resettlement (Rencana Tindak Pengadaan
Tanah dan Pemukiman Kembali)
MIS : Management Information System
MOF : Ministry of Finance
MPW : Ministry of Public Work
MPRs : Monthly Progress Reports
P2JN : Perencanaan Pengawasan Jalan dan Jembatan Nasional
PDF : Portable Document Format
PMU : Project Management Unit
PAPs : Project Affected Peoples
PMM : Project Management Manual
PMU : Project Management Unit (WINRIP)
POKJA : Bina Marga Project Managers and Procurement Committes
PPC : Project Preparation Consultants
PP3 : Pemantau Pihak ke 3
PPK : Sub Project Manager
PPR : Project Progress Report
QPRs : Quarterly Progress Reports
RKL/RPL : Rencana Pengelolaan/Pemantauan Lingkungan
RS : Road Safety
Satker : Satuan Kerja (Work Unit for Road Project Implementation)
SPPL : Surat Pernyataan Pengelolaan Lingkungan
SRIP : Strategic Road Infrastructure Project
TA : Technical Assistance
Monthly Progress Report March 2016 November 2014
Western Indonesia National Roads Improvement Project
TOR : Terms of Reference
UKL/UPL : Upaya Pengelolaan Lingkungan / Upaya Pemantauan Lingkungan
(Site Specific Environmental and Monitoring Plan)
WINRIP : Western Indonesia Roads Improvement Project
WB : World Bank
WP : Work Program
WPs : Works Programs
WPM : Wakil Pengamat dari Masyarakat (or Community Representative
Observer / CRO )
Monthly Progress Report March 2016 November 2014
Western Indonesia National Roads Improvement Project
APPENDICESAppendix A : Overall Loan Progress
Appendix B : Road Safety Audit Progress
Appendix C : Financial Progress
Appendix D : Quality Assurance Progress
Appendix E : Environmental and Social Progress
Appendix F : Procurement Plan and Progress
Appendix G : WINRIP Website Progress
Appendix H : ACAP Training/Dissemination Progress
Appendix I : Performance Indicator
Appendix J : Correspondences
ANNEXES
Annex P-1 : Package No. 1
Annex P-2 : Package No. 2
Annex P-3 : Package No. 3
Annex P-4 : Package No. 4
Annex P-5 : Package No. 5
Annex P-6 : Package No. 6
Annex P-7 : Package No. 7
Annex P-11 : Package No. 11
Annex P-13 : Package No. 13
Annex P-15 : Package No. 15
Annex P-17 : Package No. 17
Annex P-19 : Package No. 19
ATTACHMENTAttachment 1 : Summary of Studies and Reports on Environmental Activity
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
1- 1
1 EXECUTIVE SUMMARY
1.1 Current Implementation SituationCivil Works
Implementation of the WINRIP Project is scheduled to be implemented into three (3) Annual WorkPrograms (AWP’s). The implementation starts with the preparation of tender documents (detaileddesign drawings including associated bidding documents), tendering stage (procurement of works)and the actual civil works construction implementation.
The original implementation schedules of the three (3) Annual Work Programs (AWPs) arescheduled in three (3) phases namely ; AWP-1 to start in mid-2011 and to be completed on the lastquarter of 2014, AWP-2 is expected to begin in mid 2012 with target date of completion by mid-2016 and AWP-3 is expected to start during the early part of 2013 and to be completed during themiddle part of 2017.
However, due to some unavoidable circumstances the original implementation schedules did notmaterialized.
Based on the present status of the program implementation progress, a revised implementationschedule, the “Project Implementation Timeline” (as shown on Page 1-2) is to be implemented inorder to accommodate the originally delayed schedule into the remaining time frame of theWINRIP Program until the expiry date of the loan agreement by the end of December 2017. Shownon Page 1-3 is the current actual status of the implementation relative to the “ProjectImplementation Timeline”.
Implementation Status as of March 31, 2016
PackPackage Name
Contract Under Contract Proc
No. Sign Construct SignPreparation Process
1 Krui - Biha 1 Completed2 Padang Sawah - Sp.Empat 1 13 Manggopoh - Padang Sawah 1 Completed4 Ipuh - Bantal 1 15 Sp. Rampa - Poriaha 1 16 Ps. Pedati - Kerkap 1 17 Indrapura - Tapan 1 18 Bts.Pariaman - Manggopoh 1 1
10 Sp. Empat - Sp. Air Balam 111 Bantal - Mukomuko 1 112 Kambang - Indrapura 113 Sp. Rukis - Tj.Kemuning 1 114 Painan - Kambang 115 Sibolga - Bts.Tap Sel 1 116 Seblat - Ipuh 117 Sp.Gn.Kemala - Pg.Tampak 1 119 Lais - Bintunan 1 120 Lubuk Alung - Sicincin 121 Lubuk Alung - Kuraijati 1
T O T A L : 14 11 1 4
Note : Package No.9 (Rantau Tijang – Kota Agung) and Package No.18 (Mukomuko – Bts. Sumbar) are cancelled from the program.
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
1 - 2
Length C'tion
Km Period J N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
1 Krui - Biha 25,00 21 mth
2 Padang Sawah - Sp.Empat 40,90 24 mth
3 Manggopoh - Padang Sawah 32,00 24 mth
4 Ipuh - Bantal 42,40 24 mth
5 SIMPANG RAMPA - PORIAHA 11,10 18 mth
11 BANTAL - MUKOMUKO 50,10 24 mth
13 SP RUKIS - TJ KEMUNING 56,30 24 mth
17 Sp.Gn.KEMALA - Pg. TAMPAK 36,80 24 mth
6 PS. PEDATI - KERKAP 25,00 15 mth
19 LAIS - BINTUNAN 11,60 10 mth
15 SIBOLGA - BATAS TAPSEL 36,00 27 mth
7 INDRAPURA - TAPAN 19,50 21 mth
8 BTS.Kt PARIAMAN-MANGGOPOH 46,80 24 mth
10 SIMPANG EMPAT - SP.AIR BALAM 61,70 24 mth
12 KAMBANG - INDRAPURA 55,20 24 mth
14 PAINAN – KAMBANG 31,50 21 mth
16 SEBLAT – IPUH 34,50 21 mth
20 LUBUK ALUNG – SICINCIN 14,60 18 mth
21 LUBUK ALUNG – KURAITAJI 16,80 18 mth
9 RANTAU TIJANG-KOTA AGUNG 42,00 The Road has been constructed by MPW within 2011-2013. Road condition is good. Proposed to be deleted from the list of WINRIP's work program
18 MUKOMUKO-BTS SUMBAR 25,80 The Road has been constructed by MPW within 2011-2013. Road condition is good. Proposed to be deleted from the list of WINRIP's work program
Original target : 715,60 km ENVIRONMENT & SOCIAL SAFEGUARD
Revised target : 640,00 km Prequalification Detail Eng Design LARAP Study
Road Safety Owner's Estimate Appraisal & Public Consultation
Procurement & Sign Contr Bid Document LARAP Implementation
Preparation for Commencement of Work
Standard Biding Document
COW
PROC COW
PROC COW
PROC
CONSTRUCTION
CONSTRUCTION
PROC COW
PROC COW
PROC COW
PROC COW
CONSTRUCTION
CONSTRUCTION
CONSTRUCTION
CONSTRUCTION
CONSTRUCTION
Pack# PACKAGE NAME
2012 2013 2014 2015 2016 2017 2018
OE & BD
DED RSA & REVISED DED OE & BD
CONSTRUCTION
PROC COW
Review DED & RS
Review DED & RS
Review DED & RS
Review DED & RS
Review DED & RS PQ
CONSTRUCTION
Review DED & RS PQ PROC COW
Review DED & RS PQ
CONSTRUCTION
COW CONSTRUCTION
PROC
CONSTRUCTION
PQ
RS
Proc
COW
SBD
CONSTRUCTION
CONSTRUCTION
CONSTRUCTION
DED RSA & REVISED DED OE & BD
DED RSA & REVISED DED OE & BD
OE
BD
DED
SBD & OE + BD
Rev-DED RS
DED Rev-DED RS
Rev-DED RS
DED
COWPROC
COW CONSTRUCTION
OE & BD
DED Rev-DED RS OE & BD
OE & BD
DED OE & BD
COW
CONSTRUCTION
SBD & OE + BD
SBD & OE + BD
PQ PROC
PROC
CONSTRUCTION
CONSTRUCTION
DED RSA & REVISED DED
Project Implementation Timeline Schedule
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
1 - 3
Length C'tion
Km Period J N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
1 Krui - Biha 25,00 21 mth 8 Jan'14
2 Padang Sawah - Sp.Empat 40,90 24 mth 6 Jan'14
3 Manggopoh - Padang Sawah 32,00 24 mth 6 Jan'14
4 Ipuh - Bantal 42,40 24 mth 10 Jan'14
5 SIMPANG RAMPA - PORIAHA 11,10 18 mth 18 Jun'15 11 Feb'17
11 BANTAL - MUKOMUKO 50,10 24 mth 23 Feb'15 11 Feb'17
13 SP RUKIS - TJ KEMUNING 56,30 24 mth 11 Feb'17
17 Sp.Gn.KEMALA - Pg. TAMPAK 36,80 24 mth 04 Sep'15 23 Agt'17
6 PS. PEDATI - KERKAP 25,00 15 mth 11 Mar'15 02 Jun'16
19 LAIS - BINTUNAN 11,60 10 mth 11 Mar'15 CONSTRUCTION 300+125 days 08 May'16
15 SIBOLGA - BATAS TAPSEL 36,00 27 mth 20 Nov'15 06 Feb'18
7 INDRAPURA - TAPAN 19,50 21 mth 10 Dec'15 30 Agt'17
8 BTS.Kt PARIAMAN-MANGGOPOH 46,80 24 mth 23 Mar '16 CONSTRUCTION 720 days
10 SIMPANG EMPAT - SP.AIR BALAM 61,70 24 mth
12 KAMBANG - INDRAPURA 55,20 24 mth
14 PAINAN – KAMBANG 31,50 21 mth
16 SEBLAT – IPUH 34,50 21 mth
20 LUBUK ALUNG – SICINCIN 14,60 18 mth
21 LUBUK ALUNG – KURAITAJI 16,80 18 mth
9 RANTAU TIJANG-KOTA AGUNG 42,00 The Road has been constructed by MPW within 2011-2013. Road condition is good. Cancelled
18 MUKOMUKO-BTS SUMBAR 25,80 The Road has been constructed by MPW within 2011-2013. Road condition is good. Cancelled
Original target : 715,60 km ENVIRONMENT & SOCIAL SAFEGUARD
Revised target : 640,00 km Prequalification Detail Eng Design LARAP Study
Road Safety Owner's Estimate Appraisal & Public Consultation
Procurement & Sign Contr Bid Document LARAP Implementation
Preparation for Commencement of Work
Standard Biding Document
PQ
ICB
ICB
ICB
ICB
ICB
10-Jan-16CONSTRUCTION 640 + 93 days
19-Apr-16
20-Mar-16
08-Apr-16
CONSTRUCTION 540 days
Pack# PACKAGE NAME
2012 2013 2014 2015 2016 2017 2018
CONSTRUCTION
Review DED & RS PQ PROC
Review DED & RS PQ
DED
SBD & OE + BD
DED
DED RSA & REVISED DED OE & BD
DED RSA & REVISED DED OE & BD
DED
Review DED & RS
CONSTRUCTION
CONSTRUCTION 450 daysSBD & OE + BD
CONSTRUCTION 720 days
CONSTRUCTION 720 days
PROC
PQ
RS
Proc
COW
SBD
CONSTRUCTION 730 + 105 days
CONSTRUCTION 730 + 75 days
CONSTRUCTION 730 + 90 days
DED RSA & REVISED DED OE & BD
DED RSA & REVISED DED OE & BD
DED
OE
BD
Review DED & RS
PROC
PROC
PROC
Review DED & RS
PQ
Rev-DED RS
PROC
CONSTRUCTION 720 daysICB
ICB
ICB
ICB
NCB
NCB
NCB
Review DED & RS
Review DED & RS SBD & OE + BD
CONSTRUCTION 810 days
CONSTRUCTION 630 days
22-Jul-15
PROC 12 Mar'18
COW CONSTRUCTION
Rev-DED RS
Rev-DED RS
Rev-DED RS
ICB
ICB
ICB
NCB
NCB
NCB
NCB
COW
PROC COW
PROC
PROC
PROC
CONSTRUCTION
CONSTRUCTION
DED CONSTRUCTION
Actual Implementation Timeline of WINRIP
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
1 - 4
1.2 Disbursement
Loan Allocation and Percent (%) Disbursement To Date
#REF! 1.25
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
90.00
100.00
Month
% Co
mplet
e
Actual Expenditure USD52.94 mil (21.18 %)
WINRIP ACTUAL PROGRESS UP TO MARCH 2016 AND FORECAST UP TO DECEMBER 2017
ACTUAL March 2016Forecast March 2016
Forecast Expenditure USD 150.38 mil(60.15%)
Deviation = 38.97%
The total disbursement summary from the loan by The World Bank to the end of March 2016was USD 52,938,748.41 equivalent to approximately 21.18% of the loan funds. The followingtable summarizes the individual disbursements as calculated by CTC but retaining the totaldisbursement from Client Connection at the end of March 2016. Appendix A shows the OverallLoan Progress Status.
Category DescriptionLoan
RestructuringAmount US$
DisbursementThis Period
PreviousDisbursement
Totals Disbursedto End Marc in
US$
%Disbursed
1
Part 1 Bettermentand CapacityExpansion of
National Roads.
220,400,000.00 2,794,212.51 44,560,655.07 47,354,867.58 21.49
2Part 2
ImplementationSupport
17,000,000.00 0 5,583,880.83 5,583,880.83 34.90
3
Part 3Road SectorInstitutional
Development
0 0 0 0 0
4
Part 4Contingency for
Disaster RiskResponse
0 0 0 0 0
Unallocated 12,600,000.00 0 0 0 0Original Loan
Amount 250,000,000.00 2,794,212.51 50,144,535.90 52,938,748.41 21.18
Breakdown of amount disbursed during the period (March 2016) are the advance payment of newlycommenced subproject and for “Statement of Work Accomplished” for the following civil works contractpackages :
Package No. 1 : MC Nos. 23 and 24 * USD 326,297.26 Package No. 2 : MC Nos. 24 and 25 USD 158,431.89 Package No. 3 : MC Nos. 24 and 25 USD 228,489.35 Package No. 8 : Advance Payment USD 1,910,996.77 Package No.17 : MC Nos. 3 and 4 USD 169,997.24
* Unpaid balance from previous work accomplished covered under the same MC Nos. 23 and 24 inDecember 2015 because of insufficient funds from LOAN DIPA’s 2015.
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
1 - 5
1.3 World Bank Implementation Review Mission and Site Visit
During this period (March 2016) the World Bank’s Technical and Financial Audit Consultants (TFAC)mission performed and conducted site audits on Package 11 (Bantal – Mukomuko) and Package 19(Lais – Bintunan).
The mission visited the two (2) contract packages from February 29, 2016 to March 4, 2016 inorder to access the following :
The quality of works implemented by the Contractor, site management and qualitycontrol and compliance of equipment.
The actions taken by the Design Supervision Consultant (DSC) concerning qualitycontrol role.
Follow-up inspection of what actions taken up by the Contractor on the remainingnon-conformance works that were previously inspected way back in November 2015.
As the month ended, the regular monthly progress meeting was held to review and/or updatethe implementation progress and monitoring the key activities on the Ägreed Key ActionPlans”.
Also taken up during the meeting was the presentations of the results of the TFAC auditreports and recommendations to rectify the non-conformance findings.
1.4 Procurement of Civil Works Contract Under Category 1 of the Loan Agreement
The current status of Contract Packages which are under final procurement stage are asfollows :
1. Package No.8 (Bts. Kota Pariaman - Manggopoh) AWP-2
This sub-project is under implementation schedule AWP-2. The project roadline islocated in the Province of Sumatera Barat having an approximate length of46.80 kilometers.
The Contract Package is procured thru the post qualification and InternationalCompetitive Bidding (ICB) procurement method using the Full e-Procurement System.
As previously mentioned in earlier reports, Contract Agreement has been executed onJanuary 28, 2016 between the Government of Indonesia (GOI) and PT. PP (Persero)Tbk – PT. Statika Mitra Sarana J.O for a contract amount of Rp. 355,500,000,000 and720 calendar days contract time.
No Objection Letter (NOL) on the signed Contract Agreement and Form 384 fordisbursement purpose has been issued by World Bank on February 18, 2016.
Notice To Proceed (NTP) to commence works has been issued on March 23, 2016which is considered as day 1 of the 720 calendar day contract period.
2. Package No.10 (Sp. Empat – Sp. Air Balam) AWP-2
This sub-project is under implementation schedule AWP-2. The project roadline islocated in the Province of Sumatera Barat having an approximate length of61.70 kilometers.
The Contract Package is procured thru the post qualification and InternationalCompetitive Bidding (ICB) procurement method using the Full e-Procurement System.
The revised Bid Evaluation Report (BER) which was resubmitted to the Bank on
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
1 - 6
February 19, 2016 has been concurred by the World Bank on February 22, 2016 byissuing a No Objection Letter (NOL) to award the contract to the joint operation of PT.Lancarjaya Mandiri Abadi and PT. Cahaya Tunggal Abadi in the amount ofRp.424,285,260,782.50 with 720 calendar days time completion.
However, the announcement and notification of the award winner has been witheldtemporarily due to conflict with the Presidential Regulation No.54 of the Year 2010,Article 79, Paragraph (2) and Ministerial Regulation No.31 of Year 2015, Article 6d,Paragraph (1) and (2) in which the post evaluation of bids is not in line with thecurrent regulations.
3. Package No.12 (Kambang - Indrapura) AWP-2
This sub-project is under implementation schedule AWP-2. The project roadline islocated in the Province of Sumatera Barat having an approximate length of55.20 kilometers.
The Contract Package is procured thru the post qualification and InternationalCompetitive Bidding (ICB) procurement method using the Full e-Procurement System.
As previously mentioned in earlier reports, Contract Agreement has been executed onJanuary 28, 2016 between the Government of Indonesia (GOI) and PT. LancarjayaMandiri Abadi – PT. Cahaya Tunggal Abadi (JO) for a contract amount of Rp.358,650,400,000 and 720 calendar days contract time.
Copy of the signed contract has been submitted on March 7, 2016 to World Bank forrequest the issuance of Form 384 for disbursement purpose. A day after thesubmission, the Bank, on March 8, 2016, issued No Objection Letter (NOL) and theForm 384.
Issuance of Notice To Proceed (NTP) to commence the works is still to be issuedsubject to substantial completion of compensating the Project Affected People (PAP).
4. Package No.16 (Seblat-Ipuh) AWP-3
The sub-project is to be implemented under implementation schedule AWP-3. TheProject road length covers 34.50 kilometers and is located in the Province of Bengkulu.
The Contract Package is procured thru post qualification criteria and NationalCompetitive Bidding (NCB) method using the Full e-Procurement System.
Bid Evaluation Report (BER) has been completed by POKJA and submitted to WorldBank on January 11, 2016 for review and issuance of No Objection Letter (NOL).However, per Bank’s letter of January 20, 2016 regarding results of their prior reviewof the BER have comments on the proposed disqualification of five (5) lower pricedbidders.
In response with the Banks comments, POKJA explained in details the reasons todisqualify the five (5) lower priced bidders. The detailed explainations, justificationsand resubmission of the Revised Bid Evaluation Report (BER) were forwarded to theBank thru letter of March 21, 2016 by the Director of Road Network Development.
The Revised Bid Evaluation Report (BER) and recommendation for award of thecontract remain to be the same bidder as previously proposed in the original BidEvaluation Report (BER).
Due to the disqualification of the five (5) lower priced bidders, POKJA still propose andrecommend the award of the Contract to PT. Hutama Karya (Persero) for a contractamount of Rp.266,120,828,000.
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
1 - 7
5. Package No.14 (Painan - Kambang) AWP-3
The sub-project is to be implemented under implementation schedule AWP-3. TheProject road length covers 31.50 kilometers and is located in the Province of WestSumatera.
The Contract Package is procured thru post qualification criteria and NationalCompetitive Bidding (NCB) using the Full e-Procurement System.
As mentioned earlier, there were four (4) applicant bidders (3 sole entity and 1 jointventure operation) who submitted bids for the civil works implementation.
Following are the four (4) bidders with their respective bid prices :
PT. Yasa Patria Perkasa – Conbloc, JO Rp. 214,602,400,000 PT. Waskita Karya Rp. 239,449,604,000 PT. Jaya Konstruksi Rp. 239,628,825,000 PT. PP Rp. 249,277,000,000
The lowest canvassed bid is submitted by the joint venture operation of PT. YasaPatria Perkasa and Conbloc with an amount of Rp. 214,602,400,000 which is 19.80%below the approved Owner’s Estimate (OE) of Rp. 267,590,800,000 while the 2nd
lowest bid is quoted by PT. Waskita Karya with an amount of Rp. 239,449,604,000 or10.58% lower than the Owner’s Estimate.
During this reporting month (March 2016) Bid Evaluation Report (BER) andrecommendation for award of contract has been finalized and completed by theProcurement Committee (POKJA) recommending the award of contract to theevaluated lowest responsive bidder, PT. Yasa Patria Perkasa – Conbloc, JO, for acorrected contract amount of Rp.214,327,429,680.
The Bid Evaluation Report (BER) as well as the recommendation for award of contracthas been forwarded on March 21, 2016 to World Bank for Bank’s concurrence andissuance of No Objection Letter (NOL).
6. Package No.20 (Lubuk Alung - Sicincin) AWP-3
The sub-project is to be implemented under implementation schedule AWP-3. TheProject road lenght covers 14.60 kilometers and is located in the Province of WestSumatera.
The Contract Package is procured thru post qualification criteria and NationalCompetitive Bidding (NCB) using the Full e-Procurement System.
As mentioned earlier, there were five (5) applicant bidders (4 sole entity and 1 jointventure operation) who submitted bids for the civil works implementation.
Following are the five (5) bidders with their respective bid prices :
PT. Nindya Karya Rp. 113,818,300,000 PT. Conbloc Infratechno – Statika, KSO Rp. 118,172,039,000 PT. Waskita Karya Rp. 122,767,255,000 PT. Jaya Konstruksi Rp. 126,670,765,000 PT. PP Rp. 125,192,900,000
The lowest canvassed bid is submitted by PT. Nindya Karya with an amount of
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
1 - 8
Rp. 113,818,300,000 which is 13.32% below the approved Owner’s Estimate (OE) ofRp. 131,302,200,000 while the 2nd lowest bid is quoted by PT. PT. Conbloc Infratechno– Statika, KSO Joint Operation with an amount of Rp. 118,172,039,000 or 10.00%lower than the Owner’s Estimate.
During this reporting month (March 2016) Bid Evaluation Report (BER) andrecommendation for award of contract has been finalized and completed by theProcurement Committee (POKJA) recommending the award of contract to theevaluated lowest responsive bidder, PT. Nindya Karya (Persero) Tbk, for a correctedcontract amount of Rp.113,818,304,610.
The Bid Evaluation Report (BER) as well as the recommendation for award of contracthas been forwarded on March 21, 2016 to World Bank for Bank’s concurrence andissuance of No Objection Letter (NOL) and by March 23, 2016, NOL was issued.
7. Package No.21 (Lubuk Alung - Kuraitaji) AWP-3
The sub-project is to be implemented under implementation schedule AWP-3. TheProject road lenght covers 16.80 kilometers and is located in the Province of WestSumatera.
The Contract Package is procured thru post qualification criteria and NationalCompetitive Bidding (NCB) using the Full e-Procurement System.
As mentioned earlier, there were eight (8) applicant bidders (7 sole entity and 1 jointventure operation) who submitted bids for the civil works implementation.
Following are the eight (8) bidders with their respective bid prices :
PT. Multi Structure Rp. 126,301,991,200 PT. Adhi Karya Rp. 133,638,300,000 PT. Nindya Karya Rp. 141,465,600,000 Pan Asia Corporation Rp. 143,186,229,000 PT. Conbloc Infratechno – Statika, KSO Rp. 143,227,420,000 PT. Jaya Konstruksi M,P Rp. 147,718,199,000 PT. Waskita Karya Rp. 150,966,239,000 PT. PP Rp. 154,124,000,000
The lowest canvassed bid is submitted by PT. Multi Structure with an amount ofRp. 126,301,991,200 which is 23.28% below the approved Owner’s Estimate (OE) ofRp. 164,692,268,000 while the 2nd lowest bid is quoted by PT. Adhi Karya with anamount of Rp. 133,638,300,000 or 18.82% lower than the Owner’s Estimate.
During this reporting month (March 2016) Bid Evaluation Report (BER) andrecommendation for award of contract has been finalized and completed by theProcurement Committee (POKJA) recommending the award of contract to theevaluated lowest responsive bidder, PT. Multi Structure, for a corrected contractamount of Rp.126,301,991,202.
The Bid Evaluation Report (BER) as well as the recommendation for award of contracthas been forwarded on March 21, 2016 to World Bank for Bank’s concurrence andissuance of No Objection Letter (NOL) and by March 23, 2016, NOL was issued.
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
1 - 9
1.5 Procurement of Three (3) Consultancy Packages Under Category 3 of the LoanAgreement, Part 3: Road Sector Institutional Development
1. Technical Assistance for Capacity Building for Disaster Risk Reduction
The Technical Assistance for Disaster Risk Reduction was canceled based on theresults of meeting between DGH and the WB on October 12, 2015. It was decided tocancel the Technical Assistance and to be replaced by a “Technical Assistance forStudy on Slope Stabilization Design and Management” (under Loan Category-2).
Term of Reference (TOR) has already been finalized and submitted to World Bank forconcurrence prior to publication on PU Website for “Request of Expression ofInterest”(REOI) from interested consulting firms.
2. Technical Assistance for Capacity Building for Environmental Management
Cancelled.
3. Technical Assistance for Capacity Building for Road Safety
Cancelled.
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
2 - 1
2 PROJECT DESCRIPTION
2.1 Background
The Government of Indonesia wishes to continue strengthening of the National Road system inIndonesia while the Eastern Indonesia National Roads Improvement Project (EINRIP which isassisted by AusAID through the Australian Indonesia Partnership or AIP), is providing supportprogram of National road and bridge improvement works in Eastern Indonesia. The WesternIndonesia National Road Improvement Project (WINRIP) will provide similar support for Nationalroad and bridge in the Sumatera region of Indonesia. The focus of WINRIP will be roadsadministered directly by the National Government, including those currently classified asProvincial, Kabupaten (District) or non-status roads which are in process of being reclassified asNational roads. In addition, provision will be made for major bridge repair works, rehabilitation,duplication and replacement as necessary to complement road betterment works.
2.2 Project Development
The loan effectiveness date for the WINRIP is 12 March 2012 and key project data is shown in thefollowing detail.
Key Project Data WINRIP Loan No. 8043-ID
Project Cost US$350 million
Original Loan Amount US$250 million
Revised Loan Amount N/A
Board Approval Date 26 May 2011
Loan Signing Date 14 December 2011
Effectiveness Date 12 March 2012
Disbursement (as of 31 March 2016) US$ 52,938,748.41 million (21.18%)
Original Closing Date 31 December 2017
Environmental Category B-Partial Assessment
The IBRD loan amount is US$250 million. The Project is intended to finance a part of the DGHinvestment program for national roads with a particular focus on the Western corridor ofSumatera. The corridor is one of the three main corridors in Sumatera and connects the city ofPadang (with a population of around one million) to major towns along the west coast (Bukittinggi,Sibolga and Bengkulu). It also connects through connector roads on the West coast to Medan inthe northeast and to Pekanbaru in the centre of the island. The project has four components:
Project Component 1: Betterment and Capacity Expansion of National Roads
According to the Loan Agreement, this component will cover three work programs of bettermentand capacity expansion of approximately 715.6 km including replacement of 194 meters of bridges.This civil works program will be executed in three Annual Work Programs(AWP), as summarized inTable 2.1. The table shows the IBRD assisted scope and costs of civil works at estimated current(year of implementation) prices, excluding taxes.
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
2 - 2
Table 2.1 Proposed Physical Works by DGH Program
Type of WorksAWP-1 AWP-2 AWP-3
Km USDMillion
Km USDMillion
Km USDMillion
Road Betterment - - 53.10 22.77 - -
Capacity Expansion 137.10 79.70 314.60 127.67 207.60 74.58
Bridge works 0.100 1.94 - - 0.08 2.06
TOTAL(excluding tax @ current prices)
137.20 81.64 367.70 150.45 207.68 76.65
The batches of projects are termed Annual Work Programs (AWPs) in line with terminology used inother Bina Marga projects. They are not in fact “annual” programs as such but rather a series ofmulti-year programs, each commencing in consecutive years. Hence, hereinafter it will call as justWork Programs (WPs). It is expected that implementation of the first Works Program (WP-1) willcommence in the third quarter of 2013 and be completed by third quarter or late 2015. Thesecond Work Program (WP-2) is expected to commence in early 2014 and be completed by late2015 or middle 2016. The third Work Program (WP-3) is expected to commence in early 2015 andbe completed by mid-2017. The loan will be closed on December 2017.
Table 2.2 presents details of the First Works Program (WP-1). The four packages in this groupshould have been free from any land acquisition issues, but in fact two packages (Krui – Biha andManggopoh – Padang Sawah) had land issues which were solved by the DGH properly. Thus, thereare no foreseeable impediments to implementation.
Table2.2 IBRD Assisted WINRIP Civil Work WP-1
No Province LinkNo.
LinkName
Clas
s
Road
Typ
e
Road Works Bridge Works Total Cost
From
To Leng
th
Trea
tmen
t
Cost
(201
0)
No
Leng
th
Cost
(201
0)
2010
Pric
es
Equi
vale
nt
Km Km Km Rp mill m Rp mill Rp mill US$ mill
1 Lampung 053.0 Krui –Biha K1 IU 221.5 246.5 25.0 Bett’nt
to 7 m. 148,668 148,668 16.52
2 WestSumatera 047.2
PadangSawa –SimpangEmpat
K1 IU 0.0 40.9 40.9 Bett’ntto 7 m. 189,810 189,810 21.09
2a WestSumatera 34.1 AirGadan
gBridge K1 IU NewBridge 1 100 17.580 17,580 1.95
3 WestSumatera 047.1
Manggopoh –PadangSawah
K1 IU 102.2 134.2 32.0 Bett’ntto 7 m. 152,435 152,435 16.94
4 Bengkulu 015.3 Ipuh -Bantal K1 IU 0.0 42.40 42.40 Bett’nt
to 7 m. 226,275 226,275 25.14
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
2 - 3
It should be noted that all road sub-projects have been subject to economic appraisal and haveestimated Economic Internal Rates of Return (EIRR) in excess of 15%. These were selected forinclusion and are subject to completion of environmental and social screening, to confirm thatthere is no land acquisition or resettlement requirements remain outstanding.
Final Engineering Designs, Engineer’s Estimates and bidding documents have been completed forall projects proposed for WP-1.
Sub-projects to be included in WP-2 and WP-3 have also been determined as listed in Table 2.3.Final Engineering Designs and Engineer’s Estimates for all WP-2 and WP-3 proposed works requirepreparation or finalization. In the cases of some projects, preliminary Engineering Designs wereprepared during Project preparation which will require review and possible amendment by theDesign and Supervision Consultant prior to procurement.
The revised costs presented in Table 2.3 are planning estimates only, and the revisedimplementation plan is based on the “Revised Implementation Timeline Schedule” of the civilworks.
Table2.3: IBRD Loan WINRIP Civil Work WP-2 and WP-3
NO. SUBPROJECT LINK NO. AND NAME LENGTH(KM)
ENGINEER’SESTIMATE(RP. MILL)
WIDTH(M)
REVISED IMPLEMENTATION PLAN
START DURATION(MONTHS)
WP-2
5. Sumut : Link No. 015.xx,Sp. Rampa – Poriaha 11.10 152,870 6.0 Mar 2015 18
6. Bengkulu : Link No. 010.0,Ps. Pedati – Kerkap 25.00 92,127 7.0 Apr 2015 15
7. Sumbar : Link No. 019.0,Indrapura – Tapan 19.50 178,600 7.0 Jan 2016 21
8. Sumbar : Link No. 024.0,Bts. Pariaman – Manggopoh 46.80 379,034 7.0 Jan 2016 24
9. Lampung : Link No. 026.1,Rantau Tijang - Kota Agung - - - - Cancelled
10. Sumbar : Link No. 034.1,Sp. Empat - Sp. Air Balam 61.70 515,842 7.0 Jan 2016 24
11. Bengkulu : Link No. 015.2,Bantal – Mukomuko 50.10 246,500 6.0 Feb 2015 24
12. Sumbar : Link No. 017.2,Kambang – Indrapura 55.20 451,810 7.0 Jan 2016 24
13. Bengkulu : Link No. 006.1,Simpang Rukis - Tanjung Kemuning 56.30 316,305 7.0 Jun 2015 24
WP-3
14.Sumbar : Link No. 017.1,Painan – Kambang 31.50 252,000 7.0 May 2016 21
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
2 - 4
NO. SUBPROJECT LINK NO. AND NAME LENGTH(KM)
ENGINEER’SESTIMATE(RP. MILL)
WIDTH(M)
REVISED IMPLEMENTATION PLAN
START DURATION(MONTHS)
15. Sumut : Link No. 016.0,Sibolga - Bts. TapSel 36.00 376,479 7.0 Oct 2015 27
16.Bengkulu : Link No. 009.4,Seblat – Ipuh, including Air Galang andAir Guntung Bridges
34.500.052 241,500 6.0 May 2016 21
17. Lampung : Link No. 061.1,Sp. Gunung Kemala - Pugung Tampak
36.80 255,269 6.0 Sep 2015 24
18. Bengkulu : Link No. 015.3,Mukomuko - Bts. Sumbar - - - - Cancelled
19. Bengkulu : Link No. 009.1,Lais – Bintuan 11.60 35,886 7.0 Apr 2015 10
20. Sumbar : Link No. 002.0,Lubuk Alung – Sicincin 14.60 116.800 7.0 May 2016 18
21. Sumbar : Link No. 027.0Lubuk Alung – Kuraitaji 16.80 65,788 7.0 May 2016 18
Project Component 2: Implementation Support
This component provides consulting services to support project management and implementationso as to ensure implementation efficiency and overall quality of the works. It also includes fundsfor a small amount of training of DGH staff and for incremental operating costs for the project. Thiswill provide support to the MPW for the implementation of the civil works, including: (a) provisionof Core Team Consultants (CTC), Design and Supervision Consultants (DSC) and road safety audits;(b) Project management support and technical audits. This is directly related to theimplementation of the civil works and covers consulting services for design and supervision of thecivil works in Component 1; management support and technical audits to help improve the qualityof construction and support to governance improvements during procurement andimplementation; and a series of systematic road safety audits of road designs for all project roadsin Component 1. This is to ensure compliance with road safety standards and regulations, identifyroad hazards and undertake remedial treatments for safety improvements, (c) slope protectiondesign and management. This is related to Technical Assistance and Support to StrengthenDisaster Risk Mitigation in the Road Sector mainly to deal with stabilizing and strengthening, inparticular roadway side cut and high embankment slopes by providing appropriate slopeprotection structures. These activities initially is part of Component-3 : Road Sector InstitutionalDevelopment, however, due to realocation or realignment of funds, the propose work, “Designand Management of Slope Protection” implementation has been realigned to Component-2 :Implementation Support. This activity covers consulting service for design and management ofslope protection. The revised Loan Category restructuring is presented in Table 2.4 and revisedimplementation is based on the approval of GOI and World Bank.
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
2 - 5
Tabel 2.4
Project Management Core Team Consultants (CTC)
The CTC will provide support to the PMU and DGH in the management of the Project, based inJakarta. Their tasks include financial and progress monitoring and reporting, informationmanagement and dissemination, quality assurance and performance review for the Design andSupervision Consultants, implementation and monitoring of the anti-corruption action plan,support for project monitoring and evaluation, and support for implementation of a trainingprogram to support project management and implementation. The CTC contract No. 06-20/CTC/TA/LN/8043/1112 was signed on 5 November 2012 by both DGH and a Joint Venture ofPT. Perentjana Djaja, Yongma Engineering Co,Ltd, and PT. Epadascon Permata EngineeringConsultant.
Design and Supervision Consultants (DSC)
A Design and Supervision Consultant (DSC) will be responsible for design of WP-2 and WP-3 civilworks and supervision of all civil works. They will have the role of ‘Engineer’ under a FIDIC-typecontract. The tasks include the preparation and maintenance of a quality assurance plan,validation and updating of designs, supervision of all civil works, environmental and socialmonitoring and management, and support for financial and progress monitoring and reporting.The DSC will also be responsible for quality assurance of materials and workmanship, certifyingwhether or not contractors have achieved the required results, as well as documentation andreporting based on the financial management plan. They will prepare a Quality Assurance systemcovering all subprojects, and continuously monitor the effectiveness of their supervisionprocedures. The team will be contracted and managed by DGH through the Bina Marga RegionalOffice (Balai II), and will be based in Padang, West Sumatera.
CategoryOriginal Amount ofthe Loan Allocated
(expressed in USD)
Revised Amountof the Loan
Allocated(expressed in
USD)
Percentage ofExpenditures to be
financed (inclusive ofTaxes)
(1) Civil Works under Part 1 of theProject WP-l 220,400,000 220,400,000 70%
(2) Goods, Non-consulting Services,Consultants Services andIncremental Operating Costs* underPart 2 of the Project
16,000,000 17,000,000 100%
(3) Goods, Non-consulting services andConsultants' Services under Part 3of the Project
1,000,000 Cancelled Cancelled
(4) Works, Goods, Non-ConsultingServices, Consultants' Services andIncremental Operating Costs* underPart 4 of the Project
0 0 100%
(5) Unallocated 12,600,000 12,600,000 100%T O T A L : 250,000,000 250,000,000
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
2 - 6
Project Component 3: Road Sector Institutional Development
This component will provide technical assistance and support to strengthen disaster risk mitigationin the road sector, including capacity building support for the new environment/risk mitigation androad safety unit of DGH to conduct disaster risk assessments and planning, risk mapping of land-slides, coastal erosion, earthquake and floods, and analysis of alternative designs for roadsegments that pass through critical environmental assets and vulnerable areas. In the meeting,DGH and World Bank agreed upon that DGH will conduct analytical work of an alternative designfor road segment that pass through critical environtmental assets and vulnerable areas especiallyon slope protection design and management. Due to deletion of the allocated funds for Category 3of the loan agreement and reallocated to Category 2 to accommodate the implementation ofslope protection design and management, into Component-2. The Proposal Loan Categoryrestructuring can be seen in Table 2.4 page 2-5.
Project Component 4: Contingency for Disaster Risk Response
This special component will provide preparedness and rapid response to disaster, emergencyand/or catastrophic events as needed. This provisional zero dollar component will be added underthis project to allow for rapid reallocation of loan proceeds from other components understreamlined procurement and disbursement procedures.
2.3 Project Objective
The main objective of the program will be to increase the effective use of selected sections ofNational roads along the Western Sumatera Corridor by reducing road user costs, throughimproving the National road network especially in 4 (four) Provinces of Sumatera (North Sumatera,West Sumatera, Bengkulu and Lampung) and, where desirable, raise the road standard to that setby the Directorate General of Highways. This will contribute significantly to ensuring that thenational road network in the region provides acceptable standards of service and accessibility, andis capable of supporting local and regional economic development.
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
3 - 1
3 CONSULTANCY SERVICES
3.1 CTC Consultants
3.1.1 Scope of Services
The CTC contract services originally were structured in its different project management elements.
Inception Phase
A key activity during the inception phase will be to establish lines of communication with PMU-WINRIP and DSC’s Team Leader as well as with all Provincial Project Managers (Satkers) wherethe first works are to be constructed under WP-1.
Project Management and Support to PMU, including acting DSC until the DSC is established
The Terms of Reference (TOR) identify a number of sub-items to be performed by CTC. The keyfactor that will ensure success is that the CTC must work pro-actively and alongside PMUcounterparts and with DSC team in a professional manner based on mutual respect and trust.
Preparation of Work Programs
The tendering process for WP 1 sub-projects began as soon as procurement committees havebeen formed and received appropriate training in the procurement procedures required. Theindicative work programs and cost estimates identified for WP-2 and WP-3 are subject toverification, and are likely to change following more detailed investigations. Furtherpreparation for WP-2 and WP-3 will be managed by the PMU supported by the CTC.
Financial Monitoring
It will be the role of the CTC to first assess the level of understanding of the financialmanagement, monitoring and reporting procedures by the finance staff at the provincial andcentral level and subsequently devise an appropriate training program and assist the PMU intraining delivery.
Project Progress and Performance Monitoring
CTC will monitor the loan project progress and prepare the report in monthly basis. In themeantime, GOI and the World Bank have agreed on a set of Key Performance Indicators (KPIs)to measure the project’s performance in achieving its stated development objectives. CTC willtherefore first concentrate on the establishment of precise definitions, calculation methodsand data collection procedures to monitor the KPIs.
Support for the Implementation of the ACAP
The CTC will assist PMU and be responsible for ensuring the ACAP is properly implemented
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
3 - 2
And for revising the Project Management Manual on an annual basis to incorporate necessaryimprovements to processes and procedure.
ESAMP and LARAP Implementation Monitoring
CTC will closely work with BLH and DSC and will monitor and report the action of theEnvironmental Management Plan on a periodical basis and/or as required.
Training to Support Project Implementation
CTC is responsible for preparation and management of all training program required underWINRIP.
Reporting
CTC is responsible for all reports required under the contract agreement with standardizeforms, charts and tables.
3.1.2 CTC Manning
CTC professional staffs involved in the project as of end of March 2016 are listed in Table 3.1.
The International Staff ( Senior Highway Engineer, Senior Road Safety Audit Engineer and SeniorProcurement Specialist) have completed their respective engagements and man-months havedemoblized on March 31, 2014 and May 31, 2015, respectively.
The task of conducting final Road Safety Audit during post-construction phase which is supposedto be done by the Senior Road Safety Audit Engineer will be performed by the local Road SafetyAudit Engineer with man-months for the task to be covered by Amendement No.4 of theConsultancy Contract.
With the exception of the three (3) international staffs who were demobilized earlier due tocompletion of their respective allocated man-months, the composition of the CTC professionalstaffs to date remain the same as during the previous month.
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
3 - 3
Table 3.1
40.00 - - Mahbub urRahman
- - - - A
- 35.25 12.25 12.25 12.25Per WeissPedersen
Apr-2013 Mar-2014 12,25 0,00 B
- - 23.00 23.00 44,83 C.T. Arenas Apr-2014 - 19,31 25,52
Senior HighwayEngineer
8.00 12.50 14.00 14.00 14,00Moon, Sung
HyungMar-2013 Mar-2014 14,00 0,00 C
Senior RoadSafety Audit
6.00 11.00 13.00 13.00 11,00 Cho, Woo Sung Jun-2013 Mar-2014 11,00 0,00 C
18.00 - -Wasim urRahman
- - - - A
- 16.00 16.00 16.00 16,00Sanjeev Kumar
AgarwalJan-2014 May-2015 16,00 0,00 C
40.00 9,67 9,67 9.67 9,67Besar Awiat
BowoNov-2012 Sep-2013 9.67 0,00 B
- 30,33 6,66 6.66 6,66 Agus Setiawan Sep-2013 Mar-2014 6,66 0,00 B
- - 23.67 23.67 45,50 Julius J. Sohilait Apr-2014 - 24,00 21,50
36.00 7,37 7,37 7.37 7,37 Whiliyanto Nov-2012 Jun-2013 7.37 0,00 B
- 28.40 28,63 32.13 38,96 Lebiyartono Jul-2013 - 32,97 5,99
QualityAssuranceEngineer
30.00 30.00 30.00 32.00 53,83Uray Abdul
ManafJul-2013 - 32,97 20,86
36.00 10.37 10.37 10.37 10,37 Uus Martawijaya Nov-2012 Oct-2013 10,37 0,00 B
- 25,63 25,63 29.13 50,96 YD Tarwanto Oct-2013 - 29,97 20,99
EnvironmentalSpecialist
30.00 30.00 30.00 38.50 60,33 Leti Hermawati Dec-2012 - 39,43 20,90
36.00 9,37 9.37 9.37 9,37 M. Sutopo Nov-2012 Oct-2013 9,37 0,00 B
- 26,63 26,63 30.13 39,96 Witono Sep-2013 - 30,93 9,03
12.00 - - Darmansiri - - - - A
- 12.00 12.00 Muhdi - - - - A
- - 12.00 7.00 7,00 Mardiansyah Jul-2014 Mar-2015 7,00 0,00 B
12.00 - 4.10 4.10 4,10 Rudi Rungkat Nov-2012 Mar-2015 4.10 0,00 B
- 24.00 24.00 35.40 40,23 M. Edhi Fachri Mar-2013 - 36,00 4,23
30 - - Agung Lukito - - - - A
- 25.00 25.00 34.00 55,83 Sony Thamrin May-2013 - 34,97 20,86
CommunityDevelopment
Officer 36.00 36.00 36.00 38.00 59,83 Yakobus Jan-2013 - 38,90 20,92
Road SafetyAudit Engineer
25.00 25.00 19.00 21.00 42,83Aditya Moraza
AlwiJun-2014 - 22,00 20,83
Bridge Engineer 5.00 5.00 5.00 5.00 5,00Harimurti
SuprihantoroApr-2013 Aug-2013 5.00 0.00 C
TrainingSpecialist
- 12.00 12.00 25.00 30,83 Roedjitarjo Jan-2014 - 25,00 5,83
Traffic Engineer - - - 1,00 7,00 Harianto Parman Mar-2015 - 1,00 6,00 DRemarks
A - Not able to mobilizied due to poor health or personal reasonsB - Resigned due to personal reasons or poor healthC - Task assigment completedD - Intermittent assignment to update AADT
RemarksAmendNo.3
MobilizedDemob-
ilized
Man - MonthUsed as of end of
March 2016
Man - MonthRemaining
NameAmendNo.4
OriginalContract
AmendNo.1
AmendNo.2
HighwayEngineer
POSITION
Team Leader
SeniorProcurement
Specialist
Assistant TeamLeader
Man - Months Duration
FinancialManagement
Specialist
Social ImpactSpecialist
ProcurementSpecialist-2
ManagementInformationSpecialist
ProcurementSpecialist-1
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
3 - 4
3.1.3 CTC Contract
The CTC contract for “Western Indonesia National Roads Improvement Project” (Contract No.06-20/CTC/TA/LN/8043/1112) was signed on 05 November 2012. The contract is between theGovernment of Indonesia represented by Directorate General of Highways in the Ministry of PublicWorks and PT. Perentjana Djaja in joint venture with Yongma Engineering Co.Ltd. and PT.Epadascon Permata Engineering Consultant.
The Notice To Proceed was issued by letter dated 6 November 2012 from the PPK, and the officialstarting date of the contract was set at 6 November 2012.
Likewise, Amendment No. 1 to the original contract was signed on 25 October 2013 to coverall requirements of the CTC are summarized below.
Replacement of the Senior Procurement Specialist Extending the assignment of the Senior Highway Engineer. Extending the assignment of the Senior Road Safety Audit Engineer. Extending the assignment of the Procurement Specialist 2 and replacement of the
Procurement Specialist 1. Adding the new position of Bridge Engineer. Adding the new position of Training Specialist, and Adding the new position of Road Safety Engineer.
Amendment No. 2 to the Original Contract and Amendment No. 1 was signed on September 3,2014 to cover requirements of CTC are enumerated as follows :
Additional / Modification to Terms of Reference (TOR) Amendment to the Team Composition and Staffing Schedule Replacement of Foreign and Local Consultants Adjustments of Remuneration paid in foreign currency and local currency Adjustment inputs of personnel Modification to various reimbursable and provisional sum to match the actual requirement
Amendment No.3 to the current CTC Contract (Original Contract and Amendments 1 and 2 wassigned on November 30, 2015 which is in line with the Updated Timeline Bar Schedule takinginto consideration the current and look ahead situations of the WINRIP program.
Based on the current progress of the Project, the services of several local professional and sub-professional staff have been extended beyond the end of the respective dates of completionassignments under Amendment No. 2.
In addition, new position of Traffic Engineer for local professional staff have been added toconduct traffic surveys on six (6) selected road links within the WINRIP Program in order toupdate the AADTs and to prepare a “Technical Analysis of the Annual Average Daily Traffic”.
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
3 - 5
Amendment No.3 covers the requirements of CTC are as follows :
Amendment to the team composition and staffing schedule Adjustment of inputs of personnel Adjustment of remuneration paid in local currency Adding the new position of Traffic Engineer Modification to various reimbursable to match the actual requirements.
Amendment No. 4 to the current CTC Contract (Original Contract and Amendements 1, 2 and 3)was signed on March 4, 2016 and to expire or completed on December 31, 2017, the some dateas the expiry/closing date of the loan agreement.
Based on the current progress of the Project, services of professional international and local staffas well as local sub-professional staff have been extended beyond their respective dates ofassignment engagement covered by Amendment No. 3.
Amendment No.4 covers the requirements of CTC are as follows :
Consultancy services time extension Additional/Modification to TOR/Terms of Reference Adjustment of input schedule for Professional Staff, Sub Professional and Supporting Staff Amendment to the Team Composition Amendment of the Staffing Schedule Modification to the Provisional Sums Adjustment of Remuneration paid in foreign currency and local currency Adjustment to the reimbursable expenses Amendment to Clause 6.1(b) of the Special Condition of Contract
Presented in Table 3.2 is the current status of CTC contract.Table 3.2
Description USD IDR
Original Contract including 10% VAT 1,404,370 23,556,940,000
Amendment No.1 including 10% VAT 1,447,517 24,668,792,500
Variance Against Original Contract +3,07% +4,72%
Combine Variance Against Original Contract +4.12%
Amendment No. 2 including 10% VAT 1,509,117 24,704,544,150
Variance Against Original Contract +7,46% +4,87%
Combine Variance Against Original Contract +5.81%
Amendment No.3 including 10% VAT 1,473,917 26,328,054,500
Variance Against Original Contract +4.95% +11.76%
Combine Variance Against Original Contract +9.29%
Amendment No. 4 including 10% VAT 1,918,158 40,878,169,529
Variance Against Original Contract +36.58% +73.53%Combine Variance Against Original Contract +60.12%
Note : Combine variance (USD+IDR) is based on 1 USD = Rp. 9,558 exchange rate used during thetime of signing the original Contract Agreement.
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
3 - 6
3.2 DSC Consultants
The Design and Supervision Consultant (DSC) is responsible to design of WP-2 and WP-3 civil worksand supervision of all civil works. They will assume the role of ‘Engineer’ under a FIDIC-typecontract. The tasks include the preparation and maintenance of a quality assurance plan,validation and updating of designs, supervision of all civil works, environmental and socialmonitoring and management, and support for financial and progress monitoring and reporting.The DSC is also be responsible for quality assurance of materials and workmanship, certifyingwhether or not contractors have achieved the required results, as well as documentation andreporting based on the financial management plan. They will prepare a Quality Assurance systemcovering all subprojects, and continuously monitor the effectiveness of their supervisionprocedures. The team is being contracted and managed by DGH through the Bina Marga RegionalOffice (Balai II), and is being based in Padang, West Sumatera.
DSC has been established in Balai II Padang following the contract signing on 11 June 2013between Balai II and Renardet SA in joint venture with PT. Cipta Strada, PT. Daya Creasi Mitrayasa,PT. Seecons and PT. Yodya Karya. The Notice To Proceed was issued by the Balai II on 19 June2013.
Shown in Table 3.3 is the present status of the Design Supervision Consultant (DSC) contract.
Table 3.3
Description USD IDR
Original Contract plus 10% VAT 902.660 57,000,575,500
Addendum No.1 plus 10% VAT *868.340 *62,436,542,901
Variance Against Original Contract *-3.80% *+9.54%Note :
1) Draft Addendum No.1 is still subject to approval by DGH with World Bank concurrence and issuanceof No Objection Letter (NOL).
2) Figures with asterisk (*) are tentative pending approval of Addendum No.1
3.3 Technical Assistance for Capacity Building for Disaster Risks Reduction
To be cancelled and replaced by “Technical Assistance for Study on Slope Stabilization Designand Management” (under Loan Cat-2) with funds for implementation to be taken from thereallocated funds from Category 3 of the Loan Agreement.
3.4 Technical Assistance for Capacity Building for Environmental Management
Cancelled
3.5 Technical Assistance for Capacity Building for Road Safety
Cancelled
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
4 - 1
4 CIVIL WORKS
4.1 Detailed Design Preparation
Final Engineering Designs, Engineer’s Estimates and bidding documents have been completed for allprojects proposed for WP-1, WP-2, WP-3.
A brief status of the nineteen (19) sub-projects relative to the procurement of Civil works contractsand implementation can be found in “Implementation Status” table on Page 1-1 of this Report.While progress of road safety audit are shown in Appendix B.
4.2 Procurements
Procurement shall be conducted under the Bank’s Procurement Procedures as mentioned in the LoanAgreement. The International Competitive Bidding (ICB) based on the Bank letter Ref. WINRIP/136 willapply to the packages with the construction estimated cost of more than US$ 25 Million to comply withthe new Bank’s threshold for ICB. According to the GOI regulation, a prequalification shall be applied forthe packages with the construction estimated cost more than IDR 10 Billion. Review from previousprocurement process, the World Bank in the Aide Memoire requested to GOI, for next 4 ICB subprojectsqualification still used Pre-Qualification and for remaining sub-project must be process with PostQualification. As well as for all NCB the World Bank also requested to follow Post Qualification inprocurement process.
As of this reporting month (March 2016), a more detailed current updates are fully indicated inSub-Chapter 1.4 Procurement of Civil Works Contract Under Category 1 on Page 1-5 of this Report .
Under Category 3 of Loan Agreement the three (3) consultancy packages (capacity building for disasterrisk reduction, environmental management and road safety) has been cancelled. As a result of thecancellation of the three (3) Technical Assistance, the “Technical Assistance for Study on StabilizationDesign and Management” has been included as replacement, but to be part of the Loan Category-2 ;
Procurement update of the new consultancy package can be found in Sub-Chapter 1.5 Procurement ofThree (3) Consultancy Packages Under Category 3 on Page 1-9 of this Report.
The WINRIP updated Procurement Plan and Progress are shown in Appendix F.
4.3 Civil Works Implementation
As of end of this reporting month (March 2016), there are currently eleven (11) contract packagesthat are under construction. Construction implementation of two (2) contract packages underAWP-1 program have recently been completed with the issuance of “Taking Over Certificates”(TOC) and are now currently under defects liability period for twenty four (24) months effective onthe day the TOC were issued.
Details of each contract package are shown in Table 4.1.
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
4 - 2
Table 4.1
ProgramContractPackage
#Contractor Name of Road Province Contract
Signed
Commencement of
Work
Original
TimeExtension
Revised
ContractAmount
ContractTime
CompletionDate Contract Amount Contract
TimeCompletion
Date
AWP-1
1 PT. Jaya KonstruksiManggala Pratama Tbk Biha - Krui Lampung Nov 25,
2013 Jan 8, 2014 134,909,211,000 640 CD Oct 9, 2015 93 CD 154,073,015,000 733 CD Jan 10, 2016
2PT.Jaya Konstruksi ManggalaPratama Tbk
Padang Sawah –Sp. Empat includingAir Gadang
WestSumatera Dec 6, 2013 Jan 6, 2014 197,936,699,000 730 CD Jan 5, 2016 105 CD 249,348,931,000 835 CD Apr 19,
2016
3 PT. Jaya KonstruksiManggala Pratama Tbk
Manggopoh –Padang Sawah
WestSumatera Dec 6, 2013 Jan 6, 2014 143,688,963,000 730 CD Jan 5, 2016 75 CD 183,940,872,000 805 CD Mar 20,
2016
4 PT. Waskita Karya and PT.Mulya Turangga (JO) Ipuh - Bantal Bengkulu Nov 14,
2013 Jan 13, 2014 186,936,750,000 730 CD Jan 12, 2016 90 CD 196,438,084,000 820 CD Apr 11,2015
AWP-2
5 PT. Nusa KonstruksiEnjiniring Tbk.
Sp. Rampa -Poriaha
NorthSumatera
March 17,2015
June 18,2015 107,321,260,310 540 CD Dec 8, 2016 - - -
6 PT. Waskita Karya (Persero)Tbk. Ps. Pedati - Kerkap Bengkulu Feb 27,
2015Mar 11,
2015 86,517,470,000 450 CD Jun 2, 2016 - - -
7 PT. Adhi Karya Indrapura – Tapan WestSumatera
Nov 26,2015
Dec 10,2015 129,699,900,000 630 CD Aug 30,
2017 - - -
8 PT. PP/PT. Statika MitraSarana J.O
Bts. Kota Pariaman- Manggopoh
WestSumatera Jan 28, 2016 Mar 23,
2016355,500,000,000 720 CD Mar 12,
2018 - - -
11 PT. Hutama Karya/PT. DayaMulya J.O.
Bantal –Mukomuko Bengkulu Dec 18,
2014Feb 23,
2015228,899,717,000 720 CD Feb 11,
2017 - 262,611,303,000 - -
12 PT. Lancar Jaya/PT. CahayaT.A. J.O
Kambang –Indrapura
WestSumatera Jan 28, 2016 Still to be
issued358,650,400,000 720 CD Still to be
determined - - -
13 PT. Waskita Karya (Persero)Tbk.
Sp. Rukis – TJ.Kemuning Bengkulu Dec 18,
2014July 22,
2015 292,700,000,000 720 CD July 10,2017 - - -
AWP-3
15 PT. PembangunanPerumahan (Persero)
Sibolga – Bts.Tapsel
NorthSumatera
July 13,2015
Nov 20,2015 260,100,000,000 810 CD Feb 6, 2018 - - -
17 PT. Jaya KonstruksiManggala Pratama Tbk
Sp. Gunung Kemala– Pugung Tampak Lampung Nov 17,
2014 Sept 4, 2015 199,551,000,000 720 CD Aug 23,2017 - - -
19 PT. Roda Tekindo Purajaya Bintunan - Lais Bengkulu Feb 27,2015
Mar 11,2015 33,689,452,000 300 CD Jan 4, 2016 125CD 44,419,760.000 425CD May 8, 2016
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
4 - 3
4.4 Civil Works ProgressActivities done during this month were repair and restoration of deteriorated existing pavements, roadwayexcavation, embankment formation, spreading of granular pavement for roadway widening, asphalt paving,structural works, construction of stone masonry side ditches, stockpiling of raw material, production ofcrush aggregates, other minor works, bridge construction and finalization of “Field Engineering”surveys.
The four (4) contract packages under implementation program AWP-1 were not completed on the originaltarget dates of completion, however, time extensions ranging from 15 to 125 calendar days were grantedextending the completion dates at the earliest on January 10, 2016 and the latest on April 19, 2016.
Physically, two (2) of the contract packages has already been fully completed and recently handed andtaken over by the Client, while the two (2) other packages are about to be completed next month (April2016).
Under the implementation program AWP-2 and AWP-3, there are currently eight (8) contract packages thatare on-going construction implementation and one (1) contract package have just been issued Notice ToProceed (NTP) to commence works. Physical progress of two (2) of the packages are lagging far behindschedule with negative slippages of -42.77% and -57.81% while progress for the other six (6) packages arestill slightly on or behind schedule.
Generally, with the exception of the two (2) contract packages with huge negative slippages, the civil worksimplementation is fairly in the right direction.
Progress status of the thirteen (13) on-going civil works contracts as of this reporting period are shown inTable 4.2.
Following are brief status of the Thirteen (13) on-going construction contract packages :
Package No. 1 : Biha – KruiThe contract package is substantially completed on January 20, 2016 and provisionally handed over to theEmployeer.
Taking Over Certificate of the Works has been issued by the Engineer on the same day of the ProvisionalHand Over (PHO) which is also the starting date for “Defects Notification Period” until after two (2) yearsreckoned from the issuance of the TOC.
A more detailed previous status of this Package is presented in ANNEX P-I Executive Summary Report.
Package No. 2 : Padang Sawah – Sp. Empat (Including Air Gadang Bridge)As the end of this reporting period, the overall work progress based on the revised schedule is 96.83% withat least 3% of the works still to be done until the revised expiry of the completion time.
To date, the remaining 25 calendar days left from the revised extended construction period is more thanenough for the Contractor to complete the remaining works until the revised take over date on April 19,2016, but this will depend with the progress and completion of Air Gadang Bridge.
With regard to the construction of Air Gadang Bridge, all the 20 pre-cast girders required were launched inplace and two (2) spans out of the four (4) spans of bridge deck has been casted during the month of March2016. Construction of approach roads are also on-going during the period.
ANNEX P-2 Executive Summary Report present a more detailed status of the Contract Package.
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
4 - 4
Table 4.2
ProgramContractPackage
#Contractor Name of Road
Target ProgressSchedule Ending
March 2016
Actual ProgressAccomplished Slippage Time
ElapsedRemaining
Time Remarks
AWP-1
1 PT. Jaya KonstruksiManggala Pratama Tbk Biha - Krui - - - - - Completed
PHO : Jan 20, 2016
2PT. Jaya KonstruksiManggala Pratama Tbk
Padang Sawah –Sp.Empat incl.AirGadang
98.21% 96.83% -1.37% 97.00% 25 CDBased on revised scheduledue to approved timeextension.
3 PT. Jaya KonstruksiManggala Pratama Tbk
Manggopoh –Padang Sawah 100% 100% - - -
CompletedPHO : Mar 17, 2016
4 PT. Waskita Karya and PT.Mulya Turangga (JO) Ipuh - Bantal 96.29% 91.62% -4.67% 97.92% 17 CD
Based on revised scheduledue to approved timeextension.
AWP-2
5 PT. Nusa KonstruksiEnjiniring Sp. Rampa - Poriaha 52.88% 10.11% -42.77% 52.13% 258 CD Based on original contract
time and schedule
6 PT. Waskita Karya Tbk Ps. Pedati - Kerkap 85.36% 27.55% -57.81% 84.44% 70 CDBased on original contracttime and schedule
7 PT. Adhi Karya Indrapura - Tapan 0.58% 0.73% +0.14% 16.85% 523 CDBased on original contracttime and schedule
8 PT. PP/PT. Statika MitraJ.O
Bts. Kota Pariaman –Manggopoh Not Available Not Available - 1.25% 711 CD
Schedule still to beprepared
11 PT. Hutama Karya/ PT.DMT Mukomuko - Bantal 43.85% 38.87% -4.98% 55.08% 323 CD
Based on original contracttime and schedule
13 PT. Waskita Karya(Persero) Tbk
Sp. Rukis – Tj.Kemuning 26.94% 14.62% -12.32% 34.35% 472 CD
Based on original contracttime and schedule
AWP-3
15 PT. PembangunanPerumahan (Persero) Sibolga – Bts. Tapsel 5.57% 1.69% -3.88% 15.57% 683 CD
Based on original contracttime and schedule
17 PT. Jaya KonstruksiManggala Pratama Tbk
Sp. Gn Kemala – Pg.Tampak 6.10% 6.16% +0.06% 28.23% 516 CD
Based on original contracttime and schedule
19 PT. Rodatekindo Purajaya Lais - Bintunan 79.68% 80.78% +1.10% 89.62% 44 CDBased on revised scheduledue to approved timeextension.
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
4 - 5
Package No. 3 : Manggopoh – Padang SawahThe contract packages is substantially completed some few days before the target date of completion onMarch 20, 2016 and provisionally handed over to the Employeer on March 17, 2016.
Taking Over Certificate of the Works has been issued by the Engineer on the same day of the ProvisionalHand Over (PHO) which is also the starting date for “Defects Notification Period” until after two (2) yearsreckoned from the issuance of the TOC.
Based on the submitted progress report, there were quantity overruns on most of the major work itemssuch as earthworks (3.95%), asphalt pavement (3.91%) and structures (4.48%).
A more detailed status of the project progress are shown in ANNEX P-3 “Executive Summary Report”.
Package No. 4 : Ipuh – BantalAlthough the Contractor has been granted time extension of completion from January 9, 2016 to April 11,2016, the current status of this contract package still remain in critical situation with respect to the revisedcompletion date.
During this period (March 2016), the actual overall progress is 91.62% with still 8.38% of the work still to becompleted.
Based on the Contractor’s performance during the course of the contract, it seems doubtful that theremaining 8.38% of the works can be completed on the target date of completion, considering that only 17calendar days are remaining to complete the balance of the works.
Shown in ANNEX P-4 “Executive Summary Report” showing the details and status of the project.
Package No. 5 : Sp. Rampa – Poriaha
To date, since the commencement of works started nine (9) and half months ago, the actual physical workprogress is only 10.11% against scheduled work progress of 52.88%. The delayed works furtheraccumulated to -42.77% at the end of this month.
With only 48% or eight (8) months of contract time are left and a huge deficit of unfinish work of 90% to bedone, the target of completion on December 8, 2016 may never be attained unless drastic actions from thepart of the Contractor will be enforced.
Other problem that hampered the slow progress of the works which shall be addressed immediately by theconcerned authorities is the unexpected ROW problems wherein some improvements such as trees andother obstructions exist along the alignment.
Considering that the current problems are resolved anytime soon and in order for the Contractor to catch-up with the schedule to meet the completion date, at least 11% progress per month have to be achieved.
ANNEX P-5 “Executive Summary Report” shows the Contractor’s Progress Schedule.
Package No. 6 : Kerkap – Ps. Pedati
Based on the original progress schedule ending March 2016, the actual overall physical work accomplishedis 27.55% out of 85.36% schedule or -57.81% negative slippage. Works during the month were veryminimal and were mainly focused on Asphalt Pavement and Routine Maintenance Work items.
As the period ended, 72% of the works still remain to be done while 84% of the contract time have already
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
4 - 6
elapsed and based on the Contractor’s performance and average progress per month during the past 13months, completion date on June 2, 2016 is not possible.
The major work item which conributed to the huge negative slippage is the Aspahalt Pavement. To dateonly 9.10% out of the 70.65% component of whole works has been accomplished.
However, in the event that the recently concluded “Field Engineering” results with proposed 90 calendardays time extension will be formally approved, the completion date will be moved forward to August 31,2016.
ANNEX P-6 “Executive Summary Report” shows the complete details of the contract package.
Package No. 7: Indrapura – Tapan
The contract package just recently commenced on December 10, 2016.
During the period from the issuance of Notice To Proceed (NTP) until end of this month, Contractorconcentrated on the preparation for mobilization at site and finalization of the Field Engineering.
During the period only small percentages of the General, Structure and Routine Maintenance works havebeen done accumulating to just 0.14% progress for the whole month
ANNEX P-7 “Executive Summary Report” shows the complete details of the contract package.
Package No. 8 : Bts. Kota Pariaman - ManggopohNotice To Proceed (NTP) to commence the works has been issued on March 23, 2016.
At the time of the preparation of this Report, there is still no work schedule (S-Curve) submitted by theContractor.
Package No. 11 : Bantal - MukomukoBased on the revised schedule due to approval of the results of “Field Engineering”, the actual overallprogress attained by the Contractor up to end of this period is 38.87% against 43.85%.
At the end of the 13th month of the contract period, Contractor’s performance with respect to their workprogress seem to be satisfactory as the negative slippage have been minimized to a single digit. In otherwords, the Contractor have no difficulty in completing the works on or before the target date completionFebruary 11, 2017.
For more details of the Contract Package, refer to ANNEX P-11 “Executive Summary Report”.
Package No. 13 : Sp. Rukis – Tj. KemuningThe current work progress showed sign of slowing down for the past three (3) months as only 0.24%progress has been achieved during this period.
At the end of the month, the overall work accomplished is 14.62% of the 26.94% schedule at month’s end.The negative slippage suddenly dropped from -5.99% in the preceeding month to -12.32% this month.
The negative slippage is still manageable at the moment, provided the Contractor will take immediateactions on problems that are hampering the work progress. Barring any unforseen circumstances that willdisrupt or interrupt the construction implementation, it is expected that the project can be completed on-time or even ahead of the schedule.
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
4 - 7
Details of the work progress are shown in ANNEX P-13 “Executive Summary Reports.
Package No. 15: Sibolga – Bts. Tapsel
The contract package just recently commenced on November 20, 2015.
During the period from the issuance of Notice To Proceed (NTP) until end of this month, Contractorconcentrated on the preparation for mobilization at site .
At the end of this reporting month (March 29, 2016) actual overall progress achieved is 1.69% of the 5.57%schedule for the end of the month. During the month, the Contractor mainly concentrated on mobilizationto site and minor roadworks on Drainage, Earthworks, Structures and Reinstatement and Minor Works.
Detailed and work progress of the contract package are shown in ANNEX P-15 “Executive SummaryReport”.
Package No. 17 : Sp. Gunung Kemal – Pg. TampakThe current status of the sub-project is fairly being implemented as evidenced by not incurrring anynegative slippage since the Contractor commenced works way back in September 4, 2015.
Overall progress to date is 6.16% against 6.10% schedule, or the progress is slighty ahead of schedule by+0.06%.
If Contractor can maintain the trend of their monthly progress, there is no reason that the works could notbe completed on or before the target date of completion on August 23, 2017.
ANNEX P-17 “Executive Summary Report” shows the complete details and work progress of the project.
Package No. 19 : Lais – BintunanBased on corrected revised progress schedule by incorporating the results “Field Engineering”and 125calendar days time extension, the progress of work have considerably improved as compared in theprevious months.
At the end of the period, the total overall progress attained is 80.78% against 79.68% schedule or +1.10%ahead of schedule.
During the month, only Asphalt Pavement item have be done with an output of 3.45%.
Complete details of the contract package are shown in ANNEX P-19 “Executive Summary Report”
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
4 - 8
4.5 Quality AssuranceThe DSC will be responsible for quality assurance of materials and workmanship, certifying whether or notcontractors have achieved the required results, as well as documentation and reporting based on thefinancial management plan. They will prepare a Quality Assurance system covering all subprojects, andcontinuously monitor the effectiveness of their supervision procedures.
Following are current problems which were the same problems during the preceeding month and issues
relative to the execution of the works and quality assurance:
Package No.1 : Krui - Bihaa) Taking Over Certificate issued on January 20, 2016. Howwever, the Defects Notification Period
expiry date have to be corrected from January 19, 2017 to January 19, 2018.b) Non-comformance findings during road quality inspection by TFAC specifically on stone masonry
works, drainage system, implementation of road safety, erosion control and road side slopeprotections have not yet been officially closed out.
Package No.2 : Padang Sawah – Sp. Empata) Late start of Air Gadang Bridge will have considerable impact on the target date of completion if the
bridge is not completed within revised contract period.b) Non-comformance findings during road quality inspection by TFAC specifically on stone masonry
works, drainage system, implementation of road safety, erosion control and road side slopeprotections have not yet been officially closed out.
c) Separate design for side cut slope protection shall be implemented as soon as possible.
Package No.3 : Manggopoh – Padang Sawaha) Separate design for side cut slope protection have to implemented as soon as possible.b) Non-comformance findings during road quality inspection by TFAC specifically on stone masonry
works, drainage system, implementation of road safety, erosion control and road side slopeprotections have not yet been officially closed out.
c) Taking Over Certificate issued on March 17, 2016 with Defects Notification to end on March 17,2018.
Package No.4 : Ipuh - Bantala) Big percentage of works are still to be done during the remaining period until the end of the
extended completion time.b) Non-comformance findings during road quality inspection by TFAC specifically on stone masonry
works, drainage system, implementation of road safety, erosion control and road side slopeprotections have not yet been officially closed out.
Package No.5 : Sp. Rampa - Poriahaa) Field Engineering still to be finalized.b) Contractor to prepare and implement catch-up schedule to reduce the huge progress negative
slippage.
Package No.6 : Ps. Pedati - Kerkapa) Field Engineering shall be completed as soon as possible.
Package No.7 : Indrapura - Tapana) Contractor have to start “Field Engineering’surveys.
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
4 - 9
Package No.11 : Bantal - Mukomukoa) Field Engineering has been done and approved by DGH on October 28, 2015.
Package No.13 : Sp. Rukis – Tj. Kemuninga) Contractor to finalize Field Engineering.
Package No.15 : Sibolga – Bts. Tapsela) Field Engineering and Technical Justifications are still to be finalized.
Package No.17 : Sp. Gn. Kemala – Pugung Tampaka) Field Engineering and Technical Justification are still to be finalized
Package No.19 : Lais - Bintunana) Exisisting roadway embankment settlement shall have appropriate technical solution.b) Non-comformance findings during road quality inspection by TFAC specifically on stone masonry
works, drainage system, implementation of road safety, erosion control and road side slopeprotections have not yet been officially closed out.
4.6 Environmental and Social Considerations
4.6.1 Current Overall Situation
A project category is assigned to each package as either Category A, B or C depending on the likely degreeof influence on environmental issues with a brief explanation as follows:
Category A project is one which will have a significant negative impact on the environment and may havean influence on areas outside the actual project area. A project classified as such requires an AMDAL(ANDAL, RKL/RPL) study.
Category B project is one which affects the people or the environment to some extent but with a smallerimpact than a Category A. The required environmental analysis is a UKL/UPL study only.
Category C project has minimal effect on the people or environment and an environmental analysis is notrequired. SPPL are used to handle any minor problem which may arise.
Details of packages that require environmental and social safeguard are given in Appendix E and thefollowing Table 4.3 provides a summary of the work involved in the 19 WINRIP packages.
All the nineteen (19) packages require environmental impact investigations and studies which need theapproval by Environmental Agency (BLH).
Nine (9) of the nineteen (19) packages are categorized under “Category A” projects wherein AMDAL/EIAstudies are required and have to be approved by World Bank. The nine (9) packages are covered only byfive (5) AMDAL/EIA studies as some single study covers a combination of two (2) or three (3) sub-projects asindicated in Table 4.3. While 19 social studies (SLARAP and LARAP) require the approval of the World Bank.To date, all the 20 environmental studies for the nineteen (19) sub-projects including a separate study(UKL/UPL) for Air Gadang Bridge on Package No.2 were approved by BLH with 5 of these studies(AMDAL/EIA) were granted No Objection Letter (NOL) from the World Bank while all the 19 social studies(LARAP) were already issued No Objection Letter (NOL) from the World Bank.
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
4 - 10
Table 4.3Works
ProgramNo of
PackagesNo of Investigations Approval by Remarks
BLH World Bank
AWP-1 4 9
1 - AMDAL
2 - UKL&UPL
2 - SPPL
4 - Full LARAP
1 - AMDAL
2 - UKL&UPL
2 - SPPL
1 - EIA
No Need
No Need
4 - Full LARAP
Coverage of SingleAMDAL/EIA study are thefollowing Packages :
a) Packages 1 and 17
b) Package 7,12 and 14
c) Package 11 and 16
d) Package 8
e) Package 10AWP-2 9 18
5 - AMDAL
4 - UKL&UPL
1 - Simple LARAP
8 - Full LARAP
5 - AMDAL
4 - UKL&UPL
4 - EIA
No Need
1 - SLARAP
8 - Full LARAP
AWP-3 8 16
3 - AMDAL
5 - UKL&UPL
8 - Full LARAP
3 - AMDAL
5 - UKL&UPL
1 - EIA
No Need
8 - Full LARAP
Total 21 43 Env=22,Soc=21 22 Env= 5, Soc=21
Note: 1) UKL & UPL do not need a NOL from WB, and SPPL not necessary to submit to the WB.
2) Packages 9 and 18 are cancelled, but investigations and studies were already done and completed prior to cancellation.
3) Air Gadang Bridge have separate investigation, hence, total equals 22.
Appendix E shows the Progress of Environmental Safeguard Studies.
4.6.2 Environmental and Social Issues
This section outlines the activities of the Social Impact Specialist and the Environmental Specialist duringMarch 2016.
4.6.2.1 Environmental Issues
The main environmental issues, are the implementation of mitigating measures on pollution of spilled oil,grease and solid waste in the Contractors Base Camps. Air and dust pollution along stretches of thicklypopulated areas are not properly addressed by the Contractors. Water spraying is not continuouslyimplemented. Dump trucks transporting construction material are not fully covered and trafficmanagement plan is not fully implemented. In addition there exist negative impact on the quarryingoperations as existing river banks are eroded causing water pollutions. Deep excavation at the quarry siteswere not restored to its original level.
Monitoring of Environmental Aspects During Construction
CTC provided revised monitoring forms to DSC and Contractor for use in monitoring of environmental andsocial impacts. These forms are to be used every month by the DSC Site Engineers because of no availableDSC, Environmental Specialist.
CTC’s environmental staffs actively advises DSC on environmental monitoring, DSC have directly carried outmonitoring or to implement the Environmental and Social Analysis Management Plan (ESAMP) for WINRIP.
CTC’s Environment Specialist monitored the implementation of environmental mitigations during themonth of March 2016 and the following were observed :
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
4 - 11
Package No.1 : Krui – Biha
a) The quarry areas not manage by the supplier, as deep excavation areas were not yet restored tooriginal levels.
b) The supplier did not implement UKL&UPL of Quarry
c) The monitoring report prepared by the DSC site supervision team lack some necessary informationssuch as; photograph not provided, remarks not filled up.
d) External monitoring to BLH for UKL/UPL implementation on post construction stage still have to beprepared by CTC.
Package No.2 : Pd. Sawah – Sp. Empat and Air Gadang Bridge
a) Construction of the Air Gadang Bridge have impact on the activities of the resident living nearby theconstructions site, such activities as laundry chores, fetching of water for daily use and otheractivities related to the use of the river.
Contractor shall apply for standard operating procedure for bridge management construction.
b) The monitoring report prepared by the DSC site supervision team lack some necessary informationssuch as; photograph not provided, remarks not filled up.
c) Relationship and coordination by the contractor with the local residents shall be maintained in adiplomatic approach to prevent complains and unrest.
d) The quarry areas not manage by the supplier, as deep excavation areas were not yet restored tooriginal levels.
Package No.3 : Manggopoh – Pd. Sawah
a) Oil and grease pollution in the workshop at base camp were not properly managed as perEnvironmental Management Plan.
b) The monitoring report prepared by the DSC site supervision team lack some necessary informationssuch as; photograph not provided, remarks not filled up.
c) The quarry areas not manage by the supplier, as deep excavation areas were not yet restored tooriginal levels.
Package No.4 : Ipuh - Bantal
a) Oil and grease pollution in the workshop at base camp were not properly managed as perEnvironmental Management Plan.
b) Roadway excavations along the existing shoulders were provided with barriers, road signs andflagmen.
c) The quarry areas not manage by the supplier, as deep excavation areas were not yet restored tooriginal levels.
Package No.5 : Sp.Rampa - Poriaha
a) Traffic management plan is not implemented as there were no road barriers, traffic signs andflagmen on sight at the project site.
b) Roadworks on some sections cannot get started due to land acquisition problems
c) The quarry areas not manage by the supplier, as deep excavation areas were not yet restored tooriginal levels.
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
4 - 12
Package No.6 : Ps. Pedati - Kerkap
a) Oil and grease pollution at base camp not properly managed.
b) Roadway excavations along the existing shoulders were not provided with barriers, road signs andflagmen.
c) Roadway excavations along the existing shoulders are left open and not provided with barriers andwarning signs.
d) Monitoring Report prepared by DSC site supervision team is incomplete. Important imformationsand photographs were not provided.
Package No.11 : Ipuh - Bantal
a) The quarry location is not inside the protected areas but located on APL (Area Peruntukan Lain)with approximate total area of 4 hectares..
b) The quarry areas not manage by the supplier, as deep excavation areas were not yet restores tooriginal levels.
Package No.13 : Sp. Rukis – Tj. Kemuning
a) The quarry areas not manage by the supplier, as deep excavation areas were not yet restored tooriginal levels.
b) Quarrying operations has been temporarily suspended due to complains from NGO, hence,implementation of the works is being delayed.
Package No.15 : Sibolga - Bts Tapsel
a) Permits to operate stone crusher, asphalt mixing plant (AMP), material quarries and generator setsnot yet issued.
b) Traffic management plan is not implemented as there were no road barriers, traffic signs andflagmen on sight at the project site.
c) Roadworks on some sections cannot get started due to land acquisition problems
d) The quarry areas not manage by the supplier, as deep excavation areas were not yet restored tooriginal levels.
e) Contractors have not yet submitted the revised RKPPL.
Package No.17 : Sp. Gn. Kemala – Pugung Tampak
a) Base Camp has been built on a top of a hill which is potentially prone to landslide.
b) Contractor have not yet submitted RKPPL.
c) AMP, Stone Crusher and Quarry permits on-going proceesing at the Governor’s Office.
Package No.19 : Lais - Bintunan
a) Traffic management plan is not implemented as there were no road barriers, traffic signs andflagmen on sight at the project site.
b) Roadway excavations along the existing shoulders were not provided with barriers, road signs andflagmen
c) The base camp condition very poor for worker, very dirty, bad, smell, building damage not feasiblefor living worker.
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
4 - 13
d) The quarry areas not manage by the supplier, as deep excavation areas were not yet restored tooriginal levels.
As of this writing, DSC Site Supervision Team have not yet submitted the environmental monitoring reportfor March 2016.
1. Review Design Integration, Road Safety Aspects and Monitoring of Environmental Studies
Task 5.8.0 of CTC-2 TOR (Implement the Environmental and Social Analysis Management Plan/ESAMP) andparagraph 10.9 of the PMM requires ensuring that environmental management aspects of contracts havebeen implemented in accordance with AMDAL, UKL&UPL, SPPL studies and Environmental issues will beintegrated in the design and to prepare environmental mitigation on construction stage for contractor(Contractor Program for Executing Environmental Management Plan CPEMP/RKPPL). CTC has submitted toPMU all of reports of Review Integration AMDAL,UKL&UPL and SPPL.
2. External Monitoring Report (Satker/PPK to BLH) for Implementation of AMDAL/UKL&UPL/SPPL onPre Construction Phase, Construction Phase and Post Construction Phase.
The First (1st) External Monitoring during construction phase of Packages 5, 6, 7, 11, 13, 15 and 19 for BLHare preparation and the reports are expected to be submitted by end of next month.
3. The Contractor Action Plan on Environmental Management and Monitoring (RKPPL)
RKPPL for Packages No.5:Sp.Rampa-Poriaha, No.15: Sibolga-Batas Tapsel and No.17: Sp.Gn.Kemala-PgngTampak are under revision by the Contractors based review by CTC.
For remaining packages RKPPL will be prepared upon construction starts.
4. Environmental Quarterly Report
Environmental Quarterly Reports for the period January to March 2015 covering all packages that arecurrently under construction are on-going prepaation.
5. Socialization of HIV-AIDs Campaign
The socialization of HIV-AIDS activities on ten (10) contract packages has been completed. The packagescovered are as follows :
Package No.1 : Krui – Biha November 10, 2015
Package No.2 : Padang Sawah – Sp. Empat November 17, 2015
Package No.3 : Manggopoh – Pd. Sawah November 17, 2015
Package No.4 : Ipuh – Bantal December 4, 2015
Package No.5 : Sp. Rampa – Poriaha January 27, 2016
Package No.11: Bantal – Mukomuko December 5, 2015
Package No.13 : Sp. Rukis – Tj. Kemuning January 19, 2016
Package No.15 : Sibolga – Bts. Tapsel January 28, 2016
Package No.19 : Lais – Bintunan January 13, 2015
Presented in Attachment No.1 is the Summary of Studies and Submitted Reports ending March2016.
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
4 - 14
4.6.2.2 Social Issues
1. Monitoring Report of the LARAPPackage No. 1 : Krui – BihaProvince : Lampung
A. Previous Status :
LARAP implementation documents approved by World Bank on January 4, 2013
Monitoring Report No.1 (revised) approved by World Bank on June 26, 2013
Monitoring Report No.2 approved by World Bank on October 20, 2015.
B. Pending Issues, Concern and Actions
a) Certification process of the PAP land being resolved by Satker PJN II Lampung
C. Update during this reporting month of March 2016
a) Construction completed in January 20, 2016.
b) Total PAP = 2,815 ; Compensated = 2,815 ; Percent complete = 100%.
2. Monitoring Report of the LARAPPackage No. 2 : Padang Sawah – Sp. EmpatProvince : Sumatera Barat
A. Previous Status :
LARAP documents approved by World Bank on January 13, 2013
Monitoring Report No.1 (revised) approved by World Bank on July 19, 2013
Additional LARAP Implementation documents approved by World Bank on July 21, 2014
Monitoring Report No.2 approved by World Bank on Feb. 12, 2015
B. Pending Issues, Concern and Actions
a) Compensation for 24 PAP along the road link is under compensation payment process byLocal Government of West Sumatera Province
b) Price negotiation between the Land Acquisition Committee and the remaining 1 PAP alongAir Gadang Bridge is still to be finalized.
C. Update during this reporting month of March 2016
a) On-going construction
b) Total PAP = 467 ; Compensated = 442 ; Percen complete = 94,65%.
c) No update this period
3. Monitoring Report of the LARAPPackage No. 3 : Manggopoh – Padang SawahProvince : Sumatera Barat
A. Previous Status :
LARAP documents approved by World Bank on January 4, 2013
Monitoring Reports No.1, 2, 3, 4 and 5 already approved and World Bank issued No ObjectionLetter (NOL).
Monitoring Report for the remaining 1 PAP already submitted to WB
B. Pending Issues, Concerns and Actions
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
4 - 15
a) No more issue.
C. Update during this reporting month of March 2016
a) Construction completed on March 17, 2016.
b) Total PAP = 1,338 ; Compensated = 1,338 ; Percen complete = 100%.
4. Monitoring Report of the LARAPPackage No. 4 : Ipuh – BantalProvince : Bengkulu
A. Previous Status :
LARAP documents approved by World Bank on December 10, 2012
Monitoring Report No.1, 2 and 3 already approved and No Objection Letter (NOL) were issued byWorld Bank
B. Pending Issues, Concern and Actions
a) No more issue.
C. Update during this reporting month of March 2016
a) On-going construction.
b) Total PAP = 257 ; Compensated = 257 ; Percent complete = 100%.
5. Monitoring Report of the LARAPPackage No. 5 : Sp. Rampa – PoriahaProvince : Sumatera Utara
A. Previous Status :
LARAP documents approved by World Bank on September 16, 2013.
World Bank accepted the revised LARAP documents and issued No Objection Letter on November12, 2013 to the action plan implementation of the LARAP.
Additional LARAP documents approved by World Bank on January 8, 2016.
B. Pending Issues, Concern and Actions
a) Still to be submitted is the implementation report from Satker of the completed relocationof the kiosk.
b) Compensation payments for 71 PAPs not yet paid by Satker PJN II North Sumatera.
c) Monitoring Report for the LARAP implementation of the completed relocation of the kioskstill to be prepared for submission to World Bank.
C. Update during this reporting month of March 2016
a) No update this period.
b) Total PAP = 71 ; Compensated = nil ; Percent Complete = 0%.
6. Monitoring Report of the LARAPPackage No. 6 : Pasar Pedati - KerkapProvince : Bengkulu
A. Previous Status :
World Bank issued on May 30, 2015 a No Objection Letter on the revised LARAP documents forimplementation.
Monitoring Report concerning the compensation payment for 546 out of 637 PAP was given No
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
4 - 16
Objection Letter (NOL) on March 23, 2015.
Monitoring Report regarding compensation payment for the remaining 91 PAPs out of 637 PAPswas given No Objection Letter (NOL) on January 5, 2016.
B. Pending Issues, Concern and Actions
a) Certification process for 136 plots still to be finalized.
C. Update during this reporting month of March 2016
a) On-going construction.
b) Total PAP = 637 ; Compensated = 637 ; Percent complete = 100%.
c) No update for certification process of PAP lands.
7. Monitoring Report of the LARAPPackage No. 7 : Indrapura - TapanProvince : Sumatera Barat
A. Previous Status :
LARAP documents approved by World Bank on October 14, 2014.
Implementation action plan of the LARAP was issued No Objection Letter (NOL) on March 17,2015 by the World Bank.
B. Pending Issues, Concern and Actions
a) Compensation payment for 220 from total 885 PAPs is under payment preparation byPPK/Satker PJN Il West Sumatera.
C. Update during this reporting month of March 2016
a) A report of the compensation payment for 276 from total 885 PAPs already submitted toWorld Bank on February 9, 2016 and No Objection Letter (NOL) was issued on March 16,2016.
b) PMU/CTC waiting for data of payment progress for 389 PAPs from Satker PJN ll WestSumatera.
c) Total PAP = 885 ; Compensated = 665 ; Percent Complete = 75,14%.
8. Monitoring Report of the LARAPPackage No. 8 : Bts. Pariaman - ManggopohProvince : Sumatera Barat
A. Previous Status :
LARAP documents submitted to World Bank on August 7, 2014.
LARAP documents approved by World Bank on August 12, 2014.
1,203 of the total 1,736 PAPs already paid by Local Government and Monitoring Report for thepayment of 840 PAPs has been submitted to World Bank on January 14, 2016 and No ObjectionLetter (NOL) issued on March 8, 2016.
B. Pending Issues, Concern and Actions
a) Compensation payment for the remaining 283 PAPs not yet paid by PPK/Satker PJN I WestSumatera and Local Government.
C. Update during this reporting month March 2016
a) A report of the compensation payment progress for 613 is under preparation by Satker PJNI Sumatera Barat/CTC.
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
4 - 17
b) PPK/Satker PJN I West Sumatera and Local Government continue payment proceessing ofthe remaining PAP.
c) Total PAP = 1,736 ; Compensated = 1,453 ; Percent complete = 83,70%.
9. Monitoring Report of the LARAPPackage No. 9 : Rantau Tijang – Kota AgungProvince : Lampung
Cancelled from the WINRIP Program.
10. Monitoring Report of the LARAPPackage No. 10 : Sp. Empat – Sp. Air BalamProvince : Sumatera Barat
A. Previous Status :
LARAP documents submitted to World Bank on August 7, 2014.
LARAP documents approved by World Bank on August 12, 2014.
Compensation payments for 1,615 from the total 2,951 PAPs already paid and Monitoring Reportfor payment of 1,421 PAPs has been submitted to World Bank on January 14, 2016 and Bankissued No Objection Letter (NOL) on March 8, 2016.
B. Pending Issues, Concern and Actions
a) Payments for the remaining 1,190 PAPs not yet paid by PPK/Satker PJN I West Sumateraand Local Government.
C. Update during this reporting month of March 2016
a) Monitoring Report for payment of 138 PAPs on-going preparation by Satker PJN I SumateraBarat/CTC.
b) PPK/Satker PJN I West Sumatera and Local Government continue payment proceessing ofthe remaining PAP.
c) Total PAP = 2,915 ; Compensated = 1,725 ; Percent complete = 59,18%.
11. Monitoring Report of the LARAPPackage No. 11 : Bantal - MukomukoProvince : Bengkulu
A. Previous Status :
World Bank issued on May 30, 2014 a No Objection Letter (NOL) on the revised LARAP documentsfor implementation.
Monitoring Report No.1 and No.2 were issued No Objection Letters (NOL) from the World Bank.
Monitoring report for 15 of the remaining 123 PAPs was given No Objection Letter (NOL) onNovember 26, 2015
B. Pending Issues, Concern and Actions
a) No more issue.
C. Update during this reporting month of March 2016
a) Data collection for payment progress of the remaining 108 PAPs is being done by SatkerPJN l Bengkulu.
b) Total PAP = 262 ; Compensated = 262 ; Percent complete =100%.
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
4 - 18
12. Monitoring Report of the LARAPPackage No. 12 : Kambang - IndrapuraProvince : Sumatera Barat
A. Previous Status :
LARAP documents approved by World Bank on October 14, 2014.
Signed Action Plan of LARAP was given No Objection Letter (NOL) by the World Bank.
B. Pending Issues, Concern and Actions
a) Compensation payments to PAPs are under going finalization by Satker PJN ll WestSumatera .
C. Update during this reporting month of March 2016
a) No update this month.
b) Total PAP = 2,337 ; Compensated = nil ; Percent complete = 0%.
13. Monitoring Report of the LARAPPackage No. 13 : Sp. Rukis – Tj. KemuningProvince : Bengkulu
A. Previous Status :
World Bank issued on May 30, 2014 a No Objection Letter (NOL) on the revised LARAP documentsfor implementation.
Signed Action Plan of LARAP was given No Objection Letter (NOL) by the World Bank.
World Bank issued on August 18, 2015 No Objection Letter (NOL) on the monitoring Report No.1.
World Bank issued on October 13, 2015 No Objection Letter (NOL) on the monitoring Report No.2.
B. Pending Issues, Concern and Actions
a) Compensation payments for 3,030 PAPs can be started upon completion of the revision ofDIPA 2016.
C. Update during this reporting month of March 2016
a) Revision of DIPA 2016 amounting to RP. 12 Billion is under process.
b) Monitoring Report No.3 for compensation payments of 193 PAPs in Kab. Kaur submitted toWB which was submitted on February 23, 2016 has been issued by the Bank the NOL onMarch 8, 2016.
c) Total PAP = 3,412 ; Compensated = 625 ; Percent complete = 18,32%.
14. Monitoring Report of the LARAPPackage No. 14 : Painan - KambangProvince : Sumatera Barat
A. Previous Status :
World Bank issued on December 19, 2014 the No Objection Letter to the LARAP documents.
LARAP’s signed action plan was given No Objection Letter (NOL) by World Bank.
B. Pending Issues, Concern and Actions
a) Process of compensation payment is on-going.
C. Update during this reporting month of March 2016
a) Compensation payment process preparation.
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
4 - 19
b) Total PAP = 2,323 ; Compensated = nil ; Percent complete = 0%.
15. Monitoring Report of the LARAPPackage No. 15 : Sibolga – Bts. TapselProvince : Sumatera Utara
A. Previous Status :
World Bank approved the LARAP documents on February 6, 2014 for implementation in acquiringRoad Right of Ways and removal of obstruction.
Monitoring report No.1 for 40 of the remaining 1.554 PAPs was given No Objection Letter (NOL)on November 16, 2015.
Monitoring Report No.2 for payment of remaining 72 PAPs already submitted to Wolrd Bank.
B. Pending Issues, Concern and Actions
a) Due limited to limited suppy of map fields as one of the documents needed for finddisbursement by Treasury Office affect the progress of payments release.
C. Update during this reporting month of March 2016
a) Compensation payment for the remaining PAPs is under process.
b) Monitoring Report-3 for the compensation payment for 236 from the remaining 1.439 PAPsalready be submitted to WB on February 19, 2016 and Bank issued no objection letter(NOL) on March 16, 2016.
c) Total PAP = 1,554 ; Compensated = 520 ; Percent complete = 33,46%.
16. Monitoring Report of the LARAPPackage No.16 : Seblat - IpuhProvince : Bengkulu
A. Previous Status :
World Bank issued on May 30, 2014 a No Objection Letter (NOL) on the revised LARAP documentsfor implementation.
World Bank issued No Objection Letter (NOL) on Monitoring Report No.1 and 2 for LARAPimplementation.
Monitoring report for 102 of the remaining 120 PAPs was given No Objection Letter (NOL) onNovember 26, 2015.
B. Pending Issues, Concern and Actions
a) LARAP documents for this Package covers only land acquisition for the road link. If there areland acquisition for the bridge site, a separate LARAP documents need to be prepared.
b) LARAP Implementation is underway for the remaining 18 PAP be allocated 2015 nationalbudget and schedule to be settled on Dec 2015.
c) Monitoring Report for the compensation payments of previously paid PAPs still to beprepared for submission to World Bank.
C. Update during this reporting month of March 2016
a) Data of the payments to the 18 PAP (Balance from 259 PAPs) are under preparation bySatker PJN I Bengkulu.
b) Updated LARAP documents submitted on February 22, 2016 to World Bank with NOL isuedby Bank on March 8,2016.
c) Total PAP = 259 ; Compensated = 254 ; Percent complete = 98,07%.
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
4 - 20
17. Monitoring Report of the LARAPPackage No.17 : Sp. Gunung Kemala – Pg. TampakProvince : Lampung
A. Previous Status :
World Bank approved the corrected LARAP documents on November 12, 2013
Monitoring report for 154 of the total 2.273 PAPs was given No Objection Letter (NOL) onOctober 13, 2015.
Monitoring report for 735 of the remaining 2.119 PAPs was given No Objection Letter (NOL) onNovember 26, 2015
B. Pending Issues, Concern and Actions
a) No issue this period.
A. Update during this reporting month of March 2016
a) Monitoring Report for the compensation payments for the remaining 1.384 PAPs has beenissued No Objection Letter (NOL) on March 16, 2016 by the World Bank.
b) PMU/CTC waiting data of payment progress for the remaining of 1.384 PAPs from SatkerPJN II Lampung.
c) Total PAP = 2,273 ; Compensated = 2,273 ; Percent complete = 100%.
18. Monitoring Report of the LARAPPackage No.18 : Mukomuko – Bts. SumbarProvince : Bengkulu
Cancelled from the WINRIP Program.
19. Monitoring Report of the LARAPPackage No.19 : Lais - BintunanProvince : Bengkulu
B. Previous Status :
World Bank issued on May 30, 2014 No Objection Letter (NOL) on the revised LARAP documentsfor implementation
World Bank issued No Objection Letter (NOL) on Monitoring Report No.1 for the LARAPimplementation.
Monitoring report for 208 of the remaining 290 PAPs was given No Objection Letter (NOL) onNovember 26, 2015.
C. Pending Issues, Concern and Actions
a) Monitoring Report for payment of compensation to the remaining 82 PAPs still to beprepared for submission to World Bank.
b) Certification process for 136 plots still to be finalized.
D. Update during this reporting month of March 2016
a) PMU/CTC waiting data of payment progress for the remaining of 82 PAPs from Satker PJN IBengkulu.
b) Total PAP = 556 ; Compensated = 556 ; Percent complete = 100%.
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
4 - 21
20. Monitoring Report of the LARAPPackage No. 20 : Lubuk Alung - SicincinProvince : Sumatera Barat
A. Previous Status :
World Bank issued NOL to LARAP documents on December 19, 2014.
B. Pending Issues, Concern and Actions
a) LARAP implementation to be implemented by Local Government.
C. Update during this reporting month of March 2016
a) Local Government /Satker PJN I Sumatera Barat on-going inventory of affected assets.
b) Total PAP = 940 (tentative) ; Compensated = nil ; Percent complete = 0%.
21. Monitoring Report of the LARAPPackage No. 21 : Lubuk Alung - KuratajiProvince : Sumatera Barat
A. Previous Status :
World Bank issued NOL to LARAP documents on December 19, 2014.
B. Pending Issues, Concern and Actions
a) LARAP implementation to be implemented by Local Government.
C. Update during this reporting month of March 2016
a) Local Government /Satker PJN I Sumatera Barat on – going inventory of affected assets.
b) Total PAP = 1,301 (tentative) ; Compensated = nil ; Percent complete = 0%.
4.7 Anti Corruption Issues
4.7.1 Anti‐Corruption Action Plan (ACAP)
ACAP for WINRIP was developed from the previous SRIP experiences. Basically, it has the same maincomponents of involving the Community Representative Observers (CRO) in the bid opening and ThirdParty Monitoring (TPM) during the construction supervision although modification was made on theselection process of the CROs for SRIP. Within this plan there are four main pillars as indicated separatelybelow
a) Community Representative Observers (CRO)b) Publication / Disclosurec) Complaints Handling System (CHS)d) Third Party Monitoring (TPM)
4.7.2 Community Representative Observers (CRO)
The Community Representative Observers, who are required to observe the actual bidding activities, wereappointed for WP-1 group. All of the CROs were university staff, selected in accordance with the WorldBank suggestion to request assistance from local universities.
CRO is the independent observer who is not related directly or indirectly to the Contractors, Consultants,and Suppliers or not be part of the WINRIP’s management, and not a member of any political party.
CROs selection procedures:
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
4 - 22
a. Review the criteria and qualifications of candidates for the CRO.b. Director of Planning, DGH/ as Chairman of the Project Management Unit, delegated of the authority to
the selection of the CRO to the Head of National Roads Implementation Agency(BBPJN) / Head of Procurement Services Unit (Unit Layanan Pengadaan - ULP), hereinafter referred to asHead of Balai.
c. Head of Balai to invite CRO candidates from the local universities or colleges.d. Selection of CRO to be facilitated by Balai (BBPJN) / Procurement Services Unit (Unit Layanan
Pengadaan - ULP).e. Elected CRO and substitute CRO must attend one day training to be conducted by the PMU / CTC
WINRIP.f. Head of Balai to report the result of CRO selection by attaching the Minutes of Election Meeting and
send an approval application letter of the CRO to Director of Planning DGH as the Chairman of PMU.g. Based on the report and a written request from the Head of Balai, the Director of Planning DGH as the
Chairman of PMU must sign a Letter of Agreement and the Decree of the Establishment of CROs.
The duties and obligations of CRO are:
a. CRO must be present in any procurement activity (Pre-Bid Meeting, Site Visit, Bids Submission andOpening of Bids, and Announcement of Bids Winner) by invitation of the Procurement Committee, andare required to sign the attendance list
b. If the elected CRO is unable to attend on procurement activities, a Substitute CRO shall be appointed toattend these activities.
c. In discharging of duties the Substitute CRO have the same responsibilities as elected CRO.d. The CRO / Substitute CRO, after attending the Procurement activities, required to make a report of
his/her activities and submit them to the PMU and copy furnished to the related Head of Balai.
CRO as the representative of the community is to be independent observers and in performing their dutiesvoluntarily and not demanding benefits of their works.
In the performance of its duties, the CROs receive transportation cost from their home / office to thelocation of procurement meeting, and also he / she also receives per diem or Out Station Allowance (OSA)and hotel accommodation if necessary to stay. CROs also get additional charged for their reporting costs.The financing standards adjusted to the General Cost Standard (Standar Biaya Umum) issued by theMinistry of Finance.
The CRO’s financing charged to the Contract for Consulting Services for Technical Assistance for Core TeamConsultants (CTC) No: 06-20/CTC/TA/LN/8043/1112, dated 5 November 2012.
4.7.3 Publication / Disclosure
The second task under ACAP is publication of related ACAP documents for public disclosure with easyaccess to the general public and this is mainly manifest in the ACAP segment of the WINRIP website. ThisACAP section has been being designed to attain the best possible transparency of the project.
Ministry of Public Work (MPW) will provide necessary information in the Project Implementation Plan (PIP),Project Management Manual (PMM) on its website, and in the bidding documents, such as contact point
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
4 - 23
for complaint (mail and e-mail address, phone, fax, text message). The contact will also include the Bank’sFraud and Corruption Hotline. MPW will hold Annual Accountability Meetings to enhance accountabilityand project information sharing with civil society. The PMM will provide guidelines on disclosure ofinformation related to the project. MPW official website will display critical information on WINRIP toenhance both internal and external monitoring of the project:
Work Plan and Procurement Plan.
Quarterly newsletter containing information on the list of contracts, implementation progress, projectsrelated activities, number, types and status of complaints in each location. The newsletter will also bemade available to civil society in hard copy and through electronic mailing system.
Mid-Term Review Report, promptly after completion of the mid-term review implementation support iscarried out in accordance with the loan agreement;
All final audit reports (financial or otherwise, including qualified audit reports) prepared in accordancewith the loan agreement and all formal responses of the government in relation to such reports. Thepublication should be done within one month after the report is accepted as final.
Contracts awarded with information on general scope of work (with location), value, and summaryinformation of the awarded firms/ contractors. The practice in other projects demonstrates thatdisclosure of contracts awarded will help in reducing fraudulent practices
Ministry of Public Works (PU) maintains a website: http://www.pu.go.id/, with a link to 'eproc.pu.go.id' forinformation on semi e-procurement or e-procurement. PMU WINRIP supported by CTC will develop his ownwebsite: http://www.winrip-ibrd.com, and with it all the information and data about WINRIP be inputted oruploaded on this site.
In the application of one of the components of ACAP, the public disclosure and transparency, it is necessaryto spread information and increase the capacity of all stakeholders involved in the implementation of thisWINRIP project, through a variety of relevant training. The trainings have been expressed in the ToR of CTCWINRIP and described in the Project Implementation Plan (PIP).
One of the major risks to effective project implementation and management derives from the likelihoodthat project management staff does not have adequate training in or experience of the management oflarge-scale projects.
4.7.4 Complaints Handling Mechanism (CHS)
The ACAP as adopted by the Ministry of Public Works for WINRIP states on the subject of “ComplaintsHandling System”. The Community Development Specialist and the Management Information Specialist willplay a crucial role in the set-up of the Complaints Handling System (CHS) within PMU, in cooperation withthe PMU officer(s) in charge of the Complaints Handling Unit (CHU).
CHS essentially has four main components as follows:
Data Entry.
All complaints were expected to be submitted through the WINRIP website but in fact, to date, mostcomplaints have been received by letter, either directly or indirectly, although a few were sent by fax
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
4 - 24
or email. However, to attain the best possible transparency of the project, complaints submittedmanually through letter, facsimile, telephone, e‐ mail or visit to the Public Works regional offices willbe entered in the WINRIP website by the CHS team of CTC. The possibility of using the ‘short messageservice’ (SMS) from a cell phone for complaints was considered and it was decided that all SMSmessages, although not treated as formal complaints, will be recorded as additional information.
Complaint Registration.
Every submitted complaint is registered and stored into the CHS database, categorized, and sent tothe correlated expert for future consultation in order to formulate a response.
Complaint Assessment.
The CHS Team assesses the urgency and complexity of all complaints. Simple complaints are followedby the formulation of a response for PMU’s approval before uploading the formal response into theWINRIP website. Complex complaints are followed by a thorough investigation.
Field Investigation and Analysis.
In the case of an investigation being required, the CHS team will make field visits and take necessaryaction such as discussion with related institutions (Satker, Dinas, Supervision Consultant, etc); invitethe complainer; interview the contractor; etc. Findings will be used for analysis to formulate aconclusion, solution, next action and any further decision.
4.7.5 Third Party Monitoring (TPM)
All WINRIP packages are designed to have external parties involved in conducting an independentassessment of the project throughout construction. Project information is accessible through the WINRIPwebsite (under construction), project information booth which is normally maintained in thePPK/Satker/Dinas office or, project announcement (billboard) at each site. ACAP requires a third party, fromoutside the project, to independently monitor the progress of construction work of each link and thesepersonnel are provided by universities nearby each package.
It was decided that the best method of recruitment for TPM was through the universities closest to eachpackage and PMU mailed invitations asking them to express their interest in forming independentmonitoring teams of Third Party Monitors. This concept is based on the fact that Universities/TechnicalFaculties have the engineers available for recruitment and Universities could use this opportunity to beinvolved in public service. It is hoped that this concept will be more effective and more efficient in gettinglegitimate, competent, independent Third Party Monitoring (TPM).
The duties of a TPM included:
a) Report to the PPK for his intended package and obtain copies of all drawings and contractdocumentation.
b) Make at least three (3) separate visits to site, with each visit up to four (4) days long, and ascertain thatthe works are being carried out in compliance with the drawings and documentation.
c) Prepare and submit a report for the PMU following each visit with their last report post PHO.
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
4 - 25
4.8 Road Safety Audit
Since the Senior Road Safety Audit Engineer has been mobilized on 1st May 2013 and demobilized onApril 1st 2014, technical design and road safety engineering review and road safety audit for severalpacakages in AWP-2 and AWP-3 sub-projects has been implemented.
However, there were still some task which were not covered by the Senior Road Safety Engineer duringthe duration of the road safety audit stage. Upon mobilization of the National Road Safety Engineer andthe Assistant Road Safety Engineer who were mobilized on June 2, 2014 and November 3, 2014respectively, the remaining road safety audit works were continued.
The remaining works are follows :
1. Road Safety Audit Construction Stage, for :a. AWP-1 sub-projects (Packages 1, 2, 3 and 4)b. AWP-2 sub-projects (Packages 4, 5, 6, 7, 8, 10, 11, 12 and 13)c. AWP-3 sub-projects (Packages 14, 16, 17, 19, 20 and 21)
2. Road Safety and Traffic Management Monitoring, for :a. AWP-2 sub-projects (Packages 4, 5, 6, 7, 8, 10, 11, 12 and 13)b. AWP-3 sub-projects (Packages 14, 16, 17, 19, 20 and 21)
Road Safety Audit at detailed design stage is to identify the road safety weaknesses in design drawingsthrough site visiting, review of design drawings and official meeting with stake holder. Road SafetyAudit report is the recommendation for improvement of road safety.
Road Safety Engineering Review is to conduct a study of road safety on the packages that road safetyaudit were not performed during the detail design stage. The objective is same with road safety audit atdesign stage.
Traffic Management and Safety Monitoring is to check the performance of contractors related to theimplementation of application management and traffic safety in the field.
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
5 - 1
5 FINANCIAL & MANAGEMENT INFORMATION SYSTEMS
5.1 Draw‐Downs and Future Costs
Details of the disbursements already made from the loan are listed in the followingsub‐section.
5.2 Disbursement
The total disbursement by World Bank from the loan to the end of March 2016 wasUSD 52,938,748.41 equivalent to approximately 21.18% of the loan funds. A totaldisbursement of USD 2,794,212.51 was made during the month of March 2016 for the paymentInterim Payment Certificates and advance payment to Contractor of the newly startedsubproject under Category 1 Part 1 of the loan agreement.
The total expenditure to date measured in the term of the World Bank commitment, notincluding the Special Account advance, is shown in Appendix C. The following tablesummarizes the individual disbursements as calculated by CTC but retaining the totaldisbursement from Client Connection at the end of March 2016.
Category DescriptionLoan Restructuring
Amount USDTotals Disbursed toEnd March 2016 in
USD% Disbursed
1Part 1 Betterment andCapacity Expansion of
National Roads.220,400,000.00 47,354,867.58 21.49
2Part 2
Implementation Support17,000,000.00 5,583,880.83 34.90
3Part 3
Road Sector InstitutionalDevelopment
0 0 0
4Part 4
Contingency for DisasterRisk Response
0 0 0
Unallocated 12,600,000.00 0 0
Original LoanAmount
250,000,000.00 52,938,748.41 21.18
5.3. Management Information System
5.3.1. General OverviewThe Management Information System tasks are as follows below:
1) Information Systema. Develop and manage the File Storage as database system to store soft copy
documents into the server.b. Establish the Document Management System (DMS) to provide:
Letter Database System, used to record all information of incoming andoutgoing letter.
Document Library System, used to record all information of hard copydocuments then store it into library shelves.
c. Create and updated content of the WINRIP official website.
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
5 - 2
d. Develop and updated content of the Website Geographic Information System(WebGIS) of spatial and roads information that overlay into Google Maps.
e. Develop, manage and updated content of the Financial ManagementInformation System (FMIS), the web based application to monitoring thefinancial report and the physical progress report.
f. Provide and manage of the Complaint Handling System (CHS), used andsupport the ACAP activities to accommodate complaints from the public.
2) Data Collection and Document Uploada. Collecting data and updating list of data catalog every month.b. Uploading documents into a file storage server.
3) Technical and Computer Troubleshootinga. Setting up and manage cable network of local area network and internet
connection.b. Setting up and manage hardware problem of the computer, printer, copier
and phone.c. Software installation and cleaning up of computer virus.
5.3.2. Database
Incoming andOutgoing Data Administrator Saved
Stored
Inputted
File StorageServer
Shelves
DatabaseApplication
Soft File
Hard Copy
DataInformation
Typical Workflow ofDatabase Management
A typical workflow in management of incoming and outgoing data is divided into 3
types of data handling, below:
1. Hardcopy, the document is stored in a rack.
2. Soft files, saved in the File Storage Server.
3. Data information, inputted in database applications.
For further handling that needs to be made an integrated database management
system so that all data can be stored properly. The database system has been
prepared to store all of WINRIP project information in a systematic, easily
traceable, maintainable, and manageable format as outlined below with the following
systems:
Monthly Progress Report March 2016
Western Indonesia National Roads Improvement Project
5 - 3
a. File Storage Server, used to stored all files of report and other document. Pleasecheck the URL address http://storage.winrip-ibrd.com.
b. Document Management System (DMS), used to record all information of letter anddocument files. The URL address of the DMS application will be athttp://dms.winrip-ibrd.com. The DMS have 2 main modules below:
1. Letter Database System, used to record all information of incoming andoutgoing letter.
2. Document Library System, used to record all information of document andreport files.
Monthly Progress Report March 2016 November 2014
Western Indonesia National Roads Improvement Project1
6 - 1
6 PROJECT PERFORMANCE
6.1 World Bank and GOI Compliance
6.1.1 World Bank Missions
During this period (March 2016) the World Bank’s Technical and Financial Audit Consultants (TFAC)mission performed and conducted site audits on Package 11 (Bantal – Mukomuko) and Package 19(Lais – Bintunan).
The mission visited the two (2) contract packages from February 29, 2016 to March 4, 2016 inorder to access the following :
The quality of works implemented by the Contractor, site management and qualitycontrol and compliance of equipment.
The actions taken by the Design Supervision Consultant (DSC) concerning quality controlrole.
Follow-up inspection of what actions taken up by the Contractor on the remaining non-conformance works that were previously inspected way back in November 2015.
As the month ended, the regular monthly progress meeting was held to review and/or updatethe implementation progress and monitoring the key activities on the Ägreed Key Action Plans”.
Also taken up during the meeting was the presentations of the results of the TFAC audit reportsand recommendations to rectify the non-conformance findings.
6.1.2 Agreed Key Actions and Mission Plans during Recent World Bank Mission
A list of the key actions monitored during the period are listed below.
No. Action By Whom Updated StatusMarch 29, 2016 New Deadlines
1. Review BERs of packages 14 and 16 Bank April 1, 20162. Send signed contract extension of Package 4 to Bank PMU and CTC Done
3. Send signed contract extension of Package 2 and 3 toBank PMU and CTC Mid of February April 8, 2016
4. Submit signed contracts for packages 8 and 12 to Bank PMU and CTC Done
5.
Inform the Bank about the steps DGH has taken/will takein the case of the misrepresentation of facts in thebidding of Package 8 in response to the letterWINRIP/265 of December 9, 2015. If DGH is not takingany steps, please inform as also
PMU and CTC Consultation with
Legal Departmentongoing
As soon as possible
6. Inform the Bank the bidding process of package 10 PMU and CTC February 1, 2016 April 8, 2016
7. Send to Bank response to letter WINRIP /279 of January12, 2016 regarding the extension of bid validities PMU and CTC Done
8. Inform the Bank about the plans regarding the SlopeProtection in Package 3
PMU, CTC,DSC, WB May 15, 2016
9. Send technical support documents for contractmodification of package 6 (40% increase) to Bank PMU and CTC Done
10.Inform the Bank about DGH’s plans to cover theadditional drainage and slope protection requirementsunder package 19
PMU and CTC May 15, 2016
11. Send a letter to DGH regarding the swamp area inpackage 19 Bank April 8, 2016
12. Publish the Request for Manifestation of Interest for theslope stabilization, design, and management for the
SubditConstruction February 1, 2016 Once the Bank
approves the e-
Monthly Progress Report March 2016 November 2014
Western Indonesia National Roads Improvement Project2
6 - 2
No. Action By Whom Updated StatusMarch 29, 2016 New Deadlines
Bank’s review Geotechnicand Stabilityand CTC
procurement system
13. Send the RfP for the slope stabilization, design, andmanagement to Bank for NOL PMU and CTC Done End of April 2016
14. Send to the Bank the request for the extension of the CTCcontract PMU and CTC Done
15.Send to the Bank the response related to the contractmodification to the DSC contract (end date December2016)
PMU and CTC End of Feb 2016 Mid-April 2016
16.Send to the Bank an update of the environmentalmonitoring table in annex 4, including the information onthe quarries
PMU and CTC End of April 2016
17. Send the environmental management and monitoringplans (RKPPL) for packages 5 and 17 to the Bank PMU and CTC
RKPPL package#05&17 will besubmit on mid ofFeb 2016
End of April 2016
18. Carry out the workshop on HIV/ AIDS for new packages PMU / CTC/DSC
2 June 2016 (PackageNo.7)
19.Send the first environmental management andmonitoring implementation reports for all packagesunder construction to the environmental agencies (referto annex 4 or environmental safeguard compliance table)
CTC/DGH
PackagesNo.2,4,6,11&19 end ofApril 2016
PackagesNo.1,5,7,13,15 & 17for of June 2016.
20. Carry out environmental supervision missions jointly withthe Environmental Agency in order to make surecontractors comply with their environmentalmanagement plans (RKPPL)
PMU/CTC /Bank / Env.Agency
April & May 2016
21. Request additional budget for LARAP implementation in2016 (DIPA revision), especially for package 13 PMU As soon as
possible March 30, 2016
22.
Inform the Bank about the measures that will be taken toaccelerate LARAP implementation for packages 12, 13,14, 15, 20 and 21, which is risking to seriously delay thestart/implementation of the works
PMU and CTC April 15, 2016
23. Submit to the Bank additional LARAP document forpackage 16 PMU Mid-April 2016
24. Submit the IFR for January to March 2015 to the Bank PMU May 15, 2016
25. Submit 2015 financial audit report to Bank PMU andCTC
June 30, 2016
26. Disclose updated procurement plan after Bank approvalin the Winrip website linked to MPW Website PMU February 5, 2016 Done
27.
Update the newsletter quarterly, including the list ofcontracts, implementation progress, project relatedworkshops and number, typology and status ofcomplaints
PMU Every quarter
Noted
28.Send quarterly newsletter to the civil society forum ineach project province in hard copy or through anelectronic mailing system
PMU Every quarter Noted
29.Provide feedback to the formal response to the qualityimprovement support inspection reports TFAC forpackages 2, 3, 4, and 19
Bank April 15, 2016
30.Provide a formal follow-up response to qualityimprovement support inspection reports TFAC forpackage 1
PMU/DSC March 31, 2016
31.Provide a formal follow-up response to qualityimprovement support inspection reports TFAC forpackage 19
PMU/DSC April 30, 2016
Monthly Progress Report March 2016 November 2014
Western Indonesia National Roads Improvement Project3
6 - 3
No. Action By Whom Updated StatusMarch 29, 2016 New Deadlines
32.Provide a formal follow-up response to qualityimprovement support inspection reports TFAC forpackage 11
PMU/DSC May 15, 2016
33. Regularly submit the quarterly progress reports to theBank PMU Each calendar
quarter Noted
6.1.3 Performance Indicators
Key Performance Indicators are developed and agreed between the World Bank and GOI,and will be monitored over the whole project period the changes in variables will becalculated annually. The set indicators are describe in the project Appraisal Document(PAD) and the Loan Agreement between the GOI and the World Bank.
The overall progress towards achieving the PDO of increasing the effective use ofselected sections of national roads along the Western Sumatra Corridor by reducing roaduser costs is considered moderately satisfactory. Progress in implementation has pickedup, and there has been an advance with respect to several project indicators. In addition,a project restructuring is being processed which should bring the project largely back ontrack.
The PMU provided an update on the achievement of the indicator targets. There hasbeen relatively good progress on three of the five intermediate indicators. For one of theremaining intermediate indicators on bridge improvement, progress is expected withinthe next semester. The last intermediate indicator related to institutional strengtheningwill be cancelled in the framework of project restructuring. For the PDO indicator onAADT, CTC carried out static traffic counts in March 2015 and confirmed that the originalindicator targets are adequate. The mission refined a few indicators definitions/baselinesand updated some indicator targets to take into account the project implementationdelays. These changes will be reflected in the upcoming project restructuring.
From the “baseline 2010 AADT and estimated AADT for the year 2014/2015, theextrapolated AADT for the year 2013 resulted to 11,254 vehicles per day or 8.8% abovethe targeted 10,347 vehicles per day in 2013. Shown in Table 11 is the comparisonbetween target and actual estimated AADT.
Table 11Year Targeted AADT EstimatedBaseline (2010) 7,837
FY1 (2013) target 10,347FY1 (2013) actual 11,254FY2 (2014) target 11,351FY2 (2014) actual 12,696FY3 (2015) target 12,453FY4 (2016) target 13,304
FY5 (2017) end target 14,214
Monthly Progress Report March 2016 November 2014
Western Indonesia National Roads Improvement Project4
6 - 4
6.2 Implementation Support Components
6.2.1 Core Team Consultant (CTC)
The CTC is responsible to provide support to the PMU and DGH in the management of the Project,based in Jakarta. The CTC tasks include financial and progress monitoring and reporting, informationmanagement and dissemination, quality assurance and performance review for the Design andSupervision Consultants (DSC), implementation and monitoring of the anti-corruption action plan,support for project monitoring and evaluation, and support for implementation of a trainingprogram to support project management and implementation.
The CTC contract No. 06-20/CTC/TA/LN/8043/1112 was signed on 5 November 2012 by both DGHand a Joint Venture of PT. Perentjana Djaja, Yongma Engineering Co.Ltd., and PT. EpadasconPermata Engineering Consultant.
The main CTC activities during March 2016 are as follows:
Prepared and submitted Training Implementation Reports. Prepared Monthly and Bid Evaluation/Procurement Reports for Packages 13, 15 and 17. Monitoring the implementations of the ESAMP, anti-corruption action plans, complains from
project site, progress of LARAP, procurement activities and financial progress. Prepared and issued various letters to PMU and DSC. Submitted various Reports to PMU concerning environmental and the status of LARAP
implementations. Monitored the actual construction progresses of the twelve (12) on-going contract packages and
advised PMU of the current situations of the sub-projects. Attended monthly progress meeting and World Bank’s presentation of TFAC technical audit
findings on Packages 11 and 19. Site visit for technical review of road safety audit of Package 3, prepared and submitted Road
Safety Audit Report for Provisional Hand Over (PHO) stage. Finalized draft Amendment No.4 for CTC.
6.2.2 Design and Supervision Consultant (DSC)
The Design and Supervision Consultant (DSC) will be responsible for design of WP 2 and WP 3 civilworks and supervision of all civil works. They will have the role of ‘Engineer’ under a FIDIC-typecontract. The tasks include the preparation and maintenance of a quality assurance plan, validationand updating of designs, supervision of all civil works, environmental and social monitoring andmanagement, and support for financial and progress monitoring and reporting.
The DSC will also be responsible for quality assurance of materials and workmanship, certifyingwhether or not contractors have achieved the required results, as well as documentation andreporting based on the financial management plan. They will prepare a Quality Assurance systemcovering all subprojects, and continuously monitor the effectiveness of their supervision procedures.The team will be contracted and managed by DGH through the Bina Marga Regional Office (Balai II),and will be based in Padang, West Sumatera.
Monthly Progress Report March 2016 November 2014
Western Indonesia National Roads Improvement Project5
6 - 5
DSC contract was negotiated in Balai Besar Pelaksanaan Jalan Nasional II (Balai-II) of DGH. Thenegotiation result and draft contract have been sent to WB on 25 March 2013 for review andapproval. The Bank issued no objection letter on the negotiation results and draft contract withletter dated 19 April 2013.
6.2.3 Study on Slope Stabilization Design and Management
This component consists of technical assistance for analytical work of an alternative design for roadsegment that pass through critical environmental assets and vulnerable areas especially on slopeprotection design and management.
6.3 TRAINING TO SUPPORT PROJECT IMPLEMENTATIONThe work during this reporting month is actually inseparable continuation of what were
prepared and done during previous month (February 2016) summarized below:
Continuing the preparation of some trainings to be implemented on the first opportunity.:
o IFR Training was scheduled to be deliver on the 1st week of March 2016;
o PMM Application Training was scheduled on the 3rd week of March 2016.
o The RKPPL Training was scheduled on 2nd week of April 2016.
Continuing to update the PMM and other training materials as required.
Continuing to ask for confirmation of the mobilization of contractors and consultants staff
of the respective packages.
The work during this reporting month was then focused on the following activities:
6.3.1 Continuing to prepare the implementation of three training programs that actuallyshould had been delivered in November-December last year; i.e:
The fourth (4th) IFR Training or Training on Preparing Interim un-audited Financial Report (IFR)
for packages: 07 (Indrapura – Tapan), 12 (Kambang-Indrapura), 08 (Batas Kota Pariaman –
Manggopoh), and 10 (Simpang Empat – Sp. Air Balam) was initially scheduled to be held on 2nd
week of December 2015. However, it was postponed by PMU to mid of January 2016, and
then was postponed again to March 2016. However, when the invitation letter was submitted
to PMU for approval/signing on mid of March, this reporting month, it was postponed again
and has to wait for the signing of the Amendment 4.
The PMM Application Training – 3, initially scheduled for being delivered on the end of
November 2015, was postponed to mid of January 2016, and was then postponed again as
the project decided that it would be no training implementation before March 2016 because
of duty travel cost problem that required to be re-arranged. However, at the end of
February the Training Team got information that the training could not be delivered yet in
March 2016. It still has to wait until the Amendment 4 being signed.
Monthly Progress Report March 2016 November 2014
Western Indonesia National Roads Improvement Project6
6 - 6
The seventh (7th) RKPPL Training was scheduled to be carried out in January 2016
However, at the end of December 2015, the project informed that all trainings would not be
delivered earlier than March 2016. It still has to wait for the process of Amendment 4.
The work was then focused on preparation, updating/revision, preparing training
budget plan (Amendment 4) etc.
Continue to prepare the implementation of those three training: modifying letter of
invitation, checking the training materials, modifying the combination of packages
involved as well as prospective participants as required in compliance with the CTC
Timeline, identifying the suitable venues, etc. The delivery of the three trainings still
has to wait the result of Amendment 4 process
Continuing to update the PMM related to the new organization structure of the
Ministry of Public Works and Housing as well as the DGH,, new regulation, NCB
procurement , and the experiences of implementing the project up to now.
Asking for confirmation of the mobilization of contractors and consultants in every
package. It resulted, based of Status of Civil Works of March 2016, that only 3
packages of our training target that possibly could be addressed by our training in this
reporting month, i.e:
~ Package 07 : Indrapura – Tapan, status : COW issued on 10 December 2015;
~ Package 08: Bts. Pariaman – Manggopoh:: Contract Signed on 28 January 2016;
COW issued end of March 2016.
~ Package 12 : Kambang – Indrapura; : Contract signed on 28 January 20126,
Waiting for issuance of COW.
As requested, the updated Action Plans of all CTC Professional Staffs for 6 March 2016
– 31 December 2017, which refer to the TOR of WINRIP, were collected and were then
submitted to Ka. Satker PAP2PHLN on 21 March 2016.
6.3.2 Progress
In terms of training delivery, again, no training was delivered during this reporting
month, so that no one was trained during this time.
However, the preparation of the next training run better, some of the revisions of the
PMM were done as required while awaiting for the new decree concerning for instant
the revision of PMU organization.
The updated Action Plans of CTC Professional Staffs were collected and submitted to
Ka.Satker PAP2PLN.
Monthly Progress Report March 2016 November 2014
Western Indonesia National Roads Improvement Project7
6 - 7
6.3.3 Activities Plan for next month (March 2016) Continuing the preparation of three training programs to be implemented on the first
opportunity, hopefully at least one of them in April 2016 : IFR Training, PMM
Application Training, and RKPPL Training.
Continuing to update the PMM and other training materials as required.
Continuing to ask for confirmation of the mobilization of contractors and consultants
staff of the respective packages.
Summary of Workshops and Trainings – WINRIP( 2012 – 2016 )
Per : 31th March 2016
No. Activities Location DateNumber of Attendances
RemarksTarget Real. %
1.Procurement Training for ProcurementWorking Group (ProcurementCommittee)
Bandung 1-2 Nov,2012 44 36 82%
Completed
Conducted before the CTCwas mobilized
2. Workshop on Bid Documents Evaluation Jakarta27 Feb.-
1Mar2013
46 33 72%Completed
3 Workshop on World Bank ProcurementGuidelines for WINRIP
Tj.PandanBelitung
24 -25 Apr.2013 47 39 83%
Completed
4. Workshop for Project ManagementManual (PMM) Updating Jakarta 18 -19
ar.2014 47 38 81%Completed
5
RKPPL Training – 1 (First Training on“Rencana Kerja Pengelolaan danPemantauan Lingkungan ( RKPPL)” orEnvironmental Management andMonitoring Work Plan
Lampung 5-6 June2014 10 13 130%
CompletedMainly addressed to theContractors & SupervisionConsultants of Package 01:Krui – Biha
6 TPM Traaining – 1 (First Training onThird Party Monitoring) Lampung 5-6 June
2014 10 13 130%
CompletedMainly addressed to TPMTeam members of Package01: Krui-Biha
7 Workshop for Project ManagementManual Finalization of Updating Bogor 12 -14 June
2014 47 35 74,5%Completed
8
RKPPL Training – 2 (Second Training on“Rencana Kerja Penge-lolaan danPemantauan Lingkungan (RKPPL)” orEnvironmental Manage- ment andMonitoring Work Plan
Padang 18 -19 June2014 18 25 138,9%
Completed
Mainly addressed to theContractors & SupervisionConsultants of Packages 02and 03
9 TPM Training – 2 (Second Training onThird Party Monitoring) Padang 18-19 June
2014 18 25 138,9%
CompletedMainly addressed to TPMteam members of Packages02 and 03
10 RKPPL Training – 3 (Third Training on“Rencana Kerja Pengelolaan dan Bengkulu 7-8 July
2014 10 11 110 %Completed
Mainly addressed to the
Monthly Progress Report March 2016 November 2014
Western Indonesia National Roads Improvement Project8
6 - 8
Pemantauan Lingkungan” ( RKPPL) orEnvironmental Management andMonitoring Work Plan
Contractors & SupervisionConsultants of Packages04: Ipuh – Bantal
11 TPM Training – 3 (Third Training onThird Party Monitoring) Bengkulu 7-8 July
2014 10 11 110%Completed
Mainly addressed to TPMteam members of Package 04
12Workshop for Socialization of UpdatedDraft of Project Management Manual(PMM) (1)
Padang 10 -11 Sep.2014 94 81 86%
Completed
13 IFR Training – 1 (First Training onInterim unaudited Financial Report Padang 26-27 Nov.
2014 24 20 83%
CompletedPackages: 01, 02, 03 and04; and related Satkers andPPKs.
Sub-Total per 31 Dec. 2014 : 425 380 89,41 %
No Activities Location DateNumber of Attendances
RemarksTarget Real %
14.Special Training for PMM Socializationto Contractors & Consultants Jakarta
FirstlyScheduled:End January
2015.
-- -- --
Mainly for Contractors &Consultants of packages05, 11, 13, and 15. Beingpostponed by PMU,awaiting for mobilizationof targeted participants..
15. IFR Training – 2 (Second Training on Interimunaudited Financial Report)
11 – 12 February2015 20 25 125%
CompletedFor packages: 05, 11, 13,and 17 (No participantsfrom Pack.age 17, will beinvitd in next IFR)
Bengkulu11 – 12
February2015
20 25 125%
CompletedFor packages: 05, 11, 13,and 17 (No participantsfrom Pack.age 17, will beinvited in next IFR)
16
RKPPL Training – 4 (Fourth Training on“Rencana Kerja Pengelolaan dan Peman-tauan Lingkungan” (RKPPL) /Environmental Management andMonitoring Work Plan
Bengkulu 11 – 12March 2015 21 15 71,43%
CompletedFor package 11 (Bantal –Mukomuko) and 13 (Sp.Rukis – Tj. Kemuning)
17. TPM Training – 3 (Third Training onThird Party Monitoring) Bengkulu 11 -12
March 2015 21 15 71,43%
CompletedFor package 11 (Bantal –Muko- muko) and 13 (Sp.Rukis – Tj. Kemuning)
Sub Total per 31 March 2015 487 435 89,32%
18 Special Training for PMM Socializationto Contractors & Consultants - (2)
Jakartawas finallyreplaced
byBengkuluas location
6 – 7 May2015 was
selected fortrainingdelivery
24 27 112,5%
CompletedJust for packages located inBengkulu: Contractors &Consultants of packages 06,11, 13 , and 19.
19
RKPPL Training - 5 (Fifth Training on“Rencana Kerja Pengelolaan dan Peman-tauan Lingkungan” (RKPPL) /Environmental Management andMonitoring Work Plan
Bengkulu
Scheduled:20 – 21 May2015, beingrealized on 4
– 5 June2015
25 23 92 %
Completed
For package 06, 19, and17.
20 IFR Training – 3 (Third Training onInterim unaudited Financial Report)
Bengkulu/Lampun
g
Scheduled:1st week of
August2015
-- -- --
For packages: 6, 19, and 15Postponed to Augustbecause of: PMM Delivery,Fasting month, and nomobilization in package 15.Re: # 22 below
Sub Total as per 30 June 2015 : 536 485 90,49 %
Monthly Progress Report March 2016 November 2014
Western Indonesia National Roads Improvement Project9
6 - 9
21 Procurement Workshop Padang 13 July2015 15 15 100 %
CompletedOne-day ProcurementWorkshop was successfullyheld by the World Bank incollaboration with the PMU inPadang, for packages : 07(Indrapura – Tapan), 08(Bts.Kta Pariaman –Manggopoh), 10 (Sp. Empat– Sp.AiIr Balam), and 12(Kambang – Indrapura).
22 IFR Training – 3 (Third Training onInterim unaudited Financial Report) Bengkulu
5 – 6August2015
19 14 73,68%
CompletedPlaned for packages: 6,19,and 15; but still nomobilization in package 15.It was then replaced bypackage 17 (Lampung)
23
Training on Application of PMM -3(especially for Contractors &Consultants) of Packages: 05, 15, 13,and 17
Sibolgamoved to
Bogor
Scheduled:3rd week ofSeptember
2015,moved to 23
– 24 Nov.2015
45 -- -- %
PostponedMainly for Contractors &Consultants of packages 05,15, 13, and 17. Beingpostponed by PMU, awaitingfor mobilization of targetedparticipants. Then moved toBogor (See # 25)
Total as per 30 September 2015 : 570 514 90,18 %
No Activities Location DateNumber of Attendances
RemarksTarget Real %
24
RKPPL Training - 6 (Sixth Training on“Rencana Kerja Pengelolaan danPemantauan Lingkungan” (RKPPL) /Training on Management of Road WorksEnvironmental Impacts duringConstruction Phase & PreparingEnvironmental Management andMonitoring Work Plan
Sibolga7 – 8
October2015
16 13 81,25 %
COMPLETEDThe training was mainlytargeted to the staff ofContractors and SupervisionConsultants (DSC & FieldSupervision Team) workingfor packages 05 and 15 andother elements related toconstruction woks of the twopackages. Unfortunately, noconsultant staff frompackage 15 attended thetraining ( not mobilized yet)
25
Training on PMM Application(especially for Contractors &Consultants) of Packages: 05, 15, 13,and 17 (3)
InitiallySibolga,
moved toBogor
Scheduled:3rd week ofSept. 2015,moved to
23 – 24Nov. 2015
45 27 60 %
COMPLETEDMainly for Contractors &Consultants of packages 05,15, 13, 17. Being postponedby PMU, awaiting formobilization of targetedparticipants. Then actuallymoved to Bogor , just forpackages 05, 15, 17.
26Project Management Manual (PMM)Application Training – (4)(Packages: 07, 08, 10, 12)
Padang Nov. 4th
week 2015 44 -- --POSTPONED
Postponed to Jan/Feb ‘16
27 Procurement Refreshing Training Bengkulu/ Padang
Des. 1st
week 2015 20 -- -- POSTPONEDAs required *)
28
Financial Management Reporting:Interim un-audited Financial Report (IFR)Training – 4For Packages: 07, 12, 08, 10
Padang
Scheduled2nd weekof Des.2015
21 -- --
POSTPONEDBeing postponed by PMU tonext year (Febr/Mar/Apr/May…etc. 2016)
Monthly Progress Report March 2016 November 2014
Western Indonesia National Roads Improvement Project10
6 - 10
Notes: *) : As required, because of any delay of mobilization or staff replacement.
6.4 Anti‐Corruption Issues
6.4.1 Anti-Corruption Action Plan (ACAP)
The main duties of the Community Development Officer are implemented of Anti-CorruptionMeasures, and Monitoring their Effectiveness. Provide assistance as required with the establishmentof anti-corruption measures necessary to support the project, and monitor and report theireffectiveness based on the Anti-Corruption Action Plan (ACAP) agreed between the World Bank andthe DGH.
The following tasks particularly need to establish procedures to be undertaken:
Selection of Community Representative Observers (CROs) of civil society groups to attend theprocurements process on key procurement steps including pre-bid meeting and site visit, bidssubmission and bids opening, and the announcement of the bid winner. These CROs will be
29
Training on Management of RoadWorks Environmental Impacts duringConstruction Phase & PreparingEnvironmental Management andMonitoring Work Plan (RKPPL Training)- 7
Padang Des. 3rd
week 2015 28 -- --
complying with the WINRIPCTC Timeline (9 Jan. 2016),awaiting for consultants &contractors mobilization,amendment process, and thelatest condition of theproject.Some revisions/modificationswill be required, according toThe latest project.timelineand latest conditions (time,mobilization, packageinvolved, etc.)
Total as per 31 December 2015 : 631 554 87,88 %
30
Financial Management Reporting:Interim un-audited Financial Report (IFR)Training – 4For Packages: 07, 12, 08, (10)
Padang
FirstlyScheduled
2nd week ofDec.2015;postponedby PMU toJan. 2016
21 -- --
As noted last quarter, sometraining programs scheduledfor November and December2015, were postponedbecause of duty travel costproblem that should be re-arranged. Three trainingsthen scheduled to beimplemented in January –March 2016, with the notethat based on the result ofconfirmation, package 10 stillhas problem, so that it cannotbe expected to fully involved.Unfortunately, the threetrainings were thenpostponed again by PMU,and should wait the signing ofAmendment 4. Therefore,these three training programswould then be scheduled forthe next three months: April,May, June 2016.
31Application of Project ManagementManual (PMM) Training – (4)For packages: 07, 08, 12, (10)
Padang
Initiallyscheduled for
Nov. 2015,was moved to
Jan 2016
30 -- --
32
Training on Management of RoadWorks Environmental Impacts duringConstruction Phase & PreparingEnvironmental Manage-ment andMonitoring Work Plan (RKPPL Training)– 7. Packages 07,08, 12, (10)
PadangDes. 3rd
week 2015> Mar. 2016
28 -- --
Total as per 31 March 2016 - 0 - No trained person
Monthly Progress Report March 2016 November 2014
Western Indonesia National Roads Improvement Project11
6 - 11
invited from local universities or other selected independent institutions, and will sign theattendance list for the procurement/selection process.
Establishment of a Third Party Monitoring (TPM) mechanism, whereby the media and civilsociety groups can become involved in monitoring the progress of the project. This Mechanismwill include regular sharing of information with the media.
Establishment and Management of a Complaints Handling Mechanism System (CHS), whichincludes maintaining project complaint log and filing to monitor status of follow-up of eachcomplaint. This mechanism will include provision for follow up investigations of substantialcomplaints by the Inspectorate General of Ministry of Public Works or third party audit to ensureindependence and reliability of the system. The CTC assignment concerns the monitoring of theaspects of Anti-Corruption Action Plan (ACAP) implementation and where required act pro-active in resolving issues when such a matter arises. The Community Development Officer has amajor role in monitoring performance and assists PMU in the set-up and follow-through of theComplaints Handling Unit (CHU) for the ACAP related incidents
Enhanced Disclosure Provisions and Transparency, Ministry of Public Work (MPW) have beenprovided necessary information in the Project Implementation Plan (PIP), Project ManagementManual (PMM) on their website, and in the bidding documents, such as contract point forcomplaint (mail and e-mail address, phone, fax, text message). The contact will also include theBank’s Fraud and Corruption Hotlines. MPW will hold Annual Accountability Meetings toenhance accountability and project information sharing with civil society. The PMM will provideguidelines on disclosure of information related to the project. MPW official website will displaycritical information on WINRIP to enhance both internal and external monitoring of the project
6.4.2 Community Representative Observers (CRO)
The Anti-Corruption Action Plan (ACAP) activity on Community Representative Observers (CROs)aspect as is follow:
The selection and establishment of CROs for all 19 packages was completed on November2015, and for the time being of March 2016 the CROs for Packages 14, 16, 20 and 21, areawaiting the issuance of the announcement of the tender winner of the World Bank andMPW, and this document is for the appendix of their Observing Report on Bid-Openingprocess.
The activities progress of Community Representative Observers (CROs) from January 2013 untilMarch 2016, are shown in Appendix H1.
6.4.3 Third Party Monitoring (TPM)
The Third Party Monitoring (TPM) component activity during March 2016 are as follow:
The TPM for Package 01 currently preparing field monitoring report of phase I and II, andshall be sent to PMU as soon as possible.
Monthly Progress Report March 2016 November 2014
Western Indonesia National Roads Improvement Project12
6 - 12
The TPM for Package 02 currently preparing field monitoring report of phase I and II, andshall be sent to PMU as soon as possible.
The TPM for Package 03 currently preparing field monitoring report of phase II and III, andshall be sent to PMU as soon as possible.
The TPM for Package 04 currently preparing field monitoring report of phase II and III, andshall be sent to PMU as soon as possible.
The TPM for Package 06 and 11 currently preparing field monitoring report of phase I and II,and shall be sent to PMU as soon as possible.
The TPM for Package 19 currently preparing field monitoring report of phase I and II, andshall be sent to PMU as soon as possible.
The Employment Agreement or Memorandum of Understanding between TPM for packages05, 06, 15, 17 and 19 with the CTC WINRIP (PT. Perentjana Djaja) was signed by Director ofPT. Perentjana Djaja and by Project Implementation Unit / Kepala Satuan Kerja Pembinaan
Administrasi dan Pelaksanaan Pengendalian Pinjaman dan Hibah Luar Negei (PAP2PHLN).
TPM Election for the packages 14, 20, and 21 had not been implemented because there is noavailable of duty travel budget for carry out of TPM selection on Amendment 3 of CTCWINRIP contract. Similarly for the execution of TPM training for the packages 07, 08, 10, 12,and 16 having the same problem that there is no available budget for duty travel. Therefore,the implementation of the above activities is waiting of the signing of the Amendment 4 ofCTC WINRIP contract.
The activities progress of the Third Party Monitoring (TPM) from January 2013 until March 2016, asshown in Appendix H2.
6.4.4 Complaint Handling System (CHS)
The Community Development Officer with collaboration with MIS Specialist has developed asoftware application of Complaint Handling System (CHS) in integrated to website of WINRIPhttp://www.winrip-ibrd.com.
In the implementation of Complaint Handling System (CHS) essentially there are five maincomponents as follows:
Data Entry. Complaint Registration. Complaint Assessment. Field Clarification and Analysis. Problem Solving and taking the Decision
The final draft of Complaint Handling System (the framework of the complaint procedures on theweb site of WINRIP and provided ACAP inputting data in the web site) has ready to be operated.
However these applications still continuously to be refined by considering input from various parties.The CHS team has been monitored and noted the public complaints via website of Sytem Informasi
Monthly Progress Report March 2016 November 2014
Western Indonesia National Roads Improvement Project13
6 - 13
Pemantauan Proyek “SiPP” / Project Monitoring Information System and WINRIP website.
During March 2016 CHS team has not been received any complaints from any parties.
The Complaints Handling Mechanism System (CHS) Activities is shown in Appendix H3.
6.4.5. Public Disclosures / Publication
Publication and disclosure is an attempt to increase transparency of information to the public, sothe public can easily to access information about the project WINRIP. Some components ofpublication and disclosures are as follows: a) announcing the information about the project throughdissemination activities and provision the leaflets, b) installation of the project information boards,c) the provision of space / project information booth, d) providing important information that canonly be accessed by public with submitted an officially applications to the authorities, and e) theprovision of information in the website which can be accessed via the internet.
The Community Development Team has sent the CRO’s activities and Third Party Monitoring (TPM)activities and has been uploaded to the website of WINRIP.
All data and report documents of the Community Development activities on CommunityRepresentative Observers (CROs) for 19 packages (# 01, 02, 03, 04, 05, 06, 07, 08, 10, 11, 12, 13,14, 15, 16, 17, 19, 20 and 21#) has been uploaded on the website of WINRIP.
Data of Third Party Monitoring (TPM) for 16 packages (# 01, 02, 03, 04, 05, 06, 07, 08, 10, 11, 12,13, 15, 16, 17, and 19) has been entered /uploaded to the website of WINRIP. The Third PartyMonitoring (TPM) for 3 (three) packages: 14, 20 and 21 in West Sumatera Province is ongoingpreparation to selection in the near future.
The Newsletter of January – March 2016 is ongoing prepare and when it is finish will beuploaded and published in the WINRIP website and MPW website, and will be sent to societyforum: Masyarakat Transportasi Indonesia “MTI”) / Indonesian Transportation Society andHimpunan Pengembangan Jalan Indonesia (HPJI) / Indonesian Roads Development Association,via e-mail, both at the central and provincial level related to Project Location (Lampung,Bengkulu, West Sumatera, and North Sumatera.
Review and update the Project Management Manual (PMM) Chapter IX: Monitoring andEvaluation of Project Performance, and Chapter XI: Anti-Corruption Action Plan (ACAP).
The Works Activities for Publication / Disclosure is shown in Appendix H4.
6.4.6. Action Plan for Next Months
The Activities plan for future months, in order of priority are as follows:
1. Selection the TPM for package 14 (Painan – Kambang), package 20 (Lubuk Alung – Sicincin) andpackage 21 (Lubuk Alung – Kuraitaji) in West Sumatera Province,
2. Preparatory Training of TPM team for package 07 (Indrapura – Tapan) and package 12 (Kambang– Indrapura) in West Sumatera Province.
3. Preparatory Training of TPM team for package 08 (Bts. Kota Pariaman – Manggopoh) and
Monthly Progress Report March 2016 November 2014
Western Indonesia National Roads Improvement Project14
6 - 14
package 10 (Simpang Empat – Simpang Air Balam) in West Sumatera Province.
Monitoring the TPM activity for packages that will be completed in near future (Packages #02,03), in West Sumatera Province and packages 04 and 19 in Bengkulu Province.
6.5 Road Safety Audit
6.5.1 Activities during This Month (March 2016)The Road Safety activities of this month are:
1. Carry out site inspection to Road Safety Audit at PHO stage on Package #3 Manggopoh –Padangsawah: 16 – 18 March 2016.
2. Prepare and submit Road Safety Audit at PHO stage (package #11) report to PMU, Directorateof Road Development, Head of BBPJN II and Head of Subdit of Environment and Road Safety onFebruary 22, 2016.
3. Prepare and update Project Management Manual (PMM) for chapter 10 and 13 (part of RoadSafety).
4. Attend regulary meeting with World Bank in Bina Marga on March, 29, 2016.5. Regularly Road Safety Design check at the office.
6.5.2 Current status of the project for technical field as of March 2016
The Details of Program of Road Safety Audit as of the end of March 2016 are shown in the table onAppendix B.
6.6 Management Information System
We have finished developing of the Progress Photos application. Then we have passed thetesting phase to upload photos to the database that running smoothly.. And now we arewaiting time for dissemination to the SE in each packages. Then get feedback andimprovement from them that these application can be running well.
Further, we will focus to fix filling system in the CTC-WINRIP office. The current serverstorage capacity is almost fully occupied, then we necessary to prepare a new storage serverwith more capacity.
Regarding to document update, the DMS application is still online well. And upload activitiesinto the DMS database continues as usual. Then number of files that have been uploaded toincrease rapidly. The data that has been uploaded to the DMS database until the end ofFebruary are: 735 records of letters and 298 records of documents.
Monthly Progress Report March 2016 November 2014
Western Indonesia National Roads Improvement Project15
6 - 15
6.6.1 Developing The Photo Progress Application
1) Background
The progress report from DSC are contains progress data in detail that make thestakeholders can find out details of activities that are being implemented in the field. But weneed more information about photographs could be useful as information to provide apreliminary description of the real conditions in the field.
2) Objectives
We make this application for the Contractors to upload photos of progress or otherspecial cases that occur in the field.
Use as an information to provide a preliminary description of the real conditions inthe field.
3) System Development Methodology
SYSTEMASSESSMENT
COM
PLAINT TYPE, STRU
CTURES AN
D SYSTEM
REQU
IREMEN
TS
SYSTEMANALYSIS
NEEDSANALYSIS
PROCESSANALYSIS
DATABASEANALYSIS
MODULEANALYSIS
SYSTEMDESIGN
INTERFACEDESIGN
FLOW CHARTDESIGN
DATABASEDESIGN
SYSTEMARCHITECTURE
COD
E PROG
RAMM
ING
AND
TESTING
SYSTEM
IMPLEM
ENTATIO
N
FINALIZATION
4) System Analysis
1. Needs Analysis
NO. NEEDS RECOMMENDATION
1. Inputting the new projectinformation
Need to create a menu to inputting the data fornew project information.
2. Upload the photographsUpload the 3 phase of photograps as known:before, on progress, and after constructionincluding detail location.
3. Change the existing of theuploaded photographs
Provides a menu to change the existing of theuploaded photographs.
4. Delete the existing of theuploaded photographs
Provides a menu to delete the existing of theuploaded photographs.
2. Module Programming
Monthly Progress Report March 2016 November 2014
Western Indonesia National Roads Improvement Project16
6 - 16
The Photo Progress application consists of 3 modules programming as follows: Module of Project Data, to store all of WINRIP packages information into
database. Module of Photo Progress, to upload the 3 phase of photograps as known:
before, on progress, and after construction including detail location. Module of User, to store user information and password.
5) System Design
1. Database Tables
1.Table: data_paket
NO FIELD NAME TYPE
1 id_paket int(5) AUTO_INCREMENT
2 nomor_paket varchar(50)
3 nama_paket varchar(100)
4 singkatan_paket varchar(15)
5 id_provinsi int(5)
6 tipe varchar(50)
7 target_panjang varchar(20)
8 target_lebar varchar(10)
9 nomor_kontrak varchar(100)
10 tanggal_kontrak date
11 ppk varchar(50)
12 nama_ppk varchar(150)
13 kontraktor varchar(255)
14 nama_gs varchar(150)
15 konsultan_pengawas varchar(255)
16 nama_se varchar(150)
2.Table: foto_progres
NO FIELD NAME TYPE
1 id_foto int(5) AUTO_INCREMENT
2 id_paket int(5)
3 number_location int(5)
Monthly Progress Report March 2016 November 2014
Western Indonesia National Roads Improvement Project17
6 - 17
NO FIELD NAME TYPE
4 location varchar(100)
5 nomor_lokasi int(5)
6 lokasi varchar(100)
7 audit_finding varchar(255)
8 temuan_audit varchar(255)
9 recommendation text
10 rekomendasi text
11 foto_sebelum varchar(255)
NAMA FILE : P(nomor_paket)_(nomor_lokasi)_(lokasi)_ PB_(tanggal_foto_pelaksanaan)
12 tanggal_foto_sebelum date
13 foto_pelaksanaan varchar(255)
NAMA FILE : P(nomor_paket)_(nomor_lokasi)_(lokasi)_ PC_(tanggal_foto_pelaksanaan)
14 tanggal_foto_pelaksanaan date
15 foto_setelah varchar(255)
NAMA FILE : P(nomor_paket)_(nomor_lokasi)_(lokasi)_ PS_(tanggal_foto_pelaksanaan)
16 tanggal_foto_setelah date
17 nama_se varchar(150)
18 nama_gs varchar(150)
3.Table: provinsi
NO FIELD NAME TYPE
1 id_provinsi int(5)
2 nama_provinsi varchar(255)
4.Table: user
NO FIELD NAME TYPE
1 id_user int(5) AUTO_INCREMENT
2 id_paket int(5)
3 nama_lengkap varchar(100)
Monthly Progress Report March 2016 November 2014
Western Indonesia National Roads Improvement Project18
6 - 18
NO FIELD NAME TYPE
4 username varchar(50)
5 password varchar(50)
6 level int(2)
7 email varchar(255)
2. Design Interface
1.Welcome page
2.Add Photo
Monthly Progress Report March 2016 November 2014
Western Indonesia National Roads Improvement Project19
6 - 19
3.Add Project Data
Monthly Progress Report March 2016 November 2014
Western Indonesia National Roads Improvement Project20
6 - 20
4.Add User
Monthly Progress Report March 2016 November 2014
Western Indonesia National Roads Improvement Project21
6 - 21
6.6.2 DMS Statistic
Today the DMS application already stored many file of Letters and Documents. And the next
days will be more files are stored in the DMS database. At the end, it is expected to store all
of files that related with WINRIP project.
Below is the number of Letter files that have been stored in DMS database, updates until the
end of February 2016. This Letter statistics have sorted by "Package".
0
10
20
30
40
50
60
70
P1 K
rui -
Bih
a
P2 P
adan
g Sa
wah
- Sp
Em
pat
P3 M
angg
opoh
- Pa
dang
Saw
ah
P4 Ip
uh -
Bant
al
P5 S
p Ra
mpa
- Po
riaha
P6 P
asar
Ped
ati -
Ker
kap
P7 In
drap
ura
- Tap
an
P8 B
ts K
ota
Paria
man
- M
angg
opoh
P9 R
anta
u Ti
jang
- Ko
ta A
gung
P10
Sp E
mpa
t - S
p Ai
r Bal
am
P11
Bant
al -
Muk
omuk
o
P12
Kam
bang
- In
drap
ura
P13
Sp R
ukis
- Tj K
emun
ing
P14
Pain
an -
Kam
bang
P15
Sibo
lga
- Bat
as T
apse
l
P16
Sebl
at -
Ipuh
P17
Sp G
n Ke
mal
a - P
g Ta
mpa
k
P18
Muk
omuk
o - B
ts S
umba
r
P19
Lais
- Bin
tuna
n
P20
Lubu
k Al
ung
- Sic
inci
n
P21
Lubu
k Al
ung
- Kur
aita
ji
WIN
RIP
36
28
61
25
15 1711
70
6
1612 12
6 8 5 40
14
2 2
66
Package
Letter StatisticSorted by Package
And here are the number of Document files that have been stored in DMS database, updates
until the end of February 2016. This Document statistics have sorted by "Document Type".
Monthly Progress Report March 2016 November 2014
Western Indonesia National Roads Improvement Project22
6 - 22
0
10
20
30
40
50
60
70
7
38
0
66
33
15 13
6 8
18
10
28
0
8
Document StatisticSorted by Document Type
Document Type
WINRIP Website Application Progress are shown in Appendix G.
Monthly Progress Report March 2016 November 2014
Western Indonesia National Roads Improvement Project23
6 - 23
6.7 Quality AssuranceDuring the period March 2016 the Quality Assurance Engineer conducted the preparation offlow charts Provisional Hand Over (PHO) of ICB and NCB packages, review TFAC conformanceReports and the site inspections for the preparation of Provisional Hand Over (PHO) of PackageNo.3.
Appendix D shows the activities of the Quality Assurance Engineer during this period.
6.8 Project Risks and Mitigation Measures
6.8.1 Risks Related to Delays
Since the detailed engineering design (DED) is under responsibility of the Design andSupervision Consultant (DSC), delay on DSC establishment affected the procurement ofAWP-2 and AWP-3 sub-projects. The DED of several subprojects of WP-2 and WP-3 wereprepared and completed by respective P2JN. The CTC has then been instructed by DGH toreview the DEDs of seven packages completed by the P2JNs (package 5, 6, 11, 13, 15, 17 and19).
6.8.2 Financial Risks
The following factors will be monitored during implementation of the loan project. Loan Amount Actual Tender Prices Price Adjustments Contract Amendments (Additive or Deductive Variations) Currency Fluctuation Current Estimated Situation
No risk was detected until preparation of this report, however CTC prepared revised costestimates in anticipation of future cost claims to cover contract price escalations andvariation orders. A revised factor from 10% have been reduced to 5% for both additionalcost components is applied on the original cost.
6.8.3 Risks Related to Quality
The quality of work is inherently tied to the competence of the Contractors and the diligenceof the Supervision Teams. The competence of contractors shall be considered at the time ofbid evaluation and prior to the award of any contract.
The quality of supervision however is influenced by the following factors:
Ensuring that supervision staff levels are fully manned with competent, honest,qualified and experienced personnel.
The provision of properly equipped laboratories with properly trained operators foreach package.
Package supervision comes under the responsibilities of the immediate supervision teamsand the relevant DSC and the Quality Assurance Engineer from CTC.
Monthly Progress Report March 2016 November 2014
Western Indonesia National Roads Improvement Project1
7 - 1
7 ISSUES and RECOMMENDATIONS
7.1 Current Situation
The main issues during this month of March 2016 are as follows:a) The big negative slippage (behind schedule) of two (2) on-going construction sub-
projects, Packages 5 and 6.b) Delayed procurement process and issuance of Notice to Proceed will affect the twenty
four (24) months time of completion of Contract Packages 08, 10, 12, 14, 20 and 21. Ifthe Contract Packages could not get started soon, the completion dates will keep onstetching farther beyond the expiry date of the loan agreement on December 31, 2017.
c) Land acquisition and compensation payments of affected people (PAP) in Packages 10,12, 13 and 15 are already delayed.
d) Delayed action in processing the justification of the “Field Engineering” for the two (2)ongoing contruction packages (Packages 5 and 6).
e) For almost the whole month of March 2016, there was no regular Team Leader of theDesign Supervision Consultants (DSC) as he is on indefinite leave of absence due toserious ilness.
7.2 Actions Requireda) Two (2) of the twelve (12) on-going construction packages are on critical situation due to
big negative progress slippages which may affect the timely completion of the projects.Design Supervision Consultant (DSC) shall closely monitor, preferably on a weekly basis,the Contractors progress output once the pending Contractors request for timeextensions are granted and approved. Contractors shall prepare a “Catch-Up’ Scheduleon how to complete the remaining works within the extended contract time.
b) Processing time up to the issuance of Notice To Proceed shall be prioritized andexpedited in order to minimize the completion dates from going farther beyond theDecember 31, 2017 loan closing date.
c) Concerned authorities in the acquisition of the road right of way shall expedite theprocess, if possible DGH have to intervene to accelerate the LARAP implementation.
d) DSC and Contractors shall constantly follow-up with the authorities concerned for theearly approval of the “Technical Justifications of Field Engineering” results.
e) BALAI II as the other part of the contracting parties with Renardet “the Engineer” of theWINRIP Projects shall have to clarity from the Company how soon the current TeamLeader will remobilize to the site.
Monthly Progress Report March 2016 November 2014
Western Indonesia National Roads Improvement Project1
8 - 1
8 CORRESPONDENCESDuring the period the CTC received and issued letters. Lists of letters received and issued areshown in Appendix J.